Vous êtes sur la page 1sur 1

SCOPE OF WORK FOR FUNCTIONALITY TEST OF 5kV

CIRCUIT BREAKER PROTECTIVE RELAYS AT


POWERHOUSE AND SUBSTATION
1. Mobilization
2. Coordination with end user prior to the start of work
3. Ensure Safety and Disconnect Energized equipment
4. Pull out of Relay
5. Visual Assessment and checkup of relay
6. Conduct Maintenance of relay
7. Calibration/resetting of relay
8. Trip testing of relay
9. Documentation of relay new setting and behavior
10. Documentation of all data gathered
11. Installation of relay back to its panel
12. Housekeeping
13. Submission of Test Reports and Recommendations
14. Demobilization

Vous aimerez peut-être aussi