Académique Documents
Professionnel Documents
Culture Documents
HIGHWAY
PROJECT
1
1.0 GENERAL REPORT:
1.1 INTRODUCTION:
The network of roadways of a country is as essential as the arterial system to the human body. The roads in a
big way facilitate advancement in the economy of a country and they simultaneously facilitate communication.
In the matter of surface transport, they are almost equal to the railways which connect other parts of the country
through its large railway network system. These two transports are not parallel but interdependent.
Road transport is one of the most promising and potent means for rapid industrialization and agricultural
advancement. It plays an important role in the economy of the country and is particularly suitable for short and
medium distance.
It provides the basic infrastructure for bringing the majority of the people who are living in far off villages into
the mainstream of life by connecting them with the rest of the country.
It is proposed to carry out a survey work for the alignment of new Road from Anchitageri to New layout near
Timmasagar (1.000km) long. The site is in rolling terrain with red soil. The six different groups carried out the
alignment survey work in three different paths. Out of these three, this alignment is selected which is more
beneficial to people and it is economical.
1.3 SURVEYS:
All different possible alignments and nature of the terrain should be studied with the help of available toposheet
and map of the area.
Preliminary Survey is large scale investigations of the results of reconnaissance survey. Its objective is to
prepare a plan showing the location & nature of the field. The survey consists of establishing a base line
traverse, which is series of straight lines along the selected alignment. The physical features such as buildings,
trees, monuments utilities, railway lines canals etc. are located.
The detailed survey is done to fix the selected alignment in the field and to collect the additional data for the
preparation of the drawings. It also includes the preparation of longitudinal and cross-sections, computation of
earth quantities etc.
1.3.5 DESIGN:
Design of all geometric elements, thickness of pavement layer etc are explained in the upcoming sections.
Excavation for highway cutting and drainage system, construction of embankment are explained in upcoming
sections.
Construction of sub base, base and surface course explained in detail in section 1.6
In connection with this road, the following geometrical Elements are designed.
1) Width of Formation, Width of Carriage way, Camber, Speed.
2) Horizontal curve.
a) Radius.
b) Super elevation.
c) Extra widening.
d) Sight Distance.
e) Transition curve.
3) Vertical curve.
4) Quantity of cutting and filling.
Width of formation is the sum of width of pavements including separator if any and the shoulder. Formation
width is the top width of highway embankment or the bottom width of highway cutting excluding the side
drains. The widths of roadway standardized by IRC are given below.
Hence the width of formation is 7.5m as it is a plain terrain from above table.
The width of carriageway for various classes of roads is standardized by IRC as given in table below.
TABLE 1.2 WIDTH OF CARRIAGEWAY RECOMMENDED BY IRC: 73
Class of road Width of carriageway
(1) Single lane 3.75m
(2) Two lanes, without raised kerbs 7.0m
(3) Two lanes, with raised kerbs 7.5m
(4) Intermediate carriageway (except on important roads) 5.5m
(5) Multi-lane pavements 3.5m per lane
The values of camber recommended by IRC for different types of roads surfaces are given below.
TABLE 1.3 VALUES OF CAMBER RECOMMENDED BY IRC:73
Sl. Types of road surface Range of camber in areas of
No. rainfall range
Heavy to Light
1 Cement concrete and high type bituminous surface 1 in 50(2.0%) to 1 in
60(1.7%)
2 Thin bituminous surface 1 in 40(2.5%) to 1 in
50(2.0%)
3 Water bound macadam, and gravel pavement 1 in 33(3.0%) to 1 in
40(2.5%)
4 Earth 1 in 25(4.0%) to 1 in
33(3.0%)
From table as the proposed road is lying in normal rainfall area hence camber of 2.5% is considered in order to
provide thin bituminous surface.
As the road proposed is a other district road lying in plain terrain the following values are considered
Vruling = 65 kmph
Vminimum =50 kmph
v2
R (ruling) =
127 e f
Where R = Ruling Radius
V = Design Speed
e = Super elevation
f = Co-efficient of friction
v2
e =
225 R
If the value is greater than maximum super elevation of 0.07, the actual super elevation to be provided is
restricted to 0.07, check for coefficient of lateral friction.
Check for coefficient of lateral friction developed for full speed:
v2
f = 0.07
127 R
If the value is less than 0.15, the design is safe with a super elevation of 0.07, if not restrict the coefficient of
lateral friction to 0.15 and reduce the speed.
HERE
No. of Lanes n=1
Length of Wheel base l = 6 m
Width of the Pavement W = 5.5 m
Extra widening = Mechanical widening + Psychological widening
n l² v
We =
2R 9.5 R
B = W + We
v2
0.278 vt
SSD = 254 f
A1 A2 B1 B2 A3
C2 C1
s b s
d1 d2 d3
TABLE 1.8 OVERTAKING SIGHT DISTANCE ON 2-LANE HIGHWAY FOR VARIOUS SPEEDS.
Overtaking sight distance is the minimum sight distance that should be available to a driver on a two road to
enable him to over take another vehicle safely. Optimum condition for design is one in which overtaking driver
can follow the vehicle ahead for a short time while he assesses his chance for overtaking, pulls out his vehicle,
overtakes the other vehicle at design speed of the highway, and returns to his own side of the road before
meeting any oncoming vehicles from the opposite direction travelling at the same speed.
Since the length of the curve is greater than SSD, the minimum clearance or setback distance needed M = CD &
half the central angle α/2= Angle AOD as shown in the following figure.
The distance d between the centre of the pavement & the center line of the inside lane may be taken as ½ the
width of the pavement at the center (being a intermediate lane)
Clearance
A B
Obstruction
Q 2 R
Q
o
FIGURE NO 1.4 HORIZONTAL CURVE
DESIGN SPEED V=65 kmph, for Other district Road & plain terrain.
[IRC Recommendation Table No. A]
v2
e =
225 R
50 2
=
225 90
e = 0.123
As the value is greater than maximum super elevation of 0.07, the actual super elevation to be provided is
restricted to 0.07
v2
f = 0.07
127 R
50 2
= 0.07
127 90
= 0.148
As the value is less than 0.15, the design is safe with a super elevation of 0.07
1. Design speed = 50Kmph
2. Maximum rate of super elevation = (e) = 0.07
3. Maximum allowable design co-efficient of lateral friction = (f) = 0.15
e + f = v2 /127R
R =502/(127×(0.07+0.15))
= 89.47 m
Adopt R = 90 m
4.Radius of horizontal curve = R = 90 m
∆ = 85030’
HERE
No. of Lanes n=1
Length of Wheel base l = 6 m
Width of the Pavement W = 5.5 m
Extra widening = Mechanical widening + Psychological widening
n l² v
We =
2R 9.5 R
1 6² 50
=
2 90 9.5 90
= 0.2 + 0.555
= 0.755 m
Provide an extra wide of 0.755 m and hence the total width of the pavement
B = W + We
B = 5.5+0.755
B = 6.255 m
= 0.2 34 6
= 12.8 m
14.4 s
T=
A
14.4 12.8
=
4.0
= 6.78 sec
d1 = 0.28 Vb t
= 0.28 34 2.5
= 23.8 m
d2 = 0.28 Vb T 2 s
= 0.28 34 6.78 2 12.8
= 90.14 m
d3 = 0.28 V T
= 0.28 50 6.78
= 94.92 m
OSD = d1+d2+d3
= 23.8+90.14+94.92
= 208.86 m
[IRC Recommendation Min. value of OSD = 235 m. Table No.1.8)
The distance d between the centre of the pavement & the center line of the inside lane may be taken as ½ the
width of the pavement at the center (being a two lane)
d= 6.255/2
= 3.127 m
180×SSD
α /2=
2𝜋(R−D)
180×62
= 2𝜋(90−3.127)
=20026’44.1"
= 90-((90 -3.127)×cos(20026’44.1"))
= 8.60 m.
Hence the minimum setback or clearance required to provide a clear vision for an SSD of 62m is 8.60 m.
v2
e =
225 R
65 2
=
225 200
e = 0.093
As the value is greater than maximum super elevation of 0.07, the actual super elevation to be provided is
restricted to 0.07
v2
f = 0.07
127 R
65 2
= 0.07
127 200
= 0.097
As the value is less than 0.15, the design is safe with a super elevation of 0.07
HERE
No. of Lanes n=1
Length of Wheel base l = 6 m
Width of the Pavement W = 5.5 m
Extra widening = Mechanical widening + Psychological widening
n l² v
We =
2R 9.5 R
1 6² 65
=
2 200 9.5 200
= 0.09 + 0.483
= 0.573 m
Provide an extra wide of 0.573 m and hence the total width of the pavement
B = W + We
B = 5.5+0.573
B = 6.073 m
65 2
= 0.278 65 2.5
254 0.36
= 45.175+46.20
SSD = 91.37 m
OVER TAKING SIGHT DISTANCE(OSD)
Here,
Total reaction time of the Driver, t = 2.5sec
Acceleration, A = 3.28 kmph / sec.
S=spacing between vehicles
= 65-16
= 49 kmph
S = 0.2 Vb 6
= 0.2 49 6
= 15.8 m
14.4 s
T =
A
14.4 15.8
=
3.28
= 8.32 sec
d1 = 0.28 Vb t
= 0.28 49 2.5
= 34.3 m
d2 = 0.28 Vb T 2 s
= 0.28 34 8.32 2 15.8
= 145.75 m
d3 = 0.28 V T
= 0.28 65 8.32
= 151.424 m
OSD = d1+d2+d3
= 34.3+145.76+151.424
= 331.484 m
[IRC Recommendation Min. value of OSD = 340 m. Table No.1.8)
SET BACK DISTANCE
The distance d between the centre of the pavement & the center line of the inside lane may be taken as ½ the
width of the pavement at the center (being a intermediate lane)
d= 6.073/2
= 3.036 m
180×SSD
α /2=
2𝜋(R−D)
180×91.37
= 2𝜋(200−3.036)
=13017’22.28"
= 200-((200 -3.036)×cos(13017’22.28"))
= 8.31 m. "
Hence the minimum setback or clearance required to provide a clear vision for an SSD of 91.37 m is 8.31 m.
v2
e =
225 R
65 2
=
225 450
e = 0.042
As the value is less than maximum super elevation of 0.07, the actual super elevation to be provided is 0.042
v2
f = 0.042
127 R
652
= 0.042
127 450
= 0.032
As the value is less than 0.15, the design is safe with a super elevation of 0.042
HERE
No. of Lanes n=1
Length of Wheel base l = 6 m
Width of the Pavement W = 5.5 m
Extra widening = Mechanical widening + Psychological widening
n l² v
We =
2R 9.5 R
1 6² 65
=
2 450 9.5 450
= 0.04 + 0.322
= 0.362 m
Provide an extra wide of 0.362 m and hence the total width of the pavement
B = W + We
B = 5.5+0.362
B =5.862 m
65 2
= 0.278 65 2.5
254 0.36
= 45.175+46.20
SSD = 91.37 m
= 0.2 49 6
= 15.8 m
14.4 s
T =
A
14.4 15.8
=
3.28
= 8.32 sec
d1 = 0.28 Vb t
= 0.28 49 2.5
= 34.3 m
d2 = 0.28 Vb T 2 s
= 0.28 34 8.32 2 15.8
= 145.75 m
d3 = 0.28 V T
= 0.28 65 8.32
= 151.424 m
OSD = d1+d2+d3
= 34.3+145.76+151.424
= 331.484 m
[IRC Recommendation Min. value of OSD = 340 m. Table No.1.8)
The distance d between the centre of the pavement & the center line of the inside lane may be taken as ½ the
width of the pavement at the center (being a intermediate lane)
d= 6.073/2
= 2.931m
180×SSD
α /2=
2𝜋(R−D)
180×91.37
= 2𝜋(450−2.931)
=5051’17.65"
= 450-((450 -2.931)×cos(5051’17.65"))
= 5.26 m.
Hence the minimum setback or clearance required to provide a clear vision for an SSD of 91.37 m is 5.26 m.
It is generally necessary to consider the quantities of material to be excavated or generally used in the highway
excavation process. This information can be useful in the development of a preliminary cost estimate for the
work to be undertaken. It can also be used as part of the design process in the selection of the final cross-section
and alignment characteristics of the roadway. Quantity estimates are often part of the information given to the
contractors bidding to complete the work.
Estimation of Earth work is based on the Longitudinal and Cross sections along the alignment of the road which
is to be constructed.
1.4.6.2 EXCAVATION (E) - refers to any excavated material. There are two main categories for excavated
material - ordinary material (O.M.) and rock.Both O.M. and rock are generally paid for by cubic meter in terms
of excavation cost (Rs./m3). Rock is generally handled as a separate cost because it is substantially more
expensive to excavate.
Borrow (B) - refers to the fill material that must be brought to the proposed highway site from outside the
highway cross section. Borrow does not include the material that is excavated on site for use as fill, The borrow
cost is normally given in Rs./m3, and this rate normally includes cost of excavating borrow. There may be
surcharge for borrow if excavated from someone’s property (B>=E).
1.4.6.3 EMBANKMENT
Process of raising the grade line of a highway above the existing ground level.
It may be raised due to following reasons…….
1. To keep the sub grade above the high ground water table.
2. To prevent damage to pavement due to surface & capillary water.
3. To maintain the design standards of highway with respect to vertical alignment.
Cross-section of Earthwork of road in banking or in cutting is usually in the form of Trapezium, and the
quantity of earthwork is calculated using formula…..
Quantity (or volume) = Sectional area Length
If B = Formation width S = Slope
d = Depth of section L = Chainage interval
Filling…
FIGURE NO 1.5
Cutting…
FIGURE NO 1.6
= b d s d L
2
1.5 DETERMINATION OF PAVEMENT THICKNESS:
1. On an average CBR value of 10% is considered and design of pavement thickness is done for this value.
2. From the information obtained from the PWD, it is found that about 10330 commercial vehicles run on that
proposed highway per day.
From the IRC design chart for 10% CBR it is found that the total thickness of pavement is 50cm. the different
construction materials some of which are locally available. Their CBR values and thickness are calculated.
365 1 r 1 A D F
n
N=
r
Where ,
r = annual growth
N = cumulative number of standard axle’s in m
A = initial profit in year of completion in lpcd
D = lane distribution factor
F = vehicles damage factor
N = design life
Now as per standard considering the values,
F=3
r = 7.5%
n = 20 years
we get,
N=
365 1 0.075 1 100 3
22
0.075
N=5.7 msa
From IRC; 37 2001 chart fig:1
The pavement thickness of 5.7MSA & CBR of 10%
the thickness of 500mm
According to pavement design catalogue plate 1(recommended design for traffic range 1-10MSA)
The preparation of subgrade includes all operation before the pavement structure could be laid over it and
compacted. Thus the preparation of subgrade would include site clearance, grading and compaction.
The common types of base course materials used in India for the construction of flexible pavement are “wet mix
macadam” (WMM), “water bound macadam” (WBM). WMM base consist of a well graded hard crushed
aggregate and adequate proportion of water mixed thoroughly in a mixing plant. The mix spread over the
prepared subbase course with mechanical paver and rolled to a required density.The materials are chosen as per
the standards specified by MORT&H.
Bituminous prime coat is the first application of a low viscosity liquid bituminous material over an existing
porous or absorbent pavement surface ,WMM base course that penetrates deep to the bottom aggregates and
forms the bond.
Tack coat is application of a small quantity of liquid bituminous binder of low viscosity over either a primed
granular surface or over an existing bituminous or cement concrete surface. Application of tack coat is also an
important part of preparation before laying a bituminous pavement layer over any other pavement layer .The
binder of tack coat is not expected to penetrate into the pavement surface and plug the voids but it forms the
bond between the bituminous base and wearing surface.
Bituminous base layer is laid on a prepared WMM and followed by the Bituminous wearing course and are
compacted to the required density, generally 98% of the lab density. The Material are chosen as per the
standards specified by MORT&H.
CONCLUSION
A ODR is proposed which connects Anchitageri to New layout near Timmasagar. This proposal is made
because of the reason that there is no proper road for the people. The road designed as a ODR.
Many alternatives were made for the alignment of the center line of road. Out of them, the best alignment is
selected which gives a balance section.
All the designs were made according to IRC standards.
1) Length of road is 1.00km.
2) Width of formation is 7.5m
3) Width of carriage way is 5.5m
4) Camber slope provided is 2.0%
5) Design speed
For first curve is 50Kmph
For second curve 65 kmph
For third curve 65 kmph
Hence, it is concluded that this road serves a useful purpose for the villagers
REFERENCE