Académique Documents
Professionnel Documents
Culture Documents
Craig R. Thompson
Consulting Engineer
Equistar Chemicals LP
A LyondellBasell company
Michael W. Korst
Principal Engineer
Equistar Chemicals LP
A LyondellBasell company
AIChE and EPC shall not be responsible for statements or opinions contained in papers
or printed in its publications.
PHA Methodology and Training Practices
Addressing Auto-Refrigeration
Brittle Fracture Hazards –
25 Years Later
Craig R. Thompson
Consulting Engineer
Equistar Chemicals LP
A LyondellBasell company
Michael W. Korst
Principal Engineer
Equistar Chemicals LP
A LyondellBasell company
ABSTRACT
Nearly 25 years ago, the Morris, IL Equistar Chemical ethylene plant experienced
a brittle fracture failure of a heat exchanger. Subsequent to that incident, the
company undertook a program to identify auto-refrigeration brittle fracture
(ARBF) failure risks throughout the company’s processes and to mitigate those
hazards. The company’s effort to prevent a repeat of this type of incident also
includes a detailed ARBF awareness and response training program, as well as a
“Lessons Learned” training program. This paper will present details of these
efforts, summarize the focused PHA methodology utilized to identify ARBF
scenarios and provide an overview of the continuing efforts to address ARBF
risks.
NOMENCLATURE
Brittle Fracture (BF): Failure (catastrophic crack growth) of carbon steel or low
alloy steel equipment which contains a flaw greater than a required critical flaw
size when exposed to low temperatures and a stress above a minimum value.
Brittle Fracture is a primary concern because failures progress in a break-before-
leak fashion rather than the preferred leak-before-break fashion when in a
ductile condition.
In September, 1989, the Morris Ethylene Plant was being restarted after
an extended shutdown. The unit was more than 24 hours into startup, a process
that normally takes 24 to 48 hours. The three main process compressors, the
ethylene and propylene refrigeration, and the charge gas compressor were on
line and stable. The unit operations personnel had initiated process gas forward
flow from the charge gas compressor shortly after the beginning of the night
shift on September 11th. Process forward flow had been established into the
deethanizer. As the deethanizer became inventoried, the C3 and heavier tower
bottoms stream started flowing to the depropanizer. The tower overhead C2
stream flow was initiated through the acetylene conversion preheat and drying
system, while bypassing the acetylene converters. This stream was being flared
at the outlet of the Acetylene Converter Effluent Knock-Out Drum. See the figure
1 below for a simplified process flow diagram.
Isolation
ByPass OPEN
Figure 1 – Morris Olefins Unit Acetylene Converter Train
Deethanizer and Acetylene Converter Event Conditions:
The deethanizer reflux drum overhead control valve was controlling feed
to the acetylene conversion system. Pressure on the acetylene conversion
preheat system was being controlled by the control valve to the flare. The
automatic block valve that allows flow to the ethylene fractionator was in the
closed position. At approximately 0100 hours on September 12th, shortly after
starting forward flow to the acetylene converter system, a significant process gas
leak developed on the inlet flange of EA-409, a cooling water exchanger in the
system. Emergency response was activated and fire water spray was initiated on
the area of the exchanger flange leak. To stop the leak, as an emergency
response action, the deethanizer overhead pressure control valve on the vapor
outlet of the reflux drum was closed and the acetylene conversion preheat and
dryer system pressure was dropped to flare pressure. Subsequent investigation
determined that the deethanizer overhead pressure control valve was not a tight
shutoff valve and flow of material continued through the system.
The exchanger which developed the leak was equipped with a bypass and
block valves to isolate the exchanger. After the leaking exchanger had been
successfully bypassed for repair, Operations attempted to open the control valve
on the outlet of the reflux drum to reinitiate flow to the acetylene conversion
system. The valve failed to respond as the board operator called for opening
from the valve’s computer controller. Operations personnel were sent to the
valve in the field to investigate why it wasn’t opening. Actions by Operations
personnel did successfully open the valve after lowering the pressure of the
deethanizer tower. The valve did begin to respond and opened rather quickly. As
the valve opened, the acetylene converter process equipment pressurized from
near flare header pressure to a pressure of 270 psig. As the acetylene converter
system pressure increased, the first exchanger in the system downstream of the
deethanizer overhead (EA-405) failed in a brittle and explosive manner. The
ensuing process gas release ignited instantaneously with the heat exchanger
failure. See Figure 2 for EA-405 post fracture incident condition. The subsequent
conflagration resulted in two fatalities and seven serious burns to individuals who
were in the area. Additionally, the accident caused major damage to the olefins
unit and extensive business interruption. The Olefins unit was not restarted until
May, 1990.
Fail Level 2 - Max. difference between the MAT and vapor curves or User entered points = 149°F.
Difference for selected curves: Ethylene = 55°F; Ethane = 12°F; User entered points = 149°F
Min. acceptable (coldest) temperature (MAT) when the pressure is at MAWP is 62°F.
Maximum permitted pressure when the temperature is at -155°F is 170 psig
Recommended minimum field hydrotest temperature = 92°F
100 °F
MAT
Ethylene
De-Pressure with Auto-Refrigeration
MAT
50 °F Ethane
User
0 °F
Temperature
-50 °F
-100 °F
Re-Pressure while Vessel Chilled
BRITTLE FRACTURE OCCURED
-150 °F
-200 °F
0 43 85 128 170 213 255 298 340 383 425
Pressure - psig
There are two basic fundamental scenarios which can culminate in brittle
fracture failure of piping and equipment. The first scenario involves auto-
refrigeration in the conventional sense. Uncontrolled depressurization of a
system containing a light hydrocarbon liquid (C1s through C4s typically) results
in process and equipment chilling as liquid temperature follows equilibrium
conditions. Turbulent boiling action of the liquid results in rapid heat transfer and
subsequent chilling of the surrounding metal. With system repressurization, heat
transfer rate is slow (boiling stops), and consequently both liquid and metal
temperatures remain relatively unchanged as system pressure increases. As
represented in the following Minimum Allowable Temperature (MAT) curve,
stresses increase with increasing pressure until a point is reached in which the
metal fails catastrophically. This scenario is classified as a two-step ARBF
scenario since it first requires depressurization with associated chilling of vessel
contents and therefore equipment. Then, secondly, with equipment in a brittle
condition, repressurization provides the stresses necessary to cause equipment
failure.
Brittle Fracture Analysis Report for Two-Step Autorefrigeration Scenarios
Examples: Plant Trip or Loss of Reboil/Vaporization Followed by Repressure
Fail Level 2 - Maximum difference between the MAT and vapor pressure curves or User entered points = 24°F.
Difference for selected curves: User entered points = 24°F
Minimum acceptable (coldest) temperature (MAT) when the pressure is at the full design value (MAWP) is 54°F.
Maximum permitted pressure when the temperature is at -155°F is 54 psig
Recommended minimum field hydrotest temperature = 84°F
100 °F
MAT - Methods A+B
Normal Operating
Propane 95psig @ +62F
50 °F
Operating Conditions
0 °F
Temperature
-50 °F
Upset Condition - Startup Upset condition - Loss of Vaporization
with subsequent pressurization with subsequent repressurization
23psig @ -2F going to 95psig 76psig @ +48F going to 136psig
-100 °F
-150 °F
-200 °F
0 14 27 41 54 68 82 95 109 122 136
Pressure - psig
The second scenario that can result in brittle fracture equipment failure is
not truly an auto-refrigeration phenomenon. While at some sustained elevated
pressure, equipment temperature steadily drops losing ductility until a point is
reached at which the equipment fails catastrophically. Temperature reduction
may be caused by unintentional introduction of a cold liquid, loss of a heat
source (Demethanizer for example), ambient chilling of standby equipment, or
other possible mechanisms. This scenario is classified as a one-step ARBF
scenario since a single change in conditions can result in equipment failure.
Brittle Fracture Analysis Report for One Step Auto-Refrigeration Scenario: Loss of Heat Input
Examples: Loss of Cryogenic Ethylene Vaporizer, Loss of Demethanizer Reboil
Fail Level 2 - Max. difference between the MAT and vapor pressure curves or User entered points = 84°F.
Difference for selected curves: User entered points = 84°F
Min. acceptable (coldest) temperature (MAT) when the pressure is at MAWP is -50°F.
Maximum permitted pressure when the temperature is at -155°F is 143 psig
Recommended minimum field hydrotest temperature = -20°F
0 °F
MAT - Methods A+B
Normal operation 300 psig @ -13 F
-20 °F Ethylene
Operating Conditions
-40 °F
-60 °F
Temperature
-80 °F
-100 °F
-120 °F
-140 °F
-180 °F
0 36 72 107 143 179 215 251 286 322 358
Pressure - psig
The last section of the training, “what not to do when confronted with an
auto-refrigeration event”, was a significant addition and enhancement to the
company’s auto-refrigeration training and knowledge. It established clear and
concise course of action which includes;
STOP! Compose - Evaluate.
Take actions SLOWLY (order of 10’s of minutes).
Take re-warming actions very slowly (order of hours).
STOP source of auto-refrigeration.
Determine the cause of auto-refrigeration.
De-pressure with LPG present.
Leaking valve.
“Dry” Inert Gas in intimate contact with LPG.
LPG material in the wrong place.
Uncontrolled process swing (like loss of reboil on column).
Take action to stop the cause or source of auto-refrigeration.
De-inventory liquid LPG - DO NOT INCREASE PRESSURE.
Close leaking valve or isolate upstream.
Stop source of “Dry” Inert Gas - Purge with warm LPG vapor
if available.
Stop source of LPG - de-inventory liquid LPG - DO NOT
INCREASE PRESSURE.
Reestablish heat input - DO NOT INCREASE PRESSURE.
Although a detailed PHA was completed following the 1989 Morris Plant
incident including focus on auto-refrigeration hazards, with knowledge gained
since that event, a need was recognized for a much more comprehensive and
structured evaluation of ARBF hazards.
Normal Operation
Upset Conditions
Normal Startup
Normal Shutdown
Inventory
De-inventory
Emergency Shutdown
Air Freeing / Nitrogen Freeing
Not in Operation / Stand-by / Maintenance-in-Progress
Commissioning / Leak Testing
PHA Team Membership – As with any PHA, the qualifications and experience of
the PHA team members directly impacts the adequacy of the analysis. The
mechanical lead is an ARBF subject matter expert (SME) knowledgeable with API
579/ASME FFS-1 content and governing fundamentals. A limited number of
mechanical and process engineers trained in ARBF principles and mitigation
methods served as technical SMEs. In addition to providing the needed
expertize, this helped to maintain some level of consistency in the analysis,
mitigation option assessment and documentation. Other core team members
include site process engineers, site mechanical/inspection engineers and site
operations specialists. All members of the PHA team are trained in ARBF
principles. An experienced operational SME fully versed in all modes of plant
operations, all operational systems and operational procedures (written AND
practiced) is important. This individual is capable of, and responsible for,
developing and communicating methods and procedure changes to the Unit shift
organization.
MAT Curve – The equipment’s Minimum Allowable Temperature (MAT) curve
captures all critical equipment parameters defining susceptibility to brittle
fracture over the range of possible operating conditions. The graphical
representation, including process parameters, supports both the analysis process
and mitigation option identification effort. When incorporated into a report or
procedure it also becomes a very effective tool for communicating the hazard
scenarios, findings and a basis for mitigation recommendations.
Mitigation Approaches
Most companies follow a corporate risk assessment standard and
procedure. A number of factors are taken into consideration when developing
and accessing risk mitigation alternatives. The alternative selected depends in
part on whether associated independent protection layers (IPLs) are determined
adequate and valid while insuring operational reliability and performance are not
compromised.
Interlocks and Process Overrides can effectively mitigate many ARBF scenarios
which result from depressurization/repressurization cycles. In these cases,
hazardous conditions are avoided if system pressure is maintained which can be
accomplished via an isolation or “bottle-up” interlock. Interlock initiation may
involve detection of reduced pressure, low temperature, MAT curve approach
margin, forward flow loss, compressor shutdown or a combination of these
measurements. Interlock initiator redundancy, i.e., selecting the two highest or
two lowest transmitter signals from a group of three transmitters (2oo3 voting)
to activate an interlock, is important for both reliable interlock action during
hazardous conditions as well as prevention of false trips. In addition to
redundant instrumentation, dual coil solenoids, and short duration time delays
(0.5 to 2 seconds) are commonly incorporated into the interlock design to
improve reliability. When including time delays, it is particularly important to
analyze scenario dynamics to insure risk mitigation actions are not compromised.
This may necessitate an adjustment in the interlock trip set-point.
Brittle Fracture Analysis Report for Reflux Drum
Example of delayed interlock response: Reboiler condensate isolation interlock
Fail Level 2 - Max. difference between the MAT and vapor pressure curves or User entered points = 8°F.
Difference for selected curves: User entered points = 8°F
Min. acceptable (coldest) temperature (MAT) when the pressure is at MAWP is 4°F.
Maximum permitted pressure when the temperature is at -155°F is 162 psig
Recommended minimum field hydrotest temperature = 52°F
40 °F
MAT - Methods A+B
20 °F
Equilibrium Curve
0 °F MAT - Method C
-20 °F
-40 °F Continuing
pressure
Temperature
-60 °F
Rapid increase
Increase In until reboiler
-80 °F
Pressure to tubes are
-100 °F Interlock covered with
Set-point condensate
-120 °F
-140 °F
Grandfather Curve Per API 579 Method C
-160 °F
-180 °F
0 41 81 122 162 203 243 284 324 365 405
Pressure - psig
150 °F
Shutdown: 9 psig @ +90F Normal Operating
Followed by ambient 165 psig @ +90F
100 °F
cooling
Restart following warm-up
50 °F
0 °F
-50 °F Restart to
1500 RPM Use start-up permissive to prevent
compressor start-up above slow roll until
-100 °F discharge drum temperature is >= +50F
Pressure - psig
Brittle Fracture Analysis Report for Vessel with Manway Nozzle Establishing MAT
Example of Impact of Component Replacement on MAT Curve
Fail Level 2 - Max. difference between the MAT and vapor pressure curves or User entered points = 21°F.
Difference for selected curves: User entered points = 21°F
Min. acceptable (coldest) temperature (MAT) when the pressure is at MAWP is 51°F.
Maximum permitted pressure when the temperature is at -155°F is 155 psig
Recommended minimum field hydrotest temperature = 81°F
100 °F
MAT - Methods A+B
Calculated
Equilibrium Curve MAT Curve
50 °F MAT - Method C
MAT After PWHT
0 °F
Temperature
-50 °F
Impact of Manway
Nozzle Replacement
-100 °F
Grandfathered
MAT Curve -
-150 °F
Method C
-200 °F
0 39 78 116 155 194 233 272 310 349 388
Pressure - psig
Brittle Fracture Analysis Report for Vessel with Properly Selected Materials of Construction
Carbon Steel Charpy Tested at -50F
MAT is acceptable for the vapor pressure curves and the User operating pressure/temperature combinations entered.
Min. acceptable (coldest) temperature (MAT) when the pressure is at MAWP is -50°F.
Maximum permitted pressure when the temperature is at -155°F is 130 psig
Recommended minimum field hydrotest temperature = -20°F
150 °F
MAT - Methods A+B
Propylene Normal Operating
100 °F
Operating Temperature 250psig @ +100F
50 °F
Upset Condition- Depressurization to 10 psig
followed by rapid repressurization
Temperature
0 °F
-50 °F
-100 °F
Properly selected materials of
construction for propylene service
-150 °F
-200 °F
0 33 65 98 130 163 195 228 260 293 325
Pressure - psig
Dryer Applications
Equipment containing molecular sieve or other porous media pose unique
problems. Following equipment deliquification, up to 25% of the bed volume
contains “sponge” liquid trapped within the sieve by capillary action. Unassisted,
it takes a very long period of time for this trapped liquid to dissipate. Initiation of
inert gas flow through the bed results in very low bed and equipment
temperatures since the liquid component’s partial pressure near the surface of
the liquid is extremely low. Temperatures approaching the liquid’s equilibrium
temperature near vacuum conditions are possible and have been demonstrated.
Note that the definition of an ‘inert gas” is relative and is not limited to nitrogen
or methane. For example, in propylene dryers, nitrogen, methane, ethane and
ethylene purge gases behave as inert gases.
200 °F
Normal Operating
150 °F 220psig @ +100F
Depressurization:
Sponge Liquid Chilling Purge with unheated
100 °F
methane vapor (dry
gas) at 50 psig
50 °F
Temperature
0 °F
Repressure without Regen
-50 °F 190psig @ -90F
Pressure - psig
Ideally, clearing the vessel and sieve of free liquid and “sponge” liquid is
accomplished via purge with a hot regeneration gas of similar composition to the
application fluid. In the case of the propylene dryer, either hot propylene or
propane vapor is the best choice. However, this is not always feasible
necessitating development of alternative approaches. Removing all free liquid is
a critical first step. Dependent on fluid, environment and application, the liquid’s
own vapor pressure may be used to push liquid out. Application of vessel heating
in a controlled manner, i.e., heat tracing/jacketing, is a possible approach to
expedite liquid removal, however, there are specific precautions that must be
taken with this approach. A qualified engineer must review the specific
method/design for applying heat to the vessel to verify acceptability and, in
particular, to verify that the temperature differentials created don’t create
unacceptable stresses. Additionally, an acceptable pressure control methodology
(not dependent on manual adjustments or relief valve actuation) must be
implemented. If free liquid is pushed out with an inert gas, the flow rate of the
gas must be controlled and blow-through prevented. A means of DCS
temperature monitoring and alarming should be provided.
Once free liquid is removed, the alternative methods described above will
be ineffective in removing “sponge” liquid. Use of an inert gas to remove
“sponge” liquid requires sufficient heat and volume to prevent low temperature
excursions of unacceptable magnitude. Prior to initiating inert gas flow through
the dryer, the gas stream must be heated requiring the stream to be diverted
upstream of the vessel until targeted temperature is reached. The hot purge
stream through the vessel must then be introduced at a rate and temperature
adequate to offset the chilling which occurs as trapped liquid vaporizes. Providing
DCS monitored temperature instrumentation with alarming enables verification of
acceptable purge conditions. The sieve or catalyst supplier should be consulted
when developing these procedures. If temperature drops below acceptable limits
or differentials, at minimum, vessel leak checks should be performed prior to
reapplying pressure to the equipment.
Distillation Towers
Both one step and two step ARBF scenarios can be associated with
distillation tower applications. The one step scenario can be particularly
challenging to adequately mitigate without major equipment modification and/or
replacement. One step scenarios specifically associated with ethylene plant
demethanizers have been the subject of prior publications (reference 1 and 7).
Considering the significant temperature differential present in demethanizer
towers, the presence of this hazard is not particularly surprising. However, this
hazard can also be present in towers operating with much smaller differential
temperatures such as ethylene fractionators. In the case of a typical high
pressure splitter, the upper tower, lower tower, reboiler tube-side components
and reboiler shell-side components may all have different minimum design
temperatures. The upper tower section will be typically be constructed from
normalized carbon steel specified and certified (Charpy tested) for a MDMT of
-50°F. The lower tower section and reboilers may have been specified with
MDMTs of -20°F and consequently, particularly in the case of pre-1990 plants,
actual MDMT may be much higher. The authors are aware of actual MDMTs as
high as +47°F associated with this equipment
Although grandfathering equipment per procedures defined within API
579/ASME FFS-1 may produce a grandfathered minimum allowable temperature
(GMAT) curve deemed acceptable for continued operation, inevitably by the
nature of the grandfathering process, the delta between the operating
temperature curve and the GMAT curve is relatively small. This necessitates
reliance on energy source (feed and reboiler heat media as well as reflux)
isolation interlocks to adequately mitigate ARBF hazards. Avoiding interlock trips
can create start-up challenges and will likely necessitate start-up procedure
modifications. Interlock activation during significant process upsets can be
expected. Energy source isolation of reboilers using a condensing heat media
such as steam or propylene vapor may have a delayed response that must be
taken into consideration. If the reboiler’s condensate outlet control valve (or
separate trip valve) is used for this purpose, process vaporization does not cease
until the reboiler’s tube area is fully covered with condensate. This may
represent an energy source isolation delay of several minutes.
50 °F
Normal Operation
MAT - Method A+B 285psig @ +20F
Loss of Reboil,
Ethylene Tray Inventory Dumps
Ethane Sump liquid at -10F
0 °F
Process Conditions
MAT - Method C
-50 °F
Temperature
Reestablish column
feed with -10F
-100 °F
reboiler
Grandfathered MAT curve
high MAT due to use of
coarse grain carbon steel
materials of construction
-150 °F
-200 °F
0 32 63 95 126 158 189 221 252 284 315
Pressure - psig
Overpressure Conditions
Attributable to the significant safety margins included in vessel design
standards, catastrophic vessel failure is not expected even with overpressure
magnitudes up to 300% or more of MAWP if vessel integrity has not been
compromised (reference 11). However, this is not true if brittle fracture failure
risks are present. API 579/ASME FFS-1 defines the procedure for extending a
vessel’s MAT curve beyond its MAWP. The vessel’s MAT continues to increase as
pressure increases above MAWP. Compression systems in particular are at risk of
overpressure well in excess of MAWP in the event of a check valve failure. Risk
of overpressure in excess of 300% of MAWP has been identified with some
compression systems (reference 12). However, it doesn’t necessarily require a
significant overpressure magnitude to create a brittle fracture failure risk. First
stage suction equipment within an Ethylene Plant’s ethylene refrigeration system
is a case in point. Often, this equipment has been constructed from 3-1/2%
nickel alloy steel (SA 203). Although this material has a MAT of -150°F at MAWP,
the MAT increases to -144°F at 110% of MAWP and -138°F at 120% of MAWP.
With this equipment normally running below -150°F (ethylene saturation
temperature at 3 psig), following compressor trip the equipment rapidly
pressures up while liquid and metal temperatures remain at pre-trip operating
temperature. If required relief loading exceeds relief system capacity either due
to design inadequacies or check valve failure, vessel conditions can be driven
well across the MAT curve as illustrated below.
Brittle Fracture Analysis Report for Ethylene Refrigerant 1st Stage Suction Drum - 3 1/2% Nickel Alloy
Compressor Suction or Discharge AND Suction Check Valve Failure Scenario
Vessel is acceptable per Paragraph 3.4.3.3.a, since all components have a thickness equal to or less than 0.5 inches.
Minimum acceptable (coldest) temperature (MAT) when the pressure is at the full design value (MAWP) is -150°F.
Maximum permitted pressure when the temperature is at -155°F is 95 psig
Recommended minimum field hydrotest temperature = -120°F
0 °F
MAT - Methods A+B
-20 °F
Ethylene 100 Psig MAWP
-40 °F Vessel Metal Temperature
-60 °F
Normal Operation
Temperature
-100 °F
Normal Settle-Out Suction or Suction/Discharge
70 psig @ -153F Check Valve Failure
-120 °F
-140 °F
-160 °F
-180 °F
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
Pressure - psig
Surplus Equipment
Awareness of all aspects of the API 579/ASME FFS-1 Fitness-For-Service
standard is certainly warranted when evaluating internal or external surplus
equipment for alternate applications. API 579/ASME FFS-1 Part 3 addressing
assessment of brittle fracture of existing equipment is no exception. Older
equipment predating development of industry knowledge captured in API
579/ASME FFS-1 may have a U1 form certifying a minimum design temperature
of -20°F, however, in reality the MAT based on API 579/ASME FFS-1 assessment
methods may be much higher, possibly well in excess of +50°F. A simple
material of construction review can quickly identify equipment unsuitable for low
temperature (process or ambient) service. Coarse grain carbon steel as well as
steel which has not been heat treated/normalized will have elevated MATs with
magnitude a function of the specific material type/grade and thickness. When
considering surplus equipment for C2, C3 or C4 liquid service, or even operation
in cold ambient conditions, equipment with material lists including SA-105, SA-
181, SA-212, SA-283, SA-285 or SA-515 should be of particular concern.
Although hydro-testing equipment per procedures defined within API 579/ASME
FFS-1 can reduce MAT (Method 2C); there is the potential for equipment failure
during the hydro-test. Additionally, the MAT improvement may be insufficient to
provide an adequate margin between operating temperatures and MAT,
particularly when taking into consideration shutdown, start-up, and process
upset conditions.
CONTINUOUS IMPROVEMENT
CONCLUSIONS
2. McLaughlin, J.E., Sims, J. R., Findley, M. and Jones, J.P., Assessment of Older
Cold Service Pressure Vessels For Risk of Brittle Fracture, 1995 AIChE Spring
National Meeting, 7th Ethylene Producers Conference, Houston, TX, March
19-23.
6. Scego, J.P., Cooke, D.L., DeBose, M.E., Guinn, J.D., Polito, C.T., Ethylene
Fractionator Auto-Refrigeration Incident, 2007 AIChE Spring National
Meeting, 19th Ethylene Producers Conference, Houston, TX April 22-27.
9. Mullenix, D., Brittle Failure of a Carbon Steel Flare Line, 2000 AIChE Spring
National Meeting, 12th Ethylene Producers Conference, Atlanta, GA April 5-9.
10. Kuo, A., Pitt, R., Flare Line Failure Case, What Have We Learned?, 2004
AIChE Spring National Meeting, 16th Ethylene Producers Conference, New
Orleans, LA April 25-29.
lyondellbasell.com
lyondellbasell.com 4
lyondellbasell.com 5
lyondellbasell.com 6
Morris Plant Post-Event Results
• Complete Unit PHA Conducted
• Emphasis on Low Temp Metallurgy
• Failed Carbon Steel Exchanger Replaced
with Stainless Steel
• Process Modified for Flaring Capabilities
• Downstream Process Low Temp
Shutdown Added
• 11 Vessels Sampled & Charpy “V” Notch
Impact Tested
• 14 Vessels Replaced Including
Deethanizer Distillation Column.
lyondellbasell.com
Engineering Guideline – Objectives/Content
• ARBF scenario specific PHA guidelines
• Equipment assessment methodology.
• Administrative and engineering
control guidelines.
• Incident recovery guidelines.
• Post-incident equipment inspection
guidelines.
• Auto-refrigeration training package.
• Generate best practice and
engineering documents to prevent
auto-refrigeration.
lyondellbasell.com 8
Engineering Guideline - Comprehensive Training Package
Comprehensive Auto-Refrigeration training package included:
• Review of historic company and industry auto-refrigeration
events and near misses
• Auto-refrigeration basics
• Brittle fracture and susceptible metallurgies
• Process mechanisms that cause auto-refrigeration
– Lowering pressure with liquid LPG present
– Introduce dry inert gas in intimate contact with LPG
– Disturbing liquid/vapor interface (bubble through or stir)
– Increasing surface area
• Methods to avoid auto-refrigeration
• Proper response to auto-refrigeration events
• What not to do when confronted
with an event
lyondellbasell.com 9
Engineering Guideline - Auto-Refrigeration Incident Response
lyondellbasell.com
Auto-Refrigeration Brittle Fracture Focused PHA
OBJECTIVES
lyondellbasell.com 12
Auto-Refrigeration Brittle Fracture Focused PHA
MODES OF OPERATION
• Normal Operation
• Upset Conditions
• Normal Startup
• Normal Shutdown
• Inventory
• De-inventory
• Emergency Shutdown
• Air Freeing / Nitrogen Freeing
• Not in Operation / Stand-by /
Maintenance-in-Progress
• Commissioning / Leak Testing
lyondellbasell.com 13
Auto-Refrigeration Brittle Fracture Focused PHA
FOCUSED PHA SUCCESS FACTORS
Management Support (Site & Corporate)
Resource Commitment Awareness
Cost and Budget
Schedule
lyondellbasell.com 14
Auto-Refrigeration Brittle Fracture Focused PHA
FOCUSED PHA SUCCESS
FACTORS
MAT Curves
Historian Review
“Black box” review
Scenario analysis
Process Simulation
Mitigation Scope Development &
Documentation
PHA Guide-list
LOPA analysis
Interim & long term mitigation defined
Stage 1 mitigation scope developed
lyondellbasell.com 15
Auto-Refrigeration Mitigation - Continuous Improvement
Focused Auto-Refrigeration Brittle Fracture PHAs
Morris Identified additional areas of potential auto-refrigeration risk
New Employee Training
Turnaround Training and Startup Monitoring
lyondellbasell.com 16
Real Time MAT Approach Monitoring
lyondellbasell.com
Auto-Refrigeration Mitigation - Continuous Improvement
Focused Auto-Refrigeration Brittle Fracture PHAs
Morris Identified additional areas of potential auto-refrigeration risk
New Employee Training
Turnaround Training and Startup Monitoring
Lessons Learned Library
lyondellbasell.com 18
LyondellBasell Lessons Learned Library
lyondellbasell.com
19
Auto-Refrigeration Mitigation - Continuous Improvement
Focused Auto-Refrigeration Brittle Fracture PHAs
Morris Identified additional areas of potential auto-refrigeration risk
New Employee Training
Turnaround Training and Startup Monitoring
Lessons Learned Library
Process Safety Monthly Topic
lyondellbasell.com 20
LyondellBasell Process Safety Monthly Topics
lyondellbasell.com
21
Auto-Refrigeration Mitigation - Continuous Improvement
Focused Auto-Refrigeration Brittle Fracture PHAs
Morris Identified additional areas of potential auto-refrigeration risk
New Employee Training
Turnaround Training and Startup Monitoring
Lessons Learned Library
Process Safety Monthly Topic
Morris Ethylene Plant Abnormal Situation Overview Screen
lyondellbasell.com 22
Abnormal Situation Overview with MAT Curves
lyondellbasell.com
23
Auto-Refrigeration Mitigation - Continuous Improvement
Focused Auto-Refrigeration Brittle Fracture PHAs
Morris Identified additional areas of potential auto-refrigeration risk
New Employee Training
Turnaround Training and Startup Monitoring
Lessons Learned Library
Process Safety Monthly Topic
Morris Ethylene Plant Abnormal Situation Overview Screen
Auto-Refrigeration and Near-miss Responses & Reporting
lyondellbasell.com 24
AR Near Miss Incidents – Mitigation & Reporting
Ethane Feed Drum Auto-Refrigeration During Unit Shutdown
Liquid Propylene Purification Column Auto-Refrigeration
during Regeneration
Propylene Dryer Auto-Refrigeration Incident
Propane Feed Drum during Post-Turnaround Startup
– Propane Feed Drum nitrogen purging to flare
– Liquid ethane from C2 Splitter column backed into Propane Feed Drum
– Operators observed frost on the exterior of the Propane Feed Drum
– Operations ensured that the drum pressure was not above 40% of the
MAWP, and was not allowed to increase
– Gradual recovery process and full post-incident internal inspection
– Flare liquid drain lines have been segregated
lyondellbasell.com 25
Refer to Paper For:
Mitigation Alternatives
lyondellbasell.com 26
Conclusions
Industry knowledge has made substantial leaps
API 579 / ASME FFS-1 Key Technical Reference
However ARBF fundamental knowledge is only useful if
used in conjunction with:
A comprehensive program to identify, understand, prevent and
mitigate ARBF scenarios
A thorough training program including refresher training for both
Technical & Operational personnel
Management commitment
lyondellbasell.com 27
Disclaimer:
All information (“Information”) contained herein is provided without compensation and is intended to be
general in nature. You should not rely on it in making any decision. LyondellBasell accepts no responsibility for
results obtained by the application of this information, and disclaims liability for all damages, including without
limitation, direct, indirect, incidental, consequential, special, exemplary or punitive damages, alleged to have
been caused by or in connection with the use of this information. LyondellBasell disclaims all warranties,
including, but not limited to, the implied warranties of merchantability and fitness for a particular purpose,
that might arise in connection with this
information.
lyondellbasell.com 28
Back-up Slides
lyondellbasell.com 29
ARBF Basics – Two-Step Auto-Refrigeration
lyondellbasell.com 30
ARBF Basics – One Step “Auto-Refrigeration”
lyondellbasell.com 31
ARBF Mitigation - Interlocks
lyondellbasell.com 34
ARBF Mitigation – Equipment Modification
lyondellbasell.com 37
Unique or Challenging ARBF Scenarios –
Dryer Applications
Dry gas purge impact: Crack > Leak Risks and Brittle Fracture Risks
lyondellbasell.com 38
Unique or Challenging ARBF Scenarios –
Distillation Columns
lyondellbasell.com 39
Unique or Challenging ARBF Scenarios –
Compressor Overpressure – Check Valve Failure Scenario
Ethylene refrigerant 1st stage suction drum – limited overpressure crosses MAT
lyondellbasell.com 40
Unique or Challenging ARBF Scenarios –
Internal and External Surplus Equipment
lyondellbasell.com 41