POWERHOUSE AND SUBSTATION 1. Mobilization 2. Coordination with end user prior to the start of work 3. Ensure Safety and Disconnect Energized equipment 4. Pull out of Relay 5. Visual Assessment and checkup of relay 6. Conduct Maintenance of relay 7. Calibration/resetting of relay 8. Trip testing of relay 9. Documentation of relay new setting and behavior 10. Documentation of all data gathered 11. Installation of relay back to its panel 12. Housekeeping 13. Submission of Test Reports and Recommendations 14. Demobilization