Académique Documents
Professionnel Documents
Culture Documents
This article is based on the results of a master thesis carried out at Tetra Pak Business Unit Dairy
Beverage and Prepared food (BU DBF) during the spring of 2009. It aims to briefly present the case, the
methodology and theoretical framework, the findings and finally some conclusions. The main themes of
the thesis as well as the article are process improvements and performance measurements.
1
3. METHODOLOGY levels where the main process map is the highest
In order to fulfil the above described objectives level and constitutes an overview of the
a case study was conducted. A case study is an organizations most important processes. Process
empirical research method that investigates a maps should be complemented with process
contemporary event within its real-life context. specifications and depending on the
The case study relies on multiple sources of extensiveness of the process, it could be
information and is the preferred strategy when necessary to break it down into several levels
the questions “how” and “why” are of interest [8].
[1]. Since the objects of interest are the present
process and measurement system, and the Performance measurements
questions are of the described nature the choice Performance measurements are processes to
of research method is well motivated. The case quantify the efficiency and effectiveness of an
study was supported by a thorough literature action [9]. They can be employed in very differ-
research which served as benchmark for the ent parts of a business, and they can be both
proposed recommendations. financial and non-financial. The purpose of the
performance measuring is essentially to
4. THEORY determine how the company is doing internally
The theoretical framework used for the study is as well as in an external environment and
concentrated around three main areas, lean, influence people to take actions accordingly
processes and performance measurements. [10,11].
2
The first step of the process is all about devel- met. The system compares the actual ready date
oping an understanding of the order specifi- with the planned ready date and monthly
cation and on assigning personnel to the dif- presents how many of the orders that were on
ferent roles. When this is done budget cost and time for each activity.
transfer price are determined.
The New Milestones is currently constituted by
Following this is the creation of the technical twenty measures which evaluate the perform-
specification and the creation of configuration ance of the OFCE-process from end to end.
documents for the design of the equipment. Since poor results in one part of the process
The latter among others include flow diagrams could be related to problems in previous parts it
and the order BoM (Bill of Materials). When is necessary to have a holistic view.
these are done there is a planning meeting
where all aspects regarding the production of 6. CURRENT SITUATION AND
the order are clarified. IMPROVEMENT POSSIBILITIES
3
consequences late deliveries have, and how they measurements should be clearly defined, and
could be avoided. this includes handling every type of possible
scenario.
Other issues are related to deviation from
process specifications in the daily work. The In relation with the ordering of components it
process specifications state that all the additional has been identified that the Milestones called
time spent clarifying an order should be added „Materials, Confirmed date‟ and „Materials,
to the delivery date. This is not done at the Requested date‟ are not measuring what was
moment. intended, indicating a better performance than
what was the actual case. This has diverted focus
The improvement possibilities does not only from a problem area and redesign of the
cover the work conducted in the process, but measures is needed to reflect the true
also the systems and documents that supports it. performance.
Delays can occur as a result of inaccurate
templates, which have to be corrected. Inac- All the Milestones related to the performance in
curate template also increases the risk of the workshop are handled in the same way.
mistakes, which take time to correct. They are taken from the ERP-system and put
through several filters. Unfortunately this
Other causes of delays are high workloads and treatment does not guarantee that the data
insufficient competence. presented is what was intended. The
recommendation is that the filters are adjusted,
New Milestones to make sure that only the correct and relevant
After a thorough analysis of the measurement data pass through.
system several issues could be identified. These
could basically be classified as either design and The issue with „Delivery Accuracy Milestone‟,
measuring issues. the most important of the measures, is that it is
based on opinion rather than objective facts. If
The first two Milestones focusing on the order an order is late there is always a possibility to do
receiving and clarification are not measuring a review of the reason and change it manually. It
what is intended. The given time specified for is important that the measures do not leave any
certain activities are given in workdays while the room for subjectivity.
measuring measured differences between dates.
When working with tight deadlines this has a 7. CONCLUSIONS AND
significant impact on the results. RECOMMENDATIONS
Another major issue with the „Order Con- Deviations from the process descriptions
firmation Milestone‟ is that the system cannot In general the process design seems to be
handle a long clarification phase, as it is followed and only a couple of deviations from
specified in the process description. This issue the directives were identified. On the other
can only be resolved through the introduction of hand there are strong reasons to believe that
a „Date of clarification‟ to the measurement these deviations are causing problems in the
system. handling of the orders. All deviations from
process directives should be eliminated to be
An issue primarily related to the Milestones able to observe the true process performance.
measuring the BoM and the automation
software is ambiguities in how to handle Delays throughout the process
revisions and changes (i.e. when there are two The clarification of orders takes too much time
ready dates for the same Milestone). and delays later stages of the process. At the
Researchers stress the importance that same time, the engineering is suffering from
4
delays due to revisions of the BoM. To reduce [4] Keyte, Beau & Locher, Drew, 2008,
delays in these phases, feedback on the reasons Leanhandboken (orig. title The Complete Lean
of the delays should be collected. Enterprise), Liber, Malmö
In relation with purchasing of components the [5] Ljungberg, Anders & Larsson, Everth, 2001,
observed problems are related to late deliveries Processbaserad verksamhetsutveckling,
from the suppliers. To solve this problem Studentlitteratur, Lund
dialogue, incitements and fines could be used.
[6] Hammer, Michael (2007), The Process
In the testing of the produced equipment, most Audit, Harvard Business Review, Vol. 85, Issue
of the interruptions are related to problems 4, Page 111-123
originated in the previous phases. Here
feedback is available but it is not always used for [7] Galagan, Patricia A. (1992), Manage the
driving corrective actions. White Space: The Works of Geary Rummler,
Training & Development Vol. 46, Issue 8, Page
Evaluation of the measurement system 26-31
The OFCE-process has some issues but the bad
results indicated by the „New Milestones‟ are [8] Ljungberg, Anders & Larsson, Everth, 2001,
also related to problems with the measurement Processbaserad verksamhetsutveckling,
system itself. Studentlitteratur, Lund
The most prominent issue is that the „Order [9] Bourne, Mike & Neely, Andy & Mills, John
confirmation Milestone‟ does not take into & Platts, Ken (2003), Implementing
consideration that orders needs additional time performance measurement systems: a literature
to be clarified. Further, the Milestone measuring review, Int. J. Business Performance
the ordering of components do not measure Management, Vol. 5, Issue 1, Page 1-24
what was intended and thus the results are not
indicating the real process performance. [10] Neely, Andy & Gregory, Mike & Platts,
Ken (1995), Performance measurement system
In general the Milestones need to be reviewed design: A literature review and research agenda,
both in terms of design and measuring International Journal of Operations &
procedures. Production Management, Vol. 15, Issue 4, Page
80-116
[1] Yin, Robert, 1994, Case Study Research - [12] Hammer, Michael (2007), The 7 deadly
Design and Methods, Second Edition, Sage sins of performance measurement and how to
Publications, Thousand Oaks, CA avoid them, MIT Sloan Management Review,
Vol. 48, Issue 4, Page 19-28
[2] Näslund, Dag (2008), Lean, six sigma and
lean sigma: fads or real process improvement
methods?, Business Process Management
Journal, Vol. 14, Issue 3, Page 269-287
[3] Ibid.