Vous êtes sur la page 1sur 5

Design and Construction of

306m Span Hangar Roof at


Capital Airport
Liu Shutun

China Design Master, China Aeronautical Project & Design Institute.

(Received 30th November 1998, revised version received 3rd March 1999)

SUMMARY:- The 306m-span hangar of Capital Airport is one of the largest


hangars in the world, with a span of (153 + 153)m. This roof structure includes
tripe-layer pyramidal space grid together with bolted and welded long-span
steel space truss. This article describes the type of roof structure, design of
joints, quality standard and a safe method for welding and lifting the roof of
the hangar.

1. INTRODUCTION
The 306m span maintenance hangar in Beijing Capital
Airport is divided into two parts, 153m long each, with one
column in the middle to main door only (Fig.1). The hangar
can accommodate four B747-400 airplanes for being
serviced at the same time. It is believed to be the longest
span hangar in China and one of the largest hangars in the
world. Roof structure was completed in September 1995.
All the dimensions and deflection of the 306m-span steel
space truss and the 306m 3 90m space grid satisfy all the
requirements of design. No loss of stability or failure were
found in 16800 tubes 200,000 high strength bolts and over
4000 ball joints, and no warping and sliding found in the
members of space truss. 100% of ultrasonic testing results Figure 2. General view of hangar roof
complied with the standard for connecting welding seams Design of the roof structure is critical due to its long-
between ball joints and tube members. The general view of span, and the design must fully satisfy requirements as
the hangar roof during construction is shown in Fig.2. follows:

1.- Height of hangar roof should not exceed 40m


because of the height limitation over the airport.

2.- Layout and dimensions of the roof structure


should satisfy the technological requirements.

3.- Deformation of roof structure should not


influence the operation of hanging cranes and
Figure 1. Hangar Plan main door.

International Journal of Space Structures Vol. 14 No. 3 1999 185


Design and Construction of 306m Span Hangar Roof at Capital Airport

4.- Under different kinds of load, especially when The space truss is composed of truss WJ1, WJ2 and
door is opened, deformation of space grid, connected by CWJ1-4 (Fig.5). Considering the
caused by wind suction, should be consistent limitation of height over the airport, the height of WJ1
with the requirements prescribed. is 15m and the height of WJ2 is 6m. Calculation
5.- -Structure should be safe and reliable under the shows that force distribution in the space truss is
action of horizontal and vertical earthquake, reasonable and integral stability is available. WJ1 and
because the hangar is located in the seismic WJ2 are parallel-chord trusses and the spacing of
region of intensity 8. joints is 6m. H-sections, welded from high-tensile
6.- Force distribution should be reasonable for space steel plates are used for all members of the space truss.
grid members and nodes and members should be According to different bearing conditions, sections
easy for processing as well as convenient for widths are selected as 800mm, 500mm, 300mm
transportation. respectively.
7.- Construction cycle and safety should be carefully
considered in the roof lifting scheme.
With reference to above requirements and after
comparing several alternatives, a tripe-layer
pyramidal space grid together with a bolted and
welded long-span space truss was finally selected as
the structural system for the hangar roof.

2. ROOF STRUCTURE DESIGN


Selection of edge beam for space grid over the main door
of hangar is a difficult problem. As the upper support of the Figure 5. Edge beam of space grid
main door, it should satisfy the operational requirements of Triple-layer space grid is selected as the roof
the door. Moreover, as the elastic support of the space grid, structure, because of the long span rigidity of the
it should have sufficient stiffness to ensure rational force double-layer space grid is too small and its
distribution of forces in the entire space grid. Steel deformation cannot satisfy the requirements.
consumption of main door’s edge beam accounts for 40% Compared with double layer space grid, the height of
of the total and so the selection of its structural scheme triple-layer space grid can be reduced by 0.8m,
becomes a crucial problem. After comparing several internal force by 27%, deflection by 15%, and steel
design schemes, such as diagonal cable, arch, prestressed consumption by 27%. Diagonal space grid is used in
steel structure, etc., a two-span box-shaped space truss was this project because its force distribution is more
adopted as the edge beam. Figs. 3 and 4 show the plan and uniform than that of the orthogonal space grid.
section of the space grid respectively. Internal forces can be reduced by 40%, and deflection
can be reduced by 45%. All circular tube members are
connected to welded spherical nodes. The height of
the space grid is 6m, the grid of top and bottom chord
is 4.22 3 4.22m, the grid of mid chord is 6.0m 3
6.0m. Imported STK490B grade seamless steel tubes
are used for the members, their section ranges from
102 3 5 to 273 3 16 (diameter 3 thickness, mm). The
size of spherical nodes ranges from 500 3 6 to 800 3
Fig 3. Plan of space grid 22.

3. DETAI LS
3.1 Connection detail for space truss
Friction-type high strength bolts of large diameter are
used for the connection of WJ1, WJ2 and middle truss
Figure 4. Section of hangar structure
WJ3 (Fig. 6). Diameter of bolt is 30mm (grade 10.9)

186 International Journal of Space Structures Vol. 14 No. 3 1999


Liu Shutun

with designed pretension of 255kN. Splice is 3.2 Ball bearing support


composed of connecting plate, inside splice plate, Reaction force on the middle column of space truss is as
outside splice plate and web splice plate. Total area of high as 35000kN. Reaction force on side columns is
the splice plate should be larger than that of the master 7000kN. Special steel bearing support is selected in
plate. Bearing capacity of high strength bolt should be order to ensure that such large forces are safely
higher than ultimate bearing capacity of the original transmitted from roof structure to top of the column.
material, i.e. it should not fail first during strong The ball bearing support is composed of the top cover,
earthquakes. External dimension of detail for H- the bearing block and the bottom cover. The bottom
section member should be controlled strictly to ensure cover is contacted with the bearing block by spherical
that steel plates are placed tightly and to have surface. Teflon pad is placed between the bearing block
sufficient bearing capacity of the fiction surface, and top cover as well as the bottom cover (Fig. 8). The
because the number of layer of plate of plate on the friction coefficient between Teflon pad and steel will be
splice point reaches 5 to 7 and are as thick as the steel reduced when load is applied. Load can be transmitted
plates. In order to avoid delayed failure, torsion by spherical surface and the ball bearing support can
moment should be controlled strictly and should not extend and contract freely as well as rotated easily.
be greater than a certain amount. Standard deviation of
torsion moment coefficient should not exceed the
criteria. Petal-shaped connection is used as the
connection of CWJ1-4 and WJ1, WJ2. CWJ1-4 has
oblique H-section members in three-dimensional
space. It is connected outside the joint in order to
ensure the assembly is in the right position, i.e. during
manufacturing in the factory, steel corbel that connects
WJ1 and WJ2 are welded directly to the splice plate.
Space corbels in 6 different directions are welded on
the large gusset plate like a petal (Fig. 7). Special jig
is used during manufacturing in order to ensure the
correct space angle of the corbel.

Figure 8. Ball bearing support

Figure 6. Connection detail for space truss

Figure 9. Hinged support on columns

3.3 Hinged support on peripheral columns


As shown in Fig. 9, the supporting ball joints of space
frame rest through a steel ring on top of a short steel
post. Contact surface between the steel post and steel
Figure 7. Petal shaped detail ring is also a spherical surface to ensure uniform

International Journal of Space Structures Vol. 14 No. 3 1999 187


Design and Construction of 306m Span Hangar Roof at Capital Airport

transmission and free rotation. Short steel post is


strengthened by four stiffening plates. Space frame’s
ball joint is connected with the supporting concrete
column through vertical steel plates to resist the
upward wind suction and vertical seismic force.

4. CONSTRUCTION OF THE HANGAR


ROOF
The roof structure was assembled on the ground and
then lifted up by using groups of hydraulic jacks. To
suit the equipment available, the roof was divided into
7 units, i.e. the space truss in 2 units, the middle truss
Figure 12. Construction view of space truss
and space grid in 4 units (Fig. 10).

4.2 Middle truss lifting


The weight of middle truss WJ3 is about 410t. It is
lifted on two groups of lifting supports. Two jacks are
placed on the cross beam each carrying 200t. After the
main space truss and middle truss are lifted to the
designed level, these three units are connected to the
Figure 10. Lifting plan for hangar roof
middle columns and side columns to form a stable
4.1 Space truss structure.
The 306m-long steel space truss is divided in two units,
each 132m in length, and composed of WJ1, WJ2 and
4.3 Assembly and lifting of the space grid
CWJ1-4. The weight of lifting unit is 1137t, using 3 groups
The space grid is composed of steel tubes connected
of shear-leg lifting support, with two lifting cross beams
by hollow spherical nodes. The steel tube for members
located on the support. 10 jacks are placed on cross beam
is of the STK490 grade fabricated in Japan. The
near WJ1, and 6 jacks are placed on cross beam near WJ2.
standard tensile strength and yield strength of the steel
A total of 48 jacks with 48t capacity each are located on 3
are 540N/mm2 and 400N/mm2 respectively.
groups of supports. The double action hydraulic jacks are
For the welding of the space grid, high quality
established on the cross beam on top of the support (Fig.
standards and strict quality control are required.
11). The lifting speed and loading on each jack are
Detailed regulations were drafted by the construction
controlled by a computer. In this way, relative difference of
group to insure welding quality, which includes
elevations between each lifting point can be controlled
examination of the welder, selection of welding rod,
within an allowable range, and thus safety and reliability of
determination of electric current on different working
lifting unit can be ensured during lifting. Two units of the
positions and preheating of the welded metals. Care
space truss are lifted up one after another to their final
has been taken to remove the welding stresses. Ultra-
position. The construction view is shown in Fig. 12.
sonic testing is carried out for all welding seams.
Since the space grid is in triple layers, it is
constructed from sub-assembly units as shown in Fig.
13. For lifting, the space grid is divided into 4 bocks,
72m x 78m each. 12 temporary masts with 24
hydraulic jacks of 40t capacity are erected for each
unit, thus forming 48 lift points (Fig. 14). The jack
will climb up along a steel rope together with the
space grid. Difference in elevation of lifting point is
also controlled by computer which will satisfy the
requirements of the design. Fig. 15 shows the space
grid in the process of lifting.
Figure 11. Space truss lifting scheme

188 International Journal of Space Structures Vol. 14 No. 3 1999


Liu Shutun

Figure 13. sub-assembly unit of space grid

Figure 15. Construction view of space grid

By employing lifting technology in construction,


Figue 14. Space grid lifting scheme
about 87% of members are assembled on the ground.
This will create a favourable condition for fabrication
Practice shows that lifting the hangar roof by using
and the quality of welding can be guaranteed.
hydraulic jacks is an advanced technology. Each
According to design, cambering of roof is required in
lifting point should be selected so that the force
two directions, so the grid is divided into 26 units with
distribution of the members in the space grid will not
different heights during assembly on the ground, using
exceed the one specified in the design, especially
a standard dimension pyramid template for each unit.
when tension in a member changes into compression,
Thus, the co-ordinates of the centre of each node can
it must be ensured that member does not fail by
set accurately.
becoming unstable. Lifting equipment is safe due to
The experience grained in the construction of this
uniform loading on each support and stability is
hangar roof shows that it is more economical and safer
ensured by using guyed ropes around the masts. Force
to lift the roof structure in 7 units successively than
distribution in the lifting support is checked during the
assembling the whole structure in one piece at a height.
process of lifting.

International Journal of Space Structures Vol. 14 No. 3 1999 189

Vous aimerez peut-être aussi