Académique Documents
Professionnel Documents
Culture Documents
Implementation Plan
Version : 1.0
Revised by
Duc Le
Duc Le
Week# Content Date Time Room
Hoa Hướng
15-Sep-10 13:00-15:00
Dương
Team Assignment
3
#3
Team Assignment 30-Sep-10 15:30-17:00 7th Floor
3
#3
Team Assignment
8
#8
4-Nov-10 15:30-17:00 7th Floor
Team Assignment
8
#8
Team Assignment
15
#15
•Ask 30 classmates to collect data about their favorite sport. Then choosing a
chart type to graph the collected data and using that chart to answer following
questions:
- Which sport is the most popular?
- Which sport is the least popular?
- What percentage of students like the most popular sport?
• Sally walks everywhere. Here is how far she has walked the past few months.
What chart type should Sally use to show how far she walks per month and to
know if Sally’s working is increasing or decreasing?
Sally’s Walking
January 60 Km
February 48 Km
2 March 46 Km
April 50 Km
May 44 Km
June 42 Km
• Research to collect data about the amount of sugar in one serving (you get to
decide what “one serving” means) for each of the following: milk, cola, water,
orange juice, tea and coffee. Then choosing a chart type to graph the collected
data and using that chart to answer following questions:
18
Team Complete
assignment # Description before lecture#
• Brief description (≤ 3 pages) of project team roles, responsibilities
and schedule (which team member plays which roles when).
• Reporting of planned and actual individual effort log data (use
1 3
provided effort log spreadsheet) to Director by team, along with
brief analysis
• Each team presents a GQM chart for one assigned Viking project
goal:
- Reduce product schedule by 10%
- Improve productivity by 10%
- Reduce project costs by 10%
- Improve product quality by 10%
- Reduce project risk by 10%
4 - Reduce product change by 10% 7
- Improve customer satisfaction by 10%
- Increase team morale by 10%
- Reduce defects found by system test by 10%
- Increase project schedule predictability by 10%
• Reporting of actual individual effort log data to Director by team,
along with brief analysis
• Each team creates a high level network diagram, high level wbs
6 8
and high level schedule for the Viking project.