Vous êtes sur la page 1sur 17

PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING

PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.


Method Statement of RC works TOP DOWN CONSTRUCTION

CONTENTS

1. PREPARATION PRINCIPLE AND FOUNDATION


2. PROJECT OVERVIEW
3. CONSTRUCTION DEPLOYMENT
4. CONSTRUCTION PREPARATION
5. ENGINEERING CINSTRUCTION METHOD
6. PROJECT QUANTITY ASSURANCE MEASURE
7. CONSTRUCTION MEASURE OF TIME LIMIT OF PROJECT
8. SAFETY FIRE MANAGEMENT

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

Abstract: this construction is designed for PROPOSED 3 STOREY MANUFACTURING


BUILDING AND 2 STOREY CUP BUILDING, PROBE / ADMIN BUILDING AND GUARD HOUSE AT
NORTH COAST AVE. Construction organization design for the planning and direction of the
engineering construction and acceptance of the whole process of preparation of
comprehensive technical and economic documents. In prepared Shi, on engineering quality
target, and duration target, and project management institutions set, and construction
progress plans, and construction mechanical, and turnover material and the equipment, and
main construction method, and labour organization, and security civilization construction,
and environmental protection, many factors do has full consider; and to national about
technology policy, and provides, and main contractor’s requirements, and design drawings,
and tender file, and construction site related information for according to; strictly according
to construction organization design of prepared principles, from construction global
starting, combined engineering of reality, Using scientific management methods, rational
organization of the resources, in order to consume less, short duration, high quality, low
cost optimal effect.

1 Preparation principle and Foundation

1.1 Compilation principle

1. follow the rules of law, technology law and safe production of construction technology,
reasonable arrangement of construction programs and order;

2. overall planning and co-ordination arrangements to ensure focus, giving priority to key
engineering control engineering, ensure that the contract period;

3. make full use of existing machinery and equipment and expand the scope of mechanical
construction. Increased mechanization, improving working conditions, improve labor
efficiency;

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

4. arrange the construction plan, minimize the temporary works, reduce construction land
and material transfer, reducing engineering costs;

5. the adopted construction method. Network planning arrangements for the construction
schedule, arranging rainy season and night construction of science, ensure continuous,
balanced and rhythmic manner.

1.2 Prepared on the basis

1. LOA letters and tender documents and answer files.

2. Current national construction safety, construction, LTA and environmental protection


standards and related laws and regulations.

3. Quality of national mandatory technical standards, specifications, construction and acceptance


procedures.

4. Construction of the project, expectations and requirements.

5. Customs information and data on construction site.

6. PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING, PROBE


/ ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE design drawings.

2. Project summary

2.1 Project overview

This station with 5 entrance 5 vent, underground has 5 story slab: Base slab (Level:

83.990),Platform level slab (Level: 85.900), Mezzanine level slab (Level: 91.600),Concourse

level slab (Level 95.400), Top of box slab (Level: 102.000/ 103.200),under ground level max

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

deep 25.86m, main station length 241.95m, slab thickness : 300mm,800mm, 1500mm ,

2000mm, 2300mm, 2700mm,3200mm. 3.200m thk TOP SLAB max height staging 16.52m.

Table 2-1 Engineering quantity list


Item Description Unit Quantity remark
1 Lean/Blind/mass M2 15,314.00
concrete
2 Concrete M3 71,950.00
3 reinforcement TON 18,351.00
4 formwork M2 89,236.00
5 BRC M2 5,559.00

2.2 Construction conditions and features:

1. the project review has been completed and construction design, Temporary ERSS wall
and indicate strut arrangement has been completed by other contractor, excavation to base
slab lean concrete level.

2. The project is large and complex, the relative concentration of investment, a large
quantity of construction technology.

3. Compact in construction sites, can make use of the limited space, need careful
arrangements, and arrange the construction plane.

4. The number of units constructed, all aspects of coordination is especially important.

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

5. Safe and civilized construction, environmental protection requirements must be in strict


accordance with construction requirements.

3 Construction deployment

3.1 Construction overall objective

3.1.1 Quality objectives

Ensure that an inspection of the project up to the national and local acceptance of
current quality norms, rules one acceptance. Strictly according to the current national code
for construction and acceptance of construction, strengthening project quality control, to
ensure that the construction process, the construction process is closely monitored. Ensure
that all the functions of the successful implementation of this project, and to strengthen the
quality control of main branch.

3.1.2 Time schedule

Overall duration of 18 month. Station Box 10 months, station –At-Grade/ Above Ground
Works 8 month. As described in the construction schedule.

3.1.3 Safe and civilized construction goal

1. Creating a safe and civilized construction standards. Eliminate fatalities, serious injuries,
fire accidents, injury frequency controlled 4per thousand or less.Also in the area of
environmental protection, and civil construction, the company will set resources, focus.

3.2 Project management system

Project management system in accordance with the PDCA cycle for which planning
services → implementation → results → four steps, four steps is done through the company
→ project → operations teams to achieve.

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

And project Department is responsible for project planning services, including


targeting, resourcing, standardized procedures, so that project objectives are clear, the
responsibility, this work is the key prerequisite for success of the project.

Department is responsible for the Organization and implementation of the project,


results, problem solving, project management work. Project management in accordance
with the corporate project management, time schedule Central, according to the
standardization of procedures, the work of human-centered, scientific management
requirements, project management goals.

Operations team is responsible for the actual operation, in practice to do model the
way, core nodes for the process control, strict rewards and punishments.

Through three levels of management responsibility to ensure the realization of project


management, for this project we propose “emphasis on planning, results, reducing
consumption," guidelines for the management, in order to create a quality project.

3.2.1 Project management

Implementation duration as the center part in ensuring project quality as the premise,
Full coordination of the relevant units fulfill the quality requirement of the owners, strict
quality control in the project, and quality veto system to create quality projects, as objective
of project management through the layers of controls, checks, implemented by the project
organization personnel are responsible for safe and civilized construction site.

3.2.2 Project Management Institute

1. Formation of the project

Company in accordance with the relevant conditions and requirements for the
formation of the project, establish a project management system. Project managers are the
Plenipotentiary of the company on the project, commissioned by the legal person exercising

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

the right to project management, within the terms of reference for project directions,
process management, project management goals, achieve contract commitment to the
owners.

2. Project organization

Organizations see photos of the project.

3. Project Department duties of each position

Establishment of responsibility and quality supervision system, and clear division of


responsibility, the implementation of construction quality control of responsibility,
responsibility to the people.

(1) Project Manager

The establishment of responsibility system for project quality at all levels, strengthen
quality control, production and construction services in a tightly controlled state;

(2) Site manager/ site supervisor

Responsible for developing quality goals and implementation of the quality of the
Organization and guidance Department, and stages periodic supervision and inspection of
the implementation of the objectives and summarize.

(3) QA/QC Inspector /engineer

A, Organization checks the process of construction, quality, participate in or organize


concealed works of important parts of the pre-screening and checked.

B, Responsible for organize regular quality assessment, quality summaries, as well as


building owners and owners ' representatives, supervision on the quality of communication
and reporting.

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

3.3 Construction schedule

3.3.1 Project phase control scheme

Based on the identified project goals and stages are as follows:

Total duration target: overall duration of 18 month

Each part of the project as detailed in the General construction progress plan of
construction progress;

3.3.2 The construction process

1. Structure construction principle according to the principles of layout and flow,


organization sections in the water, the construction of;

2. for achieved all target, take four level plans for engineering progress of arrangements and
control, except supervision meeting outside, daily afternoon 5 Shi held the points package
of day plans check and plans arrangements coordination will, to solution day plans
implementation process in the exists of contradictions problem and arrangements second
day of plans and by adjustment of plans, to guarantee week plans of completed, through
week plans of completed guarantee months plans of completed, Through months of
planning control to ensure the implementation of an overall plan.

According to the master plan, at all stages, also prepare the secondary time control
plan, three-level schedule and weekly plans.

3.3.3 Organization of material at each stage Plan

Project for all phases of the construction materials of the Department plans to make
proper arrangements, and strictly implement the plan to guarantee duration and quality
objectives.

4 Construction preparation

4.1 Technical preparation

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

1. Carefully read and study construction drawings. Construction specifications, procedures,


read-write document and participate in drawing and design of cards on the table.

2. The construction scheme project engineer must training the site supervisor

3. Site supervisor seriously technical disclosure and safety technology gives the team leader.

4. Prepare the technical specifications and reference materials in the construction process,
as well as the technical information required for engineering construction quality
acceptance of forms and tables.

5. Provides main contractor the contract file the information requested.

6. The specialized training of workers in the process of examination and certificates,


inspection equipment that is required, meet the requirements of the workers, the
equipment may be put into the construction.

4.2 Production preparation

4.2.1 Allocation of labor force

Reasonable and scientific organization of labor, is an important factor in ensuring


smooth construction. According to the project schedule, timely deployment of labour.
According to the plans, construction engineering, and need to develop workforce planning.
Will be mainly responsible for the high quality of construction managers, skilled professional
and technical workers.

Body mass and high difficulty of the project, interspersed with more jobs, more
appropriate human resource input. Progress needed, organized the workforce phased
construction, detailed schedules of labour required at each stage.

Table 4-1 the labour required schedule

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

Serial Construction phase


Jobs Notes
number (person)
1 Steel Fixer 75 Reinforcement

2 Shelves and templates 100 Template construction

3 Concrete worker 25 Concrete pouring


4 Lifting team 9
Machinery and equipment
5 Mechanical maintenance 2
repair
Welded (documented, field
6 Welders 8
examination)
7 Safety team 8
8 General worker 6
9 Store man 2
10 Banks man 2
total 237

4.2.2 Materials configuration

In order to ensure rapid construction, play materials economy turns, reduce transport costs
and appearances of material loss, according to duration of arrangements, fully taking into
account the construction area and construction of water requirement, after resources
optimization engineering materials. Main detailed dosage schedule.

Table 4-2 the main materials required tables

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

item Description Qty Remark


1 GI PIPE 5000 pcs 6 m length
2 Swivel clamp 10,000 pcs
3 Fixed clamp 10,000 pcs 4m length
4 Steel plank 4000 pcs
5 Wall system formwork 600 m2
6 Slab system formwork 2500 m2
7 Column system formwork 200 m2
Common formwork with
8 1500m2
support
9

4.2.3 Machinery and equipment configuration

According to the construction plan, with enough intact construction equipment,


construction equipment, should be reasonable, advance maintenance, increase availability
and utilization, and admission time as required.

Table 4-3 the main equipment table


Serial Model
The number
numb Device name specificati Notes
of
er ons
CONCRETE PUMP CAR 37- FOLLOW SITE
1 6
62 M NEED
BEBAR CUTTING &
2 42MM 1 SETS
BENDING MACHINE
ELECTTICAL BENDING
3 32MM 1
MACHINE

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

4 ELECTRICAL HAND SAW 10 110V


5 BOON LIFT 24M 2
6 SCISSOR LIFT 10M 2
7 DRILING MACHINE 5 110V
8 ELECTRICAL BRAKER 15
9 AIR BREAKER 3
10 AIR COMPRESSOR 3
11 SPOT LIGHT 10 110V
12 WELDING MACHINE 5
13 WALK TALKI 10 NOS

5, Engineering construction method

5.1 Construction survey

Build construction axis of axis control must establish effective control network.
Established axis control network construction, must be considered from the entire
construction process of excavation, bedding and the axis during construction of buildings
should use the establishment of construction control network. Control axis time projection
on the building surface, then under the control of axis as column wall line details setting out
binding reinforcement and pouring concrete, vertical template use. We as main sub-
contractor must follow main contractor properly protect the control point and marked
1000mm height control level line and grid line after concrete casting.

A.ground: round pop-up 50cm horizontal line on the wall, as a construction height of
surface line of control.

B. wall: construction, pop-up wall line and 50cm line of control on both sides of the
wall, under the wall surface construction control line.

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

C. the door hole: outdoor wall structure is completed, measured by theodolite in the
middle of the window cast vertical control lines, again according to the first floor exterior
wall +50cm wire steel tape passing height and playing on the wall. Interior hole vertical axis
according to the line of control pop up, horizontal control line from +50cm line up to ensure
doors and Windows relative position accuracy.

D. lift shaft control: in the construction of structures, from the elevator shaft begins at
the bottom, is subject to construction control line, timely measurement of

elevator shaft clearance dimensions and setting out elevator shaft center line of control.

E. the stairs: according to the +50cm line on the upper level and pop-up walls, uniform
distribution by number of steps as the staircase line of control.

5.2 base slab (2300mm thk slab) and top of box slab (2700mm/ 3200 mm thk)

for this project (include concourse level, Mezzanine Level)

5.2.1 Large volume concrete casting

Its large amount of concrete with large volume concrete, in addition to satisfying the
General requirements. The hardening of the concrete raft key control process and hydration
heat caused by the temperature difference between inside and outside, preventing internal
and external temperature difference cracks as a result.

A. raft Board concrete construction technology points (1) reasonable determine tie than (by
main contractor) (2) concrete end of pouring, and conservation

B. after pouring of temperature and the temperature control specification provides, on big
volume concrete conservation, should according to climate conditions take control
temperature measures, (by other contractor)

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

C. key points in construction of raft Foundation construction quality assurance measures (1)
to strengthen the conservation, control, delaying the external cooling temperature
difference between inside and outside speed, reduce shrinkage, reduction of external
constraints and improve the reinforcement structure, and so on.

(2) Measuring (by other contractor)

(3) Strengthening technology management details before construction technology to give


the low-down, check site preparation work, clear the mouth of jobs and responsibilities.
Strictly according to the technical disclosure in the construction operations, implementation
of personal responsibility, strengthening the measuring work, regularly checking concrete
slump, deal with problems found in construction, finished pouring the concrete in time after
curing.

(4) The reasonable construction is equipped with 2 persons in the construction, once every
12 hours, reduce the number of shifts, avoid the shift brought about frequent quality
problems. Application of modern management methods throughout the construction
process, advanced technology and management support. Due to the large volume of

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

© CREC CONSTRUCTION PTE LTD


PROJECT NAME: PROPOSED 3 STOREY MANUFACTURING BUILDING AND 2 STOREY CUP BUILDING
PROBE / ADMIN BUILDING AND GUARD HOUSE AT NORTH COAST AVE.
Method Statement of RC works TOP DOWN CONSTRUCTION

© CREC CONSTRUCTION PTE LTD

Vous aimerez peut-être aussi