Académique Documents
Professionnel Documents
Culture Documents
Module : 11
Assignment No : 1
Submitted by
SRINATH SRINIVASAN
Your company has bagged a lucrative contract to construct a housing colony for an
manager have been asked by the company to evolve organization structure with
following conditions.
All supervisors to down below will be temporary for project duration only to be
communication control for all facets of construction work and management functions
as visualized by you.
buildings, 100 dwellings for white collar workers and 300 dwellings for blue collar
level.
2. This will cut down the cost involved in arranging and maintaining man power.
5. Supervisors below junior level will be on temporary job basis and to be recruited
6. Only travel arrangements can be made on demand as the people are around
The Complete colony area can be tentatively divided as indicated in the tabulated form
given below,
recreation hubs like multiplex is also proposed to be built along with the housing
INTRODUCTION
blocks for different level of personnel based on the hierarchy / and their designation
in the firm they work for the project range varies from bungalows for senior executives
to apartments and dwellings for white collar and blue collar workers.
administrative functions.
Assigning duties to the Authorities along with giving suitable jobs to junior staff
members.
Controlling and forming a structure required for the proper execution of project.
SRINATH SRINIVASAN 4 217-06-11-50971-2191
Main pillars on which a construction project is laid are proper, effective and efficient
planning and management of material flow. All the authorities guiding personnel at
between the top level & bottom of management must be smooth and clear avoiding
any conflict and misguidance. Manpower should be as lean as possible avoiding any
For planning, managing and executing a construction project following key areas are
the axis around which a Project manager emphasis and concern should revolve:-
1. Committed leadership.
4. Quality driven agenda & intelligent planning of finances and cash flow.
5. Making a task schedule clearly indicating start and finish date of project along
with time taken to complete different individual tasks at different levels and
stages of project.
1. Planning
decision making. Planning and controlling are closely interrelated. After bagging this
successfully, financially that is also best option. Entire project will be sub divided in to
sub project and also it will be further subdivided zone wise to facilitate work. Short
2. Objectives
Objectives are end points towards which activities are aimed. Objectives are verifiable
if it is possible, at the end of the period, to determine they have been accomplished.
Objectives form a hierarchy, starting from corporate missions or purposes going down
to individual goals. Managers can best determine the number of objectives they
should realistically set for themselves by analyzing the nature of the jobs and how
Without planning, it is not possible to achieve the desire goals. Planning involves the
formulation of what, how, when, where & by whom it is to be done, to evaluate and
result.
Another function of the management is to organize the business. Proper and sound
organization is the bases of success of every industry and manages. It is often said that
good people can make any organization pattern work. However there can be no doubt
that people can work together most effectively, if they have a clear understanding of
their role in the organization and the way their roles relate with their co-workers.
organizational levels, and a narrow span results in much level. There is no definite
number of people a manager can always effectively supervise; the number depends
on several underlying factors. These include the degree of training of sub ordinates
that is required and is possessed the clarity of plans, the use of objective standards,
policies and plans to achieve the ends, identifying activities, grouping these activities,
relationships.
training people.
important input for staffing tasks. The number and quality of managers required to
carry out crucial tasks depend on many different factors. One major step in staffing is
and training. On the job training includes planned progression, job rotation, creation
of' assistant to' position, temporary promotions, use of committees and junior boards.
programme. The selection process may include interviews various tests and the use of
ensure that new employees are introduced to and integrated with other persons in
the organization.
organization and group goals. While working towards, a manager must take into
account the dignity of the person. Motivation is not a single concept, rather it pertains
formally or informally, for purposes of meeting and maintaining certain group values
and interests. One or more persons in the group may assume the role of influencing
In relation to their followers in the group, leader performs several roles. They
assemble their followers into a coherent unit. They set up clarity and enforce group
goals, values and norms. They activate and control group tasks and channel group
energies into meaningful directions. Good leaders are both task oriented and people
oriented. They seek to direct group activities toward high productivity and satisfaction.
Task orientation involves defining group goals and standers, establishing task
performance in order to ensure that enterprise objectives and the plans devised to
Control techniques and systems are basically the same regardless of what being
controlled. Where it is found and whenever is being controlled, the basic control
a) Establishing standards
There are different kinds of standards and all should point out simple feedback system
deviations, developing plans for taking corrective action and implementing these
manager utilize a feed forward control approach and not rely on single feedback alone.
Overall controls are financial, one of which is profit and loss control. Another is
approach is based on the idea that profit should be considered not as an absolute
measure but as a return on the capital employed in a business or a segment of it. The
If controls are to work, they must be specially tailored to plans and positions, to
individual managers, and to the needs for efficiency and effectiveness. To be effective,
corrective action.
All above mentioned functions, managers should know that they should also know the
three basic terms and should properly deal with those terms. These three terms are
a) Responsibility
b) Authority
c) Delegating authority.
Now we will take in mind that the functions which we have to perform in site or goal
4. Plot cleaning
5. Site Mobilization
a. Site establishment
6. Construction work
8. Billing work
9. Landscaping work
the nature of work, category of work, size and stages of completion of work organize
team.
Project Manager:
Project manager is the leader for all activities and effective communication system.
Planning department
Responsibility
Plan each and every activity as per time limit given by the client. Preparing bar chart,
achieving better quality in minimum cost is the main aim of this department.
Responsibility
Execution of work as per drawings, plans and specifications is main work of execution
department. In this department Sr. Execution engineer and gang of junior engineers
are appointed.
Responsibility
making GRN, storing and housing all material on site in proper place as per the site
condition and handover material to contractor as per their requirement, keeping their
QA/QC department
Responsibility
Checking of all material coming to site and testing as per requirement (Material Test
Plan). Verifying mix design of material going to use for site execution, inspection and
checking of all activities of execution work regarding quality norms and condition,
testing of work executed like sample testing (cube testing) non-destructive testing
making of audit report maintaining material testing, mix design, concrete testing, audit
Responsibility
Checking of all drawing and specification regarding site, estimating and surveying
quantity of each work activity separately, calculating material required, quantity, labor
required for each and every activity is the work of this department.
Billing Department
Responsibility
Checking of all bills quoted by sub-contractor or contractor as per their site executed
Keeping total money expenditure regarding site, checking of departmental labor bill,
making payment of all site office related staff and helper is the main work of account
department.
Admin Department
Responsibility
electrical supply, water supply, making and repairing of any construction equipment
Each and every above mentioned entity in organization level or structure has got to
perform all the function stated above in daily work out for successful completion of
the project. Either knowingly or unknowingly while executing any activity in project.
They will be given adequate knowledge to what to do, when to do, who is to perform
what and the responsibility, also authority hold the particular person for the exact task
handed. Problem encounter and any deviation for schedule project should be follow
through proper channel and as quickly as possible. Any communication should flow
not only downward or upward in the organization structure but also horizontally and
diagonally. For this type of communication daily or weekly basis meeting as possible
to respective level should be conducted. Basically the organization structure has been
divided into two team to make project grand success with the help of manager’s
valuable guidance.
Daily report should be generated on site and it shall be submitted to head office
immediately if possible on the same day. This report will be help in to monitor the
project closely and controlling the project for its deviation can be solved by proper
decision or action. This action or decision may or may not involve financial condition,
also re-planning the activities and re-scheduling of project to avoid upcoming risk can
be easily possible with the data available in means of the daily reports. Daily report
Communication should be maintained properly at all levels. Both teams should have
information of both the project and knowledge with all daily activities of both the
projects such that communication also is carried out in horizontal and diagonal in the
structure should be well defined before work to be carried out the entity. Finance
should not be barrier on site for proceeding of work, this should be seen by head office
with keen interest to avoid project delay and indirect cost can be controlled by not
Critical activities in project should distinct and proper monitoring and control should
be obtained on them. Key date and target shall be estimated for these critical
activities, as any deviation for this may cause severe financial loses, directly and
indirectly by this project to company. Each person in the organization structure must
be made continuous aware of this activities and tight up their knuckle down to this
Ensuring the early involvement of the key project team member that have
can be defined.
Working together as a team to agree mutual goals and devise dispute resolution
mechanisms.
Dealing with the risks and rewards by using modem commercial arrangements
such as collaborative contract forms target cost and open book accounting.
Publications