Vous êtes sur la page 1sur 37

CREC Est Date : 25/4/2018

Method Statement for RC Structure Works for CUP_A1 Building Page : 1


Construction PTE
LTD Basement

-
PROJECT TITLE: PROPOSED 3 STOREY
MANUFACTURING BUILDING AND 2 STOREY CUP
BUILDING, PROBE / ADMIN BUILDING AND GUARD
HOUSE AT NORTH COAST AVE.

METHOD STATEMENT FOR CONSTRUCTION OF


REINFORCED CONCRETE WORKS FOR CUP_A1
BUILDING BASEMENT
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 2
Construction PTE
LTD Basement

CONTENTS
Section Description Page
1. CONTENTS 2
2. INTRODUCTION 3
3. SCOPE OF WORK 4
4. ORGANIZATION 4
5. RESOURCES 5
6. PREPARATORY WORKS 6
7. CONSTRUCTION SEQUENCE AND METHODOLOGY FOR R.C
STRUCTURE WORKS

7.1 Layout Plan for CUP_A1 Building Basement (Roof Slab, RC

Beam)

7.2 R.C Structure Construction Sequences for CUP_A1 Building


Basement
7.3 Typical R.C Structure Work Sequences and Methodology for
Top-Down Construction (Roof Slab and RC Beam) 7 - 31

7.4 Typical R.C Structure Work Sequences and Methodology for


Bottom-Up Construction (Basement Slab)
7.5 Typical R.C Structure Work Sequences and Methodology for
Bottom-Up Construction (Skin wall and internal wall)
7.7 Typical R.C Structure Work Sequences and Methodology for
Bottom-Up Construction (Slab)

8. SAFE WORK PROCEDURE 31-37


CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 3
Construction PTE
LTD Basement

2. INTRODUCTION
This method statement describes the construction sequences & methodology
for CUP_A1 BUILDING R.C construction works. The basement is built under
Top-down construction method for outer structure and under the Bottom-up
construction method for internal elements. The basement are consist of Roof
slab, Bottom slab and internal elements such as internal wall, columns and skin
wall, lift wall, staircase wall, staircase

Special methods and treatments will be proposed and used for the Top-Down
construction such as corrugated pipe with hot dipped galvanized will be
proposed to use as temporary opening for pouring of concrete and vibration to
fill up the R.C elements below the roof. Another option is to use pressure
grouting method to cast second lift of skin wall, lift wall, RC wall.

The R.C structures are built by conventional formwork in most cases whereas
system formwork may be designed for those R.C wall like skin wall and internal
wall.

The basement length is divided into sections. Each section and each layer of
slab will be further divided into 4-5 panels and each panel of concrete volumes
may easily up to 800 m3 and the casting period may require 8-10 hours. Such
a long period of pouring may have potential to create several major structural
quality issues such as cold joint formation, lack of vibration (honeycomb),
thermal cracking & etc. These are the most common quality issue occur during
the construction stage. Consequently, several prevention methods will be taken
during & after concreting to eliminate or eradicate these issues; Such as
external vibrator will be use to ensure surface quality, casting sequences &
plans to avoid cold joint formation, curing method to avoid thermal cracking &
etc. Vibration effect that generated from external vibrator will be take into
consideration in our formwork design accompanied with relevant details and
documents (we are in the midst of preparing the PE endorsed formwork design,
it would be submitted separately as soon as possible)
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 4
Construction PTE
LTD Basement

3. SCOPE OF WORK

The major construction activities for T301 reception tunnels consists of:

a) Bore piling, diaphragm wall, Precast Concrete Installation– By others


contractor.
b) Excavation to each layer of slab formation level– By others contractor
c) Hacking of Bore pile to COL & exposed the coupler on diaphragm
wall – By RC contractor.
d) Trim & lay blinding concrete for roof slab, basement slab – By R.C
contractor in cooperation with Excavation contractor.
e) Application of hydrophilic water-stop with Re-injectable tube & etc. –
By RC contractor
f) Roof slab construction - By R.C contractor.
g) Bottom slab & internal wall construction - By R.C contractor.
h) Skin wall, Staircase construction – By R.C contractor.

4. SITE ORGANIZATION CHART

Site Organization Chart of RC Structure Contractor (Refer to Appendix A).


CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 5
Construction PTE
LTD Basement

5. RESOURCES
5.1 Plants / Machinery
Item Description QTY Remark
1 50 to 80 ton Mobile Crane 3~4 (By main-con)
2 Air Compressor 2~3 Located on Surface
3 Concrete Pump 2~3
4 Welding Machine 3~5 Portable
5 Bar Bending Machine 2 At Yard (for minor work)
6 Bar Cutting Machine 2 At Yard (for minor work)
7 Vibrators & Engines 6~10 Diesel Driven or
electrical
8 Oxy & Acetylene gas cutter 4 Set (located on
Surface)
9 Lighting for Night Work Sufficiently
10 Ventilation Fan for air circulation 2~6 (By main-con)
Note: The Actual Quantity of plant & machinery will be adjusted depending on site
condition & production rate.

5.2 Manpower for RC works


Item Description QTY Remarks

1 Site Manager 1

2 Site Engineer 3

3 Safety Officer 1

4 Safety personnel 4 (Dayshift and


Nightshift)
5 Lifting Supervisor 3~4 (Depends on number
of crane)
6 Crane Operator 3~4

7 Rigger man & Signalman 6~8

8 Rebar worker 130 (Maximum)

9 Carpenter & Concreter 90 (Maximum)

10 General Worker 55

Note: The figure of manpower is approximate and will be increase or decrease


depending on site condition & progress.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 6
Construction PTE
LTD Basement

6. PREPARATORY WORKS
The following prerequisite works must be completed prior to commencement of
underground R.C Structure works.

I. Temporary Works & Road Diversion.


II. Bore piling & D’wall installation.
III. Excavation to formation level (progressively).
IV. Underground live cable diversion.
V. Interfacing Works to RC Structure work.
VI. Hacking and remove the excessive Bore pile to cut off level.
VII. Exposed of Coupler on D’wall.
VIII. Water-proofing & its protection (Progressively)
IX. M & E installation works (progressively)
X. Others miscellaneous works associated to RC Structure work.
XI. Produce of RC works shop-drawing.

Submission of shoring system, formwork and others design (To be


submitted separately)

i. Base slab/roof slab side formwork.


ii. Typical C.J formwork designs.
iii. Typical Wall formwork (Conventional or system).
iv. Shoring system for Suspended slab.
v. Typical Bar Chair support to reinforcement bar.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 7
Construction PTE
LTD Basement

7. CONSTRUCTION SEQUENCES & METHODOLOGY


As mentioned, the construction methods for the basement consisting of Top-
Down construction for the outer structure and Bottom-Up method for the internal
structure, as a result, the construction sequences will be separated into several
stages and the methodology will be discussed in details in the following pages.

7.1 Layout Plan for CUP_A1 BUILDING (BASEMENT)

Location of basement
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 8
Construction PTE
LTD Basement

Example of section view

7.2 R.C Structure Construction Sequences for Basement:


Stage 1 - Construction for the roof slab (Top-down construction method).
Stage 2 - Construction for the Bottom slab.
Stage 3 - Construction for the internal walls and staircase.
Stage 4 - Construction for the skin wall both sides of basement
Stage 5 - Construction of cast back access opening.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 9
Construction PTE
LTD Basement

7.3. Typical R.C Structure Work Sequences and Methodology for Top-Down
Construction (Precast Flat Slab,RC Slab, RC Beam)

a) Trimming of soil surface and lay blinding concrete shall carry out by R.C
contractor corporate with excavation contractor.
b) Land surveyor to provide offset or references point for R.C contractor to
carry out level marking for the R.C structure.
c) Timber 75mm x 25mm shall use as separator for blinding concrete for future
easy removal the blinding concrete (panel by panel) in order to reduce the
risk during excavation.
d) Contractor shall mark out the wall & column alignment according to the
surveyor offset point below the top-down slab.
e) 500mm depth shall be excavated below the soffit of the top-down slab for
internal walls, skin walls.
f) Install temporary formwork as shutting and fill up the gap with blinding
concrete and then remove the formwork after the concrete has harden.
g) Laying 6mm plywood on the blinding concrete for top–down construction
internal wall skin wall RC Beam as de-bonding materials for the RC Beam.
In our past experience, using plywood as debonding material is one of the
safe method.
h) Predominant reinforcement bar shall be fabricated by local rebar distributor
or manufacture according to the approved rebar shop drawing & bar bending
schedule (BBS). Where minor rebar changes is required, it shall be
fabricated at job site due to the shape of rebar or to suit the change of site
condition.
i) The fabricated rebar shall deliver progressively to the require job area by
trailer or lorry crane with assistance of crane.
j) The fabricated rebar shall be hoisted down to the loading bay in beneath
and transfer to the working area by manually or by trolley if crane cannot
reach.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 10
Construction PTE
LTD Basement

k) The fabricated rebar shall be installed according to the shop drawing and
supported by spacer block at bottom layer to maintain the required cover
and fix with Grade 20 GI wire at a randomly alternate spacing.
l) T13or T16 guide bars at 1.2m to 1.6m spacing will be proposed to use for
support the reinforcement bar (depend on the layers of rebar).
m) G20 GI wire will be used to secure all the necessary reinforcement bar.
n) The horizontal reinforcement bar from D-Wall will be extended by using
coupler as per shop drawings.
o) The top reinforcement bar will only be installed after completion of bottom
bar.
p) Continue install the shear links to complete the roof slab and as per
construction drawings.
q) Coupler bar shall be used as starter bar for all the walls and columns below
the top down slab as below:

RC Slab

500mm Coupler Bar


Corrugated pipe

r) Corrugated duct (100mm dia. ~ 150mm dia. and hot dipped galvanized steel)
for future wall/column casting shall be placed into designated location with
a certain distance 800 ~ 1500mm c/c along wall for purpose concrete
pouring and insert vibrator poker. These corrugated pipes to be left inside
permanently because it is difficult to take it out.
Ø100~150mm corrugated pipe

800 – 1500mm 800 – 1500mm 800 – 1500mm 800 – 1500mm


CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 11
Construction PTE
LTD Basement

Future R.C Wall below

Corrugated pipe

Previous Project Photo for rebar fixing

a) Inspection shall be arranged after the completion of rebar installation.


b) Side formwork shall carry out according to the structural alignment
provided by the land surveyor after the rebar inspection.
c) HY-Rib mesh will be proposed for CJ and for the rebar protruding area to
prevent concrete grout loss/leaking. All hy-rib material shall not left inside
slab in permanent stage.
d) Along CJ, timber strip to be used for create recess for waterstop
installation. Waterproofing details at construction joint will be provided
(others contractor) as below:

Hydrophilic water stop


Re-injectable grout tube

e) Casting area shall be cleaned up and inspection arranged with QPS team.
f) Both ends of the corrugated pipe shall be covered up by cloth tape to
prevent choke and fix to the slab by using the G.I wire.
g) R6 Bar with color tape shall be used to indicate the designated casting
level where it shall be spot welded to top layer of rebar at a random
spacing
h) The R6 bar shall be removed immediately before the concrete has harden.
i) Final inspection shall be arranged with QPS team.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 12
Construction PTE
LTD Basement

j) The concrete casting for RC slab and RC Beam basically using concrete
pump which stationed at the surface near the designate loading bay. For
those areas not reachable, additional concrete pipe will be used to extend
the concrete delivery distance.
s) Contractor supervisor shall coordinate with the main contractor supervisor
or engineers closely to ensure the continuous supply of concrete and
checked upon arrival of concrete trucks to ensure the correct grade and type
is received.
t) Each truck of concrete slump and concrete temperature will be checked by
QA/QC engineer upon each delivery of concrete truck.
u) The mechanic of concrete pump or crane (if require) shall standby during
the casting operation and respond in case of breakdown.
v) Minimum 3 sets of diesel engines and vibrator pokers shall be provided for
each concrete pump at the casting field and two (2) additional sets of engine
& poker shall standby in case of breakdown.
w) Sufficient canvas sheet shall standby as contingency plan to cover fresh
concrete in order to prevent loss of concrete grout in the event of heavy
rainfall.
x) Pre-casting program & plan shall be submitted together with the final
inspection form for each pour. The program shall state down the estimated
concrete volume, casting duration, numbers of concrete pumps and
locations, concrete placing path for each concrete pump, manpower and
shift arrangement, plant and equipment available, materials for contingency
plan of heavy rain.
y) Water treatment tank shall be provided with adequate storage in order to
discharge the rain water to prevent flooding and silty water flow to the public
drain.
z) Concrete shall be placed from one direction to another direction with a
horizontal layer approximately 300mm depth.
aa) Concrete / cement mortar used for lubricating the concrete pump lines shall
not pour into the permanent structure and it shall be disposed outside the
permanent R.C structure.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 13
Construction PTE
LTD Basement

bb) The concrete shall be deposited in horizontal layers not exceeding 300mm
height or any deeper than the length of the vibrator poker head.
cc) The poker shall extend 100mm below the layer being compacted during
placing of 2nd layers of concrete to knit the two layers together.

600mm 300mm
100mm

Bottom layer 300mm

Vibration for bottom and top layer of concrete.

a) Large heap of concrete with sloping surface shall be avoided during


placing of concrete as this may encourages segregation.
b) Each layer of freshly placed concrete shall be fully compacted until
expulsion of air has practical cease before more concrete is placed on top
of it.
c) The placing lapse time of early layer to continuous layers shall be within
2 hour or otherwise agreed to avoid cold joint formation. A diagrammatic
sketch to illustrate the operation as below:

Typical concrete placing sequences for RC Beam and RC slab

Fill 4 ~ 5 & Fill 7~8 shall be placed within Each layer of concrete shall not be
2 hour to prevent cold joint formation place more than 300mm depth

Fill 8 Fill 7 Fill 5 Fill 4

Fill 6 Fill 3 Fill 2 Fill 1


Approx. 4~5 m long strip per fill
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 14
Construction PTE
LTD Basement

d) Foreman or supervisor shall randomly check on the fresh place concrete


by using a steel rod (soft or start harden) to avoid cold joint formation.
e) Special care will be taken to ensure thorough compaction around king
posts or other similar penetration, embedded items and construction joints.

dd) The concrete surface shall level by wooden or steel trowel to achieve a
uniform flat surface upon concrete reaches to the casting level.
ee) The slab surface shall be smooth if the surfaces are design for direct finish
whereas broom finish surface shall apply for topping up works.

Levelling concrete using vibrator levelling beam


ff) Plastic sheets, Curing Compound Sto SCC-Supreme and Gunny Sacks will
be proposed as curing materials.
gg) Curing Compound shall be immediately sprayed on top of concrete surface
with help of hand pump after the surface finishing works (spray frequency is
only once).
hh) Plastic sheet shall immediately cover up those areas after the curing
compound to prevent moisture losses during concrete hydration at
continuously curing condition until four (4) days or otherwise agreed as per
requirement.
ii) The plastic sheet shall be weight down by gunny sack with thin a firm of
water which will increase moisture for curing and also to prevent
displacement which will cause moisture losses.
jj) Curing method for construction joint shall carry out similar as above except
for curing compound.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 15
Construction PTE
LTD Basement

kk) For horizontal construction joint, concrete surface retarder StoDivers CSR-
S will be spray on it; where for vertical surface concrete surface retarder
StoDivers CSR-F will be apply to the construction joint formwork.
ll) Both surfaces shall washes by high pressure washer (~160bar) at least after
24 hours to achieve the aggregate exposed surface (roughen surface).
Striking off of side formwork and C.J formwork shall be at least 24 hours
or more after the last pour of concrete.

a) For vertical surface, curing compound shall immediately apply to the


surface with help of painting roller or handled sprayer after removal of
formwork.
b) If the formwork system using form-tie as tie system, the removal of such
insertions (Cone or equivalent) then will be carried out and the holes of
insertion shall be patched by approval non-shrink grout Stocrete NSG-H
progressively to allow subsequent activities.
c) For those R.C structure elements where it level drop more than 1000mm
shall be constructed separately.
d) The bottom slab for those containment pit on RC slab where its wall height
is more than 1 meter shall be cast separately as below:

>1000mm

1st cast

2nd 2nd
cas >1000mm cas
t t
1st cast
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 16
Construction PTE
LTD Basement

Cast together with slab Cast together with slab


2nd 2nd
cas >1000mm cas
t t

1st cast

e.)The wall shall cast in 2nd stage and then backfill with suitable materials but
not concrete as it may endanger the excavator operator during the excavation
operation.
f.)Finally the sump or pit wall shall joint to the RC slab.

7.4 Typical R.C Structure Work Sequences and Methodology for Bottom
slab

a) Excavation work shall only commence after the slab has achieved enough
strength to be sustained by the D’wall or Bored Hole
b) After certain level of excavation, land surveyor and contractor supervisor
shall work with the excavator operator to avoid over excavation.
c) Trimming of soil and lay blinding concrete shall carry out by R.C
Contractor in cooperation with Excavation Contractor.
d) Similar as top down construction method for the roof slab, land Surveyor
(main-con) shall provide offset or references point for construction team
to carry out detailed marking.
e) Soil attached on the D’wall and Bored Hole shall be removed before rebar
installation.
f) Related contractor shall expose the coupler located inside D’wall and
check the level after the blinding concrete hardened enough to received
weight.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 17
Construction PTE
LTD Basement

g) Related contractor shall roughen the D’wall using pneumatic hammer &
high pressure washer to clean the D’wall surface for the connection of
Bottom slab. In the event that defect is found at the interface of D’wall with
the slab (likewise for bored pile exposed top) including water seepages
should be rectified first prior to slab rebar installation.
h) Reinforcement bar shall be fabricated by local supplier or manufacture
according to the approved rebar shop drawing & bar bending schedule
(BBS).
i) The fabricated rebar shall be delivered progressively to the require job
area by trailer or lorry crane with assistance of crane. Some of the rebar
might be fabricated at job area due to the shape of rebar not able to
transfer by trailer.
j) The delivered rebar shall be hoisted down from the designated opening to
the loading bay beneath and transfer to the fixing area manually.
k) Trolley may be used as alternative method to transfer the fabricated rebar
to the working area.
l) The fabricated bar shall be supported by approved spacer block at bottom
layer to maintain the required cover as state in the general detail drawing.
m) The fabricated bar shall be installed according to approval reinforcement
shop drawing at the arrangement of B1; B2…. and together with the bar
chair which is designed and endorsed by P.E. to support top
reinforcement bar at fixing sequences as T2; T1
n) The fabricated bar shall be tied with Grade 20 GI wire at a randomly
alternate spacing to avoid displacement during casting.
o) Starter bar for wall; links or others elements shall be placed as per drawing
stated if applicable.
p) Inspection shall be arranged after the completion of bottom and top layer
of rebar.
q) All mechanical couplers shall be tightened by spanner or wrench.
r) Mortar or cement grout sticking on starter bars will be removed by using
high pressure water jet before concrete pouring.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 18
Construction PTE
LTD Basement

s) The opening formwork shall be carried out according to the alignment


provided by surveyor before or after the rebar installation.
t) Where for the C.J Formwork installation and preparation work, it shall be
carry out after the completion of rebar installation.
u) Contractor shall provide recess line as below for hydrophilic water stop
and re-injectable grout tube where install by others.

Timber 25x75mm

v) Timber 25x75mm will be use as formwork for the recess lines.


w) R6 Bar with color tape shall be used to indicate the designated casting
level where it shall be spot welded to top layer of rebar at a random
spacing.
x) The R6 bar shall be removed immediately before the concrete has harden.
y) If the casting related to join of previous cast panel or D’wall, the hydrophilic
water-stop and re-inject able grout tubes shall be securely fixed at the
construction joint.
z) Final inspection shall be arranged with QPS team.
aa) Pre-casting program & plan shall be submitted together with the final
inspection form for each pour. The program shall state down the estimated
concrete volume, casting duration, numbers of concrete pumps and
locations, concrete placing path for each concrete pump, traffic flow
direction, manpower and shift arrangement, plant and equipment
available, standby plant and equipment, lighting provisions, contingency
for rain & etc.
bb) The casting process for the slab basically operated with the help of
concrete pump which stationed on ground level connected with concrete
pipe to deliver concrete materials to the casting area through the
temporary structure opening.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 19
Construction PTE
LTD Basement

cc) Supervisor shall inform and coordinate with the main contractor supervisor
or engineers closely to ensure the continuous supply of concrete and
checked upon arrival of concrete trucks to ensure the correct grade and
type is received.
dd) Slump and concrete temperature shall be checked upon each delivery of
concrete truck by QA/QC team.
ee) A traffic control measure is necessary for casting of concrete to the
movement of concrete trucks by assigned controllers or traffic wardens.
ff) Mechanics of concrete pump (if require) shall standby during the casting
operation and respond in case of breakdown.
gg) Minimum 3 sets of good condition vibrator engines and pokers shall
provide to serve each concrete pump at the designated casting field and
2 sets shall standby to respond or substitute when the equipment
breakdown.
hh) Sufficient canvas sheet shall standby as contingency plan to cover fresh
concrete in the event of heavy rainfall.
ii) Water treatment tank will be provided with adequate storage to discharge
the rain water to prevent flooding and silty water flow to the public drain.
jj) Concrete shall be placed starting from one direction to another direction
with a horizontal layer approximately 400~500 mm depth. (Details of
length for each layer will be indicated in the casting plan to avoid cold joint
formation).
kk) The concrete shall be deposited in horizontal layers not exceeding 500mm
in compacted depth or the depth of each layer should not be any deeper
than the length of the poker head.
ll) The poker should extend below the layer being compacted and into the
one underneath by 100mm. This will knit the two layers together, and any
laitance on top of the lower layer will be mixed into the upper one.
mm) During concrete pouring, supervisor shall avoid forming large heap of
concrete with sloping surface as this encourages segregation.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 20
Construction PTE
LTD Basement

nn) Each layer of freshly placed concrete must be fully compacted until
expulsion of air has practical cease before more concrete is placed on top
of it.
oo) Each layer of concrete placed shall be vibrated thoroughly by suitable
sizes of vibration poker as the requirement of working environment. The
placing lapse time of earlier layer to subsequent layers shall be within 2
hour or otherwise agreed.
pp) If the slab consists of lift core, ejector pit pump sump, scupper drain where
the wall height is more than 1.0m in height, the soffit of the slab shall be
cast separately as below:

Cast together with Cast together with


slab slab

>1.0 m
2nd 2nd
cast cast

1st cast

qq) Concrete surface retarder StoDivers CSR-F shall be applied to the


construction joint formwork (vertical surface) to formed aggregate
exposed surface (roughen surface) by using high pressure washer after
24 hours of casting.

7.5 Typical R.C Structure Work Sequences and Methodology for Bottom-Up
Construction (Skin wall and internal wall)

a) After 4 days of curing or otherwise agreed for the RC slab, the rebar
installation for the external wall and internal wall shall commence.
b) The pre-embedded coupler bar and starter bar which embedded in the
soffit of roof slab will be exposed by manually chipping method.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 21
Construction PTE
LTD Basement

c) The installation of reinforcement bar for the walls will only be carried out
after the visual inspection of CJ roughening and surface cleaning by QPS
team.

d) Mobile scaffold or Tower scaffold working platform will be provided for


rebar fixing and drilling for the skin wall shear/tie bar.

e) Adjust or straighten the starter bar manually prior commence of


reinforcement bar installation.

f) The threaded vertical bar will be connected to the embedded coupler and
lap with the starter bar provision at the base slab and secure with G20 GI
tie wire.

g) The horizontal bar will be installed as per drawing until the required height
of wall.

h) Continue install the shear links to complete the walls reinforcement bar.

i) Tie wire to be Grade 20 GI wire and tie at a random alternate spacing to


the correct positioned rebar.

j) After completed the require section of reinforcement bar for the walls,
concrete spacer block to be fixed with tied wire at the require spacing.

k) M&E opening formwork and insertion shall be coordinated and installed to


the wall during rebar installation.
l) The M&E cast in item shall be installed at the manner nailed onto
designated position of panel formwork and tie to reinforcement at its fiscal
(fish tail if applicable) to avoid displacement during casting.
m) Inspection will be arranged before closing up the formwork for the wall.

n) Conventional wall formwork will be considered and designed by P.E (refer


to attachment) for the internal wall with cast in kingpost where system wall
formwork with triangle frame will be designed & used for the skin wall and
internal wall without kingpost.

o) Conventional wall formwork procedure as below :-


CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 22
Construction PTE
LTD Basement

 One side of form will be erected upon completion of reinforcement


fixing by temporary aligned as per the strutting system of formwork
design.
 Upon obtained approval to close formwork and the hydrophilic
water-stop had been installed (whenever applicable), the panel
formwork then be installed at joining of standard panels (2.4m width
x full high depth of elements) operation basic until to the designate
casting length. Two lift casting operation will be adopted if vertical
element exceeded 4m high aims to ensure good quality of
compacted concrete. During 1st lift casting, rubber hose (from
concrete pump parked on surface ground) to be extended and
lower down thru corrugated pipe hole, until reaching formwork top
and then start pour concrete.
 Strutting system of formwork will be continued according to the
approved formwork design and the control to verticality, alignment
adjusting shall be carried out until fulfill to the requirement.
 All ties and nuts used for the formwork system shall be checked
and without loosen prior to casting.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 23
Construction PTE
LTD Basement

 Proper working platform shall be provided with safe mean access


for formwork installation, the final inspection and casting.

p) Where for skin wall and internal wall without kingpost, system wall
formwork with triangle frame will be used. Sample section view as shown
below for illustration:

q) The casting sequences for external and internal wall will be by concrete
pump stationed at ground and feed to concrete pipes to extend the
discharge distance.
r) The concrete rate of pour (hour/meter height) for wall formwork shall
strictly follow by the P.E design calculation (refer to attachment).
s) Supervisor shall coordinate with Main contractor supervisor or engineer to
ensure smooth continuous supply of concrete and checked upon arrival
of concrete trucks to ensure the correct grade and type is received.
t) Slump and temperature shall be checked upon each delivery of concrete
truck by QA/QC engineer.
u) Concrete cubes will be taken according to the M&W specification.
v) A traffic control measure is necessary for the delivery of concrete in
controlling the movement of concrete trucks by assigned controllers or
traffic wardens.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 24
Construction PTE
LTD Basement

w) Mechanic shall on standby during the casting operation and responding


in case of breakdown.
x) 3 sets of good condition vibrator engines and pokers shall be provided to
serve each concrete pump, and at least two (2) additional sets of engine
& poker shall standby to respond or substitute when the equipment
breakdown.
y) Sufficient canvas sheet shall be standby as contingency plan to cover
fresh concrete in the event of heavy rainfall. Water pump at designated
pump sump shall be adequate to discharge the rain water to prevent
flooding.
z) Concrete shall be placed from lower point toward rising level and always
begin the placing at end corner with a horizontal layer approximately 300
mm depth.
aa) Each layer of concrete placed shall be vibrated thoroughly by suitable
sizes of vibration poker. The placing lapse time of early layer with the
continuous layers shall be within 2 hour or otherwise agreed to avoid cold
joint.
bb) A sample diagrammatic sketch to address the pour strip operation is
illustrated below (3m height):

Arrangement of concrete placing sequences for wall (Pour Strip)

Example casting height of wall = 3.0m

Casting layer in horizontal plane = max 300mm depth

Concrete placing shall start from one end towards the other end.

Placing time for each layer shall within 2 hour and the placing mode shall
complete 1st layer and follow by 2nd layer.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 25
Construction PTE
LTD Basement

Plan View of wall

CJ Skip n Skip n Skip 2 Skip 1 CJ

Elevation view (Pouring duration shall not more than 2 hour per layer)

10th layer
9th layer
8th layer
7th layer
6th layer
5th layer
4th layer xiii xii
3rd layer xi x viii
2nd layer ix vii v iv

1st layer vi iii ii i

Concrete Discharge pipe

Maximum
300mm per layer

Single side system


wall formwork

Typical Section View for Construction of Skin wall


CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 26
Construction PTE
LTD Basement

Concrete Discharge pipe

Maximum
300mm per layer Single side system
wall formwork

Typical Section View for Construction of internal wall

a) The concrete shall be poured in as per below figure. For the opening
formed by the corrugated pipe, spacing of corrugated pipe holes need to
be close (800mm ~ 1500mm c/c spacing) to assure concrete
compactness in between slab soffit and wall top. And for the alternative
measure in the event that corrugated pipe method couldn’t apply,
pressure grouting is to be adopt with 800mm c/c pipe spacing to assure
the concrete compactness.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 27
Construction PTE
LTD Basement

Opening form by corrugated pipe

Poker vibrator
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 28
Construction PTE
LTD Basement

a) Striking off of wall panel formwork & vertical CJ formwork shall only carry
out at least after 24 hour of casting.
b) At skin wall location, there is another option to cast the second lift of skin
wall when down-hang option with corrugated pipe is not feasible. If down-
hang option with corrugated pipe is not feasible, another option is by using
pressure grouting method. In order to avoid air entrapment, 2 hose to be
fixed on formwork, that is inlet hose located at lower portion, and outlet
hose located at upper portion. Pump fresh grout thru inlet hose until
overflow thru outlet hose to avoid air entrapment. Chipping aggregate will
not be use, only use approved non-shrink grout.

Grouting method for skin wall second cast


CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 29
Construction PTE
LTD Basement

For horizontal construction joint, Concrete surface retarder StoDivers


CSR-F shall apply to the concrete surface; where for vertical
construction joint, StoDivers CSR-S shall apply to the C.J formwork
before casting in
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 30
Construction PTE
LTD Basement

cc) order to formed aggregate exposed surface (roughen surface) by using


the high pressure washer after 24 hours of casting.
dd) Curing compound Sto SCC Supreme will be use for the wall and column.
ee) Painting roller and hand held sprayer shall be used to apply the curing
compound to the wall or column (vertical) surface.
ff) If the formwork system was designed to use tie rod as tie system, the
removal of such insertions (Cone or equivalent) then shall carry out and
the holes of insertions shall patch by approved non-shrink grout
progressively to achieve the requirement or allow subsequent activities
such as water proofing membranes application if any.

7.7 Typical R.C Structure Work Sequences and Methodology for Bottom-Up
Construction (Slab)

a) C60 shoring system will be proposed as vertical support for soffit formwork.
b) The shoring system shall be designed and endorsed by P.E.
c) The erection of shoring shall according to the design drawing endorsed by
P.E.
d) Tied reinforcement for the main slab and starter bars where applicable.
e) The fabricated bar shall be supported by approved spacer block at bottom
layer to maintain the required cover as state in the general detail drawing.
f) The fabricated bar shall be installed according to approval reinforcement
shop drawing at the arrangement of B1; B2…..and together with the bar
chair which is designed and endorsed by P.E. to support top reinforcement
bar at fixing sequences as……T2; T1.
g) The fabricated bar shall be tied with Grade 20 GI wire at a randomly
alternate spacing to avoid displacement during casting.
h) Installed CJ formwork and side formwork. (if applicable).
i) Provide COS for falsework.
j) Arranged final inspection inclusive SWC and M&E clearance.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 31
Construction PTE
LTD Basement

k) Casting slab after getting approval with help of pump truck which stationed
on surface and connecting concrete pipe to facilitate the casting range.
l) Curing and gained strength for false-work removal at a period of 7 calendar
days after casting or with an effective working strength achieved to 75 %
of design strength based on cube testing result.

Dismantling False-works and Supports

i. False-work and the supports will be removed only after 7 days of casting
or with the minimum concrete strength of practical developed to 75% of
design strength. (e.g. average 30 KN for grade 40 concrete mix)
ii. Back prop system shall provide for any early removal of shoring minimum
5 days & concrete strength shall develop to 75%.
iii. Test cubes for the slab (cast) will be arranged for testing before getting
permission to false-work removal. The required practical developed
strength will be obtained through the cubes test result.
iv. The removal of false-work shall be begun at release pressure at center
portion of slab and then towards the direction of both side of D’wall, so
that the loading will transmit accordingly by loosen the U-Head jack or
Jack base.
v. After loosen the false-work supports, shuttering and secondary bearer will
be removed progressively with care follow by primary bearer and scaffold
materials.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 32
Construction PTE
LTD Basement

vi. The removed false-work materials will be transferred to the subsequent


panels repeatedly for construction until completion then transfer to the
designated loading bay manually for removal by crane.
vii. If applicable, false-work system may be assembled as Table-form basic
for the construction of RC slab to increase the productivity rate.

8. Safe Work Procedure


The construction of Substructure works for basement shall strictly comply
with the regulation of WSH Act 2006 and its subsidiary legislation regulation,
ENV Public Health Act and subsidiary legislation regulation and in-house
regulation of Authorizes requirement inclusive the safe work procedures,
Risk management, environmental control.

The enforcement in workplace safety & health and environmental aspect


control measure

8.1 General Site Safety Provisions

8.1.1 Provide assemble area and shelter as resting area to prevent heat
stroke and gathering area for site discussion.

8.1.2 Provide suitable overhead protection (in the form of safety nets,
catch platforms and hoarding, etc) where persons are required to work or
pass by places that are exposed to frequent falling materials or objects.

8.1.3 Provide proper signage to notify the hazards.

8.1.4 Provide hard barricade surrounding the crane body-turning radius.

8.1.5 Remove or cover the protruding sharp object.

8.1.6 Provide suitable storage area with proper barricade for chemical.

8.1.7 Provide alert sound for lifting operation at depth excavation area.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 33
Construction PTE
LTD Basement

8.2 Floor Opening

Openings on floors / slabs / walls and the open sides of buildings


/ structures through which a person may fall shall be barricaded
with rigid materials to prevent falls hazards. However, access for
work to progress shall provide.

8.3 Floor Surface

8.3.1 Oil, grease and other substances, which can cause slipping, shall
remove from all passageways, working platforms and other
elevated working surfaces.
8.3.2 The site, especially passageways, platforms and work areas, should
keep clean and free of debris and rubbish.

8.4 Site Access

8.4.1 Safe access in the form of stairways and ramps should be provided
to working levels above or below ground.

8.4.2 The place below any work involving welding or torch cutting of metal
shall rope off or guard against entry by other persons. Such places
shall also be free of combustible materials.
8.4.3 Slippery platforms on ground or elevated working surfaces shall
remove.
8.4.4 All passageways, platforms and other places of work should keep
free from obstacles that may cause tripping. Good housekeeping
should introduce for the proper storing of materials at work site.

8.5 Debris Disposal

8.5.1 All debris shall be disposed off through temporary refuse chutes, by
means of containers lowered by hoist/winches/lifts or by other
practical safe methods approved by the Chief Inspector.
8.5.2 Debris shall not dispose off in a manner as to pose a danger to any
person. All debris should dispose through the refuse-chute.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 34
Construction PTE
LTD Basement

8.6 Ladders

8.6.1 Ladder and stepladder adopted on site should made by rigid or


adequate strength materials.
8.6.2 The ladder shall fix or stand on firm ground to prevent slipping or
falling from height.
8.6.3 “Buddy System” shall adopt while using stepladder as working tools.

8.7 Formwork and False-work

8.7.1 Formwork and supporting shores shall be structurally safe and


should be properly braced or tied. A designated person shall appoint
to check and ensure that it is safe. The appointed supervisor shall
have the relevant supervisory certificate.
8.7.2 Appointed supervisor shall inspect the formwork, shores, braces
and other supports regularly during concreting. Any unsafe
formwork or false-work discovered should be remedied immediately.
8.7.3 Stripping formwork shall not commence until instruction is receive
from the Engineer. The stripped forms should remove or stockpiled
promptly after stripping to enable a free passageway.

8.8 Formwork Shoring

8.8.1 Vertical shores for high multi-tier scaffolds must be set plumb and in
alignment with lower tiers so that load is transfer directly.
8.8.2 Shoring members are to be straight and true without twists or bends.
8.8.3 Inclined shores must brace against slipping or sliding.
8.8.4 Shores supporting inclined formwork members should connect to
the formwork with adequate strength as design.
8.8.5 Shoring load must carry only on the legs and not on the horizontal
members.
8.8.6 There should not have any loose timber lying on the scaffold and all
platforms must securely fasten.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 35
Construction PTE
LTD Basement

8.9 Formwork Shore Supports

8.9.1 Where shores directly rest on the ground, the ground must be firm,
solid or proper plank should be provided.
8.9.2 Shores resting on new construction that has not developed
adequate strength should place as near as possible above the
shores or re-propped below the floor.
8.9.3 For multistory structure, shoring should be provided with the require
capacity to support imposed loads during construction.
8.9.4 Local overloading when a heavily loaded shore rests on thin slabs
shall avoid.

8.10 Removal of formwork Shores

8.10.1 The contractor has the responsibility of design, construction and


safety for false-work the time of removal the formwork system are
of critical importance.
8.10.2 Premature removal can be a source of great danger. As such, the
site supervisor should check with the design engineer as to when
the form and shores shall remove.
8.10.3 Removal of shores for multi-storey buildings requires special
consideration. A given floor slab may be required to support one or
two storey of dead and live loads from the work going on above.
8.10.4 Care must exercise during removal of shores and formwork; the
area concerned shall cordon off and workers should stand well clear
of the possible falling formwork.

8.11 Steel reinforcement work

8.11.1 Persons handling long bars shall position at the ends and / or bends.
8.11.2 Protective gloves shall wear. In the transportation of bars, all bars
must be securely bundled and the bundles secured to the vehicles.
Loose bars must not be left untied.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 36
Construction PTE
LTD Basement

8.11.3 Protruding bars shall cover or protected. When erecting column


bars, the bars shall secure and braced if necessary. All bars already
in position shall secure by tying wires. Experienced persons should
operate bending and cutting machines.
8.11.4 Bars for lifting shall secure and properly hooked. There should not
inflammable material in the vicinity when cutting bars by flame.
Proper walking platforms shall provide.
8.11.5 Proper walking platforms with guardrails if necessary should also
provide along the outside of edge beans and on the side of beams
without slabs. This shall ensure safety for checking and subsequent
concreting work.

8.12 Concreting work

8.12.1 The team of concreters must be properly organized under one


foreman. Proper platforms shall provide for concreting. Concrete
shall distribute whilst being discharged to prevent localized
overloading.
8.12.1 Adequate platforms shall provide for concreting cantilever beams.
Carpenters must properly construct concreting chute if required.
8.13 Concreting using pump (stationary or pump truck)
When concrete delivery by pump, all pipe segments shall properly
secure & fasten. When using boom-pumps, only experience
operators shall carry out the maneuvers.

8.14 Concreting using crane and bucket

8.14.1 The ground must be stable at the location where the concrete trucks
discharge into the bucket. Concrete bucket must be firm and in good
operating condition. The discharge opening must be able to open
and close freely.
8.14.2 A standard procedure must be agreed upon between the certified
rigger / supervisor guiding the crane operator. Concrete bucket shall
secure & hook to cranes.
CREC Est Date : 25/4/2018
Method Statement for RC Structure Works for CUP_A1 Building Page : 37
Construction PTE
LTD Basement

8.15 Concreting at Night

Adequate lighting shall provide when concreting at night; lamps


shall position such that the concrete buckets would not knock them
down.

8.16 Working at height

8.16.1 Safety belts, lifelines and devices for the attachment of lifelines (of
adequate strength and approved) shall be issued to the workers
working at height.
8.16.2 Workers shall attend the proper method of wearing and using them.
Sufficient anchorage shall provide.
8.16.3 Safety belts, helmets and proper anchorage shall provide for
workers who are carrying out external finishes work. All erected
working platforms are to be closely monitored and constantly
checked.
8.16.4 Any defects found on scaffold or working platform shall report and
remedied immediately.
8.16.5 Constant checking should be carried out to ensure that materials
are properly disposed, preventing workers from being hit by falling
object.
8.16.6 The safety officer shall remind all sub-con to ensure that their
employees comply with all the site safety requirements. He shall
also demonstrate to them the proper usage of the personal safety
equipment.
8.16.7 Any unsafe work or unsafe acts shall highlight at the site safety
committee meeting. Proper coordination with other co-contractors
on the safety aspects would then be carried out.

Vous aimerez peut-être aussi