Académique Documents
Professionnel Documents
Culture Documents
Version 1.0
1
Change Management Process
Table of Contents
1 About This Document ......................................................................................................................... 3
1.1 Document Objective .................................................................................................................. 3
1.2 Process Objectives.................................................................................................................... 3
2 Change Request Lifecycle Stages ..................................................................................................... 4
3 Change Request (CR) Requirements ................................................................................................ 4
4 Approval Requirements ...................................................................................................................... 5
5 Change Board (CB) Requirements .................................................................................................... 5
6 Work Info Entry Definitions ................................................................................................................. 5
6.1 Risk Assessment: ...................................................................................................................... 5
6.2 Service Impact Assessment: ..................................................................................................... 6
6.3 Install Plan: ................................................................................................................................ 6
6.4 Backout Plan: ............................................................................................................................ 7
6.5 Test Plan: .................................................................................................................................. 7
6.6 Communication Plan: ................................................................................................................ 7
6.7 Approvals: ................................................................................................................................. 8
6.8 Install Results – Details ............................................................................................................. 8
6.9 Test Results – Details ............................................................................................................... 8
6.10 Post Implementation Review (PIR) ........................................................................................... 9
7 Inquiries ............................................................................................................................................ 10
8 Definitions and Acronyms ................................................................................................................ 10
9 Reference ......................................................................................................................................... 13
Revision History
Author Version Description Date
Ken Merkel 1.0 Document Creation August 13, 2015
Sandy Stout
Gemma Tungul
Ken Merkel 1.0 Document August 31, 2015
Sandy Stout Publication
Gemma Tungul
Caroline Schulte
Sandy Stout 1.1 Document review Feb. 4, 2016
and update of links.
2
Change Management Process
This document applies to the changes that are managed under the Government of Alberta (GoA)
Change Management control.
3
Change Management Process
Initiate – A Request for Change (RFC) is initiated and populated by Change Coordinator/Change
Implementer. Initial classification and impact/risk assessments are performed and the ticket is
populated with the required information.
Review & Authorize – The Change Manager reviews the change for completeness, confirms the
impact of the change and identifies the appropriate approvers for the change.
Plan & Schedule – The Change Manager approves and submits the change to the appropriate
approvers ((optional) Change Board, Service Owner. If communication is required, the Change
Manager requests the communication to be distributed. The change is then scheduled for
implementation.
Implement – The Change Implementers perform and record the required tasks and activities to
implement the Change.
Closed – The Change Manager will perform a Post-Implementation Review to determine if the
Change met its objectives. The change is then closed.
1. Risk Assessment
2. Service Impact Assessment
3. Install Plan
4. Backout Plan
5. Test Plan
6. Communication Plan
4
Change Management Process
4 Approval Requirements
Approvals are required within the CR Lifecycle.
Change Board Review is required on all changes that falls under the following guidelines:
Examples:
Risk is assessed as low. This is a repeatable process done many times before
and has been tested in UAT.
Risk is assessed as low. Switch and router reloads are usually uneventful with
the device coming back online within 5 minutes. There is always a chance
(though very remote) that a device will fail it’s reload and not come back online.
In such a case a new switch or router would be provisioned during the block time.
The risk of this change is low as the changes of similar type has been completed
on other parts of the network and implemented as planned. The risk of not doing
the change is that the current infrastructure is aged and does not meet security
requirements. This could lead to vulnerabilities that may be exploited to
compromise our network.
5
Change Management Process
1. How does this impact users of the service during the change?
a. Is there an outage?
b. How long is the outage?
(Change Board review is required for all outages longer than 10 minutes).
c. What time is the outage?
2. Will this impact the users after the change,
a. Will there be a visible change to end users?
(Change Board review is required for all changes visible to the end users).
b. Will they have to do something different?
3. What Ministries are affected by this change (change board requirement only).
(Change Board review is required if more than one ministry is affected).
Examples:
No service impact & no outage are expected during the change window. This
change will be implemented seamlessly as there are 2 devices are serving
user traffic simultaneously and there is no need for reboot.
During this change, email and file services will be unavailable. Outage should
only be 15 minutes at the start of the change although I have scheduled the
entire hour in case more time is required. Ministries affected are: Service
Alberta, Energy.
The switch will be replaced during the lunch with Ministry approval to be
attached to this ticket. While connections are moved from the old to the new
switch, workstations and printers will not have network access throughout the
entire building. This change will affect the Ministry of Service Alberta.
Examples:
1-Rack new router; 2-power up the router: 3-Move cables from the old to the
new router; 4-check network connectivity
Alter Channel CLIENT.TO.QNA3 parameter HBINT from 50 to 300 using ISPF
interface. Change QNA3.PARMLIB(QNA3SGCO) member HBINT parameter
from 50 to 300 for channel CLIENT.TO.QNA3 definition
6
Change Management Process
Example:
Old router can be reconnected within 1 hour. 1-Rack old router back; 2-power
up the old router: 3-Move cables from the new to the old router; 4-check network
connectivity
1. What is the pre-testing plan? (if no pre-testing can be done explain why)
2. If applicable, detailed information on what pre-testing was done and the outcome
3. What is the post-testing plan?
Example:
After the migration, logon to the SPIN2 prod database servers and verify they are
working fine.
1. Communication Email
2. Communication Distribution Checklist
3. Communication Approval (email)
7
Change Management Process
6.7 Approvals:
The following approvals are required within the lifecycle of a change.
Examples:
Change was Successful; Change was implemented within the allowed time
without any incidents. Communication task were successfully completed. Testing
Plan was successfully complete.
Change had to be backed out by restoring previous settings. This change was
not successfully implemented. Will be recreated and scheduled at another time.
Examples:
Both the NetOps and ADS team have tested the console access and it is working
as required.
Confirmed sync script finished running successfully. When ncc esm201 was
back up, confirmed events flowing to 201 again.
8
Change Management Process
Examples:
Post-Implementation Review Results - This Change implementation has been deemed
successful.
9
Change Management Process
7 Inquiries
Refer your inquiries to ict.change@gov.ab.ca.
Change Board All Changes are classified into one of the following two classes:
Classification
Operational changes are those changes which may impact the availability
and/or quality of IT services while the changes are being performed, but which
will not result in any visible change to customers and/or their end users once
the changes are completed. Operational changes include regular maintenance
and upgrades, expansion of the IT environment, etc.
Normal is the default timing for a change. Approval from the Change Manager
and the Service Owner is required.
Emergency - This type of change would be created during business hours and
would follow the normal change management process by requiring all the work
info entries to be added in the ticket, but, communication and Change Board
requirements do not apply. Change Management approval and Service Owner
approval is required prior to implementation.
10
Change Management Process
Term Definition
Owner or an alternate change approver must be attached to the ticket.
Required work info entries must include an entry identifying what was done and
why, and an “Install Results” entry prior to the ticket being moved forward for
final review.
Minor/Localized: The Change will have little or no effect to end users during
working hours, but may require the service to be unavailable for less than 10
minutes during non-working hours.
The following are the implementation Change Board lead times required by
Service Alberta Change Management:
Minimum Lead Description
Time
7 business days - Must be submitted no later than Monday,
4:30pm in order for the change to appear on
the Wednesday Change Board Agenda.
- In case of holidays (ie. Holiday Monday)
11
Change Management Process
Term Definition
preference would be to have the CR ready by
Friday, 4:30pm BUT CRs will be accepted until
Tuesday at noon.
- Additional 5 days for Communication
Distribution
Priority Priority is an indicator of the relative importance of a change. It is used to
determine the sequence in which a change needs to be resolved, and therefore
the speed at which the resolution will be approved and deployed. It is based
primarily on the Impact and Urgency, although the business risk of not
implementing the change is another important criterion for determining the
priority of a change. Priority can be:
Low: A Change that impacts few users, and can be implemented in the long-
term
Critical: A Change that impacts both a large number of users and must be
implemented quickly
Urgency
Priority
Critical High Medium Low
Extensive Critical Critical High High
Significant Critical High High Medium
Impact
Risk Level 1-2 (Low): (E.g. Routine change with proven success; minimal
impact if Change fails; no back out required or back out is simple)
Risk Level 3-4 (Medium): (E.g. High probability of success; back out is
involved but not difficult; moderate visibility potential to customers)
12
Change Management Process
Term Definition
Risk Level 5 (High): (E.g. Change is complex or high risk; implementation is
difficult; back out is lengthy and/or difficult; high visibility potential to customers.)
9 Reference
Change Management Documentation is located here.
13