Académique Documents
Professionnel Documents
Culture Documents
The Azerbaijan Section of the Project’s Oil Pipeline including valve and
pig trap stations, laying of Fiber Optic cable and tie-ins at pumping
stations. Much of the terrain is flat and semi-arid.
The Pipeline links the Caspian sea oil wells with the Mediterranean Sea
ship tankers port.
The capacity is1 million barrels of crude oil flow per day
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,
Contents
Overview
Surveying & Setting Out
Clearing & Grading
Double Jointing i.e. welding 2 pipes together
Stringing out Pipes
Bend Pipes for changes in direction sideways and up & down
Welding Pipes into a string, Test Weld by X Ray.
Anti-corrosion Coat to Joints
Trenching i.e. excavate trench
Lowering pipe string into trench
Backfilling Trench
Reinstatement of Pipeline ROW (Right-of-Way)
Reinstatement of River Banks
Crossing - Horizontal Directional Drilling
Crossing - Thrust Boring
Crossing - River Pause Slides to Read
Hydrotest & Pigging
Tie-in i.e. connect to existing pipeline
Miscellaneous
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,
A typical sequence of activities is- surveying and setting out, preparing the land, stringing out the pipes along the
route, excavating the trench, welding and laying the pipes, backfilling the trench with the excavated soil, and
reinstating the land to its original condition.
.
6
Phase 7: Rolling Pipe
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,
Final Product
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,
Bending Pipes
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,
Bending Pipes
Bending Pipes
Bending
Completed Bends
Welding
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,
Welding
Fit-Up
Beveling
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,
Welding
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,
Trenching
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Backfilling
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Backfilling
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Backfilling
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Reinstatement ROW
Spreading Topsoil
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Reinstatement ROW
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Reinstatement ROW
Final Product
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Matting
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Sediment Control
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Lowering In
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Hydrotest
Hydrotest
Water Used For Hydrostatic Testing Is Water Is Then Passed Through Vented
Pigs Are Back Loaded Into Test Headers Break Tanks And Flow Meters
For Filling And Dewatering Test Test Headers Are Then Welded To The Filtered To 50 Microns
Sections Ends Of Test Section
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Hydrotest
Filling Spread Showing Fill Pumps, Pressurising Pumps And Instrument Control
Chemical Dump And Break Tanks Container
Tie-in
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
Tie-in
Miscellaneous
Contents
Sample Only
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
ⓒ David H Moloney
Temporary Contractors Site Facilities
Brief Description
ⓒ David H Moloney
Temporary Contractors Site Facilities - Stores
Brief Description
Pipes Delivery ⓒ David H Moloney
Brief Description
Train
Japan
Pipe Spool Fabrication Animation
Pipe Spool Fabrication Steps
Pipework
NDT
Cut Non Destructive
Testing
Bevel PWHT
Post Weld Heat
Treatment
Fit-up Blasting
Weld Painting
Tank Construction
Piperack Construction Animation
Brief Description
Before digging
establish the location
and route of
underground utilities.
ⓒ David H Moloney
General Items Dust Suppression
ⓒ David H Moloney
Organogram
Brief Description
7 km
14 minutes 7 km 14 minutes
3 minutes
Rock - Excavability
Earthworks
Brief Description
ⓒ David H Moloney
Quarry & Aggregate Production
Concrete
ⓒ David H Moloney
Concrete Batching Plant David H Moloney
Concrete
Brief Description
.
The mixing is computer controlled
and has a dynamic screen display,
showing the process. The material
storage capacity is, to match two
days concrete production.
ⓒ David H Moloney
Concrete Batching Plant
Concrete
ⓒ David H Moloney
Temporary Sheet-pile Shaft
Cable laying 132KVa Electric
Fencing
Concrete
ⓒ David H Moloney
Central Control Building for Refinery
Concrete
ⓒ David H Moloney
Main Electrical Sub Station
Concrete
ⓒ David H Moloney
Main Electrical Sub Station
Concrete
ⓒ David H Moloney
Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC
END
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ