PROGRAMME AND ESTIMATE
Content
1. How does the project program influence the project cost?
2. Content of a basic construction programme
3. How to allow for weather and other risks
4. Typical time related risks other than inclement weather
5. How to mitigate time related risks in your programme
6. Turn Key Projects as a method to fast track projects
7. Resource programming

©2018 Copyright Alusani Skills & Training Network®. All Rights Reserved.
The format, design, content and arrangement of this document constitute a trademark of Alusani Skills & Training Network®.
Unauthorised reproduction will be actionable under South African law. 2
Programme influence on cost
• Confirm start and finish dates with clien

• Estimate to take the programme period into account

• Builders holiday

• Calculation of interest

• Calculation of escalation

• Programme for estimate must include all activities prior to start


of construction (design, tender production, tender period,
tender report).

©2018 Copyright Alusani Skills & Training Network®. All Rights Reserved.
The format, design, content and arrangement of this document constitute a trademark of Alusani Skills & Training Network®.
Unauthorised reproduction will be actionable under South African law. 3
Construction programme content
• It must be indicative
• It must reflect the proposed sequence of the main construction activities
• It must reflect the proposed tempo of execution of the main construction
activities.
• It must indicate the critical path. The Critical Path is the longest necessary
path through a network of activities when respecting the interdependencies.
• It must be produced with the required software if specified.
• The Client does not want to see the detail at tender stage
• You have to do detail programming to make sure what you present in your
tender is correct and achievable
• Different Clients have different requirements.
• The Client will expect a programme that meets his PC date
• See if you can negotiate sectional completion in tender submission.
• Advise the Client if you think their programme expectation are unrealistic
• Watch out for copy and paste exercises!
• Watch out when you use a template based on another project!
• Programmer and project manager must be on the same page
©2018 Copyright Alusani Skills & Training Network®. All Rights Reserved.
The format, design, content and arrangement of this document constitute a trademark of Alusani Skills & Training Network®.
Unauthorised reproduction will be actionable under South African law. 4
Allowance for weather etc.

• Weather risks is not only rain


• Consider wind and temperature
• Check the tender document for clause changes about
inclement weather
• Make use of past weather reports and long term
forecasts

©2018 Copyright Alusani Skills & Training Network®. All Rights Reserved.
The format, design, content and arrangement of this document constitute a trademark of Alusani Skills & Training Network®.
Unauthorised reproduction will be actionable under South African law. 5
Other time related risks

• Municipal connections

• Commissioning of services

• Green building requirements

• Lead times of materials

• Late instructions and late information

• Time needed to study the provided information


©2018 Copyright Alusani Skills & Training Network®. All Rights Reserved.
The format, design, content and arrangement of this document constitute a trademark of Alusani Skills & Training Network®.
Unauthorised reproduction will be actionable under South African law. 6
Turn key projects (fast track)

• Level of information
• Manage design consultants
• Design liability
• Better control
• Smaller team
• Fast track opportunity
• More processes & responsibilities
• More risks

©2018 Copyright Alusani Skills & Training Network®. All Rights Reserved.
The format, design, content and arrangement of this document constitute a trademark of Alusani Skills & Training Network®.
Unauthorised reproduction will be actionable under South African law. 7
Resource programming

• Compile a staffing management plan

• Plot the staffing management plan in a histogram

• Make use of a responsibility assignment matrix

©2018 Copyright Alusani Skills & Training Network®. All Rights Reserved.
The format, design, content and arrangement of this document constitute a trademark of Alusani Skills & Training Network®.
Unauthorised reproduction will be actionable under South African law. 8
THANK YOU
©2017 Copyright Alusani Skills & Training Network®. All Rights Reserved.

Len Holder
Tel: 011 447 7470
Web: www.alusani.co.za

Vous aimerez peut-être aussi