Académique Documents
Professionnel Documents
Culture Documents
IG01/1
GUIDELINES
1. Introduction
To secure safe cables installation and assure their reliability, it has to be
confirmed that the selected cable is suitable for the application and no damage
occurred in transit or storage.
Proper cable inspection, handling and storage have to be carried out in order
to detect existing cable damage and prevent any further damage from occurring.
2. Cable inspection
Every cable reel has to be inspected for damage before accepting a
shipment. The following signs should draw the attention for possible cable damage:
A reel has been dropped: hidden damage likely!
The bobbin lagging is broken: the cable underneath may be harmed.
A reel flange is damaged.
A reel is lying flat on its side.
Extraneous load is stacked on a reel.
Several reels are stacked.
Nails have been driven into the reel flanges to fasten shipping blocks.
A cable covering is removed stained or damaged.
A cable end seal has been removed or damaged.
3. Reel unloading
DO NOT DROP!
Reels have to be carefully unloaded from a truck using a fork lift truck, a hoist or a
crane. NEVER DROP REELS. Unloading equipment should not come in contact
with the cable or it’s protective covering. Care should be taken not to loose nor
damage the reel identification labels.
DO NOT!
DO
DO DO NOT!
Page 2 of 4
U:\Installation instruction\IG01_1 Synergy 09_05_07.doc
POWER CABLES INSTALLATION
IG01/1
GUIDELINES
6. Storing
6.1. Cable wound on wooden or metal reels may be stored outdoors.
6.2. For long term storage, keep the cable reels in relatively inactive areas.
6.3. Storage temperatures should be between –20 oC (-4 oF) and 50 oC
(120 oF). Even though some types of cables may be stored beyond the
given temperatures, special precautions should be taken immediately
before the cable installation.
6.4. Keep the cable dry, at a temperature that will not generate degradation
and protect the cable from damage. Do not store in sites where
standing water is likely.
6.5. Reels should be stored upright on their flanges and handled in such a
way as to prevent deterioration of, or physical damage to the reel or to
the cable. Multiple reels stacked on top of each other (“Pancake”
storage) is not recommended for medium voltage cable. A
concentration of stress on the bottom reel may cause its collapse and
subsequently damage the cable. Additionally, the inner cable end,
which normally protrudes through one of the flanges, will very likely be
damaged. Further damage will probably occur when the reel is flipped
for transit.
DO NOT!
6.6. During storage, the ends of the cables must be sealed against the
entrance of moisture or contamination. Electrical tape does not provide
sufficient seal. Rubber or plastic sealing caps should be used when
lengths are cut to protect the end of the cable. Maintain the cable ends
fixed to the reel flanges without puncturing the jackets of the end caps.
6.7. Reels should also be stored on solid ground to prevent the flanges
from sinking into the earth. Power poles or crossarms, conveniently
distanced, should cradle and raise the flange above the ground.
Page 3 of 4
U:\Installation instruction\IG01_1 Synergy 09_05_07.doc
POWER CABLES INSTALLATION
IG01/1
GUIDELINES
Periodically change also the contact point between the reel flange and
its support. All this should protect the reels from decay and prevent
them from rolling.
6.8. Organize the storage in a way that will ease the application of the “first
in, first out” criteria.
6.9. Maintain a covering on the cable reels so that any damage on it will
draw the attention to a probable damage also on the cable underneath
it.
6.10. In zones of rodent infestation, the cable reels should be protected with
full lagging, steel plates over flange penetrations and / or other suitable
means.
Page 4 of 4
U:\Installation instruction\IG01_1 Synergy 09_05_07.doc
POWER CABLES INSTALLATION
IG02/2
GUIDELINES
1. Introduction
Cable installation comprises a series of operations that when carried out
carefully will result in a reliable cable system. Some of them are common to all the
types of installation: raceways, cable tray, trough, buried duct, direct burial,
tunnels, conduit, etc. Other – are specific of the type of installation. It is assumed
that the cable has been correctly selected for the application.
Proper cable inspection, handling and storage have to be carried out in order
to detect existing cable damage and prevent any further damage from occurring.
The cable routing should be thoroughly inspected to avoid bends and/or
pulling tensions that exceed specified limits.
During cold weather installation, the cable should be pulled more slowly and
trained in place the same day it is removed from storage. Care should be taken not
to impact, drop, kink or bend the cable sharply in low temperatures.
Page 2 of 9
U:\Installation instruction\IG02_2 Synergy 09_05_07.doc
POWER CABLES INSTALLATION
IG02/2
GUIDELINES
5.2. Cable reels should be supported so that the cable may be unreeled
and fed into the raceway without subjecting the cable to a reverse
bend as it is pulled from the reel. To further assure adequate pulling of
the cable, a reel drive mechanism or adequate manpower should be
provided as the cable is being removed from the cable reel.
Freewheeling should be avoided. The drive mechanism (equipped with
braking ability) works best in controlling cable payoff. A fulcrum and
wedge device may sometimes be used to prevent freewheeling.
5.3. A tension measuring device should be used on runs when pulling force
calculations indicate that allowable stresses may be approached.
5.4. Pulling tension will be increased when the cable is pulled off the reel.
Turning the reel and feeding slack cable to the duct entrance will
reduce the pulling tension.
5.5. The direction of pulling has a large influence on the pulling tension in
conduit runs containing bends. Whenever a choice is possible, the
cable should be pulled so that the bend or bends are closest to the
reel. The worst condition possible is to pull out of a bend at or near the
end of the run.
5.6. Sufficient cable slack should be left in each manhole and temporarily
supported so that the cable can be trained to its final location on racks,
hangers or trays along the sides of the manhole. Cable splices should
not be placed directly on racks or hangers.
5.7. For cable equipped with pulling eye or pulling bolt, i.e. pulling trough
the cable conductor, the formula shown below is used to calculate the
maximum allowable pulling tension on the cable for the entire routing:
Tm = K × n × CMA (1)
5.8. In the next table are given the allowed tensions for the normal range of
circular mil areas:
MAXIMUM ALLOWABLE PULLING TENSIONS (LBS)
AREA Copper conductor Aluminum conductor
Number of conductors Number of conductors
kcmil
1 2 3 4 1 2 3 4
2 531 1,062 1,593 1,699 398 796 1,194 1,274
1 670 1,339 2,009 2,142 502 1,004 1,506 1,607
1/0 845 1,690 2,534 2,703 634 1,267 1,901 2,028
2/0 1,065 2,130 3,194 3,407 799 1,597 2,396 2,556
3/0 1,342 2,685 4,027 4,296 1,007 2,014 3,020 3,222
4/0 1,693 3,386 5,078 5,417 1,270 2,539 3,809 4,063
250 2,000 4,000 6,000 6,400 1,500 3,000 4,500 4,800
300 2,400 4,800 7,200 7,680 1,800 3,600 5,400 5,760
350 2,800 5,600 8,400 8,960 2,100 4,200 6,300 6,720
400 3,200 6,400 9,600 10,240 2,400 4,800 7,200 7,680
450 3,600 7,200 10,800 11,520 2,700 5,400 8,100 8,640
500 4,000 8,000 12,000 12,800 3,000 6,000 9,000 9,600
600 4,800 9,600 14,400 15,360 3,600 7,200 10,800 11,520
750 6,000 12,000 18,000 19,200 4,500 9,000 13,500 14,400
1000 8,000 16,000 24,000 25,600 6,000 12,000 18,000 19,200
Ts = L × W × f (2)
Page 4 of 9
U:\Installation instruction\IG02_2 Synergy 09_05_07.doc
POWER CABLES INSTALLATION
IG02/2
GUIDELINES
Tb = Tb × e fa (3)
Page 6 of 9
U:\Installation instruction\IG02_2 Synergy 09_05_07.doc
POWER CABLES INSTALLATION
IG02/2
GUIDELINES
P = Tb ÷ r (4)
10.2. In certain zones, where frost conditions could damage the cable,
greater burial depths should be adopted.
10.3. Where supplemental protection is provided, lesser depth may be used.
Page 7 of 9
U:\Installation instruction\IG02_2 Synergy 09_05_07.doc
POWER CABLES INSTALLATION
IG02/2
GUIDELINES
10.4. If the earth surface is not to final grade, the cable should placed to
meet or exceed the requirements indicated above, at the time of
installation and when the surface is to final grade.
10.5. Trenching. The bottom of the trench should be smooth, well tamped
earth or sand. When excavation is in rock or rocky soil, the cable
should be laid on a protective layer of well-tamped backfill. Within four
inches of the cable, the backfill should be free of materials that may
damage the cable (large rocks, paving materials, large or sharply
angular substances, etc.). The backfill should be well compacted.
Within six inches of the cable no machine compaction should be
employed. A protective covering above the cable will serve as a
warning for excavators of the presence of an underlying cable.
Under pedestrian and vehicular traffic ways it is recommended to pull
the cables through a conduit.
11. Cable Tray installation
11.1. The NEC (ed. 2002) article 392 covers widely the cable tray system
installation.
11.2. Single-conductor cables shall be 1/0 AWG or larger and shall be of a
Listed type and marked on the surface for use in cable trays. Such
cables have a proven reduced fire propagation behavior.
11.3. Spacing of the rollers must be appropriate to prevent the moving cable
from touching or rubbing the tray. The rollers should be placed to keep
the cable in a fairly level position. As the cable approaches the end of
the pull, the tension is higher allowing for more distance between
rollers.
11.4. A high-strength, low-stretch abrasion resistance pulling rope should be
employed. Its strength should exceed the maximum tension to be
encountered during the pull by a factor of five. Double-braided
aramid/polyester ropes are recommended. Manila hempline is also
good.
11.5. The layout of the tray should be carried out in full consideration of the
future pulling operation. Reel location, pulling equipment and cable
tray bends should be facilitated at the cable tray planning stage.
12. Cable pulling stages
12.1. Preparation
12.1.1. Establish the direction of the pull based on safe pulling tensions and
sidewall pressure calculations.
12.1.2. Select the correct size pulling eyes, bolts or grips.
12.1.3. Locate feeder reels, spools, etc. such that the tension at the feeding
end is minimized.
12.1.4. Use pulling equipment that provides smooth speed control.
Page 8 of 9
U:\Installation instruction\IG02_2 Synergy 09_05_07.doc
POWER CABLES INSTALLATION
IG02/2
GUIDELINES
12.1.5. Choose a pulling rope that has the required tensile strength.
12.1.6. Prior to pulling, make sure the conduit is clean and free of dirt, water,
scale, etc.
12.1.7. For long or heavy pulls, pre-lubricate the conduit and pull rope,
particularly when using PVC.
12.1.8. Install a dynamometer.
12.2. Cable pulling
12.2.1. Apply cable lubricant liberally during the installation.
12.2.2. If possible, use two-way communication at both ends of the run,
particularly on long runs.
12.2.3. Accelerate slowly and smoothly to a constant pulling speed.
12.2.4. Avoid letting the cable stop part way through the pull . The friction is
greatly increased when re-starting a pull.
12.3. After pulling:
12.3.1. Seal the ends of the installed cable to prevent moisture from getting
inside the cable.
12.3.2. High voltage testing is recommended after the installation.
Page 9 of 9
U:\Installation instruction\IG02_2 Synergy 09_05_07.doc
POWER CABLES INSTALLATION
IG03/1
GUIDELINES
1. Introduction
Cables undergo thorough testing according to the applicable standards
before leaving the factory. Nevertheless, it is recommended to test the cable during
and after its installation. The purpose of these tests is to discover possible damage
caused by accidental mishandling of the cable during the pulling operations and/or
faulty mounting of the required accessories. As sooner the detection of such faults
is made, the better. Early corrective actions taken will diminish the delays in project
completion and additional expenditures will be avoided. It should be noted,
however, that these tests might not detect damage that may eventually lead to
cable failure in service, e.g., damage to the cable jacket or insulation shield.
After a cable system has been completely installed and placed in service
ICEA cable standards allow to make DC tests within the first five years. But, as
stated in the mentioned standards, “DC test voltages are applied to discover gross
problems such as improperly installed accessories or mechanical damage. DC
testing is not expected to reveal deterioration due to aging in service. There is
some evidence that DC testing of aged cross-linked polyethylene cables can lead
to early cable failures. Information on this subject is available in EPRI project report
TR-101245, “Effect of DC Testing on Extruded Cross-Linked Polyethylene
Insulated Cables”” (ICEA standards S-94-649-2000 and S-97-682-2000).
Consequently, maximum restraint should be exercised in front of the in service
testing of such cables. Maintenance DC hipot testing of such cable systems should
be avoided at all, or, at the most, limited only to those exceptional situations where
it would be imperative. Otherwise, cables good enough to operate fault free for
many years would unnecessarily been broken down.
The tests should be carried out according to the following guidelines.
2. Safety precautions
Only qualified personnel should run the DC high potential voltage tests. The
testing personnel should be familiar with IEEE Standard 400: “Guide for Making
High DC Voltage Tests on Cable Systems in the Field”.
The testing personnel should follow the instructions provided by the test
equipment manufacturer for the safe operation of the test equipment.
Before conducting tests on any cable system, it should be verified that the
cable system is de-energized. If the cable system has been previously energized,
the prescribed rules for conducting the switching required to de-energize, lockout,
tagging and grounding should be followed.
Adequate instructed personnel should guard or barricade the remote cable
end areas to prevent unauthorized access to the cable system under test.
U:\Installation instruction\IG03_1.doc
POWER CABLES INSTALLATION
IG03/1
GUIDELINES
4. Conducting test
4.1. During installation
At any time during installation, a DC proof test may be made at a voltage not
exceeding the DC test voltage specified in the following table under the
During/After Installation column, applied for five consecutive minutes.
DC Field Test Voltages
Rated Maximum DC Field Test
Nominal Insulation
Voltage Conductor Size Voltages [kV]
Thickness
Phase to [AWG or kcmil During/After First 5
[mils (mm)]
Phase (mm2)] Installation Years
[kV] A B A B A B
8-1000 (8.4-507) 90 (2.29) 115 (2.92)
5 28 36 9 11
Above 1000 (507) 140 (3.56) 140 (3.56)
6-1000 (13.3-507) 115 (2.92) 140 (3.56)
8 36 44 11 14
Above 1000 (507) 175 (4.45) 175 (4.45)
2-1000 (33.6-507) 175 (4.45) 220 (5.59)
15 56 64 18 20
Above 1000 (507) 220 (5.59) 220 (5.59)
25 1-2000 (42.4-1013) 260 (6.60) 320 (8.13) 80 96 25 30
28 1-2000 (42.4-1013) 280 (7.11) 345 (8.76) 84 100 26 31
35 1/0-2000 (53.5-1013) 345 (8.76) 420 (10.7) 100 124 31 39
46 4/0-2000 (107.2-1013) 445 (11.3) 580 (14.7) 132 172 41 54
Column A - 100% insulation level. Column B - 133% insulation level.
Page 2 of 4
U:\Installation instruction\IG03_1.doc
POWER CABLES INSTALLATION
IG03/1
GUIDELINES
25
20
15
B [inch]
10
0
0 10 20 30 40 50 60 70 80 90 100 110
kV DC
Page 4 of 4
U:\Installation instruction\IG03_1.doc