Introduction:
This Blog gives an in sight on how quantity confirmation are carried out during results recording with 03
inspection type.
Requirement:
During manufacturing of product there are certain inprocess operations which will be cleared by
production department sequentially and some particular operation which needs to be inspected by
quality department. Based on the inspection results quantity needs to be confirmed and notification to be
triggered for the defects to production dept. During results recording quality department require to view
the confirmation screen to record the yield, scrap and rework quantity. Based on the confirmations
entered by quality department further activity will be carried out by the production department for the
subsequent operations.
0030 is Quality operation where quality department will inspect and enter the results, yield, scrap and
rework
Production Order 60004172 created and released. System generated in process inspection lot
30000002532
Operations 0010 and 0020 operations are con med by production dept.
Step 5: Results Recording (From QA32 or QE01) and Trigger Noti cation for defects
Quality dept enters the results in QE01 against the lot and operation number. Results are entered as
given below. One characterisctic is rejected as results are not within the specification. Now this defect
information needs to be communicated to production dept through notification. As shown below click on
create defect.
System will pop up the Defect overview sreen as shown below. Enter the code group and code, enter
the defect quantity. Then click on continue system will trigger notification in backend on save of the
results. F3 notification type is used.
For con rming the quantity Go to Menu – Edit – Con rm Activities as displayed below.
System will pop up the confirmation screen as displayed below. Since there is defect all the 20 qty is
send for rework.
On SAVE of the results below notification 565 is created for defect quantity with reference to the
inspection lot number and order number. Further notification is processed by production dept and finally
re-offered for quality inspection.
Re-Inspection by Quality Dept: Quality dept does results recording and updates the new results as
given below.
Since 20 qty is under rework now quality team needs to move the same from rework to yield. As results
are now as per specifications, quality team needs to cancel the rework in CO13 and again confirm the
Yield in QE01.
Cancel order con rmation (CO13): Enter the order number and operation number and click on SAVE
as displayed below. Rework qty will be reversed.
Go to QE11 – Enter the inspection lot. From Menu bar -Go to Edit – Confirm Activities. Below screen will
be displayed. Enter the yield quantity and SAVE. Now rework qty of 20 is cleared as Yield 20 qty.
Production Confirms the final operation 0040 and Auto GR is completed. Stock updated in MMBE as
displayed below.
Alert Moderator
8 Comments
swathi rege
Really helpfull..Is there any other way we can avoid cancelling the rework quantity and automate the process?
Hi Swathi,
If we use Inspection Points in CA02 Header and maintain for the respective operation under operation overview –
Quality Management for Inspection Points – Insp.point completion as “Quantity,valuation and
confirmation(production) then after results recording on SAVE system will pop to enter yield/rework/scrap as
required and accordingly valuation like Reject/Accept can be entered. Based on rejection/acceptance rework qty
changes can be done in this tcode itself at Menu- Goto – Data for Insp point. No need to go to CO13.
If you use inspection points system will not allow to do reversal using CO13 once qty is confirmed or rejected in
Quality.
Ramagiri
swathi rege
Thx Ramagiri
GS
good stuff!! any idea how I could integrate time event CO19 transaction with results recording instead of integrating CO11N
transaction.
Hi GS,
Thanks for your comments. As of now no idea. Will try to find out and update you.
Ramagiri
VN
Hi Ramagiri,
Thanks for this content. I have also little bit same requirement.
If I reject a inprocess material after confirming a operation and enter results then how can I restrict not to confirm for further
operations and also I want to know that we enter defects after confirming from a operations.
Thanks
Sarfaraz Ahmed
Hi,
Nice blog.
S Ahmed
Sarang Phansalkar
Hello,
Nice blog, thanks for sharing. I observed one issue in in-process inspection & confirmation. If we don’t assign MIC’s in
routing/master recipe, then system not restricting user to confirm operation even if inspection lot exists. Is there any way to
restrict confirmation even if MIC’s not assigned.
Regards
Sarang Phansalkar