China International Water & Electric Corp.(S) No.

JIMT-C02-Q-04-20006
Pte.Ltd.
Date: 13 Feb 2017
Revision: 2
Training Procedure
Page 1 of 2

1. Reference

1.1 All project plans and procedures as following:

1 JIMT-C02-Q-04-20000 Quality management manual


2 JIMT-C02-Q-04-20001 Project quality plan
3 JIMT-C02-Q-04-20002 Non-conformance product control procedure
4 JIMT-C02-Q-04-20003 Corrective and preventive action procedure
5 JIMT-C02-Q-04-20004 Internal audit procedure
6 JIMT-C02-Q-04-20005 Management review procedure
7 JIMT-C02-Q-04-20007 Quality document and data control procedure
8 JIMT-C02-Q-04-20008 Quality record control procedure
9 JIMT-C02-Q-04-20009 Factory inspection procedure
10 JIMT-C02-Q-04-20010 Material control procedure
11 JIMT-C02-Q-04-20011 Monitoring and measuring devices control procedure
12 JIMT-C02-Q-04-20012 Field inspection procedure
13 JIMT-C02-Q-04-20013 General welding control procedure
14 JIMT-C02-Q-04-20014 Welder and welding operator qualification procedure
15 JIMT-C02-Q-04-20015 Welding consumable material control procedure
16 JIMT-C02-Q-04-20016 Welding repair procedure
17 JIMT-C02-Q-04-20017 Material identification & traceability procedure
18 JIMT-C02-Q-04-20018 Punch handling procedure
19 JIMT-C02-Q-04-20019 Quality control procedure for piling works
20 JIMT-C02-Q-04-20020 Inspection and testing plan for piling works
21 JIMT-C02-Q-04-20021 Quality control procedure for civil works
22 JIMT-C02-Q-04-20022 Inspection and testing plan for civil works
23 JIMT-C02-Q-04-20023 Quality control procedure for steel structure works
24 JIMT-C02-Q-04-20024 Inspection and testing plan for steel structure works
25 JIMT-C02-Q-04-20025 Quality control procedure for tank fabrication works
26 JIMT-C02-Q-04-20026 Inspection and testing plan for tank fabrication works
27 JIMT-C02-Q-04-20027 Quality control procedure for tank erection works
28 JIMT-C02-Q-04-20028 Inspection and testing plan for tank erection works
China International Water & Electric Corp.(S) No. JIMT-C02-Q-04-20006
Pte.Ltd.
Date: 13 Feb 2017
Revision: 2
Training Procedure
Page 2 of 2

29 JIMT-C02-Q-04-20029 Quality control procedure for rotating equipment works


30 JIMT-C02-Q-04-20030 Inspection and testing plan for rotating equipment works
31 JIMT-C02-Q-04-20031 Quality control procedure for static equipment works
32 JIMT-C02-Q-04-20032 Inspection and testing plan for static equipment works
33 JIMT-C02-Q-04-20033 Quality control procedure for piping works
34 JIMT-C02-Q-04-20034 Inspection and testing plan for piping works
35 JIMT-C02-Q-04-20035 Quality control procedure for electrical works
36 JIMT-C02-Q-04-20036 Inspection and testing plan for electrical works
37 JIMT-C02-Q-04-20037 Quality control procedure for instrument works
38 JIMT-C02-Q-04-20038 Inspection and testing plan for instrument works
39 JIMT-C02-Q-04-20039 Quality control procedure for painting works
40 JIMT-C02-Q-04-20040 Inspection and testing plan for painting works
41 JIMT-C02-Q-04-20041 Radiographic testing procedure
42 JIMT-C02-Q-04-20042 Ultrasonic testing procedure
43 JIMT-C02-Q-04-20043 Liquid penetrant testing procedure
44 JIMT-C02-Q-04-20044 Magnetic particle testing procedure
45 JIMT-C02-Q-04-20045 Hydro-test procedure
46 JIMT-C02-Q-04-20046 Soak test procedure
47 JIMT-C02-Q-04-20047 Vacuum-box test procedure
48 JIMT-C02-Q-04-20048 Factory acceptance test procedure
49 JIMT-C02-Q-04-20049 Site acceptance test procedure
50 JIMT-C02-Q-04-20050 Pre-commissioning and commissioning procedure
51 JIMT-C02-Q-04-20051 Water flotation procedure for internal floating roof