PRESUPUESTO DE CIMETACION PARA MAQUINARIA

OBRA CIMENTACION PARA MAQUINARIA


DIRECCION AV. ALEXANDER FLEMING N°…..
PARTIDA ESTRUCTURAS
FECHA 02 DE FEBRERO DEL 2018

Item Descripción Und.

1.00 OBRAS PRELIMINARES Y PROVISIONALES


1.1 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPOS glb
1.2 OFICINA Y ALMACEN DE OBRA und.
1.4 CERCO PERIMETRICO CON MALLA ml
1.50 DEMOLICION DE PISO EXISTENTE INC. ELIMINACION glb
1.00 MOVIMIENTO DE TIERRAS
1.10 EXCAVACION DE CIMIENTOS MANUAL m3
1.30 NIVELACIÓN Y COMPACTACIÓN DEL TERRENO NATURAL MEJORADO 5 CM m2
1.60 ELIMINACIÓN DE MATERIAL EXCEDENTE m3
2.00 OBRAS DE CONCRETO SIMPLE
2.10 SOLADO DE CONCRETO 5 CM m2
3.00 OBRAS DE CONCRETO ARMADO
3.10 ZAPATAS
3.1.1 CONCRETO PARA ZAPATAS f'c=245 kg/cm2 - mano de obra m3
3.1.2 ENCOFRADO Y DESENCOFRADO PARA CISTERNAS m2
3.1.3 ACERO DE REFUERZO mano de obra kg
3.20 POZA
3.2.1 CONCRETO PARA POZA f'c=245 kg/cm2 - mano de obra m3
3.2.2 ENCOFRADO Y DESENCOFRADO PARA CISTERNAS m2
3.2.3 ACERO DE REFUERZO mano de obra kg
4.00 ARQUITECTURA
4.10 SOLAQUEO DE POZA m2

5.00 OTROS
5.10 INSTALACION DE TUBERIAS PVC glb

Notas
No incluye seguros ni SCTR
No incluye instalcionde redes IISS ni IIEE.
El agua y la energia electrica debe ser suministrada por el cliente.
Adelanto: 50%

PLAZO: 15 DIAS calendario


ION PARA MAQUINARIA

METRADO P.U. SUB-TOTAL TOTAL


S/. 1,210.00
1.00 S/. 300.00 S/. 300.00
1.00 S/. 200.00 S/. 200.00
21.00 S/. 10.00 S/. 210.00
1.00 S/. 500.00 S/. 500.00
S/. 1,934.85
16.82 S/. 45.00 S/. 757.08
13.10 S/. 9.00 S/. 117.86
23.55 S/. 45.00 S/. 1,059.92
S/. 327.38
13.10 S/. 25.00 S/. 327.38
S/. 2,960.70
S/. 1,823.80
15.00 S/. 45.00 S/. 675.00
17.15 S/. 25.00 S/. 428.80
400.00 S/. 1.80 S/. 720.00
S/. 1,136.90
5.81 S/. 60.00 S/. 348.55
13.53 S/. 25.00 S/. 338.34
250.00 S/. 1.80 S/. 450.00
S/. 476.47
16.43 S/. 29.00 S/. 476.47

S/. 90.60
1.00 S/. 90.60 S/. 90.60

COSTO DIRECTO S/. 7,000.00


DIREC. TECNICA 0% S/. -
GG y UTIL 0% 0% S/. -
SUB TOTAL S/. 7,000.00
IGV S/. 1,260.00
TOTAL S/. 8,260.00
2000
360

deben 2360

pagaron 500

deben 1860

desc1 120
detrac 94.4

saldo a pagar 1645.6


PRESUPUESTO CONTRATADO
PPTO. CONTRATADO (SIN IGV) S/. 7,000.00
PPTO. CONTRATADO (CON IGV) S/. 8,260.00
MONTOS PAGADOS
1ER PAGO S/. 2,900.00

2DO PAGO S/. 2,000.00


PRESTAMO S/. 600.00

PAGOS REALIZADOS AL 26.02.18 S/. 5,500.00


INC. IGV

LIQUIDACION FINAL S/. 2,760.00


FACTURAS YA ENTREGADAS MONTO SE PAGO
1ERA FACT S/. 2,900.00 S/. 2,900.00
2DA FACTURA S/. 3,000.00 S/. 2,000.00

A LA FECHA SE ME DEBIO HABER S/. 5,900.00 S/. 4,900.00 SOLO SE ME CANCELO


CANCELADO
S/. 1,000.00 SE ME ESTA DEBIENDO DE LA
SEGUNDA FACTURA ENTREGADA

OJO: DADO QUE YATE ENTREGE DOS FACTURAS POR EL MONTO TOTAL DE 5,900.
TE DEBO ENTREGAR UNA ULTIMA FACTURA POR EL MONTO DE S/. 2,360.00
EBIENDO DE LA
TURA ENTREGADA