Académique Documents
Professionnel Documents
Culture Documents
7 November 2013
Production is back on track following the installation of a new separator at
Sillaro in July. This is driving cash flow to fund both near-term Price A$0.12
development and exploration, with the offshore Teodorico development Market cap A$15m
the most significant project. The jury is still out on Gradizza commerciality US$1.35/€, US$1.03/A$
pending flow testing in November, while Selva Stratigraphic is now looking Net debt (€m) end September 2013 2.3
like a key target in 2014 following recent G&G work. Our RENAV of A$0.51
Shares in issue 122.4m
suggests considerable upside, with Teodorico still the main value driver.
Free float 45%
Code PVE
Year end Revenue EBITDA PBT* Debt Net debt Capex
(€m) (€m) (€m) (€m) (€m) (€m)
Primary exchange ASX
12/11 9.1 4.4 1.0 (5.8) (3.9) (2.3)
Secondary exchange N/A
12/12 8.2 4.5 0.2 (4.0) (2.8) (3.7)
12/13e 7.9 3.9 (1.2) (5.0) (0.9) (0.8) Share price performance
12/14e 10.5 6.1 0.5 (15.0) (11.3) (12.4)
Note: *PBT is normalised, excluding intangible amortisation, exceptional items and share-
based payments.
Next events
Development: Portfolio remains healthy
Gradizza-1 testing Q413
We consider development projects as the main value drivers for PVE. Pre-FEED
Teodorico seismic interpretation Q114
studies for its offshore AR94PY project (now renamed Teodorico) are ongoing in
parallel with 3D seismic reprocessing. We look for concept select for Teodorico in Bezzecca EIA approval Q114
Q114 ahead of detailed FEED studies. Meanwhile, the production concession for Analysts
Bezzecca is in the last stage of the regulatory approval process, with approval
Ian McLelland +44 (0)20 3077 5756
expected in Q114 and production potentially within two to three months of approval.
Will Forbes +44 (0)20 3077 5749
Angus McPhail +44 (0)20 3077 5731
Valuation: Continuing to trade below core NAV
oilandgas@edisongroup.com
Reflecting lower Castello production our core NAV drops slightly to A$0.16, but is still
Edison profile page
ahead of the current share price. However, we continue to steer investors to our
RENAV, which has now increased to A$0.51 with the inclusion of Selva Stratigraphic.
Realising this as always requires successfully negotiating Italian regulations.
Following installation and commissioning of a new three-phase separator at Sillaro in July 2013, we
have seen a marked improvement in the company’s production (Exhibit 1). In Q313, PVE has
reported total production of 69,000scm/d (2.4mmscf/d), with current rates now at c 76,000scm/d
(2.6mmscf/d). The one negative point in this is the continued low production rates at Castello, which
is now restricted to c 5,000scm/d due to higher than anticipated water-cut. However, water
production has stabilised at Castello in recent months and PVE expects to be able to continue to
produce at current rates for the foreseeable future. PVE’s most recent financials indicated a €5.0m
impairment loss in H113, the majority we expect to be charged to Castello.
Selva Stratigraphic
Moving into 2014, PVE has a number of potential exploration targets. The most likely candidate
based on recent releases is the Selva Stratigraphic prospect within PVE’s Podere Gallina licence,
which previously formed part of the ENI-operated Selva field (Exhibit 2 and Exhibit 3). This field
produced 83bcf from 15 wells over a 35-year period before being abandoned.
Exhibit 2: Selva Stratigraphic contour map Exhibit 3: Podere Gallina licence area
PVE is targeting an updip volume of the Selva field based upon new interpretation of the position of
the lapout edge towards the Selva-3 well. Independent consultant Robertson CGG has estimated
2C contingent resources of 17bcf for the Pliocene target and PVE has already selected a drill
location for a well, named Podere Maiar-1d. A drilling application was submitted in Q213 and,
subject to consents, we expect this to be a key exploration priority for PVE during 2014.
The first draft of the pre-FEED study has been finalised and is currently being reviewed by PVE.
The company intends to present a preliminary development plan based on the pre-FEED work as
The production concession for the Bezzecca gas field is in the final stages of the regulatory
approval process (EIA approval). This included a final meeting with the Lombardy Region
Commission in late September with no major issues noted. PVE is steering towards production
concession award in Q114. If secured, we would expect the company to press on with bringing the
existing Bezzecca-1 well into production within two to three months after receiving the authorisation
to install surface facilities. This will involve a 7km pipeline tie-back to the nearby Castello gas plant.
Bezzecca is particularly attractive to PVE as it intends to develop the field (subject to EIA approval)
via a phased approach with a tie-in to the nearby Castello gas plant, limiting capital costs in the first
year of production to primarily pipeline capex (which we estimate at €1.8m).
Following Bezzecca, the next most advanced onshore development programme is Sant’Alberto.
PVE has begun a pre-feasibility study for this project as part of the EIA process. This EIA is in the
final stages of the initial regional regulatory process after which a preliminary production concession
can be awarded.
Turning to financials we expect PVE to post a modest loss (c €1m) in 2013 at the normalised PBT
level. However, with a €5.0m impairment charge for Castello booked in H113 the company will be
facing a significant PBT loss of c €6m for 2013.
PVE exited Q313 with €2.7m of cash and net debt of €2.3m. The company has currently drawn
€5m of its €20m RBL facility with Nedbank. We anticipate that this facility will accommodate the
required capital expenditure to fund the development of both Bezzecca and Sant’Alberto, assuming
sufficient reserves are booked against these assets once development approvals have been
secured.
As discussed in our previous note this facility will not cover development of the offshore Teodorico
field, for which we would expect PVE to seek an offshore specialist as partner in return for a
development carry. Including development of Selva Stratigraphic we estimate that at current
working interests the company would require an additional €35m in addition to its existing RBL
facilities. However, the extent of any funding gap will only become clear in 2014 once pre-FEED
activities for Teodorico have been completed and PVE has confirmed its funding route for this
development, given the increased debt capacity it will have available and any farm-out it has
secured.