A Project Report
Presented to
The Faculty of the Department of
General Engineering
San Jose State University
In Partial Fulfillment
of the Requirements for the Degree
Master of Science in Engineering
By
Farhan Jaleel
Muhammad Jawwad ul Haque Siddiqui
May 2009
© 2009
Farhan Jaleel
Muhammad Jawwad ul Haque Siddiqui
____________________________________________________
Technical Advisor,
____________________________________________________
_____________________________________________________
USING SIMULATION
by
Farhan Jaleel
Simulation is a modeling and analysis technique that is used to evaluate and improve any
dynamic system. The aim of this project was to do the optimization of inventory
Optimization of inventory management is a useful technique that can be used to decrease the
lead time and cost incurred in any manufacturing company, while increasing the customer
service level. The overall impact is a significant increase in the net profit of a company.
Thorough research was carried with the help of various case studies and research papers from
recognized journals. Our results are similar to the findings of an earlier study (Terry Harris,
1997), except that we used simulation modeling to carry out the optimization of inventory
We would like to express our gratitude, respect and appreciation to Professor. Jim
Dorosti, Professor, Department of General Engineering, San Jose State University for
his continuous support, guidance and encouragement in completion of the project.
We would like to thank Mr. Rehan Jalil, Chief Executive Officer and Mr. Lee
Khan, Vice President Manufacturing Operations, WiChorus Inc.for their kind support
and guidance in achieving our goal.
Farhan Jaleel
Page
S No. Description
No.
1. Introduction 1
Inc. by simulation modeling. The simulation modeling is to be carried with the help of
ProModel software. The goal is to reduce the lead-time and inventory carrying cost, which
subsequently increases the net profit (without changing the revenue) and customer service
The purpose of this project is to optimize the inventory management of the company named
stages of development and includes raw material inventory, work-in-process inventory and
finished goods inventory by using simulation-modeling tool. Supply chain of the company
involves material and information flows from raw material suppliers to all the way to the end
customers and back (some times). Optimization is to be carried out in terms of total cost and
lead time, considering all the economical and operational issues, which can contribute to the
success of WiChorus Inc. in future. This project includes optimization of the inventory
management process with the help of Promodel software. This software is a simulation tool.
Major part of the total cost of the product development also depends on the overall activities
of supply chain. These activities include transportation from point of origin to the point of
consumption and the storage of different forms of inventory. Techniques like standardization,
minimizing cost by design and cost of quality are not in scope of our project. The key to the
1
success of company is to keep the total cost of the product development as low as possible.
Due to efficient inventory management, the lead-time and inventory carrying cost can reduce
the cost of the product development. Reduction in lead-time can increase responsiveness and
thus improving customer service level. Reduction in the amount of carried inventories
1.2 Problem
WiChorus holds or carries the inventory in three forms, namely raw materials (like integrated
circuits, memory modules, cables, switches etc.), semi-finished products (Fully assembled
and tested printed circuit boards, Field replaceable modules) and finished
organization, it has to manage the flow of an inventory (specially raw materials and semi-
finished products) throughout its manufacturing processes, till customer receives the finished
product. For the entity that has a weak management of inventory, there will be no economy
of scale for the manufacturing operations and it will subsequently impact the net profit.
WiChorus Inc. has its flow of inventory like any manufacturing organization of specialized
equipment. There are many stages for the inventory that is involved in the manufacturing
operations of WiChorus Inc. The manufacturing operations include ordering of the parts,
transportation of the parts (between PCB manufacturer and WiChorus, PCB assembler and
2
The serial production of equipment at WiChorus has recently started. If the inventory is not
optimally managed, than there would be many problems that could be faced by WiChorus or
any other manufacturing company. Since the cost of products being produced at WiChorus
facility is very high, the impact of mismanaged inventory is tremendous in terms of cost and
customer service (lead time). The problems that can be faced in the case of mismanaged
In case of WiChorus raw material inventory includes memory modules, integrated circuits,
capacitors, chassis, bezels, labels, lite pipes, holders etc. For the purpose of this project, we
have taken into account the raw material that contributes to 80 percent of inventory carrying
includes goods in transit (e.g. on trucks, on railway cars or on airplanes) between levels of
multi-echelon distribution system, or between adjacent workstation in the factory. In the case
of WiChorus, work in process inventory exists in the form of assembled PCBs. Once the
3
PCBs are manufactured they are sent to another third party manufacturers along with other
raw materials for assembling. There is a certain amount of cost, which remains tied up with
these assembled PCBs, until they are installed in the chassis with other parts at WiChorus’s
facility, tested and shipped to customers. So if quantity is high for these semi assembled or
assembled PCBs, it incurs as inventory carrying cost, till the time of its shipment.
Once the manufactured equipment at WiChorus is ready for shipment to customers, it is held
at WiChorus facility and it is called finished goods inventory. There is also a cost associated
for holding finished goods. Usually semi finished products (assembled PCBs) are held at
WiChorus for the ease of responsiveness to unplanned customers orders, along with raw
materials inventory such as chassis, bezels, memory modules, shelf managers, power
management modules etc. This can be taken as safety stock that is always there to respond to
As per Sunil Chopra, P. Meindl & D. V. Kalra (2007), lead-time is the gap between when an
order is placed and when it is received. According to Silver et al (1998), the replenishment
lead-time is composed of five distinct components and they are given as:
2. Transit time to the supplier. This is negligible if the order is placed electronically.
3. Time at the supplier. Its duration is materially influenced by the availability of stock
4
4. Transit time back to the stocking point.
The problem, which is being faced by WiChorus is that, specialized raw material (like
programmable chips, memory modules etc.) is required for equipment production. Most of
these raw materials are not available off the shelf; neither off the shelf materials can be used
as raw materials for the specialized equipment. The lead times are longer for these types of
items and it ranges from 2 to 12 weeks. Once these items reach manufacturing facility, only
then manufacturing operations could start. WiChorus also uses third party manufacturers for
the PCB manufacturing and assembling. So these items needs to be ordered and stored at
WiChorus facility for the time being as raw material, and further sent to third party
manufacturers for PCB assembling. There is a cost incurred to purchase and store these raw
materials.
According to Chopra et al (2007), overstocking cost is the loss incurred by a firm for each
unsold unit at the end of selling season. For example if finished or semi-finished goods
inventory is present at the end of selling season than that cost will be called as overstocking
cost for WiChorus Inc. Copra et al (2007) elaborates the understocking cost as the margin
lost by a firm for each lost sales because there is no inventory on hand. These costs also
lack of future uncertainty. Since WiChorus do not have a simulation process so they cannot
track its inventory process when it desires. They have to put an input to the inventory system
5
based on the previous data and information. It is always undesirable to have an unwanted
inventory in the process. It may be a safety inventory, raw material, WIP or finished goods.
Inventory present in the process is an invested cost and increase the total cost.
Also another problem is that if the inventory design has to be change, it will give the great
risk of loss to the company in case of failure or wrong decision. Presently there is no
particular method available to implement the change in design without having a chance of
losing profit.
A very cost effective solution, which can be applicable to the above-mentioned problems, is
the use of simulation modeling to achieve the inventory optimization. Simulation is used to
foresee the system’s behavior by changing system inputs; with this advantage we can give
minimum input (input stands for raw material and work-in-process inventory) to the system
to get the desired output. This reduction of the inventory saves the input cost and thus
reduces the final manufacturing cost. Cost is also reduced by altering the overdesign and
unwanted safety factors that were designed when system projection was uncertain or unclear.
1.4 Hypothesis
“If the inventory management involved in the process of product development is optimized,
the total product development cost can be reduced. Optimal utilization of resources and time
product development cost. Reduction in lead-time and carrying cost can be achieved by the
6
1.5 Summary of the phenomenon
There are different kinds of inventories involved in the production process at WiChorus Inc.
Raw materials are imported from various countries including Japan, Israel, Taiwan and
China. Expensive raw material inventory is kept at head office warehouse. Product
designing, testing and assembly are also conducted at head office. Manufacturing and
Safety inventory is also maintained for any unforeseen circumstances, which can affect the
smooth and timely supply of raw material and work in process items from its suppliers.
2. Company Background
Increasingly, users are looking for a similar broadband Internet experience in the wireless
world as they have in the wired world. Service providers like Sprint PCS, Verizon Inc. etc.
are eager to deliver this experience but need a cost-effective, scalable solution. Combining
the advances of OFDMA technology with the power of IP networking. Mobile WiMAX has
emerged as an ideal architecture to deliver these services. Arguably the first 4G networking
solution, mobile WiMAX offers greater bandwidth than previous technologies. WiChorus
Inc. manufactures WiMAX mobile Internet gateway products and was established in 2005.
Its head office is located in San Jose, California and branch offices in India and Pakistan.
7
According to WiChorus website (Retrieved Ja
January,
nuary, 2009), WiChorus is a leader in Smart
4G Gateways and is a specialist that provides a new class of intelligent wireless core
networks. Leveraging this platform, the company's Gateway and Home Agent products
provide content management, advanced services, and subscriber management and network
performance, WiChorus solutions are designed to accommodate the future bandwidth and
platforms, keeping in view the data & control capacity and content management needs of
8
future 802.16e, 802.16m and LTE networks. The result was adv
advanced
anced SmartCore™ SC 1400,
carefully designed for the specific tasks and intelligence needed at all levels of functionality.
software design enable the massive processing and learning capabilities of the SmartCore
platforms. SmartCore future proofs the mobile core for advances in WiMAX and 4G
technologies.
SmartCore
rtCore platforms are also being leveraged to develop 3GPP/LTE products, as follows:
WiMAX Base Stations. The Open R6 software is being commercially used by more than five
WiMAX equipment companies, in their Base Stations, for Profile C compliance. WiChorus
is funded by top-tier venture capitalists including Accel Partners, Mayfield Fund, Pinnacle
Ventures and Redpoint Ventures. These investors have previously funded IP and telecom
USA
US wireless market accounts for almost one-tenth of the global cellular subscribership. As of
2004, US customers alone counted for 163 million of the 1.7 billion subscribers in the
Association’s recently released market review and forecast. According to the review USA
alone will have 200 million wireless subscribers and account for $150 billion in spending in
2008. This study reveals that average revenue per voice minute stopped its decline at $.10 in
2006 whereas usage of total minutes keeps on increasing to 485 (average minutes of use per
month). The voice prices keeps on falling so it means that all of the efforts that carriers have
been putting into data services might actually be paying some dividend. The different graphs
showing historical data related to US wireless industry are shown below (refer figure 4 to 8).
These facts clearly defines that we have a big market where optimization of inventory
management can be applied. As all these wireless internet or cell services provider are going
11
Average Minutes of Use per Month
600 540
485
500
427
380
400
300 255
185
200 136
119 125 117
100
0
1995 1996 1997 1998 1999 2000 2001 2002 2003 2004
20 2007
0
2001 2002 2003 2004 2005 2006 2007
12
Average Revenue per Minute in $
0.5 0.47
0.45 0.41 1995
0.4
0.4 1996
0.33 1997
0.35
0.3 1998
0.24
0.25 1999
0.18 2000
0.2
0.15 0.12 0.11 2001
0.1 0.1
0.1 2002
0.05 2003
0 2004
1995 1996 1997 1998 1999 2000 2001 2002 2003 2004
13
US Wireless Capex in Billion $
25
21.9
21
18.9 19
20 17.9 2001
17
15.4 2002
15 2003
2004
10 2005
2006
5
2007
0
2001 2002 2003 2004 2005 2006 2007
companies.
A supply chain consists of all parties involved directly or indirectly in fulfilling a customer’s
request. The supply chain includes not only the manufacturer and supplier, but also
transporter, warehouses, retailers and even customers themselves (Chopra ett al, 2007). The
supply chain management may be viewed as a growing field of practice and an emerging
domain in academics. Both of these perspectives are not totally mature, but each one has a
conjunction with Global Supply Chain Forum offer following definition of supply chain
management:
end users through original suppliers that provides products, services, and the
information that add value for customers and other stake holders”
Recently, supply chain management has seen its role shifting from the theory of passive cost
profitability. The top-level management has recognized this by building efficient and
effective supply chains that sustainable competitive opportunities can be achieved and
materialized. The significant advantages are timely product availability, reduced costs,
shorter lead times and improved customer service. There has been an increased development
of new manufacturing methodologies such as agile, mass customization and lean. These have
reduced manufacturing costs significantly, but at the same time they have brought new
challenges for supply chain managers. These paradigms have led manufacturing firms to
emphasize their supply chain relationships toward fewer suppliers. Moreover, there has been
an increasing movement towards adopting the concept of supply chain integration, both
15
Figure 9: Generalized Supply Chain network for an individual firm
Figure 9 shows the generalized supply chain network for an individual firm. After each
processing facility, transportation should be carried out in order to deliver the raw material or
semi finished/finished products to next manufacturing facility, until it reaches the final
is stored at third party manufacturer’s facility. The complete supply chain process of
The key enabler of supply chain is information sharing. It can bbee between vendor, supplier
and customer externally, and internally within the organization between different
departments. The Information that is required depends upon the nature of problem to be
16
organization in which different entities cooperatively organize the networks of production,
distribution and supply for products and services. There is a well-accepted technique for this
Grabis & Armen Tumanyan (2006) who has mentioned Li et al (2006) in their research
paper, four types of data are to be shared across the supply chain. These are order, demand,
inventory and shipment data. Moreover, customer service management and order fulfillment
are the issues that need to be managed by supply chain. The information related to these two
issues needs to be shared in order to accomplish the effectiveness and efficiency in supply
chain. Another thing that is of importance is how we share the information. The common
methods to share information are ERP (Enterprise Resource Planning), Web-based portals,
EDE (Electronic Data Exchange) etc. Handsome amount of cost is related to acquire these
resources.
Understanding this complexity helps to realize the business requirements which are further
used to offer adequate solutions. Once supply chain’s operational and organizational details
are studied, its uncertain and dynamic nature is exposed. Most of the time ad-hoc supply
chain arrangements are used, due to which the life span of supply chain’s member is too
short. Due to this reason a collaborative information sharing system must be in place in any
17
Table 1: Different levels of decision making in supply chain
DECISION MAKING
TIMELINE TYPE OF DECISION MAKING
LEVEL
Investment on plants and capacities.
Strategic 5-10 years Creation of a logistic network.
Introduction of a new product.
For the purpose of this project we will be focusing on Tactical and Operational decisions.
Most of the products of WiChorus are special in nature with an expected life cycle of 3 years.
chain procedures are adopted, although lean manufacturing techniques are followed.
behavior in particular directions and in particular ways. Moreover, he suggests that there are
a number of interconnected ideas and suggestions, which constitutes the assumption and
18
Table 2: Difference between conventional management and supply chain management
CONVENTIONAL CONVENTIONAL
DIMENSION
MANAGEMENT MANAGEMENT
Functional, department,
Unit of analysis, focal Functional, department, or
or firm as main unit of
point of allegiance firm as main unit of analysis
analysis
Use of information Information denial; lack Information denial; lack of
and knowledge of transparency transparency
One sided benefit; win-
Beneficiaries One sided benefit; win-lose
lose
Optimization; cost Optimization; cost reduction;
Targets
reduction; price control price control
Short-term wins; periodic Short-term wins; periodic
Time horizons
negotiation negotiation
Relationship episode Transactional Transactional
Multiple competitive Multiple competitive
Range of Partners
sourcing sourcing
Connectivity Independent logistics Independent logistics
Reactive vs proactive Reactive buyers Reactive buyers
Process of supplier
Competitive tendering Competitive tendering
selection
Replenishment device Inventory Inventory
Source: (Storey et al, 2006)
The main keystone idea relates to integration and alignment is, whether services and sub-
components should be made or bought. Various researches found that a number of factors
can enable or inhibit supply chain management, which also depends on the circumstances
and the method in which the factor is utilized. These factors are transparency of information
and knowledge, supply chain behavior and performance measurements (John Storey &
19
As mentioned by Kimball E. Bullington & Stanley F. Bullington (2005), Deming (1986)
emphasized on the importance of long term relationships with a single source supplier in his
discussion of his fourth principle for management. He emphasized the fact that supplier
importance too. Here relationship means that instead of abstract corporate entities, people are
required for the people who depend on the success of these relationships. (e.g. service
personnel, engineers, buyers at both customer and supplier companies). It is also possible that
team members are not being trained for creating manufacturer and supplier relationships.
In the same research paper (Refer Bullington et al (2005)), Schonberer (1986) described this
relationship by stating that key suppler should be treated “like family”. Keki Bhote (1989)
mentioned this relationship as marriage. McHugh et al (2003) also stated this relationship as
marriage. If the word marriage is suitable to define this relationship then distinctive qualities
found in close families should be used as a guide for forming and sustaining strong
manufacturer supplier relationship. This relationship can be further elaborated by figure 10.
20
Time Together
Change
Principles
Appreciation
Commitment Communicate
Here supply chain relationship model is shown graphically. If we start from the bottom,
commitment and communication are illustrated as foundation. At the top change is shown to
describe the fact that the outputs obtained during the crisis of change are the cause of
partnership. At the centre, principle acts as a compass to guide the relationship between
considerably high. In the case of WiChorus Inc, it is mandatory to keep multiple suppliers,
due to the diversity of the components/raw material required for manufacturing different
kinds of raw materials. Commitment can be judged by actions such as lead-time, source
21
Communication acts as a backbone in customer-supplier relationship. The information like
order quantity, prices, payment schedule (terms and conditions) and design data are of
proper inventory level through forecasting, customer service level, costs, maintenance etc.
are more of technical nature if compared with external communication. Nature of internal
and external communication is considerably different from each other, and different team
members should do them. Here change is referred as crisis, which stand for a turning point.
of handling unplanned change. Product and process change can be termed as planned change.
unplanned change and to take full advantage of the benefits of planned change.
integration etc. This has done in order to broaden the operations efficiency spectrum to
include the internal manufacturing operations as well as the upstream and downstream
operations. Nowadays competition is not only between companies but also between there
respective supply chain. Whoever has a proficient supply chain management wins the game.
Now it has become important for any service or manufacturing firm to confirm that the
operations at partner companies are also competent. For the last two decades just in time
(JIT) strategy has been applied in manufacturing firms. The traditional approach of JIT has
been applicable to the internal manufacturing operations of the companies. Some research
work has been done in order to investigate how the just in time strategy can be applicable to
the supply chain of an organization. The just in time approach contains principles and
22
operational techniques to improve the response time to corresponding customers. If the
delivery times of raw materials and finished products are reduced, an organization can
produce components or products efficiently. It could be said that supply chain management
Before going into the details of inventory’s role in supply chain network, we should define
what inventory is and why it is necessary to carry inventory by any manufacturing or service
(Merriam Webster, 2009). Another definition is, “Inventory is a list of goods and material (in
semi finished or finished form) or those goods and materials themselves, held available in
stock by business” (Wikipedia, 2009). The word inventaire originated from France and it was
used for “detailed list of goods”. Inventory management is basically all about enumerating
the location and quantity of stocked items or goods. It is required at different stages within a
circumstance due to which shortage could occur. The unforeseen circumstances can be an
unplanned sales order from customer, environmental hazard (earthquake, flooding etc.),
Different aspects are covered in the scope of inventory management and they include safety
physically present inventory, available and consumed space for storing inventory, quality
management characteristics and defective goods which are returned. There are some
23
essential reasons to keep an inventory in any organization. The reasons are time, uncertainty
and economies of scale. Lead-time is a time between order placement and once the product is
received. Certain quantity of inventory should be present in stock to be used during the lead-
time. Some amount of inventory should also be kept due to uncertainty of demand. We have
already discussed the presence of uncertainty due to couple of reasons in the beginning.
Another important factor is economy of scale. In many organizations bulk buying is adapted
According to Cynthia Wallin, M. Johny Rungtusanatham & Elliot Rabinovich (2006), the
typical manufacturing firm spends on average 56 cents out of every dollar of revenue (i.e. 56
percent of revenue) to cover the direct cost of purchased goods, with this percentage figure
even higher for the typical wholesaler or retailer (Monczka et al, 2002; Hansfield, 2002).
Further he refers that if we add to this figure the indirect cost of having to manage inventory
of purchase goods (which has been estimated to be 30-35 percent of the value of purchased
goods-see Chase et al, 2004), the total cost of purchased goods inventory can be quite
alarming. It means that for any time period a firm carrying $10 million in purchased items
goods will incur an additional cost of 3-3.5 million in inventory carrying and material
handling cost. Once these direct and indirect costs are reduced they can improve firms net
profit. This is the reason why different types of organizations including manufacturing,
wholesale and retail are focusing their efforts not only on direct cost but also on indirect costs
inventory management approach for any purchased item or raw material must not only
address the cash tied up in physical inventory but also the costs of planning, storing and
1. Inventory Speculation
2. Inventory postponement
3. Inventory Consignment
All these approaches are for inbound inventory of different kinds, like raw material,
components, sub-systems and retails inventory. WiChorus maintains all these types of
inventory at its own location and moreover at the location of third party manufacturers.
Relevant factors associated with these different approaches are elaborated in table 3.
25
Table 3: Four types of inventory management approaches
26
We agree with the findings of Dave Janiga (2005) that there are five most important factors
that needs to be considered while making inventory management strategies and these are:
3. Replenishment quantity
4. Re-order point
Carrying costs in any manufacturing facility are associated with holding or carrying
inventories for a certain time period. An organization or company has to spend additional
money on the top of purchase cost in the form of storage (space), insurance, additional
equipment and personnel, clerical support, processing, forms and taxes. Most of the time
carrying costs is varying, depending upon certain factors. It is estimated that carrying costs
The second factor that affects the strategy of company’s inventory management is the role of
the inventory itself. At WiChorus three types of inventories are maintained namely raw
material inventory, semi finished product inventory and finished product inventory.
Inventory is normally composed of two types of stock. First one is the working stock and the
second is safety stock. The first one supports the day-to-day operation of a company. And it
27
will continuously change as the component/material is consumed and replenished. The
second one, which is a safety stock, is basically kept for any unforeseen circumstance. It acts
as a barrier to shortage. It is not used under ideal operations but consumed as required, due to
unexpected events including high consumption rate. Safety stock can be taken as insurance
policy against any unexpected event and it is replenished once inventory goes below safety
limit or point.
It can be mentioned as the amount or quantity to fill the place of used inventory items.
According to Dave Janiga (2005), the most economic replenishment quantity, commonly
called the EOQ (Economic Order Quantity), represents the lowest total sum cost of total
inventory and inventory acquisition costs (order placement costs, invoice processing costs,
payable costs, freight etc.). Once replenishment order quantity is large, then less number of
replenishment cycles is required to meet the demand, and when order replenishment quantity
is small then more number of replenishment cycles is required to meet the demand. The
economic order quantity can be elucidated as the function of consumption rate, inventory
The reorder point can be mentioned as a point at which components/items must be ordered to
replenish the inventory to a certain level. It can be determined by the rate of consumption and
manufacturing facility consumes 20 items per day and it takes 10 days to receive material
from supplier once order is placed, the items should be reordered when the quantity of
28
working stock reaches 200. If the company’s inventory management system is working at
100 percent (ideally speaking), the quantity of company’s working stock will get to zero as
replenishment arrives.
It is not unproblematic to reduce inventory and inventory related cost without getting to the
point where company’s both kinds of stocks reaches zero. Some amount of risk is always
involved in reducing inventory related costs. Operations and supply chain people should
work with the suppliers to shorten order replenishment cycle fulfillment time in order to
minimize the need of safety stock. In order to reduce the inventory related cost another
technique would be to follow product consolidations. Here product consolidation stands for
reducing the different types of safety stock into one typically smaller safety stock. Once the
products are consolidated the consumption rates becomes higher, which in turn makes
According to Terry Harris (1997), optimized inventory management eliminates the arbitrary
A, B, C classes (these classes are with respect with sales, quantities, cost or combination of
these) prevalent in finished goods reorder point systems by treating every item individually
(every time becomes its own class). This approach also optimizes availability of inventory (in
terms of per dollar invested in inventory). According to him this approach is better than any
other approach with respect to the availability the inventory provides and the investment
required by it. In the same case study it is mentioned that a distributor Cummins Engine
29
Company, service parts inventory was reduced by 32% and availability was increased from
81% to 90% within the time period of three months. This study was carried out for finished
goods inventory, but at WiChorus we are dealing with raw material inventory and semi
The time taken to convert semi-finished goods to finished goods, ready for delivery to
customers is not too long. Due to the reason that WiChorus produces specialized products, its
customers sometimes are willing to wait for a day or two to obtain the equipment, but not
later than that. The basic reason of having finished goods inventory is to provide required
items to customer, when they require and how much they require. If the items are not
available, than the customers go elsewhere and sale is lost. This not only impacts the
immediate sale but it also hurts future business with the same customer. Since the lifecycle of
products that WiChorus produces is short, so the lost sales could impact more.
30
According to Terry Harris (1997), as can be seen in figure 11, availability is the percent of all
items that can be supplied from inventory over a specific time period. The mentioned time
period can be an arbitrary time, lead-time or review time. The value of inventory mentioned
is for the average inventory, over the same time period at a certain cost. In figure 11 optimal
curve is generated from a series of points. Specific stocking strategy is represented item-by-
item, by each point. Each strategy represented here is optimal, at the dollar level of that point.
No other stocking strategy can give a higher or equal availability level at the dollar level of
that point. There is another curve of some other approach, which is above the optimal curve.
As per Terry Harris (1997), an inventory manager can optimize inventory in one of two ways
2. Specify an investment level and use it to achieve the highest possible availability of
items.
by using some other technique, it should be worse than the optimal curve. Every point on the
other curve is on the left side of corresponding availability point on the optimal curve.
Moreover, it is above the optimal curve. Improvements can be made if we pursue following
steps. The inventory manager or planner can move from any point on the other curve to the
that of the optimal curve and in result increase the availability at the same dollar value. And
decrease dollars at the same availability level, or do some of the both strategies. There are
some enormous improvements has been achieved by the companies who had followed the
same strategy. Terry Harris (1997) has mentioned the improvements as follows. Inventory
dollar (figure 11) and availability (figure 12) figures for all the approaches, whether they are
32
optimized or not, are the targets. These are the targets at which inventory manager or planner
can aim. Although the aim is to achieve the target but it cannot be achieved fully. This is due
to the reason that actual forecast and lead-times are never fixed (as in ideal condition), but
they are variable. Optimized approach has confirmed it that lead-time variability and forecast
According to Terry Harris (1997), optimized inventory management fits inside normal re-
order point systems. The optimized approach uses item level data, like cost and lead-time
(refer figure 14). Very simple interface files can be used to make data available for an
optimizing module. That in turn produces optimized re-order points as per different items.
33
3.3 Time As A Key To Inventory Management
The pattern of high level of inventory precision and reduced inventory cost that were once
standards for material management have had another crucial element added. This is the
marketplace, time has become the vital factor to effectively manage inventory. This has also
been witnessed by the development of just in time(JIT) approach and Kanban systems. These
methodologies were developed to cater for world-class costumer services. For certain
markets the standards for time measurements have become hours, days and weeks instead of
months or years as a quarter. In the case of WiChorus, question is asked that how much
inventory do we need to satisfy customer’s demand with avoiding the pitfalls of creating
excess inventory, while reducing the cycle time? As per Patrick C. Scanlon (1995), an
additional tool that is called week-on-hand reporting system were developed at Rosemount
Analytical Inc. The design of this system was helpful to project forward inventory usage I
dollars. Moreover this system was helpful to identify potentially excess or obsolete inventory
before it becomes liability for the Rosemount Analytical. The results for the time span of four
years were 50% inventory reduction and increase of on-time performance from 70% to 92%.
Now a days trend is shifted towards shorter life cycle products in several industries.
According to Abbas A. Kurawarala& Hirofumi Matsuo (1996), the shorted life cycles are
caused by fast changing consumer preferences that lead to fashion and fad effect. These
trends are also due to rapid rate of innovation, especially in the computers industry, consumer
34
Due to the mismatch of supply and demand, inventory exists in a supply chain. The
important role of inventory in the supply chain is that, it can be used to increase the amount
of demand that can be satisfied by having the product ready and available when the customer
needs it. Throughout in the process of supply chain, inventory is held in the form of raw
materials, work-in-process and finished goods. It is a major source of cost in the supply chain
Inventory is considered to be as a cost to the company. Inventory is the static money that
should be as least as possible. Therefore, the target for any manufacturing company is to
keep the inventory as minimum as possible. Reducing the inventory ultimately increase the
4. Literature Survey
Various credible sources were used for the research purpose; these sources are used to
optimize the inventory management process. Different research papers were reviewed in
detail in order to retrieve the information that is relevant with the company’s infrastructure,
products and manufacturing methods. Two books related to Supply Chain Management were
short-listed which consists the different techniques that can be applied for calculation of
various aspects like quantity; cost and lead-time related time frames. Details of the case
studies and research papers that are short-listed are given as follows:
This research paper is taken from European Journal of Purchasing and Supply Chain
Management, and it is written by Ronan McIvor in July 1999. The publisher of this journal is
35
Elsevier. The objective if this research paper is to analyze whether the principles of lean
supply model are currently present in the electronics industry. This research basically focuses
on the two key dimensions of lean supply chain management. The first one is the supplier
involvement in customer design activities. And the second one is joint buyer-supplier cost
reduction. The products being produced by WiChorus are customized according to different
requirements of wireless data service providers. Moreover this research has revealed that
considerable barriers currently exist to meeting the requirements of equality between partners
This paper is taken from International Journal of Production Economics. The authors of this
research paper are Mark A. Vonderembse, Mohit Uppal, Samuel H. Huang and John P.
Dismukes and it was completed in March 2002. The publisher of the journal is Elsevier. This
research paper describes a typology for designing supply chains that work in harmony to
design, produce and deliver products with different characteristics and customer
expectations. This study blends literature and theory development with case study research to
create a typology. Moreover this paper discusses supply chain types that are compulsory for
success transversely three types of products. It also develops a framework for categorizing
4.3. Modeling the metrics of lean, agile and leagile supply chain: An
ANP-based approach
Asish Agarwal, Ravi Shankar and M.K. Tiwari carried out this research. It was published in
36
December 2004 and it is taken from European Journal of Operational Research. The
publisher of this journal is Elsevier. The emphasis of this paper is on adaptability to changes
in the business environment and on addressing market and customer need proactively.
Flexibility is fundamentally needed in the supply chain in order to counter the uncertainty in
decision parameters. Moreover this paper explores the relationship among service level,
quality, cost and lead-time and agility and leanness of supply chain.
This research paper is taken from the journal of Computers and Operational Research and it
was published in February 2007. The authors of this research paper are Haralambos
Sarimveis, Panagiotis Patrinos, Chris D. Tarantilis, Chris T. Kiranoudis. All the authors are
Economics and Business and School of Chemical Engineering National Technical University
of Athens. The publisher of this journal is Elsevier. This paper emphasizes the fact that
supply chains are complicated dynamical systems, which are triggered by the demands of the
key component of supply chain systems. Efficiency of supply chains most of the times
depends upon management decisions, which are based on experience and intuition. The main
goal of this research paper is that a joint co-operation between control experts and supply
chain managers has the potential to introduce more realism to the dynamical models and to
endeavor
The authors of this paper are Matthias Holweg and John Bicheno. It is taken from
37
International Journal of Production Economics. The authors are the professors in Lean
Enterprise Research Centre, Cardiff Business School, Wales. This paper was published in
November 2000 and the publisher of this journal is Elsevier. This research paper describes
how a participative simulation model can be used to demonstrate supply chain dynamics and
using supply chain simulations, then it is a tool to demonstrate and discuss supply chain
improvements. A three-year research project in the steel supply chain for automotive industry
revealed that lack of understanding of core processes throughout supply chain causes
This book is written by Sunil Chopra, Dharam Vir Kalra and Peter Meindl. It is used as a
course textbook for ISE-245 (Advanced Supply Chain Engineering) at San Jose State
University. The publisher of this book is Pearson Prentice Hall and it is third edition, which
was published in 2007. It is a credible book with the details of various techniques for the
formulation of supply chain strategies and their optimization supported by various case
studies. Sunil Chopra is the IBM Professor of Operations Management and Information
Systems ate Kellog School of Management. He is a PhD in Operations Research from SUNY
at Stony Brook. Peter Meindl is Finance and Economics PhD candidate in Stanford
portfolio optimization and dynamic hedging using stochastic programming, Monte Carlo
simulation and receding horizon control. Dharam Vir Kalra is retired army officer and holds
38
a MSc in defense studies from Madras University. He is a guest faculty at the Indian Institute
of Foreign Trade, New Delhi, and Institute of Management Technology where he teaches
The goal of this book is to cover not only high-level supply chain strategy and concepts, but
also to give its readers a solid understanding of analytical tools necessary to solve supply
chain problems. In the beginning of the book strategic importance of good supply chain
design, operations and planning is discussed and highlighted. It is also emphasized that how a
good supply chain management can be a competitive advantage in a firm, and weaknesses in
the supply chain can hurt the performance of a firm. The Strategic frameworks and concepts
discussed in the book are supported with a variety of actual examples that shows how a
techniques elaborated in this book will be highly beneficial for the optimization of WiChorus
supply chain.
This book is written by Charles R. Harrell, Biman K. Ghosh and Royce O. Bowden and it
was published in July 2003. It is a second edition and publisher of this book is McGraw-Hill.
University and Director of the Simulation and Advanced Computation Laboratory. This book
covers the art and science of simulation with the help of promodel software version 6.0. It
provides a deeper coverage how random behavior is simulated and how output results are
generated and evaluated. Case study assignments are included in this book to have deeper
39
learning of promodeling by presenting actual application in business, services and
manufacturing. It starts from simulation basics and further covers planning, data collection
and analysis, model building, model verification and validation, experimental analysis and
output analysis. It covers simulation optimization using modern techniques. This book will
be used as a learning tool for doing simulation modeling of WiChorus Inc. as some chapters
of this book are devoted to typical modeling issues encountered in manufacturing, material
This research paper is taken from Production and Inventory Management Journal and it was
published in second quarter of 1995. The author of this research paper is Patrick C. Scanlon.
At the time when this article was written he was materials manager with Rosemount
Analytical Inc. This company was located in La Habra, California and he already had an
experience of over 20 years in inventory management, at the time ofpublish of the article.
This research paper emphasizes the addition of the element of time, in inventory
management. He had introduced a new tool for inventory management for critical review of
inventory being held at Rosemount Analytical Inc. The name of the tool was weeks-on-hand-
reporting system. This tool was designed to project forward inventory usage in dollars, and
Scanlon, 1995). This research paper has given an in-depth knowledge regarding the usage of
40
4.9 Optimized Inventory Management
The author of this research paper is Terry Harris and he was the member of Chicago
Consulting at the publishing time of this article. This research paper is taken from
Production and Inventory Management journal. The volume of the journal is second quarter,
1997. This research paper has helped us a lot in the formulation of hypothesis, recognizing
prevalent in finished goods reorder point system by treating every item individually-every
item becomes its own class (Terry Harris, 1997). Different techniques were applied to reduce
the lead-time and inventory quantity at various stages of production. These techniques have
supported our goal to increase the net profit of WiChorus Inc. by doing its inventory’s
optimization. Author had lead a project related to optimization at Cummins Engine Company
and they were able to reduce the inventory investment by 32% and had increased product
This article was published in the magazine, Plant Engineering, in June 2005. Plant
Inc. The author of this article is Dave Janiga who works at ExxonMobil Lubricants and
Specialties. Maintaining an efficient inventory management strategy can help industrial plant
managers to improve and ensure the success of their operations (Dave Janiga, 2005). When
inventory management is considered than there are some important factors that also needs to
be taken into consideration. These factors include understanding your stock, replenishment
41
quantity, lead-time, re-order point and most significant is lead time. These factors were
they are described in this article. Although the article was written while taking into
consideration oil industry(as the author works in ExxonMobil Lubricants), but the provided
Designing of PCB is carried out at WiChorus facility. Once designing is completed, a Gerber
file is sent to 3rd party PCB manufacturer(A). PCB manufacturing(A) is carried out there and
after its completion, they carry out quality assurance. In the mean time raw material
expensive parts are held at WiChorus facility, till the time they are required for PCB
assembly manufacturer(B). In addition to these parts there are many other parts, which are
held at WiChorus till the time they are required for final product manufacturing and
assembling.
42
Figure 15: Manufacturing process and inventory locations at WiChorus Inc.
43
Additional raw material (low cost items) is held at 3rd party manufacturer(B), and they charge
some amount of inventory carrying cost to WiChorus. These are the parts that are used for
PCB assembly manufacturing(B) by third party manufacturer. After PCB assembling quality
inventory. Certain amount of this inventory is carried at WiChorus for the ease of quick
assembling/fabrication. Final assembly and testing is carried out at WiChorus facility. After
6. Simulation
Our project is based on the simulation modeling, which is used to optimize the inventory
management process. One of the significant methods to optimize any inventory system is by
which are used to mimic the activities of some manufacturing phenomenon. Typically, the
phenomenon or entity being simulated is from the field of the tangible, ranging from the
behavior of a light aircraft during wind shear to the operation of integrated circuits.
Simulation may also be used to investigate and verify theoretical models, which is very
One of the key advantages of simulation is that it is able to provide us with practical
feedback, which helps in designing real world systems. This allows the design engineers to
understand the correctness and competence of a design, before the system is actually
constructed in real time. Consequently, the user can explore the merits of alternative plan
without physically constructing the systems. By examining the effects of specific design
44
decisions during the design phase rather than constructing the system in real time, the overall
Another advantage of simulation is that they permit system design engineers to understand
level, the designer is in better position to understand the behaviors and relations of all the
high level components within the structure, and is therefore well equipped to work against
the complication of the whole system. The system designer may easily overcome this
complexity if the problem had been approached from a lowest level. It is better to understand
the system of the higher-level components by the use of simulator, and then lower level
components may then be designed and after that system will be simulated for verification and
Simulation is very frequently used system in designing and analysis of system. There are
2. It permits change to operating system at any time interval, in designing process without
In addition, the visual representation is often an important point that can sell an idea to
45
Figure 16: Simulation Modeling Flow
2008)
46
“The entire
ntire system may be built based upon this ``top
``top-down''
down'' technique. This approach
is often referred to as hierarchical decomposition and is essential in any design tool and
simulator which deals with the construction of complex systems.” (Craig, 2006)
the future of the present input. In this manner company can easily target their goal and
can also achieve them successfully. Considering current trend in industries, WiChorus
is also looking for the Six Sigma implementation. “Six Sigma at many organizations
simply means a measure of quality that strives for near perfection. Six Sigma is a
disciplined, data-driven
driven approach and methodology for eliminating defects (driving
towards
owards six standard deviations between the mean and the nearest specification
speci limit) in
47
The production process of WiChorus is based on Build to Order (BTO) phenomenon. BTO
organizations can be explained as the manufacturing organizations where products are made
after the arrival of the order. WiChorus keep a safety inventory and buys many of the parts as
per order and do the process. WiChorus requires simulation because it keeps an inventory in
advance and also itrequiresit to know the process time in each and every step and further to
track it. In our project we are using software “ProModel” for the purpose of simulation. “The
advantages of special purpose simulation tools over general purpose languages are that, they
are easier to learn, generally very little programming knowledge of simulation is needed to
operate the system. In addition, the graphical component in these programs gives another
7. ProModel
The ProModel is a powerful simulation tool for modeling all the different types of processes
and it is mostly used for manufacturing process. Process or a system, ranging from very
small to large and complex mass production, can be modeled by the ProModel software. In
WiChorus, the production is not the mass production type, but they have large inventory
process and flexible manufacturing process. ProModel is Windows based software with a
modeling structure, which constructs the model and eliminate the need for programming. It
has combination of the flexible general-purpose simulation language with the expediency of
a data-driven simulator. ProModel is considered to be the best optimization tool for the
48
In WiChorus, we targeted to reduce the cost and time as minimum as possible with the
available resources.
• Use the saved amount and resources for research and development purpose
And by reducing the time, advantages that we are providing areas follows:
The developed simulation model is completely object oriented and graphical. To the highest
degree possible, all inputs are given graphically. Moreover, all the given information is
grouped by presenting an object and its type, and in a spreadsheet-like format. Its purpose is
for quick and intuitive access. ProModel works with Graphical User Interface (GUI)
standards, it means that modeler who is familiar with other standard of Windows software
like word processors or spreadsheets will have no problem in learning and using ProModel.
This way of data input approach, helps in reducing the learning curve for us to make a model
for WiChorus and maximizes the efficiency and accuracy for modifying large and complex
49
models as for WiChorus Inventory process. Development of animation is integrated with the
definition of model.
Considering the unpredictable economy in current market in USA, uncertainty factor is also
very important factor in designing the model. Considering that WiChorus also has to consider
the uncertainty of the market and unpredictability of the time and money, ProModel is
considered to be the best solution for the inventory supply chain modeling. Variability is
related to many factors, it can be internal or external, may be controllable to some degree or
defined as “The lack of complete certainty, that is, the existence of more than one possibility.
In his seminal work Risk, Uncertainty and Profit, Frank Knight (1921) established the
“... Uncertainty must be taken in a sense radically distinct from the familiar notion of
risk, from which it has never been properly separated. The term "risk," as loosely
50
used in everyday speech and in economic discussion, really covers two things which,
organization, are categorically different. ... The essential fact is that "risk,” means in
something distinctly not of this character; and there are far-reaching and crucial
really present and operating. ... It will appear that a measurable uncertainty, or "risk"
proper, as we shall use the term, is so far different from an immeasurable one that it is
not in effect an uncertainty at all. We ... accordingly restrict the term "uncertainty" to
ProModel consider the standard deviation of the process involved in the entities. Every single
1 Chips 60 5
2 PCB 40 4
3 Network Board 5 1
4 Chassis 20 3
5 Bezels 5 1
51
6 Filler Assembly 2 1
7 Face Plate 2 1
Table 4 shows the standard deviation of the entities process time. These deviation are taken
ProModel has a flexibility feature that it can automatically put a given deviation randomly to
the process time to consider the uncertainty from the normal values.
ProModel has structure built on the modeling element and the model to build is represented
physically and logically by the building block. The inventory supply chain of WiChorus is
built on the building block provided by the ProModel. Different physical elements involve in
the process as in our case like Chases, PCB, ICs etc are represented graphically in the model.
52
Figure 18: ProModel’s Modeling Element
Table 4 shows the list of the entities we used in our simulation models. Gerber file is the
design file that goes to Network Board Assembler and other entities are the raw materials
that arrive at WiChorus and become the integrated part of SmartCore products. Figure 18 is
the picture of the ProModel showing the options for building the entities.
7.3 Locations
These are a fixed places in the model’s design e.g. machines, warehouse, workstations,
shelves, etc. These are the places where above-mentioned entities are routed in their
53
processing. These locations are either physical unit, like a single machine or a group of
These routing locations may have a capability greater than one entity to process and may
have periodic downtimes as a function of usage time (e.g. tool wear), clock time (e.g. shift
Figure 19:: ProModel picture showing the different location in design Model
selecting which entity toprocess next while output rules are of purpose for ranking entities
54
and Conveyors are two special types of locations that offer movements as well as performing
holding and operation functions. Conveyors have a load spacing and particular to take the
entities from one location to the others. On the other hand queue work as of waiting lines,
which includes the movement of those entities, which has to be shifted through line.
Conveyors are the networks, which are provided to provide interconnection.There are
different locations in WiChorus where the entities are being routed as per requirements.
Following is the list of locations involved in the inventory supply chain of WiChorus.
2 Warehouse (WiChorus)
3 PCB manufacturer
4 PCB Assembler
6 Configuration (WiChorus)
Production Department
7
(WiChorus)
8 QA Department (WiChorus)
55
7.4 Entities (or parts)
The items being processed in the system are called entities. These can be consists of piece
parts, WIP, raw materials, finished products, assemblies, loads etc. The entities being
processed may be of same types. These same or different type entities may merge into a
single entity, or single entity can be separated into two or more same types of entities or
change into different types of new entities. “Entities may be assigned attributes that can be
S No. Name
1 Chips
2 PCB
3 Network Board
4 Chassis
5 Bezels
6 Filler Assembly
7 Face Plate
8 Gerber File
56
7.5 Path Networks
Path networks define the possible paths on which the entities and resources, which are in
designing process, may travel when moving in between locations or through the system. Path
networks are made of nodes connected by its segments and defined by simple mouse click
graphically. These networks may be defined as multiple path networks or multiple entities
share the same network. Such movement along a path network may be describes in terms of
speed or distance. On defining the layout scale, path distances can be automatically
computed.
• passing
• non-passing
• crane
For open path movement mostly a passing network is used where resources and entities are
free to surpass one another. Non-passing networks are those networks that consist of guide
paths of single file tracks. Crane networks describe the operating interface and envelop points
7.6 Resources
A resource may be a tool, person, vehicle or other things that may be used to:
57
• Perform repairing or maintenance on a location or other resource to avoid or reduce
down time.
Resources may be either dynamic assigned to a path network or may be manually. Crane
orforklift is the special kind of dynamic resources. Since in WiChorus the entities are of
small size, mostly the human resources are used. It has an option of built-in decision rules
program that can be used for resource allocation and part prioritization of the entities pickup
Processing or routing defines the processing sequence of the entities and their flow logic in
etc. or a combination of these having an expression. There are different logics available for
routing in ProModel
• IF-THEN-ELSE statements
• Loops
• Subroutine calls.
Some statements are related to resources that are used with Boolean expression
• GET
58
• USE
• JOINTLY GET
• ACCUM
• JOIN
• GROUP
These statements greatly simplify the logics otherwise logics will be complex and required
has feature that the external files, which may be arrival data or production schedules, can be
read into the arrivals element. Table 7 shows the list of the arrivals at different locations in
design model for WiChorus inventory simulation. ProModel can also use user defined or
built-in spread sheet or distributions to define the internal arrival frequency, quantities and
times.
S No. Name
1 Chips
2 PCB
3 Network Board
4 Chassis
5 Bezels
6 Service Card
59
7.9 Shifts (or work schedules)
ProModel has a powerful feature to define the work by own used and schedules can be
broken through ProModel's shifts module. Break and work schedules are graphically defined
as time and day of the week. After that locations or resources are allocated to a particular
shift schedule. In addition, shift and break logic can be defined as, that controls resources and
location actions when they become off-line and the behavior once they become off-line
“The runtime interface (RTI) is a convenient and controlled environment for modifying
selected model parameters (capacities, operation times, etc.) without having to change the
scenarios to be designed, defined and simulated. The Runtime Interface can be approached at
the start of a simulation run for the purpose of making modifications for a single simulation
run or for the modification of alternatives for doing the analysis of multiple scenarios.
There are additional modeling elements available to make an extra options and functions to
the model.
• Variables
• Attributes
• Arrays
60
• Macros
• Subroutines
• External Files
8. Method of Investigation
The simulation model locates the machine location in accordance to the layout and design the
61
8.1.1 Capacity Inputs
The information provided in this module indicates the number of machines in each process
and the schedule cycles of workers to operate. These aids in determining the amount of
Processingdata required each product type such as setup, load-unload time, production rates,
62
8.1.3 User Specific Data
In ProModel user can be able to customize the simulation design by altering certain
The sequencing time table of product items for production to follow, this aims to find the
ability of the plant to complete the demand within the limitation period, one month.”
Since WiChorus is not a mass production organization, they produce an average of 15 units
of SmartCore every month. They do the forecasting by using a survey method from
marketing and sales persons. We started our investigation by analyzing the current inventory
process in WiChorus. As per our scope of project we are only focusing on the production on
SmartCore but there are few other products that are being manufactured at WiChorus.
SmartCore is the prominent and revenue driven product among all. Research has been done
on the current and past data to find the values and numbers to design our model. There are
To optimize the inventory process these two factors should be the major part in investigation
as in our project. We did not include cost as a direct input but we consider the entities that are
the cost driven in the production of SmartCore. But the time is the direct input in designing
Forecasting has been done in WiChorus through surveying from marketing and sale
personnel. Forecasting is the first input data to the simulation model. This forecasting data is
obtained as month-by-month basis. Forecast data is adjusted in the arrivals at locations where
they arrive. In our research we have found the following forecasting data from year 2009 for
the SmartCore.
16.2
16
15.8
15.6 No. of SmartCore
15.4
15.2
15
14.8
14.6
14.4
Jan (2009) Feb (2009) March (2009)
We used the forecasted data because when the simulation will be used, the input will be the
forecasted data. Purpose of the simulation is to foresee the future and to analyze and alter the
currents inputs to the system considering the future situation. Above table shows that demand
for January 2009 and February 2009 is15 units and for March 2009 is 16 units. Taking an
64
Following data shows the demand for individual parts for the single and the number of unit
being ordered for the parts. This data is given by the WiChorus, it shows the number of parts
1 20
1 Chips
2 30
2 Service Card
1 20
3 Network Board
1 15
4 Chassis
1 30
5 Bezels
Above table shows that Chassis are ordered in exact quantity, which is 15 numbers for 15
forecasted units. Whereas the other order quantities are ordered greater than the required
They always keep a safety inventory in order to be safe from shortage of resource available
65
8.1.6 Inventory Process
Inventory process starts with the arrival of the entities or parts at WiChorus. Each part has
Parts that arrives WiChorus have the lead-time depending upon the origin locations of the
parts. Following is the lead-time of the different parts that arrive at WiChorus.
Lead Time
7
5
Nunber of weeks
0
Chips PCB Network Chassis Bezels Service Card Face Plate
Board
Parts
Chips PCB Network Board Chassis Bezels Service Card Face Plate
Above table shows that PCB has very high lead-time of 6 weeks. WiChorus send the gerber
file (PCB design file) to the printed circuit board-manufacturer; they take 4 weeks to return
66
8.1.7 Issue of considering Network Board in Lead Time:
Issue: All of the lead time involve in the inventory process are before the arrival of the
system but the process time(manufacturing time) for the network board should be considered
Reason: Reason for the this consideration is that if we wait 6 weeks for the single process we
will not be able to reach the target of making 15 units in one month
Action: Because of having this problem, instead of considering this as a process time for
advance because of having large process time and considered as a lead time. In our model we
put a process time at the location of PCB manufacturing of 120 min to avoid the lead-time of
6 weeks.
Arrival Collected input data are being put as input to the location in terms of arrival. These
arrivals have different frequencies and occurrences. Since we are modeling for 1 month, the
occurrence for every arrival is put to be 1. It is because the raw material or part required to
Queue: Queue is present between every location. Purpose of having this queue is when the
entities are entering the locations and being process, rest of the entities wait in the queue
before its turn. If we have to find how many entities are in process after the completion of the
target output we can find in the locations and in the queue that how much is the remaining
67
All entities arrive at the WiChorus warehouse. In warehouse these entities kept in there, until
required to process further. There is a certain process time at every location to process the
entities.
First the Gerber file that is designed at the design departmentis being transferred to the
Printed Circuit Board Manufacturer (locations). They have a process time of about 4 weeks
but as suggested before this process time considered as a lead-time. Giving the design to
we applied the standard deviation to the process. ProModel has remarkable feature of
considering the standard deviation of the process time. It is given in range value that is
After the Gerber file being processed, this entity is converted into the printed circuit board.
PCB goes to the PCB assembler and in the mean time chips from the WiChorus also
transferred to the PCB manufacturer or assembler. After the assembling of PCB is tested, it is
then shifted to the assembly department of WiChorus. In this department other entities that
are kept at warehouse along with assembled PCB are started to assemble in the chassis.
Chassis is the main structure on which the other entities being assembled.
As can be seen from the ordering data, WiChorus ordered 15 numbers of chassis. WiChorus
always ordered the exact number of chassis considering the forecast for the month. Reason is
that the cost of chassis is very high and it is not a good idea to keep chassis as safety
68
inventory. After assembling stage assembled unit transfer to configuration department after
8.1.9 Verification
After the modeling is done, design is to be verified for its feasibility. When the simulation is
run it is verified that the desired number of units i.e. 15 units in our case is exit at the end of
After modeling a simulation design of WiChorus Inventory process and following the
simulation process flow, we have carried out the analysis and optimization of the model.
From our modeling of inventory process we get the output results. Result investigation is
done in two parts, which has first shown the validity and then the significance of the
simulation modeling.
In our investigation we targeted time and cost. In cost optimization, the process cost has been
reduced. This cost is related to inventory, which comprises of raw material inventory, work
in process inventory, and finished goods inventory. Reduction in cost results increase in
profit as described earlier. Secondary target is time. Reducing the total time for the
production gives a benefit of good customer service, better time to market and increase in
Firstly, investigation shows the validity of the model and after that investigation of the
69
8.2.1 Credibility of the Model
Credibility of the model describes the validity of the input and output data. According to our
research data of the WiChorus, it has been found that they are making 15 units of SmartCore
per month as described earlier. We used the process time as found for each entity at every
location similar as found in WiChorus inventory process. The number of output units as per
requirement can find out validation. Run time of the simulation is one month. Following is
the output result from our design model in ProModel for inventory process at WiChorus.
Chassis
assembly time 14.54 (Average)
Chassis
assembly time 2.17 (Std. Dev.)
Chassis
assembly time 12.99 (95% C.I. Low)
Chassis
assembly time 16.1 (95% C.I. High)
70
Above result are shown in detail in Appendix A1. This is an extract part from the simulation
result. This result shows the validity of the optimized result. The process time of the chips
assembling and chassis assembling is N(120,5) and N(15,2) respectively. It means that for
chips assembling time, time has to be between115 and 125, which is visible from the above
table that C.I.(control limit) low and C.I.(control limit) high is in range. Similarly the range
for the Chassis assembly time is 13 and 17 and current value of the output is in range of the
given deviation.
Lead-time optimization is the optimization to reduce the total time to make a single unit. In
WiChorus inventory simulation model, total time to make 15 units is the runtime of the
model. Entities, which are the part of the SmartCore unit, arrived at the start of the simulation
time, and ends with the exit of the 15 units. Runtime of the simulation model is 1 month. In
regular model, which is designed with current scenario with the exit of 15 units per month,
the schedule hours is 49 hours to get 15 unit ready at the end of the month.
We made a separate model for the time optimization model. By applying the optimization
techniques, schedule hours have been reduced. It has been done, by changing the available
resources. It has been found from the analysis that the resources can make the most
significant change to reduce the runtime. It has been found by the utilization of the resources
and also depends upon which location or resources have high dependency in the process. In
our case we have found that PCB Testing Department can affect the lead-time for the
production. If the capacity of the testing department is increased or by increasing the staff of
the testing department, lead-time or run time can be reduced significantly to 36 hours as
71
shown in figure 24. Detailed results are shown in Appendix A2. Therefore, by the
optimization analysis, there is a possibility of 13 hours reduction in time to make the same
number of units (15 units). It helps the company to have good customer service and better
Before Optimization
After Optimization
Before Optimization
0 10 20 30 40 50 60
# of Replication
Cost optimization has been done to reduce the total cost. In our scope we focused on the
material related cost. After simulation of the regular model with the real values, weakness
has been found out in the process. With the number of orders been made for raw materials
and put into the process to make SmartCore, with the simulation it is found that there are still
some parts or entities which remains in the system after desired output of 15 units. These
extra parts or inventory are considered to be the waste and it just only increases the material
72
cost of the production. Eventually it increases the total cost of the unit. From Appendix A1,
Table 10: Number of parts left in the system and corresponding savings
COST SAVINGS
PARTS MATERIAL COST HOLDING COST TOTAL
TOTAL $104,670
From the simulation investigation it has been found that there is a possibility of cost
optimization and total of $104,670. Reduction in cost allows WiChorus to reduce the
production cost and can increase their profit margin. (Note: Annual Savings=Material cost +
In addition to the time and cost investigation, we did the analysis to find out the maximum
capacity of WiChorus to build SmartCore with present resources. Previous two models are
designed to build 15 units per month. To investigate the analysis of the maximum capacity of
WiChorus to produce SmartCore with the current scenario, new model is generated with
maximum runtime. Maximum runtime is for the 1 month and comprises of 168 hours per
month, so the model has run time of 168 hours. After the simulation has been done for
maximum output analysis, we came to know that WiChorus have a capacity of making 36
73
units per month, if all the resources has been utilized to their maximum available usage.
Results are shown in Appendix A3. Right now WiChorus is making an average of 15 units
per month, because of the arrival of low number of orders, since WiChorus is a startup
company. That is why they are not using their full capacity for the production but when their
business will grow they can produce up to 36 units with the same available resources.
9. Economic Justification
The economic justification gives the advantages and justifications of the project in terms of
financial investment. ProModel gives an optimized simulation that helps to reduce the
“Cost is always an important issue when considering the use of any software tool, and
simulation is no exception. Simulation should not be used if cost exceeds the expected
This statement shows that both the benefits and costs should be carefully estimated before
making a design simulation decision. It is often observed that the simulation is too soon
dismissed because of failure in recognizing the savings and potential benefits, which
simulation can produce. Most people are reluctant to use simulation because of the notion
that simulation is difficult to execute, time consuming and very expensive. But this concept is
not true because in long run observation simulation saves much more in terms of cost.
74
9.1 Executive Summary
Simulation identifies and eliminates the problems and inefficiencies present in the system.
These inefficiencies remain unnoticed until the model design is formulated and simulated. In
the absence of simulation, companies usually keep much more extra safety factors because of
failure to know the future outcome at the present stage. This extra safety inventory introduces
an extra cost to the system, which consequently increases the production cost. In our project
we are targeting to reduce the manufacturing cost and consequently increasing the profit. A
WiChorus keeps safety inventory at their warehouse in case of uncertainty of demand and
supply. If simulation helps in reducing the safety inventory, it can save WiChorus or any
other firm thousands of dollars every year. We plan to provide a low cost inventory
optimization solution to manufacturing industry of USA. The main advantage in getting the
inventory optimized by using low cost inventory optimization solution is that total
manufacturing cost is reduced significantly without the change in revenue. Our potential
customers are going to be from manufacturing industry, because in-depth research shows that
California, USA has the highest market share among the manufacturing industries of USA.
We require $235,000 as initial investment and we will achieve break-even point in the end of
third quarter since the company startup. We can generate revenue of up to $414,000 by the
When the purchase orders of the productsstart arriving in an organization, it has to manage
the flow of an inventory (specially raw materials and semi-finished products) throughout its
manufacturing processes, till customer receives the finished product. If the operational
75
management has not made the methodical decision proactively about the inventory
management, then there can be many problems that can arise like increased manufacturing
cost and lower customer service level. For the manufacturing company that has a weak or
There exists an only solution to the problem of having an extra inventory, and that is the
simulation modeling. Simulation can foresee the system; with this advantage we can give
minimum input to the system to get the desired output. This reduction of the inventory save
the input cost and thus reduces the manufacturing cost. Cost is also reduced by altering the
overdesign and unwanted safety factors that were designed when system demand and supply
Very significant savings in terms of cost and time comes from the fact that simulation using
promodel allows the design engineer to make errors or mistakes on the design model rather
than in actual world. In case of WiChorus it is $104,670 per annum and lead time can be
“This principle states that the cost to correct a problem increase by a factor 10 for every
design stage through which it passes without being detected.” (Herrel et al, 2004).
76
Figure 25: Cost of making changes at subsequent stage
2009)
Figure 25 shows the increase in the cost if change occurs in subsequent stages of system.
77
Figure 26: Comparison of the cumulative system costs with and without simulation
Simulation definitely helps in many outstanding costs that can be incurred by poor decision
made in designing phase. Figure 26 show that how the simulation reduces the cumulativecost
for system design with simulation as compared to without simulation. It is possible the initial
cost with simulation is little bit higher because of initial investment (included training and
software cost) but long term cost of the capital investment is higher without simulation.
78
9.4 Market Size
ProModel is suitable for any kind of industry where the process is involved (it can be a
manufacturing or service process). But the main industry that can be beneficial by the
effective in helping to sort the complex manufacturing issues and decisions. Kochan (1986)
“The possible permutation and combination of work pieces, tools, pallets, transport
vehicles, transport routes, operations etc, etc., and their resulting performance, are
design of practical systems, and the trend toward broadening its capabilities is
continuing as systems move to encompass more and more of the factory.” (R.
Harrel, 2004)
79
US Total GDP for Top 15 States, 2007 (in
million $)
California $1,813
$1,142
New York $1,103
$735
Illinois $610
$531
Ohio $466
$465
North Carolina $399
$397
Virginia $383
$382
Massachusetts $352
$311
Maryland $269
California is biggest contribution to GDP of the US as shown in figure 27. Moreover, from
millions amongst all states,, when considering contribution to GDP by manufacturing sector.
sector
80
USA-Contribution
Contribution to GDP (in million $) by
Manufacturing Sector
Sector-2007
California $179
$153.30
Ohio $85.10
$76.60
Pennsylvania $75.20
$74
New York $66
$64.50
Indiana $62.70
$50
Wisconsin $47.70
$43.60
Tenessee $39.40
$40.80
Florida $36.60
9.5 Competitors
Since we are providing the Inventory Optimization Solution (IOS), our competitors are the
supply chain solution providers. There are many companies (as shown in table
tab 11), who
provide the inventory optimization solutions, but they provide expensive services,
services which is
not feasible for the low scale (in terms of volume) companies. Also most of them provide
web based solution which requires extra resources like data bac
backup,
kup, large memories or RAM,
internet facilities etc.. that is a limitation for many of the consumers. But our solution
provides a low cost solution with minimum required resources and it works on real time data.
81
Table 11: List of competitors and solutions provided by them.
management systems, which are designed to centralize both the purchasing and distribution
processes, and are perfect for the multi-physician practice that keeps stock on location
9.5.2 TC Logic
Since 1997, TCLogic has provided an inventory optimization solution that provides the
highest level of service at the least cost. This is accomplished through our web-based
application called, ROI+. It is through this application that our clients have achieved
inventory reductions as high as 30% while maintaining or increasing service levels above
82
9.5.3 Terra Technology
Terra Technology is the leading provider of demand sensing and inventory optimization
software for consumer goods companies. Terra's solutions incorporate demand signals from
throughout the supply chain including retailer data, reducing forecast error by up to 50
percent and inventory up to 20 percent. More accurate forecasts and inventory targets
improve customer service, lower inventory, decrease unplanned changeovers and reduce
MCA’s offerings encompass the complete range of a company’s service needs, from strategic
consulting that helps organizations evaluate their current service offerings and create a
roadmap for the future, to our industry-leading Service Planning and Optimization (SPO™)
9.5.5 Optiant
Optiant helps companies optimize their bottom-line performance by creating responsive and
resilient supply chains. As the leading provider of inventory planning and optimization
solutions, Optiant’s solutions optimally balance resources, total costs, and customer service
across the supply chain to deliver greater profitability, increase satisfaction, more efficient
use of capital and a resilient, and a resilient supply chain that fully handles uncertainty in
83
9.6 Potential Customers
Manufacturing industries are considered to be our top targeted potential customers. All
Al the
Other than manufacturing industry, in every industry there can be our customers that require
potential customers.
Since we provide a low cost solution so we can target the low scale or low budget companies,
wireless
less equipment manufacturers
manufacturers.
COMPARISON OF GDP
Manufacturing 18.60%
Finance & Insurance 12.71%
Real Estate, Rental & Leasing 9.43%
Retail Trade 6.27%
Healthcare & Social Assistance 6.18%
Wholesale Trade 5.32%
Professional Scientific & Tech. 4.93%
Construction 4.19%
Information 3.17%
Administrative & Waste Services 2.60%
0.00% 2.00% 4.00% 6.00% 8.00% 10.00% 12.00% 14.00% 16.00% 18.00% 20.00%
Figure 29
29: GDP based on industrial sector (top 10)
Source: Manufact
Manufacturing Matters, 2009
84
One of the reasons that we are targeting the manufacturing industry is that because it is the
biggest industry in USA. In USA manufacturing contributes the 18.6% of the industries
Since we are located in the Silicon Valley, our targeted customers are specialized and mass
production companies, which are situated in, bay area. WiChorus is the present customer.
9.7 Personnel
As a start company we need to hire some personnel to carry out the operations of the
company. Initially CEO will be hired who will be responsible for the formulation of whole
setup including hiring senior management of his or her choice. Senior management will
further hire the managerial staff, while keeping CEO in the loop. The organizational structure
85
CEO
VP VP
Business Sales and
Delopment Marketing
Figure 30
30: Organizational Structure
We need to hire a chief executive officer to start and run our company. CEO should have
over 15 years of technical management and sales experience in manufacturing and services
industry. System integration is a plus. Preferably he or she should be from Silicon Valley. It
is going to give added advantage due to familiarity with the companies of San Jose.
Vice president of sales and marketing will be responsible for over all sales and marketing of
our company. Multicultural experience is required for this post, as sales people should be
covering customers through out the United States. Sales and marketing team will work under
his guidance.
As we plan to expand our company to cater for design for manufacturability services to
to hire a team member with over 15 years experience at this post. He or she should have very
good relationship with the present manufacturing companies in Silicon Valley, as it will also
Company will need one system engineer who should know the complexities of
be responsible for his or her supervision. Required education will be at least Masters in
operations will be helpful in the identification of slack times in the manufacturing industry.
87
9.7.6 Quality Engineer
Black belt in quality will be required to carry out the quality assurance for our inventory
Company will need a MBA in marketing for doing the publicity and moreover to work with
VP of marketing and sales. He or she will be responsible for carrying out the marketing
closely working with VP of sales and marketing to increase the customer’s strength.
Company will also need a sales engineer. Preferably MBA in sales will be required.
Simulation design models are designed internally for the customers. These models are going
to be designed by our expert design engineers. In our company there is no manufacturing cost
occurred. We are using the simulation software ProModel that use to simulate the process to
be visualize and optimize. We charged the customers out consultancy charges and customer
service, which incur after the model is sold. We use the software ProModel that we bought
and get the license that we have to pay the yearly fees for using it. Simulation model design
88
9.8.1 Investment Capital Requirement
Capital is required in the initial stage to invest in the startup company. To keep the initial
investment to low amount, we prefer lease the building, equipments and other facilities. It is
trade-off between reducing the net profit quarterly and targeting the breakeven point much
earlier. This lease will be paid off and assets will owned when the company will financially
established.
This cost incurred periodically and remain fixed for design &development in a company.
This cost in minimumis supposed to be covered by the selling price. This cost does not vary
with the increase number of the customers or number of model design sale. Since some assets
are leased in start therefore these lease amount is also considered as fixed cost incurred to the
company. Fixed cost also includes the license fees of ProModel, which has to be paid
89
Table 13: Fixed cost for 2009 and 2010
2009 2010
Expenses Q3 Q4 Q1 Q2
Salaries
Variable cost depends on the market and sales. One of the variable cost the customer service
cost. When the model is sold to the customer it required maintenance and revision of the
model as per customer requirement. Other variable cost is the part time employee salaries,
which will require if the demand is higher than the current capacity of the company or there
is a need of specialist engineer. Table 14 shows the list of variable cost per quarter.
90
Table 14: Variable Cost per Quarter
Expenses Cost
Consultancy $3,000
Total $9,500
We are offering an inventory optimization solution to the customers. For the optimization
existing process has to be analyzed, visualize and optimize to get the desired cost efficient
results. For optimization purpose simulation model have to be design with current scenario
and optimize. We sell this model and solution to the customers. The price of this service
depends upon the total cost incurred to the company and also influenced by the market
values. Using the total cost analysis and market analysis we plan to charge our simulation
model price as $30,000, which is a one-time cost, and also the customer service as $8,000 per
quarter. Targeted customers will be willing to this investment since these optimization
solutions can save them up to $100,000 per annum and improve relationships with their
customers. Customer service charges include the maintenance and upgrade of the model as
per customer requirements and also providing the detailed result analysis of the simulation
output. In company policy, minimum duration of the customer service is 2 quarter, which can
91
Initially the target companies are small size and size companies but with the time when the
business gets in better shape the target will be the large size company. This will also affect
the service charges because big scale companies have large inventory process and they can
be charge more than the fixed service charges, as it requires more work and analyzing.
Total income will be depends on the number of target achieved, which is expected to be low
in initial stages. By using the marketing strategies business will increase eventually and more
Once the services and model has been sold it requires maintenance and updating of the model
when the customer alter it process. This customer service charge will be applied from the
same quarter. The duration of the service charges depends on the customers. In cost analysis
we fixed the duration to the 2 quarters as per out policy, which is a minimum duration. Total
Expected Customers 3 4 6 7 9 9
Simulation Model Price 30000 30000 30000 30000 30000 30000
per Customer
Customer Service 8000 8000 8000 8000 8000 8000
charges per customer
Total Customer charges 24000 56000 80000 104000 128000 144000
Total Revenue 114000 183000 260000 314000 398000 414000
92
Customers are expected to increase from 2009 to 2010, which will eventually increase the
revenue. Total customers service charges vary depend on the number of customers.
Total Revenue
500 $398 $414
Revenue (x1000 $)
400 $314
$260
300
$183
200 $114
100
0
Q3 '09 Q4 '09 Q1 '10 Q2 '10 Q3 '10 Q4 '10
Time
Profit and loss analysis shows the comparison of the revenue and profit for different quarters.
Forecast has been done to find out the expected number of customers in the next six quarters.
Profit and loss diagram also determine the breakeven point of the company. Following
This cost remains fixed and does not vary with the number of customer.
This cost related to the customer and varies with number of customers. It is equal to multiple
9.11.7 Profit/Loss
Following table shows the profit and loss analysis from the total cost and revenue.
94
Table 16: Profit and Loss value for Q3(2009) to Q4(2010)
Figure 32 shows the P&L diagram showing the profit and loss as depending on the forecasted
number of customers. From profit and loss analysis it has been found that we required
$235,000 as an initial investment. This investment will be used in covering the fixed costs
and some part of it will be in vested in customer service cost, depending on the numbers of
95
Profit and Loss
$500,000
$400,000
$300,000
Fixed Cost
Total Variable Cost
$200,000
Total Cost
$100,000 Total Rvenue
Profit/Loss
$0
Q3(2009) Q4(2009) Q1(2010) Q2(2010) Q3(2010) Q4(2010)
-$100,000
-$200,000
Figure 32
32: Profit and loss Diagram
Breakeven point is the point at which company starts to recover the invested cost and
generates the profit. Breakeven point is an important factor for the investors to attract
towards
rds the project. It provides the information that after at quarter certain company starts to
generate profit. Figure 33 shows that in the end of 3rd quarter company achieve its breakeven
96
Break-Even
450000
400000
350000
300000
Dollars
250000
Total Cost
200000
Total Rvenue
150000
100000
50000
0
Q3(2009) Q4(2009) Q1(2010) Q2(2010) Q3(2010) Q4(2010)
Figure 33
33: Break-Even Analysis Graph
9.13 Norden-Rayleigh
Rayleigh Graph
of the project with respect to time. It is calculated by the following probability density
function formula:
V(t) = 2adtexp(-at2)
t ; time
97
Table 17: Norden-Rayleigh Cost Analysis
t d a e(-at2) v(t)=2adtexp(-at2)
0 258000 0.1 1 0.0000
Keeping value of “a” to low level because of having consideration of startup company. It is
designed to have a low investment cost and low risk. Figure shows the Norden-Rayleigh
graph.
98
Norden-Rayleigh Graph
80000
70000
Dollars ($) 60000
50000
40000
30000
20000
10000
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Time (t)
Cumulative Expenditure
200000
180000
160000
140000
Dollars ($)
120000
100000
80000
60000
40000
20000
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Time (t)
99
9.14 SWOT Assessment
STRENGTH WEAKNESS
OPPORTUNITIES THREATS
There is always a chance of recession, whichcan force the consumers to not to go towards
our opportunity. We have few exit strategies in case of some unfortunate’s scenario:
2. Selling the models to the competitors that can recover the asset values.
3. We can also switch to service provider companies other than manufacturing industries.
100
In case if the software cost is increases, we have the following strategies like,
2. We can switch to the more affordable optimization software. There are many others
a. Arena Simulation
Project schedule describes the sequences and duration of the task that we assigned in the start
of the project. All the tasks have been completed in accordance to the schedule. Figure 30
shows the Gantt chart for our project, which is the graphical presentation of the project
schedule.
101
Figure 36: Project Schedule
102
11. Team and Committee Members
Farhan holds a BE degree in Aerospace. He has about seven and half years of experience in
fighter aircraft maintenance and operations. These aircraft include MFI-17, T-37, K-8, F-7,
and Mirage. He also possesses an experience of various structural and avionics modifications
on these aircraft. He has also worked for about two years in an IT company as general
manager operations. He has accomplished various wireless networking projects during this
He was responsible for the optimization of structural framework for the inventory
management process of WiChorus Inc. Moreover he also looked after the WiChorus
transportations strategy, and pricing structure of the process. He has also worked with
Muhammad Jawwad Siddiqui has about 1 year of industrial work experience. He has worked
Automation engineer on several project and also has an experience as a project engineer in
PARCO (Oil and Gas Company). He has done his undergraduate in Electronics Engineering.
103
He was responsible for analyzing the past and current data for the supply chain, formulation
of the data; analyze the inputs to simulation to optimize the inventory management procedure
chief architect of WiMAX for Aperto Networks and played diverse leadership roles in
Dr. Dorosti was the Director of MSE Programs, College of Engineering at San Jose State
University where he also teaches engineering courses in the MSE program. Jim has extensive
experience with Fortune 500 and start-up businesses in the semiconductor industry, and a
unique record in managing both technical organizations as well as Corporate Total Quality
12. Conclusion
Optimization of the inventory management of WiChorus Inc. was successfully carried out
with the help of simulation modeling. Lead-time and production cost (inventory carrying and
buying cost based on quantity) was reduced significantly with the proposed model. Total
capacity to manufacture products was also calculated which will be helpful in the future
expansion program of the company. The saved cost can be effectively used in the research
104
and development programs of the company. Reduced lead-time will be helpful in competing
the competitors of WiChorus, because time to satisfy customers demand and time to market
is reduced. Moreover, simulation helps to foresee the future and let the designer to analyze
and design the process. Simulation nullifies the risk of change in process design, which
WiChorus can be reduced by 26% for higher service level and quick product availability in
market.We will reach break-even point for our proposed company quickly by the end of 3rd
105
13. References
McIvor, Ronan (2001). Lean supply: the design and cost reduction dimensions. European
Vonderembse, M A., Uppal, M., Huang, S H. and Dismukes, J P. (2002). Designing supply
Agarwal A., Shankar, R. and Tiwari, M.K. (2005). Modeling the metrics of lean, agile and
Sarimveis, H., Patrinos, P., Tarantilis, C.D. and Kiranoudis, C.T. (2007). Dynamic modeling
Holweg, M. and Bicheno, J. (2002). Supply chain simulation: a tool for education,
(2002), 163-175.
Chopra S., Meindl P. & Kalra, D.V. (2007). Supply chain management: strategy, planning
Harrell, C.R., Ghosh, B.K. & Bowden, R.O. (2004). Simulation using promodel. McGraw
Hill.
Angulo, A., Natchmann, H. & Waller, M.A. (2004). Supply chain information sharing in a
101-120.
Kurawarwala, A.A. & Matsuo, H. (1996). Forecasting & inventory management of short life-
Cousins, P.D. & Menguc B. (2005). The implication of socialization and integration in
Chandra, C., Grabis, J. & Tumayan, A. (2006). Problem taxonomy: a step towards effective
Bullington, K.E. & Bullington S.F. (2005). Stronger supply chain relationships: Learning
107
Ballou, R.H. (2004). Business logistics/supply chain management. Pearson Prentice Hall.
Silver, E.A., Pyke, D.F. & Peterson, R. (1998). Inventory Management and Production
Storey, J. & Emberson, C. (2006). Supply chain management: theory, practice and future
(2006), 754-774.
Janiga, D. (2005, June). Five keys to effective inventory management. Plant Engineering
Monthly, 36-37.
http://www.wichorus.com/page/311
Lambert, D. M., Garcia-Datugue, S. J., & Croxton, K. L. (2008). The role of logistics
www.mun.ca
Charles R. Harrell, Kevin C. Field (2001). Simulation Modeling and Optimization Using
108
Risk. Retrieved February 19, 2009, from Wikipedia. http://en.wikipedia.org/wiki/Risk
Knight, Frank H. (1921). Risk, Uncertainty, and Profit. Boston, MA: Hart, Schaffner &
Six Sigma - What is Six Sigma? (2000) retrieved on 3 February, 2009, from
http://www.isixsigma.com/sixsigma/six_sigma.asp
Deborah Benson (1997), Simulation Modeling and Optimization Using Promode. IEEE
(2008). Using ProModel as a simulation tools to assist plant layout design and
http://www.ies.ncsu.edu/ncmanufacturing/
http://www.henryschein.com/us-en/medical/services/IOS.aspx
http://www.terratechnology.com/en/about/index.php
http://www.mcasolutions.com/section/company/default.aspx
110
14. Appendices
--------------------------------------------------------------------------------
General Report
--------------------------------------------------------------------------------
Replication : Average
Simulation Time : 49 hr
--------------------------------------------------------------------------------
LOCATIONS
Average
111
Location Scheduled Total Minutes Average Maximum Current
Name Hours Capacity Entries Per Entry Contents Contents Contents % Util
112
PCB Assmb 49 1 20 120.44 0.81 1 0 81.93 (95% C.I.
Low)
114
Manf Assmb Q 49 999999 20 1150.15 7.82 20 0 0.0
(Average)
115
Testing Prod Q 49 999999 14.87 0.0 0 1 0 0.0 (95% C.I.
Low)
116
Prod Confg Q 49 999999 0 0.0 0 0 0 0.0 (Average)
117
Warehouse Q 49 999999 15 1640.79 8.37 15 0 0.0 (95% C.I.
High)
118
Bezel Q 0 0 0 12.41 0.12 0 0 0.0 (Std. Dev.)
% |
119
Manf Assmb Q 49 21.73 78.27 0.0 | 0.0 (Average)
120
Warehouse Assmb Q 49 100.00 0.0 0.0 | 0.0 (Average)
122
Filler Q 0 0.02 0.02 0.0 | 0.0 (Std. Dev.)
Location Scheduled % % % % % %
123
Warehouse Wi 0 0.0 0.0 0.0 0.0 0.0 0.0 (Std. Dev.)
Warehouse Wi 49 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
Warehouse Wi 49 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
PCB Manf 0 0.0 0.0 0.0 0.0 0.0 0.0 (Std. Dev.)
PCB Manf 49 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
PCB Manf 49 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
PCB Assmb 0 0.53 0.0 0.53 0.0 0.0 0.0 (Std. Dev.)
PCB Assmb 49 81.93 0.0 17.31 0.0 0.0 0.0 (95% C.I. Low)
PCB Assmb 49 82.69 0.0 18.07 0.0 0.0 0.0 (95% C.I. High)
PCB Testing 0 0.14 0.0 0.14 0.0 0.0 0.0 (Std. Dev.)
124
PCB Testing 49 95.82 0.0 3.98 0.0 0.0 0.0 (95% C.I. Low)
PCB Testing 49 96.02 0.0 4.18 0.0 0.0 0.0 (95% C.I. High)
Configuration Wi 49 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
Configuration Wi 49 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
QA Dept 49 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
QA Dept 49 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
Prod Dept Wi 0 0.83 0.0 0.83 0.0 0.0 0.0 (Std. Dev.)
125
Prod Dept Wi 49 30.74 0.0 68.07 0.0 0.0 0.0 (95% C.I. Low)
Prod Dept Wi 49 31.93 0.0 69.26 0.0 0.0 0.0 (95% C.I. High)
FAILED ARRIVALS
126
Network Board Manf Assmb Q 0 (Average)
127
Service Card Filler Q 0 (Average)
ENTITY ACTIVITY
128
Name Exits In System System Logic Res, etc. Operation Blocked
Final Board 15 0 1606.86 0.0 979.37 360.27 265.29 (95% C.I. Low)
Final Board 15 0 1641.55 0.0 1008.03 364.43 271.00 (95% C.I. High)
PCB 0 0 - - - - - (Average)
130
Service Card 15 25 1624.01 0.0 1432.09 0.0 191.91 (Average)
Service Card 15 25 1606.70 0.0 1416.10 0.0 190.40 (95% C.I. Low)
Service Card 15 25 1641.31 0.0 1448.09 0.0 193.42 (95% C.I. High)
Final Product 15 0 1606.94 0.0 1606.94 0.0 0.0 (95% C.I. Low)
Final Product 15 0 1641.81 0.0 1641.81 0.0 0.0 (95% C.I. High)
131
ENTITY STATES BY PERCENTAGE
% %
132
PCB - - - - (Average)
133
Bezels 0.0 88.18 0.0 11.82 (Average)
134
VARIABLES
Average
Chips Assmb time 20 114.36 0 128.26 115.04 120.29 (95% C.I. Low)
Chips Assmb time 20 115.80 0 132.30 122.82 121.28 (95% C.I. High)
135
PCB Testing time 16.1 176.16 0 133.27 119.34 115.02 (Average)
PCB Testing time 0.31 2.04 0 2.83 10.37 1.89 (Std. Dev.)
PCB Testing time 15.87 174.70 0 131.25 111.92 113.66 (95% C.I. Low)
PCB Testing time 16.32 177.62 0 135.30 126.76 116.38 (95% C.I. High)
Chasis assmb time 0.31 2.33 0 0.85 2.17 0.43 (Std. Dev.)
Chasis assmb time 14.87 186.17 0 18.17 12.99 13.38 (95% C.I. Low)
Chasis assmb time 15.32 189.50 0 19.40 16.10 14.01 (95% C.I. High)
Filler Assmb time 15 187.28 0 3.90 0.65 1.38 (95% C.I. Low)
Filler Assmb time 15 190.38 0 9.39 3.28 2.32 (95% C.I. High)
136
Pcb Faceplate time 15 188.96 0 6.11 2.49 1.78 (Average)
Pcb Faceplate time 15 187.42 0 4.32 1.15 1.46 (95% C.I. Low)
Pcb Faceplate time 15 190.51 0 7.90 3.83 2.11 (95% C.I. High)
Final Assmb Testing Time 0 2.15 0 2.42 1.20 0.44 (Std. Dev.)
Final Assmb Testing Time 15 187.58 0 6.18 1.08 1.67 (95% C.I. Low)
Final Assmb Testing Time 15 190.67 0 9.65 2.81 2.30 (95% C.I. High)
Installing Network Board 15 187.75 0 43.59 38.35 34.87 (95% C.I. Low)
Installing Network Board 15 190.77 0 46.56 42.95 35.91 (95% C.I. High)
PCB Configuration 15.12 181.93 0 66.87 55.65 54.52 (95% C.I. Low)
PCB Configuration 15.87 185.40 0 71.53 63.14 56.06 (95% C.I. High)
138
14.2 Appendix ‘A2’ Optimized Time Model Output
--------------------------------------------------------------------------------
General Report
--------------------------------------------------------------------------------
Replication : Average
Simulation Time : 36 hr
--------------------------------------------------------------------------------
139
LOCATIONS
Average
Name Hours Capacity Entries Per Entry Contents Contents Contents % Util
141
PCB Testing 0 0 0.51 4.90 0.01 0 0.51 0.98 (Std. Dev.)
142
QA Dept 0 0 0 0.0 0 0 0 0.0 (Std. Dev.)
143
Des Manf Q 0 0 0 0.0 0 0 0 0.0 (Std. Dev.)
144
Assmb Testing Q 36 999999 17.6 0.0 0 1 0 0.0 (Average)
145
Warehouse Assmb Q 36 999999 0 0.0 0 0 0 0.0 (Average)
146
Warehouse Prod Q 36 999999 15 1212.38 8.41 15 0 0.0 (95%
C.I. High)
147
Confg QA Q 36 999999 0 0.0 0 0 0 0.0 (95% C.I.
High)
148
Chips Q 36 999999 20 1435.64 13.29 20 5 0.0 (95% C.I.
Low)
149
Bezel Q 0 0 0 6.67 0.09 0 0 0.0 (Std. Dev.)
% |
150
PCB Testing 36 5.56 46.30 45.19 | 0.0 (95% C.I. Low)
151
Manf Assmb Q 36 0.01 99.94 0.0 | 0.0 (95% C.I. Low)
153
Warehouse Prod Q 36 6.46 95.24 0.0 | 0.0 (95% C.I. High)
156
LOCATION STATES BY PERCENTAGE (Single Capacity/Tanks)
Location Scheduled % % % % % %
Warehouse Wi 36 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
Warehouse Wi 36 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
PCB Manf 0 0.0 0.0 0.0 0.0 0.0 0.0 (Std. Dev.)
157
PCB Manf 36 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
PCB Manf 36 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
PCB Assmb 0 0.03 0.0 0.03 0.0 0.0 0.0 (Std. Dev.)
PCB Assmb 36 99.94 0.0 0.02 0.0 0.0 0.0 (95% C.I. Low)
PCB Assmb 36 99.98 0.0 0.06 0.0 0.0 0.0 (95% C.I. High)
158
Configuration Wi 36 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
Configuration Wi 36 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
QA Dept 36 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
QA Dept 36 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
Prod Dept Wi 0 1.16 0.0 1.65 0.72 0.0 0.0 (Std. Dev.)
Prod Dept Wi 36 44.03 0.0 53.39 0.06 0.0 0.0 (95% C.I. Low)
159
Prod Dept Wi 36 45.68 0.0 55.75 1.09 0.0 0.0 (95% C.I. High)
FAILED ARRIVALS
160
Network Board Manf Assmb Q 0 (Average)
162
Final Product Warehouse Prod Q 0 (Std. Dev.)
ENTITY ACTIVITY
163
Final Board 15 0 1203.69 0.0 728.32 363.30 112.06 (Average)
Final Board 15 0 1195.00 0.0 721.62 361.31 111.16 (95% C.I. Low)
Final Board 15 0 1212.37 0.0 735.02 365.29 112.96 (95% C.I. High)
PCB 0 0 - - - - - (Average)
164
PCB 0 0 - - - - - (Std. Dev.)
165
Chasis 0 0 12.64 0.0 11.30 0.0 1.70 (Std. Dev.)
Service Card 15 25 1212.89 0.0 1075.98 0.0 137.16 (95% C.I. High)
Final Product 15 0 1194.62 0.0 1194.62 0.0 0.0 (95% C.I. Low)
Final Product 15 0 1212.38 0.0 1212.38 0.0 0.0 (95% C.I. High)
167
ENTITY STATES BY PERCENTAGE
% %
168
Chips 0.0 88.71 0.0 11.29 (Average)
PCB - - - - (Average)
169
Network Board - - - - (Average)
171
Final Product 0.0 0.0 0.0 0.0 (Std. Dev.)
VARIABLES
Average
Chips Assmb time 0.51 1.15 0 3.04 3.79 1.40 (Std. Dev.)
Chips Assmb time 18.23 112.61 0 125.77 117.81 119.01 (95% C.I. Low)
Chips Assmb time 18.96 114.27 0 130.12 123.25 121.02 (95% C.I. High)
PCB Testing time 0.51 1.38 0 3.46 7.38 1.02 (Std. Dev.)
PCB Testing time 17.23 118.90 0 131.31 113.57 113.36 (95% C.I. Low)
173
PCB Testing time 17.96 120.88 0 136.26 124.14 114.83 (95% C.I. High)
Chasis assmb time 16 129.92 0 18.09 13.80 12.66 (95% C.I. Low)
Chasis assmb time 16 132.25 0 19.52 15.38 13.06 (95% C.I. High)
Filler Assmb time 16 130.81 0 6.21 0.94 1.74 (95% C.I. Low)
Filler Assmb time 16 133.18 0 7.97 3.12 2.38 (95% C.I. High)
174
Pcb Faceplate time 16 132.12 0 7.78 2.53 1.81 (Average)
Pcb Faceplate time 16 130.93 0 5.77 1.01 1.51 (95% C.I. Low)
Pcb Faceplate time 16 133.32 0 9.78 4.06 2.12 (95% C.I. High)
Final Assmb Testing Time 0 1.64 0 2.86 0.67 0.60 (Std. Dev.)
Final Assmb Testing Time 16 131.11 0 3.56 0.58 1.05 (95% C.I. Low)
Final Assmb Testing Time 16 133.46 0 7.66 1.54 1.91 (95% C.I. High)
175
configuration time 0 0.0 0 0 0 0 (Average)
176
Installing Network Board 16 132.35 0 44.55 40.52 33.94 (Average)
Installing Network Board 16 131.16 0 43.76 38.81 33.34 (95% C.I. Low)
Installing Network Board 16 133.54 0 45.34 42.22 34.55 (95% C.I. High)
PCB Configuration 16.03 126.00 0 67.67 57.78 53.27 (95% C.I. Low)
PCB Configuration 16.76 128.37 0 72.12 65.27 54.98 (95% C.I. High)
177
14.3 Appendix ‘A3’ Maximum Capacity Model Output
--------------------------------------------------------------------------------
General Report
--------------------------------------------------------------------------------
Replication : Average
--------------------------------------------------------------------------------
178
LOCATIONS
Average
Name Hours Capacity Entries Per Entry Contents Contents Contents % Util
180
PCB Testing 168 2 33 179.18 0.58 1 0.6 29.33 (Average)
181
QA Dept 168 1 0 0.0 0 0 0 0.0 (Average)
Prod Dept Wi 168 1 32.03 60.03 0.19 1 0.03 19.38 (95% C.I.
Low)
Prod Dept Wi 168 1 32.76 61.79 0.19 1 0.76 19.77 (95% C.I.
High)
182
Des Manf Q 168 999999 0 0.0 0 0 0 0.0 (Average)
183
Assmb Testing Q 168 999999 33 0.0 0 1 0 0.0 (Average)
184
Testing Prod Q 168 999999 32.76 0.0 0 1 0 0.0 (95% C.I.
High)
185
Warehouse Prod Q 168 999999 81 8146.02 65.45 81 49 0.01 (95%
C.I. Low)
186
Confg QA Q 0 0 0 0.0 0 0 0 0.0 (Std. Dev.)
187
Chips Q 168 999999 81 8153.24 65.51 81 49 0.01 (Average)
Filler Q 168 999999 165 8180.84 133.91 165 101 0.01 (95%
C.I. Low)
188
Filler Q 168 999999 165 8195.32 134.15 165 101 0.01 (95%
C.I. High)
189
LOCATION STATES BY PERCENTAGE (Multiple Capacity)
% |
PCB Testing 168 41.01 58.33 0.0 | 0.0 (95% C.I. Low)
PCB Testing 168 41.67 58.99 0.0 | 0.0 (95% C.I. High)
Des Manf Q 168 100.00 0.0 0.0 | 0.0 (95% C.I. Low)
Des Manf Q 168 100.00 0.0 0.0 | 0.0 (95% C.I. High)
Manf Assmb Q 168 0.0 99.99 0.0 | 0.0 (95% C.I. Low)
Manf Assmb Q 168 0.01 100.00 0.0 | 0.0 (95% C.I. High)
191
Assmb Testing Q 0 0.0 0.0 0.0 | 0.0 (Std. Dev.)
Assmb Testing Q 168 100.00 0.0 0.0 | 0.0 (95% C.I. Low)
Assmb Testing Q 168 100.00 0.0 0.0 | 0.0 (95% C.I. High)
Testing Prod Q 168 100.00 0.0 0.0 | 0.0 (95% C.I. Low)
Testing Prod Q 168 100.00 0.0 0.0 | 0.0 (95% C.I. High)
Warehouse Assmb Q 168 100.00 0.0 0.0 | 0.0 (95% C.I. High)
Warehouse Prod Q 168 0.0 99.99 0.0 | 0.0 (95% C.I. Low)
Warehouse Prod Q 168 0.01 100.00 0.0 | 0.0 (95% C.I. High)
193
Prod Confg Q 168 100.00 0.0 0.0 | 0.0 (95% C.I. Low)
Prod Confg Q 168 100.00 0.0 0.0 | 0.0 (95% C.I. High)
195
Filler Q 168 0.02 100.00 0.0 | 0.0 (95% C.I. High)
Location Scheduled % % % % % %
Warehouse Wi 168 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
Warehouse Wi 168 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
PCB Manf 168 0.0 0.0 100.00 0.0 0.0 0.0 (Average)
PCB Manf 0 0.0 0.0 0.0 0.0 0.0 0.0 (Std. Dev.)
PCB Manf 168 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
PCB Manf 168 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
PCB Assmb 168 100.00 0.0 0.0 0.0 0.0 0.0 (Average)
197
PCB Assmb 0 0.01 0.0 0.01 0.0 0.0 0.0 (Std. Dev.)
PCB Assmb 168 99.99 0.0 0.0 0.0 0.0 0.0 (95% C.I. Low)
PCB Assmb 168 100.00 0.0 0.01 0.0 0.0 0.0 (95% C.I. High)
Configuration Wi 168 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. Low)
Configuration Wi 168 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
QA Dept 168 0.0 0.0 100.00 0.0 0.0 0.0 (95% C.I. High)
Prod Dept Wi 168 19.58 0.0 80.42 0.0 0.0 0.0 (Average)
Prod Dept Wi 0 0.27 0.0 0.27 0.0 0.0 0.0 (Std. Dev.)
Prod Dept Wi 168 19.38 0.0 80.23 0.0 0.0 0.0 (95% C.I. Low)
Prod Dept Wi 168 19.77 0.0 80.62 0.0 0.0 0.0 (95% C.I. High)
199
FAILED ARRIVALS
201
Bezels Bezel Q 0 (95% C.I. Low)
ENTITY ACTIVITY
Final Board 32 0 5186.65 0.0 4355.53 540.14 290.28 (95% C.I. Low)
203
Final Board 32 0 5222.21 0.0 4386.33 544.27 292.30 (95% C.I. High)
Service Card 64 101 5185.74 0.0 5032.14 0.0 153.48 (95% C.I. Low)
Service Card 64 101 5222.33 0.0 5067.78 0.0 154.66 (95% C.I. High)
Final Product 32 49 5186.03 0.0 5186.03 0.0 0.0 (95% C.I. Low)
Final Product 32 49 5222.53 0.0 5222.53 0.0 0.0 (95% C.I. High)
206
ENTITY STATES BY PERCENTAGE
% %
208
Chassis 0.0 0.02 0.0 0.02 (Std. Dev.)
VARIABLES
Average
210
Name Changes Per Change Value Value Value Value
Chips Assmb time 34 290.76 0 321.18 286.60 299.82 (95% C.I. Low)
Chips Assmb time 34 292.76 0 326.88 298.04 301.78 (95% C.I. High)
211
PCB Testing time 33 300.60 0 133.80 118.52 117.05 (Average)
PCB Testing time 33 299.57 0 131.40 112.30 116.32 (95% C.I. Low)
PCB Testing time 33 301.63 0 136.20 124.75 117.77 (95% C.I. High)
Chassis assmb time 0.51 1.68 0 0.61 2.27 0.36 (Std. Dev.)
Chassis assmb time 32.03 304.95 0 18.43 13.23 14.04 (95% C.I. Low)
Chassis assmb time 32.76 307.37 0 19.31 16.49 14.56 (95% C.I. High)
212
Filler Assmb time 32.3 306.74 0 8.11 1.12 1.89 (Average)
Filler Assmb time 0.48 1.62 0 2.60 0.99 0.34 (Std. Dev.)
Filler Assmb time 31.95 305.57 0 6.25 0.41 1.65 (95% C.I. Low)
Filler Assmb time 32.64 307.90 0 9.98 1.83 2.14 (95% C.I. High)
Pcb Faceplate time 0.42 1.58 0 2.09 1.96 0.33 (Std. Dev.)
Pcb Faceplate time 31.89 305.72 0 6.47 1.09 1.74 (95% C.I. Low)
Pcb Faceplate time 32.50 307.99 0 9.47 3.90 2.22 (95% C.I. High)
213
Final Assmb Testing Time 32.2 306.93 0 9.00 1.99 2.01 (Average)
Final Assmb Testing Time 0.42 1.58 0 2.28 2.44 0.36 (Std. Dev.)
Final Assmb Testing Time 31.89 305.80 0 7.37 0.25 1.75 (95% C.I. Low)
Final Assmb Testing Time 32.50 308.06 0 10.63 3.74 2.27 (95% C.I. High)
214
QA time 0 0.0 0 0 0 0 (Average)
Installing Network Board 0.42 1.57 0 1.02 3.18 0.60 (Std. Dev.)
Installing Network Board 31.89 305.87 0 45.38 37.67 37.65 (95% C.I. Low)
Installing Network Board 32.50 308.12 0 46.85 42.23 38.52 (95% C.I. High)
PCB Configuration 32.49 303.20 0 67.78 56.39 56.27 (95% C.I. Low)
PCB Configuration 33.10 305.43 0 70.82 60.52 57.62 (95% C.I. High)
216