Académique Documents
Professionnel Documents
Culture Documents
DETAILED ESTIMATE
Item No. I
Reinforced Concrete(Additional of Column)
I. Direct Cost
Qty. Unit Unit Cost (Php) Total Cost (Php)
Materials
1) Portland Cement 9 bags 280.00 2,520.00
2) Sand 0.5 cu.m. 900.00 450.00
3) Gravel 1 cu.m. 1,000.00 1,000.00
4) 16 mm. dia. R.S.B. 8 pcs. 410.00 3,280.00
5) 10 mm. dia. R.S.B. 10 pcs. 160.00 1,600.00
6) 1/4" M. Plywood 4 pcs. 500.00 2,000.00
7) Coco Lumber 2x2x16 27 pcs. 70.00 1,890.00
8) Coco Lumber 2x3x16 13 pcs. 105.00 1,365.00
9) Ga. # 16 Tie Wire ###
2 kls. 65.00 130.00
10) CW Nails (assorted sizes) 9.5 kls. 60.00 570.00
Total Materials . . . . . 14,805.00
Prepared by:
CRISPOLO P. TEJERERO
Engineer II
Item No. V
Roofing (Steel Beam & Girts)
I. Direct Cost
Qty. Unit Unit Cost (Php) Total Cost (Php)
Materials
1) 1/4"x1 1/2" Angle Bar 20 pcs. 850.00 17,000.00
2) 1/4"x1 " Angle Bar 18 pcs. 650.00 11,700.00
3) Welding Rod 10 kls. 125.00 1,250.00
Total Materials . . . . . 29,950.00
SUMMARY
Amount
Prepared by:
CRISPOLO P. TEJERERO
Engineer II
DETAILED ESTIMATE
Item No. I
Roofing
I. Direct Cost
Qty. Unit Unit Cost (Php) Total Cost (Php)
Materials
1) 0.50mm G.I. Corrugated Sheet 12 ft. 26 pcs. 1,075.00 27,950.00
2) 0.40 mm. Plain G.I. Shts. 6 pcs. 375.00 2,250.00
2) 1/2 thk. M. Plywood 4 pcs. 1,000.00 4,000.00
3) 2" Textscrew 700 pcs. 2.00 1,400.00
4) 0.50 mm x2x3 C-Purlins 15 pcs. 750.00 11,250.00
5) Welding Rod 4 kls. 125.00 500.00
6) Primer Paint (red oxide) 5 gals. 530.00 2,650.00
Total Materials . . . . . 50,000.00
SUMMARY
Amount
Prepared by:
CRISPOLO P. TEJERERO
Engineer II
Item No. III
Masonry Work
I. Direct Cost
Qty. Unit Unit Cost (Php) Total Cost (Php)
Materials
1) Portland Cement 15 bags 275.00 4,125.00
2) Sand 2 cu.m. 900.00 1,800.00
3) 4" CHB 260 pcs. 15.00 3,900.00
4) 10 mm. dia. R.S.B. 15 pcs. 150.00 2,250.00
5) Ga. # 16 Tie Wire 2 kls. 65.00 130.00
Total Materials . . . . . 12,205.00
Item No. II
Reinforced Concrete
I. Direct Cost
Qty. Unit Unit Cost (Php) Total Cost (Php)
Materials
1) Portland Cement 25 bags 260.00 6,500.00
2) Sand 2 cu.m. 800.00 1,600.00
3) Gravel 4 cu.m. 900.00 3,600.00
4) 10 mm. dia. R.S.B. 20 pcs. 140.00 2,800.00
9) Coco Lumber 2x4x16 5 pcs. 120.00 600.00
10) Ga. # 16 Tie Wire 3 kls. 65.00 195.00
11) CW Nails (assorted sizes) 1 kl. 60.00 60.00
Total Materials . . . . . 15,355.00
Item No. III
Masonry Work(w/out plastering)
I. Direct Cost
Qty. Unit Unit Cost (Php) Total Cost (Php)
Materials
1) Portland Cement 48 bags 275.00 13,200.00
2) Sand 4 cu.m. 900.00 3,600.00
3) 4" CHB 850 pcs. 14.00 11,900.00
4) 10 mm. dia. R.S.B. 40 pcs. 140.00 5,600.00
5) Ga. # 16 Tie Wire 5 kls. 65.00 325.00
Total Materials . . . . . 34,625.00
collected #REF!
Remaining #REF!
SOP 15% 7,500.00
Balance(labor) #REF!
Item No. V
Roofing
I. Direct Cost
Qty. Unit Unit Cost (Php) Total Cost (Php)
Materials
1) 0.40mm G.I. Corrugated Sheet 12 ft. 26 pcs. 432.00 11,232.00
2) 0.40 mm. Ridge Roll 11 pcs. 275.00 3,025.00
3) 2" Textscrew 850 pcs. 2.00 1,700.00
4) 1/4"x1 1/2" Angle Bar 38 pcs. 597.00 22,686.00
5) 0.40 mm x2x3 C-Purlins 18 pcs. 435.00 7,830.00
6) Welding Rod 15 kls. 80.00 1,200.00
7) 1/4"x1" Flat Bar 8 pcs. 250.00 2,000.00
8) Primer Paint (red oxide) 6 gals. 300.00 1,800.00
Total Materials . . . . . 51,473.00
Labor No. Rate/Day Period
1) Const. Foreman 1 400.00 6 days at 2,400.00
2) Masons 2 350.00 6 days at PHP 4,200.00
3) Laborers 6 250.00 6 days at 9,000.00
Total labor . . . . . . . . . PHP 15,600.00
Item No. I
Basketball Board
I. Direct Cost
Prepared by:
CRISPOLO P. TEJERERO
Engineer II
CONSTRUCTION OF BEDEGA
% weight Amount
I. Direct Cost
Material Cost : #REF! #REF!
Labor Cost: #REF! #REF!
Equiptment Rental #REF! 0.00
II. Indirect Cost
Contingencies #REF! #REF!
Profit #REF! #REF!
City Tax #REF! #REF!
VAT #REF! #REF!
#REF! #REF!
Prepared by:
CRISPOLO P. TEJERERO
Engineer I
0.92
3.11 10 31.10
5.3
5.75 10 57.50
6.2
6.60 10 66.00
7
5.58 10 55.75
4.15
4.90 10 49.00
5.65
5.08 10 50.75
4.5
5.35 10 53.50
6.2
7.18 10 71.75
8.15 435.35 535.4805
Republic of the Philippines
OFFICE OF THE CITY ENGINEER
Calbayog City
#REF!
ESTIMATED COST OF PROPOSED WORK
DIRECT COST
ITEM NO. DESCRIPTION QUANTITY UNIT ADJ. UNIT COST
TOTAL UNIT COST
I Excavation/Chipping of Concrete 1.00 L.S #REF! #REF!
Removal of ExistingStructure
II Reinforced Concrete 0.89 CU.M. 14,805.00 16,672.30
III Masonry Works #REF! SQ.M. #REF! #REF!
IV Embankment #REF! CU.M. #REF! #REF!
V Roofing 44.40 SQ.M. 50,000.00 1,126.13
Spc'l I Handling Cost 1.00 L.S. #REF! #REF!
TOTAL---- #REF!
Date: __________
Date: __________
RAFAELITO F. SERRANO
Asst. City Engineer
Brgy. Captain