I. PEKERJAAN PERSIAPAN II. PEKERJAAN CENTRE PLAZA III. PEKERJAAN BANGKU CENTRE PLAZA
MULAI
Start: Fri 22/06/18 ID: 2 Start: Fri 22/06/18 ID: 3 Start: Fri 06/07/18 ID: 4
Milestone Date: Fri 22/06/18 Finish: Wed 19/09/18Dur: 90 days Finish: Thu 19/07/18Dur: 28 days Finish: Thu 26/07/18Dur: 21 days
ID: 1 Res: Res: Res:
V. PEKERJAAN CHILDREN PLAY GROUND AREA VI. PEKERJAAN BANGKU CHILDREN PLAY GROUND AREA (2 UNIT)
Start: Fri 20/07/18 ID: 6 Start: Fri 10/08/18 ID: 7
Finish: Thu 23/08/18Dur: 35 days Finish: Thu 23/08/18Dur: 14 days
Res: Res:
CV. PROSPERA PRIMADHIA Noncritical Critical Summary Inserted Critical External Highlighted Critical
SELESAI
CV. PROSPERA PRIMADHIA Noncritical Critical Summary Inserted Critical External Highlighted Critical