Académique Documents
Professionnel Documents
Culture Documents
March 2018
Finally, we hope that this report will provide benefits for MCA-
Indonesia as the Owner of this project, for Badan Restorasi Gambut and all
readers as well.
Hernawan Mahfudz
Project Chief Operating Officer
Preface i
Contents ii
List of Figuresiv
List of Tables v
Chapter I. Introduction....................................................................................................................................1
1.1 Background ............................................................................................................... 1
1.2 Objectives ................................................................................................................... 2
1.3 Report Systematics ................................................................................................. 3
1.4 Problems Arose ........................................................................................................ 4
1.4.1 Change in Scope of Work ........................................................................... 4
1.4.2 Devices Procurement .................................................................................. 5
1.1 BACKGROUND
1.2 OBJECTIVES
Chapter I. Introduction
1.1 Background
1.2 Objectives
1.3 Report Systematics
1.4 Problems Arose
The purchasing process of the Water Table Pilot Monitoring Devices also
requires delicate attention. After consulting with Procurement Agent of MCA-
I, it was concluded that the purchasing process may not meet the deadline of
this Contract.
During the consultation period, it was found that area of Ogan Komering Ilir
and Kubu Raya are already planned under the National State Budget (APBN).
These locations cannot receive funding from other sources that have similar
end-products, to avoid further conflict.
replacement locations are Musi Banyuasin and Pulang Pisau. Deputy-II of BRG
(Mr. Alue Dohong) also requested that the location of Pulang Pisau which was
already programmed by APBN last year, to be reconducted.
The proposal was made official through Contract Amendment No.1. The whole
process in deciding the change of the Consultant’s Scope of Work took 2
months.
This situation of course will reduce the benefit planned to be received by BRG
significantly. At this time, BRG is in need of remote devices for monitoring the
water table. Based on regulation, at least 15% of production blocks should be
monitored.
Figure II-1 shows the interrelationships between the activities. As one of the
main goals’ manifestation, Detailed Engineering Design (DED) requires
primary and supporting data, namely:
Some activities indeed run in series, such as surveys and analysis. But as a
whole, these activities also work together, since the analysis of DED requires
more analysis conducted by other activities.
In the end of this project, the product of this Technical Assistance to BRG are:
a. Water Table
b. Rain Gauge
c. Temperature
d. Methane
e. Soil Moisture
f. Wind Direction
3.1 PRODUCT
2. Fire Hazard Map. This map is required to determine the priority area map
for canal blocking plan.
3. Peat Thickness Map. This map was produced from field survey.
4. Priority Area Map. This map will narrow down the target, increasing the
leverage impact of the canal blocking structures planned to implement in
the area.
Complete product can be found in the soft files, in native format and in Portable
Document Format (PDF).
3. Field survey:
3.3 CHALLENGES
During the project, there are challenges that had to be overcame. Under close
coordination with MCA-I, BRG and the team as well, those challenges were
managed. Some challenges and the mitigation actions are described in Table
III-1 below.
3.4 IMPLEMENTATION
3.4.1 Survey Timeline
FPIC team that had already arrived in the project area, was preceding
technical team, collecting information and meeting important
stakeholders in project area. Preliminary information such as local
people’s perception on this project, land status, concession area
delineation and other information was collected and discussed with
technical team, finding the best strategy to start the survey.
GPR data acquisition was conducted and followed the survey routes
defined during field orientation.
e. Data Processing
After GPR data acquisition acquired, data will be processed to obtain the
depth of peat layer in survey area.
3.4.2 Result
In Musi Banyuasin, Hand-Auger data result shows the peat thickness in the
survey points ranged between 1.5 – 2 meters. According to georadar peat
contour map, the Hand-Auger points are located in area with peat
thickness around 1.5 to 2 meters. The matching range values between the
hand-auger and georadar result lead to the conclusion that peatland
contour map surveyed with georadar is valid. Range values are used since
the Hand-Auger estimated the peat thickness based on depth sampling
interval.
4.1 PRODUCT
1. Concession Area Delineation Map. Together with FPIC Team, the Canal
Blocking Team visited the assisted area to reconfirm the boundaries.
2. Priority Area Map. Together with Peatland Mapping team, the Canal
Blocking Team developed and analyzed the priority area criteria.
4. Canal Blocking Types. Canal Blocking types also considered the inputs
from local land owners, demanded the canal blockings to facilitate river
transport.
In order to produce those products, the data sources used are listed below:
2. Field Survey:
Hydrometry survey
Cross-sectional topography
Geotechnical survey
Interviews with local villagers
4.3 CHALLENGES
During the project, there are challenges that had to be overcame. Under close
coordination with MCA-I, BRG and the team as well, those challenges were
managed. Some challenges and the mitigation actions described in Table IV-1
below.
4.4 IMPLEMENTATION
To identify canal block locations in Musi Banyasin and Pulang Pisau, site
surveys in those location were conducted to get the coordinate and type of
canal block that will be implemented.
The administrative documents such as: (1) introduction letter for permit,
addressed to the office of provincial, district, sub-district; (2) surveyor
team member list; (3) survey duration estimation document; and (4) other
documents on the flight tickets, local transport as well as the necessary
equipment.
The information obtained by FPIC team was analyzed further for the
survey activities.
3. Survey execution.
The survey was conducted for 3 (three) days in Musi Banyuasin and 20
(twenty) days in Pulang Pisau. More detailed information about the
duration is explained in the following table.
The data acquired from secondary data and site visit survey were used to
determine canal block locations, considering the acquired data such as canal
properties, elevation, and land use. The result of this activity is canal block
locations and types, 20 units in Musi Banyuasi, and 971 units in Pulang Pisau.
These canal blocking locations and types then analyzed by DED activity, to
produce 720 DEDs in both area.
5.1 PRODUCT
2. 700 canal blocking structures that are located in KHG Sungai Kahayan-
Sungai Sebangau.
In order to produce those products, the data sources used are listed below:
5.3 CHALLENGES
During the project, there are challenges that had to be overcome. Under close
coordination with MCA-I, BRG and the field teams, those challenges were
managed. Some challenges and the mitigation actions described in Table V-1
below.
5.4 IMPLEMENTATION
Detailed Engineering Design (DED) analyzed the result of Canal Blocking Plan,
where further survey was conducted to acquire primary data for dimension
calculations. Description of Detailed Engineering Design is presented as
follows:
3. Based on the Contract, the amount of DED for Musi Banyuasin and Pulang
Pisau is 720 units. Therefore, we selected 20 locations in Musi Banyuasi
and 700 locations in Pulang Pisau for DED.
6.1 PRODUCT
Those products are mainly acquired from series of local approaches, FGD
(Forum Group Discussion) held in Sub-District level and Village level.
6.3 CHALLENGES
During the project, there are challenges that had to be overcome. Under close
coordination with MCA-I, BRG and the Consultant’s field teams, those
challenges were managed. Some challenges and the mitigation actions are
described in Table VI-1 below.
7.1 PRODUCT
1. Water Table
2. Rain Gauge
3. Temperature
4. Methane
5. Soil Moisture
6. Wind Direction
c. GSM. The data are transmitted through GSM connections to the server,
together with data received from the other device through Radio
Frequency.
1. Coordinate points from BRG. BRG already has planning for Water Table
Monitoring Devices across peatland in Indonesia. Every new water table
monitoring device should refer to the stipulated coordinates.
7.3 CHALLENGES
During the project, there are challenges that had to be overcame. Under close
coordination with MCA-I, BRG and the team as well, those challenges were
managed. Some challenges and the mitigation actions are described in Table
VII-1 below.
7.4 IMPLEMENTATION
The installation location of Water Table Monitoring Devices must follow BRG
direction. This direction is also listed in the group of coordinates in Jambi
Province and Central Kalimantan. Based on the recommendation of
representatives of TRGD Jambi, TRGD Central Kalimantan, and Universitas
Jambi, the installation locations had to consider the security aspect and
maintenance aspect. Best practices were discussed, to minimize disturbances
against insects, rodents, and also against theft as well.
Moreover, the location was quite remote from the nearest road and local
residences. This condition might lead to lack of surveillance against theft and
vandalism.
The process implemented by MCA-I had already run in the track to produce
proper Detailed Engineering Design for the Canal Blocking Plan. Activities
were monitored by milestones, each one is closed by deliverable. This
deliverable is required, as a requirement to proceed to the next step.
Restoring the ecosystem function of the canal with backfilling might drastically
change the daily behavior of local inhabitants. However, when the land was
stipulated to be conservation area, especially when the peat thickness is ≥ 3m,
the area sooner or later should be restored back to conservation. In this case,
social approach should come first, bridging the demand of social welfare and
conservation interest.
1. Water Table
2. Soil Moisture
3. Rain Gauge
4. Air Temperature and Humidity
5. Wind speed and bearing
Data transmissions are directed to BRG server. BRG server has not been
equipped with fully-working Data Center, but it can be configured to be able to
receive data transmissions from devices.
System alert can be implemented into this Dashboard too. The alert is
essential for TRGD and local officers to address forest fire as soon as
possible, which allows them to reach the location and take actions before
forest fire spreads.
There are some important points developed during this Project. We expect
these points may be considered to furtherly studied and developed in order to
support the Peatland Restoration efforts.
We expect that this method can be used to create peatland thickness map
in other areas and furthermore make significant boost to Peatland
Restoration Program.
Peatland are well-known for its soft texture and having less or no shear
strength to support man-made structure like roads, buildings etc. The footing
design for Water Table Monitoring Device might consider adaptation to this
soil characteristic, providing adequate support to the equipment’s weight with
less cost. Another potential problem is if the devices are to be installed in area
invested by monkeys. Monkeys have the ability to climb the mast and may
damage the sensors installed.
The soil condition also reduces the accessibility to canal area. Some peatland
areas are only accessible by boat. This condition should be considered when
designing the timeline for survey.
Locations of remote devices should be set prior to the contract, to allow the
installation of remote devices in timely manner.