Vous êtes sur la page 1sur 20

CURVE NO 7(LH)

A=06 -27'-57"
R=400m
T=22.59m
CL=45.14m
D-29

D-28A
CURVE NO 6(RH)

300
A=06 -15'-01"
R=400m
T=21.84m
CL=43.636m
199 199
5500

5500
6959

750 1660 750 1660 750750 1750 750 1750 750 750 1750 750 1750 750750 1660 750 1660 750 GENERAL NOTES :-
1. ALL DIMENSIONS ARE IN MILLIMETRES AND LEVELS IN METRES
UNLESS OTHERWISE SPECIFIED.
2. LOADING ---------- 25T LOADING-2008.
3. DESIGN CRITERIA
i) IRS BRIDGE RULES.
ii) IRS CONCRETE BRIDGE CODE.

750 iii) IRS BRIDGE SUBSTRUCTURE AND FOUNDATION CODE.


3600 3600 150 TH P.C.C M25 3600 3600
8700 8700 4. CONCRETE GRADE:-
750
i) ABUTMENTS -------------M-35.(DESIGN MIX)
ii) PILES & PILE CAPS --------M-35.(DESIGN MIX)
iii) APPROACH SLAB ----------M-35 (DESIGN MIX).
iv) LEVELLING COURSE --------M-25.
5. HIGH YIELD STRENGTH DEFORMED BAR OF GRADE Fe-500 CONFORMING TO I.S. 1786-1986.
SHALL BE USED AS REINFORCEMENT.
6.
7. ALL DIMENSIONS AND LEVEL SHOULD BE VERIFIED & RECONCILED BEFORE EXECUTION.
8. BACK FILL SHOULD BE AS PER CLAUSE 7.5 OF IRS BRIDGE SUB STRUCTURE CODE.
9. WEEP HOLES SHALL BE OF 75/100 DIA PVC PIPES STAGGERED @ 1000 C/C BOTH HORIZONTALLY
AND VERTICALLY THROUGH RETURN WALL & ABUTMENT.
10. DRAINAGE OF DECK SHALL BE PROVIDED 1 IN 40 (CROSS SLOPE) VIDE CLAUSE 15.2.2.1 OF IRS
CONCRETE BRIDGE 1997.
11. EXPOSURE CONDITION-MODERATE.
12. PILE LOAD TEST INITIAL AND ROUTINE SHALL BE CARRIED OUT CONFERMING TO IS: 2911
PART-IV (1985)
(i) VERTICAL LOAD TEST
(a) INITIAL LOAD TEST SHALL BE CARRIED FOR TEST LOAD OF 2.5 TIMES THE WORKING
LOAD( AS PER Cl 6.1.5 OF IS:2911 PART IV-1985 )
(b) ROUTINE LOAD TEST SHALL BE CARRIED FOR TEST LOAD OF 1.5 TIMES THE WORKING
LOAD( AS PER Cl 6.1.5.1 OF IS:2911 1985 PART IV)
(ii) HORIZONTAL LOAD TEST
(a) LATRAL LOAD TEST SHALL BE CARRIED FOR TEST LOAD OF 2.5 TIMES THE WORKING
LOAD( AS PER Cl 7.4 OF IS:2911 PART IV-1985 )
13. LOAD CARRYING CAPACITY OF PILE AS BELOW
(a) ABUTMENT -- HORIZONTAL (i) NORMAL --12t (ii) SEISMIC --15t.
(b) ABUTMENT -- VERTICAL (i) NORMAL -- 105t (ii) SEISMIC -- 110t.
(c) PIER----- HORIZONTAL (i) NORMAL --12t (ii) SEISMIC -- 9.5t.
(d) PIER----- VERTICAL (i) NORMAL-- 210t (ii) SEISMIC -- 205t.
THESE VALUES SHALL BE VERIFIED AT SITE BEFORE EXECUTION.
14. FINAL LAYOUT OF PILES AND THE LENGTH OF PILES TO BE DECIDED ON THE BASIS OF PILE
LOAD TEST RESULTS.
450

15. PILES ARE OF 1200 DIA BORED CAST IN SITU AND THEIR CONSTRUCTION SHALL CONFORM TO

4000 RELEVANT CLAUSE OF I.S. 2911 (PART-1/SEC-2) 1979 AND IRS BRIDGES SUB-STRUCTURE
750 1750 750 1750 750750 1660 750 1660 750
AND FOUNDATION CODE.
16. GROUND PROFILE SHOULD BE VERIFIED BEFORE EXECUTION, CHANGES IF ANY, SHOULD
5000

BE INTIMATED TO THE CONSULTANT


17. 12MM THICK TARRED FELT SQUEEZED TO 6MM WILL BE USED UNDER ALL THE BED PLATES
UNDER BEARING.

THIS DRG. IS BASED ON R.D.S.O. STANDARD DRG. NO. RDSO/B-16014

THIS DRAWING FOR CONSTRUCTION PURPOSE.


1676
6850
738

2137 1676 2137


1285

1850 450 450


450
738

450
1000

1285

1050 1050 1850

0
0
60
10
1050 1050

5500
450
6459

0
10

1650
300
3000 250
250
6850

540
1800

15918 950
1650

1650
250 250
450 450
1800

3600 3600 250 1450 1450 250


540

540
750 750 DETAILS OF
8700 TOE WALL ( A GOVT. OF INDIA ENTERPRISE )
950 3600 3600 950
SCALE 1:50
750 750
8700

RITES/KOL/DVC/MTPS/MEJIA - /2013
100,50 & 25
R.BANERJEE
FEBRUARY-/2013
RPO/KOL/
P. Pal Drawn By P.SINHA ROY
CBE DY.CE. (BR.) XEN (BR.) Sr. DEN (WEST) H.S. GHOSH T.K. BISWAS Checked By /2013
Sr. DEN (Co-Ord) GM (P)
S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./KGP. Sr. DGM (C) (D &S) Sr. DGM ( C) R.Banerjee (Design) (T.A)
S.E. RLY./KGP. RITES
RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA
/KOLKATA
TO RANIGANJ
N.H.-60

DN LINE
UP LINE
D-46

Br.No. 8R, 1 x 3.0m RC Box,


Km 2/850
GENERAL NOTES :-

THIS DRG. IS BASED ON R.D.S.O. STANDARD DRG. NO. RDSO/B-16014

THIS DRAWING FOR CONSTRUCTION PURPOSE.

0
0
60
10
450

0
10

1650
300
250
250 ( A GOVT. OF INDIA ENTERPRISE )

540
950

DETAILS OF
TOE WALL
SCALE 1:50

RITES/KOL/DVC/MTPS/MEJIA - /2013
100,50 & 25
R.BANERJEE
FEBRUARY-/2013
RPO/KOL/
P. Pal Drawn By P.SINHA ROY
CBE DY.CE. (BR.) XEN (BR.) Sr. DEN (WEST) H.S. GHOSH T.K. BISWAS Checked By /2013
Sr. DEN (Co-Ord) GM (P)
S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./KGP. Sr. DGM (C) (D &S) Sr. DGM ( C) R.Banerjee (Design) (T.A)
S.E. RLY./KGP. RITES /KOLKATA
RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA
400 TH APPROACH SLAB x1.2m)
o27(1
RDSO DWG NO. RDSO/B-11678 BR.N
E
H.PIP
300

300
150 TH P.C.C
M-25

2220
2000 2000

500
GENERAL NOTES :-
4116 4116
1. ALL DIMENSIONS ARE IN MILLIMETRES AND LEVELS IN METRES
UNLESS OTHERWISE SPECIFIED.
2. LOADING ---------- 25T LOADING-2008.
3. DESIGN CRITERIA
750 150 TH P.C.C M25 150 TH P.C.C M25 750 150 TH P.C.C M25 i) IRS BRIDGE RULES.
3600 3600 3600 3600
8700 750 ii) IRS CONCRETE BRIDGE CODE.
750 8700 iii) IRS BRIDGE SUBSTRUCTURE AND FOUNDATION CODE.
4. CONCRETE GRADE:-
i) ABUTMENTS -------------M-35.(DESIGN MIX)
ii) PILES & PILE CAPS --------M-35.(DESIGN MIX)
iii) APPROACH SLAB ----------M-35 (DESIGN MIX).
iv) LEVELLING COURSE --------M-25.
5. HIGH YIELD STRENGTH DEFORMED BAR OF GRADE Fe-500 CONFORMING TO I.S. 1786-1986.
SHALL BE USED AS REINFORCEMENT.
6.
7. ALL DIMENSIONS AND LEVEL SHOULD BE VERIFIED & RECONCILED BEFORE EXECUTION.
8. BACK FILL SHOULD BE AS PER CLAUSE 7.5 OF IRS BRIDGE SUB STRUCTURE CODE.
9. WEEP HOLES SHALL BE OF 75/100 DIA PVC PIPES STAGGERED @ 1000 C/C BOTH HORIZONTALLY
AND VERTICALLY THROUGH RETURN WALL & ABUTMENT.
10. DRAINAGE OF DECK SHALL BE PROVIDED 1 IN 40 (CROSS SLOPE) VIDE CLAUSE 15.2.2.1 OF IRS
CONCRETE BRIDGE 1997.
11. EXPOSURE CONDITION-MODERATE.
12. PILE LOAD TEST INITIAL AND ROUTINE SHALL BE CARRIED OUT CONFERMING TO IS: 2911
PART-IV (1985)
(i) VERTICAL LOAD TEST
(a) INITIAL LOAD TEST SHALL BE CARRIED FOR TEST LOAD OF 2.5 TIMES THE WORKING
LOAD( AS PER Cl 6.1.5 OF IS:2911 PART IV-1985 )
(b) ROUTINE LOAD TEST SHALL BE CARRIED FOR TEST LOAD OF 1.5 TIMES THE WORKING
LOAD( AS PER Cl 6.1.5.1 OF IS:2911 1985 PART IV)
(ii) HORIZONTAL LOAD TEST
(a) LATRAL LOAD TEST SHALL BE CARRIED FOR TEST LOAD OF 2.5 TIMES THE WORKING
LOAD( AS PER Cl 7.4 OF IS:2911 PART IV-1985 )
13. LOAD CARRYING CAPACITY OF PILE AS BELOW
(a) ABUTMENT -- HORIZONTAL (i) NORMAL --12t (ii) SEISMIC --15t.
(b) ABUTMENT -- VERTICAL (i) NORMAL -- 105t (ii) SEISMIC -- 110t.
(c) PIER----- HORIZONTAL (i) NORMAL --12t (ii) SEISMIC -- 9.5t.
(d) PIER----- VERTICAL (i) NORMAL-- 210t (ii) SEISMIC -- 205t.
THESE VALUES SHALL BE VERIFIED AT SITE BEFORE EXECUTION.
14. FINAL LAYOUT OF PILES AND THE LENGTH OF PILES TO BE DECIDED ON THE BASIS OF PILE
LOAD TEST RESULTS.
3600 3600
15. PILES ARE OF 1200 DIA BORED CAST IN SITU AND THEIR CONSTRUCTION SHALL CONFORM TO
RELEVANT CLAUSE OF I.S. 2911 (PART-1/SEC-2) 1979 AND IRS BRIDGES SUB-STRUCTURE
AND FOUNDATION CODE.
16. GROUND PROFILE SHOULD BE VERIFIED BEFORE EXECUTION, CHANGES IF ANY, SHOULD
2000 BE INTIMATED TO THE CONSULTANT
2000
17. 12MM THICK TARRED FELT SQUEEZED TO 6MM WILL BE USED UNDER ALL THE BED PLATES
4116 UNDER BEARING.
4116

8700 THIS DRG. IS BASED ON R.D.S.O. STANDARD DRG. NO. RDSO/B-16014

THIS DRAWING FOR CONSTRUCTION PURPOSE.


1676
6850
738

2137 1676 2137


1285

1850 450 450


738
1000

1285

1050 1050 1850

0
0
60
10
1050 1050
450

0
10

1650
600 1800 600
1800

8612

300
1650

1650

250 250
450 250 250
1800

250 450 250

540
540

540

750 3600 3600 750 950


950 3600 3600 950
8700
750 750
8700 DETAILS OF
TOE WALL ( A GOVT. OF INDIA ENTERPRISE )
SCALE 1:50

RITES/KOL/DVC/MTPS/MEJIA - /2013
100,50 & 25
R.BANERJEE
FEBRUARY-/2013
RPO/KOL/
P. Pal Drawn By P.SINHA ROY
CBE DY.CE. (BR.) XEN (BR.) Sr. DEN (WEST) H.S. GHOSH T.K. BISWAS Checked By /2013
Sr. DEN (Co-Ord) GM (P)
S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./ASN. Sr. DGM (C) (D &S) Sr. DGM ( C) R.Banerjee (Design) (T.A)
S.E. RLY./GRC. S.E. RLY./ASN. RITES
RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA
/KOLKATA
C.L OF BEARING 400 TH APPROACH SLAB
C.L OF BEARING CL OF BRIDGE RDSO DWG NO. RDSO/BA-10059

RAIL LEVEL 195.895


FORMATION LVL 195.207

STIFFENING PLATE
300X25X480
600 TH FILTER MATERIAL 150 TH P.C.C
150 THK. P.C.C M-25 (TYP) GENERAL NOTES :-
M-25
1 1
1.5 1.5

L.B.L 191.580m.

SECTION A - A
SLOPE 2 IN 1

DRY STONE PITCHING

SLOPE 1 IN 1.5

CL OF BRIDGE
BED PLATE C.L. OF BEARING
390X50X750
C.L. OF TRACK

APPROACH SLAB

BEARINGPLATE
210X50X420
C.L. OF BEARING
PEDESTAL
630X150X1050

SLOPE 1 IN 1.5
SLOPE 2 IN 1

DRY STONE PITCHING


HALF TOP & HALF BOTTOM PLAN

0
0
60
10
THIS DRG. IS BASED ON R.D.S.O. STANDARD DRG. NO. RDSO/B-16014
450

0
10

1650
300
250 THIS DRAWING FOR CONSTRUCTION PURPOSE.
250

540
950

RAIL LEVEL 195.907 (GAUGE) DETAILS OF


FORMATION LVL 195.207
TOE WALL
SCALE 1:50

( A GOVT. OF INDIA ENTERPRISE )

RITES/KOL/DVC/MTPS/MEJIA - /2013
100,50 & 25
R.BANERJEE
FEBRUARY-/2013

P.SINHA ROY
RPO/KOL/
P. Pal Checked By
CBE DY.CE. (BR.) XEN (BR.) Sr. DEN (WEST) H.S. GHOSH T.K. BISWAS Drawn By /2013
Sr. DEN (Co-Ord) GM (P) R.Banerjee
E. RLY./KOLKATA E. RLY./KOLKATA E. RLY./KOLKATA E. RLY./ASANSOL Sr. DGM (C) (D &S) Sr. DGM ( C) (T.A)
E. RLY./ASANSOL RITES /KOLKATA Manager (Design)
RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA
300
1500
To Plant

1620
250 250

300

540
To Raniganj
1771

SL

:1
O
950

1
PE

AN
N

TH
O
T

R
ST
DETAILS OF

PE
3500 4125
300

EE

EE
PE

ST
DROP WALL / CURTAIN WALL

T
O
TH

N
AN

PE
1

O
400
350

:1

SL
20 MM GAP
X Y
GENERAL NOTES :-
225

3000

2949
450

225
2. LEVELS ARE IN METRES.

575

350
3. ALL DIMENSIONS AND LEVELS SHOULD BE VERIFIED & RECONCILED BEFORE EXECUTION.
4. LOADING STANDARD I.R.S. 25 TONNE LOADING OF 2008.

400
350
5. FOR CONCRETE, SPECIFICATION REFER I.S. 456 -2000 & I.R.S. CONC. BRIDGE CODE.

20 MM GAP 6. DESIGN CRITERIA :-


300 i) I.R.S. BRIDGE RULES.
10800 ii) I.R.S. CONCRETE BRIDGE CODE.
iii) I.R.S. BRIDGE SUB-STRUCTURE & FOUNDATION CODE.

3000
7. REINFORCEMENT SHALL BE HYSD BAR OF GRADE Fe 500 CONFORMING TO
IS: 1786-1985 AND ALL RCC SURFACE COMING IN CONTACT WITH SOIL SHOULD BE
PAINTED WITH BITUMEN OR COALTAR OF APPROVED QUALITY @ 1.464 KG/SQM.
8. CONCRETE GRADE :-

738
i) R.C.C. BOX ....................................................M-35 (DESIGN MIX.)

150
ii) ALL R.C.C. WORK ...................................M-35 (DISIGN MIX)

225
iii) ALL P.C.C. WORK ................................M-25 (NOMINAL MIX)
PLAN

1196
9. MAX. SIZE OF AGGREGATE TO BE USED IS 20 mm.

350
1500

350
10. EXPOSURE CONDITION IS MODERATE REF. C.L. NO. 5.4.1 OF I.R.S. CONCRETE BRIDGE CODE.
11. CLEAR COVER OF 50 mm.

1200
300

850
12. LAPPING OF BARS SHOULD BE MINIMISED & ALL STAGGERED WHEREVER NECESSARY

2850
MINIMUM LENGTH OF LAP SHALL BE AS GIVEN IN IRS CONCRETE CODE 50 FOR TOR

3000
STEEL, THE NUMBER & LOCATION OF LAP IS TO BE DECIDED AT SITE.

750
13. WEEP HOLES TO BE PROVIDED IN RETURN WALLS BY USING 100/75 mm. DIA PVC PIPE
225 450
@ 1000 C/C VERT. & 1000 mm.C/C HOR. IN A STAGGERED BOTHWAY.

900
1200
3500 4125 1771

1500

350
600
OF BAR.
TYP.DETAILS AT A & B 15. 600 mm. WELL HAND PACKED BOULDERS BACK FILLING TO BE PROVIDED BESIDE THE BOX
738

AND RETURN WALLS AS PER C.L 7.5 OF I.R.S BRIDGE SUBSTRUCTURE & FOUNDATION CODE.

300
450 350
3000 350
1036
1196

225
11683 17. ENGINEER-IN-CHARGE AT SITE SHOULD SATISFY HIMSELF WITH S.B.C. OF SOIL.
225
2546

350

400
18. BED SLOPE SHALL BE ADJUSTED AS PER SITE CONDITIONS BY COMPETENT AUTHORITY
BAR BENDING SCHEDULE OF BOX IT SHOULD BE KEPT MINIMUM 1 IN 100.
4396

1000
4396

19. DEPTH OF FOUNDATION SHOWN TENTATIVELY. HOWEVER, THIS MAY VARY TO SUIT SITE
SECTION ALONG THE TRACK
3190

3000

CONDITION & TO BE DECIDED BY THE ENGINEER-IN-CHARGE.


3290

2850

20. DRAWING AND DESIGN BASED ON SOIL TEST REPORT.


300 SCALE 1:100 MARK
DIA & SPACING
BENDING OF BAR REMARKS 21. DESIGN MAX. BERING PRESSURE AT FOUNDATION LEVEL = t/m sq.
OF BARS(m.m.)
750

20 MM GAP 22. SEPARATE WATERWAY CALCULATION ARE NOT PROVIDED AS IT IS


1305 BALANCING CULVERT.
a1 3600
350

400

16@200 C/C 1305 23. FOR ALIGNMENT PLAN REFER DRG. No. RITES/KOL./KBUNL. SHEET No.- OF
1200

CE'S DRG. No.-


24. TOLERANCES FOR FINISHED CONCRETE BRIDGE STRUCTURE SHOULD NOT EXCEED THE
a2 12@200 C/C 1293 3600 1293
20 MM GAP
LIMIT AS GIVEN IN CLAUSE 6.5 OF CONCRETE BRIDGE CODE.
225
450
TABLE SHOWING BRIDGE DETAILS
900 3600
b 16@100 C/C
10800

16@200 C/C

100
300
c 1289
3600
1289
100

SECTIONAL ELEVATION AT X-Y d 16@100 C/C 3600


THIS DRG. IS BASED ON R.D.S.O. STANDARD DRG. NO. RDSO/B-10151/3

e 12@200 C/C 3600

VARYING 3190 TO 750


183
f1 16@200 C/C 1173
THIS DRAWING FOR CONSTRUCTION PURPOSE.
3500

183
A A
183
f2 16@200 C/C
100

100 350 1173


B 183
B
100
900
750

g1 10@200 along
240
1500

barell and
along span 100
600
1350

g2 10@200 along 100


300

C barell and 240


C along span
100
400

1633 620 2647


g3 10@200 along 240 ( A GOVT. OF INDIA ENTERPRISE )
4900
567 350 783 barell and 100 100
1700 along span
DETAILS OF R.C.C. WING WALL h1 10@200 C/C 10700
SECTION OF RETURN WALL BORE-LOG DETAILS SECTION A-A
SECTION AT C-C h2 10@200 C/C 10700
SCALE 1:50
SCALE 1:50 h3 10@200 C/C 10700

RITES/KOL/DVC/MTPS/MEJIA - /2012
100,50 & 25
R.BANERJEE
OCTOBER-/2012
RPO/KOL/
Drawn By P.SINHA ROY
CBE DY.CE. (BR.) XEN (BR.) Sr. DEN (WEST) P. Pal H.S. GHOSH P.K. Das Checked By /2012
Sr. DEN (Co-Ord) R.Banerjee (Design)
S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./KGP. GM (P) Sr. DGM (C) (D & S) DY. G.M ( C) (T.A)
S.E. RLY./KGP.
RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA
300
3500 6000 550 6100 550 To
Ra
nig

1620
450 an
j

225
225

738

738
261

550
550
250 250

1811

1000

540
950

4661

3850
5100

4000
20 MM GAP

2850

4550
300 DETAILS OF
750 DROP WALL / CURTAIN WALL

4000
SL

:1
550
20 MM GAP

1
PE
1200

AN
N

TH
O
T

R
ST

PE
EE
450

EE
225

PE

ST
225 450

T
GENERAL NOTES :-

TH

O
900 7002

225
N
AN

PE
1

775
:1

SL

550
2. LEVELS ARE IN METRES.
3. ALL DIMENSIONS AND LEVELS SHOULD BE VERIFIED & RECONCILED BEFORE EXECUTION.

550
4. LOADING STANDARD I.R.S. 25 TONNE LOADING OF 2008.
SECTIONAL ELEVATION AT X-Y 5. FOR CONCRETE, SPECIFICATION REFER I.S. 456 -2000 & I.R.S. CONC. BRIDGE CODE.
6. DESIGN CRITERIA :-

150
i) I.R.S. BRIDGE RULES.
ii) I.R.S. CONCRETE BRIDGE CODE.

4000
iii) I.R.S. BRIDGE SUB-STRUCTURE & FOUNDATION CODE.
300 7. REINFORCEMENT SHALL BE HYSD BAR OF GRADE Fe 500 CONFORMING TO
IS: 1786-1985 AND ALL RCC SURFACE COMING IN CONTACT WITH SOIL SHOULD BE
1500

PAINTED WITH BITUMEN OR COALTAR OF APPROVED QUALITY @ 1.464 KG/SQM.


8. CONCRETE GRADE :-
i) R.C.C. BOX ....................................................M-35 (DESIGN MIX.)
ii) ALL R.C.C. WORK ...................................M-35 (DISIGN MIX)

150
iii) ALL P.C.C. WORK ................................M-25 (NOMINAL MIX)

9. MAX. SIZE OF AGGREGATE TO BE USED IS 20 mm.


0
30

550
10. EXPOSURE CONDITION IS MODERATE REF. C.L. NO. 5.4.1 OF I.R.S. CONCRETE BRIDGE CODE.

1200
11. CLEAR COVER OF 50 mm.

650
12. LAPPING OF BARS SHOULD BE MINIMISED & ALL STAGGERED WHEREVER NECESSARY
300 3500 6000
MINIMUM LENGTH OF LAP SHALL BE AS GIVEN IN IRS CONCRETE CODE 50 FOR TOR
225 450 STEEL, THE NUMBER & LOCATION OF LAP IS TO BE DECIDED AT SITE.

225
738
13. WEEP HOLES TO BE PROVIDED IN RETURN WALLS BY USING 100/75 mm. DIA PVC PIPE
300 @ 1000 C/C VERT. & 1000 mm.C/C HOR. IN A STAGGERED BOTHWAY.
TYP.DETAILS AT A & B

550
400
OF BAR.
550

20 MM GAP 15. 600 mm. WELL HAND PACKED BOULDERS BACK FILLING TO BE PROVIDED BESIDE THE BOX
AND RETURN WALLS AS PER C.L 7.5 OF I.R.S BRIDGE SUBSTRUCTURE & FOUNDATION CODE.

3850
4000
TABLE SHOWING BRIDGE DETAILS
17. ENGINEER-IN-CHARGE AT SITE SHOULD SATISFY HIMSELF WITH S.B.C. OF SOIL.
X Y

750
18. BED SLOPE SHALL BE ADJUSTED AS PER SITE CONDITIONS BY COMPETENT AUTHORITY
6100

6500

IT SHOULD BE KEPT MINIMUM 1 IN 100.

900

550
1200
1500
19. DEPTH OF FOUNDATION SHOWN TENTATIVELY. HOWEVER, THIS MAY VARY TO SUIT SITE

600
CONDITION & TO BE DECIDED BY THE ENGINEER-IN-CHARGE.
20. DRAWING AND DESIGN BASED ON SOIL TEST REPORT.

300
550 6100 550 21. DESIGN MAX. BERING PRESSURE AT FOUNDATION LEVEL = t/m sq.
11683 22. SEPARATE WATERWAY CALCULATION ARE NOT PROVIDED AS IT IS
BALANCING CULVERT.
550

400

23. FOR ALIGNMENT PLAN REFER DRG. No. RITES/KOL./KBUNL. SHEET No.- OF
300 CE'S DRG. No.-
20 MM GAP
24. TOLERANCES FOR FINISHED CONCRETE BRIDGE STRUCTURE SHOULD NOT EXCEED THE
SECTION ALONG THE TRACK LIMIT AS GIVEN IN CLAUSE 6.5 OF CONCRETE BRIDGE CODE.
BAR BENDING SCHEDULE OF BOX
SCALE 1:100

DIA & SPACING


MARK OF BARS(m.m.) BENDING OF BAR REMARKS
30
0

2495
a1 25@200 C/C 5000
2495
THIS DRG. IS BASED ON R.D.S.O. STANDARD DRG. NO. RDSO/B-10151/3
PLAN a2 12@200 C/C 1849 7100 1849
1500

7100
b 20@100 C/C
300
c 16@200 C/C 1849
7100
1849

THIS DRAWING FOR CONSTRUCTION PURPOSE.

100
300
100
d 25@100 C/C 7100

VARYING 2340 TO 750


e 12@200 C/C 5000
3500

243
100
A A f1 25@200 C/C 2021
100

350 243
B
B 243
f2 25@200 C/C 2021
750

900

243
1500

100
g1 10@200 along
440
600
1350

barell and
along span 100
300

C C
g2 10@200 along 100
400

( A GOVT. OF INDIA ENTERPRISE )


barell and 440
567 350 783
1633 620 2647 along span
4900 100
1700

g3 10@200 along 440


barell and 100 100
BORE-LOG DETAILS along span
SECTION OF RETURN WALL DETAILS OF R.C.C. WING WALL
SECTION A-A h1 10@100 C/C 6902
SECTION AT C-C
SCALE 1:50 SCALE 1:50 h2 10@100 C/C 6902

h3 10@100 C/C 6902

RITES/KOL/DVC/MTPS/MEJIA - /2012
100,50 & 25
R.BANERJEE
OCTOBER-/2012
RPO/KOL/
Drawn By P.SINHA ROY
CBE DY.CE. (BR.) XEN (BR.) Sr. DEN (WEST) P. Pal H.S. GHOSH P.K. Das Checked By /2012
Sr. DEN (Co-Ord) R.Banerjee (Design)
S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./KGP. GM (P) Sr. DGM (C) (D & S) DY. G.M ( C) (T.A)
S.E. RLY./KGP.
RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA
To R
anig
an j
225
738

350
350 2000 350

1800
750
SL

350

:1
O

350
PE

AN

1500

1350
N

TH
O
T

R
ST

PE
EE

EE

400
PE

ST
R

T
SL 1800

O
TH

N
AN

PE
350 350
2000

H)
:1

O 5(R

T=41. .932m
CUR -58'-51"

R=100 3m
A=04 0m
VE N

49
4824

CL=86
350
GENERAL NOTES :-
C.L. OF EXT. TRACK C.L. OF PROP. TRACK
SECTION ALONG THE TRACK
6000
2. LEVELS ARE IN METRES.
SCALE 1:100

150
2980 3000 3500 450
RAIL LEVEL 83.172m. 3. ALL DIMENSIONS AND LEVELS SHOULD BE VERIFIED & RECONCILED BEFORE EXECUTION.

738
4. LOADING STANDARD I.R.S. 25 TONNE LOADING OF 2008.
688

20 mm. CLEAN JOINT

P.C.C. SLEEPER
FORMATION LEVEL 82.434m.
120

5. FOR CONCRETE, SPECIFICATION REFER I.S. 456 -2000 & I.R.S. CONC. BRIDGE CODE.
350
418

850

500
6. DESIGN CRITERIA :-
H.F.L.= 81.584

2000
1738

1990
300 i) I.R.S. BRIDGE RULES.
1200

1800
INVERT LEVEL = 80.568m.
ii) I.R.S. CONCRETE BRIDGE CODE.

750
GROUND LEVEL 80.434m. iii) I.R.S. BRIDGE SUB-STRUCTURE & FOUNDATION CODE.
350

300
7. REINFORCEMENT SHALL BE HYSD BAR OF GRADE Fe 500 CONFORMING TO

1200
120

IS: 1786-1985 AND ALL RCC SURFACE COMING IN CONTACT WITH SOIL SHOULD BE
150 TH. P.C.C. BASE COURSE (M-20) PAINTED WITH BITUMEN OR COALTAR OF APPROVED QUALITY @ 1.464 KG/SQM.
450 TH. P.C.C. BASE COURSE (M-20)

1620
6950 8. CONCRETE GRADE :-
0.45m. SOIL TO BE EXCAVATED & FILLED BACK 225 i) R.C.C. BOX ....................................................M-35 (DESIGN MIX.)
WITH WEL COMPACTED SAND 450 ii) ALL R.C.C. WORK ...................................M-35 (DISIGN MIX)
900 iii) ALL P.C.C. WORK ................................M-25 (NOMINAL MIX)

225
250 250 9. MAX. SIZE OF AGGREGATE TO BE USED IS 20 mm.

350
10. EXPOSURE CONDITION IS MODERATE REF. C.L. NO. 5.4.1 OF I.R.S. CONCRETE BRIDGE CODE.
SECTIONAL ELEVATION AT X-Y

540
11. CLEAR COVER OF 50 mm.
950 12. LAPPING OF BARS SHOULD BE MINIMISED & ALL STAGGERED WHEREVER NECESSARY
MINIMUM LENGTH OF LAP SHALL BE AS GIVEN IN IRS CONCRETE CODE 50 FOR TOR
STEEL, THE NUMBER & LOCATION OF LAP IS TO BE DECIDED AT SITE.

1800
DETAILS OF 13. WEEP HOLES TO BE PROVIDED IN RETURN WALLS BY USING 100/75 mm. DIA PVC PIPE
@ 1000 C/C VERT. & 1000 mm.C/C HOR. IN A STAGGERED BOTHWAY.
DROP WALL / CURTAIN WALL
OF BAR.

350
15. 600 mm. WELL HAND PACKED BOULDERS BACK FILLING TO BE PROVIDED BESIDE THE BOX
AND RETURN WALLS AS PER C.L 7.5 OF I.R.S BRIDGE SUBSTRUCTURE & FOUNDATION CODE.

800
17. ENGINEER-IN-CHARGE AT SITE SHOULD SATISFY HIMSELF WITH S.B.C. OF SOIL.
18. BED SLOPE SHALL BE ADJUSTED AS PER SITE CONDITIONS BY COMPETENT AUTHORITY
IT SHOULD BE KEPT MINIMUM 1 IN 100.
225 450

100
100 350 19. DEPTH OF FOUNDATION SHOWN TENTATIVELY. HOWEVER, THIS MAY VARY TO SUIT SITE
CONDITION & TO BE DECIDED BY THE ENGINEER-IN-CHARGE.
20. DRAWING AND DESIGN BASED ON SOIL TEST REPORT.
21. DESIGN MAX. BERING PRESSURE AT FOUNDATION LEVEL = t/m sq.
TYP.DETAILS AT A & B

750
22. SEPARATE WATERWAY CALCULATION ARE NOT PROVIDED AS IT IS
300 BALANCING CULVERT.
23. FOR ALIGNMENT PLAN REFER DRG. No. RITES/KOL./KBUNL. SHEET No.- OF
1500

CE'S DRG. No.-


C.L. OF EXT. TRACK 24. TOLERANCES FOR FINISHED CONCRETE BRIDGE STRUCTURE SHOULD NOT EXCEED THE

1350
6000 LIMIT AS GIVEN IN CLAUSE 6.5 OF CONCRETE BRIDGE CODE.
1V
2H:
PE
LO
300 HS
RT

100
300 EA

400
100
300
2980 3000 3500
350

A 567 350 783

VARYING 1990 TO 750


1700
120

THIS DRG. IS BASED ON R.D.S.O. STANDARD DRG. NO. RDSO/B-10151/3


410

X Y
CL OF R.C.C. PIPE 450 SECTION OF RETURN WALL
2000
2260
1440
1200

SECTION AT C-C
410

SCALE 1:50
350
120

THIS DRAWING FOR CONSTRUCTION PURPOSE.


A
300
1400

CL OF HUME PIPE
1750

RAIL LEVEL 82.994m.

688
350

1 NO 1200 DIA (NP4) PIPE


1500

FORMATION LEVEL 82.306m.

120
300 150 980 980 150
TOP LEVEL = 81.888 m.

PLAN SHOWING THE DETAILS 680 460 2160


BED LEVEL OF HUME PIPE = 3.210 m.
3300
OF R.C.C. PIPE AT CH.5/907

450
P.C.C M - 20
DETAILS OF R.C.C. WING WALL P.C.C M - 20
( A GOVT. OF INDIA ENTERPRISE )

450
120
SECTION C-C 150 THK. P.C.C (M-20)
SCALE 1:50

450
SAND FILLING
(COMPACTED)
2260

SECTION AT A-A
SCALE - 1:50

RITES/KOL/DVC/MTPS/MEJIA - /2013
100,50 & 25
R.BANERJEE
JANUARY-/2013
RPO/KOL/
Drawn By P.SINHA ROY
CBE DY.CE. (BR.) XEN (BR.) Sr. DEN (WEST) P. Pal H.S. GHOSH P.K. Das Checked By /2013
Sr. DEN (Co-Ord) R.Banerjee (Design)
S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./KGP. GM (P) Sr. DGM (C) (D & S) DY. G.M ( C) (T.A)
S.E. RLY./KGP.
RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA
300
3500 6000
450

1620
738
225

510
620
225
250 250

400
2020
To Raniganj

540
To MTPS

1000
3370

SL

:1
3300

O
2740

1
2500

PE
2350

AN
950
300

TH
O
T

R
ST

PE
750

EE

EE
PE

ST
DETAILS OF

T
400

O
TH

N
1200 20 MM GAP

AN
DROP WALL / CURTAIN WALL

PE
1

O
:1

SL
20 MM GAP
225
450
900 7720 GENERAL NOTES :-
225
450

225
2. LEVELS ARE IN METRES.

625
3. ALL DIMENSIONS AND LEVELS SHOULD BE VERIFIED & RECONCILED BEFORE EXECUTION.

400
4. LOADING STANDARD I.R.S. 25 TONNE LOADING OF 2008.
SECTIONAL ELEVATION AT X-Y 5. FOR CONCRETE, SPECIFICATION REFER I.S. 456 -2000 & I.R.S. CONC. BRIDGE CODE.
6. DESIGN CRITERIA :-
i) I.R.S. BRIDGE RULES.

300 ii) I.R.S. CONCRETE BRIDGE CODE.

2500
iii) I.R.S. BRIDGE SUB-STRUCTURE & FOUNDATION CODE.
7. REINFORCEMENT SHALL BE HYSD BAR OF GRADE Fe 500 CONFORMING TO
1500

IS: 1786-1985 AND ALL RCC SURFACE COMING IN CONTACT WITH SOIL SHOULD BE
PAINTED WITH BITUMEN OR COALTAR OF APPROVED QUALITY @ 1.464 KG/SQM.

150
8. CONCRETE GRADE :-
i) R.C.C. BOX ....................................................M-35 (DESIGN MIX.)
ii) ALL R.C.C. WORK ...................................M-35 (DISIGN MIX)
0
30

738
iii) ALL P.C.C. WORK ................................M-25 (NOMINAL MIX)

400
9. MAX. SIZE OF AGGREGATE TO BE USED IS 20 mm.

1200
10. EXPOSURE CONDITION IS MODERATE REF. C.L. NO. 5.4.1 OF I.R.S. CONCRETE BRIDGE CODE.

800
300 3750 6000 11. CLEAR COVER OF 50 mm.

3562

3337
12. LAPPING OF BARS SHOULD BE MINIMISED & ALL STAGGERED WHEREVER NECESSARY
225 450 MINIMUM LENGTH OF LAP SHALL BE AS GIVEN IN IRS CONCRETE CODE 50 FOR TOR
STEEL, THE NUMBER & LOCATION OF LAP IS TO BE DECIDED AT SITE.

225
300
13. WEEP HOLES TO BE PROVIDED IN RETURN WALLS BY USING 100/75 mm. DIA PVC PIPE
@ 1000 C/C VERT. & 1000 mm.C/C HOR. IN A STAGGERED BOTHWAY.
TYP.DETAILS AT A & B

400
400
400

OF BAR.
1200

20 MM GAP 15. 600 mm. WELL HAND PACKED BOULDERS BACK FILLING TO BE PROVIDED BESIDE THE BOX

2350
AND RETURN WALLS AS PER C.L 7.5 OF I.R.S BRIDGE SUBSTRUCTURE & FOUNDATION CODE.

2500
400

X Y

750
4000

1200

17. ENGINEER-IN-CHARGE AT SITE SHOULD SATISFY HIMSELF WITH S.B.C. OF SOIL.

400
900
1200
1500
18. BED SLOPE SHALL BE ADJUSTED AS PER SITE CONDITIONS BY COMPETENT AUTHORITY
400

BAR BENDING SCHEDULE OF BOX IT SHOULD BE KEPT MINIMUM 1 IN 100.

600
19. DEPTH OF FOUNDATION SHOWN TENTATIVELY. HOWEVER, THIS MAY VARY TO SUIT SITE
1200

CONDITION & TO BE DECIDED BY THE ENGINEER-IN-CHARGE.


400

300
400 400 20. DRAWING AND DESIGN BASED ON SOIL TEST REPORT.
400

4000
DIA & SPACING 21. DESIGN MAX. BERING PRESSURE AT FOUNDATION LEVEL = t/m sq.
MARK OF BARS(m.m.) BENDING OF BAR REMARKS
11683
300 22. SEPARATE WATERWAY CALCULATION ARE NOT PROVIDED AS IT IS
20 MM GAP 1670 BALANCING CULVERT.
a1 20@200 C/C 3200
1670 23. FOR ALIGNMENT PLAN REFER DRG. No. RITES/KOL./KBUNL. SHEET No.- OF
CE'S DRG. No.-
SECTION ALONG THE TRACK 24. TOLERANCES FOR FINISHED CONCRETE BRIDGE STRUCTURE SHOULD NOT EXCEED THE
a2 16@200 C/C 1254 4700 1254 LIMIT AS GIVEN IN CLAUSE 6.5 OF CONCRETE BRIDGE CODE.
SCALE 1:100
4700
b 20@100 C/C
30
0
c 12@200 C/C 1208
4700
1208

PLAN d 20@100 C/C 4700


1500

THIS DRG. IS BASED ON R.D.S.O. STANDARD DRG. NO. RDSO/B-10151/3

300 3200
300 100 e 16@200 C/C

100
265
f1 20@200 C/C 1314
THIS DRAWING FOR CONSTRUCTION PURPOSE.
VARYING 2740 TO 750
265
3500

265
f2 20@200 C/C 1314

A
265
A
TABLE SHOWING BRIDGE DETAILS
100

100 350
100
g1 10@200 along
B barell and 290
B
along span 100
750

900

100
1500

g2 10@200 along
barell and 290
along span
600
1350

100
300

C C g3 10@200 along 290 ( A GOVT. OF INDIA ENTERPRISE )

barell and 100 100


400

along span
1633 620 2647
567 350 783 h1 10@100 C/C 7620
4900
1700
h2 10@100 C/C 7620
SECTION OF RETURN WALL DETAILS OF R.C.C. WING WALL
BORE-LOG DETAILS h3 10@100 C/C 7620
SECTION AT C-C SECTION A-A
SCALE 1:50 SCALE 1:50

RITES/KOL/DVC/MTPS/MEJIA - /2012
100,50 & 25
R.BANERJEE
OCTOBER-/2012
RPO/KOL/
Drawn By P.SINHA ROY
CBE DY.CE. (BR.) XEN (BR.) Sr. DEN (WEST) P. Pal H.S. GHOSH P.K. Das Checked By /2012
Sr. DEN (Co-Ord) R.Banerjee (Design)
S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./KGP. GM (P) Sr. DGM (C) (D & S) DY. G.M ( C) (T.A)
S.E. RLY./KGP.
RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA
300
3500 6000

1620
450

225

738

738
To Raniganj

225

225
250 250

620
510
620
To MTPS

REPEAT SAME AS ON
OTHER SIDE OF BOX
400

400
2020

540
2970

1000
300

2340

1950

1950
950

2100

2100
750

750
DETAILS OF

400

400
900
DROP WALL / CURTAIN WALL

1500
1200

600
20 MM GAP

400
20 MM GAP
225
450
900 8270 400 400 400 400
2000 2000 2000 GENERAL NOTES :-
11683 225
450
2. LEVELS ARE IN METRES.

400 225
3. ALL DIMENSIONS AND LEVELS SHOULD BE VERIFIED & RECONCILED BEFORE EXECUTION.

625
SECTIONAL ELEVATION AT X-Y 4. LOADING STANDARD I.R.S. 25 TONNE LOADING OF 2008.

SECTION ALONG THE TRACK 5. FOR CONCRETE, SPECIFICATION REFER I.S. 456 -2000 & I.R.S. CONC. BRIDGE CODE.
6. DESIGN CRITERIA :-
SCALE 1:100 i) I.R.S. BRIDGE RULES.
ii) I.R.S. CONCRETE BRIDGE CODE.
300

2100
iii) I.R.S. BRIDGE SUB-STRUCTURE & FOUNDATION CODE.
7. REINFORCEMENT SHALL BE HYSD BAR OF GRADE Fe 500 CONFORMING TO
1500

IS: 1786-1985 AND ALL RCC SURFACE COMING IN CONTACT WITH SOIL SHOULD BE

150
PAINTED WITH BITUMEN OR COALTAR OF APPROVED QUALITY @ 1.464 KG/SQM.
8. CONCRETE GRADE :-
i) R.C.C. BOX ....................................................M-35 (DESIGN MIX.)

400
ii) ALL R.C.C. WORK ...................................M-35 (DISIGN MIX)
0
30

iii) ALL P.C.C. WORK ................................M-25 (NOMINAL MIX)

1200
9. MAX. SIZE OF AGGREGATE TO BE USED IS 20 mm.

800
10. EXPOSURE CONDITION IS MODERATE REF. C.L. NO. 5.4.1 OF I.R.S. CONCRETE BRIDGE CODE.
5824

300 3750 6000 11. CLEAR COVER OF 50 mm.

225 450 12. LAPPING OF BARS SHOULD BE MINIMISED & ALL STAGGERED WHEREVER NECESSARY
MINIMUM LENGTH OF LAP SHALL BE AS GIVEN IN IRS CONCRETE CODE 50 FOR TOR
STEEL, THE NUMBER & LOCATION OF LAP IS TO BE DECIDED AT SITE.
300
13. WEEP HOLES TO BE PROVIDED IN RETURN WALLS BY USING 100/75 mm. DIA PVC PIPE
@ 1000 C/C VERT. & 1000 mm.C/C HOR. IN A STAGGERED BOTHWAY.
TYP.DETAILS AT A & B
700
400

OF BAR.
20 MM GAP 15. 600 mm. WELL HAND PACKED BOULDERS BACK FILLING TO BE PROVIDED BESIDE THE BOX
AND RETURN WALLS AS PER C.L 7.5 OF I.R.S BRIDGE SUBSTRUCTURE & FOUNDATION CODE.
1850
2000

17. ENGINEER-IN-CHARGE AT SITE SHOULD SATISFY HIMSELF WITH S.B.C. OF SOIL.


400

700

18. BED SLOPE SHALL BE ADJUSTED AS PER SITE CONDITIONS BY COMPETENT AUTHORITY
X Y IT SHOULD BE KEPT MINIMUM 1 IN 100.
2000

7600

19. DEPTH OF FOUNDATION SHOWN TENTATIVELY. HOWEVER, THIS MAY VARY TO SUIT SITE
1850

TABLE SHOWING BRIDGE DETAILS CONDITION & TO BE DECIDED BY THE ENGINEER-IN-CHARGE.


20. DRAWING AND DESIGN BASED ON SOIL TEST REPORT.
400

700

21. DESIGN MAX. BERING PRESSURE AT FOUNDATION LEVEL = t/m sq.


22. SEPARATE WATERWAY CALCULATION ARE NOT PROVIDED AS IT IS
BALANCING CULVERT.
2000

1850

23. FOR ALIGNMENT PLAN REFER DRG. No. RITES/KOL./KBUNL. SHEET No.- OF
CE'S DRG. No.-
24. TOLERANCES FOR FINISHED CONCRETE BRIDGE STRUCTURE SHOULD NOT EXCEED THE
400

700

LIMIT AS GIVEN IN CLAUSE 6.5 OF CONCRETE BRIDGE CODE.

20 MM GAP 20 MM GAP

300

100
100 300 THIS DRG. IS BASED ON R.D.S.O. STANDARD DRG. NO. RDSO/B-10151/3
PLAN

VARYING 2340 TO 750


3500 THIS DRAWING FOR CONSTRUCTION PURPOSE.

A A
100

100 350

900
1500
B
B
750

600
300
1350

1633 620 2647 ( A GOVT. OF INDIA ENTERPRISE )


C C
4900
400

567 350 783


1700 DETAILS OF R.C.C. WING WALL
SECTION A-A
SECTION OF RETURN WALL BORE-LOG DETAILS SCALE 1:50
SECTION AT C-C
SCALE 1:50

RITES/KOL/DVC/MTPS/MEJIA - /2012
100,50 & 25
R.BANERJEE
OCTOBER-/2012
RPO/KOL/
Drawn By P.SINHA ROY
CBE DY.CE. (BR.) XEN (BR.) Sr. DEN (WEST) P. Pal H.S. GHOSH P.K. Das Checked By /2012
Sr. DEN (Co-Ord) R.Banerjee (Design)
S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./KGP. GM (P) Sr. DGM (C) (D & S) DY. G.M ( C) (T.A)
S.E. RLY./KGP.
RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA
3750 6000

300
738
To MTPS

1620
738
250 250

2962
450

2089

540
225
225
4412

700
950
6262

450

6477
DETAILS OF
1000 DROP WALL / CURTAIN WALL
3240

3900

2850

3100
3000
300
750

225

450
GENERAL NOTES :-

700
450
1200

450 225
675
20 MM GAP 2. LEVELS ARE IN METRES.
225 20 MM GAP
3. ALL DIMENSIONS AND LEVELS SHOULD BE VERIFIED & RECONCILED BEFORE EXECUTION.
900 12854 4. LOADING STANDARD I.R.S. 25 TONNE LOADING OF 2008.
5. FOR CONCRETE, SPECIFICATION REFER I.S. 456 -2000 & I.R.S. CONC. BRIDGE CODE.
6. DESIGN CRITERIA :-
i) I.R.S. BRIDGE RULES.

SECTIONAL ELEVATION AT X-Y ii) I.R.S. CONCRETE BRIDGE CODE.


iii) I.R.S. BRIDGE SUB-STRUCTURE & FOUNDATION CODE.

3000
738
7. REINFORCEMENT SHALL BE HYSD BAR OF GRADE Fe 500 CONFORMING TO
IS: 1786-1985 AND ALL RCC SURFACE COMING IN CONTACT WITH SOIL SHOULD BE
PAINTED WITH BITUMEN OR COALTAR OF APPROVED QUALITY @ 1.464 KG/SQM.
300 8. CONCRETE GRADE :-
i) R.C.C. BOX ....................................................M-35 (DESIGN MIX.)

150
2962
1200

ii) ALL R.C.C. WORK ...................................M-35 (DISIGN MIX)


iii) ALL P.C.C. WORK ................................M-25 (NOMINAL MIX)

225
9. MAX. SIZE OF AGGREGATE TO BE USED IS 20 mm.

450
10. EXPOSURE CONDITION IS MODERATE REF. C.L. NO. 5.4.1 OF I.R.S. CONCRETE BRIDGE CODE.

450

REPEAT SAME AS ON
OTHER SIDE OF BOX
0

1200
30

11. CLEAR COVER OF 50 mm.

750
12. LAPPING OF BARS SHOULD BE MINIMISED & ALL STAGGERED WHEREVER NECESSARY
MINIMUM LENGTH OF LAP SHALL BE AS GIVEN IN IRS CONCRETE CODE 50 FOR TOR

2850
3000
STEEL, THE NUMBER & LOCATION OF LAP IS TO BE DECIDED AT SITE.
300 3750 6000 225 450
13. WEEP HOLES TO BE PROVIDED IN RETURN WALLS BY USING 100/75 mm. DIA PVC PIPE

750
@ 1000 C/C VERT. & 1000 mm.C/C HOR. IN A STAGGERED BOTHWAY.

450
TYP.DETAILS AT A & B

900
1200
1500
300 OF BAR.
15. 600 mm. WELL HAND PACKED BOULDERS BACK FILLING TO BE PROVIDED BESIDE THE BOX

600
AND RETURN WALLS AS PER C.L 7.5 OF I.R.S BRIDGE SUBSTRUCTURE & FOUNDATION CODE.
700
450

TABLE SHOWING BRIDGE DETAILS

300
450 400 450
20 MM GAP 3000 3000 17. ENGINEER-IN-CHARGE AT SITE SHOULD SATISFY HIMSELF WITH S.B.C. OF SOIL.
11683 18. BED SLOPE SHALL BE ADJUSTED AS PER SITE CONDITIONS BY COMPETENT AUTHORITY
IT SHOULD BE KEPT MINIMUM 1 IN 100.
2850
3000

19. DEPTH OF FOUNDATION SHOWN TENTATIVELY. HOWEVER, THIS MAY VARY TO SUIT SITE
CONDITION & TO BE DECIDED BY THE ENGINEER-IN-CHARGE.
7300

X Y
SECTION ALONG THE TRACK 20. DRAWING AND DESIGN BASED ON SOIL TEST REPORT.
21. DESIGN MAX. BERING PRESSURE AT FOUNDATION LEVEL = t/m sq.
400

700

SCALE 1:100 BAR BENDING SCHEDULE OF BOX 22. SEPARATE WATERWAY CALCULATION ARE NOT PROVIDED AS IT IS
BALANCING CULVERT.
23. FOR ALIGNMENT PLAN REFER DRG. No. RITES/KOL./KBUNL. SHEET No.- OF
DIA & SPACING
3000

CE'S DRG. No.-


2850

MARK BENDING OF BAR REMARKS


OF BARS(m.m.)
24. TOLERANCES FOR FINISHED CONCRETE BRIDGE STRUCTURE SHOULD NOT EXCEED THE
2455 LIMIT AS GIVEN IN CLAUSE 6.5 OF CONCRETE BRIDGE CODE.
3800 DIA & SPACING
a1 20@200 C/C MARK OF BARS(m.m.) BENDING OF BAR REMARKS
2455
450

700

194 194
1455 1455
20 MM GAP h1 20@200C/C
20 MM GAP 2520
a2 20@200 C/C 194 194
300

194 194

100
300 2455
100 THIS DRG. IS BASED ON R.D.S.O. STANDARD DRG. NO. RDSO/B-10151/3
3800 h2 20@200C/C
a3 20@200 C/C 2455 1455 1455
194 194

PLAN 194 194


a4 20@200 C/C 1415 7200 1415 h3 20@200C/C 1455 1455 THIS DRAWING FOR CONSTRUCTION PURPOSE.
VARYING 3240 TO 750

194 194
7200
b 12@100 C/C 194 194
3500

h4 20@200C/C 1455 1455

c 7200 194 194


16@100 C/C
A A
100
100

350
100
j1 10@100 along
B d1 20@200 C/C 1415 1415
7200 barell and 340
B
along span
750

100
900
1500

d2 20@200 C/C 2520


j2 10@100 along 100
barell and
600
1350

340
along span
100
300

C e 20@100 C/C 3800 ( A GOVT. OF INDIA ENTERPRISE )


C
400

j3 10@100 along
barell and 340
1633 620 2647 100 100
567 350 783 along span
4900
1700
f 16@200 C/C 3800

j4 10@100 along
290
SECTION OF RETURN WALL BORE-LOG DETAILS DETAILS OF R.C.C. WING WALL
barell and
12754 along span 100 100
g
SECTION AT C-C SECTION A-A
10@100 C/C

SCALE 1:50 SCALE 1:50

RITES/KOL/DVC/MTPS/MEJIA - /2011
100,50 & 25
R.BANERJEE
OCTOBER-/2012
RPO/KOL/
Drawn By P.SINHA ROY
CBE DY.CE. (BR.) XEN (BR.) Sr. DEN (WEST) P. Pal H.S. GHOSH P.K. Das Checked By /2012
Sr. DEN (Co-Ord) R.Banerjee (Design)
S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./GRC. S.E. RLY./KGP. GM (P) Sr. DGM (C) (D & S) DY. G.M ( C) (T.A)
S.E. RLY./KGP.
RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA RITES /KOLKATA
X,
X
BO
.)

BO
.B

C
.O

C.
RC
(R

R.
BO 0
C /00

0m
X

0m
RC 3

3.

6.
m

1X

3x
6m , K

0,

3/ 2
7,
Km 42
1X G

21

27
, X IN

.
3/

52
/2
9A D

m
o. A

,K

3
N RO

1,
Km
10

.1
BR CA

o.

O
II
.N

N
C

TP
PU

BR

BR
CURVE No:5 RH
CURVE No:4 (LH)

3/779.465

3/862.412
84.056
84.056
R =356.0m

3/357.1
86.300
R =400.0m TL=154.037m
TL=158.598m
ALIGNMENT CL=301.986m
CL=290.756m

R I S E 1 IN 270 FALL 1 IN 150 (C) LEVEL


MTPS PLANT
GRADIENT
DATUM (+) 50.00m
0.509
2.711

4.069
3.966
4.099

4.219
4.327
4.414

4.675
5.299
5.861
5.967

6.083

6.350
6.664
6.841
5.109
3.224

3.268
3.274

3.449
3.449
3.655
4.061

4.617
4.023

3.499

3.105
2.891

2.247
2.143
2.039

2.145
2.071
2.177

1.683
1.536

1.442
1.289
2.136

1.051
1.021

0.956

1.156
1.327
1.041

1.056
1.576
CUTTING / FILLING
84.977
85.051

85.126
85.200
85.274

85.348
85.422
85.496

85.570
85.644

85.718
85.792

85.866

85.940
86.014
86.089

86.163
86.237
86.300
86.281
86.147

86.014
86.014
85.905
85.811

85.717

85.623
85.529

85.435
85.341

85.247
85.153
85.059

84.965

84.871
84.777

84.683
84.586

84.452
84.319
84.186

84.056

84.056
84.056

84.056
84.027
84.056

84.056
84.596
FORMATION LEVEL
84.468
82.340

81.057
81.234
81.175

81.129
81.095
81.082

80.895
80.345
79.857
79.825

79.783

79.590
79.350
79.248
81.054

83.013

83.013
82.873

82.565
82.250
81.750

81.100
81.600

82.030

82.330
82.450

83.000
83.010
83.020

82.820
82.800

82.600

83.000

83.050
83.010
83.030

82.050
83.005
83.035

83.100

82.900
82.700
83.015

83.000
83.020
GROUND LEVEL

3/862.412
3/779.465
3/357.1
3/000
3/020

3/040
3/060
3/080

3/100
3/120
3/140

3/160
3/180

3/200
3/220

3/240

3/260
3/280
3/300

3/320
3/340

3/360
3/380

3/400
3/420
3/440
3/460

3/480
3/500

3/520
3/540

3/560
3/580
3/600
3/620

3/640
3/660

3/680
3/700

3/720
3/740
3/760
3/780

3/800
3/820

3/840
3/860
CHAINAGE

1. All DIMENSIONS ARE IN METRES UNLESS OTHER WISE MENTIONED.

Km 3/779.465 F/BQT. 2. ALL LEVELS ARE RELATED TO THIS SURVEY ARE BASED ON THE RAIL TOP
65m LEVEL OF EXISTING POWER HOUSE LINE CLOSE TO THE POWER UNITS.
THE VALUE IS 111.000m ABOVE M.S.L. ( GTS )
FL : 84.056
Km 4/750

40m
3. TAKE OFF POINT OF PROPOSED LINE IS ASSUMED AS 0.000

4. HEIGHT MENTIONED IN DRAWING FOR OVERHEAD CROSSING ARE ABOVE


GROUND LEVEL.

5. DIFFERENCE BETWEEN FORMATION LEVEL AND RAIL TOP LEVEL IS 0.638m


40m

65m 7. 60KG RAIL AND 60KG PSC SLEEPER SHALL BE PROVIDED IN PROPOSED LINE.

8. ALL POINTS AND CROSSING SHALL BE PROVIDED 1 IN 12 FAN SHAPE CURVE


SWITCH WITH 60 Kg RAIL AND SLEEPER. UNLESS OTHERWISE MENTIONED.
FL : 84.124

(0/769.22)
Km 4/750

N O T E S :-
THIS DRAWING IS PREPAIRED BASED ON CE's DRG No. D-000-98, DRM/ ASN/ Drg. No 124-98,
125-98 AND ACTUAL FIELD SURVEY.

EASTERN RAILWAY

DAMODAR VALLEY CORPORATION


PROVISION OF DOUBLING
BETWEEN RANIGANJ & WAITING BAY LINE OF
MEJIA CAPTIVE LINE INCLUDING BYPASS LINE
CONNECTING BAKTARNAGAR.
(BY PASS)
PLAN & LONGITUDINAL SECTION FROM Km 3/000 TO Km 3/985.125

SCALE Drg, No. RITES/KOL/DVC-000/12

3 OF 14
Sh.No

Date JULY 2012


RITES LIMITED
( A GOVT. OF INDIA ENTERPRISE )
PROJECT CODE : REV.
ALIGNMENT

GRADIENT

DATUM (+)50m

CUT / FILL

FORMATION LEVEL

65m

40m
40m

15m
15m
To MTPS

40m
40m

65m

1. All DIMENSIONS ARE IN METRES UNLESS OTHER WISE MENTIONED.

FL : 84.124
2. ALL LEVELS ARE RELATED TO THIS SURVEY ARE BASED ON THE RAIL TOP

FL : 84.124

Km 4/585
(0/769.22)
Km 4/750
LEVEL OF EXISTING POWER HOUSE LINE CLOSE TO THE POWER UNITS.
THE VALUE IS 111.000m ABOVE M.S.L. ( GTS )

3. TAKE OFF POINT OF PROPOSED LINE IS ASSUMED AS 0.000

FL : 84.056

FL : 83.823
(0/769.22)

Km 1/500
Km 4/750
4. HEIGHT MENTIONED IN DRAWING FOR OVERHEAD CROSSING ARE ABOVE
GROUND LEVEL.

5. DIFFERENCE BETWEEN FORMATION LEVEL AND RAIL TOP LEVEL IS 0.638m

8
.88 4
: 87 25 .46 7. 60KG RAIL AND 60KG PSC SLEEPER SHALL BE PROVIDED IN PROPOSED LINE.
FL 5/5 =88
P
Km TO
IL
RA 8. ALL POINTS AND CROSSING SHALL BE PROVIDED 1 IN 12 FAN SHAPE CURVE
SWITCH WITH 60 Kg RAIL AND SLEEPER. UNLESS OTHERWISE MENTIONED.
.22
/5 19
.5
Km

N O T E S :-
THIS DRAWING IS PREPAIRED BASED ON CE's DRG No. D-000-98, DRM/ ASN/ Drg. No 124-98,
125-98 AND ACTUAL FIELD SURVEY.

EASTERN RAILWAY
.62
Km 6 .165
/047
89
FL :

DAMODAR VALLEY CORPORATION


PROVISION OF DOUBLING
BETWEEN RANIGANJ & WAITING BAY LINE OF
MEJIA CAPTIVE LINE INCLUDING BYPASS LINE
CONNECTING BAKTARNAGAR.
(DOUBLING)
PLAN & LONGITUDINAL SECTION FROM Km (-)0/050.05 TO Km 1/500

SCALE Drg, No. RITES/KOL/DVC-000/12

4 OF 14
Sh.No

Date JULY 2012


RITES LIMITED
( A GOVT. OF INDIA ENTERPRISE )
PROJECT CODE : REV.
CURVE NO 2(LH)
A=68 -24'-51"
R=350m
ALIGNMENT T=237.923m
CL=417.918m

GRADIENT

DATUM (+)50m
CUT / FILL

FORMATION LEVEL
To
Ran
iga
nj

15m

3
.82
: 83 00
FL
1/5
Km
20m

Km 2/863.6
FL : 85.000
Km 2/219.22
FL : 86.091
CU
FL : 85.621

Km 3/300
R
60 A=6 VE N
m R=3 9 -36 o 2 LH
'
T=2 44m -45"

3/250
15
m CL= 39.142
NO 417.94 m 1. All DIMENSIONS ARE IN METRES UNLESS OTHER WISE MENTIONED.

SRJ, Km 2/260.32 / Km
NT 70m
RA 9m
NSI
TIO 70m
20
m
A=
6
N 2. ALL LEVELS ARE RELATED TO THIS SURVEY ARE BASED ON THE RAIL TOP
R= 9
3
T= 50 6 - 3 LEVEL OF EXISTING POWER HOUSE LINE CLOSE TO THE POWER UNITS.
CL 243 m '-45" 60m
=4 .31 THE VALUE IS 111.000m ABOVE M.S.L. ( GTS )
25 m
.24 TO RANIGANJ
60 m 25m
m N.H.-60 3. TAKE OFF POINT OF PROPOSED LINE IS ASSUMED AS 0.000
25m
DN MAIN
UP MAIN 4. HEIGHT MENTIONED IN DRAWING FOR OVERHEAD CROSSING ARE ABOVE
GROUND LEVEL.

Br.No. 8R, 1 x 3.0m RC Box,


15m

Km 2/850 / Km. 2/660.32


15m
5. DIFFERENCE BETWEEN FORMATION LEVEL AND RAIL TOP LEVEL IS 0.638m

70m
70m
60m
CUR
V
7. 60KG RAIL AND 60KG PSC SLEEPER SHALL BE PROVIDED IN PROPOSED LINE.
A=69 E No 2A
R=35 -36'-45" LH
T=24 6m 8. ALL POINTS AND CROSSING SHALL BE PROVIDED 1 IN 12 FAN SHAPE CURVE
CL= 7.484m
Km 2/219.22

SWITCH WITH 60 Kg RAIL AND SLEEPER. UNLESS OTHERWISE MENTIONED.


FL : 85.621

4
NON 32.528m
TRA
NSIT
ION

Km 2/655.62
FL : 84.934
N O T E S :-
THIS DRAWING IS PREPAIRED BASED ON CE's DRG No. D-320-98, DRM/ ASN/ Drg. No 123-98
AND ACTUAL FIELD SURVEY.

EASTERN RAILWAY

DAMODAR VALLEY CORPORATION


PROVISION OF DOUBLING
BETWEEN RANIGANJ & WAITING BAY LINE OF
MEJIA CAPTIVE LINE INCLUDING BYPASS LINE
CONNECTING BAKTARNAGAR.
PLAN & LONGITUDINAL SECTION FROM Km. 1/500 TO Km. 3/000

SCALE Drg, No. RITES/KOL/DVC-000/12

5 OF 14
Sh.No

Date MAY' 2012


RITES LIMITED
( A GOVT. OF INDIA ENTERPRISE )
PROJECT CODE : REV.
ALIGNMENT

GRADIENT

DATUM (+)50m

CUT / FILL

FORMATION LEVEL

Km 1/513.2
FL : 85.000
1. All DIMENSIONS ARE IN METRES UNLESS OTHER WISE MENTIONED.

2. ALL LEVELS ARE RELATED TO THIS SURVEY ARE BASED ON THE RAIL TOP
LEVEL OF EXISTING POWER HOUSE LINE CLOSE TO THE POWER UNITS.
80m 80m THE VALUE IS 111.000m ABOVE M.S.L. ( GTS )
70m 70m
3. TAKE OFF POINT OF PROPOSED LINE IS ASSUMED AS 0.000
DAMODAR RIVER
RA
80m NKU 4. HEIGHT MENTIONED IN DRAWING FOR OVERHEAD CROSSING ARE ABOVE
UR / BA
AVP GROUND LEVEL.
URL

D-43
TO D 15m 15m

42
D-
N.H.-60 N.H.-60 N.H.-60 N.H.-60
N.H.-60 N.H.-60 DN LINE 5. DIFFERENCE BETWEEN FORMATION LEVEL AND RAIL TOP LEVEL IS 0.638m
To Raniganj
D-44 UP / DN LINE UP LINE
ROAD CUM RAIL BRIDGE No 5R ( DAMODAR RIVER )
D-45

COMMON LOOP
25m 25m
80m

BR.No. 4R, 1x6.1m RCC Slab


DAMODAR RIVER 7. 60KG RAIL AND 60KG PSC SLEEPER SHALL BE PROVIDED IN PROPOSED LINE.

Km 1/575, Km 3/944.22
8. ALL POINTS AND CROSSING SHALL BE PROVIDED 1 IN 12 FAN SHAPE CURVE
70m
2X32.976m + 15X 48.5m STEEL GIRDER,

70m SWITCH WITH 60 Kg RAIL AND SLEEPER. UNLESS OTHERWISE MENTIONED.


80m 80m
Km 2/100, PROP. Km 3/410.22

FL : 84.934
PROP. Km 4/006.02
Km 1/513.2,

N O T E S :-
THIS DRAWING IS PREPAIRED BASED ON CE's DRG No. D-319-98, DRM/ ASN/ Drg. No 122-98 AND
ACTUAL FIELD SURVEY.

EASTERN RAILWAY

DAMODAR VALLEY CORPORATION


PROVISION OF DOUBLING
BETWEEN RANIGANJ & WAITING BAY LINE OF
MEJIA CAPTIVE LINE INCLUDING BYPASS LINE
CONNECTING BAKTARNAGAR.
(DOUBLING)
PLAN & LONGITUDINAL SECTION FROM Km. 3/000 TO Km. 4/500

SCALE Drg, No. RITES/KOL/DVC-000/12

6 OF 14
Sh.No

Date JULY 2012


RITES LIMITED
( A GOVT. OF INDIA ENTERPRISE )
PROJECT CODE : REV.
X
BO
R. 9
5m .5
C
1. 07
1x 5/9
AS m
K
ED ,
N D 8A
TE o
EX R . N
BE . B
T
TO I S
EX
CURVE NO 3(LH)
A=57 -30'-00"
R=500m CURVE NO 4(RH)
T=274.31m A=11 -02'-53"
ALIGNMENT CL=501.78m R=600m
T=58.027m
CL=115.695m

GRADIENT
DATUM (+)50m

CUT / FILL

FORMATION LEVEL

00
5
8.37

FL : 82.5
Km 2/52
17
0
Km 2/63
FL : 82.2
Km 0/00
1. All DIMENSIONS ARE IN METRES UNLESS OTHER WISE MENTIONED.

2. ALL LEVELS ARE RELATED TO THIS SURVEY ARE BASED ON THE RAIL TOP
LEVEL OF EXISTING POWER HOUSE LINE CLOSE TO THE POWER UNITS.
THE VALUE IS 111.000m ABOVE M.S.L. ( GTS )

3. TAKE OFF POINT OF PROPOSED LINE IS ASSUMED AS 0.000


25m
4. HEIGHT MENTIONED IN DRAWING FOR OVERHEAD CROSSING ARE ABOVE
DN LINE
25m
25m
GROUND LEVEL.
E UP LINE
LAG
VIL
5. DIFFERENCE BETWEEN FORMATION LEVEL AND RAIL TOP LEVEL IS 0.638m
35m
25m

7. 60KG RAIL AND 60KG PSC SLEEPER SHALL BE PROVIDED IN PROPOSED LINE.
15m

30m
8. ALL POINTS AND CROSSING SHALL BE PROVIDED 1 IN 12 FAN SHAPE CURVE
SWITCH WITH 60 Kg RAIL AND SLEEPER. UNLESS OTHERWISE MENTIONED.

D-40

45m

N O T E S :-
THIS DRAWING IS PREPAIRED BASED ON CE's DRG No. D-318-98& 317-98, DRM/ ASN/ Drg. No
121-98, 129-98 AND ACTUAL FIELD SURVEY.

EASTERN RAILWAY

DAMODAR VALLEY CORPORATION


PROVISION OF DOUBLING
BETWEEN RANIGANJ & WAITING BAY LINE OF
MEJIA CAPTIVE LINE INCLUDING BYPASS LINE
CONNECTING BAKTARNAGAR.
(DOUBLING)
PLAN & LONGITUDINAL SECTION FROM Km. 4/500 TO Km. 6/000

SCALE Drg, No. RITES/KOL/DVC-000/12

7 OF 14
Sh.No

Date JULY 2012


RITES LIMITED
( A GOVT. OF INDIA ENTERPRISE )
PROJECT CODE : REV.
E
D, B
N E TO
AN G
M IN
SS L-X

ER
LA D

E 65
RD
' C NE

AT 7/4
GI
52 'C N
0. AS MA

L Km
82 D N-

EE A ,
PL
6/ IVE U

ST . 2
G

5
Km OV TIN

m o
.2 . N
PR IS

12 Br
EX

5x op.
Pr
CURVE NO 6(RH) CURVE NO 7(LH)
A=06 -15'-01" A=06 -27'-57"
R=400m R=400m
CURVE NO 5(RH) T=21.84m T=22.59m
A=04 -58'-51" CL=43.636m CL=45.14m
ALIGNMENT
R=1000m
T=41.493m
CL=86.932m

GRADIENT

DATUM (+)50m

CUT / FILL

FORMATION LEVEL

BR No. 2A, 5x12.2m P.R.C. GIRDER,


FL : 84.000
Km 0/850
BR No. 7A, 1x1.2m R.C.C. PIPE, Km 2/025

FL : 83.000
Km 1/350
FL : 82.500

1. All DIMENSIONS ARE IN METRES UNLESS OTHER WISE MENTIONED.


Km 1/850

Km 0/700
BR. No. 6A (1x1.2m)
R.C. PIPE, Km 1/800

2. ALL LEVELS ARE RELATED TO THIS SURVEY ARE BASED ON THE RAIL TOP
55m
LEVEL OF EXISTING POWER HOUSE LINE CLOSE TO THE POWER UNITS.

E
55m

AG
1" TO CURVE NO 7(LH) THE VALUE IS 111.000m ABOVE M.S.L. ( GTS )
A=04 -58'-5

L
N.H

VIL
.-6 A=06 -27'-57"
R=1 00 0m 0 R=400m
T=41.493m E 3. TAKE OFF POINT OF PROPOSED LINE IS ASSUMED AS 0.000
VILLAG T=22.59m
CL=86.932m CL=45.14m
15m
15m 6m
D-29
4. HEIGHT MENTIONED IN DRAWING FOR OVERHEAD CROSSING ARE ABOVE

D-28A
D-30
33 D-32 GROUND LEVEL.
D- DN LINE
DN LINE 10m

5x 12.2m STEEL PLATE GIRDER


10m CURVE NO 6(RH)
D-31

UP LINE
UP LINE A=06 -15'-01" 5. DIFFERENCE BETWEEN FORMATION LEVEL AND RAIL TOP LEVEL IS 0.638m

Prop. Br. No. 2A, Km 7/465


DITCH R=400m

U/M L-XING, (TO BE PROVIVED AS


'C' CLASS MANNED),Km 6/820.525
TO T=21.84m
CH 55m
AT CL=43.636m
E
)

NA 55m
L.T. LIN
IE D

D)
MODIF

5(RH) 7. 60KG RAIL AND 60KG PSC SLEEPER SHALL BE PROVIDED IN PROPOSED LINE.
CURVE NO
FIE

4 -58'-51"
ODI

A =0
R=1000m
(TO BE

Km 6/807.59
BE M

8. ALL POINTS AND CROSSING SHALL BE PROVIDED 1 IN 12 FAN SHAPE CURVE


FL : 82.934

T=41.493m
CL=86.932m SWITCH WITH 60 Kg RAIL AND SLEEPER. UNLESS OTHERWISE MENTIONED.
(TO

N O T E S :-
THIS DRAWING IS PREPAIRED BASED ON CE's DRG No. D-000-98, DRM/ ASN/ Drg. No 120-98
AND ACTUAL FIELD SURVEY.

EASTERN RAILWAY

DAMODAR VALLEY CORPORATION


PROVISION OF DOUBLING
BETWEEN RANIGANJ & WAITING BAY LINE OF
MEJIA CAPTIVE LINE INCLUDING BYPASS LINE
CONNECTING BAKTARNAGAR.
(DOUBLING)
PLAN & LONGITUDINAL SECTION FROM Km. 6/000 TO Km. 7/500

SCALE Drg, No. RITES/KOL/DVC-000/12

8 OF 14
Sh.No

Date JULY 2012


RITES LIMITED
( A GOVT. OF INDIA ENTERPRISE )
PROJECT CODE : REV.
/
1
16
9/
m
,K
NG
XI
L-
/M
88 U
8/ ASS
4
K m ' CL
'C
CURVE No 8(LH)
A=06 -29'-13"
R=500m
CL=56.609m CURVE NO 10(LH)

R= 400.0m
T=119.659m
ALIGNMENT CURVE No 9(RH) CL=232.54m
A=06 -30'-08"
R=500m
CL=56.74m

GRADIENT
DATUM (+)50m

CUT / FILL

FORMATION LEVEL

CU
A= RVE N
R= 06 -29 O 8(L

G, Km TENDED)
5
T=2 00m '-13" H)
CL 8.33m

9/161,
=56
.60
9m

/M L TO BE EX
CU
A= RVE
N
R= 06 -30 O 9(
T= 500m '-08" RH)

N
9
Km 4.000

I
CL 8.40m

G
03.8

X
'C' CL 84, (L-XIN
=56

-
.74
0/6
8

m
FL :

ASS U
TO
30m 1. All DIMENSIONS ARE IN METRES UNLESS OTHER WISE MENTIONED.

/8
N.
30m

8
H.

m
-6
55m

K
0
2. ALL LEVELS ARE RELATED TO THIS SURVEY ARE BASED ON THE RAIL TOP
55m
E( U/C) 10m
HT LIN LEVEL OF EXISTING POWER HOUSE LINE CLOSE TO THE POWER UNITS.
HT 11 KV THE VALUE IS 111.000m ABOVE M.S.L. ( GTS )
LIN
E( 35m
U/C
) 30m
6.350
FL : 8 50

3. TAKE OFF POINT OF PROPOSED LINE IS ASSUMED AS 0.000


30m
9 /8

30m
Km
Km 0/2 5

E 4. HEIGHT MENTIONED IN DRAWING FOR OVERHEAD CROSSING ARE ABOVE


.87

LIN
00

LT
7

FL : 85

GROUND LEVEL.
D-2

20m
INE
55m 3 DN L
D-2 NE 5. DIFFERENCE BETWEEN FORMATION LEVEL AND RAIL TOP LEVEL IS 0.638m
/C UP L
INE LT LI
INE U E
55m HT L VHT LIN
A=33 ' 32" 11 K
R=400m
35m

TO VILLAGE
T=119.659m
D
CL=232.54m RTE
IVE
10m BE D 7. 60KG RAIL AND 60KG PSC SLEEPER SHALL BE PROVIDED IN PROPOSED LINE.
D TO
ROA

Box
35m RS
ATE LIN
E
8. ALL POINTS AND CROSSING SHALL BE PROVIDED 1 IN 12 FAN SHAPE CURVE
. QU

R.C.C
5 No
6

LT
D-2

20m SWITCH WITH 60 Kg RAIL AND SLEEPER. UNLESS OTHERWISE MENTIONED.


ION
D-24

ERT

Km 8/ AS 1x1.5m
D DIV
30m ROA
E

UR
TO B

445
ID ASP

BR No XTENDED
20m
KAL
TO 30m
K
TRAC
TING ED

,
CURVE N

6
E
1
O 10(LH)

TO BE
ANTL

R= 400.0m VILLAGE
T=119.65
DISM

9m
S

CL=232.54
I

m
E X
57.59
Km 7/9 9
.80
FL : 85

N O T E S :-
THIS DRAWING IS PREPAIRED BASED ON CE's DRG No. D-316-98, DRM/ ASN/ Drg. No 118-98
AND ACTUAL FIELD SURVEY.

EASTERN RAILWAY

DAMODAR VALLEY CORPORATION


PROVISION OF DOUBLING
BETWEEN RANIGANJ & WAITING BAY LINE OF
MEJIA CAPTIVE LINE INCLUDING BYPASS LINE
CONNECTING BAKTARNAGAR.
(DOUBLING)
PLAN & LONGITUDINAL SECTION FROM Km. 7/500 TO Km. 9/000

SCALE Drg, No. RITES/KOL/DVC-000/12

9 OF 14
Sh.No

Date JULY 2012


RITES LIMITED
( A GOVT. OF INDIA ENTERPRISE )
PROJECT CODE : REV.
ALIGNMENT CURVE NO 11(RH)

R= 1000.0m
T=364.122m
CL=698.132m

GRADIENT
DATUM (+)50m

CUT / FILL

FORMATION LEVEL

BR No. 13, 2x1.20m R.C.C. PIPE, Km 7/850

BR No. 12, 1x1.20m R.C.C. PIPE, Km 7/550


Km 10/495, (BR TO BE EXTENDED)
FL : 91.850
Km 7/900
NE
LI
HT
KV
11

HT LINE U/C 25m 1. All DIMENSIONS ARE IN METRES UNLESS OTHER WISE MENTIONED.
25m

/C 2. ALL LEVELS ARE RELATED TO THIS SURVEY ARE BASED ON THE RAIL TOP
INE U 11 KVHT LINE
HT L LEVEL OF EXISTING POWER HOUSE LINE CLOSE TO THE POWER UNITS.
10m THE VALUE IS 111.000m ABOVE M.S.L. ( GTS )

D-18
m
0.0
100 2m 30m
R= 364.12 132m D-19 3. TAKE OFF POINT OF PROPOSED LINE IS ASSUMED AS 0.000

BR TO BE EXTENDED AS 1x3.0m R.C.C Box


T= =698. 30m
CL
HEIGHT
1.5m 4. HEIGHT MENTIONED IN DRAWING FOR OVERHEAD CROSSING ARE ABOVE
L O NG X L
E 700m ING WAL GROUND LEVEL.
LIN IN
DN LINE RETA
UP
5. DIFFERENCE BETWEEN FORMATION LEVEL AND RAIL TOP LEVEL IS 0.638m

BR No. 13, Km 10/195


NE H)
LI 1(R
HT O1
KV N
11 RVE
CU m
0.0

FL : 91.784
Km 10/145
= 100 122m m 7. 60KG RAIL AND 60KG PSC SLEEPER SHALL BE PROVIDED IN PROPOSED LINE.
R 364. 132
T= =698.
CL 8. ALL POINTS AND CROSSING SHALL BE PROVIDED 1 IN 12 FAN SHAPE CURVE
SWITCH WITH 60 Kg RAIL AND SLEEPER. UNLESS OTHERWISE MENTIONED.
LT LINE
86
0.

C
83 21

U/
8/ 9/

NE
0

Km Km

LI
E, D)

T
1. 50
0

m H
N
85
: /7

LI OU

m 25
FL 8

30
HT GR
9

Km

KV ER
11 ND
(U

m
10

m
30

N O T E S :-
THIS DRAWING IS PREPAIRED BASED ON CE's DRG No. D-315-98, DRM/ ASN/ Drg. No 117-98
AND ACTUAL FIELD SURVEY.

EASTERN RAILWAY
1. 95

NE
4
78
: /2

U/
C LI
FL 9

HT
9

Km

NE V
LI 1 K
T 1
H
m
30
DAMODAR VALLEY CORPORATION
G 0m
EI 3
T

m
H LL
H

30
5m A
2. W
X NG

PROVISION OF DOUBLING
I
NG IN
LO TA

BETWEEN RANIGANJ & WAITING BAY LINE OF


RE

MEJIA CAPTIVE LINE INCLUDING BYPASS LINE


CONNECTING BAKTARNAGAR.
(DOUBLING)
PLAN & LONGITUDINAL SECTION FROM Km. 9/000 TO Km. 10/5

SCALE Drg, No. RITES/KOL/DVC-000/12

10 OF 14
Sh.No

Date JULY 2012


RITES LIMITED
( A GOVT. OF INDIA ENTERPR
PROJECT CODE : REV.
ER
RD
GI
E
AT
PL
m
.2
6x 6
12
AS 20.
ED 0/8
ND 1
TE Km
EX 1,
BE o. 1
TO . N
BR
CURVE NO 12(RH)
CURVE NO 13(LH)
R= 500.0m CURVE NO 14(LH)
CL=30.91m R= 500.0m
CL=30.54m R= 500.00m
T=26.16m
CL=52.275m
ALIGNMENT CURVE NO 15(RH)

R= 500.00m
T=26.46m
CL=52.876m

RISE 1 IN 200
GRADIENT

DATUM (+)50m

CUT / FILL

FORMATION LEVEL

BR No. 9, 1x3.05m R.C.C. BOX, Km 6/699.40

BR No. 7, 1x3.05m R.C.C. BOX, Km 6/262.40


PROP. Km 11/345.6, ( BR TO BE EXTENDED

PROP. Km 11/782.6, ( BR TO BE EXTENDED


PROP. Km 11/566.6, ( BR TO BE EXTENDED
BR No. 8, 1x3.05m R.C. BOX, Km 6/478.40
)
FL : 87.000

m 11 ODIFIED
FL : 87.000

Km 6/800
Km 7/415

BR No. 11, 6x12.2) P.R.C. GIRDER,

.3
/502
1. All DIMENSIONS ARE IN METRES UNLESS OTHER WISE MENTIONED.

AS 1X 3.0m RCC BOX)


AS 1X 3.0m RCC BOX)
AS 1X3.0m RCC BOX)

G, K
O B E
T
2. ALL LEVELS ARE RELATED TO THIS SURVEY ARE BASED ON THE RAIL TOP
NALA

LINE
LEVEL OF EXISTING POWER HOUSE LINE CLOSE TO THE POWER UNITS.

XI N

( LT
THE VALUE IS 111.000m ABOVE M.S.L. ( GTS )

L.T.
I
PHAR
Km 7/224.40

3. TAKE OFF POINT OF PROPOSED LINE IS ASSUMED AS 0.000


CHOU

45m 45m

HT LINE U/C HT LINE U/C


25m 25m HT LINE U/C
45m 4. HEIGHT MENTIONED IN DRAWING FOR OVERHEAD CROSSING ARE ABOVE
GROUND LEVEL.
D-17

DN LINE D-14
D-17A
15

UP LINE 5. DIFFERENCE BETWEEN FORMATION LEVEL AND RAIL TOP LEVEL IS 0.638m
30m

D-15
30m
6x12.2m STEEL PLATE GIRDER
PROP BR No. 11, Km 10/820.6

30m

7. 60KG RAIL AND 60KG PSC SLEEPER SHALL BE PROVIDED IN PROPOSED LINE.

8. ALL POINTS AND CROSSING SHALL BE PROVIDED 1 IN 12 FAN SHAPE CURVE


SWITCH WITH 60 Kg RAIL AND SLEEPER. UNLESS OTHERWISE MENTIONED.
PROP Km 11/245

CURVE NO 13(LH) CURVE NO 14(LH) CURVE NO 15(RH)


FL : 86.934
PROP Km 10/630

CURVE NO 12(RH) R= 500.0m R= 500.00m R= 500.00m


T=15.27m T=26.16m T=26.46m
CL=30.54m
FL : 86.934

R= 500.0m CL=52.275m CL=52.876m


T=15.46m
CL=30.91m

N O T E S :-
THIS DRAWING IS PREPAIRED BASED ON CE's DRG No. D-314-98, DRM/ ASN/ Drg. No 116-98
AND ACTUAL FIELD SURVEY.

EASTERN RAILWAY

DAMODAR VALLEY CORPORATION


PROVISION OF DOUBLING
BETWEEN RANIGANJ & WAITING BAY LINE OF
MEJIA CAPTIVE LINE INCLUDING BYPASS LINE
CONNECTING BAKTARNAGAR.
(DOUBLING)
PLAN & LONGITUDINAL SECTION FROM Km. 10/500 TO Km.12/000

SCALE Drg, No. RITES/KOL/DVC-000/12

11 OF 14
Sh.No

Date JULY 2012


RITES LIMITED
( A GOVT. OF INDIA ENTERPRISE )
PROJECT CODE : REV.
ED x
AS
ND Bo
TE .C
EX R.C
BE 3m
Bo (TO 1.8
C . 5 2x
R. /54 3,
0m 14 o.

x)
2. m . N
2x . K BR
op .
Pr IST
EX
CURVE NO 16(LH)

R= 500m
T=188.191m
CL=359.434m CURVE NO 17(RH)
ALIGNMENT
R= 500m
T=136.543m
CL=266.163m

RISE 1 IN 200(C)
GRADIENT
DATUM (+)50m

CUT / FILL

FORMATION LEVEL

HT
LINE
U/C

R= 500m
634

Box
4/1 300

T=136.543m

D
39.

PON
Km 100.

CL=266.163m
.C

1. All DIMENSIONS ARE IN METRES UNLESS OTHER WISE MENTIONED.


R.C
:

VI
FL

RA LLA
0m

D-6
NI GE
PU
x3.

R
2. ALL LEVELS ARE RELATED TO THIS SURVEY ARE BASED ON THE RAIL TOP
DE /100
S1

LEVEL OF EXISTING POWER HOUSE LINE CLOSE TO THE POWER UNITS.


DA
4
EXT Km
0A

THE VALUE IS 111.000m ABOVE M.S.L. ( GTS )


D-1

EN
X,

VI
TO C. BO

RA LLA
NI GE
PU
R
3. TAKE OFF POINT OF PROPOSED LINE IS ASSUMED AS 0.000
BE
.C.
3/9 5m R

HT
LIN
45,

TO 4. HEIGHT MENTIONED IN DRAWING FOR OVERHEAD CROSSING ARE ABOVE


0

EU N
. K 1x3.

/C .H.
-60 /C GROUND LEVEL.
PO NE U
m1

T LI
,
PR o. 4

ND H
N

5. DIFFERENCE BETWEEN FORMATION LEVEL AND RAIL TOP LEVEL IS 0.638m


OP

R= 50
BR

T= 18 0m
CL=3 8.191m
59.43
4m TO CURVE NO 17(RH)
VILL
INE AGE
UP L R= 500m
NE 7. 60KG RAIL AND 60KG PSC SLEEPER SHALL BE PROVIDED IN PROPOSED LINE.
DN LI T=136.543m
D-9

D-8
CL=266.163m
8. ALL POINTS AND CROSSING SHALL BE PROVIDED 1 IN 12 FAN SHAPE CURVE
SWITCH WITH 60 Kg RAIL AND SLEEPER. UNLESS OTHERWISE MENTIONED.

CUR
VE N
O 16(
LH)
R= 50
T=18 0m
8
CL=3 .191m
59.43
4m
6
.36
13/ 234
905
Km 100.
:
FL

N O T E S :-
THIS DRAWING IS PREPAIRED BASED ON CE's DRG No. D-312-98, DRM/ ASN/ Drg. No 114-98
AND ACTUAL FIELD SURVEY.

EASTERN RAILWAY

DAMODAR VALLEY CORPORATION


PROVISION OF DOUBLING
BETWEEN RANIGANJ & WAITING BAY LINE OF
MEJIA CAPTIVE LINE INCLUDING BYPASS LINE
CONNECTING BAKTARNAGAR.
(DOUBLING)
PLAN & LONGITUDINAL SECTION FROM Km. 13/500 TO Km. 15/000

SCALE Drg, No. RITES/KOL/DVC-000/12

13 OF 14
Sh.No

Date JULY 2012


RITES LIMITED
( A GOVT. OF INDIA ENTERPRISE )
PROJECT CODE : REV.

Vous aimerez peut-être aussi