First day of our OJT in the proposed road heightening and tide embankment
for section 3 and 4 in Tacloban City and Palo, Leyte. First, Engr. Timkang
conducted an introduction on the things that we should expect and things that we
will do for the week. Then after that, we proceeded to the site and there I observed
a lot of operations by heavy machineries and by hardworking laborers. I observed
a lot of activities including the spreading of filling materials to the embankment
above the geotextile, hauling of filling materials for the embankment in sta. 7+520
– 7+540 and the sloping in the landside area near sta. 7+600. I was assigned to
monitor the backhoe operated by Joel Colon and at this first day, he assisted the
pouring of concrete in the landside area near sta. 7+ 520.With actual
measurements taken, we computed the total volume which is 4.447 cu. m.