Present:-
1.0 LINE 5
TNB issue at MH5/36a, MH5/51 & MH5/52 CBB
2.0 LINE 6
2.01 ADUN meeting in morning for current issue
info
2.02 MH6/26 & MH6/18 - Backfilling for MH6/18
- MH6/26 to MH6/27 Jacking Pipe
______________________________________________________________________________________________________________________________________________________________
Charter Built Builders Sdn Bhd
72-3-28 Jln Mahsuri, Arena Curve, 11950 Bayan Lepas, Pulau Pinang Tel. No : 04 – 637 0165
ITEM MATTERS DISCUSSED DATELINE
ACTION BY
2.06 MH6/41-2 – meeting with ADUN and waiting for feedback
from YB on the next meeting together with school
info
representative.
2.08
MH6/46-2 – to confirm backdrop size and type from supplier
CBB
before instruction on piloting and excavation issued.
2.15 MH6/42 – Sheetpile use for the manhole need to paas back to
WM, Mr Tan request on replace MH6/42 with MH6/38. All
3.0 LINE 7
3.01 NIL
4.0 LINE 12
4.01 NIL
5.0 LINE 14
5.01 NIL
6.0 HOUSEKEEPING
5.01 All subcon shall aware housekeeping should be done in order All
to revolve coupon from authourity
7.0 PERMIT
7.01 NIL
8.0 OVERALL
8.01 Handing over pit – WM to ensure supervisor and surveyor WM
from CBB to do inspection on pit before handing over pit