Vous êtes sur la page 1sur 61

 

M‐29 Corridor Study 
City of St. Clair 
Michigan Department of Transportation – Bay Region 

DRAFT – March 29, 2018 
CS 77052, JN 131491 

Prepared By: 

 
 

 
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

TABLE OF CONTENTS 

References .................................................................................................................................................. vii 
ACRONYMS ................................................................................................................................................. vii 
EXECUTIVE SUMMARY ................................................................................................................................ vii 
I.  INTRODUCTION ..................................................................................................................................... 1 
II.  PREVIOUS STUDIES ................................................................................................................................ 1 
A.  Background ....................................................................................................................................... 1 
B.  M‐29 Corridor Study (2005) ‐ Spalding DeDecker Associates, Inc. ................................................... 1 
C.  M‐29 Corridor Analysis (2010) ‐ Spalding DeDecker Associates, Inc. ............................................... 2 
D.  M‐29 and Clinton Intersection Analysis (2010) ‐ Spalding DeDecker Associates, Inc. ...................... 2 
III.  STUDY OBJECTIVES ............................................................................................................................ 3 
IV.  METHODOLOGY ................................................................................................................................ 3 
A.  Public Agency and Stakeholder Coordination ................................................................................... 3 
B.  Public Participation ........................................................................................................................... 4 
  Public Input Meetings and Workshops ......................................................................................... 4 
  Survey Distribution and Results .................................................................................................... 4 
V.  EXISTING CONDITIONS ANALYSIS.......................................................................................................... 4 
A.  History ............................................................................................................................................... 4 
B.  Non‐Motorized Plans ........................................................................................................................ 6 
  St. Clair County Nonmotorized Guidelines (2005) ........................................................................ 6 
  St. Clair County Trails and Routes Master Plan (2008) ................................................................. 7 
C.  Land‐Use and Zoning ......................................................................................................................... 7 
D.  Traffic Operations ............................................................................................................................. 7 
  Field Traffic Data Collection and Observation .............................................................................. 7 
  Inventory ....................................................................................................................................... 7 
  Redevelopment ............................................................................................................................. 7 
E.  Safety Evaluation .............................................................................................................................. 8 
  Crash Analysis ............................................................................................................................... 8 
  Conflicts with roadways ................................................................................................................ 9 
  Conflicts with road‐users .............................................................................................................. 9 
F.  Right‐of‐Way Constraints .................................................................................................................. 9 
G.  Environmental Issues ........................................................................................................................ 9 

Page i
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

H.  Accessibility Issues .......................................................................................................................... 10 
I.  Future User Experience ................................................................................................................... 11 
VI.  USER NEEDS ANALYSIS .................................................................................................................... 12 
A.  Public Input ..................................................................................................................................... 12 
B.  Online Survey .................................................................................................................................. 12 
C.  Future Traffic Operations ................................................................................................................ 12 
D.  Future Needs ................................................................................................................................... 12 
VII.  ALTERNATIVE DESIGN ANALYSIS ..................................................................................................... 12 
A.  Option 1 – Traditional Road Diet .................................................................................................... 12 
  Description .................................................................................................................................. 12 
  Safety .......................................................................................................................................... 13 
  Accessibility ................................................................................................................................. 13 
  Functionality ............................................................................................................................... 13 
  Neighborhood Impacts ............................................................................................................... 13 
  Environmental Impacts ............................................................................................................... 13 
  Aesthetics .................................................................................................................................... 13 
  Cost ............................................................................................................................................. 13 
  Right‐of‐way Availability ............................................................................................................. 14 
  Consistency with Local Plans ................................................................................................... 14 
  Multiple Use Opportunities .................................................................................................... 14 
B.  Option 2 – Protected Bike Lanes ..................................................................................................... 14 
  Description .................................................................................................................................. 14 
  Safety .......................................................................................................................................... 14 
  Accessibility ................................................................................................................................. 14 
  Functionality ............................................................................................................................... 15 
  Neighborhood Impacts ............................................................................................................... 15 
  Environmental Impacts ............................................................................................................... 15 
  Aesthetics .................................................................................................................................... 15 
  Cost ............................................................................................................................................. 15 
  Right‐of‐Way Availability ............................................................................................................ 15 
  Consistency with Local Plans ................................................................................................... 15 
  Multiple Use Opportunities .................................................................................................... 15 
C.  Option 3 – Angled Parking with Two Lanes .................................................................................... 16 
 

Page ii
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

  Description .................................................................................................................................. 16 
  Safety .......................................................................................................................................... 16 
  Accessibility ................................................................................................................................. 16 
  Functionality ............................................................................................................................... 16 
  Neighborhood Impacts ............................................................................................................... 16 
  Environmental Impacts ............................................................................................................... 17 
  Aesthetics .................................................................................................................................... 17 
  Cost ............................................................................................................................................. 17 
  Right‐of‐Way Availability ............................................................................................................ 17 
  Consistency with Local Plans ................................................................................................... 17 
  Multiple Use Opportunities .................................................................................................... 17 
D.  Option 4 – Angled Parking with Three Lanes .................................................................................. 17 
  Description .................................................................................................................................. 17 
  Safety .......................................................................................................................................... 17 
  Accessibility ................................................................................................................................. 18 
  Functionality ............................................................................................................................... 18 
  Neighborhood Impacts ............................................................................................................... 18 
  Environmental Impacts ............................................................................................................... 18 
  Aesthetics .................................................................................................................................... 18 
  Cost ............................................................................................................................................. 18 
  Right‐of‐way Availability ............................................................................................................. 18 
  Consistency with Local Plans ................................................................................................... 18 
  Multiple Use Opportunities .................................................................................................... 18 
E.  Option 5 – Clinton Avenue Intersection Improvements ................................................................. 18 
  Description .................................................................................................................................. 18 
  Safety .......................................................................................................................................... 18 
  Accessibility ................................................................................................................................. 19 
  Functionality ............................................................................................................................... 19 
  Neighborhood Impacts ............................................................................................................... 19 
  Environmental Impacts ............................................................................................................... 19 
  Aesthetics .................................................................................................................................... 19 
  Cost ............................................................................................................................................. 19 
  Right‐of‐Way Availability ............................................................................................................ 19 
 

Page iii
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

  Consistency with Local Plans ................................................................................................... 19 
  Multiple Use Opportunities .................................................................................................... 19 
VIII.  DESIGN ALTERNATIVES ................................................................................................................... 20 
A.  Potential Improvements ................................................................................................................. 21 
  Special Emphasis Crosswalks ...................................................................................................... 21 
  Decorative Crosswalks ................................................................................................................ 22 
  Pedestrian Refuge Islands ........................................................................................................... 23 
  Staggered Crosswalk ................................................................................................................... 24 
  Enhanced Crosswalk Lighting ...................................................................................................... 24 
  Improved Corridor Lighting ......................................................................................................... 25 
  Contrasting Pavement................................................................................................................. 26 
  Pedestrian‐Activated Flashing LEDs in the Border of a Warning Sign ........................................ 27 
  Pedestrian Hybrid Beacon (HAWK Signal) .................................................................................. 28 
  Temporary Pedestrian Island .................................................................................................. 29 
  Extended Pedestrian Refuge Island ........................................................................................ 29 
  Curb Extensions at Intersections and Mid‐Block .................................................................... 30 
  Landscaping and Landscaped Boulevards ............................................................................... 31 
IX.  IMPLEMENTATION PLAN ................................................................................................................. 31 
A.  Option 1 .......................................................................................................................................... 31 
  Short Term .................................................................................................................................. 31 
  Medium Term ............................................................................................................................. 32 
  Long Term ................................................................................................................................... 32 
B.  Option 2 .......................................................................................................................................... 32 
  Short Term .................................................................................................................................. 32 
  Medium Term ............................................................................................................................. 32 
  Long Term ................................................................................................................................... 32 
C.  Option 3 .......................................................................................................................................... 32 
  Short Term .................................................................................................................................. 32 
  Medium Term ............................................................................................................................. 32 
  Long Term ................................................................................................................................... 32 
D.  Option 4 .......................................................................................................................................... 32 
  Short Term .................................................................................................................................. 32 
  Medium Term ............................................................................................................................. 32 
 

Page iv
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

  Long Term ................................................................................................................................... 32 
X.  CONCLUSIONS AND RECOMMENDATIONS ......................................................................................... 32 
 

LIST OF TABLES 

Table 1. Speed Limit Variations Along M‐29 ................................................................................................. 4 

Table 2. Proposed Improvements and Related Crash Reductions per Crash Type (MDOT) ......................... 8 

Table 3. Implementation Plan Matrix ......................................................................................................... 20 

Table 4. List of Proposed Treatments and Associated Cost ........................................................................ 31 

LIST OF FIGURES 

Figure 1. Location Map ................................................................................................................................. 5 

Figure  2.  ADA  Ramp  Opening  Along  Palmer  Park  325  feet  North  of  Jay  Street  Intersection  without  a 
Receiving Ramp on the Opposite Side of the Street ................................................................................... 10 

Figure 3. Non‐Compliant ADA Ramp Opening 245 feet North of Jay Street Intersection Without a Receiving 
Ramp on the Opposite Side of the Street. .................................................................................................. 11 

Figure 4. Proposed view of Option 1 at Jay Street looking north ............................................................... 13 

Figure 5. Proposed View of Option 2 at the Riverfront Pavilion ................................................................. 14 

Figure 6. Proposed View of Option 3 at the Riverfront Pavilion ................................................................. 16 

Figure 7. Proposed View of Option 4 at the Riverfront Pavilion ................................................................. 17 

Figure 8. Example of Special Emphasis Crosswalk ...................................................................................... 21 

Figure 9. Example of a Pedestrian Refuge Island ........................................................................................ 23 

Figure 10. Example of a Contrasting Pavement Crosswalk and Intersection ............................................. 26 

Figure 11. Example of a Crosswalk with a Flashing LED in the Border of a Warning Sign .......................... 27 

Figure 12. An Example of a Pedestrian Hybrid Beacon (HAWK) Signal ...................................................... 28 

Figure 13. An Example of a Temporary Pedestrian Island .......................................................................... 29 

Figure 14. Example of a Mid‐Block Crossing with Bump Out ..................................................................... 30 

   

Page v
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

LIST OF APPENDICES 

A.  Steering Committee Meeting Minutes  

1.  August 24, 2017 

B.  Conceptual Layouts 

   

Page vi
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

REFERENCES 

Spalding  DeDecker  Associates,  Inc.  (2005).  M‐29  Corridor  Study  .  St.  Clair:  Michigan  Department  of 
Transportation. 

Spalding DeDecker Associates, Inc. (2010). M‐29 and Clinton Intersection Analysis. St. Clair: City of St. Clair. 

Spalding DeDecker Associates, Inc. (2010). M‐29 Corridor Analysis. St. Clair: City of St. Clair. 

The Greenway Collaborative, Inc. (2008). St. Clair County Trails and Routes Master Plan. St. Clair County 
Parks and Recreation Commission. 

The  Greenway  Collaborative,  Inc.  and  Midwestern  Consulting.  (2005).  St.  Clair  County  Nonmotorized 
Guidelines. Michigan Department of Transportation. 

ACRONYMS 

ADA  Americans with Disabilities Act 

ADT  Average Daily Traffic 

MDOT  Michigan Department of Transportation 

RRFB  Rectangular Rapid Flashing Beacon 

SCCOTS  St. Clair County Transportation Study 

SEMCOG  Southeast Michigan Council of Governments 

TSC  Transportation Service Center 

vpd  vehicles per day 

EXECUTIVE SUMMARY 

To be completed later. 

Page vii
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

I. INTRODUCTION 

The  Michigan  Department  of  Transportation  (MDOT)  Bay  Region  has  commissioned  this  study  to 
evaluate roadway improvements along the M‐29 corridor that will increase safety for pedestrians and 
bicyclists, increase mobility, provide traffic calming, and be easily implemented.  These improvements 
will be implementable in single locations or throughout the entire corridor.  Additionally, low‐, mid‐, 
and high‐range cost options will be evaluated for potential future implementation.  

II. PREVIOUS STUDIES 

A. Background 
Several previous studies have been completed for the M‐29 corridor in the City of St. Clair.  These 
studies have looked at several potential options for improvements, such as reducing the number 
of  lanes  from  four  to  three,  placing  boulevards,  and  non‐motorized  improvements  along  the 
corridor.  The studies presented comprehensive alternatives for the whole corridor that were high 
cost  and  therefore  have  not  been  implemented.    Below  is  a  summary  of  the  previous  studies 
completed. 

B. M‐29 Corridor Study (2005) ‐ Spalding DeDecker Associates, Inc. 
In 2005, MDOT worked with the City of St. Clair and volunteers who composed the M‐29 Corridor 
Planning Committee to develop a plan that included a long‐term vision for the corridor.  The study 
focused on safety, capacity, and ride quality while offering the following goals. 

 Plan for a continuous non‐motorized path 
 Reduce roadway noise 
 Encourage motorists to obey posted speeds 
 Improve safety at pedestrian crossings 
 Improve turning movements, especially at Clinton Street 
 Provide adequate on‐street parking 
 Improve aesthetics and suggest wayfinding signage and strategic placement of signs 

The  objectives  identified  in  this  study  were  intended  to  provide  recommendations  for  several 
desirable corridor improvements along M‐29 to be incorporated into future projects.  Due to the 
size and scope of the projects, none of the following alternatives presented in the study were 
implemented. 

The following were the options identified in this study: 

1. A boulevard with two lanes in each direction, 10‐foot parking lanes, and decorative median 
street lighting ‐ $1.8M 
2. Three lanes, one in each direction with CLTL and 10‐foot parking lanes on both sides with 10‐
foot non‐motorized path on east side ‐ $1.55M 
 

Page 1
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

3. Three lanes, one in each direction with CLTL and angled parking on east side, and 10‐foot non‐
motorized path on east side ‐ $1.66M 
4. North and south of downtown – road diet to three lanes, one in each direction with CLTL and 
6‐foot bike lanes on each side.  Achieved by re‐paving to match joint lines with lane lines ‐ 
$230K 

C. M‐29 Corridor Analysis (2010) ‐ Spalding DeDecker Associates, Inc. 
In 2010, the City of St. Clair commissioned a study to evaluate and compare the existing roadway 
operations to a proposed alternative which replaced the center left turn lane with a proposed 
boulevard  with  street  lights.    The  two  travel  lanes  in  each  direction  would  remain  along  with 
adjacent parallel parking on both sides. 

The existing and proposed cross‐section was evaluated from Clinton to Vine.  For the proposed 
alternative, left turns were allowed only at Trumbull, Jay, and Vine; therefore, these were the only 
intersections evaluated for existing and proposed conditions.  The level of service for the through 
movements along the corridor was an A for both existing and proposed cross‐sections.  The left 
turns ranged from level of service A to B for both Jay and Trumbull AM and PM peak hours but 
fell to a level of service C to F for AM and PM peak hours at Vine.   

This evaluation concluded that the corridor would continue to operate at a high level of service if 
a boulevard was added and left turns limited; however, a traffic signal would likely be warranted 
at  the  intersection  at  Vine  to  accommodate  the  increase  in  left  turns  from  eastbound  to 
northbound.  

D. M‐29 and Clinton Intersection Analysis (2010) ‐ Spalding DeDecker Associates, Inc. 
In 2010, the City of St. Clair contracted for a study of the intersection at M‐29 and Clinton Avenue.  
The  study  was  to  provide  alternatives  for  improving  the  intersection  operations,  including  the 
ingress and egress to the driveway of the Voyageur (east leg).  The alternatives studied were as 
follows: 

 Addition of an actuated driveway signal phase for the westbound driveway approach 
 Addition of a left turn phase for southbound M‐29 traffic turning into the driveway 
 Addition of both options above 
 Reconstruction of the intersection with a roundabout 

The results of the analysis showed that the intersection operated at a level of service C or above 
through both the AM and PM peak hours under existing conditions and future volumes projected 
only  a  slight  increase  in  delay.    The  first  three  alternatives  remained  at  an  acceptable  level  of 
service for the overall intersection.  It was determined that the roundabout would not be feasible 
without the acquisition of considerable right of way and would still require a signal for the bridge.  
It  was  concluded  that  the  first  option  of  adding  an  actuated  driveway  signal  phase  was  most 
desirable.   

Page 2
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

III. STUDY OBJECTIVES 

This study looks to build upon the recommendations identified in the previous studies along the M‐
29  corridor  that  focus  on  pedestrian,  bicycle  safety,  and  mobility.    By  expanding  on  the  potential 
improvements identified in previous plans, this study will produce a set of implementable investments 
that will improve bicycle and pedestrian safety and mobility along the M‐29 corridor in the City of St. 
Clair.  The objective is to identify feasible improvements that will improve mobility and safety for all 
modes of traffic. 

The study will identify and evaluate short‐, medium‐ and long‐term transportation system needs to 
enhance bike and pedestrian mobility while maintaining vehicular and bus transit operations.  Costs 
for these enhancements will range from low‐to‐high to allow implementation over time. 

All existing and proposed pedestrian and bicycle paths, transit stops/routes, and activity centers such 
as schools, businesses, and parks/open space should be considered to transform the corridor into a 
multi‐modal environment that balances the needs of all modes and is sensitive to evolving land use 
and land development plans.  

IV. METHODOLOGY 

A. Public Agency and Stakeholder Coordination 
To  assure  public  buy‐in  for  the  proposed  alternatives,  a  steering  committee  was  created, 
comprising  of  representatives  from  the  City  of  St.  Clair,  St.  Clair  County  Transportation  Study 
(SCCOTS), Southeast Michigan Council of Governments (SEMCOG), St. Clair County, and MDOT.  
The  committee  was  responsible  for  providing  initial  comments,  reviewing  technical  data, 
reviewing the draft plan, reviewing workshop material, and reviewing the final plan.  

Following is a list of the representatives invited to participate on the Steering Committee 

 Jay Reithel – MDOT Bay Region 
 Erik Tamlyn – MDOT Huron Transportation Service Center (TSC) 
 Trevor Block – MDOT Huron TSC 
 Brian Pawlik – SEMCOG 
 Mike Booth – City of St. Clair 
 Davis Struck – St. Clair County Planning 
 Lindsay Wallace – SCCOTS 
 Jeff Bohm – St. Clair County Board of Commissioners 
 Kirk Weston – St. Clair County Road Commission 
 William Hazelton – St. Clair County Road Commission 
 Randy Maiers – Community Foundation of St. Clair County 
 Dan Casey – Economic Development Alliance of St. Clair County   

Page 3
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

B. Public Participation 
Public Input Meetings and Workshops 
Survey Distribution and Results 

V. EXISTING CONDITIONS ANALYSIS 

A. History 
M‐29 is a state trunkline that begins at I‐94 in Chesterfield Township in Macomb County, and runs 
easterly along the northern shore of Lake St. Clair into St. Clair County.  At Algonac, M‐29 turns 
northerly and runs along the St. Clair River through Marine City, St. Clair, and Marysville to its 
terminus at Business Loop I‐94, just south of Port Huron.  Within the City of St. Clair, M‐29 is a 
four‐lane  roadway  between  Palmer  Road  and  just  south  of  the  northern  city  limits,  where  it 
transitions to the two‐lane roadway section that continues northerly to Marysville.  Between the 
southern city limits and Palmer Road, M‐29 is a two‐lane roadway.  It is known locally as Oakland 
Avenue at the south end of the city, and Riverside Avenue in the business district and north end 
of the city.  Sidewalk is located along the west side of M‐29 between the South Riverside Drive 
and Oakland Avenue intersection and the northern city limits.  From just south of the Pine River 
to just south of Vine Street, this sidewalk is located adjacent to the back of curb.  Along the east 
side of M‐29, sidewalk is limited to between Clinton Avenue and approximately 1,000 feet north 
of Vine Street.  This sidewalk is primarily located adjacent to the back of curb as well.  In this same 
area, from the Pine River to the St. Clair Inn, there is a boardwalk located adjacent to the St. Clair 
River.  A location map of the study area can be found in Figure 1 on the following page. 

The  segment  of  M‐29  for  this  study  is  the  0.7‐mile‐long  section  between  Clinton  Avenue  and 
Brown Street.  Within this segment, M‐29 is a four‐lane roadway with on‐street parallel parking 
in  both  the  northbound  and  southbound  directions.    The  average  daily  traffic  (ADT)  for  this 
segment of M‐29 is 11,550 vehicles per day.  There are currently four pedestrian crosswalks within 
this segment, located at Clinton Avenue, Jay Street, Riverview Plaza, and the St. Clair Inn.  The 
intersection of M‐29 and Clinton Avenue is signalized and located immediately north of the M‐29 
over the Pine River Bascule Bridge.  Speeding has been identified as a concern throughout the 
study limits, with an emphasis on the northern end due, in part, to the steep roadway grade for 
southbound traffic from Brown Street to Vine Street which increases vehicular speeds heading 
into the business district.  Table 1 shows the speed variations along M‐29 in the City of St. Clair. 

Table 1. Speed Limit Variations Along M‐29 
Speed (MPH)  From  To 

35  Southern City Limits  Clinton Avenue 

30  Clint Avenue  Brown Street 

40  Brown Street  Northern City Limits 

Page 4
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

 
Figure 1. Location Map 
 

Page 5
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

At the northern end of the corridor, on the east side of M‐29, immediately north of Vine Street, 
is the St. Clair Inn.  Opened in 1926, the St. Clair Inn was a prominent vacation spot for boaters 
and travelers from out of town.  The St. Clair Inn had 78 rooms and was a full‐service hotel to 
accommodate business and personal events.  In 1995, the English Tudor‐style hotel was put on 
the National Registers of Historic Places.  However, the St. Clair Inn has been vacant since February 
2014 when it was foreclosed on.  In January 2016, Jeff Katofsky purchased the St. Clair Inn and, in 
September 2017, announced that work on the historic building would begin.  This renovation is 
projected to be complete and the inn open for business in the spring of 2019. 

In the central portion of the corridor is the St. Clair Riverview Plaza on the west side of M‐29.  
Enhancements were completed at the plaza in 2014 which included outdoor seating, green space, 
and  an  Americans  with  Disabilities  Act  (ADA)‐compliant  mid‐block  crossing.    The  plaza  houses 
several restaurants and shops with parking behind the building.  This plaza is a destination for 
visitors and residents year‐round.  Palmer Park is located on the east side of the corridor between 
M‐29  and  the  St.  Clair  River  and  is  a  destination  for  residents  and  visitors  during  the  spring, 
summer, and fall.  The park is accessible from the adjacent northbound on street parking and from 
the southbound on street parking by using the crosswalks.  

At the southern end of the corridor is intersection  of Clinton  Avenue and M‐29, the Voyageur 


restaurant, and the Pine River Bascule Bridge.  The Voyageur is located on the east side, with two 
driveway entrances onto M‐29, one for employees and patrons and one for deliveries.  The Pine 
River Bascule Bridge is located immediately south of the intersection and opens on the half hour 
and hour during boating months.  Drivers on northbound M‐29 must stop behind the Voyageur 
driveway approach.  Drivers on Clinton Avenue are only allowed left and right turns, but entering 
the  Voyageur  requires  a  through  movement,  sometimes  causing  confusion.    Drivers  on 
southbound M‐29, who wish to turn left into the Voyageur, must wait for traffic in the opposite 
direction to clear in addition to northbound drivers waiting to turn left and people exiting the 
Voyageur by turning right.  

On street parallel parking is available on the east side of M‐29 from just north of the Voyageur 
service driveway and continues to the northerly driveway for the St. Clair Inn.  On street parking 
in the southbound direction begins just after Trumbull Street and continues until the Riverview 
Plaza parking lot.  There are currently no bike lanes within the corridor, so bikers use the street 
or sidewalks.  

B. Non‐Motorized Plans 
St. Clair County Nonmotorized Guidelines (2005) 
The study looked at various MDOT design guidelines to determine if they met guidelines for 
bicycle facilities.  The study developed a recommended general policy statement which states 
bicycle  and  pedestrian  ways  shall  be  established  in  new  construction  and  reconstruction 
projects  in  all  urbanized  areas  unless  bicycles  and  pedestrians  are  prohibited  by  law  from 
using the roadway, the cost of establishing bikeways or walkways exceeds 25 percent of the 
cost of the overall project, or if there is absence of need.  Additionally, the recommended 
general  policy states  that  sidewalks, shared use paths, street crossings, pedestrian signals, 
transit stops and facilities, and all connecting pathways shall be designed and constructed so 
 

Page 6
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

that all pedestrians, including those with disabilities, can travel safely and independently.  The 
study highlights the M‐29 corridor in the City of St. Clair for planned nonmotorized roadway 
improvements.  Examples are given of roadway layouts with bike lanes and how to transition 
from/to the bike lane on the roadway.  The layouts include the use of the shared‐use arrow 
(sharrow) where road widths will not accommodate a full bike lane.   

St. Clair County Trails and Routes Master Plan (2008) 
The  study  evaluated  the  existing  trail  system,  identified  gaps,  and  prioritized  the 
implementation  of  proposed  improvements.  M‐29  through  St.  Clair  is  identified  for  a 
proposed on‐road bike route as a part of the Bridge to Bay Trail.  This trail has existing off‐
road facilities along Carney Drive in the City.  The priority identified for this implementation 
is to upgrade the existing facilities. 

C. Land‐Use and Zoning 
From the 2012 City of St. Clair Community Comprehensive Plan, the current land use along the M‐
29 corridor within the study limits is commercial on the west side with a small area of multiple‐
family residential just  north of Clinton  and parks, recreation, and open space  on the east side 
within the limits of Palmer Park.  Outside of the park, the east side is also commercial.  North of 
the St. Clair Inn, both the east and west side of M‐29 is single‐family residential.  The zoning plan 
included as a part of the comprehensive plans identifies this commercial area as the Downtown 
Redevelopment  Area  and  discusses  the  desire  to  implement  complete  streets  through  the 
corridor for convenient access between the downtown buildings and Palmer Park. 

D. Traffic Operations 
Field Traffic Data Collection and Observation 
Traffic volumes were taken from hose counts between 2003 and 2017 for the corridor.  In 
2017, the ADT was 11,550 vehicles with AM and PM peak hour volumes of about 400 vehicles.  
A  growth  rate  of  0.5  percent  was  used  to  model  for  2025  and  2045  traffic  volumes  and 
projected  an  ADT  of  12,025  vehicles  and  13,300  vehicles,  respectively.    From  observation, 
volumes may grow further due to the reopening of the St. Clair Inn.  

Pedestrian crosswalk counts were collected over an 8‐hour period, on Friday, August 25, 2017 
at the three crosswalk locations: Jay Street, Riverview Plaza, and the St. Clair Inn.  The counts 
show that more people travel westbound at Jay Street and more people travel eastbound at 
the Riverview Plaza.  Pedestrian traffic at the St. Clair Inn crosswalk is significantly lower than 
the others.  Bicycle traffic was 11 percent and 15 percent for Jay Street and Riverview Plaza, 
individually.  

Inventory 
To be completed later. 

Redevelopment 
To be completed later.   

Page 7
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

E. Safety Evaluation 
Crash Analysis 
A crash analysis was completed for the corridor.  Crash reports (UD‐10s) were collected over 
a five‐year period from 2012‐2016 and show 67 crashes.  Nineteen of the crashes resulted in 
injures,  both  major  and  minor.    Listed  below  are  the  number  of  crashes  per  crash  type 
reported. 

 Three (3) were head‐on left turn crashes 
 Twenty (20) were sideswipe crashes 
 Fifteen (15) were angle crashes 
 Twenty‐four (24) were rear end crashes 
 Five (5) were single motor vehicle or other crashes 
For the types of crashes experienced along the corridor, potential roadway improvements to 
mitigate each crash type can be found in Table 2 below. 
Table 2. Proposed Improvements and Related Crash Reductions per Crash Type (MDOT) 
Proposed Improvement % Reduction Associated Crash Types
80% Rear‐End Left‐Turn
50% Head‐On Left‐Turn
Center Left‐Turn Lane ‐ Install 
20% Head‐On, Sideswipe Opposite, Angle
15% Non Left‐Turn Rear‐End
50% Suburban ‐ All Crash Types
Road Diet (4‐3 Lane Conversion) ‐ Install
30% Urban ‐ All Crash Types
Box Span Signal ‐ Upgrade from Diagonal Span 10% All Applicable Crashes+
Protected Left‐Turn Signal Phase ‐ Add 30% Left‐Turn
Signal Head Size ‐ Increase to 12 " 10% All Applicable Crashes+
Signal Optimization & Timing Updates 10% All Applicable Crashes+
30% Angle
Intersection Improvements (Realignment, Sight‐
15% Rear‐End
Distance Improvements, Radii Improvements, 
Etc.) 10% Head‐On, Sideswipe, Pedestrian, Bicycle, 
Left‐Turn Related  
Ten crashes occurred due to a driver turning left.  The most notable intersections are Vine 
Street, Jay Street, and Brown Street.  There was a crash a Brown Street which resulted in a 
serious personal injury.  These crashes may be mitigated with a road diet which will allow for 
the addition of a center left turn lane.  

There  were  also  multiple  accidents  due  to  cars  utilizing  the  on‐street  parking  and  drivers 
changing lanes.  These crashes may be mitigated with cross‐sectional improvements to the 
roadway through restriping or permanent roadway modifications. 

Thirty‐three  crashes  occurred  at  the  intersection  of  Clinton  Avenue  and  M‐29.    Of  these 
crashes, six occurred from vehicles entering or exiting The Voyageur restaurant.  Only one 
resulted in personal injury; however, these crashes could potentially be mitigated through 

Page 8
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

cross‐sectional  improvements.    MDOT  is  currently  analyzing  different  options  to  improve 
safety and operations at this intersection. 

Although none of the reported crashes involved pedestrians or bikers, there may have been 
near miss crashes that occurred.  

Conflicts with roadways 
Conflicts with road‐users 

F. Right‐of‐Way Constraints 
The existing road right‐of‐way is 100 feet through the limits of the corridor being studied.  The 
roadway width varies from 48 feet in areas without parking to 68 feet in areas where parking is 
present on both sides of M‐29.  The only constraints are with the building locations at the right‐
of‐way which will limit the potential to complete sidewalk improvements along the west side of 
the street. 

G. Environmental Issues 
To be completed later.   

Page 9
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

H. Accessibility Issues 
While there are four crosswalks within the corridor, there are also two locations in which there 
are ADA ramps with no ramp opening on the other side of the street.  Pictures of these locations 
are shown in Figure 2 and Figure 3. 

 
Figure 2. ADA Ramp Opening Along Palmer Park 325 feet North of Jay Street Intersection 
without a Receiving Ramp on the Opposite Side of the Street 

Page 10
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

 
Figure 3. Non‐Compliant ADA Ramp Opening 245 feet North of Jay Street Intersection Without 
a Receiving Ramp on the Opposite Side of the Street. 

These locations can cause confusion for pedestrians looking to cross the road, especially since one 
location leads to an entrance for Palmer Park on the east side.  The ramp on the west side is just 
south of the Palmer Park location. 

I. Future User Experience 
Work  to  restore  the  St.  Clair  Inn  began  Monday,  September  11th  and  is  expected  to  continue 
through  May  2019.    The  St.  Clair  Inn  has  been  vacant  since  2014  but  is  set  to  reopen  after 
construction is completed.  The inn is looking to bring significant business back to the City of St. 
Clair,  becoming  a  resort  hotel  and  providing  facilities  for  various  events.    The  proposed 
improvements will utilize not only the existing building on the eastern side of M‐29, but includes 
a proposed building on the west side of M‐29 which will house meeting rooms and hotel services.  
It is anticipated that this redevelopment will bring additional pedestrian traffic along the M‐29 
corridor, increasing the use of crosswalks and sidewalks through downtown St. Clair. 

Page 11
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

VI.  USER NEEDS ANALYSIS 

A. Public Input 
To be completed later. 

B. Online Survey 
To be completed later. 

C. Future Traffic Operations 
To be completed later. 

D. Future Needs 
To be completed later. 

VII. ALTERNATIVE DESIGN ANALYSIS 

A review of the existing pavement widths, existing and future estimated traffic volumes, and safety 
evaluation promote a road diet along the corridor.  Several options exist which provide a reduction in 
the through lanes from two in each direction to one, while providing auxiliary left and right turn lanes 
where  needed.    Each  option  offers  a  low,  medium,  and  high  cost  treatment  option  to  allow  for 
immediate and future roadway treatments to occur.  These options are intended to be constructed 
over time utilizing the alternatives presented in Section VIII.  Layouts vary in the location of proposed 
parking, the type of parking proposed, the location of bike lanes, and pedestrian crossing treatments.  
Each option is detailed below. 

A. Option 1 – Traditional Road Diet 
Description 
Option  1  is  a  traditional  four‐  to  three‐lane  conversion  with  one  lane  in  each  direction,  a 
center left turn lane, a 5‐foot bike lane in each direction, and parallel parking.  A conceptual 
layout of this option can be seen in Figure 4. 

Page 12
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

 
Figure 4. Proposed view of Option 1 at Jay Street looking north 
Safety 
A  standard  four‐lane  to  three‐lane  conversion  would  mitigate  crashes  that  occurred  when 
drivers were turning left into either the westbound side streets or businesses.  It would also 
force  drivers  to  travel  at  slower  speeds  as  there  would  be  no  opportunity  to  pass  slower 
moving vehicles. 

Accessibility 
To be completed later. 

Functionality 
The  current  ADT  for  M‐29  along  the  study  section  is  11,550  with  a  future  ADT  in  2045  of 
13,300 vehicles per day (vpd).  A three‐lane roadway has been shown to operate at the same 
capacity as a four‐lane roadway at ADTs less than 15,000 vpd.  The proposed Option 1 layout 
will allow the existing on street parking to be retained with 126 spaces, add bike facilities, and 
increase safety with the addition of a left turn lane through the study segment. 

Neighborhood Impacts 
To be completed later. 

Environmental Impacts 
To be completed later. 

Aesthetics 
To be completed later. 

Cost 
To be completed later.   

Page 13
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Right‐of‐way Availability 
To be completed later. 

Consistency with Local Plans 
To be completed later. 

Multiple Use Opportunities 
To be completed later. 

B. Option 2 – Protected Bike Lanes 
Description 
Option 2 is similar to Option 1 in that it is a road diet with a lane in each direction, a center 
left  turn  lane,  and  parking  on  both  sides  of  the  roadway.    Additionally,  this  option  offers 
protected bike lanes by placing a 10‐foot‐wide bi‐directional bike lane along the eastern curb 
line.  The roadway width allows for a 4‐foot buffer separating the bike lanes from the parallel 
parking along the east side of M‐29.  This buffer would be marked and contain delineators to 
make the buffer more visible and highlight the separation of vehicles from bikes.  A conceptual 
layout of this option can be seen in Figure 5. 

 
Figure 5. Proposed View of Option 2 at the Riverfront Pavilion 
Safety 
This option offers the same overall safety benefits of Option 1 with increased safety for the 
bicyclists due to the buffered area between the parked cars and the bike lanes.  When bike 
lanes  are  adjacent  to  parking  lanes,  there  is  a  potential  for  injury  to  bicyclists  due  to 
interaction with the vehicles while the vehicle is entering or exiting the parking area and/or 
when a driver enters or exits their car. 

Accessibility 
To be completed later. 
 

Page 14
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Functionality 
The  current  ADT  for  M‐29  along  the  study  section  is  11,550  with  a  future  ADT  in  2045  of 
13,300 vpd.  A three‐lane roadway has been shown to operate at the same capacity as a four‐
lane roadway at ADTs less than 15,000 vpd.  The proposed Option 2 layout will operate in a 
similar fashion to the Option 1 layout by allowing the existing on street parking to be retained 
with 114 spaces, adding bike facilities, and increasing safety with the addition of a left turn 
lane through the study segment. 

Neighborhood Impacts 
To be completed later. 

Environmental Impacts 
To be completed later. 

Aesthetics 
To be completed later. 

Cost 
To be completed later. 

Right‐of‐Way Availability 
To be completed later. 

Consistency with Local Plans 
To be completed later. 

Multiple Use Opportunities 
To be completed later.   

Page 15
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

C. Option 3 – Angled Parking with Two Lanes 
Description 
Option  3  incorporates  the  use  of  reverse  angle  parking  along  the  eastern  curb  line.    This 
parking  maneuver  is  considered  easier  to  complete  than  parallel  parking.    The  remaining 
cross‐section is composed of a parallel parking lane along the western curb line, a 6‐foot bike 
lane, 2‐ to 12‐foot vehicular lanes  (one in each direction), a 6‐foot bike lane, and a 4‐foot 
buffer area between the bike lane and the reverse angle parking.  A conceptual layout of this 
option can be seen in Figure 6. 

 
Figure 6. Proposed View of Option 3 at the Riverfront Pavilion 
Safety 
Reverse angle parking is considered safer than traditional pull in parking because the driver is 
able to see traffic and bicyclists as they pull out of the parking stall.  Additionally, the driver 
and passengers can exit the vehicle away from passing traffic and eliminates the “door zone” 
for passing bicyclists. 

Accessibility 
To be completed later. 

Functionality 
The  current  ADT  for  M‐29  along  the  study  section  is  11,550  with  a  future  ADT  in  2045  of 
13,300 vpd.  The proposed Option 3 layout accommodates on street parking with 135 spaces 
and adds bike facilities but the reduction from four to two lanes through the study section is 
anticipated  to  cause  delays  for  through  traffic  due  to  left  turns  onto  Trumbull  Street,  Jay 
Street, and Vine Street.  This decrease in capacity could lead to an increase in crashes through 
the corridor. 

Neighborhood Impacts 
To be completed later. 
 

Page 16
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Environmental Impacts 
To be completed later. 

Aesthetics 
To be completed later. 

Cost 
To be completed later. 

Right‐of‐Way Availability 
To be completed later. 

Consistency with Local Plans 
To be completed later. 

Multiple Use Opportunities 
To be completed later. 

D. Option 4 – Angled Parking with Three Lanes 
Description 
This option also includes the use of reverse angle parking along the eastern curb line.  The 
remaining cross‐section includes a 6‐foot bike lane, two vehicular lanes, one in each direction, 
with  a  left  turn  lane,  and  a  6‐foot  bike  lane  adjacent  to  the  reverse  angle  parking.    A 
conceptual layout of this option can be seen in Figure 7. 

 
Figure 7. Proposed View of Option 4 at the Riverfront Pavilion 
Safety 
In this option the parallel parking is removed leaving only the safer reverse angle parking and 
the added capacity and safety of a left turn lane.   

Page 17
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Accessibility 
To be completed later. 

Functionality 
The  current  ADT  for  M‐29  along  the  study  section  is  11,550  with  a  future  ADT  in  2045  of 
13,300 vpd.  A three‐lane roadway has been shown to operate at the same capacity as a four‐
lane roadway at ADTs less than 15,000 vpd.  The proposed Option 4 layout will allow for on 
street parking with 89 spaces along the eastern side of the road, adds bike facilities, and will 
increase safety with the addition of a left turn lane through the study segment. 

Neighborhood Impacts 
To be completed later. 

Environmental Impacts 
To be completed later. 

Aesthetics 
To be completed later. 

Cost 
To be completed later. 

Right‐of‐way Availability 
To be completed later. 

Consistency with Local Plans 
To be completed later. 

Multiple Use Opportunities 
To be completed later. 

E. Option 5 – Clinton Avenue Intersection Improvements 
Description 
A proposed improvement for the intersection of Clinton Ave. & M‐29 would be to update the 
signal timing to have a phase that allows those to enter and exit The Voyager driveway approach 
along with the addition of a left turn only lane on northbound and southbound M‐29. The 
addition of the left turn lane on southbound M‐29 would give drivers entering the driveway 
approach a designated lane while waiting for a green arrow to turn left. Due to there being a left 
turn only lane on southbound, a left turn only lane would be needed for northbound as well. 
The green arrow would come from updating the signal. An update to the signal would have to 
have green arrows for left turns on northbound and southbound M‐29, a whole cycle for the 
driveway approach, and a cycle for Clinton Ave. Separating the signal cycle for each individual 
direction will significantly decrease the crashes at this intersection.  This intersection is currently 
being analyzed separated by the MDOT Bay Region office. 
Safety 
To be completed later.   

Page 18
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Accessibility 
To be completed later. 

Functionality 
To be completed later. 

Neighborhood Impacts 
To be completed later. 

Environmental Impacts 
To be completed later. 

Aesthetics 
To be completed later. 

Cost 
To be completed later. 

Right‐of‐Way Availability 
To be completed later. 

Consistency with Local Plans 
To be completed later. 

Multiple Use Opportunities 
To be completed later.   

Page 19
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

VIII. DESIGN ALTERNATIVES 

Previously completed studies have offered several options for corridor improvements, but they have 
not  been  implemented  due  to  their  entire  corridor  impacts  and  the  high  cost  of  proposed 
enhancements.  Following, we present several options for traffic calming and improved pedestrian 
and bicycle safety.  These options can be implemented in one location or throughout the corridor.  
Initially pavement markings will be utilized to alter the corridor cross‐section with permanent changes 
implemented over time.  Each of the following potential improvements are not compatible with the 
proposed final roadway cross sections in Section VII.  An implementation chart is included in Table 3 
to  better  illustrate  how  the  improvements  can  be  included  in  the  proposed  roadway  design 
alternatives presented in Section VII. 

Table 3. Implementation Plan Matrix 

Medium Cost  High Cost 
Option Low Cost Improvements
Improvements Improvements

Improved Corridor Lighting Curb Extensions at  Extended Pedestrian 


Special Emphasis Crosswalk Intersections and Mid‐ Islands
Decorative Crosswalk Block Pedestrian Hybrid 
1 Enhanced Crosswalk Lighting Pedestrian Refuge Islands Beacon
Temporary Pedestrian Island Staggered Crosswalks Landscaping and 
Contrasting Pavement Warning Signs with Flasing  Landscaped 
Raised Crosswalks LEDS Boulevards
Improved Corridor Lighting
Special Emphasis Crosswalk
Pedestrian Refuge Islands
Decorative Crosswalk Pedestrian Hybrid 
2 Warning Signs with Flasing 
Enhanced Crosswalk Lighting Beacon
LEDS
Temporary Pedestrian Island
Contrasting Pavement
Improved Corridor Lighting
Curb Extensions at 
Special Emphasis Crosswalk
Intersections and Mid‐
Decorative Crosswalk Pedestrian Hybrid 
3 Block
Enhanced Crosswalk Lighting Beacon
Warning Signs with Flasing 
Contrasting Pavement
LEDS
Raised Crosswalks
Improved Corridor Lighting
Curb Extensions at 
Special Emphasis Crosswalk
Intersections and Mid‐
Decorative Crosswalk Pedestrian Hybrid 
4 Block
Enhanced Crosswalk Lighting Beacon
Warning Signs with Flasing 
Contrasting Pavement
LEDS
Raised Crosswalks

Page 20
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

A. Potential Improvements 
Special Emphasis Crosswalks 
Existing crosswalks along M‐29 are both mid‐block and at intersections.  To enhance driver 
awareness of the crosswalk locations, special emphasis crosswalk markings can be used.  The 
markings are 12‐inch white longitudinal lines that are spaced 2 feet apart the length of the 
crosswalk.  These crosswalks are already marked at the intersection of M‐29 and Jay Street 
and in front of the Riverview Plaza.  The existing markings are worn and should be restriped.  
These markings can be added to the intersection at M‐29 and Clinton Avenue, in front of the 
St.  Clair  Inn,  and  any  additional  locations  that  crosswalks  are  proposed.    This  cost  for  this 
treatment is approximately $1,500 per crosswalk location. 

 
Figure 8. Example of Special Emphasis Crosswalk   

Page 21
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Decorative Crosswalks 
To  enhance  the  crosswalks  further,  after  placement  of  the  special  emphasis  crosswalk, 
decorative paint may be added to further highlight the crosswalk.  This could be in the form 
of a city logo or colorful paint applied to the pavement surface.  The cost for this treatment is 
approximately $2,500 per crosswalk location. 

 
   

Page 22
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Pedestrian Refuge Islands 
Pedestrian refuge islands allow pedestrians to cross one direction of traffic at a time.  This 
decreases the complexity of the crossing for the pedestrian.  The presence of the island can 
also have a calming effect on vehicular traffic.  Studies have shown that the installation of 
pedestrian  refuge  islands  have  decreased  pedestrian  and  vehicular  crashes  and  decreased 
vehicular speeds on the roadway.  This treatment is only applicable if the chosen cross‐section 
includes a left turn lane that will allow for placement of the pedestrian refuge island without 
compromising  required  stacking  length  for  left  turn  vehicles.    The  cost  for  this  treatment 
averages $13,500 per location. 

 
Figure 9. Example of a Pedestrian Refuge Island   

Page 23
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Staggered Crosswalk 
The design of the staggered crosswalk is such that it forces pedestrians to cross one direction 
of traffic and then turn and face oncoming traffic in the opposite direction before crossing the 
other  half  of  the  street.    The  crossing  utilizes  a  pedestrian  refuge  island  to  protect  the 
pedestrian from the roadway traffic with openings on each side offset from one another.  This 
treatment is intended to be used at midblock crossing locations.  The cost for this type of 
treatment averages $15,000 per location. 

 
Enhanced Crosswalk Lighting 
To better illuminate the pedestrian crossings, proper street lighting should be considered at 
each crossing location.  Overhead lighting should be placed on each side of the crosswalk to 
properly  light  the  crossing  for  the  pedestrian  and  to  illuminate  the  pedestrian  for  the 
approaching vehicles.  The cost for this treatment averages $2,500 per crosswalk. 

 
   

Page 24
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Improved Corridor Lighting 
Currently, there are overhead cobra lights along the east side of the roadway.  It is suggested 
that a luminescence survey be completed to determine if and where street lighting is needed 
along the west side of the street to better illuminate the corridor for both pedestrians and 
vehicles.  If bike lanes are to be added, this will help to light the roadway for bicyclists and to 
help drivers identify when the bike lane is in use.  The cost for this treatment, including labor, 
averages $1,000 per additional street light. 

 
   

Page 25
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Contrasting Pavement 
While  it  does  not  replace  the  requirement  for  pavement  markings,  a  decorative  concrete 
crosswalk is one way to further enhance the crosswalks along M‐29.  This visual difference in 
pavement  materials  will  further  alert  the  driver  to  the  potential  presence  of  a  pedestrian 
traversing the roadway.  Unlike pavement markings, the contrasting color will not fade.  The 
cost for this treatment averages $10,000 per crosswalk. 

 
Figure 10. Example of a Contrasting Pavement Crosswalk and Intersection

Page 26
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Pedestrian‐Activated Flashing LEDs in the Border of a Warning Sign 
Flashing LEDs in the border of a warning sign are user‐actuated supplemental flashing white 
or yellow LEDs in the border of the pedestrian crossing warning sign.  The flashing LEDs make 
the crossing sign more conspicuous when a pedestrian desires to cross the roadway.  The cost 
for installing a pedestrian crossing warning sign with LED lights in the border averages $20,000 
per crosswalk location. 

 
Figure 11. Example of a Crosswalk with a Flashing LED in the Border of a Warning Sign

Page 27
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Pedestrian Hybrid Beacon (HAWK Signal) 
The pedestrian hybrid beacon or more commonly known HAWK signal, is a special signal that 
remains dark until activated by a pedestrian.  The signal head consists of two red signal lenses 
above one yellow signal lens.  Once activated, a steady yellow indication illuminates prior to 
a solid red indication for both red lenses.  These remain solid for the duration of the walk 
signal for the pedestrian and then flash for the duration of the flashing do not walk indication.  
Once the pedestrian signal becomes a solid do not walk, the vehicular signals go dark again.  
The cost for installing a pedestrian hybrid beacon averages $80,000. 

A HAWK signal may by installed only after meeting the warrant described in Section 4F.01 of 
the MMUTCD.  The warrant looks at vehicular volume, pedestrian volume, and the length of 
the  crosswalk  for  one  hour  (peak  volume)  of  an  average  day.    It  is  anticipated  that  this 
treatment will be desirable for pedestrians crossing from the parking lot on the west side of 
M‐29 to the St. Clair Inn.   

 
Figure 12. An Example of a Pedestrian Hybrid Beacon (HAWK) Signal 

Page 28
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Temporary Pedestrian Island 
Prior  to  installing  a  permanent  pedestrian  island,  a  temporary  island  can  be  placed.    The 
islands can be removed during the winter months to not inhibit snow removal.  The placement 
of the temporary islands allows communities to experience the benefit of installing an island 
without the expense of placing a permanent island.  This treatment is only applicable if the 
chosen cross‐section includes a left turn lane that will allow for placement of the pedestrian 
refuge island without compromising required stacking length for left turn vehicles.  The cost 
for this treatment is $8,000 per location. 

 
Figure 13. An Example of a Temporary Pedestrian Island 
Extended Pedestrian Refuge Island 
An extended pedestrian island creates additional area at the pedestrian crossing to potentially 
install additional street lighting or decorative plantings to further enhance the corridor.  This 
treatment is only applicable if the chosen cross‐section includes a left turn lane that will allow 
for placement of the pedestrian refuge island without compromising required stacking length 
for left turn vehicles.  The cost for these enhancements can be up to $40,000. 

   
 

Page 29
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Curb Extensions at Intersections and Mid‐Block 
To shorten the distance a pedestrian has to cross in order to reach the opposite side of the 
street, the curb at the intersection can be bumped out.  The bump outs can be installed in 
areas where there is on street parking and occupy the area between the curb and the edge of 
the parking lane.  They can be installed at both the intersection and mid‐block crossings.  The 
average cost for this treatment is approximately $13,000 for each location. 

 
Figure 14. Example of a Mid‐Block Crossing with Bump Out   

Page 30
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Landscaping and Landscaped Boulevards 
In situations where a left turn lane is not needed, the full length of a corridor due to the lack 
of driveways or cross‐streets, a landscaped boulevard works well as a traffic calming roadway 
enhancement  and  can  serve  as  a  pedestrian  refuge  island  at  the  location  of  pedestrian 
crosswalks.    This  would  be  a  long‐term  option  to  be  considered  when  the  roadway  is 
reconstructed.  The cost for this treatment will be over $100,000 and will only be considered 
when the roadway is reconstructed. 

 
Table 4. List of Proposed Treatments and Associated Cost 
Treatment Cost
Improved Corridor Lighting $          1,000.00
Special Emphasis Crosswalk $          1,500.00
Low Cost

Decorative Crosswalks $          2,500.00
Enhanced Crosswalk Lighting $          2,500.00
Temporary Pedestrian Island $          8,000.00
Contrasting Pavement $       10,000.00
Raised Crosswalks $       10,000.00
Curb Extensions at intersections and mid‐block $       13,000.00
Medium 

Pedestrian refuge islands $       13,500.00
Cost

Staggered crosswalks $       15,000.00
RRFBs $       20,000.00
Extended Pedestrian Island $       40,000.00
High 
Cost

Pedestrian Hybrid Beacon (HAWK Signal) $       80,000.00
Landscaping and landscaped boulevards $     100,000.00  

IX. IMPLEMENTATION PLAN 

A. Option 1 
Short Term 
To be completed later. 

Page 31
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Medium Term 
To be completed later. 

Long Term 
To be completed later. 

B. Option 2 
Short Term 
To be completed later. 

Medium Term 
To be completed later. 

Long Term 
To be completed later. 

C. Option 3 
Short Term 
To be completed later. 

Medium Term 
To be completed later. 

Long Term 
To be completed later. 

D. Option 4 
Short Term 
To be completed later. 

Medium Term 
To be completed later. 

Long Term 
To be completed later. 

X. CONCLUSIONS AND RECOMMENDATIONS 

To be completed later. 

Page 32
M‐29 Corridor Study – DRAFT   MDOT – Bay Region 

Appendix A – Steering Committee Meeting Minutes  
1. August 24, 2017 
 

Appendix 

 
Project M-29 Corridor Study
Brown to Clinton
City of St. Clair
MDOT JN 131491 – CS 77052
RE 8/24/2017 – Steering Committee Meeting #1 Minutes

• Attendees
o See attached sign-in sheet

• Meeting began with introduction of attendees

• Matthew Seitz, Project Manager from ROWE, began with an overview of previous studies and
discussion of project objectives.
o Previous studies overview
▪ M-29 Corridor Study (2005) – Spalding DeDecker
➢ Planning for a non-motorized path
➢ Laneage and operational features of M-29 for geometric modifications
➢ Optimize transportation and aesthetic features benefitting motorists,
pedestrians, and bicyclists
➢ Corridor Study Goals
• Plan for a continuous non-motorized path
• Reduce roadway noise
• Encourage motorists to obey posted speeds
• Improve safety at pedestrian crossings
• Improve turning movements, especially at Clinton Street
• Provide adequate on-street parking
• Improve aesthetics and suggest wayfinding signage and
strategic placement of signs
➢ The objectives identified in this study were intended to provide
recommendations for several desirable corridor improvements along M-
29 which may be incorporated into future projects
➢ Identified alternatives
• No build
• Boulevard - $1.8M (2 lanes in each direction with 10’ parking
lanes and decorative median street lighting)
• Three lanes, one in each direction with CLTL and 10’ parking
lanes on both sides with 10’ non-motorized path on east side –
$1.55M
• Three lanes, one in each direction with CLTL and angled parking
on east side, and 10’ non-motorized path on east side - $1.66M
• North and south of downtown – road diet to three lanes, one in
each direction with CLTL and 6’ bike lanes on each side.
Achieved by re-paving to match joint lines with lane lines -
$230K
▪ M-29 Corridor Analysis (2010) – Spalding DeDecker
➢ Level-of-service for through traffic between Clinton and Vine
➢ Intersection operations at Trumbull, Jay, and Vine
➢ Analyzed boulevard cross section from previous study
• Left turns to only be allowed at Trumbull, Jay, and Vine
• LOS C-F at Vine, A-B at Trumbull and Jay
➢ Current and future expected high level of service, except at Vine due to
redirected left turns.
▪ M-29 and Clinton Intersection Analysis (2010) – Spalding DeDecker
➢ Level-of-service at intersection for three different alternatives
• No-build – Existing C, Future C
• Actuated driveway phase for restaurant – Intersection C,
Driveway D
• Left turn phase for SB into restaurant – intersection C, SB LT C
• Combination of two – Intersection D, Driveway – E
➢ Also looked at feasibility of roundabout
• Insufficient ROW, still need signal at bridge
▪ Was informed there is an additional 2008 study that was not formally provided
by MDOT or the City of St. Clair

o Objectives of this study


▪ Identify bicycle and pedestrian improvements, including various design
alternatives, along the corridor
▪ Identify improvements that will increase the frequency of biking and walking as
a transportation mode
▪ Short, medium, and long-term transportation system needs to enhance bike and
pedestrian mobility while maintaining vehicular and bus transit operation
▪ All existing and proposed connecting pedestrian and bicycle paths, transit
stops/routes, and activity centers such as schools, businesses and parks/open
space should be considered to transform the corridor into a multi-modal
environment that balances the needs of all modes and is sensitive to evolving
land use and development plans
▪ Build upon previous recommendations that focus on pedestrian, bicycle safety,
and mobility
▪ Set of implementable investments
▪ Develop reasonable improvements of varying costs, that can be phased

o After background of the previous studies was given, an outline of study objectives was
provided, remainder of the meeting was spent in a roundtable format discussing the
various stakeholders goals and concerns. A summary of which follows:
▪ Proposed project at the former St. Clair Inn is driving the need for an updated
study
▪ Location of and length of crosswalks is a significant concern
▪ Increasing pedestrian safety is of utmost importance
▪ A road diet, with no loss of number of on-street parking spaces seems like the
logical solution
▪ It would be desirable to increase the amount of available on-street parking
➢ However, cannot impact park
▪ Consider reverse angle parking
➢ Preferred to have parking adjacent to park
▪ Survey was distributed to residents regarding changes on M-29
➢ Over 1000 responses, comments have been consistent
➢ Don’t want to see much change, but 80% want to see some kind of
change, with slower speeds being a primary goal
➢ This preceded St. Clair Inn redevelopment
▪ Balance community goals with what’s feasible
▪ Consider roundabout at Vine
➢ Slow traffic?
➢ ROW available?
▪ Concern with speed limits
➢ 33.5 mph average speed
➢ North of Vine speeds increase. Difficult to get out of driveways
➢ Look at speed limits and laneage in Algonac
➢ Slow traffic and crosswalk safety was again emphasized
➢ Coming from North, downhill at high speed
▪ Discussion regarding funding and funding sources
➢ A minimum 20% local match will likely be required
➢ SEMCOG – Projects in St. Clair County likely to be funded
➢ State funding? TAP funding? DNR Trust Fund?
▪ Re-striping is a cheap, potentially temporary solution/trial
➢ Interest in similar communities in which this has been imp
▪ Gold route for trucks which requires 12’ lane widths
▪ 76 feet of existing pavement
▪ Open to any ideas, selling potential projects will not be an issue
▪ Traffic impact study/traffic impact assessment encouraged for St. Clair Inn
▪ MDNR Grant for Boardwalk improvements
➢ Bike path connectivity?
➢ Leveraging funds, phased approach discussed
▪ Work with MEDC
▪ Related to St. Clair Inn, parking will be across the street. Safe, visible, crosswalk
important
➢ Special emphasis (lighting, markings, signing)
▪ Extensive discussion on HAWK signals
➢ Wadhams Road – south of Lapeer (St. Clair County Road Commission)
➢ Marysville
➢ Estimated 80k cost
➢ Education with HAWK signals is critical
▪ Consider urban roundabouts
▪ Consider pedestrian refuge islands
▪ Currently free-for-all for pedestrians, need to better “channelize” and force
crossing locations
➢ Trumbull intersection important
▪ Architect for St. Clair Inn discussed desire for clearly defined crosswalks that
stand out
➢ Visibility related to hill is a concern
➢ Warning signs for signal ahead if HAWK?
▪ Discussed special events
➢ Jazz Festival
▪ Flexible bollards at crosswalks?
▪ Sidewalk at Brown?
▪ Look at safety funding
▪ Marysville doing road diet on Huron
▪ Concerns with Clinton intersection
➢ Temp signal timing during recent bridge work seems to function the
best
➢ MDOT currently looking at intersection and potential CMAQ funding.

R:\Projects\17C0160\Docs\Meetings\Steering Committee Meeting #1 Minutes.docx


ROWE PROFESSIONAL SERVICES COMPANY
CORPORATE OFFICE UPEER MT. PLEASANT MYRTLE BEACH, SC TRI-C?TIES AIR-LAND SURVEYS FARMINGTON HILLS GUYLING

(810)341-7500 (810)664-9411 (989)772-2138 (843) 444-] 020 (989) 894-4001 (810) 762-6800 1248) 675-1096 (989) 348-4036

CALCuLATED BY JOB NUMBER

DATE SHEET

WEATHER
ffi

%Q-lTh S'-*ce,,fslry.=, 4r,;h:'? @l


'jL7 9?; (?' i l,-,1
ptaa+ -'z s 'ti ].w-t,- 6l0-'3'tl"l<,C>O h s e s'Q e r? '8< = ("'
i.

'-7-c? ? 810 -126-S;-[37 hMk:) rm-ef9-.

J 2.'x T'0-e- ?) hbos o?8'l (gzt ?4rl4 ees'?c'l


a !a!il'l:5
T?vo.g %toc! H '?ov -Huhursc 9m2q-ha bl?oa'ZGu:C)oi/
(E<}K T4MLIJ MC5-Htix! 9(- IE?'> 13?'?tZ8 faJayvzs0m;cA,ys, g
Va?f# &-a? ? C #'l ,? ng2
fl - '3;' /i'Y-t-'f Y , ,(/ '?i? D
t,f[C!'C!)y'-COy'4Pr%0?)
81L(,- llkLeLTCJ sT CcsiL (2-i??Y 8tQ 3Ff" S'CZu @yz25ctrc4(!,
Lh> Cc*4srusss'oy 6rcuixl e o t o v v y c:i a
A;;':,! ?-],, eckt-I Cv-=4ay 91(1-3e8-?'ID?LI 3v-r*s4-b-D'a*(6i
(?vac/ cr>mth i*'ioi< l
(.?l,,J5z s*k"e- '>+ ck,,r cr>s*xy XwsShJ7 FlCi-H (o'i50 lwqiis-cells
/?4 },! s..ce (5i 'stc%'r<>x* (?
ts.. !z %? 54 ? C.lo,.-, < gcb-5Z'i.Jg'Th(,, M?c{j%s-kal
-,J .Cs

%tltCeJl
t,'t (,4q(5R
?
J
'r< Bto i-t3([-7/'i'(,i tutela@7osxu

pAt) P4tV)gV 9w? p/g"<yi-1aa;iJl f%i*!; 'fiv%bV


k'k
17?

!?) s 11 C=xct '? OP sgcwC r?0-?t'H-sril- !b-5m'>gg@e;.%,,:), -,, ,l,,


%llSOe Cf?r>o (lsf31 52,,2'fS7(iA mvziJ.,lecsaci,-rr.+
iii.'qclcu-v' 9,xc gD-a=*i-irbo .;yw.revbtt(:gr.4w
l((15-eq?O%lqsec
DvhCA'jX5 CDn fio-9?=2-?5rl?a3')j
Project – DRAFT  Owner 

Appendix B – Conceptual Layouts 
 
 
Appendix 

Project
PINE RIVER CLINTON AVE

N
M-29 (S RIVERSIDE AVE)

M-29 (S RIVERSIDE AVE)


12'
6'
7 PARALLEL PARKING SPOTS

12'12'12'12'

12'12'12'
34 PARALLEL PARKING SPOTS

6'

8'
VOYAGEUR RESTAURANT

OPTION 1A - TRADITIONAL ROAD DIET

PINE RIVER

PINE RIVER CLINTON AVE

N
M-29 (S RIVERSIDE AVE)

M-29 (S RIVERSIDE AVE)


12'
6'
7 PARALLEL PARKING SPOTS
12'12'12'

12'12'12'
34 PARALLEL PARKING SPOTS

6'

8'
VOYAGEUR RESTAURANT

OPTION 1B - TRADITIONAL ROAD DIET

PINE RIVER

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: ) SHEET


DATE:12/15/17 CS:77052 M-29 CORRIDOR STUDY DRAWING
NO. DATE AUTH DESCRIPTION NO. DATE AUTH DESCRIPTION
SECT
Michigan Department of Transportation
NO SCALE DESIGN UNIT:REITHEL JN: 131491 OPTION 1 - TRADITIONAL ROAD DIET

FILE: TSC:BAY REGION


CLINTON AVE CASS ST TRUMBULL ST

N
M-29 (S RIVERSIDE AVE)

M-29 (S RIVERSIDE AVE)


12'

6'
7 PARALLEL PARKING SPOTS 4 PARALLEL PARKING SPOTS 3 PARALLEL PARKING SPOTS

12'12'12'
34 PARALLEL PARKING SPOTS

6'

8'
VOYAGEUR RESTAURANT

OPTION 1 - TRADITIONAL ROAD DIET

JAY ST

N
RIVERVIEW PLAZA
M-29 (S RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


12'

6'
12 PARALLEL PARKING SPOTS 13 PARALLEL PARKING SPOTS

12'12'12'
26 PARALLEL PARKING SPOTS 3 PARALLEL PARKING SPOTS 2 PARALLEL PARKING SPOTS 5 PARALLEL PARKING SPOTS

6'

10'

OPTION 1 - TRADITIONAL ROAD DIET

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: ) SHEET


DATE:12/15/17 CS:77052 M-29 CORRIDOR STUDY DRAWING
NO. DATE AUTH DESCRIPTION NO. DATE AUTH DESCRIPTION
SECT
Michigan Department of Transportation
NO SCALE DESIGN UNIT:REITHEL JN: 131491 OPTION 1 - TRADITIONAL ROAD DIET

FILE: TSC:BAY REGION


VINE ST

N
M-29 (N RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


6'

12'12'12'
3 PARALLEL PARKING SPOTS 4 PARALLEL PARKING SPOTS 2 PARALLEL PARKING SPOTS 8 PARALLEL PARKING SPOTS

10'
6'
ST. CLAIR INN

OPTIONAL 1 - TRADITIONAL ROAD DIET

BROWN ST

N
M-29 (N RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


6'

12'12'12'

6'

OPTION 1 - TRADITIONAL ROAD DIET

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: ) SHEET


DATE:12/15/17 CS:77052 M-29 CORRIDOR STUDY DRAWING
NO. DATE AUTH DESCRIPTION NO. DATE AUTH DESCRIPTION
SECT
Michigan Department of Transportation
NO SCALE DESIGN UNIT:REITHEL JN: 131491 OPTION 1 - TRADITIONAL ROAD DIET

FILE: TSC:BAY REGION


CLINTON AVE CASS ST TRUMBULL ST

N
M-29 (S RIVERSIDE AVE)

M-29 (S RIVERSIDE AVE)


12'
7 PARALLEL PARKING SPOTS 4 PARALLEL PARKING SPOTS 3 PARALLEL PARKING SPOTS

12'12'12'
13 PARALLEL PARKING SPOTS 16 PARALLEL PARKING SPOTS

10'

5'

5'
VOYAGEUR RESTAURANT

OPTION 2 - PROTECTED BIKE LANES

JAY ST

N
RIVERVIEW PLAZA
M-29 (S RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


12'
12 PARALLEL PARKING SPOTS 13 PARALLEL PARKING SPOTS

12'12'12'
22 PARALLEL PARKING SPOTS 3 PARALLEL PARKING SPOTS 2 PARALLEL PARKING SPOTS 4 PARALLEL PARKING SPOTS

10'

5'
5'
2' BUFFER

OPTION 2 - PROTECTED BIKE LANES

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: ) SHEET


DATE:12/15/17 CS:77052 M-29 CORRIDOR STUDY DRAWING
NO. DATE AUTH DESCRIPTION NO. DATE AUTH DESCRIPTION
SECT
Michigan Department of Transportation
NO SCALE DESIGN UNIT:REITHEL JN: 131491 OPTION 2 - PROTECTED BIKE LANES

FILE: TSC:BAY REGION


VINE ST

N
M-29 (N RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


12'12'12'
2 PARALLEL PARKING SPOTS 4 PARALLEL PARKING SPOTS 2 PARALLEL PARKING SPOTS 7 PARALLEL PARKING SPOTS

10'

5'
5'
2' BUFFER

ST. CLAIR INN

OPTION 2 - PROTECTED BIKE LANES

BROWN ST

N
M-29 (N RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


12'12'12'

5'
5'

2' BUFFER

s)
ent
em
El
ton
i
ruc
nst
Co
P(
EO

20°
OPTION 2 - PROTECTED BIKE LANES

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: ) SHEET


DATE:12/15/17 CS:77052 M-29 CORRIDOR STUDY DRAWING
NO. DATE AUTH DESCRIPTION NO. DATE AUTH DESCRIPTION
SECT
Michigan Department of Transportation
NO SCALE DESIGN UNIT:REITHEL JN: 131491 OPTION 2 - PROTECTED BIKE LANES

FILE: TSC:BAY REGION


CLINTON AVE CASS ST TRUMBULL ST

N
M-29 (S RIVERSIDE AVE)

M-29 (S RIVERSIDE AVE)


12'

6'
7 PARALLEL PARKING SPOTS 3 PARALLEL PARKING SPOTS 3 PARALLEL PARKING SPOTS

12'12'

20'
22 PARKING SPOTS

6'
VOYAGEUR RESTAURANT

OPTION 3 - REVERSE ANGLE PARKING 2 LANES

JAY ST

N
RIVERVIEW PLAZA
M-29 (S RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


12'

6'
12 PARALLEL PARKING SPOTS 10 PARALLEL PARKING SPOTS

12'12'

20'
4 HANDICAP PARKING SPOTS
5 PARKING SPOTS 4 PARKING SPOTS 7 PARKING SPOTS
37 TOTAL PARKING SPOTS

6'

OPTION 3 - REVERSE ANGLE PARKING 2 LANES

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: ) SHEET


DATE:12/15/17 CS:77052 M-29 CORRIDOR STUDY DRAWING
NO. DATE AUTH DESCRIPTION NO. DATE AUTH DESCRIPTION
SECT
Michigan Department of Transportation
NO SCALE DESIGN UNIT:REITHEL JN: 131491 OPTION 3 - REVERSE ANGLE PARKING 2 LANES

FILE: TSC:BAY REGION


VINE ST

N
M-29 (N RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


6'
3 PARALLEL PARKING SPOTS

12'12'

20'
6'
4 PARKING SPOTS 5 PARKING SPOTS 13 PARKING SPOTS

ST. CLAIR INN

OPTION 3 - REVERSE ANGLE PARKING 2 LANES

BROWN ST

N
M-29 (N RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


6'

12'12'12'

6'

OPTION 3 - REVERSE ANGLE PARKING 2 LANES

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: ) SHEET


DATE:12/15/17 CS:77052 M-29 CORRIDOR STUDY DRAWING
NO. DATE AUTH DESCRIPTION NO. DATE AUTH DESCRIPTION
SECT
Michigan Department of Transportation
NO SCALE DESIGN UNIT:REITHEL JN: 131491 OPTION 3 - REVERSE ANGLE PARKING 2 LANES

FILE: TSC:BAY REGION


CLINTON AVE CASS ST TRUMBULL ST

N
M-29 (S RIVERSIDE AVE)

M-29 (S RIVERSIDE AVE)


6'

12'12'12'

20'
22 PARKING SPOTS

6'
VOYAGEUR RESTAURANT

OPTION 4 - REVERSE ANGLE PARKING 3 LANES

JAY ST

N
SB LANE SHIFT BUMP OUT SB LANE SHIFT

RIVERVIEW PLAZA
M-29 (S RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


6'

12'12'12'

20'
4 HANDICAP PARKING SPOTS
5 PARKING SPOTS 4 PARKING SPOTS 7 PARKING SPOTS
37 TOTAL PARKING SPOTS

6'

OPTION 4 - REVERSE ANGLE PARKING 3 LANES

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: ) SHEET


DATE:12/15/17 CS:77052 M-29 CORRIDOR STUDY DRAWING
NO. DATE AUTH DESCRIPTION NO. DATE AUTH DESCRIPTION
SECT
Michigan Department of Transportation
NO SCALE DESIGN UNIT:REITHEL JN: 131491 OPTION 4 - REVERSE ANGLE PARKING 3 LANES

FILE: TSC:BAY REGION


VINE ST

N
M-29 (N RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


6'

12'12'12'
4 PARKING SPOTS
2 PARALLEL PARKING SPOTS 8 PARALLEL PARKING SPOTS

6'

10'
ST. CLAIR INN

OPTION 4 - REVERSE ANGLE PARKING 3 LANES

BROWN ST

N
M-29 (N RIVERSIDE AVE)

M-29 (N RIVERSIDE AVE)


6'

12'12'12'

6'

OPTION 4 - REVERSE ANGLE PARKING 3 LANES

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: ) SHEET


DATE:12/15/17 CS:77052 M-29 CORRIDOR STUDY DRAWING
NO. DATE AUTH DESCRIPTION NO. DATE AUTH DESCRIPTION
SECT
Michigan Department of Transportation
NO SCALE DESIGN UNIT:REITHEL JN: 131491 OPTION 4 - REVERSE ANGLE PARKING 3 LANES

FILE: TSC:BAY REGION

Vous aimerez peut-être aussi