Académique Documents
Professionnel Documents
Culture Documents
2 10.00 Km Fixing TBM & PBM and Marking centre line 6,000 One Kilo
for New Alignment Metre
4 20.00 Trial Pits Soil Sample collection from Trial Pit 5,400 One Trial
1mx1mx1m and conducting FDD,Moisture Pit
Content, atterberg limits, CBR test and other
regular tests for
road work as per MORTH Specification
10 3.00 Sets Drawing works and plotting, printing and 7,500 Set
Binding for L.S.C.S Detailed drawings for
Road Works and CD Works
Total Amount
90,000
60,000
90,000
1,08,000
Amount
36,000
25,000
60,000
25,000
25,000
22,500
12,000
5,53,500
77,490
6,30,990
Amount
GS Associates
GEO-TECH ENGINEERING DIVISION
To
Mr. HANUMANT DHAWARE,
Patil Construction & Infrastructe Ltd.,
2 & 3rd Floor, PMPML Commercial building No.1,
Opp. Income tax building, Shankarsheth Road, Swarget, Pune - 411042
Cont.No. 020 24479626, 24479978 / 79 / 80
COST FOR THE WORK OF FOLLOWING ITEMS COVERED IN EPC MODE PROJECT IN MAHARASTRA
Rates in
Sl.N Probable Description of work Unit in Amount
o Quantity words
Figures
Rupees Ninety Five Lakhs Eighty Six Thousand and Four Hundred Only
Time Schedule :
1. Commencement of Work within 15 days from the date of Receipt of Work order.
2. Completion of field work within 45 days from the date of Receipt of Work order.
3. Submission of report within 20 days from the date of completion of field works.
For GS Associates
Sd/--------------------------
P.Rajendran
(91) - 9840073732
Project Co ordinator