Relocation of boundaries-Clearing Delivery of Materials Making of forms and jambs Forms and scaffolding installation

Start: Mon 04/12/17ID: 1 Start: Wed 06/12/17ID: 2 Start: Fri 08/12/17 ID: 5 Start: Tue 12/12/17 ID: 10
Finish: Tue 05/12/17Dur: 2 days Finish: Thu 07/12/17Dur: 2 days Finish: Mon 11/12/17Dur: 2 days Finish: Wed 27/12/17Dur: 12 days
Res: Res: Res: Res:

Staking and batter boards Cutting and assembling of steel reinforcements


Start: Wed 06/12/17ID: 3 Start: Fri 08/12/17 ID: 6
Finish: Thu 07/12/17Dur: 2 days Finish: Fri 15/12/17 Dur: 6 days
Res: Res:

Digging/excavation
Start: Fri 08/12/17 ID: 7
Finish: Mon 25/12/17Dur: 12 days
Res:

Construction of field office Gf-Electrical, plumbing and water pipe conncetion


Start: Wed 06/12/17ID: 4 Start: Mon 18/12/17ID: 8
Finish: Thu 07/12/17Dur: 2 days Finish: Fri 22/12/17 Dur: 5 days
Res: Res:

Positioning steel reinforcement Pouring of Footing and C


Start: Mon 18/12/17ID: 9 Start: Thu 28/12/17
Finish: Mon 25/12/17Dur: 6 days Finish: Fri 29/12/17
Res: Res:

Page 1
Page 2
Footing and Column Dismantling of Forms Door and window jambs installation
28/12/17 ID: 11 Start: Mon 01/01/18ID: 12 Start: Thu 04/01/18 ID: 15
9/12/17 Dur: 2 days Finish: Wed 03/01/18Dur: 3 days Finish: Tue 09/01/18Dur: 4 days
Res: Res:

Chb laying and buckfilling 2-F Beams, Columns and slab reinforcement installation 2-F Electrical, Plumbing and water pipe connections
Start: Mon 01/01/18ID: 14 Start: Thu 25/01/18 ID: 18 Start: Fri 02/02/18 ID: 20
Finish: Wed 24/01/18Dur: 18 days Finish: Thu 01/02/18Dur: 6 days Finish: Thu 08/02/18Dur: 5 days
Res: Res: Res:

Construction of Stairway Pouring of Columns, Slab, Stairs and Beam


Start: Thu 25/01/18 ID: 19 Start: Mon 29/01/18ID: 21
Finish: Fri 26/01/18 Dur: 2 days Finish: Tue 30/01/18Dur: 2 days
Res: Res:

Page 3
Delivery of Materials Cutting and assembling of steel reinforcements
Start: Mon 01/01/18ID: 13 Start: Wed 03/01/18ID: 16
Finish: Tue 02/01/18Dur: 2 days Finish: Mon 08/01/18Dur: 4 days
Res: Res:

Forms and scaffolding installation


Start: Wed 03/01/18ID: 17
Finish: Wed 10/01/18Dur: 6 days
Res:

Page 4
Dismantling of Forms Delivery of Materials Plastering and tile works Final work and clean
Start: Wed 31/01/18ID: 22 Start: Mon 05/02/18ID: 25 Start: Wed 07/02/18ID: 29 Start: Tue 13/03/18
Finish: Fri 02/02/18 Dur: 3 days Finish: Tue 06/02/18Dur: 2 days Finish: Mon 12/03/18Dur: 24 days Finish: Tue 20/03/18
Res: Res: Res: Res:

Cutting and assembling of steel reinforcements


Start: Mon 05/02/18ID: 26
Finish: Thu 08/02/18Dur: 4 days
Res:

Roof Framing and roofing sheets Plumbing and drainage system Installation of Plumbing Fixtures Painting and varnish
Start: Mon 05/02/18ID: 27 Start: Tue 13/02/18 ID: 28 Start: Wed 21/02/18ID: 30 Start: Wed 28/02/18
Page 5
Start: Mon 05/02/18ID: 27 Start: Tue 13/02/18 ID: 28 Start: Wed 21/02/18ID: 30 Start: Wed 28/02/18
Finish: Mon 12/02/18Dur: 6 days Finish: Tue 20/02/18Dur: 6 days Finish: Tue 27/02/18Dur: 5 days Finish: Thu 15/03/18
Res: Res: Res: Res:

Installation of Electrical wirig and fixtures


Start: Wed 21/02/18ID: 31
Finish: Tue 27/02/18Dur: 5 days
Res:

CHB laying and buckfilling


Start: Wed 31/01/18ID: 23
Finish: Fri 23/02/18 Dur: 18 days
Res:

Door and window jambs installation


Start: Wed 31/01/18ID: 24
Finish: Mon 05/02/18Dur: 4 days
Res:

Page 6
ork and cleaning
Tue 13/03/18 ID: 33
Tue 20/03/18Dur: 6 days

g and varnishing
Wed 28/02/18ID: 32
Page 7
Wed 28/02/18ID: 32
Thu 15/03/18Dur: 12 days

Page 8
Critical Milestone Critical Inserted Marked Project Summary

Project: Cad Noncritical Critical Summary Inserted Critical External Highlighted Critical
Date: Sun 03/12/17
Critical Milestone Summary Critical Marked External Highlighted Noncritical