Académique Documents
Professionnel Documents
Culture Documents
management…
Risk identification.
4) Serius errors were found in the product during a test cycle in a software, :cpi is 0,8 and the
spi is 0,75, additionally, the project is struggling lack of sources, most likely cause.
Unidentified risk.
Owner.
7) The project manager wants to organize project risk by category to facilite their
management. What tool should de used.
Level 2:
2) The team is determining an overall project risk score. In which process is team involved.
3) What tool would you use to assess the probabilities and impacts of available alternatives?
4) After preparing the risk management plan, the project manager identified the project risk
and documented them in the risk register. Want has the project manager done wrong?
5 minutes.
Risk thresholds.
10) What is the risk expected value if the project quantitative risk analysis identified value if
the project quantitative risk analysis identified two risk with the following probabilities
and impacts?
. Risk A with a 10 percent probability of 5000 increase in materials costs . Risk B with a 10
percent probability of decrease of 2000 in travel expenses.
300
11) You have identified risk, assessed them using a probability impact matrix, and ranked
them according to their priority. What should you do NEXT?
12) The Monte Carlo technique analyzes the schedule risk based on:
PERT estimates.
Level 3.
The team will plan responses to all project risk to avoid future risk monitoring.
2) In two-year project, the project manager has intentionally delayed a solution design
activity. The project manager and the team are expecting that in the next few months, a
new and more effective technology might be available on the market. This is an example
of:
Enhance risk.
3) The project manager has identified has identified, analyzed, and prioritized risk, as well as
completed and prioritized risk, as well as completed the risk response plan, What should
be done NEXT?
4) A risk with a significant impact occurred. The risk was not previously identified, so there is
no risk available. What should the project manager do FIRST?
Establish a workaround.
Mitigate.
It assesses how well risk management processes were implemented in the project.
10) Which of the following options is NOT part of the plan risk responses process?
Workarounds.
12) All of the following processes are applied to every project, EXCEPT:
14) Fearing airline strikes, your company has decided to cancel all onsite meetings scheduled
for the month of April. Web meetings have been scheduled instead. What type of risk
response strategy has been used?
Avoid.