Description of work Rate(App) No. Amount, Taka

BORING [5 nos]
Drilling and SPT for 50m BH; SPT @1.5m
interval Including equipment mobilisation 15,000 5 75,000
and demobilisation

Lab test on disturbed soil (3 Nos) 3,500 5 17,500


Lab test on undisturbed soil (1 No) 3,500 5 17,500
Reporting 20,000 1 20,000

ROADSIDE SOIL EXPLORATION [4]


Making pits to 1.5m approx. 2,000 4 8,000
Classification, Compac. &CBR tests 8,500 4 34,000

PAV'T MATERIAL SURVEY


DCP test and m/c tests incl. pit excavation 2,500 10 25,000
LAA test 3,000 1 3,000

GRAND TOTAL: 200,000


t Mirpur Cantt.
Widening and Improvement of Road and Construction of Flyover at Mirpur Cantt.

Estimation for Soil Investigation

Description of work Rate(App) No. Amount, Taka

BORING [30 nos]


Drilling and SPT to 40m BH; SPT @1.5m
interval Including equipment mobilisation and 37,000 10 370,000
demobilisation

Drilling and SPT to 20m BH; SPT @1.5m


interval Including equipment mobilisation and 18,000 20 360,000
demobilisation

Lab test on disturbed soil (3 samples/BH) 3,500 30 105,000


Lab test on undisturbed soil (1 sample/BH) 3,500 30 105,000
Reporting 40,000 1 40,000

ROADSIDE SOIL EXPLORATION [#8]


Making pits to 1.5m approx. 2,000 8 16,000
Classification, Compac. &CBR tests 8,500 8 68,000

EXISTING PAV'T MATERIAL SURVEY


DCP test and m/c tests incl. pit excavation at 2,500 10 25,000
road edge

EXPLORATION OF SOFT SOIL


Drilling and SPT to 8m BH; SPT @1.5m interval
Including equipment mobilisation and 6,400 8 51,200
demobilisation

Lab test on disturbed soil (2 samples/BH) 2,500 8 20,000


Lab test on undisturbed soil (1 sample/BH) 3,500 8 28,000
Reporting

GRAND TOTAL(TAKA): 1,188,200

* All work shall include "reporting"


Widening and Improvement of Road and Construction of
Flyover at Mirpur Cantt.

Estimation for Soil Investigation Work


Description of work Rate(App) No. Amount, Taka

BORING [30 nos]


Drilling and SPT to 40m BH; SPT @1.5m
interval Including equipment mobilisation 60,000 10 600,000
and demobilisation

Drilling and SPT to 20m BH; SPT @1.5m


interval Including equipment mobilisation 30,000 20 600,000
and demobilisation

Lab test on disturbed soil (3 samples/BH) 3,500 30 105,000


Lab test on undisturbed soil (1 sample/BH) 4,000 30 120,000
Reporting 80,000 1 80,000

Subtotal: 1,505,000

ROADSIDE SOIL EXPLORATION [#8]


Making pits to 1.5m approx. , carrying 6,000 8 48,000
samples etc., Classification, Comp. & CBR 16,000 8 128,000

Subtotal: 176,000

EXISTING PAVEMENT MATERIAL SURVEY


DCP test and m/c tests incl. pit excavation
6,500 10 65,000
at road edge
Subtotal: 65,000

EXPLORATION OF SOFT SOIL


Drilling and SPT to 8m BH; SPT @1.5m
interval Including equipment mobilisation 10,000 8 80,000
and demobilisation

Lab test on disturbed soil (2 samples/BH) 2,500 8 20,000


Lab test on undisturbed soil (1 sample/BH) 6,000 8 48,000
Reporting 40,000 1 40,000
Subtotal: 188,000

GRAND TOTAL(TA): 1,934,000


Note
The rate mentioned above includes costs
of sampling, marking, preservation, tools,
transportation, personels, etc.