Académique Documents
Professionnel Documents
Culture Documents
8.1 Conclusions
into
Various types of contracts of the above two methods are described in detail in
chapter 2.
2. In Sri Lanka, the traditional bill of quantities (Measure and pay) types of
contracts are widely used in both the public and private sector in procuring
in the U.K. for different types of procurement methods. The important feature is
that the building and civil engineering contracts use different conditions of
4. FIDIC 3 although intended for measure and pay type civil engineering works,
have been used for building construction works as well in other countries.
5. Problems arising from using FIDIC 3 for building works have been documented.
120
(ii) Tenders advertise locally:- Conditions of contract is I C T A D 89.
7. Building construction works of the private sector in Sri Lanka uses a modified
conditions of contract.
(i) About 55% think that the separate conditions of contract for building and
civil engineering construction works are not required. But 35% think
other way.
are the general clauses cover for both building and civil engineering
(iv) Some consultants have not faced much problems with ICTAD 89. It may
works.
10. Building and civil engineering construction works have some different notable
121
In building construction works
(v) Design and supervision works are usually carried out by chartered
(iv) Design and supervision works are usually carried out by chartered civil
engineers
122
(i) 25 clauses of the ICTAD 89 can be used without any modifications.
clause of FIDIC 4.
72.
8.2 Recommendations
1. ICTAD should take steps to introduce, explain and solve problems arising of the ICTAD
2. Periodic seminars should be held to discuss experiences and to identify revisions required
(i) Local practices and views of the professionals involved in building construction
123
works.
(iv) Studying other conditions of contract (Make use of the comparison done in this
study).
4. Contractors should be taught and allowed to comment freely on any changes made by the
5. There should be a national policy to use ICTAD conditions of contract without changing
6. There should be separate conditions of contract for major and minor building construction
works.
consultants, clients and contractors in association with the ACCSL, the I C T A D , the
Surveyors.
124
REFERENCES
REFERENCES
Austen, A.D. and Neale, R.H.(1990). "Managing Construction Projects - A Guide to Processes
and Procedures". Genova, International Labour Office, pp 5-33.
Balasooriya, B.M.A. (1992). "Historical aspects of the building industry in Sri Lanka".
Proceedings of a seminar on engineering research and development, Faculty of Engineering,
University of Peradeniya, (Jubilee 1942-92).
Dickason, Ivan (1985). "JCT 80 and the builder an introduction", CIOB publication.
Fernando, C.C.T.(1986). "Consulting practice in Sri Lanka". Lecture note delivered at the
(World bank/UNDP/FIDIC/The Association of Consulting Engineers, Sri Lanka) seminar held
in Hotel Galadari Meridian, Colombo.
FIDIC conditions of contract for works of civil engineering construction, FourUi edition,
September 1987, FIDIC publication.
10. Ganeshan, S.(1991). "Development of the national construction industry - A case study of Sri
Lanka". An ICTAD publication in association with the world bank.
11. General conditions of contract for building and civil engineering- GC/WORKS/1 (Edition 3),
(Lump sum with quantities)(December 1989, Revised edition 1990),HMSO, Department of the
Environment Property Holdings, London.
12. "Guide to the use of FIDIC" (Fourth edition),(1989). Conditions of contract for works of civil
engineering construction, FIDIC publication.
13. Gunasekara, Mervyn. P. (1990) "Procuring construction projects in Sri Lanka - Contractor's view
point". Seminar notes on construction management of Asian Productivity Organisation conducted
by the ICTAD and the NI13M.
14. Hugh Clamp and Stanley Cox. (1990). Which contract? choosing the appropriate building
contract, RIBA publications.
15. ICE conditions of contract and forms of tender, agreement and bond for use in connection with
works of civil engineering construction, Filth edition (June 1973) (Reprinted January 1986).
16. ICTAD conditions of contract for building work, Sri Lanka. Unpublished document (Draft).
17. ICTAD conditions of contract (First edition - September 1986), CITP Publication No. SCA/1.
18. ICTAD conditions of contract (Revised edition - January 1989), ICTAD Publication No. SCA/1.
19. JCT Standard form of building contract 1980 edition (Local authorities with quantities), RIBA
publications Ltd, London.
20. Joachim, M.E.(1988). Survey report on construction industry in Sri Lanka (Phase 1)., Asian
Productivity Organisation.
21. Jones, Glyn P.(1979). " A new approach to the international civil engineering contract". New
York, The Construction Press Ltd.
22. Kulasinghe, A.N.S. (1986). "The Development of Consulting Engineering Practice in Sri Lanka".
Lecture note delivered at the (World bank/UNDP/FlDIC/ The Association of Consulting
Engineers, Sri Lanka) Seminar held in Hotel Galadari Meridian, Colombo.
23. Kumarasinghe, Jaliya and Kumarasinghe, Ananda (1990). "Country paper on the construction
industry in Sri Lanka". Seminar notes on construction management of Asian Productivity
Organisation conducted by the ICTAD and the NIBM.
24. Ramus, J.W.(1989). "Contract Practice for Quantity surveyors". Second edition,
U.K.,Heinemann, Newnes.
25. Ratnayake, A.(1991). "Contract administration practices in Sri Lanka". Seminar notes on
engineering consultancy and contracting practices in the SAARC region held in Colombo,
Organised by the Institution of Engineers Sri Lanka with Federation of Engineering Institutions
of South and Central Asia.
26. Rush Brooke, P.L. (1983). Working with FIDIC", A practical approach to its use in the Middle
East, CIOB publication.
27. Sawyer, John.G. and Arthur Gillott, C. (1990). "The FIDIC Digest - Contractual relationships,
responsibilities and claims under the fourth edition of the FIDIC conditions". First edition,
London, Thomas Telford Ltd.
28. Spiers, G.S.(1983). "The standard form of contract in times of change", CIOB publication.
29. Tissera, CH.de.(1990). "ICTAD Profile". Ministry of Policy Planning and Implementation.
30. Wallace, Duncan I.N. (1974). "The international civil engineering contract". First edition,
London, Sweet and Maxwell Ltd.
31. Weerakkody, Felix (1986). "Historical background of the construction industry in Sri Lanka".
Research paper submitted to the master of business administration degree at University of Sri
Jayawardanapura on managerial analysis of the construction industry in Sri Lanka.
32. Zylva, Eddie De., Weddikkara, Chitra., and Emmanuel, M.P.R.(1989). "Sri Lanka construction
industry in the 80's". (Project SRL/86/001-IDA/UNDP/ILO).
INTERVIEWS AND DISCUSSIONS
Professionals Participated in the Interviews a n d Discussions
A T T E N T I O N OF
Dear Sirs,
Therefore I will be very much grateful to you, if you could give information by filling
the attached questionnaire at your earliest convenience and send it to my Colombo address. For
your convenience, I am enclosing a self-addressed stamped envelope.
Since no telephone facilities are available at my working place, it will be very difficult
to contact you over the telephone during working hours.
Please also note that all information provided by you will be treated strictly confidential
and used solely for the specific purpose of the survey.
I hope your kind co-operation and assistance to make this survey a success.
Thanking you,
Yours faithfully,
(signed)
N . Logeswaran
R E S E A R C H PROTECT QUESTIONNAIRE FOR M.Eng. D E G R E E IN C O N S T R U C T I O N
M A N A G E M E N T . D E P A R T M E N T O F CIVIL E N G I N E E R I N G . U N I V E R S I T Y O F
MORATUWA
(i) The types of conditions of contracts used in Sri Lanka, in the past
and the present.
(ii) The necessity to modify the ICTAD conditions of contract to suit
local building construction works.
1.0 GENERAL
1.4 Discipline of work:- (If you do work in more than one discipline please indicate the
order of priority)
1.5 Name, designation, contact address and telephone number of the officer
responding :-
NAME:-
DESIGNATION:-
CONTACT ADDRESS:-
T E L E P H O N E NO:-
2.0 CONDITIONS OF CONTRACTS
2.1 What were/are the types of conditions of contract for building construction works you
or your organisation has used in the past and what are presently being used?
(Eg. FIDIC 3 , FIDIC 4, ICTAD 89, JCT 80 etc., with or without modification or any
other)
(a) What are the problems you or your organisation encounter while using ICATD
conditions of contract for building construction works?
(b) What are the clauses in the ICTAD conditions of contract do you consider to require
modification with regard to building construction works?
(c) H o w could the ICTAD conditions of contract be modified for the local building
construction works?
(For eg. Based on some other conditions of contract or your own)
(a) Why the ICTAD conditions of contract is not used for building construction works?
(b) What are the changes to be made to ICTAD conditions of contract in your opinion
to use for building construction works?
2.4 What are your views about having separate conditions of contract for building and civil
engineering construction works?
2.5 ICTAD conditions of contract is the modification of the FIDIC conditions of contract
(Third edition) and the FIDIC is meant only for civil engineering construction works
whereas the ICATD conditions of contract is meant for both building and civil
engineering construction works.
2.6 If you have mentioned the FIDIC conditions of contract at 2.1 above.
What are the specific problems you or your organisation encounter while using it for
building construction works?
2.7 What are your views about the cabinet decision for having one conditions of contract
(ICTAD) for both building and civil engineering construction works?
2.8 If you have mentioned the RIBA conditions of contract at 2 . 1 , what are the main
differences between the RIBA and the ICTAD conditions of contract?
APPENDIX - B
APPENDIX B
COMPARISON OF CONDITIONS OF CONTRACTS WITH CLAUSE NUMBER AND DESCRITPION
No. FIDIC conditions of contract ICTAD conditions of FIDIC conditions of JCT 80(Local GC/Works/1 (Edition Remarks
(Third edition) = FIDIC 3 contract (Revised edition contract(Fourth Authorities with 3) =GCW1
1989)=ICTAD 89 edition) = FIDIC 4 Quantities)=JCT 80
No. FIDIC conditions of contract ICTAD conditions of FIDIC conditions of JCT 80(Local GC/Works/1 (Edition Remarks
(Third edition)=FIDIC 3 contract (Revised edition contract(Fourth Authorities with 3) =GCW1
1989)=ICTAD 89 edition) = FIDIC 4 Quantities) = JCT 80
ASSIGNMENT AND SUB ASSIGNMENT AND SUB ASSINGMENT AND SUB 19 Assignment and
LETTING LETTING CONTRACTING Sub- Contracts
3 3 Assignment 3 Assignment 61 Assignment
3.1 Assignment of Contract 19.1 Assignment C
62 Sub-letting
4 4 Sub-letting 4 Sub-letting 19.2 Sub-letting-
4.1 Sub-Contracting Domestic
4.2 Assignment of Sub Sub-Contractors.-
-Contractor's Obligations Architect's/
Supervising
Officer's consent
19.3 Sub-letting-list in
Contract Bills
19.4 Sub-letting
-Determination
of Employment of
Domestic Sub
-Contractor
6 6.1 Custody of Drawings 6.1 Custody of Drawings 6.1 Custody and Supply of 5. Contract Documents - 2 Contract Documents c
6.2 One Copy of Drawings to 6.2 One Copy of Drawings to be Drawings and Documents other documents - issue of
be kept on Site kept on Site 6.2 One Copy of Drawings to be certificates
6.3 Disruption of Progress 6.3 Disruption of Progress kept on Site 5.1 Custody of Contract Bills
6.4 Delays and cost of delay of 6.4 Delays and Cost of Delay of 6.3 Disruption of Progress and Contract Drawings
Drawings Drawings 6.4 Delays and Cost of Delay of 5.2 Copies of Documents
Drawings 5.3 Descriptive Schedules etc-
6.5 Failure by Contractor to Master Programme of
Submit Drawings Contractor
5.5 Availability of certain
documents
5.6 Return of Drawings etc.
5.7 Limits to use of
documents
7. 7. Further drawings and 7. Further drawings and 7.1 Supplementary drawings and 5.4 Drawings or details No clause c
instructions instructions instructions.
10 10. Performance Bond 10. Performance Bond 10.1 Performance Security No clause No clause B
D* 10.2 Period of Validity of
Performance Security
10.3 Claims under
Performance Security
F4.10*
11 11. Inspection of Site 11. Inspection of Site 11.1 Inspection of Site No clause 7.1' Conditions B
D* D* 7.2 . affecting
7.6 Works
E*
12 12. Sufficiency of Tender 12. Sufficiency of Tender. 12.1 Sufficiency of Tender No clause 7.3") Conditions C
Adverse Physical Adverse Physical 12-2. Adverse Physical 7.4( affecting
Conditions and Artificial Conditions and Artificial Obstructions or Conditions 7.5j Works
Obstructions Obstructions
13 13. Work to be to the 13. Work to be to the 13.1 Work to be in Accordance 2.1 Contract Documents No clause A
Satisfaction of Engineer Satisfaction of Engineer with Contract E*
D* * F4.13
33 Programme C
14 14 Programme to be 14 Programme to be 14.1 Programme to be Submitted 5.3.1.2
Furnished Furnished 14.2 Revised Programme Descriptive
14.3 Cash Flow Estimate to be Schedules etc-
Submitted Master Programme
14.4 Contractor not Relieved of of Contractor
Duties or Responsibilities
t-4.8* - Clearly explained and covers more conditions.
JC.8* - Not clearly covered as FIDIC 3 .
E* - Similar to FIDIC3.
D* - No change.
F4.10* - Clearly explained and covers more conditions.
F4.13* - No change, but only the heading differs.
Continued.
16 16. Contractor's Employees 16. Contractor's Employees 16.1 Contractor's Employees 8.5 Exclusion from 6 Contractor's C
16.2 Engineer at Liberty to the Works of employees
Object persons employed
thereon
17 17. Setting-out 17. Setting-out 17.1 Setting out 7. Levels and setting 9. Setting-out C
out of the Works
and clause 2
(extracts)
18 18. Boreholes and Exploratory 18. Boreholes and Exploratory 18.1 Boreholes and No clause No clause A
Excavation Excavation Exploratory Excavation
D* D*
D* - No change.
IC.15* - 15.1 is a new clause, all others are similar to FIDIC 3.
JC.10* - Differs from FIDIC 3 .
GC.5* - Similar to JCT 8 0 .
Continued.
19 19. Watching and lighting 19. Watching and lighting 19.1 Safety. Security and No Clause 13 Protection of C
Protection of the Works
Environment
14 Nuisance and
19.2 Employer's pollution
Responsibilities
20 20.1 Care of Works 2 0 . 1 . Care of Works 20.1 Care of Works No Clause 54 Emergency C
Work
20.2 Excepted Risks 20.2. Excepted Risks 20.2 Responsibility to Rectify
Loss or Damage
21. 21. Insurance of Works, 21. Insurance of Works, 2 1 . 1 . Insurance of Works 22. Insurance of 8. Insurance C
etc. etc. and Contractor's the Works
Equipment 22A. Erection of
F3.21* IC.21* 21.2. Scope of Cover new buildings
21.3. Responsibility for - Al! Risks
Amounts not Insurance of
Recovered the Works by
21.4. Exclusions the Contractor
22B Erection of
new
buildings
- All Risks
Insurance of
the
Works by the
Employer
22C. Insurance of
existing
structures
- Insurance of
Works or
extensions to
existing
structures
2 2 D . Insurance for
Employer's
ikftftlt*^. loss
of liquidated
* s % damages
I ill
Continued.
22 22.1 Damage to Persons 22.1 Damage to Persons 22.1 Damage to Persons 20 Injury to persons 19 Loss or Damage C
and Property and Property and Property and property and
22.2 Indemnity by 22.2 Indemnity by 22.2 Exceptions indemnity to
Employer Employer 22.3 Indemnity by Employer Employer
23 23.1 Third Party Insurance 23.1 Third Party Insurance 23.1 Third Party Insurance 21 Insurance against 8 Insurance B
23.2 Minimum Amount of 23.2 Minimum Amount of (Including Employer's injury to persons or
Third Party Insurance Third Party insurance Property) property
23.3 Provision to 23.3 Provision to 23.2 Minimum Amount of
Indemnify Employer Indemnify Employer Insurance
23.3 Cross Liabilities
D* F4.23* E* E*
TJ* - No change.
F4.23* - Similar to FIDIC 3 , but this says that the insurance should be in the joint names of the Employer and the Contractor.
E* - Similar to FIDIC 3 .
Continued.
24 24.1 Accident or Injury to 24.1 Accident or Injury to 24.1 Accident or Injury to 21 Insurance against 8 Insurance A
Workmen Workmen Workmen injury to persons
24.2 Insurance against 24.2 Insurance against 24.2 Insurance against or property
Accident, etc., to Accident, etc., to Accident to
Workmen Workmen Workmen
JC.21* GC.8*
D* D*
25 25 Remedy on Contractor's 25 Remedy on Contractor's 25.1 Evidence and Terms of No clause No clause C
Failure to Insure Failure to Insure Insurances
25.2 Adequacy of Insurances
F3.25* IC.25* 25.3 Remedy on Contractor's
Failure to Insure
25.4 Compliance with Policy
Conditions
D* - No change.
JC.21* and GC.8* - Partly covers the FIDIC 3 contents.
F3.25* and IC.25* - Refer clause 2 1 .
Continued.
26 26.1 Giving of Notices and 26.1 Giving of Notices and 26.1 Compliance with Statutes, 6 Statutory 11 Statutory C
Payment of Fees Payment of Fees Regulations, etc. obligations, notices
notices, fees and
26.21 Compliance with Statutes, 26.2") Compliance with Statutes, charges
28 28 Patent Rights and 28 Patent Rights and 28.1 Patent Rights 9 Royalties and 12 Patents C
Royalties Royalties 28.2 Royalties patent rights
29 29 Interference with Traffic 29 Interference with Traffic 29.1 Interference with Traffic No clause No clause B
and Adjoining Properties and Adjoining Properties and Adjoining Properties.
D* F4.29*
30 30.1 Extra ordinary Traffic 30.1 Avoidance of Damage to 30.1 Avoidance of Damage to No clause No clause C
30.2 Special Loads Highway, etc. Roads
30.3 Settlement of Extra 30.2 Transport of 30.2 Transport of Contractor's
ordinary Traffic Claims Constructional Plant Equipment or Temporary
30.4 Water borne Traffic 30.3 Water bome Traffic Works
30.3 Transport of Materials or
Plant
30.4 Water borne Traffic
D* - No change.
F4.29* - No change, but FIDIC4 covers for execution and completion of the works.
Continued.
31 31. Opportunities for Other 31.1 Facilities for Other 31.1 Opportunities for Other 29 Works by 65 Other works A
Contractors Contractors Contractors Employer or
31.2 Delay and Extra work 31.2 Facilities for Other persons employed
Contractors or engaged by
IC.31* Employer
E*
E* E*
32 32. Contractor to keep Site 32.1 Contractor to keep Site 32.1 Contractor to keep Site No clause 34.2 Commencement A
Clear Clear Clear and Completion
D* D*
33 33. Clearance of Site on 33 Clearance of Site on 33.1 Clearance of Site on No clause 34.2 Commencement B
Completion Completion Completion and Completion
• D* F4.33*
D* - No change.
IC.31* - Similar to FIDIC 3, but 31.2 is a new clause from ICE conditions of contract (5th edition).
F4.33* - Little elaborated. Even contractor shall be entitled to retain on site upto the end of the defects liability period.
Continued.
34 34.1 Engagement of labour 34.1 Engagement of Labour 34.1 Engagement of Staff and 19A Fair Wages 15 Returns C
34.2 Supply of Water 34.2 Supply of Water Labour
34.3 Alcoholic Liquor or 34.3 Alcoholic Liquor or
Drugs Drugs
34.4 Arms and Ammunition 34.4 Arms and Ammunition
34.5 Festivals and Religious 34.5 Festivals and Religious
Customs Customs
34.6 Epidemics 34.6 Epidemics
34.7 Disorderly Conduct, 34.7 Disorderly Conduct,
etc. etc.
34.8 Observance by Sub 34.8 Rates
-Contractors 34.8 Observance by Sub
34.9 Other Conditions -Contractors
affecting Labour and 34.9 Other Conditions
Wages affecting Labour and
Wages
36 36.1 Quality of Materials and 36.1 Quality of Materials and 36.1 Quality of Materials, Plant 8 Materials, goods No clause B
Workmanship and Tests Workmanship and Tests and Workmanship and Tests and workman
36.2 Cost of Samples 36.2 Cost of Samples 36.2 Cost of Samples ship to conform
36.3 Cost of Tests 36.3 Cost of Tests 36.3 Cost of Tests to description,
36.4 Cost of Tests not 36.4 Cost of Tests not testing and
Provided for, etc. Provided for inspection
IC.36* 36.5 Engineer's Determination 8.1 Kinds and
where Tests not Provided standards
for 8.2 Vouchers -
materials and
F4.36* goods
8.3 Inspection-tests
8.4 Removal from
the site-work.
materials or
goods
JC.8*
37 37 Inspection of Operations 37 Inspection of Operations 37.1 Inspection of Operations 11 Access for 31.4 Quality C
37.2 Inspection and Testing Architect/ 31.5 -do-
37.3 Dates for Inspection and Supervising 31.6 -do-
Testing Officer to the 31.7 -do-
37.4 Rejection works
37.5 Independent Inspection
38 38.1 Examination of Work 38.1 Examination of Work 38.1 Examination of Work 8.3 Inspection-tests 16 Foundations A
before Covering up before Covering up before Covering up 17 Covering work
38.2 Uncovering and Making 38.2 Uncovering and Making 38.2 Uncovering and Making
Openings Openings Openings JC.8.3* GC. 16/17*
F4.38*
D*
39 39.1 Removal of Improper 39.1 Removal of Improper 39.1 Removal of Improper 8.4 Removal from 53 Non B
Work and Materials Work or Materials Work or Materials or Plant the site-work, -compliance with
39.2 Default of Contractor in 39.2 Default of Contractor in 39.2 Default of Contractor in materials or Instructions
Compliance Compliance. Compliance goods
D* F4.39* GC.53*
-
JC.84 *
SUSPENSION
40 40.1 Suspension of Work 40.1 Suspension of work 40.1 Suspension of Work No clause 40.2g PM's B
40.2 Suspension Lasting more 40.2 Suspension lasting more 40.2 Engineer's Determination Instructions
than 90 days ' than 90 days following Suspension
D* 40.3 Suspension Lasting more GC.40*
than 84 Days
F4.40*
D* - No change-
F4.38* - Similar to FIDIC 3 , but the name Engineer is used throughout.
F4.39* - Similar to FIDIC 3, but the plant and the Contractor's design is also included here.
F4.40* - Similar to FIDIC 3, only the days differ.
JC.8.3* and JC.8.4* - Not clearly covered as FIDIC 3.
GC.53*, GC.40* and GC. 16/17* - Not clearly covered as FIDIC 3.
Continued.
D* D*
42 42.1 Possession of Site 42.1 Possession of Site 42.1 Possession of Site and 23.1 Date of 34.1 Commencement B
42.2 Wayleaves, etc. 42.2 Wayleaves, etc. Access thereto Possession - and Completion
42.2 Failure to Give Progress to
Possession Completion Date GC.34*
D* 42.3 Wayleaves and Facilities
F4.42* JC.23*
43 43 Time for Completion 43 Time for Completion 43.1 Time for Completion
D* D* No clause No clause A
44 44 Extension of Time for 44.1 Extension of Time for 44.1 Extension of Time for 25 Extension of 36 Extensions of C
Completion Completion Completion time time
44.2 Assessment of Extension 44.2 Contractor to Provide
During the Course of Work Notification and Detailed
44.3 Assessment of Due Date Particulars
for Completion 44.3 Interim Determiantion of
Extension
45 45 No Night or Sunday Work 45 No Night or Sunday Work 45.1 Restriction on Working No clause No clause A
Hours
D*
F4.45*
D* - N o change.
F4.45* - Similar to FIDIC3,but (a) The wording Sunday is removed here, and
(b) Engineer's Representative is replaced by Engineer.
Continued.
47 47.1 Liquidated Damages for 47.1 Liquidated Damages for 47.1 Liquidated Damages for 24 Damages for 55 Liquidated A
Delay Delay Delay non-completion Damages
47.2 Reduction of Liquiated 47.2 Reduction of Liquidated 47.2 Reduction of Liquidated
Damages Damages Damages 18.1.4 Liquidated E*
47.3 Bonus for Completion 47.3 Bonus for Completion F4.47» damages -
D* relevant part
E*
48 48.1 Certification of 48.1 Certification of 48.1 Taking-Over Certificate 17.1 Certificate of 37 Early C
Completion of Works Completion of Works 48.2 Taking Over of Sections Practical Possession
48.21 Certification of 48.2] Certification of or Parts Completion
4 8 . 3 \ Completion by Stages 48.3 Completion by Stages 48.3 Substantial Completion of 18.1 Employer's
48.4J 48.4. Parts wish-
48.4 Surfaces Requiring Contractor's
Reinstatement consent
23.3 Possession by
Contractor-use or
occupation by
Employer
D* - No change.
F4.47* - No change, but the bonus clause is omitted here.
Continued.
50 50 Contractor to Search 50 Contractor to Search 50 Contractor to Search 8.3 Inspection - tests 21 Defects in C
17.3 Defects etc. - Maintenance
Architects Periods
/Supervising
Officers instructions
c S «
% £ W
Continued.
54 54 Approval of Materials > 54 Approval of Materials, 54.8 Approval of Materials No clause No clause A
etc., not implied etc., not implied not Implied
D* E*
D* - N o change.
E* - Similar to FIDIC 3 .
Continued.
D* D* E*
56 56 Works to be Measured 56 Works to be Measured 56.1 Works to be Measured 13.6 Contractor's right to 18 Measurement A
be present at
D* D* measurement GC.18*
JC.13.6*
TJ' - No change.
IC.57* - Similar to FIDIC 3 , but the Contractor has to submit a cashflow statement
within 28 days to Engineer for approval of all Lump Sum items .
JC.13.6* - Similar to FIDIC 3 , but not fully covered.
GC.18* - Similar to FIDIC 3 , but not fully covered.
F4.57* - Similar to FIDIC 3 .
Continued
PROVISIONAL SUMS PROVISIONAL SUMS PROVISIONAL SUMS 13.3 Instructions on 64 Provisional Sums
58 58.1 Definition of 58.1 Definition of 58.1 Definition of provisional sums
"Provisional Sums" "Provisional Sums" "Provisional Sums"
58.2 Use of Provisional 58.2 Use of Provisional 58.2 Use of Provisional
Sums Sums Sums
58.3 Production of 58.3 Production of 58.3 Production of
Vouchers, etc. Vouchers, etc. Vouchers, etc.
IC.58* F4.58*
1C.58* - Similar to FIDIC J, but the construction managment services are also included here.
F4.58* - Similar to FIDIC 3 > u t only the wordings differ.
Continued.
60 60.1 Certificates and 60.1 Advance Payment 60.1 Monthly Statements 30 Certificates and Payments 47 Finance Charges C
Payment 60.2 Monthly Statements 60.2 Monthly Payments 48 Advances on Account
60.2 Advances on 60.3 Monthly Payments 60.3 Payment of Retention 49 Final Account
Constructional Plant 60.4 Payment of Retention Money 50 Certifying payments
and Materials Money 60.4 Correction of 51 Recovery of Sums
60.3 Payment in Foreign 60.5 Correction and Certificates 52 Cost Savings
Currencies Withholding of 60.5 Statement at
Certificates Completion
60.6 Final Account 60.6 Final Statement
60.7 Time for Payment 60.7 Discharge
60.8 Currency Account 60.8 Final Certificate
and Rates of Exchange 60.9 Cessation of
60.9 Payments to Employer's Liability
Contractor 60.10 Time for Payment
60.10 Payments to the
Employer
60.11 Advances on
Constructional Plant
and Materials
60.12 Payments in Foreign
Currency
62 62.1 Maintenace Certficate 62.1 Maintenace Certficate 62.1 Defects Liability No clause No clause A
62.2 Cessation of 62.2 Cessation of Certificate
Employer's Liability Employer's Liability 62.2 Unfulfilled
62.3 Unfulfilled Obligations 62.3 Unfulfilled Obligations
Obligations
F4.62*
D*
64 64 Urgent Repairs 64 Urgent Repairs 64.1 Urgent Remedial 33 War damage 54 Emergency Work A
D* Work
F4.64* JC.33* GC.54*
65 65.1 No Liability for War, 65.1 No liability for War, 65.1 No Liability for 32 Outbreak of hostilities No clause
etc., Risks etc.. Risks Special Risks
65.2 Damage to Works, 65.2 Damage to Works, 65.2 Special Risks
etc., by Special Risks etc., by Special Risks 65.3 Damage to Works by
65.3 Projectile, Missile, 65.3 Projectile, Missile, Special Risks
etc. etc. 65.4 Projectile, Missile,
65.4 Increased Costs 65.4 Increased Costs etc.
arising from Special arising from Special 65.5 Increased Costs
Risks Risks arising from Special
65.5 Special Risks 65.5 Special Risks Risks
65.6 Outbreak of War 65.6 Outbreak of War 65.6 Outbreak of War
65.7 Removal of Plant on 65.7 Removal of Plant on 65.7 Removal of
Termination Termination Contractor's
65.8 Payment if Contract 65.8 Payment if Contract Equipment on
Terminated Terminated Termination
65.8 Payment if Contract
IC.65* Terminated
F4.65* St-32*
IC.65* - Special Risks include whether riot is directed against the State, persons or property.
F4.65*- Special risks exclude loss or damage due to (a) the use or occupation by the Employer of any section and (b) the Engineer's design of the works.
IC.32* - Partly covers FIDIC 3 contents.
Continued.
66 66 Payment in Event of 66 Payment in Event of 66.1 Payment in Event of 32 Outbreak of Hostilities No clause A
Frustration Frustration Release from
D* Performance JC.32*
F4.66*
68 68.1 Service of Notices on 68.1 Service of Notices on 68.1 Notice to Contractor N o clause 1.3 Definitions etc.
Contractor Contractor 68.2 Notice to Employer
68.2 Service' of Notices on 68.2 Service of Notices and Engineer
Employer or Engineer on Employer or 68.3 Change of Address
68.3 Change of Address Engineer
68.3 Change of Address F4.68* GC.l*
69 69.1 Default of Employer 69.1 Default of Employer 69.1 Default of Employer 28 Determination by No clause
69.2 - do- 69.2 - do - 69.2 Removal of Contractor
69.2 - do- 69.2 - do- Contractor's
Equipment
69.3 Payment on
Termination
69.4 Contractor's
Entitlement to
Suspend work
69.5 Resumption of Work
M . 6 8 * - No change, but in addition the cable, telex or lacsimile transmission is included here.
G C . l * - Partly covers FIDIC 3 contents.
Continued.
F4.71*
IC.71*
F4.72*
rrf\
iocs / Oi \&'A
!*. - &\ t \
! 8
A i|
^ Is
I C 7 1 * , I C 7 2 * , F4.71* and F4.72* - Number of days are changed from 30 to 28.