Institute of technology
Nirma University
B. Tech Civil – Sem.VII
Construction Project Management – 2CL401
Tutorial VI
PERT Network
1. Find out the expected time for each activities in series. Also find out standard
deviation for the project.
Activity to tm tp
1-2 4 6 8
2-3 6 7 8
3-4 10 12 15
4-5 12 15 18
2. Determine the slack for each event and critical path. Prepare table. What would be the
time duration of the project to complete project with 60% probability?
Activity Expected
time (te)
1-2 5
1-3 8
2-4 9
3-4 3
3-7 12
4-5 4
4-7 12
5-6 8
6-7 2
6-8 10
7-8 5
3. Find out the earliest expected time and latest allowable occurrence time of each event.
Also find out slack for every event. Find critical path. Find out probability to
complete project in 25 days and in 30 days.
Activities tp tm to
A 5 2 1
B 5 3 1
C 8 5 2
D 6 2 1
E 9 4 2
F 10 7 4
G 4 2 1
H 12 8 4
I 8 3 1
J 6 2 1
K 9 6 2
L 9 6 3
M 15 11 7
N 8 5 3
O 9 5 3
P 10 6 3
Q 8 4 2
4. For construction project, for a particular activity P, time estimates provided by three
managers are as under. State, who is more certain about the time of completion of the
activity P.
Most likely
Optimistic time Pessimistic time
time
Manager A 8 10 12
Manager B 7 10 14
Manager C 9 12 15
5. Find out the earliest expected time and latest allowable occurrence time of each event.
Also find out slack for every event. Find critical path. Find out probability to
complete project in 40 days and in 50 days.
Activity tp tm to
90-100 6 8 10
80-90 5 7 9
70-90 2 3 4
60-80 14 16 18
50-70 7 8 9
40-70 4 5 6
30-60 2 4 6
10-60 6 8 10
30-50 10 14 18
20-40 8 12 16
10-30 4 6 10
10-20 4 10 16