Oil Pipeline 42” by 450km.

25th June David H Moloney

Photographic Record of Construction


Baku - Tbilisi - Ceyhan (BTC) Oil Pipeline

The Azerbaijan Section of the Project’s Oil Pipeline including valve and
pig trap stations, laying of Fiber Optic cable and tie-ins at pumping
stations. Much of the terrain is flat and semi-arid.

The Pipeline links the Caspian sea oil wells with the Mediterranean Sea
ship tankers port.

The capacity is1 million barrels of crude oil flow per day
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Contents
Overview
Surveying & Setting Out
Clearing & Grading
Double Jointing i.e. welding 2 pipes together
Stringing out Pipes
Bend Pipes for changes in direction sideways and up & down
Welding Pipes into a string, Test Weld by X Ray.
Anti-corrosion Coat to Joints
Trenching i.e. excavate trench
Lowering pipe string into trench
Backfilling Trench
Reinstatement of Pipeline ROW (Right-of-Way)
Reinstatement of River Banks
Crossing - Horizontal Directional Drilling
Crossing - Thrust Boring
Crossing - River Pause Slides to Read
Hydrotest & Pigging
Tie-in i.e. connect to existing pipeline
Miscellaneous
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Overview Construction Sequence

A typical sequence of activities is- surveying and setting out, preparing the land, stringing out the pipes along the
route, excavating the trench, welding and laying the pipes, backfilling the trench with the excavated soil, and
reinstating the land to its original condition.
.

Crossing Railway, Roads, Rivers, etc.


Pump Station
Overview Pipeline Construction Animation

To see animations, view YouTube film.


Overview Pipeline Crossings Construction Animation
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Surveying & Setting Out


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Surveying & Setting Out


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Surveying & Setting Out

FCI-ROW Set Out


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Clearing & Grading ROW (Right of Way)


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Clearing & Grading

Concrete Slabs Installed For


Foreign Service Detection Foreign Services Protection
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Clearing & Grading


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Clearing & Grading


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Double Jointing Facility

Welding 2 nr 12m long pipes


together prior to stringing out.
Located at Pipe Storage areas.
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Double Jointing Facility


Outline Process

1. Single piles 12m long are delivered and stacked.


2. At the Bevelling Station. The ends of the pipes are
bevelled. Two pipes are aligned using an internal
clamp, the joint is preheated and the root pass
weld is done.
3. At the Hot Pass Station. The fill and cap passes
will be carried out using Submerged Arc Welding
(SAW)
4. The joints will be x-rayed
5. The double pipes 24m long are stored ready for
transportation to the site
6. Purpose made dollies will transport the pipes
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Double Jointing i.e. welding two pipes together

6
Phase 7: Rolling Pipe
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Stringing out Pipes


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Stringing out Pipes


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Stringing out Pipes

Final Product
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Bending Pipes
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Bending Pipes

Pipe Will Be Lifted Using Choker Choker Belts Placed On


Toolbox Talk Belts Pipe

The Bending Machine Uses A


Preparation For Lifting Series Of Clamps And Hydraulic
Loading Pipe On Bending Pressure To Make A Very
Pipe Machine Smooth, Controlled Bend Bending Start
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Bending Pipes

Bending

Completed Bends

Maximum Bend angle Is 1.3


Clamps Pulled Through The Pipe Degrees Per Meter
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Welding
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Welding

Fit-Up
Beveling
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Welding
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

X Ray Pipeline Crawler for testing joint welds


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Joint Field Coating for Anti-corrosion


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Joint Field Coating

Preparation For Grit Blasting


1. Toolbox Talk Wearing Special Coverall
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Joint Field Coating


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Trenching i.e. excavate trench.


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Trenching
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Lowering Pipe string into Trench


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Lowering Pipe string into Trench

Lifting Belts Supported by Side-Booms Will Be


Utilized For Pipe Handling And Not Placed Over Any
Field Joint Area
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Lowering Pipe string into Trench


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Backfilling
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Backfilling
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Backfilling
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement ROW Right-of-Way


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement ROW

Spreading Topsoil
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement ROW
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement ROW

Final Product
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement River Bank


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement River Bank

Matting
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement River Bank

Grass Is Growing On River Banks Final Product


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Horizontal Directional Drilling


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Horizontal Directional Drilling

Rig Anchoring System; During The


Drilling Works, The Rig Will HaveTo
Be Secured To Stop It From Moving
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Horizontal Directional Drilling


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Horizontal Directional Drilling


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Thrust Boring


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Thrust Boring


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Thrust Boring


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing - River Crossing


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing - River Crossing

Sediment Control
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing - River Crossing

Lowering In
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Hydrotest, Pigging (clean out pipeline) & Dry Pipeline


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Hydrotest

Trains Of Brush Pigs With Slugs Of Flushing


Water Are Used For Cleaning The Pipeline Pigs Are Loaded Into Temporary Pig Launchers
Block Valve Pre-Testing
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Hydrotest

The Final Pig Is Fitted With An Aluminium


Pigs Are Received Into Temporary Pig Gauging Plate 95 % Of The Internal Diameter To
Pigs Are Launched With Compressed Air Receiver Check For Geometrical Defects

Water Used For Hydrostatic Testing Is Water Is Then Passed Through Vented
Pigs Are Back Loaded Into Test Headers Break Tanks And Flow Meters
For Filling And Dewatering Test Test Headers Are Then Welded To The Filtered To 50 Microns
Sections Ends Of Test Section
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Hydrotest

Filling Spread Showing Fill Pumps, Pressurising Pumps And Instrument Control
Chemical Dump And Break Tanks Container

The Dewatered Section Is Then Dried


To -10degC Dewpoing Using
Compressed Air Passed Through
Drying Units

After Hydrotest The Test Section Is


Pressurising injection Manifold Incorporating Dewatered And Water Transferred Into The
High Pressure Flow Meter Next Section
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Tie-in i.e. connecting to existing pipeline

Welded Joint on the Azerbaijan and Georgia Border


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Tie-in
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Tie-in

Tie-In: Manually Welding Joints In


Preparation For Tie-In Trench Between Two Sections

Tie-In Final Product


Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Miscellaneous
Contents

Time Chainage Diagram


Pipe Spool Fabrication
Tank Construction
Piperack
Crane Heavy Lift
Slug Catcher
Road construction
Reinforced Concrete Wall
Crossing under Existing Utilities
Trench Excavation
Load & Haul
Rock excavation
Quarry & aggregate Production
Concrete Batching Plant
Temporary Sheet Pile shaft
Cable Laying
Fencing
Buildings
Time Chainage Diagram The chart has two axis: one for time and the other for location
A legend explains meaning of the colours, symbols and line types

Sample Only
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Histograms for Resources & Outputs


Dashboard is a single page, graphical representation of current
Progress Monitoring & Reporting - Dashboard progress and historical trends
Dashboard is a single page, graphical representation of
HSE Monitoring & Reporting - Dashboard current HSE Issues and historical trends
Plant & Equipment List & Worker’s Job Titles

ⓒ David H Moloney
Temporary Contractors Site Facilities

Brief Description

Site Offices, Camp Accommodation for


1,250 workers, Canteen, Recreation,
Fabrication shops, Stores, Plant Yard. In five
locations along the route.

ⓒ David H Moloney
Temporary Contractors Site Facilities - Stores

Brief Description
Pipes Delivery ⓒ David H Moloney

Brief Description

Pipes were manufactured in Japan, coated


with a plastic covering in Malaysia, and
shipped to the Georgian ports of Poti.
Transported by Train and trucks across land.
Georgia

Train
Japan
Pipe Spool Fabrication Animation
Pipe Spool Fabrication Steps
Pipework

NDT
Cut Non Destructive
Testing

Bevel PWHT
Post Weld Heat
Treatment

Fit-up Blasting

Weld Painting
Tank Construction
Piperack Construction Animation

The Pipe Racks carry pipes and cables


between the different processes..
Cranes Heavy Lift Animation

Lift column from the horizontal and


rotate into the vertical
Slug Catcher Construction Sequence Animation

Separates the Gas from the Oil & Water


Also to dissipate any pressure surges
Road Construction Sequence Animation
Reinforced Concrete Wall Construction Sequence Animation
Existing Underground Utilities
Earthworks

Brief Description

Before digging
establish the location
and route of
underground utilities.

Locator to find Utilities


Spray Paint to mark pavement ⓒ David H Moloney
Crossing Under Buried Utilities & Overhead Power Cables Animation
General Items Wheel Wash Drive-through
General Items Weighbridge & Sheeting Access

ⓒ David H Moloney
General Items Dust Suppression

ⓒ David H Moloney
Organogram

Brief Description

Shown are the line and


lateral relationships
between the various team
members and their relative
position in the site
organisation.
Trench Excavation with Stepped Faces
Trench Excavation with Battered Faces
Excavate & Load, Cart, Tip & Return
Earthworks

Brief Description 7 minutes

Cycle Time for 7km haulage distance


using an Excavator 45 tonne weight
and Dumper with a 40 tonne capacity,
the cycle time is 34 minutes

7 km

14 minutes 7 km 14 minutes

3 minutes
Rock - Excavability
Earthworks

Brief Description

The excavability of rock depends


mainly on the rock strength and the
layer thickness. This diagram shows
excavation methods for rock of
various strengths and thicknesses,
with a free face.

ⓒ David H Moloney
Quarry & Aggregate Production
Concrete

ⓒ David H Moloney
Concrete Batching Plant David H Moloney
Concrete

Brief Description
.
The mixing is computer controlled
and has a dynamic screen display,
showing the process. The material
storage capacity is, to match two
days concrete production.

ⓒ David H Moloney
Concrete Batching Plant
Concrete

ⓒ David H Moloney
Temporary Sheet-pile Shaft
Cable laying 132KVa Electric
Fencing
Concrete

ⓒ David H Moloney
Central Control Building for Refinery
Concrete

Cross Sections Horizontal moving upwards

ⓒ David H Moloney
Main Electrical Sub Station
Concrete

Cross Sections Horizontal moving upwards

ⓒ David H Moloney
Main Electrical Sub Station
Concrete

Cross Sections Vertical moving along

ⓒ David H Moloney
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

END