Vous êtes sur la page 1sur 4

TESTING AND COMMISSIONING SHEET

FIRE PROTECTION SYSTEM

1. Project : Fire Protection System for National Environmental Secretariat


Building
2. Client : Ministry of Mahaweli Development and Environment
3. Consultancy : Central Engineering Consultancy Bureau (CECB)
4. Main Contractor : Central Engineering Services (Pvt) Ltd. (CESL)
5. Equipment Installed : Frigi Engineering Services (Pvt) Ltd.

Item Equipment Make Model No. Qty.


Number
Main Fire Pumps – MAS-DUF CMK-V 80
01 2
(Duty/Stand By) 2A1612084185
02 Jockey Pump MAS-DUF I1402016 1
03 Landing Valves Kolling 10
04 Fire Hose Kolling 30
05 Hose Reel Kolling HRS16 - 195 10
06 Pillar Hydrant Kolling BS-750-M4 2
07 Breeching Inlet Kolling BS-5041-3 1

6. INSPECTION OF THE SYSTEM

(i) Have all the equipment in the fire protection


system inspected for comply with the Yes
specifications?

(ii) Have the fire protection system inspected for


proper installation to comply with the Yes
Specifications and drawings?

7. TESTING OF THE SYSTEM

7.1 Testing of landing valves

(i) Number and location of landing valves kept open 10

(ii) Length of water jet 15 m

(iii) Length of Landing Valve Hose Reel 15 m × 3

7.2 Testing of Hose Reels

(i) Number and location of hose reels kept open 10

1
(ii) Length of water jet 5m

(iii) Automatic operation of hose reels Ok

(iv) Length of Hose Reel 45 m

7.3 Testing of Pillar Hydrants

(i) Number and location of pillar hydrants kept open 2

(ii) Length of water jet 15 m

7.4 Testing of Fire Pumps

(i) Operation of Duty Pump Ok

(ii) Operation of Standby Pump Ok

(iii) Operation of Jockey Pump Ok

(iv) Sequence of Operation /Pump Control System Ok

7.5 Fire Pump control panel

(i) Have all wiring inside the fire pump control inspected for
damage, loose, connection etc. Yes

(ii) Indicators function Ok

(iii) Operation of switches ,push buttons etc. Ok

7.6 Testing of portable fire extinguishers

(i) Checking of water/CO2 portable fire extinguisher Ok

(ii) Checking of CO2 portable fire extinguisher Ok

2
8. DECLARATION

We certify that on................................ the Fire Protection System was examined and to be
generally comply with the requirements except the snagging list given in Annexure - 01.

For Client/Consultant: Signature: ..............................................


Name: ........................................................

Date: ..........................................................

For Main Contractor Signature: .................................................

Name: ........................................................

Date: ..........................................................

For Fire System Contractor Signature: ...............................................

Name: ........................................................

Date: ..........................................................

3
Annexure - 01

SNAGGING LIST

(a) Pressure gauge shall be added to top of the fire hydrant riser.
(b) Contractor hadn’t provided three landing valve hoses to each fire cabinet except
some fire cabinets.
(c) Contractor shall paint 1ʺ pipe in fire cabinet which is connected to fire hose reel.
(d) Wet riser path shall paint in 8th floor.
(e) Contractor shall be provided fire hoses for pillar hydrant in suitable location which
can connect to the pillar hydrant in emergency fire case.