Académique Documents
Professionnel Documents
Culture Documents
(Received 30th November 1998, revised version received 3rd March 1999)
1. INTRODUCTION
The 306m span maintenance hangar in Beijing Capital
Airport is divided into two parts, 153m long each, with one
column in the middle to main door only (Fig.1). The hangar
can accommodate four B747-400 airplanes for being
serviced at the same time. It is believed to be the longest
span hangar in China and one of the largest hangars in the
world. Roof structure was completed in September 1995.
All the dimensions and deflection of the 306m-span steel
space truss and the 306m 3 90m space grid satisfy all the
requirements of design. No loss of stability or failure were
found in 16800 tubes 200,000 high strength bolts and over
4000 ball joints, and no warping and sliding found in the
members of space truss. 100% of ultrasonic testing results Figure 2. General view of hangar roof
complied with the standard for connecting welding seams Design of the roof structure is critical due to its long-
between ball joints and tube members. The general view of span, and the design must fully satisfy requirements as
the hangar roof during construction is shown in Fig.2. follows:
4.- Under different kinds of load, especially when The space truss is composed of truss WJ1, WJ2 and
door is opened, deformation of space grid, connected by CWJ1-4 (Fig.5). Considering the
caused by wind suction, should be consistent limitation of height over the airport, the height of WJ1
with the requirements prescribed. is 15m and the height of WJ2 is 6m. Calculation
5.- -Structure should be safe and reliable under the shows that force distribution in the space truss is
action of horizontal and vertical earthquake, reasonable and integral stability is available. WJ1 and
because the hangar is located in the seismic WJ2 are parallel-chord trusses and the spacing of
region of intensity 8. joints is 6m. H-sections, welded from high-tensile
6.- Force distribution should be reasonable for space steel plates are used for all members of the space truss.
grid members and nodes and members should be According to different bearing conditions, sections
easy for processing as well as convenient for widths are selected as 800mm, 500mm, 300mm
transportation. respectively.
7.- Construction cycle and safety should be carefully
considered in the roof lifting scheme.
With reference to above requirements and after
comparing several alternatives, a tripe-layer
pyramidal space grid together with a bolted and
welded long-span space truss was finally selected as
the structural system for the hangar roof.
3. DETAI LS
3.1 Connection detail for space truss
Friction-type high strength bolts of large diameter are
used for the connection of WJ1, WJ2 and middle truss
Figure 4. Section of hangar structure
WJ3 (Fig. 6). Diameter of bolt is 30mm (grade 10.9)