Enquiry Reference Number: RC-10

For the attention of:


Date: 19 April 2018
Dear Sirs,

CONTRACT:

We are currently preparing a price for the above project and would be grateful to receive your quotation for
carrying out the necessary works as detailed in the attached scheme specific documents and in accordance
with the terms and conditions of our subcontract.

Your price should include for all necessary resources including labour, plant, materials and any sub-
subcontracts to carry out all the relevant works. Please submit your price along with a detailed programme
of works, a fully completed risk register and a list of any subcontractors you propose to employ in
undertaking of these works.

Your quotation should be received at the below address not later than Friday 13th December 2013, clearly
marked for the attention of the undersigned.

Please note no late submissions will be accepted and late returns will be excluded from the
tendering process.

Any technical or commercial queries should be addressed to the undersigned and in the event of you not
wishing to submit a quotation for these works please inform the same without any delay.

Yours faithfully

Quantity Surveyor

Documents enclosed:
1. Enquiry Summary Schedule and Associated Documents
2. Tender Return Form
3. CDM018b (HA1-97453281) Non-Notifiable Pre-Construction Information..
4. Design Philosophy dated October 2013
5. Bill of Quantities
6. Drawings RC-10440-100, 101 rev B, 102 rev B, 110 rev B, 500 rev B, 501 rev B, 502 rev B, 503 rev
B, 504 rev B, 505 rev C, 1100 rev B
ENQUIRY SUMMARY SCHEDULE

Item Description Applicable Comments

Terms and Conditions

Main Contract N Conditions of Contract for Managing Agent


Contractor.
Subcontract Basis Y Long Form of Subcontract
Priced B.O.Q’s Y

Re-Measurable Y

Price Adjustment for Inflation N Not applicable for B.O.Q’s priced for specific
schemes.
Payment Terms Y As per the Subcontract Order (30 days from the
invoice date)

Scope of the Subcontract Works


Design N EM Highway’s responsibility unless instructed
otherwise. In the event that EnterpriseMouchel’s
documentation referred to herein incorporating a
design element, you are to include within your
quotation for all costs related thereto including
provision of all supporting documentation to the
satisfaction of his Engineer and in addition for
the provision of adequate Professional
Indemnity insurance cover.
Calculations N Only required for design. It is responsibility of
the subcontractor for any temporary works that
are required as part of subcontractors works.
Drawings N As built drawings if required
Site Survey N If specifically requested as part of the scheme
specific details attached herein
Fabrication & Storage N
Supervision Y Subcontractors responsibility to supervise own
works.
Supply and Delivery N
Delivery Date N
Testing N
Trial Panels / Areas N Subcontractors responsibility
Installation N
Traffic Management N EM Highways to provide all TM
Site Establishment Y Subcontractors responsibility
Start on Site Y 10th February 2014
ENQUIRY SUMMARY SCHEDULE

Completion Date / Period Y 14th March 2014 (25 working days)


Welfare Y Subcontractor’s responsibility.
Interfaces Y With EM Highways in provision of traffic
management, if necessary.

Tender Enquiry Documents

Specification Y MCHW Specification (details contained on


drawings)
Pre-Construction Information Y As listed above
Drawings Y As listed above

Bill of Quantities Y As listed above

Scheme Specific Risk Register N


Any other Scheme Specific Y Design Philosophy dated October 2013
Information

Selection Criteria (Adjust Scoring Criteria to Suit Scheme Specific Requirements)

Price 90%
Fully Detailed Programme 10%
TENDER RETURN FORM

Contract: Area 1
RC-10441 A38 Dartbridge Ditch Renewal
To
EM Highway Services Limited
Ash House
Falcon Road
Sowton Industrial Estate
Exeter
EX2 7LB

For the attention of: Phil Morris

1. TENDER SUM

Having examined the Tender Enquiry Documents including all Drawings, Specifications, Contract
Conditions and other details enclosed referred to within your Enquiry Letter and all other Enquiry
Documents for the above Subcontract Works, as well as the site and any conditions affecting the
Subcontract Works, we offer to provide all supervision, plant, labour, equipment and materials
necessary to carry out and complete the Subcontract Works in accordance therewith for the sum of:

(£_________________) ( in words)

On a Priced Bill of Quantities subject to re-measure basis in accordance with the details attached.

The Tender Sum is on a NETT BASIS.

We understand that you are not bound to accept the lowest or any tender received.

Please name here any subcontractors you propose to employ in undertaking these works:

2 VALIDITY

We agree that this offer shall remain open for acceptance for a period of 180 days from the date set
for return of tenders.

COMPANY Authorised Signatory


(Name)

ADDRESS Signature