COMOPERAMA CRONOGRAMA DE EJECUCION - PIASS SIMA IQUITOS SRL

ID % Nombre de tarea TALLER/TERCERO Duration Start Finish Qtr 3, 2014 Qtr 4, 2014
Complete June July August September October November December January
E B M E B M E B M E B M E B M E B M E B M E B M E B
1 0% MODIFICACION MOTOCHATA A PIASS II-III DOS 240 days Mon 02/06/14 Tue 27/01/15
MOTORES
2 0% Preliminares 194 days Mon 02/06/14 Fri 12/12/14
3 0% Planos 194 days Mon 02/06/14 Fri 12/12/14
4 0% Rediseño de la embarcación por variación de DD 30 days Mon 02/06/14 Tue 01/07/14
características bajo y sobre cubierta principal

5 0% Entrega planos casco, superestructura y sistemas DD 30 days Wed 02/07/14 Thu 31/07/14

6 0% Suministro de Motor, GGEEs, Sistemas , LOGISTICA 194 days Mon 02/06/14 Fri 12/12/14
equipos, Accesorios y Acabados
7 0% Sistema Electrico 60 days Fri 01/08/14 Mon 29/09/14
8 0% Sistema Electronico 55 days Thu 21/08/14 Tue 14/10/14
9 0% Sistema Central aire acondicionado 120 days Fri 15/08/14 Fri 12/12/14
10 0% Sistema Agua Potable 60 days Mon 11/08/14 Thu 09/10/14
11 0% Sistema Desague 70 days Tue 22/07/14 Mon 29/09/14
12 0% Sistema Combustible 70 days Tue 22/07/14 Mon 29/09/14
13 0% Sistema Contra Incendio 67 days Sun 10/08/14 Wed 15/10/14
14 0% Sistema Lastre 70 days Sun 27/07/14 Sat 04/10/14
15 0% Sist. Achique Sentinas sala maquinas 67 days Sun 27/07/14 Wed 01/10/14
16 0% Sistema de forrado en Al y en Inox. 70 days Fri 15/08/14 Thu 23/10/14
17 0% Sistema Gobierno 60 days Fri 15/08/14 Mon 13/10/14
18 0% Sistema de Propulsión, motor 60 days Fri 15/08/14 Mon 13/10/14
19 0% Material en Bronce 16 days Fri 01/08/14 Sat 16/08/14
20 0% Suministros Equipos de Ministerios 54 days Thu 21/08/14 Mon 13/10/14
21 0% Productos Pintura y solventes 60 days Tue 22/07/14 Fri 19/09/14
22 0% Grua Toimil 154 days Mon 02/06/14 Sun 02/11/14
23 0% Dique Flotante 91 days Mon 02/06/14 Sun 31/08/14
24 0% Confeccion cama varado X:92 6HD 1 day Mon 02/06/14 Mon 02/06/14
25 0% Ingreso de Embarcacion X:92 6HD 1 day Mon 02/06/14 Mon 02/06/14
26 0% Estadía 90 days Tue 03/06/14 Sun 31/08/14
27 0% Sistema de Propulsion y Gbno. Existente TERCERO 2 days Tue 03/06/14 Wed 04/06/14
28 0% Desmontaje del sistema propulsion 1 day Tue 03/06/14 Tue 03/06/14
29 0% Desmontaje de sistema de Gbno. 1 day Wed 04/06/14 Wed 04/06/14
30 0% Ejecucion Obra 214 days Mon 02/06/14 Thu 01/01/15
31 0% Casco y Superestructura 161 days Mon 02/06/14 Sun 09/11/14
32 0% Calibaracion planchas casco 2 days Mon 02/06/14 Tue 03/06/14
33 0% Calibración de espesores de planchas en X:40 4HD, DDCC 2 days Mon 02/06/14 Tue 03/06/14
casco(fondo, bandas, espejos) y cubierta.

34 0% Modificacion de popa TERCERO 45 days Tue 03/06/14 Thu 17/07/14


35 0% Modificacion de cuadernas y varengas 45 days Tue 03/06/14 Thu 17/07/14
36 0% Modificacion sala de maquinas TERCERO 15 days Fri 18/07/14 Fri 01/08/14
37 0% Corte y retiro de mamparos de tanques existente 8 days Fri 18/07/14 Fri 25/07/14
Er y Br.
38 0% Instalacion de platina en borde de planchas 7 days Sat 26/07/14 Fri 01/08/14
retiradas
39 0% Casco y Estructuras TERCERO 159 days Wed 04/06/14 Sun 09/11/14
40 0% Montaje de nuevas estructuras long y transv. 6 days Sat 12/07/14 Thu 17/07/14

41 0% Reemplazo planchas en fondo 9 days Fri 18/07/14 Sat 26/07/14


42 0% Remplazo planchas en bandas 12 days Fri 18/07/14 Tue 29/07/14
43 0% Reemplazo de pantoques 8 days Fri 18/07/14 Fri 25/07/14
44 0% Instacion de verdiuguete Er , Br , Proa y Popa. 9 days Wed 30/07/14 Thu 07/08/14

45 0% Soldadura de acabado 15 days Wed 30/07/14 Wed 13/08/14


46 0% Aplicación de tintes penetrantes 8 days Fri 01/08/14 Fri 08/08/14
47 0% Cubierta principal existente TERCERO 64 days Wed 04/06/14 Wed 06/08/14
48 0% Corte y retiro de soportes de tuberia 4 days Wed 23/07/14 Sat 26/07/14
existentes
49 0% Confeccion e Instalacion de escotillas 26 days Sat 12/07/14 Wed 06/08/14
50 0% Reparacion de soldadura defectuosa 2 days Wed 04/06/14 Thu 05/06/14
51 0% Bajo cubierta principal TERCERO 15 days Sat 12/07/14 Sat 26/07/14
52 0% Retiro de mamparos longitudinales en 9 days Sat 12/07/14 Sun 20/07/14
bodegas 2 Er,Br y 3Ery Br.
53 0% Reubicacion de mamparos a nueva ubicacion 9 days Thu 17/07/14 Fri 25/07/14

54 0% Montaje de nuevos mamparos transversales 9 days Wed 16/07/14 Thu 24/07/14

55 0% Montaje de nuevos mamparos longitudinales 9 days Thu 17/07/14 Fri 25/07/14

56 0% Reemplazo de cartelas deformadas 14 days Sat 12/07/14 Fri 25/07/14


57 0% Aplicacion de soldadura acabado 10 days Thu 17/07/14 Sat 26/07/14
58 0% Aplicación de tintes penetrantes 9 days Wed 16/07/14 Thu 24/07/14
59 0% Superestrutura TERCERO 70 days Tue 17/06/14 Mon 25/08/14
60 0% Galibus de Superestructura 3 days Tue 17/06/14 Thu 19/06/14
61 0% Prefabr Superstrct.1ª Cbta. 15 days Tue 17/06/14 Tue 01/07/14
62 0% Prefabr Superstrct.2ª Cbta. 14 days Fri 20/06/14 Thu 03/07/14
63 0% Erecc. Superestrct.1ª Cbta. 38 days Wed 02/07/14 Fri 08/08/14
64 0% Erecc. Superestrct.2ª Cbta. 38 days Fri 04/07/14 Sun 10/08/14
65 0% Soldaduray tintes penetrantes 1ra. 28 days Wed 02/07/14 Tue 29/07/14
Superestructura
66 0% Soldaduray tintes penetrantes 2da. 28 days Wed 02/07/14 Tue 29/07/14
Superestructura
67 0% Montaje de accesorios en cubierta principal 24 days Wed 30/07/14 Fri 22/08/14

68 0% Aplicación de soldadura acabado 1ra. y 2da. 15 days Mon 11/08/14 Mon 25/08/14
Cub.
69 0% Fabricac. Miscelaneos TERCERO 116.3 days Wed 02/07/14 Sun 26/10/14
70 0% Palo Trinquete 4 days Wed 27/08/14 Sat 30/08/14
71 0% Bitas, Cornamus 3 days Fri 29/08/14 Sun 26/10/14
72 0% Fabricac. Chimenea 3 days Mon 11/08/14 Wed 13/08/14
73 0% Escotillas 10 days Wed 02/07/14 Fri 11/07/14
74 0% Puerta metalicas 72 days Wed 02/07/14 Thu 11/09/14
75 0% Arenado y Pintado TERCERO 103 days Wed 30/07/14 Sun 09/11/14
76 0% Arenado y Pintado Casco Exterior y cubierta 20 days Sat 20/09/14 Sun 09/11/14
principal
77 0% Arenado y Pintado Interior bodegas 18 days Thu 14/08/14 Sun 31/08/14
78 0% Arenado, pintado Superstrctura 1ª 50 days Wed 30/07/14 Wed 17/09/14
79 0% Arenado, pintado Superstrctura 2da. 50 days Wed 30/07/14 Wed 17/09/14
80 0% Instalaciones Varias TERCERO 146 days Sat 09/08/14 Thu 01/01/15
81 0% Instalac. Electricas 75.8 days Tue 30/09/14 Sun 14/12/14
82 0% Habilitado bases para elementos electricos 28 days Tue 30/09/14 Thu 27/11/14

83 0% Tendido canaletas en casco 28 days Tue 30/09/14 Mon 27/10/14


84 0% Tendido canaletas en superestructura 10 days Sat 04/10/14 Mon 13/10/14
85 0% Instalac. Tablero Principal 7 days Tue 14/10/14 Mon 20/10/14
86 0% Instal. Tableros Distribución 9 days Thu 27/11/14 Sat 06/12/14
87 0% Tendido Cables Sala Máq. 6 days Tue 28/10/14 Sun 02/11/14
88 0% Tendido Cables Super estrct. 17 days Thu 27/11/14 Sun 14/12/14
89 0% Instal. Artefactos_Sala Máq. 9 days Wed 29/10/14 Thu 06/11/14
90 0% Instal. Artefact_Superstrct 9 days Tue 14/10/14 Wed 22/10/14
91 0% Instal. Equipo Electricos 12 days Wed 15/10/14 Sun 26/10/14
92 0% Instalac. Electrónics TERCERO 1 day Mon 27/10/14 Mon 27/10/14
93 0% Radar, radio , GPS(M.G.P) 1 day Mon 27/10/14 Mon 27/10/14
94 0% Instalación Maquinaria TERCERO 29 days Thu 18/09/14 Thu 16/10/14
95 0% Instalación Motores Propuls. 20 days Thu 18/09/14 Tue 07/10/14
96 0% Instalación GG EE 9 days Wed 08/10/14 Thu 16/10/14
97 0% Instalación Miscelaneos TERCERO 9 days Wed 08/10/14 Thu 16/10/14
98 0% Trinquete, bitas, chimenea 9 days Wed 08/10/14 Thu 16/10/14
99 0% Habitabilidad TERCERO 61 days Thu 18/09/14 Mon 17/11/14
100 0% Instalación de piso flexible en los 5 days Thu 13/11/14 Mon 17/11/14
compartimentos internos.
101 0% Confeccion Camas metálicas triples 10 days Thu 18/09/14 Sat 27/09/14
102 0% Confeccion Camas metálicas dobles 7 days Thu 18/09/14 Wed 24/09/14
103 0% Confeccion Cama metálica simple 6 days Thu 18/09/14 Tue 23/09/14
104 0% Muebles, mobiliario y menaje de cocina. 7 days Wed 24/09/14 Tue 30/09/14
105 0% Suministro e Instalación Sistm. Frio TERCERO 140 days Fri 15/08/14 Thu 01/01/15
106 0% Central Aire Acondondiconado 120 days Fri 15/08/14 Fri 12/12/14
107 0% Ductos, y extract., Aire Forzado 20 days Sat 13/12/14 Thu 01/01/15
108 0% Instalación Sistemas TERCERO 92.1 days Mon 01/09/14 Tue 02/12/14
109 0% Sist. Propuls y Gob. 48 days Tue 14/10/14 Sun 30/11/14
110 0% Fabricac.Tubo Codate, ejes,prensa estopa, X:37 144HD,X:40 28 30 days Tue 14/10/14 Wed 12/11/14
etc.
111 0% Instal. Tubo Codaste, +Prensa Estopa 5 days Thu 13/11/14 Mon 17/11/14
112 0% Instal. Ejes y helices 2 days Tue 18/11/14 Wed 19/11/14
113 0% Fabric. Timon 13 days Thu 13/11/14 Tue 25/11/14
114 0% Instal.Tub.Limera 10 days Tue 18/11/14 Thu 27/11/14
115 0% Instal.Pist. Hidraul. 3 days Fri 28/11/14 Sun 30/11/14
116 0% Tendid Tuber. Hidraul. (Incl. Decapado) 12 days Tue 18/11/14 Sat 29/11/14

117 0% Sist. Gases Escape TERCERO 42 days Wed 08/10/14 Tue 18/11/14
118 0% Tendido Tuberia Escape, Motores 7 days Wed 08/10/14 Tue 14/10/14
119 0% Tendido Tuberia Escape, GGEE 6 days Thu 13/11/14 Tue 18/11/14
120 0% Instal. Silenciadores. 4 days Tue 14/10/14 Fri 17/10/14
121 0% Instal.Aislante Escape 6 days Wed 08/10/14 Mon 13/10/14
122 0% Instal. Chimenea 6 days Tue 14/10/14 Sun 19/10/14
123 0% Sist. Petroleo TERCERO 85 days Mon 01/09/14 Mon 24/11/14
124 0% Inst. Electrobomba 8 days Tue 30/09/14 Tue 07/10/14
125 0% Tendido Tuberias 18 days Mon 01/09/14 Thu 18/09/14
126 0% Instal. Válvulas y accesorios 10 days Mon 01/09/14 Wed 10/09/14
127 0% Equipo Purificador Centrifugo 5 days Fri 03/10/14 Mon 24/11/14
128 0% Sist. Agua Potable TERCERO 16 days Fri 10/10/14 Sat 25/10/14
129 0% Sistema de Tratamiento de Agua y 16 days Fri 10/10/14 Sat 25/10/14
equipamiento
130 0% Sist. Desague TERCERO 52.75 days Tue 30/09/14 Fri 21/11/14
131 0% Tendido Tuberias 25 days Tue 30/09/14 Fri 21/11/14
132 0% Instal. Válvulas y accesorios 15 days Fri 10/10/14 Fri 24/10/14
133 0% Sist. Contra Incendio TERCERO 43.1 days Mon 20/10/14 Tue 02/12/14
134 0% Inst. electrobomba 3 days Mon 20/10/14 Wed 22/10/14
135 0% Tendido Tuberias 23 days Mon 20/10/14 Tue 11/11/14
136 0% Instal. Válvulas y mangas CI. 2 days Wed 22/10/14 Tue 02/12/14
137 0% Sist. Lastre TERCERO 18 days Thu 23/10/14 Sun 09/11/14
138 0% Tendido Tuberias 18 days Thu 23/10/14 Sun 09/11/14
139 0% Instal. Válvulas y accesorios 18 days Thu 23/10/14 Sun 09/11/14
140 0% Sist. Achique Sentinas Sala maquinas TERCERO 25 days Thu 23/10/14 Sun 16/11/14

141 0% Tendido Tuberias 17 days Thu 23/10/14 Sat 08/11/14


142 0% Instal. Válvulas en manifold 8 days Sun 09/11/14 Sun 16/11/14
143 0% Sist. Refriger. Motor TERCERO 22 days Wed 08/10/14 Wed 29/10/14
144 0% Keel Coller, canales en casco 10 days Wed 08/10/14 Fri 17/10/14
145 0% Tendido Tuberias conexión motor 5 days Thu 23/10/14 Mon 27/10/14
146 0% Instal. Válvulas y accesorios 6 days Fri 24/10/14 Wed 29/10/14
147 0% Acabados TERCERO 128 days Sat 09/08/14 Sun 14/12/14
148 0% Instal. Enchapados con aluminio, acero 38 days Thu 18/09/14 Sat 25/10/14
inoxidable y fibra de vidrio
149 0% Instal. Marcos y Puertas Metalicas 15 days Sun 26/10/14 Sun 09/11/14
150 0% Instal. Marcos y Ventanas 19 days Mon 10/11/14 Fri 28/11/14
151 0% Instal. Muebles y anaqueles y menaje de cocina 7 days Mon 08/12/14 Sun 14/12/14

152 0% SS.HH 30 days Thu 25/09/14 Fri 24/10/14


153 0% Instal. Barandas 26 days Sat 09/08/14 Wed 03/09/14
154 0% Construcción Zampan y Acond. B/D Ambulancia X:67 HD:220 X:90 25 HD 66.4 days Tue 15/07/14 Fri 19/09/14

155 0% Construcción del casco 45 days Tue 15/07/14 Thu 28/08/14


156 0% Preparacion superficie y pintado 6 days Fri 29/08/14 Thu 04/09/14
157 0% Suministro e instalación 02 motores fuera borda 19 days Fri 29/08/14 Tue 16/09/14

158 0% Instalación sistemas y acabados 15 days Thu 04/09/14 Fri 19/09/14


159 0% Pruebas 43.2 days Sun 14/12/14 Mon 26/01/15
160 0% Protocolo de Pruebas DCC 23.2 days Sun 14/12/14 Tue 06/01/15
161 0% Sistema Electrico 5 days Sun 14/12/14 Fri 19/12/14
162 0% Sistema Electronico 5 days Mon 15/12/14 Fri 19/12/14
163 0% Sistema Central aire acondicionado 5 days Fri 02/01/15 Tue 06/01/15
164 0% Sistema Agua Potable 5 days Sat 20/12/14 Wed 24/12/14
165 0% Sistema Desague 5 days Sat 20/12/14 Wed 24/12/14
166 0% Sistema Contra Incendio 5 days Sat 20/12/14 Wed 24/12/14
167 0% Sistema Lastre 5 days Sat 20/12/14 Wed 24/12/14
168 0% Sist. Achique Sentinas 5 days Sat 20/12/14 Wed 24/12/14
169 0% Verificación Acabados 5 days Thu 25/12/14 Mon 29/12/14
170 0% Verificación inventarios 5 days Thu 25/12/14 Mon 29/12/14
171 0% Sistema Hidráulico 5 days Thu 25/12/14 Mon 29/12/14
172 0% Sistema de Propulsion 5 days Thu 25/12/14 Mon 29/12/14
173 0% Prueba botes deslizadores 2 days Tue 30/12/14 Wed 31/12/14
174 0% Pruebas de Navegacion DCC,X:37 20 days Wed 07/01/15 Mon 26/01/15
175 0% Navegación en vacio 10 days Wed 07/01/15 Fri 16/01/15
176 0% Navegación con carga 10 days Sat 17/01/15 Mon 26/01/15
177 0% Entrega de Buque 1 day Tue 27/01/15 Tue 27/01/15
178 0% Firma de Acta 1 day Tue 27/01/15 Tue 27/01/15