RECENT MDOT PROJECTS/ACTIVITIES ASSOCIATED WITH THE BLUE WATER
BRIDGE CORRIDOR AND PLAZA EXPANSION
(mitigation items shaded in green) Activity Approximate Cost Agency Expected Completion Environmental clearance study for the BWB corridor $13,900,000 MDOT Done in 2009
ROW acquisition for BWB
corridor $40,900,000 MDOT Suspended in 2009
City of Port Huron and
Economic Re-development Plan surrounding St. Clair for Port Huron area $224,000 County Done in 2010
Construction of I-94/I-69 Freeway
and Black River bridge replacement $91,965,000 MDOT Done in 2012
Construction of Pine Grove
Connector $348,000 MDOT Done in 2012
Fund a local visitors center
(tourism kiosks pilot project) $50,000 Chamber of Commerce Done in 2015
Construction of local wayfinding
sign program $100,000 City of Port Huron Done in 2013
Develop land use/zoning/master
plan update $50,000 City of Port Huron active with city
Increased emergency services Port Huron Township and
payment $103,100 City of Port Huron extra $103,100/yr for 10 years
Signal sychronization study on
Pine Grove (M-25) $125,000 MDOT TBD
Reconstruction of the I-94/I-69
interchange and bridges $76,152,000 MDOT Done in 2015
Construction of new Welcome
Center on westbound I-94/I-69 $5,500,000 MDOT Done in 2015
Fund Economic Development
Services each year (to date) $800,000 City of Port Huron $100k per year thru 2020