Académique Documents
Professionnel Documents
Culture Documents
INTRODUCTION:
Starting from the power generation for Lucky One mall till the finishing installation
for the luminaries a well synchronize system is observed that effectively delivered
the power to 21 Mega Watt connected load. This project can be recognize as a
vertically integrated system that involves generation, transmission and distribution
of power. Currently there are three main bench marks that insure maximum safety
and provide remedy from total power failures, they are listed as follow:
1. Power House.
2. Main Distribution Switch Gears (MDSG).
3. Substation
4. Electrical Control Room
The main purpose of substation is to step down 11KV voltage to 0.4KV line or 230V
phase voltage and here the lucky power has used 200 KVA dry type transformers
with delta to wye connection configuration. From the secondary side of these
transformers Schneider busways are feed, these power busways are of 630 ampere
rating. These busways are rigid and are not flexible but assure low maintenance
and immunity from fire due to its robust physical nature. For vertical distribution
of power risers are use which are similar to that of busways but their method to
connect with each other is different. They are used to energize electrical control
rooms that are used to provide power to various services, such as lightning scheme
is illuminated using lightning bus which is of 60 amperes. Moreover HVAC system,
emergency lights, escalators, travellators, motor control center, public addressing
service, back box, floor box, elevators are the services that are energized through
this power network.
1
POWER GENERATION
As discussed earlier this project is capable of self-generation and for this purpose a
total of 10 generators are employed of which 2 diesel generators are reserved for
back-up purpose in case of any fault.
Specifically speaking 4 caterpillar generators are installed which are gas fueled in
nature the model name is Caterpillar 3520 and is of 1.95 MW generation capacity.
The remaining four generators of Gen Pak are also of gas each with of 1.33 MW
generation. The use of GAS fuel not only serves to reduce generation cost but also
gas is easily available in the current condition of the state. Here we use Automatic
Transfer Switch to move our load on the back-up generators In case of fault.
2
of working drawings for the average electrical system in large projects usually
consists of:
1. A plot plan showing the building's location and outside electrical wiring
2. Floor plans showing the location of electrical systems on every floor
3. Power-riser diagrams showing panel boards
4. Control wiring diagrams
5. Schedules and other information in combination with construction
drawings.
It is obvious that we focused on floor plans because in lucky one mall each floor
electrical diagram is of great importance. Starting from zonal division the lucky one
mall project is electrically distributed in 4 divisions except ground floor that is
divided into only 3 divisions. Each division is build on the basis of power provided
from sub-station so that any problem due to over loading can be eliminated. The
electrical drawing also shows the connections of HVAC system as well as back boxes
and floor boxes. The drawing also indicate the connection off UPS that are provided
to energize HVAC system and some specific luminaries in case of power failures.
The drawing not only indicate the power flow but also shows the specification of
cables used and Bus way power ratings, for example the power bus ways are of 630
ampere, bus risers for HVAC range from 200A to 600A depending upon nature of
load and the HT cables are 3C,30mm,Cu/xlpe/unarmored. All this information can
be read directly from electrical drawing. The symbols use to indicate an object are
pre-defined and can be easily found from online libraries. Lucky one has prepared
a uniform sketch which nearly remain same for all floors and help the engineers to
easily design lightning scheme and to conduct maintenance in future.
Fire-resistant dry type or "cast resin" transformers are well suited for installation in
high-rise buildings, hospitals, underground tunnels, school, steel factories,
chemical plants and places where fire safety is a great concern. Hazard free to the
environment, dry type transformers have over the years proven to be highly
reliable. “Dry type” simply means it is cooled by normal air ventilation. The dry type
transformer does not require a liquid such as oil or silicone or any other liquid to
cool the electrical core and coils. Dry type transformers are voltage changing (Step-
up or Step-down) or isolation device that is air cooled rather than liquid cooled. The
transformer case is ventilated to allow air to flow and cool the coil (coils).
Dry type transformers differ from liquid-filled units in many ways, and separate
industry standards apply to their design, construction, and maintenance. Dry-Type
Transformers suitable for indoor and outdoor applications anywhere that safe and
dependable power are important. Cooling ducts in the windings allow heat to be
dissipated into the air. Dry-types can operate indoors under almost all ambient
conditions for commercial buildings and light manufacturing facilities. For outdoor
operations, a dry-type transformer's enclosure will usually have louvers for
ventilation. But, these transformers can be affected by hostile environments (dirt,
moisture, corrosive fumes, conductive dust, etc.) because the windings are
exposed to the air. Other approaches to building dry-type transformers for harsh
environments include cast coil units, cast resin units, and vacuum pressure
encapsulated (VPE) units, sometimes using a silicone varnish. Unless the dry-type
units are completely sealed, the core/coil and lead assemblies should be
4
periodically cleaned, even in non-harsh environments, to prevent dust and other
contaminant buildup over time.
There are several different construction methods used in manufacturing dry type
transformers. Each of these different types is suited for particular environments or
applications. If you are looking for corona protection and increased mechanical
strength a VPI dry type transformer would be your best options. But, if you are in a
harsh environment a cast coil transformer may be your answer.
In the cast coil design, the coils are solidly cast in resin under a
vacuum in a mold. Winding processes controlled by advanced
electronics also ensure even distribution and high level of
precision. The cast coil transformers are reliable, have a high
short circuit withstands, and can be exposed to extreme
conditions with minimal maintenance. They are used inside
buildings and tunnels, on ships, offshore platforms and cranes,
food-processing plant, nuclear plants and mining industry.
6
in most ambient conditions are also sealed with an epoxy resin mixture. Another
version of the dry-type transformer is a cast coil insulation system. It is used when
addition coil strength and protection are advisable. These type of transformer are
used in located where environments are harsh, such as cement and chemical plants
and outdoor installations where moisture, salt spray, corrosive fumes, dust, and
metal particles can destroy other types of dry-type transformers. These cast coil
units are better able to withstand heavy power surges, such as frequent but brief
overloads experienced by transformers serving transit systems and various
industrial machinery.
Cast coil units are now being used where previously only liquid-filled units were
available for harsh environments. They can have the same high levels of BIL while
still providing ample protection of the coils and the leads going to the terminals.
Dry-type transformer according to ANSI/EEE C57.96-1989 that you can have a 20-
yr life expectancy for the insulation system in a transformer. For dry-type
transformers having a 220°C, insulating system and a winding hot-spot
temperature of 220°C, and with no unusual operating conditions present, the 20 yr
life expectancy is a reasonable time fame. However, due to degradation of the
insulation, a transformer might fail before 20 years. Most 150°C rise dry-type
transformers are build with 220°C insulation systems. Operating such a transformer
at rated kVA on a continuous basis with a 30°C average ambient should equate to
a "normal" useful life. The life of a transformer increases appreciably if the
operating temperature is lower than the maximum temperature rating of the
insulation. However, you should recognize that the life expectancy of transformers
operating at varying temperatures is not accurately known. Fluctuating load
conditions and changes in ambient temperature make it difficult, if not impossible,
to arrive at such definitive information.
7
Temperature rise ratings are based on full-load rise over ambient (usually 40°C
above ambient and are 150°C (available only with Class H insulation), 115°C
(available with Class H and Class F insulation) and 80°C (available with Class H, F,
and B insulation). A 30°C winding hot spot allowance is provided for each class. The
lower temperature rise transformers are more efficient, particularly at loadings of
50% and higher. Full load losses for 115 °C transformers are about 30% less than
those of 150°C transformers. And 80°C transformers have losses that are about 15%
less than 115°C transformers and 40% less than 150°C transformers. Full load losses
for 150°C transformers range from about 4% to 5% to 30 kVA and smaller to 2% for
500 kVA and larger. When operated continuously at 65% or more of full load, the
115°C transformer will pay for itself over the 150°C transformer in 2 years or less
(1 year). If operated at 90% of full load). The 80°C transformer requires operation
at 75% or more of full load for a 2-year payback, and at 100% load to payback in 1
year over the 150°C transformer. If operated continuously at 80% or more of full
load, the 80°C transformer will have a payback over the 115°C transformer in 2
years or less. You should note that at loadings below 50% of full load, there is
essentially no payback for either the 115°C or the 80°C transformer over the 150°C
transformer, Also at loadings below 40% the lower temperature rise transformers
become less efficient that the 150°C transformers. Thus, not only is there no
payback, but also the annual operating cost is higher.
Wave Cast coil transformers from GE are characterized by high safety, reliability,
energy-savings, and convenient maintenance. Advanced design of the winding
assembly establishes superior performance to meet today’s exacting needs.
Indoors or outdoors, they are designed for use in the most demanding and diverse
environments and in all applications requiring reliable power.
8
METAL CLAD SWITCH GEAR:
Metal-clad switchgear act as an intelligent fault detection switch, which disconnect
the supply under faulty conditions as well as for maintenance purpose. It may be
either a circuit breaker (usual) or a load-break interrupter switch (unusual). Circuit
breakers are always electrically operated. Extensive barriering, shutters over the
primary circuit elements when the interrupter is withdrawn, and insulation-
covered bus are all required. The minimum rated voltage is 4.76 kV. This rating is
commonly used on 2400 V ac circuits, but is seldom used at lower voltages. Ratings
are available up to 38 kV. Metal-clad is usually considered the top of the line of
medium-voltage metal-enclosed switchgear.
9
Seco Gear metal clad switchgear is designed and manufactured with advanced
technology and has been comprehensively and successfully type tested by KEMA.
Seco Gear switchgear is typically used in power plants, substations and suitable to
provide control and protection for transformers, capacitors and motors. The rated
voltage of Seco Gear is 12kV - 17.5kV and rated current ranges from 630A to 4000A
(4000A has force cooling). All Seco Gear with switching device are equipped with
Seco vacuum circuit breaker with corresponding specifications. Seco Gear
switchgear is designed for indoor applications, and is particularly suitable for
applications in industry, mining, oil and gas and infrastructure. Seco Gear is
designed, assembled and tested to meet or exceed applicable IEC and GB/DL
standards.
10
BUSBAR TRUNKING (BUSWAYS)
Busways, also referred to as busbar trunking systems, stand out for their ease of
installation, flexibility and number of possible connection points Busbar trunking is
intended to distribute power (from 20 A to 5000 A) and lighting (in this application,
the busbar trunking may play a dual role of supplying electrical power and
physically holding the lights).
11
Radial distribution using busways
Supplied:
STANDARDS
Busbar trunking systems must meet all rules stated in IEC 61439-6.This defines the
manufacturing arrangements to be complied with in the design of busbar trunking
systems (e.g.: temperature rise characteristics, short-circuit withstand, mechanical
strength, etc.) as well as test methods to check them.
The new standard IEC61439-6 describes in particular the design verifications and
routine verifications required to ensure compliance. By assembling the system
components on the site according to the assembly instructions, the contractor
benefits from conformity with the standard.
14
Simplicity
Design can be carried out independently from the distribution
and layout of current consumers.
Performances are independent of implementation: the use of
cables requires a lot of derating coefficients.
Clear distribution layout
Reduction of fitting time: the trunking system allows fitting
times to be reduced by up to 50% compared with a traditional
cable installation.
Manufacturer’s guarantee.
Controlled execution times: the trunking system concept
guarantees that there are no unexpected surprises when
fitting. The fitting time is clearly known in advance and a quick
solution can be provided to any problems on site with this
adaptable and scalable equipment.
Easy to implement: modular components that are easy to
handle, simple and quick to connect.
Dependability
Reliability guaranteed by being factory-built
Fool-proof units
Sequential assembly of straight components and tap-off units
making it impossible to make any mistakes
Continuity of service
The large number of tap-off points makes it easy to supply
power to any new current consumer. Connecting and
disconnecting is quick and can be carried out in complete
safety even when energized. These two operations (adding or
modifying) take place without having to stop operations.
Quick and easy fault location since current consumers are near
to the line
Maintenance is nonexistent or greatly reduced
15
Busbar trunking systems allow circuits to be combined.
Compared with a traditional cable distribution system,
consumption of raw materials for insulators is divided by 4 due
to the busbar trunking distributed network concept.
Reusable device and all of its components are fully recyclable.
Does not contain PVC and does not generate toxic gases or
waste.
Reduction of risks due to exposure to electromagnetic fields.
16