Académique Documents
Professionnel Documents
Culture Documents
CONTENTS :
1. PURPOSE
2. SCOPE
4. WORK ORGANIZATION
ATTACHMENTS
A. REPORT FORM
388781120.doc Page 2 of 8
Standard Procedure Responsible Procedure No. Revision No.
JOINT COATING Department FP.009.SPI..03 0
PROCEDURE Engineering
1. PURPOSE
The purpose of this procedure is to get complete joint protection by fast tape wrapping (for
under ground service) within proper time when the coated pipe is installed and to get complete
anti corrosion effect by fast repair within proper time when the coated pipe was damaged.
2. SCOPE
This procedure shall be applied to field joint in job site for anticorrosion while coated pipe is
installed and applied to repair methods for defect which may occur during storage,
transportation and handling of line pipe as per Betara complex Development Project
requirement.
4. WORK ORGANIZATION
1. The field joint coating crew would be supervised by piping supervisor in applying
the coating on the welding joint and repair damage coating in accordance with this
procedure.
2. QC Inspector shall check to ensure that applied coating meet the project
specification.
3. QC Inspector is responsible to QC Coordinator for joint coating and repair coating
report and record.
388781120.doc Page 3 of 8
Standard Procedure Responsible Procedure No. Revision No.
JOINT COATING Department FP.009.SPI..03 0
PROCEDURE Engineering
5.2. Consumables
5.3.1. Surface preparation and pre-heat coating application or coating repair would be
performed on:
Water Disposal Line welds joint.
Butane Gas Line welds joint
Butane Crude Line welds joint.
5.3.2. Application of repair material for line pipe coating and damage top/protective coat.
Polyken 934 or Servi-Wrap HCB for weld joint of underground pipe line except HDD
crossing.
6.1.1. Preparation - 1
Clean exposed steel and adjacent pipe coating to be covered by wrapping using suitable
means. Remove all contaminant such as oil, grease, and dirt. Use a solvent that contains no
grease or oil type materials.
6.1.2. Preparation - 2
All bare steel surface shall be cleaned with dry brushes referred to SSPC-SP-3.
6.1.3. Preparation - 3
Hand tool cleaning is only permitted in tightly space areas where it is not possible to operate
power tools. Hand tool shall be done in accordance with SSPC-SP-2 followed by brushing
with clean dry brushes.
6.1.4. Pre-Heating
Immediately prior to primer application, the pipe shall be cleaned to remove any wetness or
others contamination. The pipe shall be heated, if necessary to achieve a surface a surface
temperature of approximately 300C to 400C.
388781120.doc Page 4 of 8
Standard Procedure Responsible Procedure No. Revision No.
JOINT COATING Department FP.009.SPI..03 0
PROCEDURE Engineering
6.1.6. Application -1
The surface shall be spirally wrapped with a minimum of 50 mm overlap. The wrapping
extend 75 mm onto the pipe coating at one side of the joint and terminate 75 mm onto the pipe
coating on the other side. Sufficient tension shall be applied to ensure that the tape and filler
comply with the surface of the pipe
6.1.7. Application - 2
The second wrap shall be applied so that the angle of the spiral is opposite of the first wrap.
1. Before repairing the damaged area, check shape of the damaged area
2. At this time, all coating from an area extending at least 50 mm on all sides of the damage
shall be removed and the surface in accordance with SSPC-SP-3
3. Remove dirt, scale, grease and other contaminants which impair the adhesion of the repair
material
B. Applied patch sheet for not exposed bare steel damaged area:
1. Before repairing the damaged area, check shape of the damaged area
2. Remove dirt, scale, grease and other contaminants which impair the adhesive of the repair
material.
3. Remove the damage coating to provide a clean binding surface for the repair material.
388781120.doc Page 5 of 8
Standard Procedure Responsible Procedure No. Revision No.
JOINT COATING Department FP.009.SPI..03 0
PROCEDURE Engineering
When coated steel pipes are completely repaired with wrapping sheet, after finishing the
repair, the condition will be checked by holiday detection.
When coated steel pipes area completely applied by tape coating with Polyken 934 or Servi-
wrap HBC after finishing the butt welding joint, the condition shall be confirmed by holiday
detection and reported using “Field Joint Coating Inspection Report while holiday test would
be recorded on HT Inspection Report.
3. Holiday Inspection.
388781120.doc Page 6 of 8
Standard Procedure Responsible Procedure No. Revision No.
JOINT COATING Department FP.009.SPI..03 0
PROCEDURE Engineering
ATTACHMENT
A
388781120.doc Page 7 of 8
Standard Procedure Responsible Procedure No. Revision No.
JOINT COATING Department FP.009.SPI..03 0
PROCEDURE Engineering
ATTACHMENT
B
A. FIGURE FOR FIELD JOINT COATING
1. Preparation – 1
2. Preparation – 2
3. Preparation – 3
4. Preheating
5. Primer applied
6. Primer applied
7. Application - I
8. Application - 2
9. Application - 3
10. Application - 4
11. Application - 5
12. Application - 6
13. Application - 7
388781120.doc Page 8 of 8