Vous êtes sur la page 1sur 5

Process oriented measurements and improvements

- An analysis of the OFCE-process at Tetra Pak BU DBF


Ingemar Edman & Alejandro Lisson
July 2009

Department of Industrial Management and Engineering


Faculty of Engineering, Lund University
Box 118
SE‐221 00 Lund, Sweden

This article is based on the results of a master thesis carried out at Tetra Pak Business Unit Dairy
Beverage and Prepared food (BU DBF) during the spring of 2009. It aims to briefly present the case, the
methodology and theoretical framework, the findings and finally some conclusions. The main themes of
the thesis as well as the article are process improvements and performance measurements.

1. INTRODUCTION 2. PURPOSE AND OBJECTIVES OF THE


During the last decades markets have become STUDY
increasingly competitive due to globalization. As The study is constituted by a critical analysis of
the number of products available has increased, the OFCE-process as well as of its measurement
so have the customer expectations in respect to system, focusing on identifying improvement
quality, service and price. Companies have thus areas. The process in Lund is going to be used
been forced to become process oriented in as benchmark for Tetra Pak‟s plants in
order to increase efficiency and effectiveness to Greenwood, USA and Shanghai, China and
provide more value to the customer. An thus it is important that first identify and
important step in achieving this is to introduce a eliminate issues here, both in process execution
measurement system that can monitor and the measuring of it.
performance and determine improvement
areas. Based on the problems mentioned in the
introduction three objectives were formulated:
Tetra Pak BU DBF is a company within Tetra
Pak that produces processing equipment for  The first objective was to establish a good
dairy products, beverages and prepared food. understanding of the process and its
During the last years BU DBF has become characteristics.
process oriented and at present they are working
with introducing the lean philosophy. To  The second objective was to analyze the
overview the progress they in 2005 introduced a process and identify improvement
measurement system called „New Milestones‟ possibilities.
which measures the internal delivery accuracy in
the order fulfilment process (OFCE). The  The third objective was to describe the
results from the last two years indicate issues in measurement system and its connections
the process and the delivery accuracy target to the process. The system should be
towards the external customers is only met analyzed and improvements should be
through the use of overtime and excessive suggested.
resources.

1
3. METHODOLOGY levels where the main process map is the highest
In order to fulfil the above described objectives level and constitutes an overview of the
a case study was conducted. A case study is an organizations most important processes. Process
empirical research method that investigates a maps should be complemented with process
contemporary event within its real-life context. specifications and depending on the
The case study relies on multiple sources of extensiveness of the process, it could be
information and is the preferred strategy when necessary to break it down into several levels
the questions “how” and “why” are of interest [8].
[1]. Since the objects of interest are the present
process and measurement system, and the Performance measurements
questions are of the described nature the choice Performance measurements are processes to
of research method is well motivated. The case quantify the efficiency and effectiveness of an
study was supported by a thorough literature action [9]. They can be employed in very differ-
research which served as benchmark for the ent parts of a business, and they can be both
proposed recommendations. financial and non-financial. The purpose of the
performance measuring is essentially to
4. THEORY determine how the company is doing internally
The theoretical framework used for the study is as well as in an external environment and
concentrated around three main areas, lean, influence people to take actions accordingly
processes and performance measurements. [10,11].

Lean There are several attributes that characterizes a


The original lean concept essentially aims at good measurement system. Good measures
eliminating waste that can be defined as activities must for example be well-defined and accurate
that increase cost without generating value to the in order to provide trustable results. They
customers. The focus has historically been on should also be easy to understand and
the production workshop [2] but lately it has communicate, and their results should provide
also been applied to the office environment. feedback that can be translated into action.
The most commonly identified wastes are
overproduction, waiting, transport, inappropri- Designing a measurement system is not an easy
ate processing, excess inventory, unnecessary task and many companies have “succeeded
movements, defects [3] and unexploited despite their measurement systems, rather than
creativity [4]. with of them” [12].

Processes 5. THE OFCE-PROCESS AND THE NEW


Processes are networks of in order linked ac- MILESTONES
tivities that use information and resources to
transform input to output in order to satisfy the The OFCE-process
customer‟s needs [5]. The process framework The OFCE process starts when an order is
can be used on different levels, to describe received from one of Tetra Pak‟s market
entire procedures or a single activity. Since companies. The market company (MC) has,
processes are used to describe the work being prior to this, worked out an agreement with the
carried out in the organization, their designs are end customer which has been specified into an
of vital importance for the organizational per- order.
formance [6].
The OFCE-process essentially includes five
The best way to describe a company‟s processes steps.
is by visualising them, i.e. by creating process
maps [7]. A process map can include different

2
The first step of the process is all about devel- met. The system compares the actual ready date
oping an understanding of the order specifi- with the planned ready date and monthly
cation and on assigning personnel to the dif- presents how many of the orders that were on
ferent roles. When this is done budget cost and time for each activity.
transfer price are determined.
The New Milestones is currently constituted by
Following this is the creation of the technical twenty measures which evaluate the perform-
specification and the creation of configuration ance of the OFCE-process from end to end.
documents for the design of the equipment. Since poor results in one part of the process
The latter among others include flow diagrams could be related to problems in previous parts it
and the order BoM (Bill of Materials). When is necessary to have a holistic view.
these are done there is a planning meeting
where all aspects regarding the production of 6. CURRENT SITUATION AND
the order are clarified. IMPROVEMENT POSSIBILITIES

Following the planning meeting is the The OFCE-process


engineering of the different components. This The OFCE-process is well mapped and planned
work includes designing the process according but still contains a number of improvement
to the requested performance, programming the possibilities. The issues mostly exist in the
automation software used to operate the ma- interfaces and handovers between functions,
chine(s) and the creation of the mechanical where both sides has a responsibility and an
design drawings used in assembly. This phase interest to contribute to a better solution.
also involves costs calculations and the
purchasing of non-stock parts. One major problem is that orders are not fully
and correctly specified when received from the
When all the machine specifications are done market companies. The additional time spent
and the ordered components have arrived, the on clarifying the order delays the start of the
machine is ready to be assembled. This step of process and time lost here is hard to catch up
the process includes the bending of pipes, later. Since both sides of the handover exist
assembling, welding of components within Tetra Pak, there is a common interest to
(manufacturing) and electrical wiring. Once the improve. The market companies should make
machine is assembled and ready, it can proceed sure that they do not place an order until they
to the next step, the workshop tests. have all the necessary input from the end
customer, and BU DBF should make sure that
This last step exists to ensure that the machine order forms and instructions are clear and up to
follows the specifications, that it is correctly date.
assembled and that the software is correctly
programmed. When tests are completed and Another interface where problems exist is the
possible deviations from specifications are relation with the suppliers. Neither BU DBF
corrected, the machine is packed and sent to the nor the suppliers follow the agreements stated in
customer‟s site. There it is installed and tested the contract. BU DBF often requests a shorter
until it is meeting the agreed performance delivery time than agreed upon, while suppliers
specified in the order/contract. sometimes confirms a longer delivery time than
agreed upon. In some cases the suppliers even
New Milestones deliver later than they have confirmed. BU DBF
The „New Milestones‟ is a measurement system first has to make sure that their process comes
used to track the performance of the OFCE- to a good start and that the contracts are aligned
process. It focuses on measuring how well the with process specifications. There also must be
planned ready dates for the main activities are a dialogue with the suppliers about what

3
consequences late deliveries have, and how they measurements should be clearly defined, and
could be avoided. this includes handling every type of possible
scenario.
Other issues are related to deviation from
process specifications in the daily work. The In relation with the ordering of components it
process specifications state that all the additional has been identified that the Milestones called
time spent clarifying an order should be added „Materials, Confirmed date‟ and „Materials,
to the delivery date. This is not done at the Requested date‟ are not measuring what was
moment. intended, indicating a better performance than
what was the actual case. This has diverted focus
The improvement possibilities does not only from a problem area and redesign of the
cover the work conducted in the process, but measures is needed to reflect the true
also the systems and documents that supports it. performance.
Delays can occur as a result of inaccurate
templates, which have to be corrected. Inac- All the Milestones related to the performance in
curate template also increases the risk of the workshop are handled in the same way.
mistakes, which take time to correct. They are taken from the ERP-system and put
through several filters. Unfortunately this
Other causes of delays are high workloads and treatment does not guarantee that the data
insufficient competence. presented is what was intended. The
recommendation is that the filters are adjusted,
New Milestones to make sure that only the correct and relevant
After a thorough analysis of the measurement data pass through.
system several issues could be identified. These
could basically be classified as either design and The issue with „Delivery Accuracy Milestone‟,
measuring issues. the most important of the measures, is that it is
based on opinion rather than objective facts. If
The first two Milestones focusing on the order an order is late there is always a possibility to do
receiving and clarification are not measuring a review of the reason and change it manually. It
what is intended. The given time specified for is important that the measures do not leave any
certain activities are given in workdays while the room for subjectivity.
measuring measured differences between dates.
When working with tight deadlines this has a 7. CONCLUSIONS AND
significant impact on the results. RECOMMENDATIONS

Another major issue with the „Order Con- Deviations from the process descriptions
firmation Milestone‟ is that the system cannot In general the process design seems to be
handle a long clarification phase, as it is followed and only a couple of deviations from
specified in the process description. This issue the directives were identified. On the other
can only be resolved through the introduction of hand there are strong reasons to believe that
a „Date of clarification‟ to the measurement these deviations are causing problems in the
system. handling of the orders. All deviations from
process directives should be eliminated to be
An issue primarily related to the Milestones able to observe the true process performance.
measuring the BoM and the automation
software is ambiguities in how to handle Delays throughout the process
revisions and changes (i.e. when there are two The clarification of orders takes too much time
ready dates for the same Milestone). and delays later stages of the process. At the
Researchers stress the importance that same time, the engineering is suffering from

4
delays due to revisions of the BoM. To reduce [4] Keyte, Beau & Locher, Drew, 2008,
delays in these phases, feedback on the reasons Leanhandboken (orig. title The Complete Lean
of the delays should be collected. Enterprise), Liber, Malmö

In relation with purchasing of components the [5] Ljungberg, Anders & Larsson, Everth, 2001,
observed problems are related to late deliveries Processbaserad verksamhetsutveckling,
from the suppliers. To solve this problem Studentlitteratur, Lund
dialogue, incitements and fines could be used.
[6] Hammer, Michael (2007), The Process
In the testing of the produced equipment, most Audit, Harvard Business Review, Vol. 85, Issue
of the interruptions are related to problems 4, Page 111-123
originated in the previous phases. Here
feedback is available but it is not always used for [7] Galagan, Patricia A. (1992), Manage the
driving corrective actions. White Space: The Works of Geary Rummler,
Training & Development Vol. 46, Issue 8, Page
Evaluation of the measurement system 26-31
The OFCE-process has some issues but the bad
results indicated by the „New Milestones‟ are [8] Ljungberg, Anders & Larsson, Everth, 2001,
also related to problems with the measurement Processbaserad verksamhetsutveckling,
system itself. Studentlitteratur, Lund

The most prominent issue is that the „Order [9] Bourne, Mike & Neely, Andy & Mills, John
confirmation Milestone‟ does not take into & Platts, Ken (2003), Implementing
consideration that orders needs additional time performance measurement systems: a literature
to be clarified. Further, the Milestone measuring review, Int. J. Business Performance
the ordering of components do not measure Management, Vol. 5, Issue 1, Page 1-24
what was intended and thus the results are not
indicating the real process performance. [10] Neely, Andy & Gregory, Mike & Platts,
Ken (1995), Performance measurement system
In general the Milestones need to be reviewed design: A literature review and research agenda,
both in terms of design and measuring International Journal of Operations &
procedures. Production Management, Vol. 15, Issue 4, Page
80-116

SOURCES [11] Ibid.

[1] Yin, Robert, 1994, Case Study Research - [12] Hammer, Michael (2007), The 7 deadly
Design and Methods, Second Edition, Sage sins of performance measurement and how to
Publications, Thousand Oaks, CA avoid them, MIT Sloan Management Review,
Vol. 48, Issue 4, Page 19-28
[2] Näslund, Dag (2008), Lean, six sigma and
lean sigma: fads or real process improvement
methods?, Business Process Management
Journal, Vol. 14, Issue 3, Page 269-287

[3] Ibid.

Vous aimerez peut-être aussi