Vous êtes sur la page 1sur 185

ODISHA POWER TRANSMISSION CORPORATION LIMITED

OFFICE OF THE SENIOR GENERAL MANAGER


CENTRAL PROCUREMENT CELL
JANAPATH, BHUBANESWAR-751022
TEL NO 0674-2541801 FAX NO 0674-2542964

TENDER SPECIFICATION NO
Sr.G.M.-CPC-DTR& PTR-12/2016-17

FOR

PROCUREMENT OF DISTRIBUTION & POWER TRANSFORMERS

SECTION-I : INSTRUCTION TO TENDERERS.


SECTION-II : GENERAL CONDITIONS OF CONTRACT
SECTION-III : LIST OF ANNEXURE (SCHEDULES & PROFORMA)
SECTION-IV : TECHNICAL SPECIFICATION.

Request for online tender documents –From dt-25.05.2016 (10.00 Hrs) to dt- 11.07.2016(11.00 Hrs)

Last date of submission of online tender – Up to dt.11.07.2016 (12.00 Hrs)

Date of opening of Tender - dt. 12.07.2016(11.00 Hrs)

Pre-bid meeting- 09/06/2016

Page 1 of 185
ODISHA POWER TRANSMISSION CORPORATION LTD.
REGD. OFFICE: JANPATH, BHUBANESWAR – 751 022,
ODISHA

e- TENDER NOTICE NO: CPC-12/2016-17

For and on behalf of ODISHA POWER TRANSMISSION CORPORATION LTD,


Sr.G.M. [C.P.C.] invites Tenders from reputed manufacturers in two part bidding system
for supply of DISTRIBUTION & POWER TRANSFORMERS. Bidders would be required to
enroll themselves on the tender portal www.tenderwizard.com/OPTCL for participating
in the above tender .Complete set of bidding documents are available in
www.tenderwizard.com/OPTCL from 25.05.2016 (10.00 Hrs) to dt- 11.07.2016(11.00 Hrs).
Interested manufacturers may visit OPTCL’s official web site http://www.optcl.co.in
and www.tenderwizard.com/OPTCL for detail specification.

N.B:-All subsequent addendums / corrigendum to the tender shall be hosted in the


OPTCL’s official web site http://www.optcl.co.in and www.tenderwizard.com/OPTCL
only.

SENIOR GENERAL MANAGER [C.P.C.]

Page 2 of 185
NOTICE INVITING TENDER
ODISHA POWER TRANSMISSION CORPORATION LIMITED
REGD. OFFICE: JANPATH, BHUBANESWAR – 751 022,
ODISHA, INDIA.
TENDER NOTICE NO CPC-12/2016-17

For and on behalf of the Odisha Power Transmission Corporation Limited, the
undersigned invites bids from manufacturers under two-part bidding system in e-Tender
mode only for supply of items as per the following details.

Earnest Cost of
Tender Last date of
Tender Pac Money Tender
Sl. Qty. Processin receipt &
Specification k- Description of materials. Deposit Spec.
No In N os. g Fee opening of
No. age (in Document
(in INR) tender
INR) (in INR)
25 KVA
14,73,86
1 I DISTRIBUTION 2250
3/-
TRANSFORMERS
63 KVA
2,48,163
2 II DISTRIBUTION 197
/-
TRANSFORMERS
3
100 KVA 2,35,8
3 III DISTRIBUTION 2055 85/-
TRANSFORMERS Rs. 11.07.201
SR.G.M.- 10,000+ 6 (12.00
Rs 5,000/
5% VAT Hrs) &
C.P.C. - DTR 3 + service
250 KVA 7,99,2 Tax @ 12.07.2016
& PTR- 12 (Rs
4 IV DISTRIBUTION 1160 91/- 10,500/-)
14.50% (11.00
/ 2016-17 TRANSFORMERS Rs Hrs)
5,725/-
500 KVA
41,12,95
5 V DISTRIBUTION 653
9/-
TRANSFORMERS

5 MVA POWER 74,67,57


6 VI 156
TRANSFORMERS 3/-

8 MVA POWER 89,08,68


7 VII 136
TRANSFORMERS 2/-

The bidders can view the tender documents from Tender Portal free of cost.

Page 3 of 185
The bidders who want to submit bids shall have to pay non-refundable amount of
Rs. 10,500/- (Rupees Ten thousand five hundred) only including VAT @ 5%) towards
the tender cost, in the form of Demand draft/Pay order/Cash only, drawn in favour of
the D.D.O Head Qrs, OPTCL, Bhubaneswar.
The bidders shall have to submit non-refundable amount of Rs.5,725/- (Rupees
Five thousand & seven hundred Twenty Five) only including Service Tax @ 14.50%)
towards the tender processing fee to K.S.E.D.C.Ltd, in e-payment mode. The e-payment
of above amount is to be made to enable the bidder to down load the bid proposal sheets
& bid document in electronic mode.
The bidder shall deposit the tender cost, tender processing fee & EMD BG prior to
last date & time for submission of bid as notified in tender notice. Local micro & small
enterprisers (MSEs) based in Odisha and registered with respective DICs, Khadi, Village,
Cottage & Handicrafts Industries, OSIC and NSIC can participate without payment of
the cost of tender specification. They have to submit notarized hard copy of valid
registration as local MSE as above on or before the date & time of submission of techno-
commercial bid.
The demand draft/pay order for tender cost , processing fees are to be submitted
along with the EMD at the office of the undersigned on or before the last date & time of
submission of tender.

The bidders shall scan the Demand Draft/Pay order/ Bank guarantee, towards EMD/ notarised
hard copy of valid registration as local MSE(if any) and upload the same in the prescribed form
in .gif or .jpg format in addition to sending the original as stated above.

The prospective bidders are advised to register their user ID, Password, company
ID from website www.tenderwizard.com/OPTCL by clicking on hyper link “Register
Me”.

Any clarifications regarding the scope of work and technical features of the tender
can be had from the undersigned during office hours.

Minimum qualification criteria of bidders: AS STIPULATED IN SECTION-II,


(G.T.C.C) OF THE TENDER SPECIFICATION.

SENIOR GENERAL MANAGER,


CENTRAL PROCUREMENT CELL

Page 4 of 185
PART – I.

SECTION – I.

INSTRUCTIONS TO TENDERERS

Clause. Title. Page.

1. Submission of Bids. 02
2. Division of Specification. 02
3. Tenders shall be in two parts.
4. Opening of Bids . 03
5. Purchaser’s right regarding alteration in 04
Quantities, Tendered.

6. Procedure and opening time of tenders. 04


7. Bidder’s liberty to deviate from specification.
8. Eligibility for submission of bids. 04
9. Purchaser’s right to accept/reject bids. 10
10. Mode of submission of tenders. 10
11. Earnest money deposit. 10
12. Validity of the bids. 11
13. Price. 11
14. Revision of Tender Price by Bidders. 11
15. Tenderers to be fully conversant with 11
the clauses of the Specification.

16. Documents to accompany Bids. 11


17. Documents/Papers to Accompany PART – II Bid. 12
18. Conditional Offer. 12
19. General. 12

Page 5 of 185
COMMERCIAL SPECIFICATION.
PART–I
SECTION- I
INSTRUCTIONS TO TENDERER
1. Submission of Bids:-
The bidder shall submit the bid in Electronic Mode only i.e
www.tenderwizard.com/OPTCL. The bidder must ensure that the bids are received in
the specified website of the OPTCL by the date and time indicated in the Tender notice.
Bids submitted by telex/telegram will not be accepted. No request from any bidder to the
OPTCL to collect the Bids in physical form will be entertained by the OPTCL.

The OPTCL reserves the right to reject any bid, which is not deposited according to
the instruction, stipulated above. The participants to the tender should be registered
under ODISHA Sales Tax, Act, VAT Act / Central sales Tax Act.

1. For all the users it is mandatory to procure the Digital Signatures of Class-III.
2. Contractors / Vendors / Bidders / Suppliers are requested to follow the below steps
for Registration:
a. Click “Register”, fill the online registration form.
b. Pay the amount of Rs. 2290/- through DD in favour of K S E D C Ltd Payable at
Bangalore.
c. Send the acknowledgment copy for verification.
d. As soon as the verification is being done the e-tender user id will be enabled.

3. After viewing Tender Notification, if bidder intends to participate in tender, he has to


use his e-tendering User Id and Password which has been received after registration
and acquisition of DSCs.
4. If any Bidder wants to participate in the tender he will have to follow the instructions
given below:
a. Insert the PKI (which consist of your Digital Signature Certificate) in your System.
(Note: Make sure that necessary software of PKI be installed in your system).
b. Click / Double Click to open the Microsoft Internet Explorer (This icon will be
located on the Desktop of the computer).
c. Go to Start > Programs > Internet Explorer.
d. Type www.tenderwizard.com/OPTCL in the address bar, to access the Login
Screen.
e. Enter e-tender User Id and Password, click on “Go”.
f. Click on “Click here to login” for selecting the Digital Signature Certificate.
g. Select the Certificate and enter DSC Password.
h. Re-enter the e-Procurement User Id Password
Page 6 of 185
5. To make a request for Tender Document Bidders will have to follow below mentioned
steps.
 Click “Un Applied” to view / apply for new tenders.
 Click on Request icon for online request.
6. After making the request Bidders will receive the Tender Documents which can be
checked and downloaded by following the below steps:
 Click to view the tender documents which are received by the user.
 Tender document screen appears.
 Click “Click here to download” to download the documents.
7. After completing all the formalities Bidders will have to submit the tender and they
must take care of following instructions.
 Prior to submission, verify whether all the required documents have been attached
and uploaded to the particular tender or not.
 Note down / take a print of bid control number once it displayed on the screen
8. Tender Opening event can be viewed online.
9. Competitors bid sheets are available in the website for all.
10. For any e-tendering assistant contact help desk number mentioned below.
 Bangalore – 080- 40482000.
The participants to the tender should be registered under ODISHA Sales Tax Act, VAT
Act/Central sales Tax Act.

2. Division of Specification.
The specification is mainly divided into two parts viz. Part-I & Part-II.
Part-I Consists of
[i] Section-I Instruction to Tenderers.
[ii] Section-II General Terms & conditions of contract.
[iii] Section-III Schedules and forms etc.
[iv] Section-IV Technical Specification.

Part-II Consists of
[i] Abstract of price components as per Annexure-IV

[ii] Schedule of prices as per Annexure-V

3. Tenders shall be in Two Parts.

The Tenderers are required to submit the tenders in two parts viz. Part-I ( Techno
commercial) & Part-II (Price bid).

Page 7 of 185
The Tenderers are required to submit the tenders in two parts Part-I, technical and
commercial and Part-II “Price Bid”.

4. Opening of Bids.

[a] The part-I shall be opened on the date and time fixed by the OPTCL for opening of bids in
Electronic mode in presence of such of the Tenderers or their authorized representatives
[limited to one person only] on the due date of opening of tender who opt remain present.
After scrutiny of the technical particulars and other commercial terms, clarifications, if
required, shall be sought for from the bidders. The Tenderers shall be allowed 15 days
time for such activity.
[b] On receipt of technical clarification, the bids shall be reviewed, evaluated and those not in
conformity with the technical Specification / qualifying experience, shall be rejected. If
any of the technical proposal requires modification to make them comparable, discussion
will be held with the participating bidders.

All the responsive bidders shall be given opportunity to submit the revised
technical and revised price proposals as a follow up to the clarification (modification if
any) on the technical proposals. The qualified bidders shall be given opportunity to submit
revised price proposals within 15 days from the date of such discussion or within time
frame mutually agreed, whichever is earlier.

[c] When the revised price proposals are received, the original price proposals will be
returned to the bidders unopened along with their original technical proposals. Only the
revised technical and price proposals will be considered for bid evaluation. The price bids
[Part-II] of such of the Tenderers, whose tenders have been found to be technically and
commercially acceptable, including those supplementary revised price bids, submitted
subsequently, shall be opened in the presence of the bidder’s representative on a date and
time which will be intimated to all technically and commercially acceptable Tenderers.

[d] The bidders are required to furnish sufficient information to the Purchaser to establish
their qualification, capacity to manufacture and/or supply the materials/perform the
work. Such information shall include details of bidder’s experience, its financial,
managerial and technical capabilities.

[e] The bidders are also required to furnish details of availability of appropriate technical staff
and capability to perform after sales services. The above information shall be considered

Page 8 of 185
during scrutiny and evaluation of bids and any bid which does not satisfactorily meet
these requirements, shall not be considered for price bid evaluation.

[f] The price bids of the technically and otherwise acceptable bids shall only be evaluated as
per the norms applicable in terms of this Specification.

5. Purchaser’s Right Regarding Alteration of Quantities Tendered.


The Purchaser may alter the quantities of materials/equipment at the time of placing
orders. Initially the purchaser may place orders for lesser quantity with full freedom to
place extension orders for further quantity under similar terms and conditions of the
original orders. Orders may also be split among more than one tenderer for any particular
item, if considered necessary in the interest of the Purchaser to get the goods/equipment
earlier.

6. Procedure and opening time of tenders.

Tenders will be opened in the office of the Senior General Manager [C.P.C.] on the
specified date and time in presence of the Tenderers or their authorized representatives
[limited to one person only] in case of each bidder who may desire to be present, at the
time of opening the bids.
7. Bidder’s Liberty to deviate from Specification.

The Tenderer may deviate from the specification while quoting, if in his opinion, such
deviation is in line with the manufacturer’s standard practice and conducive to a better
and more economical offer. All such deviations should however be clearly indicated giving
full justifications for such deviation. [Read with Clause-9, Section-II of the Specification].
8. Eligibility for submission of bids.

Only those manufacturers who have deposited the cost of tender specification are eligible
to participate in the tender. They should submit the money receipt as a proof of such
payment. The local Micro and small Enterprises (MSEs) based in Odisha and registered
with respective DICs, Khadi, Village, Cottage & Handicrafts Industries, OSIC and NSIC
can participate without payment of the cost of tender specification
9. Purchaser’s right to accept/reject bids:

The purchaser reserves the right to reject any or all the tenders without assigning any
reasons what so ever if it is in the interest of OPTCL, under the existing circumstances.
[Read with clause-10, Section-II of the specification].
10. Mode of submission of Tenders.

[A] Tenders shall be submitted in electronic mode only. (www.tenderwizard.com/OPTCL)


Page 9 of 185
[B] Telegraphic or FAX tenders shall not be accepted under any circumstances.
11. Earnest money deposit:
The tender shall be accompanied by Earnest Money deposit of value specified in the notice
inviting tenders against each lot / bid. Tenders without the required EMD as indicated at
Annexure-VIII will be rejected out rightly.

The local Micro and small Enterprises(MSEs) based in Odisha and registered with
respective DICs, Khadi, Village, Cottage & Handicrafts Industries, OSIC and NSIC
can participate by submitting Earnest Money Deposit @ fifty percent of the amount
indicated in the Notice Inviting Tender.
The earnest money deposit shall be furnished in one of the following forms subject
to the conditions mentioned below:
(a) Cash:-Payable to drawing & disbursing Officer, OPTCL (Hd.qrs. Office), Bhubaneswar -
751022
(b) Bank Draft: -To be drawn in favour of Drawing & Disbursing Officer, OPTCL
[H.Qrs.Office], Bhubaneswar-751 022.
(c) Bank Guarantee from any Nationalized/Scheduled Bank strictly as per enclosed proforma
vide Annexure-VI to be executed on non-judicial stamp paper worth Rs.29.00 or as
applicable, as per prevailing laws in force and also to be accompanied by the confirmation
letter of the issuing Bank Branch.
NOTE:
(i). The validity of the EMD in the form of Bank Guarantee shall be at least for 240 days from
the date of opening of tender failing which the tender will be liable for rejection.
(ii) No interest shall be paid on the Earnest Money Deposit.
(iii) E.M.D. in shape of cash may be submitted up to Rs. 25,000/- (Rupees Twenty-five)
Thousand) only. Above Rs. 25,000/- (Rupees Twenty-five thousand) the Earnest Money
Deposit shall be furnished in any one of the forms indicated above (i.e. Through Bank
Draft, Bank Guarantee/ National Savings Certificate).
(iv) No adjustment towards EMD shall be permitted against any outstanding amount with the
ODISHA POWER TRANSMISSION CORPORATION LTD.
(v) The chart showing particulars of EMD to be furnished by Tenderers of different categories
is placed at Annexure-VIII.
(vi) In the case of un- successful tenderer, the EMD will be refunded after the tender is
decided. In the case of successful Tenderer, this will be refunded only after furnishing of
security money referred to at clause-19of Section-II.
(vii) Suits, if any, arising out of this clause shall be filed in a Court of law to which the
jurisdiction of High Court of ODISHA extends.

Page 10 of 185
(vii) EMD will be forfeited if the tenderer fails to accept the letter of intent and/or purchase
order issued in his favour or to execute the order, placed on them.
(viii) Tenders not accompanied by Earnest Money shall be disqualified.

12. Validity of the Bids: -


The tenders should be kept valid for a period of 180 days from the date of opening of the
tender, failing which the tenders will be rejected.
13. PRICE: -
i)Tenderers are requested to quote-‘FIRM’ Price. No deviation from FIRM PRICE will be
entertained irrespective of deviation clause No.7 of this part of the specification.

14. Revision of tender price by Bidders: -


[a] After opening of tenders and within the validity of period, no reduction or enhancement in
price will be entertained. If there is any change in price, the tender shall stand rejected
and the EMD deposited shall be forfeited.
[b] After opening of price bid if the validity period is not sufficient to place purchase order,
the tenderer may be asked by the purchaser to extend the validity period of the bid under
the same terms and condition as per the original tender.
However, the tender are free to change any or all conditions including price except delivery
period of their bids at their own risk, if they are asked by the purchaser to extend the
validity period of the bid prior to opening of price bid.
15. Tenderers to be fully conversant with the clauses of the Specification: -
Tenderers are expected to be fully conversant with the meaning of all the clauses of the
specification before submitting their tenders. In case of doubt regarding the meaning of
any clause, the tenderer may seek clarification in writing from the Senior General
Manager (Central Procurement Cell) OPTCL. This, however, does not entitle the Tenderer
to ask for time beyond due date, fixed for receipt of tender.
16. Documents to Accompany Bids.
Tenderers are required to submit tenders in the following manner:
Part-I of the Tender shall Contain the following documents.
[i] Declaration Form. [As per Annexure-I]
[ii] Earnest Money. [As per Annexure-VIII], Tender Cost.
[iii] Technical specification and Guaranteed Technical Particulars conforming to the
Purchaser’s Specification along with drawings, literatures and all other required
Annexures, duly filled in.
[iv] Photostat copies of type test certificates of materials/equipment offered as stipulated in
the Technical Specification.

Page 11 of 185
[v] Abstract of Terms & conditions in prescribed proforma as per Annexure-II.
[vi] General Terms & Conditions of supply offer as per Section-II of the Specification.
[vii] List of orders executed for similar materials/equipment during preceding 2 (two) years
indicating the customer’s name, Purchase Order No. & Date, date of supply and date of
commissioning etc.
[viii] Data on past experience as per Clause-7 of Section-II of the Specification.
[ix] Sales tax clearance certificate for the previous year. The permanent account number
[PAN] of the firm is required under Income tax Act.
[x] Audited Balance sheet & profit loss accounts of the bidder, for past (3) three years.
[xi] Schedule of quantity and delivery in the prescribed Proforma vide Annexure, as
appended.
[xii] List of Orders in hand to be executed.
[xiii] Deviation schedule.
(xiv) Local micro & small enterprisers (MSEs) based in Odisha and registered with
respective DICs, Khadi, Village, Cottage & Handicrafts Industries, OSIC and NSIC have
to submit notarized hard copy of valid registration as local MSE as above on or before
the date & time of submission of techno-commercial bid and upload the scan/soft copy
of the same in e-tender portal.

17. Documents/Papers to accompany Part-II Bid.


(a) Part – II of the tender shall consist of the following
(i) Schedule of prices in the prescribed proforma
18. Conditional Offer:
Conditional offer shall not be accepted.
19. General: -
(i) In the event of discrepancy or arithmetical error in the schedule of price, the decision of
the purchaser shall be final and binding on the Tenderer.
(ii) For evaluation, the price mentioned in words shall be taken if there is any difference in
figures and words in the price bid.
(iii) Notice inviting tender shall form part of this specification.
(iv) The price bids of the technically and otherwise acceptable bids shall only be evaluated.
The EMD of others, if any, shall be returned to the bidders.
(v) Tenderer can offer any lot or all the lots of the tender, if there are more than one lots. But
the tender (bid) must be furnished separately for each lot. For each lot, the tenderer has
to submit PART-I & PART-II of the bids separately.
(vi) It should be distinctly understood that the part-II of the bid shall contain only
details/documents relating to price, as outlined in clause-17 mentioned herein above.

Page 12 of 185
Inclusion of any of the documents/information etc. shall render the bid liable for
rejection.
20.0 Expenses in respect of OPTCL’s representative for witnessing the inspection &
testing of the offered equipment/materials at the inspection and testing site.
The testing and inspection of the equipment/ materials at manufacturer works are in the
scope of work of the Contractor/Supplier.
OPTCL inspecting officer, on receipt of offer for inspection from the contractor/supplier,
proceeds to the manufacturer works to witness the Type/Acceptance/Routine test.
Important:
It is hereby informed to all the bidders that the relevant clauses of the contract
specification, pertaining to inspection and testing of equipment/materials, are hereby
supplemented with following additional terms and conditions.
The expenses under the following heads, in respect of OPTCL’s representative for
witnessing the inspection & testing of the offered equipment/materials at the inspection
and testing site, shall be borne by the contractor / supplier.
a) Hotel Accommodation:

I. Single room accommodation in 4 star hotel for the OPTCL inspecting officer of the rank of
Assistant General Manager (Grade E-6) and above.

II. Single room accommodation in 3 star hotel for the OPTCL inspecting officer of the rank
below Assistant General Manager (Grade E-6).

N.B.: It is the responsibility of the contractor to arrange the hotel accommodation matching with
their inspection and testing schedule, so that the inspecting officer can check-in the hotel
one day prior to the date of inspection and check out after the completion of the
inspection, subject to availability of the return travel ticket. In case of extended duration
of inspection or non-availability of the return travel ticket,
Contractor/supplier/manufacturer shall arrange for the extended stay of the inspecting
officer in the Hotel accordingly. In case there is no hotel with prescribed standard in and
around the place of inspection, the contractor/supplier/manufacturer shall suggest
alternative suitable arrangement at the time of offer for inspection, which is subjected to
acceptability of OPTCL inspecting officer.
b) Journey of the inspecting officer:
(i) To and fro travel expenditure from the Head Quarters of the inspecting officer to the place
of inspection/testing shall be borne by the contractor/supplier/manufacturer. Journey
from the Head Quarters of the inspecting officer to the nearest Air Port by train (Ist/IInd

Page 13 of 185
A.C) & A/C Taxi then by Air to the place of inspection/testing or to the nearest place of
inspection/testing and then by train (Ist/IInd A.C) & A/C taxi to the place of
inspection/testing shall be arranged by the contractor/supplier/manufacturer.
(ii) For train journey, inspecting officer of the rank Assistant General Manager and above
shall be provided with 1st class AC ticket and inspecting officer below the rank of
Assistant General Manager shall be provided with 2nd class AC ticket.
(iii) The Air-ticket / train-ticket booking/cancellation is the responsibility of the contractor /
supplier.
(iv) Moreover, if during the journey there is an unavoidable necessity for intermediate travel
by road/ waterway/sea-route, the contractor/supplier shall provide suitable conveyance
to the inspecting officer for travel this stretch of journey or bear the cost towards this. Any
such possibilities shall be duly intimated to OPTCL at the time of their offer for inspection.
c) Local Conveyance:
At the place of the inspection/testing, for local journey of the inspecting officer between
Hotel and inspection/testing site and or any other places, Air-conditioned four wheeler
vehicle in good condition shall be provided by the contractor/supplier/manufacturer.
d) Following points are also to be considered:
(i) All the above expenses shall be deemed to be included in the bidder’s quoted price for that
supply item. Bidder shall not be eligible to raise any extra claim in this regard.
(ii) Contractor/supplier/manufacturer may assume that only in 40% of the inspection and
testing offer cases, OPTCL inspecting officer, not below the rank of Assistant General
Manager will witness the inspection and testing.
(iii) In case of inspection and testing of some critical equipment/materials like Power
transformers, OPTCL may depute more than one inspecting officer.
(iv)Contractor/supplier/manufacturer shall judiciously plan the inspection/testing
schedule and place of inspection/testing, so that optimum number of inspection/testing
and minimum time shall be required to cover all the equipment/materials of the relevant
contract package.
(v) It shall be the responsibility of the Contractor/Supplier to organize the above tour related
matters of OPTCL inspecting officer including the matters related to overseas
inspection/testing, if any.
21.0 (a). Detailed information on any litigation or arbitration arising out of contract completed
or under execution by it over the last five years. A consistent history of litigation by or
against the bidder may result in rejection of bid.
21.0 (b). The bidder should not have any pending litigation or arbitration with OPTCL with
regard to any project or related activity. The bidder should certify / declare the same in
the unequivocal terms by way of an affidavit duly sworn before a magistrate. Bid

Page 14 of 185
furnished by the bidder shall not be eligible for consideration if it is not accompanied by
the affidavit. Further the bid / LOA/ LOI shall be liable for outright rejection/ cancellation
at any stage if any information contrary to the affidavit / declaration is detected.

Page 15 of 185
SECTION – II.

GENERAL TERMS AND CONDITIONS OF CONTRACT [G.T.C.C.]

Clause. Title. Page.

1. Scope of the contract. 03

2. Definition of terms. 03

3. Manner of execution. 04

4. Inspection and testing. 04

5. Training facilities. 05

6. Rejection of materials. 05

7. Experience of bidders. 05

8. Language and measures. 06

9. Deviation from Specification. 06

10. Right to reject/accept any tender. 06

11, Supplier to inform himself fully. 07

12. Patent rights etc. 07

13. Delivery. 07

14. Despatch Instructions. 07

15. Supplier’s Default Liability. 07

16 Force Majeure. 07

17. Extension of Time. 08

18. Guarantee Period. 08

19. Bank Guarantee towards Security Deposit, 08

Payment and Performance.

20. Import License. 09

21. Terms of Payment. 09

Page 16 of 185
22. Penalty for Delay in Completion of Contract. 20

23. Insurance. 09

24. Payment Due from the Supplier. 09

25. Sales Tax clearance, Balance Sheet& P/L A/C 09

26. Certificate of exemption from E.D/Sales Tax. 10

27. Supplier’s Responsibility. 10

28. Validity. 10

29. Evaluation. 10

30. Minimum qualification criteria of Bidders. 10

31. Jurisdiction of High Court of ODISHA. 11

32. Correspondences. 11

33. Official Address of the Parties to the Contract. 11

34. Outright rejection of Tenders. 12

35. Documents to be treated as confidential. 13

36. Scheme/Projects. 13

Page 17 of 185
PART-I
SECTION-II
GENERAL TERMS AND CONDITIONS OF CONTRACT [G.T.C.C.]
1. Scope of the contract:
The scope of the contract shall be to design, manufacture, supply of equipment as per the
specification at the consignee’s site, and rendering services in accordance with the
enclosed technical specification and bill of quantity.
2.0 Definition of terms:
For the purpose of this specification and General Terms and Conditions of contract
[GTCC], the following words shall have the meanings hereby indicated, except where
otherwise described or defined.
2.1 “The Purchaser” shall mean the Senior General Manager[Central Procurement Cell] for
and on behalf of ODISHA POWER TRANSMISSION CORPORATION LTD., Bhubaneswar.
2.2 “The Engineer” shall mean the Engineer appointed by the Purchaser for the
purpose of this contract.
2.3 “Purchaser’s Representative” shall mean any person or persons or consulting firm
appointed and remunerated by the Purchaser to supervise, inspect, test and examine
workmanship and materials of the equipment to be supplied.
2.4 “The supplier” shall mean the bidder whose bid has been accepted by the purchaser and
shall include the bidder’s executives, administrators, successors and permitted
assignees.
2.5 “Equipment” shall mean and include all machinery, apparatus, materials, and articles to
be provided under the contract by the suppliers.
2.6 “Contract Price” shall mean the sum named in or calculated the bid.
2.7 “General Condition” shall mean these General Terms and Conditions of Contract.
2.8 The Specification” shall mean both the technical as well as commercial parts of the
specification annexed to or issued with GTCC and shall include the schedules and
drawings, attached thereto as well as all samples and pattern, if any.
2.9 “Month” shall mean “Calendar month”.
2.10 Writing” shall include any manuscript, type written, printed or other statement
reproduction in any visible form and whether under seal or under hand.
2.11 “FOR Destination costs”shall mean the cost of equipment and material at the
consignee’s store/site. The cost is inclusive of Excise duty, Sales tax and other local
taxes, packing, forwarding and insurance and freight charges.

Page 18 of 185
2.12 The term “Contract document” shall mean and include GTCC, specifications, schedules,
drawings, form of tender, Notice Inviting Tender, covering letter, schedule of prices or the
final General Conditions, any special conditions, applicable to the particular contract.
2.13 Terms and conditions not herein defined shall have the same meaning as are assigned to
them in the Indian Contract Act, failing that in the Odisha General Clauses Act.
3. Manner of execution:
All equipment supplied under the contract shall be manufactured in the manner, set out
in the specification or where not set out, to the reasonable satisfaction of
the Purchaser’s representative.
4. Inspection and Testing:
[i] The purchaser’s representative shall be entitled at all reasonable times during
manufacture to inspect, examine and test at the supplier’s premises, the materials and
workmanship of all equipment/materials to be supplied under this contract and if part of
the said equipment/material is being manufactured in other premises, the supplier shall
obtain for the purchaser’s representative permission to inspect, examine and test as if the
equipment/material were being manufactured in the contractor’s premises. Such
inspection, examination and testing shall not relieve the supplier from his obligations
under the contract.
[ii] The Supplier shall give to the purchaser adequate time/notice (at least clear 15 days for
inside the state suppliers and 20 days for outside the state suppliers) in writing for
inspection of materials indicating the place at which the equipment/material is ready for
testing and inspection and shall also furnish the shop Routine Test Certificate,
Calibration certificates of Testing instruments, calibrated in Govt. approved laboratory
with authenticity letter of that laboratory along with the offer for inspection. A packing list
along with the offer, indicating the quantity which can be delivered in full truck load/Mini
truck load to facilitate issue of dispatch instruction shall also be furnished.
[iii] Where the contract provides for test at the Premises of the supplier or any of his sub-
vendors, the supplier shall provide such assistance, labour, materials, electricity, fuel and
instruments, as may be required or as may be reasonably demanded by the Purchaser’s
representative to carryout such tests efficiently. The supplier is required to produce shop
routine test Certificate, calibration certificates of Testing Instruments before offering their
materials/equipment for inspection & testing. The test house/laboratory where tests are
to be carried out must be approved by the Govt. A letter pertaining to Govt. approved
laboratory must be furnished to the purchaser along with the offer for inspection.
[iv] After completion of the tests, the Purchaser’s representative shall forward the test results
to the Purchaser. If the test results conform to the specific standard and specification, the
Purchaser shall approve the test results and communicate the same to the supplier in

Page 19 of 185
writing. The supplier shall provide at least five copies of the test certificates to the
Purchaser.
[v] The Purchaser has the right to have the tests carried out at his own cost by an
independent agency whenever there is dispute regarding the quality of supply.
[vi] If the firm fails to present the offered items for inspection/testing as per their inspection
call due to any reason(s) during the visit of inspecting officer at the testing site ,the firm
shall have to bear all expenses towards repetition of inspection and testing of the total
offered quantity or part thereof.
5. Training facilities.
The supplier shall provide all possible facilities for training of Purchaser’s Technical
personnel, when deputed by the Purchaser for acquiring first hand knowledge in assembly
of the equipment, its erection, commissioning and for its proper operation & maintenance
in service, wherein it is thought necessary by the purchaser.
6. Rejection of Materials.
In the event any of the equipment /material supplied by the manufacturer is found
defective due to faulty design, bad workmanship, bad materials used or otherwise not in
conformity with the requirements of the Specification, the Purchaser shall either reject the
equipment/material or ask the supplier in writing to rectify or replace the defective
equipment/material free of cost to the purchaser. The Supplier on receipt of such
notification shall either rectify or replace the defective equipment/material free of cost to
the purchaser within 15 days from the date of issue of such notification by the purchaser.
If the supplier fails to do so, the Purchaser may:-
[a] At its option replace or rectify such defective equipment /materials and recover the extra
costs so involved from the supplier plus fifteen percent and/or.
[b] Terminate the contract for balance work/supplies, with enforcement of penalty Clause as
percontract for the un-delivered goods and with forfeiture of Performance Guarantee/
CompositeBankguarantee.
[c] Acquire the defective equipment/materials at reduced price, considered equitable under
the circumstances.
7. Experience of Bidders:
The bidders should furnish information regarding experience particularly on the following
points:
[i] Name of the manufacturer:
[ii] Standing of the firm and experience in manufacture of equipment/material quoted:
[iii] Description of equipment/material similar to that quoted, supplied and installed during
the last two years with the name(s) of the Organisations to whom supplies were made
wherein, at least one (1) certificate shall be from a state/central P.S.U.

Page 20 of 185
[iv] Details as to where installed etc.
[v] Testing facilities at manufacturer’s works.
[vi] If the manufacturer is having collaboration with another firm [s], details regarding the
same.
[vii] A list of purchase orders of identical material/equipment offered as per technical
specification executed during the last two years along with users certificate. User’s
certificate shall be legible and must indicate, user’s name, address, designation, place of
use, and satisfactory performance of the equipment/materials for at least two years from
the date of commissioning. Wherein at least one (1) certificate shall be from a
State/Central or P.S.U.Bids will not be considered if the past manufacturing experience is
found to be un-satisfactory or is of less than 2 (two) years on the date of opening of the
bid and bids not accompanying user’s certificate will be rejected..
8. Language and measures:
All documents pertaining to the contract including specifications, schedule, notices,
correspondence, operating and maintenance instructions., drawings or any other writing
shall be written in English language. The metric system of measurement shall be used
exclusively in this contract.
9. Deviation from specification:
It is in the interest of the tenderers to study the specification, specified in the tender
schedule
thoroughly before tendering so that, if any deviations are made by the Tenderers,(both
commercial and Technical), the same are prominently brought out on a separate sheet
under heading “Deviations Commercial” and “ Deviations Technical”.
A list of deviations shall be enclosed with the tender. Unless deviations in scope,
technical and commercial stipulations are specifically mentioned in the list of deviations,
it
shall be presumed that the tenderer has accepted all the conditions, stipulated in the
tender specification, not- withstanding any exemptions mentioned therein.
10. Right to reject/accept any tender:
The purchaser reserves the right either to reject or to accept any or all tenders if the
situation so warrants in the interest of the purchaser. Orders may also be split up
between different Tenderers on individual merits of the Tenderer. The purchaser has
exclusive right to alter the quantities of materials/ equipment at the time of placing final
purchase order. After placing of the order, the purchaser may defer the delivery of the
materials. It may be clearly understood by the Tenderer that the purchaser need not
assign any reason for any of the above action [s].
11. Supplier to inform himself fully:

Page 21 of 185
The supplier shall examine the instructions to tenderers, general conditions of contract,
specification and the schedules of quantity and delivery to satisfy himself as to all terms
and conditions and circumstances affecting the contract price. He shall quote price [s]
according to his own views on these matters and understand that no additional
allowances except as otherwise provided there in will be admissible. The purchaser shall
not be responsible for any misunderstanding or incorrect information, obtained by the
supplier other than the information given to the supplier in writing by the purchaser.
12. Patent rights Etc.
The supplier shall indemnify the Purchaser against all claims, actions, suits and
proceedings for the infringement of any patent design or copy right protected either in the
country of origin or in India by the use of any equipment supplied by the manufacturer.
Such indemnity shall also cover any use of the equipment, other than for the purpose
indicated by or reasonably to be inferred from the specification.
13. Delivery:-
[a] Time being the essence of the contract; the equipment shall be supplied within the
delivery period, specified in the contract. The Purchaser, however, reserves the right to
reschedule the delivery and change the destination if required. The delivery period shall
be reckoned from the date of placing the Letter of Intent/Purchase order, as may be
specified in LOI/Purchase order.
[b] The desired delivery period shall be as indicated at Appendix-II (Quantity & Delivery
Schedule) of Section-IV (Technical Specification).
14. Despatch instructions.
I] The equipment / materials should be securely packed and dispatched directly to the
specified site at the supplier’s risk by Road Transport only.
II] Loading & unloading of Ordered Materials.
It will be the sole responsibility of the supplier for loading and unloading of materials
both at the factory site and at the destination site/store.
The Purchaser shall have no responsibility on this account.
15. Supplier’s Default Liability.
[i] The Purchaser may, upon written notice of default to the supplier, terminate the contract
in circumstances detailed hereunder.
[a] If in the judgement of the Purchaser, the supplier fails to make delivery of
equipment/material within the time specified in the contract or within the period for
which if extension has been granted by the Purchaser in writing in response to written
request of the supplier.
[b] If in the judgement of the Purchaser, the supplier fails to comply with any of the
provisions of this contract.

Page 22 of 185
[ii] In the event, Purchaser terminates the contract in whole or in part as provided in Clause-
15 {I) of this section, the Purchaser reserves the right to purchase upon such terms and in
such a manner as he may deem appropriate in relation to the equipment/material similar
to that terminated and the supplier will be liable to the Purchaser for any additional costs
for such similar equipment/material and/or for penalty for delay as defined in clause-22
of this section until such reasonable time as may be required for the final supply of
equipment.
[iii] In the event the Purchaser does not terminate the contract as provided in clause 15(I) of
this Section, supplier shall be liable to the Purchaser for penalty for delay as set out in
Clause-22 of this section until the equipment is accepted. This shall be based only on
written request of the supplier and written willingness of the Purchaser.
16 Force Majeure:
The supplier shall not be liable for any penalty for delay or for failure to perform the
contract for reasons of force majeure such as acts of god, acts of the public enemy, acts of
Govt., Fires, floods, epidemics, Quarantine restrictions, strikes, Freight Embargo and
provided that the supplier shall within Ten (10)days from the beginning of delay on such
account notify the purchaser in writing of the cause of delay. The purchaser shall verify
the facts and grant such extension, if facts justify .
17. Extension of time:-
If the delivery of equipment/material is delayed due to reasons beyond the control of the
supplier, the supplier shall without delay give notice to the purchaser in writing of his
claim
for an extension of time. The purchaser on receipt of such notice may or may not agree to
extend the contract delivery date as may be reasonable but without prejudice to other
terms and conditions of the contract.
18. Guarantee period: - ( As per clause 35 of the technical specification.
[i] The stores covered by this specification should be guaranteed for satisfactory operation
and against defects in design, materials and workmanship for a period of at least 42 [forty
two] months from the last date of delivery or 36 [thirty six] months from the date of
commissioning whichever is earlier. The above guarantee certificate shall be furnished in
triplicate to the purchaser for his approval. Any defect noticed during this period should
be rectified by the supplier free of cost to the purchaser provided such defects are due to
faulty design, bad workmanship or bad materials used, within one month upon written
notice from the purchaser failing which provision of clause 22 (ii) shall apply.
[ii] Equipment/material failed or found defective during the guarantee period shall have to be
guaranteed after repair/replacement for a further period of 36 months from the date of

Page 23 of 185
commissioning or 42 months from the date of receipt at the store/site after such
repair/replacement which ever is earlier . The Bank Guarantee is to be extended
accordingly. Date of delivery as used in this clause shall mean the date on which the
materials are received in OPTCL’S stores/site in full & good condition which are released
for Despatch by the purchaser after due inspection.
19. B.G. towards security deposit, 100% payment and performance guarantee:
[i] For manufacturers situated Inside & out side the state of Odisha.
A Composite Bank Guarantee as per the Proforma enclosed at Annexure-VII of the

specification for 10% [ten percent] of the total FORD cost of the purchase order (In case
of successful bidder who is a local Micro and small
Enterprise(MSEs),based in Odisha & registered with respective DICs,
Khadi, Village, Cottage & Handicrafts Industries, OSIC and NSIC 5%
(five percent), shall be furnished from any nationalized/scheduled bank having a place
of business at Bhubaneswar, to the office of Sr.General Manager [Central Procurement
Cell] OPTCL within 15 days from the date of issue of the purchase order,. The BG shall be
executed on non-judicial stamp paper worth of Rs.29.00 [Rupees twenty nine] only or as

per the prevalent rules, valid for a period of 2 months more than from guarantee period
(as indicated this clause-18 of above) from the last date of stipulated delivery period ,
for scrutiny and acceptance, failing which the supply order will be liable for cancellation
without any further written notices. The BG should be accompanied by a confirmation
letter from the concerned bank and should have provision for encashment at
Bhubaneswar, before the Bank Guarantee is accepted and all concerned intimated. The
B.G should be revalidated as and when intimated to you to cover the entire guarantee
period.
[ii] No interest is payable on any kind of Bank Guarantee.
[iii] In case of non-fulfillment of contractual obligation, as required in the detailed purchase
order/Specification, the composite Bank guarantee shall be forfeited.
20. Import License
In case imported materials are offered, no assistance will be given for release of Foreign
Exchange. The firm should arrange to import materials from their own quota. Equipment
of indigenous origin will be preferred.
21. (A) Terms of Payment.
100% value of each consignment with 100% Excise duty, Entry Tax, if any, and sales tax in full
as applicable along with freight & Insurance charges will be paid on receipt of materials in good
condition at stores/desired site and verification thereof, subject to furnishing and approval of
Composite Bank Guarantee at the rate of 10% (Ten percent) (In case of successful bidder who is
a local Micro and small Enterprise(MSEs),based in Odisha & registered with respective DICs,
Page 24 of 185
Khadi, Village, Cottage & Handicrafts Industries, OSIC and NSIC 5% (five percent), of the cost of
supplied materials, as stipulated under clause-19 of this specification & on prior approval of
guarantee certificate & Test certificate by the Purchaser.

Any imposition of new tax or revision of tax shall be paid/reimbursed at the time of dispatch,
scheduled or actual whichever is lower (i.e. If delivery is within schedule period, tax variation as
applicable shall be paid, and if delivery is made beyond schedule date, any additional financial
implication due to statutory variation in tax shall be to bidder’s account)

(ii) Payment of Freight & Insurance charges and Entry Tax.


Freight & Insurance Charges & Entry Tax, incorporated in the Purchase contract shall be
paid after receipt of materials at stores/desired site in good condition and on production
of authenticated documentary evidence, otherwise no Freight, Insurance charges & entry
taxes shall be payable.
[B] The supplier shall furnish Composite Bank Guarantee of appropriate amount to
OPTCL covering 10% of F.O.R. Destination cost of the purchase order well in advance
(within 15 days from the date of issue of the purchase order) before despatch of materials.
22. Penalty for Delay in Completion of Contract
I) If the Supplier fails to deliver the materials/equipment within the delivery schedule,
specified in the contract including delivery time extension, if any, granted thereto, the
Purchaser shall recover from the Supplier, penalty for a sum of half percent (0.5 percent)
of the Ex-works price of the un-delivered equipment for each calendar week of delay or
part thereof. For this purpose, the date of receipted chalan shall be reckoned as the date
of delivery. The total amount of penalty shall not exceed five percent (5%) of the ex-works
price of the unit or units so delayed. Equipment will be deemed to have been delivered
only when all its components and accessories as per technical Specification are also
delivered. If certain components & accessories are not delivered in time, the equipment
will be considered delayed until such time as the missing parts are delivered.
II) If the Supplier fails to rectify /replace the equipment/material within 30 days from the
date of intimation of the defect, so noticed by the purchaser within the guarantee period
then the penalty for sum of one half of the one percent (0.5%) of the total Purchase order
amount for each calendar week of delay shall be recovered by the purchaser within the
guarantee period. For this purpose, penalty date will start from the 30 th. day from the date
of issue of letter on defectiveness of equipment/material, so supplied, by the purchaser.
The total amount of penalty in this case shall not exceed 10% (TEN PERCENT) of the
purchase order amount. The purchase order amount shall mean ex-works price + freight &
insurance and all taxes & duties. If the defects so intimated within the guarantee period
will not be rectified by the

Page 25 of 185
Supplier within the stipulated period as per clause 18 (i), then whole of the B.G. will be
forfeited by the purchaser, without any intimation to the Supplier.
23. Insurance
The Supplier shall undertake insurance of stores covered by this Specification unless
otherwise stated. The responsibility of delivery of the stores at destination in good
condition rests with the Supplier. Any claim with the Insurance Company or transport
agency arising due to loss or damage in transit has to be settled by the supplier. The
Supplier shall undertake free replacement of materials damaged or lost, which will be
reported by the consignee within 30 days of receipt of the materials at destination without
awaiting for the settlement of their claims with the carriers and underwriters.
24. Payment Due from the Supplier. All costs and damages, for which the supplier is
liable to the purchaser, will be deducted by the purchaser from any money, due to the
supplier, under any of the contract (s), executed with OPTCL.
25. Sales Tax clearance certificate and Balance sheet and profit & Loss Account:
i. Sales Tax clearance certificate for the previous year shall be enclosed with the tender.
i. Audited Balance Sheet and Profit & Loss Account of the bidder for the previous three
years shall be enclosed to assess the financial soundness of the bidder(s).
26. Certificate of Exemption from Excise Duty/Sales tax.
Offers with exemption from Excise duty including sales tax shall be accompanied with
authenticated proof of such exemption. Authenticated proof for this clause shall mean
attested Photostat copy of exemption certificate. Any claim towards Excise duty/ Sales
Tax shall be paid on actual basis subject to production of authenticated documentary
evidence.

27. Supplier’s Responsibility.


Notwithstanding anything mentioned in the Specification or subsequent approval or
acceptance by the Purchaser, the ultimate responsibility for design, manufacture,
materials used and satisfactory performance shall rest with the Tenderers. The Supplier(s)
shall be responsible for any discrepancy noticed in the documents, submitted by them
along with the bid(s)

28. Validity.
Prices and conditions contained in the offer should be kept valid for a minimum period of
180 days from the date of opening of the tender, failing which the
tender shall be rejected.
29. EVALUATION.

Page 26 of 185
(i) Evaluation of bids will be on the basis of the FOR DESTINATION PRICE (By Road
Transport) including Excise Duty, sales Tax & other levies as may be applicable. The
FORD PRICE shall consist of the following components
a) Ex-works price.
b) Packing & Forwarding charges.
c) Freight
d) Insurance.
e) Excise Duty.
f) Sales Tax.
g) Other levies.
h) Mandatory spares, if any for maintenance of equipment. (At the discretion of
the purchaser)
i) Test charges, if any.
j) Supervision of erection, testing and commissioning charges, if any.
k) Any other items, as deemed proper for evaluation by the purchaser.
l) Loading factors will be taken in to account during evaluation if the prices of
some of the items, not quoted.
m) Any imposition of new tax or revision of tax shall be considered at the
time of price bid evaluation.

(II) Weightage shall be given to the Following factors in the Evaluation &
Comparison of Bids.
In comparing bids and in making awards, the Purchaser will consider other factors
such as compliance with Specification, minimum qualification criteria as per
clause-30, outright rejection of tenders clause-34 of this tender, relative quality,
adaptability of Supplies or services, experience, financial soundness, record of
integrity in dealings, performance of materials/equipment earlier supplied, ability
to furnish repairs and maintenance services, the time of delivery, capability to
perform including available facilities such as adequate shops, plants, equipment
and technical organization.
(III) The local MSE bidders, based in Odisha, shall be required to furnish their
willingness to match their bid price with that of the lowest evaluated bidder without
any price preference and in case they agree, they shall be eligible to get up to 20%
of the tendered quantity to be distributed suitably among the willing MSE bidders
failing which the said 20% of the tendered quantity be awarded to the lowest
evaluated bidder.

Page 27 of 185
30. Minimum Qualification Criteria of Bidders.
All the prospective bidders are requested to note that their bids for tendered equipment
can only be considered for evaluation if:
i) The bidder should have manufacture and supply experience of above rated or higher
capacity equipment for a minimum period of 3 (three) years as on the date of opening of
the tender
ii) At least 50% of the tendered quantity. of above rated or higher capacity equipment should
have been supplied within the above-stipulated period.

iii) The above rated or higher capacity equipment should have at least 3 (three) years
successful performance from the date of commissioning. At least one of the performance
certificates shall be submitted from Govt. of India/State Govt.(s) or their undertakings.
iv) The bidder should have conducted type tests on the tendered equipment in Government
approved laboratory within five years from the date of opening of the tender.
v) The bidder must possess BIS license for the tendered transformers.

31. Jurisdiction of the High Court of Odisha.


`Suits, if any, arising out of this contract shall be filed by either Party in a court of Law to
which the jurisdiction of High court of Odisha extends.
32. Correspondences.
i) Any notice to the supplier under the terms of the contract shall be served by Registered
Post or by hand at the Supplier’s Principal Place of Business.
ii) Any notice to the Purchaser shall be served at the Purchaser’s Principal Office in the
same manner.
33. Official Address of the Parties to the Contract
The address of the parties to the contract shall be specified:-
[i] Purchaser: Senior General Manager (Procurement)(CPC) OPTCL
Bhubaneswar-751022 (Odisha)
Telephone No. 0674 - 2541801
FAX No. 0674 - 2542964
[ii] Supplier: Address
Telephone No.
Fax No.
34. Outright Rejection of Tenders
Tenders shall be outrightly rejected if the followings are not complied with.
[i] The tenderer shall submit the bid in electronic mode only and shall submit the tender
cost on or before the date and time of submission of technical bid. . In case of local Micro
and small Enterprises(MSEs), based in Odisha & registered with respective DICs, Khadi,
Page 28 of 185
Village, Cottage & Handicrafts Industries, OSIC and NSIC participating in the tender they
have to submit notarised hard copy of valid registration as local MSE as above on or
before the date and time of submission of technical bid.
[ii] The tenderer shall submit the bid in electronic mode only
[iii] The Tender shall not be submitted telegraphically or by FAX.
[iv] The prescribed EMD shall be submitted on or before the date and time of opening of
technical bid.
[v] The Tender shall be kept valid for a minimum period of 180 days from the date of opening
of tender.
[vi] The Tender shall be submitted in two parts as specified.
[vii] The Tenders shall be accompanied by a list of major supplies effected prior to the date of
opening of tender. Data of at least 3 (three) years shall be furnished.
[viii] The tenderer shall upload the scanned copy of latest type test certificates (for the tests,
carried out on the tendered equipment , being offered). Such type tests should have been
conducted within last five years from the date of opening of this tender in a Government
approved laboratory/CPRI in presence of any Government Organisation’s
representative(s).
[ix] The schedule of prices should be filled up fully to indicate the break-up of the prices
including taxes and duties. Incomplete submission of this schedule will make the tender
liable for rejection. Vide Clause-4(ii) of Part-II..
[x] The Tenderer should quote ‘FIRM’ price only and the price should be kept valid for a
minimum period of 180 days from the date of opening of the tender.
(xi) The tenderer shall upload the scanned copy legibly written user’s certificate to prove the
satisfactory operation of the offered equipment /materials for a minimum period of 3
(three) years from the date of commissioning/use as per the tender specification. User’s
certificate shall include the detailed address of the user with Equipment/Material, Name
and type as per this specification, number of years of satisfactory use/operation & date of
issue of this user’s certificate with official seal written in English only & clearly visible
must be furnished. At least one of the user’s certificates shall be from state or Central
Govt. or their Undertakings.
(xii) Guaranteed Technical particulars & Abstract of terms and Conditions should be filled in
completely.
(xiii) (a) Detailed information on any litigation or arbitration arising out of contract completed or
under execution by it over the last five years. A consistent history of litigation by or
against the bidder may result in rejection of bid.
(xiii) (b) The bidder should not have any pending litigation or arbitration with OPTCL with
regard to any project or related activity. The bidder should certify / declare the same in

Page 29 of 185
the unequivocal terms by way of an affidavit duly sworn before a magistrate. Bid
furnished by the bidder shall not be eligible for consideration if it is not accompanied by
the affidavit. Further the bid / LOA/ LOI shall be liable for outright rejection/ cancellation
at any stage if any information contrary to the affidavit / declaration is detected.

35. Documents to be treated as confidential.


The supplier shall treat the details of the specification and other tender documents as
private and confidential and these shall not be reproduced without written authorization
from the Purchaser.
36. Scheme/Projects
The materials/equipment covered in this specification shall come under “O&M WORKS “

Page 30 of 185
SECTION – III.

LIST OF ANNEXURES

[I TO XI]

[PAGE 01 TO 19 ]

Page 31 of 185
SECTION – III
[LIST OF ANNEXURES]

The following schedules and proforma are annexed to this specification and contained in
Section-III as referred to in the relevant clauses.

1 Declaration form ANNEXURE-I


2 Abstract of terms and conditions to accompany ANNEXURE-II
Section-II of Part-I
3 Schedule of Quantity and Delivery ANNEXURE-III
4 Abstract of price component [to accompany Part-II ANNEXURE-IV
of this specification]
5 Schedule of prices to accompany Part-II ANNEXURE-V
6 Bank Guarantee form for earnest money deposit ANNEXURE-VI
7 Composite Bank Guarantee form for security ANNEXURE-VII
deposit, payment and performance
8. Chart showing particulars of E.M.D. ANNEXURE – VIII
9. Data on Experience. ANNEXURE – IX
10. Schedule of spare parts. ANNEXURE-X
11. Schedule of Installations. ANNEXURE-XI
12. Schedule of deviations. ANNEXURE-XII

ANNEXURE - I
DECLARATION FORM

Page 32 of 185
To
The Sr. General Manager (CPC)
OPTCL Head Qrs.BBSR,751022

Sub:- Tender Specification No-_________________________________________

Sir,

1. Having examined the above specification together with terms & conditions referred to
therein * I/We the undersigned hereby offer to supply the materials/equipment covered
therein complete in all respects as per the specification and General conditions, at the
rates, entered in the attached contract schedule of prices in the Tender.

2. * I/We hereby undertake to have the materials/equipment delivered within the time
specified in the Tender.
3. * I/We hereby guarantee the technical particulars given in the Tender supported with
necessary reports from concerned authorities.

4. * I/We certify to have submitted the bid electronically by remitting *cash/money


order/D.D./ remitting the cost of tender, herewith and this has been acknowledged by
your letter/ money receipt No. Dated,

5. In the event of Tender, being decided in *my/our favour, * I/We agree to furnish the
Composite B.G. in the manner, acceptable to ODISHA POWER TRANSMISSION
CORPORATION LTD., and for the sum as applicable to *me/us as per clause-19 of
section-II of this specification within 15 days of issue of letter of intent/purchase order
failing which *I/We clearly understand that the said letter of Intent/Purchase order will be
liable to be withdrawn by the purchaser, and the EMD deposited by us shall be forfeited
by OPTCL.

Signed this day of 2016

Yours faithfully

Signature of the Tenderer with seal of the company

[This form should be dully filled up by the tenderer and uploaded at the time of submission of
tender.]

* (Strikeout whichever is not applicable).

Page 33 of 185
ANNEXURE-II
ABSTRACT OF GENERAL TERMS AND CONDITIONS OF CONTRACT [COMMERCIAL] TO ACCOMPANY PART-I

1 (a) OPTCL Money Receipt No. & Date towards purchase of Tender.

(b) Earnest money furnished.

(A) Bank Guarantee, (B) Bank Draft.

2 Manufacturer’s supply experience including user’s certificate


Yes/No
furnished or not.[As per clause No.7 of Section-II.]

3 Deviations to the specification if any[list enclosed or not]

[As per clause-9 of the Section-II]


Yes/No
(a) Commercial
Yes/No
(b) Technical.
4 Delivery (period in months from the date of purchase order).

Pkg-I. 9 months.

Pkg -II. 6 months.

Pkg -III. 9 months.

Pkg -IV . 6 months.

Pkg -V . 6 months.

Pkg -VI . 12 months.

Pkg -VII . 12 months

5 Guarantee:- Whether agreeable to OPTCL’s terms. Yes/No

[As per clause-18 of Section-II]

6 Whether agreeable to furnish Composite B.G. in case his tender be Yes/No


successful [As per clause-19 of Section-II]

7. Terms of payment:- Whether agreeable to OPTCL’s terms or not Yes/No.

[As per clause-21 of Section-II]

8. Nature of price:- FIRM Yes/No

9. Penalty:- Whether agreeable to OPTCL’s terms or not (As per Yes/No


clause-22 of Section-II)

10. Whether STCC/ P&L A/C, Balance Sheet for the required period Yes/No
are furnish hed as per clause-25 of Section-II

11. Validity: - Whether agreeable to OPTCL’s terms or not Yes/No

[As per clause-28 of Section-II


12. Whether recent type test certificates from any Government Yes/No
approved laboratory are furnished or not. [As per clause-34[viii] of
section-II]

13. Whether guaranteed technical particulars in complete shape are


Yes/No
furnished or not

14. Whether dimensional design/drawings furnished or not Yes/No

15. Whether materials are ISI/ISO marked. Yes/No

16. Manufacturer’s name and it’s trademark. Yes/No

17. Whether registered under ODISHA Sales Tax Act. 1947 Yes/No

18. Whether declaration form duly filled in furnished or not. Yes/No.

Place: -
Date: - Signature of the
Tenderer
with seal of the
company

ANNEXURE-III

SCHEDULE OF QUANTITY AND DELIVERY

(To be filled up by the tenderer)

SL Description of materials Quantity Desired Destination Remarks.


required Delivery
No

1 2 3 4 5 6

LOT-I 25 KVA, (11 / 0.433 2250 9 months from Any Store /


KV) the P.O.
sites of
Transform
er, Energy OPTCL /
level-1
6 months from DISCOM in
LOT-II 197 the P.O.
63 KVA, (11 / 0.433
KV)
Transform
LOT-III er, Energy 2055 9 months from
level-1 the P.O.

6 months from
LOT-IV 100 KVA, (11 / 0.433 1160 the P.O.
KV)
Transform
er, Energy
LOT-IV level-1 653 6 months from
the P.O.
250 KVA, (11 / 0.433
KV) 12 months
156
Transform from the P.O.
LOT-V er, Energy
level-3 Odisha.
12 months
500 KVA, (11 / 0.433
LOT-VI 136 from the P.O.
KV)
Transform
er, Energy
level-1

5 MVA, (33 KV / 11 KV)


Power
Transform
er, Energy
level-1

8 MVA, (33 KV / 11 KV)


Power
Transform
er, Energy
level-3
Signature of
Tenderer

with seal of
Company
ANNEXURE-IV

ABSTRACT OF PRICE COMPONENT [TO ACCOMPANY PRICEBID]

1 F.O.R. Purchaser’s
destination
Price basis Stores/sites.

2 Packing & forwarding

3 Rate of Insurance charges

4 Rate of Freight charges

5 Rate of excise duty

6 Rate of sales Tax

7 Rate of other taxes/levies /duties etc.

8 Rate of entry tax.

9. Rate of Service Tax.

10. Nature of price.

11. Whether MODVAT benefit if any, has been fully


Yes / No.
passed on to the purchaser.

Place

Date: Signature of
Tenderer

With seal of
company

NB:- Abstract of price component shall be done for equipment/material


offered, for testing & commissioning charges, if any. All the above
prices will be taken during bid price evaluation.

ANNEXURE-V.
SCHEDULE OF PRICES TENDER SPECIFICATION No.

Ite Descriptio Qty Unit Unit Unit Unit Unit landing cost at
m n. (unit Ex- Packing & Freight Insuran destination
factory
) ce store/site excluding
No. Forwardin Charge
Price ST,ED & Entry tax.
includi g. s. Charges
ng
.
transfo
rmer
oil &
other
access
ories &
testing
as per
spec.

1. 2. 3. 4. 5. 6. 7. 8.

Unit Unit Unit Entry Unit landing Cost including Total landing cost
E.D. Tax. All taxes & Duties. Including all taxes &
S.T.
duties.

9. 10. 11. 12= (8+9+10+11) 13= (3X12)

Signature of Tenderer

Name, Designation and Seal

NB: -

1. The tenderer should fill up the schedule properly


and in full in Excel file of e-tender mode. The tenderer
should fill up the schedule properly and in full. The tender will be
rejected, if the schedule of price is submitted in incomplete form. No
post tender correspondence will be entertained on break-up of prices.
Also, the supplier should agree for delivery at sub-station site.
2. In case, where F&I components are not specifically indicated in this
schedule, 5% of the ex-works price shall be taken towards F&I
components for the purpose of comparison of price.
3. The Tenderer shall certify in the price bid that MODVAT benefit, if
any, has been fully passed on to the purchaser while quoting the
tender price.
4. Conditional offers will not be acceptable.
5. The bidder is to clearly indicate the period up to which the tax
holidays are available to them.
6. Price bid in any other format will not be acceptable and the offer will
be rejected.
7. All the above charges will be taken into account, during bid price
evaluation.
ANNEXURE-VI

PROFORMA FOR BANK GUARANTEE FORM FOR EARNEST MONEY

DEPOSIT

Ref Date Bank Guarantee No:

1 In accordance with invitation to Bid No. Dated of

ODISHA POWER TRANSMISSION CORPORATION LTD. [OPTCL]

[herein after referred to as the OPTCL for the purchase of

___________________________________________

Messers____________________________________________________________

Address_____________________________________________________________

_________________________________________________________________wis

h/wished to participate in the said tender and as a Bank Guarantee

for the sum of

Rs.______________[Rupees________________________________________

Valid for a period of 240 days [Two hundred forty days] is required to

be submitted by the Tenderer. We the

__________________________________________________________________

[Indicate

the Name of the Bank]

[Hereinafter referred to as ‘the Bank’] at the request of M/S

__________________________________________________________________

[Herein after referred to as supplier (s)] do hereby unequivocally and

unconditionally guarantee and undertake to pay during the above said

period, on written request by the Sr. General Manager [Procurement]

ODISHA POWER TRANSMISSION CORPORATION

LTD._______________________________________________
[Indicate designation of the

purchaser]

an amount not exceeding Rs._________________to the OPTCL, without

any reservation. The guarantee would remain valid up to 4.00 PM of

___________________

[date] and if any further extension to this is required, the same will be

extended on receiving instructions from

the_______________________________________ on whose

behalf this guarantee has been issued.

2. We the _____________________________________do hereby, further


undertake
[Indicate the name of the bank]

to pay the amounts due and payable under this guarantee without

any demur, merely on a demand from the OPTCL stating that the

amount claimed is due by way of loss or damage caused to or would

be caused to or suffered by the OPTCL by reason of any breach by the

said supplier [s] of any of the terms or conditions or failure to perform

the said Bid . Any such demand made on the Bank shall be conclusive

as regards the amount due and payable by the Bank under this

guarantee. However, our liability under this guarantee shall be

restricted to an amount not exceeding

Rs._____________________________________________

3. We undertake to pay the OPTCL any money so demanded not


withstanding any dispute or disputes so raised by the contractor [s] in
any suit or proceeding instituted/pending before any Court or
Tribunal relating thereto, our liability under this present being
absolute and unequivocal. The payment so made by us under this
bond shall be a valid discharge of our liability for payment there under
and the supplier(s) shall have no claim against us for making such
payment.
4. We, the______________________________________further agree that the
guarantee
[Indicate the Name of the Bank]

herein contained shall remain in full force and effect during the

aforesaid period of 240 days [two hundred forty days] and it shall

continue to be so enforceable till all the dues of the OPTCL under or

by virtue of the said Bid have been fully paid and its claims satisfied

or discharged or till Managing Director, ODISHA POWER

TRANSMISSION CORPORATION LTD. certifies that the terms and

conditions of the said Bid have been fully and properly carried out by

the said Supplier [s] and accordingly discharges this guarantee.

Unless a demand or claim under this guarantee is made on us in

writing on or before the _________________

we shall be discharged from all liability under this guarantee

thereafter.

5. We, the _______________________________further agree with the OPTCL

that

[Indicate the name of the Bank]

the OPTCL shall have the fullest liberty without our consent and

without affecting in any manner our obligations hereunder to vary any

of the terms and conditions of the said Bid or to extend time of

performance by the said Supplier [s] from time to time or to postpone

for any time or from time to time any of the powers exercisable by the

OPTCL against the said supplier [s] and to forbear or enforce any of

the terms and conditions relating to the said bid


and we shall not be relieved from our liability by reason of any such

variation, postponement or extension being granted to the said

Supplier [s] or for any forbearance act or omission on the part of the

OPTCL or any indulgence by the OPTCL to the said Supplier[s] or by

any such matter or thing whatsoever which under the law relating to

sureties would, but for this provision, have effect of so relieving us.

6. This guarantee will not be discharged due to the change in the name,
style and constitution of the Bank or the supplier [s].
7. We,____________________________________lastly undertake not revoke
this
[Indicate the name of the Bank]

Guarantee during its currency except with the previous consent

of the OPTCL in writing.

8. We the _________________________________ Bank further agree that this

guarantee shall also be invokable at our place of business at

-------------- Branch of Bhubaneswar ( indicate the name of the

branch)in the state of ODISHA.

Not withstanding any thing contained here in.

1) Our liability under this bank guarantee shall not exceed


Rs.--------------------------( Rupees-------------------).
2) The bank guarantee shall be valid up to dt.-----------------
3) We are liable to pay the guaranteed amount or any part there of
under this bank guarantee only & only if you serve upon us at
--------------branch at Bhubaneswar a written claim or demand on
or before dt.-----------------.
Dated ________________________ Day of

_________________________

For_____________________

________
[Indicate the name of

Bank]

Witness ((Signature, names & address)

1.

2.

ANNEXURE-VII

PROFORMA FOR COMPOSITE BANK GUARANTEE FOR SECURITY DEPOSIT

PAYMENT AND PERFORMANCE

This Guarantee Bond is executed

this________________________day of_______________ 2012 by us the

_______________________________________Bank at _____________________

P.O.____________________________P.S.________________________________

District_________________________State_______________________________

1. WHEREAS the ODISHA POWER TRANSMISSION CORPORATION


LTD., a body corporate constituted under the Electricity Act, 2003
[hereinafter called “the OPTCL” which shall include its successors and
assigns has placed orders No. _______________Date
______________[hereinafter called “The Agreement”] on
M/s.______________________________________
[hereinafter called “The Supplier”] which shall include its successors &

assigns for supply of materials.


AND WHERE AS the supplier has agreed to supply materials to

the OPTCL in terms of the said agreement AND

WHEREAS the OPTCL has agreed [1] to exempt the supplier

from making payment of Security [2] to release 100% payment of the

cost of materials as per the said agreement and [3] to exempt from

performance guarantee on furnishing by the Supplier to the OPTCL, a

Composite bank Guarantee of the value of 10 % [ten percent] of the

contract price of the said agreement.

NOW THEREFORE, in consideration of the OPTCL having

agreed [1] to exempt the Supplier from making payment of Security [2]

releasing 100% payment to the Supplier and [3] to exempt from

furnishing performance guarantee in terms of the said agreement as

aforesaid, we, the ________________________________ [Bank]

[hereinafter referred to as ‘the Bank’] do hereby undertake to pay to

the OPTCL an amount not exceeding Rs._____________

[Rupees_____________________________against any loss or damage

caused to or suffered by or would be caused to or suffered by the

OPTCL by reason of any breach by the said Supplier [s] of any of the

terms or conditions contained, in the said agreement.

2. We the (______________________________________Bank) do hereby


undertake to pay the amounts due and payable under this guarantee
without any demur, merely on demand from the OPTCL stating that
the amount claimed is due by way of loss or damage caused to or
suffered by the OPTCL by reason of any breach by the said Supplier [s]
of any of the terms or conditions, contained in the said agreement or
by reason of the supplier’s failure to perform the said agreement. Any
such demand made on the bank shall be conclusive as regards the
amount due and payable by the Bank under this guarantee. However,
our liability under this guarantee shall be restricted to an amount not
exceeding Rs.__________________
[Rupees____________________________________________________________
3. We the_____________________________ Bank} also undertake to pay to

the OPTCL any money so demanded not withstanding any dispute or

disputes raised by the supplier [s] in any suit or proceeding

instituted/pending before any Court or Tribunal relating thereto our

liability under this present being absolute and unequivocal.

The payment so made by us under this bond shall be a valid

discharge of our liability for payment there under and the Supplier [s]

shall have no claim against us for making such payment.

4 We, (_____________________________________Bank) further agree that

the guarantee herein contained shall remain in full force and effect

during the period that would be taken for the performance of the said

agreement and that it shall continue to do so enforceable till all the

dues of the OPTCL under or by virtue of the said agreement have been

fully paid and its claims satisfied or discharged or till Managing

Director, ODISHA POWER TRANSMISSION CORPORATION LTD.

certifies that the terms and conditions of the said agreement have

been fully and properly carried out by the said Supplier [s] and

accordingly discharges this Guarantee.

Unless a demand or claim under this guarantee is made on us

in writing on or before the [Date________________], we shall be

discharged from all liability under this guarantee thereafter.

5. We,(_____________________________Bank) further agree that the OPTCL

shall have the fullest liberty without our consent and without affecting

in any manner our obligations hereunder to vary any of the terms and

conditions of the said agreement or to extend time of performance by

the said Supplier [s] and we shall not be relieved from our liability by

reason of any such variations or extension being granted to the said

supplier [s] or for any forbearance, act or omission on the part of the
OPTCL or any indulgence by the OPTCL to the said Supplier [s] or by

any such matter or thing whatsoever which under the law relating to

sureties would but these provisions have effect of so relieving us.

6. This guarantee will not be discharged due to the change in the

name , style and constitution of the Bank and supplier [s].

7. We,[________________________Bank] lastly undertake not to revoke this

guarantee during its currency except with the previous consent of the

OPTCL in writing.

8. We the _________________________________ Bank further agree that this

guarantee shall also be invokable at our place of business at

------------ Branch of Bhubaneswar ( indicate the name of the

branch)in the state of ODISHA.

Not withstanding any thing contained here in.

1) Our liability under this bank guarantee shall not exceed

Rs.--------------------------( Rupees-------------------).

2) The bank guarantee shall be valid up to dt.-----------------

3) We are liable to pay the guaranteed amount or any part there of under

this bank guarantee only & only if you serve upon us at

--------------branch at Bhubaneswar a written claim or demand on or

before dt.-----------------.

Dated ________________________ Day of

_________________________

For_____________________

________
[Indicate the name of

Bank]

Witness ((Signature, names & address)

1.

2.

ANNEXURE-VIII

CHART SHOWING PARTICULARS OF EARNEST MONEY DEPOSIT

FURNISHABLE BY TENDERERS

1. Central and State Government Undertakings Exempted


2. All other inside & outside state units. The amount of

EMD as specified

in the specification

/Tender Notice in

shape of bank

guarantee /DD.

NB: - REFUND OF E.M.D.

[a] In case of unsuccessful tenderers, the EMD will be refunded

immediately after the tender is decided. In case of successful tenderer,

this will be refunded only after furnishing of Composite Bank

Guarantee referred to in clause No.19 of Section-II of this

specification.
Suits, if any, arising out of EMD shall be filed in a court of law to

which the jurisdiction of High Court of ODISHA extends.

[b] Earnest Money will be forfeited if the tenderer fails to accept the letter

of intent/purchase order, issued in his favour or revises the bid

price[ s] within the validity period of Bid.

ANNEXURE-IX

DATA ON EXPERIENCE
[a] Name of the manufacturer.

[b] Standing of the firm as manufacturer of equipment quoted.

[c] Description of equipment similar to that quoted [supplied and


installed during the last two years with the name of the organizations
to whom supply was made].

[d] Details as to where installed etc.

[e] Testing facilities at manufacturer’s works.

[f] If the manufacturer is having collaboration with another firm, details


regarding the same and present status.

[g] A list of purchase orders, executed during last three years.

[h] A list of similar equipment of specified MVA rating, voltage class,


Impulse level, short circuit rating, Designed, manufactured, tested and
commissioned which are in successful operation for at least two years from
the date of commissioning with legible user’s certificate. User’s full complete
postal address/fax/phone must be indicated. (Refer clause No.7 of the Part-I,
Section-II of the specification).

Place:

Date:
Signature of tenderer
Name, Designation,
Seal
ANNEXURE-X

SCHEDULE OF SPARE PARTS FOR FIVE YEARS OF NORMAL


OPERATION & MAINTENANCE

SL. Particulars Quantity Unit delivery rate Total price

No

Place:
Date: Signature of Tenderer

Name, Designation,
Seal
ANNEXURE-XI

SCHEDULE OF INSTALLATIONS.

Rated MVA Rated Voltage Place of installation Year of


and complete postal commissioning
address

Place: -

Date Signature of Tenderer:

Name, Designation, Seal


ANNEXURE-XII

DEVIATION SCHEDULE.

Tenderer shall enter below particulars of his alternative proposal


for deviation from the specification, if any.

A) Technical

Sl.No Clause No. Particulars of deviations.


of
specification

Place: -

Date Signature of Tenderer:

Name, Designation, Seal

B) Commercial deviations.

A) Commercial.

Sl.No Clause No. Particulars of deviations.


of
specification
.

Place: -

Date Signature of Tenderer:

Name, Designation, Seal


TECHINICAL SPECIFICATIONS

OF

ENERGY EFFICIENT

BIS ENERGY LEVEL-I RATING DISTRIBUTION TRANSFORMERS

(25 KVA, 63 KVA, 100 KVA, 250 KVA & 500 KVA 11/0.433 KV)
TABLE OF CONTENTS

OF

25 KVA, 63 KVA, 100 KVA, 250 KVA & 500 KVA 11/0.433 KV,
11/0.433

BIS ENERGY LEVEL-I RATING DISTRIBUTION TRANSFORMER.


No Description Page

1.0 Scope 1.0


2.0 Standards
3.0 Type
4.0 Main contacts & moving arm
5.0 Arcing horn and grading horn
6.0 Electrical interlock / mechanical
interlock
7.0 Auxiliary switches
8.0 Earth switch
9.0 Operating mechanism
10.0 Design, materials and workmanship
11.0 Protective coatings
12.0 Insulators
13.0 Control cabinet
14.0 Gear
15.0 Terminal block and wirings
16.0 Tests
17.0 Inspection
18.0 Documentation
19.0 Instruction manuals
TECHNICAL SPECIFICATION OF
25 KVA, 63 KVA, 100 KVA, 250 KVA & 500 KVA 11/0.433 KV ,
BIS ENERGY LEVEL-I RATING DISTRIBUTION TRANSFORMER

1 . 0 S C O P E

1.1 The specification covers the design, engineering, manufacture,


stage inspection, testing, pre-delivery inspection, supply, delivery,
loading, unloading and performance requirements of nominal
system voltages 11/0.433 KV non-sealed type aluminum wound
Distribution Transformers of 25 KVA, 63 KVA , 100 KVA and 250
KVA rating and copper wound Distribution Transformers of 500
KVA rating for outdoor use in the networks of CESU,
NESCO,WESCO & SOUTHCO. The transformers shall be double

wound, three phases, CRGO  Electrical Steel, oil immersed with ONAN


cooling with Oil filled up to maximum permissible level. The ratings
required under this specification are 25 KVA, 63 KVA, 100 KVA and
250 KVA with Aluminum windings & 500 KVA with Copper
windings.

1.2 The equipment offered should have been successfully type


tested

Within five years from date of opening of the tender and the designs
should have been in satisfactory operation for a period not less
than three years as on the date of bid opening. Compliance shall be
demonstrated by submitting with the bid,

(i) Authenticated copies of the type test reports and

(ii) Performance certificates from the users, specifically from


Central Govt./ State Govt. or their undertakings. The duration of
performance shall be taken from the date of commissioning to the
date of issue of certificates.

1.3 The scope of supply should also include the provision of


type test. The charges for conducting each of type tests shall be
included in the bid price and no separate type test charges shall be
paid. Only one no. of transformer of each rating will be subjected to type
tests as per relevant IEC/IS in CPRI/ ERDA in presence of authorized
Engineer(s) of OPTCL.

1.4 The transformer shall conform in all respects to highest standards


of engineering, design, workmanship, this specification and the latest
revisions of relevant standards at the time of offer and the owner
shall have the power to reject any work or material, which, in his
judgment, is not in full accordance therewith.

2.0 CODES & STANDARDS

2.1 Except where modified by this specification, the Transformers


shall be designed, manufactured and tested in accordance with the
latest editions of the following standards. The Bidder may
propose alternative standards, provided it is demonstrated that
they give a degree of quality and performance equivalent to or better
than the referenced standards. Whether to accept or reject any
alternative standard shall be adjudged by the owner. The Bidder shall
furnish a copy of the alternative standard proposed along with the bid.
If the alternative standard is in a language other than English, an
English translation shall be submitted with the standard. In the
case of conflict the order of precedence shall be 1) Indian Standards
IS 1180 (Part-I), 2014. Latest revision. 2) IEC or ISO Standards, 3)
other alternative standards.

LIST OF REFERRED INDIAN STANDARDS

Sl. IS No. Title


No.

1 191 : 2007 Copper

2 335 : 1993 New Insulating Oils

3 554 : 1999 Pipe threads where pressure- tight joints are


made on the threads-Dimensions, tolerances
and designation

4 1576 : 1992 Solid pressboard for electrical purpose

5 1608 : 2005 Mechanical testing of metals-Tensile testing

6 1747 : 1972 Nitrogen

7 1885 (Part-38) : Electro technical vocabulary : Part 38 Power


1993 transformers and rectors

8 1897 : 2008 Copper strip for electrical purpose


9 2026 Power Transformers :

10 (Part-1) : 2011 General

11 (Part-2) : 2010 Temperature rise

12 (Part -3) : 2009 Insulation levels, dielectric tests and external


clearances in air

13 (Part-5) : 2011 Ability to withstand short circuit

14 (Part-8) : 2009 Application guide

15 (Part-10) : 2009 Determination of sound levels

16 2099 : 1986 Bushings for alternative voltages above 1000


volts

17 3024 : 2006 Grain oriented electrical steel sheets and strips

18 3347 Dimensions for porcelain transformer bushings


for use in lightly polluted atmospheres

19 (Part-1 / Sec-1) : Up to and including 1 KV, Section 1 Porcelain


1979 parts

20 (Part-1 / Sec-2) : Up to and including 1 KV, Section 2 Metal


1979 parts

21 (Part-2 / Sec-1) : 3.6 KV Bushings, Section 1 Porcelain parts


1979

22 (Part-2 / Sec-2) : 3.6 KV Bushings, Section 2 Metal parts


1979

23 (Part-3 / Sec-1) : 17.5 KV Bushings, Section 1 Porcelain parts


1988

24 (Part-3 / Sec-2) : 17.5 KV Bushings, Section 2 Metal parts


1988

25 (Part-4 / Sec-1) : 24 KV Bushings, Section 1 Porcelain parts


1988

26 (Part-4 / Sec-2) : 24 KV Bushings, Section 2 Metal parts


1982

27 (Part-5 / Sec-1) : 36 KV Bushings, Section 1 Porcelain parts


1979

28 (Part-5 / Sec-2) : 36 KV Bushings, Section 2 Metal parts


1979

29 3639 : 1966 Fittings and accessories for power


transformers

30 4253 (Part-2) 2008 Cork composition sheet : Part 2 Cork and


rubber

31 6162 Paper-covered aluminium conductors :

32 (Part-1) : 1971 Round conductors

33 (Part-2) : 1971 Rectangular conductors

34 7404 (part-1) : Paper covered copper conductors : Part 1


1991 Round conductors

35 7421 : 1988 Porcelain bushings for alternating voltages up


to and including 1000 V

36 8999 : 2003 Pipe threads where pressure tight joints are


made on the threads- Verification by means of
limit gauges

37 9335 (Part-1) : Cellulosic papers for electrical purpose :


1979 Definitions and general requirements

38 (Part-2) : 1998 Methods of test

39 (Part -3 / Sec-1) : Specifications for individual materials, Section


1984 1 General purposes electrical paper

40 (Part -3 / Sec-3) : Specifications for individual materials, Section


1984 3 Crepe paper

41 (Part -3 / Sec-5) : Specifications for individual materials, Section


1985 5 Special papers

42 11149 : 1984 Specification for rubber gaskets

12444 : 1988 Continuously cast and rolled electrolytic


copper wire rods for electrical conductors

43 13730 Specification of particular types of winding


wires

44 (Part-0 /Sec-3) : General requirements, Section 3 Enamelled


2012 round copper wire

45 (Part-17) : 1996 Polywiny1 actual enamelled rectangular copper


wire, Class 105

46 (Part-27) : 1996 Paper covered rectangular copper wire

47 16081 : 2013 Insulating liquids – Specification for unused


synthetic organic esters for electrical purposes

This list is not to be considered exhaustive and reference to a


particular standard or recommendation in this specification does not
relieve the Supplier of the necessity of providing the goods
complying with other relevant standards or recommendations.
3.0 The service conditions shall be as follows:

Provisions of IS 2026 (Part-I) shall apply.

SERVICE
CONDITIONS

[a] Maximum altitude above sea level 1000 m

[b] Maximum ambient temperature 50 0C

[c] Maximum daily average ambient air temperature 40 0C

[d] Minimum ambient air temperature -5° C

[e] Maximum temperature attainable by an object 60 ° C


exposed to the sun

[f] Maximum yearly weighted average ambient 32° C


temperature

[g] Maximum relative humidity 100%

[h] Average no. of rainy days in a year. 120 days

[i] Average annual rainfall 150 cm

[j] Maximum wind pressure 260 Kg/Sq.m

[k] Average number of thunderstorm days per 70


annum (isokeraunic level)

Environmentally, the region where the equipment will be


installed includes coastal areas, subject to high relative humidity,
which can give rise to condensation. Onshore winds will frequently be
salt laden. On occasions, the combination of salt and condensation may
create pollution conditions for outdoor insulators.

Therefore, outdoor material and equipment shall be designed and


protected for use in exposed, heavily polluted, salty, corrosive, tropical
and humid coastal atmosphere.

4.0 SYSTEM CONDITIONS:


The equipment shall be suitable for installation in supply systems of
the following characteristics.
Frequency 50 Hz ± 5%

11 KV 11 KV
Nominal system voltages
System
LV 433/250 V
System
11 KV 12 KV
Maximum system voltages
System
LV 476 V
System
Minimum LV voltage (NEC)
392V

Nominal short circuit 11kV 500MV


apparent power of the System A
system (IS:202
6)
Insulation levels:
1.2/50µ sec impulse withstand 11kV 75 KV
System
Power frequency one minute 11kV 28KV
withstand (wet and dry) System (rms)
LV 3 KV (rms)
System
Neutral earthing arrangements: LV Solidly
System earthed

5.0 TECHNICAL SPECIFIC TECHNICAL REQUIREMENTS

25, 63, 100, 250, 500 KVA,


Rated KVA (ONAN rating)
11/0.43 KV
No. of phases 3

Type of installation Outdoor


Frequency 50 Hz (± 5% )
Cooling medium Insulating Oil (ONAN)
Type of mounting On Channels.
Rated voltage
a) High voltage winding 11 KV
b) Low voltage winding 0.433 KV
Highest continuous system voltage
a)Maximum system voltage ratio 12 KV / 0.476 KV
(HV / LV)
b) Rated voltage ratio (HV / LV) 11 KV / 0.433 KV
No. of windings Two winding
Transformers
Type of cooling ONAN ( Oil natural / Air
natural
KVA Rating corresponding to ONAN 100%
cooling system
Method of connection:

HV: Delta

LV: Star

Connection symbol Dyn 11

System earthing Neutral of LV side to be solidly

Percentage impedance voltage on 4.5 %


normal tap and KVA base at 75 0 C
corresponding to HV/ LV rating and (No negative tolerance will be
applicable tolerance. allowed)

Intended regular cyclic overloading of As per IEC —76-1, Clause 4.2


windings

Anticipated unbalanced loading Around 10%

Anticipated continuous loading of 110 % of rated current


windings (HV / LV)

Type of tap changer NA

Range of taping No Tap up to 100 KVA.

Neutral terminal to be brought out On LV side only

Over Voltage operating capability and 112.5 % of rated voltage


duration ( continuous )

Maximum Flux Density in any part


of the core and yoke at rated voltage
and frequency shall be such that the
flux density with +12.5% combined 1.9 Tesla
voltage and frequency variation from
rated voltage and frequency shall
not exceed

Insulation levels for windings

a) 1.2 / 50 microsecond wave shape


Impulse withstand (KVP) HV: 75 LV: N.A.

b) Power frequency voltage withstand HV: 28 LV: 03


(KVrms)
Type of winding insulation

a) HV winding
Uniform

b) LV winding
Uniform

Withstand time for three phase short


2 Seconds
circuit

Determination of sound levels IS 2026 (Part-10) : 2009


Permissible Temperature Rise over
ambient temperature of 500 C

350C up to 100 KVA & 40°C for


a) Of top oil measured by
thermometer. 250 & 500KVA

400 C up to 100 KVA & 45°C for


b) Of winding measured by 250 & 500KVA
resistance.

Minimum HV clearances in air


(mm) :-

a) Phase to Phase
255

b) Phase to ground
140

Bushings & Terminals

a) HV winding line end 12 KV oil filled porcelain


communicating type of
bushings (Antifog type )

b) L V w i n d i n g 0.4 KV porcelain type of


bushing (Antifog type)

Insulation level of bushing HV LV

a) Lightning Impulse withstand 75 Not applicable


(KVP)
b) 1 Minute Power Frequency 28
withstand voltage (KV —rms )
c) Creepage distance (mm)
25 mm/ KV
(minimum)

Material of HV & LV Conductor EC grade Aluminum

1.4 Amp/ mm2


Maximum current density for HV and
LV winding for rated current (For Aluminium winding)

2.4 Amp/ mm2

(For Copper winding)

Polarisation index i.e. ratio of Shall be greater than or


megger equal to

values at 600 sec. to 60 sec for HV to 1.5, but less than or equal to
earth '5'.

1.5, but less than or equal to


L.V to earth and HV to LV.
'5'.

Core Assembly Boltless type


Transformer Max. Losses at 50%
Max. Losses at 100%
Rating load (Watts).
load (Watts).

25 KVA 210 695

63 KVA 380 1250

100 KVA 520 1800

250 KVA 1050 3150

4750 ( Copper wound


500 KVA 1600
transformer)

No-load current for 25 KVA, 63 KVA & 100 kVA shall not exceed 3
percent of full load current and will be measured by energizing the
transformer at rated voltage and frequency. Increase of 12.5 percent of
rated voltage shall not increase the no-load current by 6 percent
maximum of full load current.

6 0 TYPE OF TRANSFORMER
.6.1 The Transformers shall be of core type construction, double
wound,

three phase, oil immersed, 11/0.433KV, 50 Hz with natural oil


and air cooling (ONAN) to be used as step down transformers for
outdoor use. The design of the tank, fittings, bushings, etc shall be
such that it will not be necessary to keep the Transformer energised
to prevent deterioration as the transformers may be held in reserve,
outdoors, for many years.

7.0 PERFORMANCE, CAPACITY AND SHORT CIRCUIT


RATING

7.1 The following ratings are covered under this specification

 25 KVA,11/0.433 KV, Aluminum wound


 63 KVA,11/0.433 KV, Aluminum wound
 100 KVA,11/0.433 KV, Aluminum wound
 250 KVA,11/0.433 KV, Aluminum wound
 500 KVA,11/0.433 KV, Copper wound
7.2 The Transformer shall be capable of supplying a continuous
load

equal to its KVA rating, under the following conditions :

¨ continuous steady load;


¨ design at maximum ambient air temperature of 50 0 C;
¨ 40 0 C average winding temperature rise and 35 0 C top oil
temperature rise for conventional breathing transformers up to
100 KVA rating and 45 0 C average winding temperature rise and
40 0 C top oil temperature rise for conventional breathing
transformers above 100 KVA ie for 250 KVA and 500 KVA..

7.3 The transformer may be overloaded during emergency up


to 150%

of its continuous rating in accordance with IEC Publication


354 or IS: 6600. Bushings and other current-carrying parts shall
also be designed for this condition.

7.4 The transformer shall be capable of withstanding for


t w o s e c o n d s w i t h o u t damage to any external short circuit,
with the short circuit MVA available at the terminals of either
winding with rated voltage on the other winding . If short circuit
tests have been carried out on the particular design of
transformer offered, the test results shall be supplied with the
bid.

7.5 The th e r ma l a bi lit y t o w it h st a n d sh or t c ir c ui t sh a ll


be de mon str a t e d by calculation. The Transformer shall
be capable of withstanding the thermal and dynamic
effects of short circuits, as specified in IEC 76-5 or IS:
2026: Ability to withstand short circuits.

Maximum Flux Density in any part of the core and yoke at


rated voltage and frequency shall be such that the flux density with
+12.5% combined voltage and frequency variation from rated voltage
and frequency shall not exceed 1.9 Tesla.

8.0 VOLTAGE RATIO & TAPPING RANGE


8.1 The transformers shall have the following ratio :-

¨ the nominal voltage ratio shall be 11,000/ 433 V for 25 KVA,


63 KVA, 100 KVA, 250 KVA & 500 KVA 11/0.4KV transformers;
¨ Tolerance on the voltage ratio shall be ± 0.5%.

¨ for transformers up to 100 KVA, 11/0.4 KV no tap changer is


required.

Tapping Ranges and Thpping Methods for 250 KVA and 500 KVA.

The standard tapping ranges, shall be as follows:

Wnding tapped HV

Number of tap positions:- 7

Voltage variations:- (+ 5) percent to (-10) percent in steps of 2.5 percent for


variation of HV

Off circuit tap-changing arrangement shall be by means of an externally-


operated switch with mechanical locking device and a position indicator.
Arrangement for padlocking shall be provided.

8.2 The bidder shall state in the technical schedule, the percentage
regulation at

full load, power factor 1.0 and at full load, power factor 0.85 lagging.

Transformers shall be suitable for parallel operation with each other.

9.0 PERCENTAGE IMPEDANCE

9.1 The Percentage of Impedance at 75 0


C shall be 4.5 % for 25
KVA,63 KVA

100 KVA, 250 KVA & 500 KVA Transformers. No negative tolerance
on percentage Impedance is allowed.

10.0 LOSSES

The load losses shall not exceed the values given below: -
KVA Rating Maximum losses at Maximum losses at
50% loading (Watts) 100% loading (Watts)
25 KVA 210 695
63 KVA 380 1250
100 KVA 520 1800
250 KVA 1050 3150
500 KVA 1600 4750

10.1 The above losses are maximum allowable and there should not
be any positive tolerance.

10.2 The offered transformer(s) should have been type-tested


at CPRI/ NABL Accredited laboratory. The bid shall be
accompanied with type-test reports (short circuit test and
Impulse test) conducted at Central Power Research Institute /
NABL Accredited laboratory for the offered transformers within five
years from date of tender. The short circuit test report(s) must
contain the measured no load loss and load loss, determined by
CPRI/ NABL Accredited laboratory.

In case of any doubts, Owner reserves the right to verify the


original type test reports of CPRI/ NABL Accredited laboratory or
ask the supplier to conduct the type tests at CPRI/ NABL Accredited
laboratory at his (supplier's) cost for re-confirmation of the test
results particularly no load losses, load losses and percentage
impedance.

10.3 If the bidder quotes lower values of losses than the CPRI's
measured

losses, he has to prove the same by conducting the Impulse & short
Circuit tests at CPRI/ NABL Accredited laboratory along with
measurement of no load losses and load losses at his own cost in
presence of Owner' s authorized representative without any financial
liability to owner.

10.4 However, if the loss figures will exceed the stipulated


values as p e r specification, the Transformer(s) shall be out rightly
rejected.
11.0 VECTOR GROUP

11.1 The Transformers shall be connected delta-star, in


accordance with vector group reference Dyn11 of IEC - 76/ IS – 2026
(Part-I).

11.2 The LV neutral shall be brought out to a terminal bushing,


which shall

be identical to the phase bushings in all respects.

1 2 . 0 L O S S E S

12.1 Transformers would be out rightly rejected if losses exceed the


values

indicated at clause-10 above.

13.0 FLUX DENSITY


Maximum Flux Density in any part of the core and yoke at rated
voltage and frequency shall be such that the flux density with
+12.5% combined voltage and frequency variation from rated voltage
and frequency shall not exceed 1 . 9 T e s l a .

14.0 INSULATION LEVELS

The insulation levels as defined in IEC 76-C/ IS: 2026 Insulation


levels and dielectric test shall apply as per Table 2:

Table 2 : Transformer insulation level

HV Winding LV Winding
Basic Impulse voltage Level (Kvp) 75 Not
(1.2/50 micro. sec. Wave ) Applicable

Power Frequency voltage withstand 28 3


level, Wet and Dry (KV)

Bushings and terminals shall be adequate for the winding insulation


tests and shall flash over externally before puncture or internal
failure can occur.
1 5 . 0 N O I S E L E V E L : Determination of sound levels [IS 2026 (part l0)
l.

16.0 RADIO INFLUENCE VOLTAGE

The maximum radio influence voltage shall be 250 micro Volt,


measured as specified in IEC 437.

17.0 CORE AND WINDINGS

17.1 Core

17.1.1 Stage level inspection for core construction shall be carried out by
the owner.

17.1.2 Each lamination shall be insulated such that it will not


deteriorate due to mechanical pressure & the action of the hot
transformer oil.

17.1.3 T h e c o r e s h a l l b e c o n s t r u c t e d f r o m h i g h g r a d e , n o n -
a g e i n g , Cold Rolled Grain Oriented (CRGO) silicon steel of M3
Grade or HIB grade laminations only. No other core materials
shall be entertained. Bidders are requested to note that only
PRIME CORE M3 Grade (0.23mm) materials HIB grade are to be
used. In no case, second grade core material is to be used. The
purchaser at his discretion, may select samples from the core
laminations and get the same tested in CPRI/ NABL Accredited
laboratory to prove the quality of the core material.

For the above purpose, the supplier shall have to offer every batch of
core laminations received from his Sub-Vendor along with
Invoice of the sub-vendor, Mills test certificate, packing list,
Bill of landing, Bill of entry certificate to customs etc. towards
proof of prime core materials for verification by the Purchaser's
representative without any cost to the Owner. Besides, the
contractor must mention in his bid about the type of CRGO /
Amorphous laminations to be utilized for the offered
transformers along with a copy of the specific core loss curve at
different flux densities.

17.1.4 Core materials should be directly procured either from the


manufacturer or through their accredited marketing organization of
repute, but not through any agent.
17.1.5 The core and winding shall be capable of withstanding
shocks during transport, installation and service. Provision shall
be made to prevent movement of the core and windings relative to
the tank during these conditions and also during short circuits.

17.1.6 The design shall avoid the presence of pockets which


would prevent the complete emptying of the tank through the drain
valve. The core material offered in the tender to be checked for its
correctness before core coil assembly. For this, the tendered must
ask for core and coil inspection before its tanking.

17.1.7 The laminations shall be free of all burrs and sharp


projections. Each sheet shall have an insulting coating resistant to the
action of hot oil.

17.1.8 The insulation structure for the core to bolts and core to
clamp plates shall be such as to withstand 2000 V DC voltage for one
minute.

17.1.9 The completed core and coil shall be so assembled that


the axis and the plane of the outer surface of the core assemble shall
not deviate from the vertical plane by more than 25mm.

17.1.10 All steel sections used for supporting the core shall be
thoroughly shot or sand blasted, after cutting, drilling and welding.

17.1.11 The finally assembled core with all the clamping structures
shall be free from deformation and shall not vibrate during operation.

17.1.12 The core clamping structure shall be designed to minimize


eddy current loss.

17.1.13 The framework and clamping arrangements shall be securely


earthed.

17.1.14 The core shall be carefully assembled and rigidly clamped


to ensure adequate mechanical strength.
17.1.15 Oil ducts shall be provided, where necessary, to ensure
adequate cooling inside the core. The welding structure and major
insulation shall not

obstruct the free flow of oil through such ducts.

17.1.16 The design of magnetic circuit shall be such as to avoid static


discharges, development of short circuit paths within itself or to the
earth clamping structure and production of flux component at right
angle to the plane of the lamination, which may cause local heating.
The supporting framework of the cores shall be so designed as to
avoid the presence of pockets, which would prevent complete
emptying of the tank through the drain valve or cause trapping of air
during filling.

17.1.17 The construction is to be of boltless core type. The core


shall be provided with lugs suitable for lifting the complete core
and coil assembly. The core and coil assembly shall be so fixed in
the tank that shifting will not occur during transport or short
circuits.

1 7 . 2 INTERNAL EARTHING

17.2.1 All internal metal parts of the transformer, with the


exception of individual laminations and their individual clamping
plates shall be earthed.

17.2.2 The top clamping structure shall be connected to the tank by a


copper strap. The bottom clamping structure shall be earthed by one
or more the following methods:

a) By connection through vertical tie-rods to the top structure.


b) By direct metal to metal contact with the tank base.
c) By a connection to the structure on the same side of the core as the
main earth connection to the tank.

17.2.3 The magnetic circuit shall be connected to the clamping


structure at one point only and this shall be brought out of the top
cover of the transformer tank through a suitably rated insulator. A
disconnecting link shall be provided on transformer tank to
facilitate disconnections from ground for IR measurement purpose.

17.2.4 Coil clamping rings of metal at earth potential shall be


connected to the adjacent core clamping structure on the same side as
the main earth connections.

17.3 Windings

17.3.1 Winding shall be subjected to a shrinking and seasoning process,


so that no further shrinkage occurs during service. Adjustable devices
shall be provided for taking up possible shrinkage in service.

17.3.2 Winding shall be subjected to a shrinking and seasoning process,


so that no further shrinkage occurs during service. Adjustable devices
shall be provided for taking up possible shrinkage in service.

17.3.3 All low voltage windings for use in the circular coil concentric
winding shall be wound on a performed insulating cylinder for
mechanical protection of the winding in handling and placing around the
core. Winding shall not contain sharp bends which might damage the
insulation or produce high dielectric stresses. No strip conductor wound
on edge shall have width exceeding six times the thickness.

17.3.4 The winding insulation shall be free from insulating compounds


which are liable to soften, ooze out, shrink or collapse. It shall be non-
catalytic and chemically inert in hot transformer oil during normal
service.

17.3.5 The stacks of windings are to receive adequate shrinkage


treatment.

17.3.6 The windings and connections are to be braced to withstand


shocks during transport switching, short circuit or other transient
conditions.

17.3.7 Permanent current carrying joints in the windings and leads


shall be welded or brazed. Clamping bolts for current carrying parts
inside oil shall be made of oil resistant material which shall not be
affected by acidity in the oil steel bolts, if used, shall be suitably treated.
17.3.8 Terminals of all windings shall be brought out of the tank
through bushings for external connections.

17.3.9 The windings shall be uniformly insulated and the L.V


neutral points shall be insulated for full voltage.

17.3.10 The completed core and coil assemble shall be dried in


vacuum at not more than 0.5mm of mercury absolute pressure and shall
be immediately impregnated with oil after the drying process to ensure
the elimination of air and moisture within the insulation. Vacuum may be
applied in either vacuum over or in the transformer tank.

17.3.11 The winding shall be so designed that all coil assembles of


identical voltage ratings shall be interchangeable and field repairs to the
winding can be made readily without special equipment. The coils shall
have high dielectric strength.

17.3.12 Coils shall be made of continuous smooth high grade


electrolytic copper or aluminium conductor shaped and braced to provide
for expansion and contraction due to temperature changes.

17.3.13 Adequate barriers shall be provided between coils and core


and between high and low voltage coil. End turn shall have additional
protection against abnormal line disturbances.

17.3.14 The insulation of winding shall be designed to withstand


voltage stress arising from surge in transmission lines due to
atmospheric or transient conditions caused by switching etc

17.3.15 Tapping shall not be brought out from inside the coil or from
intermediate turns and shall be so arranged as to preserve as far as
possible magnetic balance of transformer at all voltage ratios.

17.3.16 Magnitude of impulse surges transferred from HV to LV


windings by electromagnetic induction and capacitance coupling shall be
limited to BIL of LV winding.

17.3.17 The winding conductor shall be of Aluminum. The current


density shall not exceed 1.4 Amp/ mm2 for aluminium at normal full
load current.

18.0 BUSHINGS AND TERMINATIONS


18.1 Bushings

18.1.1 Bushings shall be of the outdoor type and easily replaceable.


Cemented in types will not be accepted. They shall be sufficiently robust
to withstand normal transport and erection hazards and shall confirm to
TEC 137 /TS 3347 and 2099.

18.1.2 All bushings shall have a minimum creepage distance of 25


mm /KV and shall have a continuous rating of 200% of the transformer
rating. The protected creepage distance shall not be less than 50% of the
total.

The following minimum 11 KV clearance shall be provided:

External (Air) for 11 KV

Phase to phase 255 mm

Phase to earth 140 mm

18.1.3 The 11 KV bushings of transformers shall be provided with a bi-


metallic terminal connector or suitable device to receive 35 —100 mm2
AAAC or ACSR conductor directly without any bi-metallic action. The dia
of HT bushing stud should not be less than 12.5 mm.

18.1.4 The secondary bushings of transformers shall be fitted with


non ferrous threaded terminals of dia not less than 20 mm. With the
exception of brass the terminals shall be protected from atmospheric
deterioration by suitable tinning or by some other approved coating.

18.1.5 The terminals are to be supplied with one 16mm bolt, one conic
spring washer, one matching flat washer, one nut and one lock nut for
each hole in the terminal plate.

18.2 Bushing Labels

18.2.1 The HV bushings shall be labeled U, V and W and the LV bushing


u, v, w and n. Marking letters shall be at least 12 mm high. The means of
marking shall be either,engraved metal plate; or ¨ etched anodized
aluminum.

Phase identification by adhesive stickers shall not be acceptable.


18.2.2 If labeling is to be carried out on the tank, it is preferred that one
plate bused rather than individual markings for each phase, in order to
prevent incorrect phase markings. Labels shall conform to the
requirements of the section on labels in this specification.

18.3 Earthing Terminals

All transformers shall be provided with two earthing terminals


conforming to relevant Standards and M12 ISO metric bolt and nut
which shall be non ferrous. It shall include a spring washer and lock
washer.

18.4 LIGHTNING ARRESTORS

9 KV, 5KA metal oxide lightning arresters of reputed make conforming to


IS=3070 Part=III, one number per phase shall be provided.(Under the HV
bushing with GI earth strip 25x4 mm connected to the body of the
transformer with robust clamping arrangement). Lightening arrestors
with polymer insulators in conformance with relevant IEC can also be
used.

19.0 TANK FABRICATION

19.1 All transformer sizes, the tank shall be of bolted type construction
in accordance with IS1180 (Part 2).

• The tank shall be at atmospheric pressure at an internal


temperature of 100 C;

• The tank shall be designed for an internal pressure of 100 Kg/ m2


at 500 C ambient conditions. It shall be capable of withstanding an
unlimited number of 24 hours cyclic variations of internal pressure from
atmospheric to this value.

• The tendered shall state the top oil temperature at which the tank
internal pressure shall reach the value of 100 kN/ m2 and the value of
steady load which will result in this top oil temperature with an ambient
temperature of 450 C.

• Adequate space shall be provided at the bottom of the tank for


collection of sediments.
19.2 Transformer tanks of all types shall be designed so that the
completed transformer can be lifted and transported without permanent
deformation or oil leakage. Stiffeners provided on all the four side walls
for rigidity should be so designed that there is no accumulation of water.

19.3 The Tank shall be of rectangular shape with round edges fabricated
from tested quality mild steel plates with minimum thickness of 3.15
mm. for the side walls while top cover and the bottom plate of the tank
shall have a minimum thickness of 5 mm. The transformer tank and the
top cover shall be designed in such a manner as to leave no external
pockets in which water can log, or any internal pocket where air/ gas can
accumulate. Edge of Top cover should be bend downwards so as to avoid
water through cover plate gasket. The width of the bend plate shall be
25mm minimum.

19.4 All sealing washers / gaskets shall be made of oil and heat
resistant neoprene rubber or neoprene bonded cork seals suitable for
temperature as stipulated in this specification. Surfaces at gasketted
joints shall be such that an even face is presented to gasket, thereby
eliminating the necessity for the gasket to take up surface irregularities.

19.5 All pipes, radiators, stiffeners or corrugations which are welded to


the tank wall shall be welded externally and shall be double welded
wherever possible. All welds shall be stress relieved.

19.6 The transformer tank shall be complete with all accessories, lifting
lugs etc. and shall be designed to allow the complete transformer filled
with oil to be lifted by crane or jacks without risk of any damage and can
be transported by Rail/ Road without straining any joints and without
causing any leakage of oil.

19.7 Provision of Cable End Box with suitable gland.

19.8 The height of the tank shall be such that minimum vertical
clearance up to the top cover plate of 80mm is achieved from the top of
the yoke.

20.0 PRESSURE RELIEF DEVICE

Transformers shall be fitted with a pressure relief device in the form of


explosion Vent.
The tendered shall state the pressure at which it is designed to
operate.

21.0 OIL LEVEL GAUGE

Oil level gauge indicating oil level at minimum, 30°C and maximum
operating

Temperature.

NOTES: Minimum and maximum positions correspond to the operating


temperature of -5°C and 90°C respectively (for non-sealed type
transformer).

22.0 CONSERVATORS AND BREATHERS

All the transformers shall be provided with a conservator tank.

22.1 The conservator tank shall be so designed and located as to


eliminate any trapping of air in the transformer or pipe work. It shall be
inclined at an angle of about 5 degrees to the horizontal towards the
drain plug and the pipe connecting the main tank to the conservator
should project about 2° mm above the bottom of the conservator so as to
create a sump for the collection of impurities. Minimum oil level
corresponding to 5° C shall be well above the sump level.

22.2 All transformers shall be fitted with a silica gel breather of


weather proof design at a convenient height with oil seal at the bottom,
draw in plug and filling holes with covers to isolate the silica gel from the
atmosphere. The breather pipe should be connected at top of the
conservator tank with two bends at right angles. The cover of the main
tank and bushings turrets shall be provided with air release plug to
enable the trapped air to be released.

23.0 FITTINGS AND ACCESSORIES

23.1 The following standard fittings and accessories shall be provided :

¨ Rating, diagram and terminal marking plate.

¨ Two earthing terminals.

¨ Lifting lugs/ platform lugs.

¨ Pressure relief device or explosion vent.


¨ Silicagel breather.

¨ Oil level gauge indicating oil level at minimum, 30°C and maximum
operating temperature. NOTES: Minimum and maximum positions
correspond to the operating temperature of -5°C and 90°C respectively
(for non-sealed type transformer).

- Top filter valve with locking arrangement.

¨ Bottom filter valve with locking arrangement.

¨ Air release plugs at transformer top cover, bushing turrets etc.

¨ Set of Radiators.

¨ Conservator Tank

- Oil temperature indicator and winding temperature indicators for


trans formers above 200 KVA.
- Buchholz relay (for transformers above 200 KVA.
- Non return valve (for conducting pressure test).
Bi-metallic terminal connectors on the bushings for connection with
overhead ACSR/ AAAC conductor. The Specification and brief details of
the salient features of these terminals should be stated.

24.0 TRANSFORMER OIL

The transformers shall be supplied complete with first filling of


transformer oil up to maximum permissible level. The quantity of
oil required for the first filling of the transformer and its full
specification shall be stated in the bid. The complete first filling
shall be of new oil free from inhibitors and additives up to
maximum permissible level for the supplied Transformer. The
bidder shall quote the price of transformer including the cost of
Transformer Oil required for initial filling.

The insulating oil for the transformer shall be of EHV grade,


generally conforming to latest version of IS: 335. No inhibitors shall
be used in the oil. The dielectric strength of the oil shall not be
less than 60 KV at 2.5 mm. gap when tested in accordance with IS:
6792/ 1972. If an anti-oxidant inhibitor is recommended, its use
shall be subject to the purchaser's approval.

The design and materials used in the construction of the transformer


shall be such as to reduce the risk of the development of acidity in the
oil.

Th e co n t ra cto r sh a ll wa rra n t th a t oil fu rn i sh ed is in

a cco rda n ce w ith t h e fo llo w i n g speci fi ca t i o n s.

S.No Characteristic Requirement Method of Test


01 Appearance The oil shall be clear & A representative
sample of oil shall be
transparent & free from
examined in a 100 mm
suspended matter or
thick layer at ambient
sediment
temp.
02 Density at 200 C 0.89 g/cm3 Max. IS:1448
03 Kinematic 27 CST IS:1448
Viscosity at 27
04 deg. C Maxtension at
Interfacial 0.03 N/m IS: 6104

05 Flash Point 136 0C IS:1448

06 Pour Point Max. -6 0C IS:1448


07 Naturalization Value 0.03 mg KOH/gm IS:335

(Total Acidity) Max.


08 Electric strength 72.5 KV IS: 6792

Breakdown
(voltage) Min.
09 Dielectric 0.03 Max IS: 6262
dissipation

factor tan delta at


900 C
10 Min specific resistance 35X10 12 ohm cm (min.) IS:6103
(resistively) at 90
deg.C

11 Oxidation stability

12 Neutralization 0.40mg KOH/g


value after
oxidation

13 Total sludge after 0.10% by weight max.

14 Presence of The oil shall not contain IS:335


oxidation anti-oxidant Additives.
15 Water content Max: Less than 25ppm IS:2362

26.0 RATING AND CONNECTION PLATE

Each transformer shall be provided with a rating plate of


weatherproof material showing the following items indelibly marked:

¨ type of transformer
¨ standard to which it is manufactured (preferably
IEC 76)

¨ manufacturer's name
¨ transformer serial number

¨ year of manufacture
¨ rated frequency in Hz (50)
¨ rated voltages in KV (11/0.433)
¨ number of phases (3)

¨ rated power in KVA


¨ type of cooling (ONAN)

¨ rated currents in A
¨ vector group symbol (Dyn11)
¨ 1.2/501.ts wave impulse voltage withstand level
in KVp
¨ power frequency withstand voltage in KV

impedance voltage at rated current and frequency

in percentage at 75° C at normal tap

¨ Measured load loss in KW at rated current and at 75°C at


normal tap
¨ Measured no-load loss in KW at rated voltage and rated
frequency continuous ambient temperature at which ratings apply
in °C
¨ top oil and winding temperature rise at rated load in ° C

¨ winding connection diagram


¨ Total weight in kg with complete oil filled.
¨ total weight of the transformer without oil
¨ Volume of oil in litres.
¨ weight of core and windings in kg; and
¨ name of the purchaser O P T C L
The rating plate shall conform to the requirements of the
section of Labels in this specification.

27.0 BASE MOUNTING ARRANGEMENT


The under-base of all three phase transformers up to 200 kVA ratings shall
be provided with two 75 mm x 40 mm channels 460 mm long as shown in
Fig. 6 of IS: 1180 Part-I, 2014, to make them suitable for fixing to a platforrm
or plinth.

The under-base of all transformers beyond 200 kVA shall be as per Fig. 7 of
IS: 1180 Part-I, 2014,to make them suitable for mounting on rollers.

27 (a) PUNCHINGS: Non=erasable Punching and embossing of


Volume of oil in litres, name of the Owner-----, Name of the
Supplier — M/s - ------------------------------, Year of Manufacture,
Guarantee Period ( i.e. 3 years from the date of installation)and Sl.
No. of each transformer is to be made on top core channel, top
cover, side walls and name plates of transformers.

27 (b) BIS ENERGY LEVEL-I: In addition to above, the supplied


Distribution Transformers must contain BIS ENERGY LEVEL-I
with style and information provided by the Bureu of Indian
Standard.

28.0 PAINTING

28.1 A l l p a i n t s s h a l l b e a p p l i e d i n a c c o r d a n c e w i t h t h e
p a i n t m a n u f a c t u r e r ' s recommendations. Particular attention
shall be paid to the following:

28. 2 a) Proper storage to avoid exposure as well as extremes of


temperature.

b) Surface preparation prior to painting.


c) Mixing and thinning
d) Application of paints and the recommended limit on time
intervals between coats.
e) Shelf life for storage.
28.3 All paints, when applied in normal full coat, shall be free from
runs, sags, wrinkles, patchiness brush marks or other defects.

28.3.1 All primers shall be well marked into the surface, particularly
in areas where painting is evident, and the first priming coat shall be
applied as soon as possible after cleaning. The paint shall be applied
by airless spray according to the manufacturer's recommendations.
However, wherever airless spray is not possible, conventional spray be
used with prior approval of purchaser.

28.3.2 The supplier shall, prior to painting protect nameplates,


lettering gauges, sight glasses, light fittings and similar such items.

28.4 Cleaning and Surface Preparation

28.4.1 After all machining, forming and welding has been completed,
all steel work surfaces shall be thoroughly cleaned of rust, scale,
welding slag or spatter and other contamination prior to any painting.

28.4.2 Steel surfaces shall be prepared by Sand/Shot blast cleaning


or Chemical cleaning by Seven tank process including Phosphating to
the appropriate quality.

28.4.3 The pressure and Volume of the compressed air supply for the
blast cleaning shall meet the work requirements and shall be
sufficiently free from all water contamination prior to any painting.

28.4.4 Chipping, scraping and steel wire brushing using manual or


power driven tools cannot remove firmly adherent mill-scale and
shall only be used where blast cleaning is impractical.

28.5 Protective Coating

28.5.1 As soon as all items have been cleaned and within four hours
of the subsequent drying, they shall be given suitable anticorrosion
protection.

28.6 Paint Material

Followings are the type of paints that may be suitably used for the items
to be painted at shop and supply of matching paint to site:

i) Heat resistant paint (Hot oil proof) for inside surface.

ii) For external surfaces one coat of Thermo Setting Paint or 2 coats of
Zinc chromate followed by 2 coats of P.0 (Poly-urethene) paint. The
color of the finishing coats shall be dark admiral gray.

28.7 Painting Procedure

28.7.1 All painting shall be carried out in conformity with both


specifications and with the paint manufacture's recommendations.
All paints in any one particular system. Whether shop or site applied,
shall originate from one paint manufacturer.

28.7.2 Particular attention shall be paid to the manufacture's


instructions on storage, mixing, thinning and pot life. The paint
shall only be applied in the manner detailed by the manufacturer
e.g. brush, roller, conventional or airless spray and shall be applied
under the manufacturer's recommended conditions. Minimum and
maximum time intervals between coats shall be closely followed.

28.7.3 All prepared steel surfaces should be primed before visible re-
rusting occurs or within 4 hours whichever is sooner. Chemical
treated steel surfaces shall be primed as soon as the surface is dry and
while the surface is warm.

28.7.4 Where the quality of film is impaired by excess film


thickness, (wrinkling, mud cracking or general softness) the
supplier shall remove the unsatisfactory paint coatings and apply
another. As a general rule, dry film thickness should not exceed the
specified minimum dry film thickness by more than 25%. In all
instances, where two or more coats of the same paints are specifies,
such coatings may or may not be of contrasting colors.

28.7.5 Paint applied to items that are not be painted, shall be removed
at supplier's expense, leaving the surface clean, un-stained and
undamaged.

28.8 Damages to Paints Work

Any damage occurring to any part of the painting scheme shall be


made good to the same standard of corrosion protection and
appearance as that originally employed.

Any damaged paint work shall be made as follows:

a) The damaged area, together with an area extending 25mm


around its boundary, shall be cleaned down to bare metal.

b) A priming coat shall immediately applied, followed by a


full paint finish equal to that originally applied and extending 50mm
around the perimeter of the originally damaged.

The repainted surface shall present a smooth surface. This shall be


obtained by carefully chamfering the paint edges before & after
priming.

28.9 Dry Film Thickness

To the maximum extent practicable, the coats shall be applied as a


continuous film of uniform thickness and free of pores. Over-spray,
skips, runs, sags and drips should be avoided. The different coats
may or may not be same color.
Each coat of paint shall be allowed to harden before the next is applied
as per manufacture's recommendations. Particular attention must be
paid to full film thickness at edges.

The requirement for the dry film thickness(DFT) of paint and the
material to be used shall be as given below:

Sl. Paint Type Area to be No of Total Dry


No painted Coats film
thickness(
1. Powder paint Inside 01 Min)
30 micron
outside
(2) Thermo setting
powder.
01 60 micron
2. Liquid paint
a) Zinc Chromate Out side 01 30 micron
(Primer)
b) P.U. Paint Out side 02 45 each
Coat)
c) Hot Oil paint inside 01 35/10
micron

The colour of the finishing coat shall be Sky Blue/ Dark Admiral
Gray/ Deep Green or any other colour as decided by the Purchaser

29.0 SEALING GASKETS

Gaskets shall be made of synthetic rubber or synthetic rubberized cork


resistant to hot transformer oil.

Gaskets wherever used shall conform to Type III as per IS


1l149/Type C as per IS 4253 (Part2)'

30.0 SUPRESSION OF HARMONICS

The transformer shall be designed with attention to the suppression


of harmonic voltage especially the third and fifth.

31.0 TESTS

31.l General

All routine, type and special tests as described in 31.2 to 31.4 shall be
performed as per relevant parts of IS 2026. Pressure and oil leakage test
shall be conducted as per 31.5.

31.2 Routine Tests (to be conducted on all units)

The following shall constitute the routine tests:


a) Measurement of winding resistance [IS 2026 (Part l)1.

b) Measurement of voltage ratio and check of phase displacement [IS 2026


(Part l)].

c) Measurement of short-circuit impedance

(principal tapping, when applicable) no load loss at 50 percent and 100


percent load US 2026 (Part l)1.

d) Measurement of no-load loss and current lls 2026 (Part l)1.

e) Measurement of insulation resistance US 2026 (Part l)1.

f) Induced over-voltage withstand test [lS 2026 (Part 3)1.

g) Separate-source voltage withstand test US 2026 (Part 3)1.

h) Pressure test (see 21.5)'

j) Oil leakage test (see 21.5).

31.3 type Tests (to be conducted on one unit)

The following shall constitute the type tests:

a) Lightning impulse test [lS 2026 (Pa*3)]' t3 IS 1180 (Part t) z 2014

b) Temperature-rise resr [IS 2026 (part 2)).

NOTE _ Maximum measured total loss (No load at rated excitation + load
loss at maximum current tap converted to 75 °C reference temperature) at
100 percent loading shall be supplied during temperature rise test.

c) Short-circuit withstand test IIS 2026(part 5)] (up to 200 kVA).

NOTE _ Routine tests before and after short circuit test shall be conducted
as per IS 2026 (part l).

d) Pressure test (see 2l.S)

31.4 Special Tests (to be conducted on one unit)

The following special tests shall be carried out.

a) Determination of sound levels [IS 2026 (part l0)l

b) Short-circuit withstand test US 2026 (part 5)l (above 200 kVA)

NOTE - Routine tests before and after short circuit test shall be conducted as
per IS 2026 (part l).

c) No load current at I12.5 percent voltage (see 5,9.3).

d) Paint adhesion tests. The test is performed as per ASTM D3359 (Standard
Test Methods for measuring adhesion by Tape test).
e) BDV and moisture content of oil in the transformer (lS 335).

NOTE - Tests at (d) and (e) may be carried out on more than one unit (One
unit in each Lot of inspection).

31.5 Pressure and Oil Leakage Test

31.5.1 For Transformers up to 200 kVA

31.5.1.1 Pressure test (type test)

For non-sealed and sealed type transformers, the transformer tank


shall be subjected to air pressure of 80 kPa for 30 min and vacuum of
250.mm of mercury for 30 min. The permanent deflection of flat plates, after
pressure/vacuum has been released, shall not exceed the values given below.

Sl.No Length of plate Deflection

1 Up to 750 mm 5.0 mm

2 751 mm to 1250 mm 6.5 mm

31.5.1,2 Pressure (routine test)

a) Non-sealed type transformers (plain tanks)

The transformer with bolted cover shall be tested at an air pressure of 35


kpa above atmosphere pressure maintained inside the tank for l0 min.
There should be no leakage at any point.

31.5.1.3 Oil leakage test (routine test)

The assembled transformer for non-sealed and sealed type with all fittings
including bushings in position shall be tested at a pressure equivalent to
twice the normal head measured at the base of the tank for 8 h. There
should be no leakage at any point. Tank with corrugations shall be tested for
oil leakage test a pressure of l5 kpa measured at the top of the tank for 6 h.
There should be no leakage at any point.

31.5.2 For Transformers above 200 kVA and Up to including 2 500 kVA

31.5.2.1 Pressure test (Type test)

For non-sealed and sealed type transformers, the transformer tank subjected
to air pressure of 80 kpa for 30 min and vacuum of 500 mm of mercury
for 30 min. The permanent deflection of flat plate, after pressure/vacuum has been
released, shall not exceed the values given below.
Sl.No Length of plate Deflection

1 Up to 750 mm 5.0 mm

2 751 mm to I 250 mm 6.5 mm

3 I 251 mm to I 750 mm 8.0 mm

4 Above I 751 mm 9.0 mm

31.5.2.2 Pressure test (routine test)

The transformer tank with welded/bolted cover shall be tested at a pressure


of 35 kpa above atmosphere pressure maintained inside the tank for l0
min. There should be no leakage at any point.

b) Corrugated tanks

The corrugated transformer tank shall be tested for air pressure of l5 kpa
above atmosphere pressure maintained inside the tank for l0 min. There
should be no leakage at any point.

31.5.2.3 Oil leakage test (routine test)

The assembled transformer for non-sealed and sealed type with all fittings
including bushing in position shall be tested at a pressure equivalent to
twice the normal head measured at the base of the tank for 8 h. There
should be no leakage at any point. Tank with corrugations shall be tested for
oil leakage test a pressure of 15 kPa measured at the top of the tank for 6 h.
There should be no leakage at any point.

31.4 TEST VOLTAGE

Transformers shall be capable of withstanding the Power

frequency and Impulse test voltage as described below:

N o m in a l Highest Impulse Test Power frequency


system System voltage test voltage
voltage voltage
433 V
3 KV (rms)
(rms)

11 KV 12 KV (rms) 75 KV 28 KV (rms)
(rms) (Peak)
32.0 COMPLIANCE WITH SPECIFICATION

The transformers shall comply in all respects with the requirements


of this specification. However, any minor departure from the
provisions of the specification shall be disclosed at the time of
tendering in the Non Compliance Schedule as in Annexure-3.

33.0 COMPLIANCE WITH REGULATIONS

All the equipment shall comply in all respects with the Indian
Regulations and acts in force.The equipment and connections shall
be designed and arranged to minimize the risk of fire and any
damage which might be caused in the event of fire.

34.0 INSPECTION AND TESTING

34.1 The Purchaser shall have free entry at all times, while
work on the contract is being performed, to all parts of the
manufacturer's works which concern the processing of the equipment
ordered. The manufacturer shall afford the Purchaser without
charge, all reasonable facilities to assure that the equipment being
furnished is in accordance with this specification. After approval of
Drawings by the Purchaser, the manufacture shall manufacture a
Prototype Model as per the Approved Drawing and offer the same
for inspection. The Inspection of the Prototype Model shall be carried
out as per the Format prescribed at Clause 41, Section-IV of our
Tender Specification. The Supplier shall offer the core, windings
and tanks of each transformer for inspection by the Owner's
representative(s). During stage inspection of the Prototype Model, all
the measurements like diameter, window, height, leg centre, stack
width, stack thickness, thickness of laminations etc for core
assembly, conductor size, insulation thickness, I.D., O.D.,
Winding height, major and minor insulations for both HV and LV
windings, length, breadth, height and thickness of plates of
transformer tanks, the quality of fittings and accessories will be
taken/ determined.
The Inspection Report for the Tests conducted by our Authorized
Inspectors in presence of the manufacturer's representative, for
the Prototype Model offered for inspection with suggested
modifications, if any shall be submitted to the undersigned for
approval.

After Inspection, the Prototype Model shall be kept sealed, in the


premises of the manufacturer till the completion of delivery of final
consignment, for future reference during subsequent Inspections.

The Supplier can offer for final inspection of the transformers


subject to clearance of the stage inspection report by the Purchaser.

34.2 The equipment shall successfully pass all the type tests and
routine tests mentioned in the above Clauses and those listed in the
most recent edition of the standards given in Clause 2, of this
specification.

34.3 The Owner reserves the right to reject an item of equipment if


the test results do not comply with the values specified or with the
data given in the technical data schedule.

34.4 Routine tests shall be carried out by the Supplier at no extra


charge at

their works. Adeq uat e fa ci li ty wi th cal ibra ted t estin g


eq uipmen t mu st be provided by the manufacturer free of cost to
carry out the tests. Type test certificates must be furnished along
with the tender for reference of the Owner.

34.5 The Purchaser will witness all required tests. In order to


facilitate this, the Supplier shall give the Purchaser a minimum of
two weeks’ notice as mentioned in clause-7(ii) of General Terms
and Condition of Contract (GTCC) that the materials are ready
for testing. If the Purchaser does not indicate his intention to
participate in the testing, the manufacturer may proceed with the
tests only after receipt of written confirmation to this effect from the
Purchaser and shall furnish the results thereof to the Purchaser
consequent upon such testing.
34.6 Full details of the proposed methods of testing, including
connection diagrams, shall be submitted to the Purchaser by the
Supplier for approval, at least one month before testing.

All costs in connection with the testing, including any necessary


re-testing, shall be borne by the Supplier who shall provide the
Purchaser with all the test facilities which the latter may require,
free of charge. The Purchaser shall have the right to select the
samples for test and shall also have the right to assure that the
testing apparatus is duly calibrated and correct. Measuring
apparatus for routine tests shall be calibrated at the expense of the
Supplier at an approved laboratory and shall be approved by the
Purchaser.

34.7 The supplier shall submit to the Purchaser five signed copies
of the test certificates, giving the results of the tests as required. No
materials shall be dispatched until the test certificates have been
received by the Purchaser and the Supplier has been informed that
they are acceptable.

The test certificates must show the actual values obtained from the
tests, in the units used in this specification, and not merely confirm
that the requirements have been met.

In the case of components for which specific type tests or routine


tests are not given in this specification or in the quoted standards
in Clause 2, of this specification, The Supplier shall include a list
of the tests normally required for these components. All materials
used in the Contract shall withstand and shall be certified to have
satisfactorily passed such tests.

34.8 The Purchaser at his discretion may re-confirm the Routine


Test Results, particularly no load losses, load losses and percentage
impedance in his own laboratory or laboratory of his choice.

No inspection or lack of inspection or passing by the Purchaser's


Representative of equipment or materials whether supplied by the
Supplier or sub-supplier, shall relieve the Supplier from his liability
to complete the contract works in accordance with the contract or
exonerate him from any of his guarantees.

However in case of future discrepancy, if any, after acceptance


of transformers, observed at any stage during guarantee period,
the matter may be referred to BIS for random testing of
transformers supplied. In such cases the observation of BIS shall
be binding to both parties.

35.0 GUARANTEE

The supplier shall guarantee the following:

¨ Quality and strength of materials used;


¨ Satisfactory operation during the guarantee period of thirty six
months (36 months) from the date of commissioning, or 42
months from the date of acceptance of the equipment by the
Purchaser following delivery, whichever is earlier;

¨ Performance figures as supplied by the tendered in the


schedule of guaranteed particulars;
¨ The offered surface treatment shall protect the treated metal
from corrosion for a period of not less than five years from the
date of delivery.

36.0 PACKING AND SHIPPING

36.1 Packing

The equipment and any supporting structures are to be transported


adequately sealed against water ingress. All accessories and
spares shall be packed and securely clamped against movement
in robust, wooden, non-returnable packing cases to ensure safe
transit in rough terrain, cross country road conditions and in heavy
rains from the manufacturer's works to the work sites/ earmarked
destinations.

36.1.1 All accessories shall be carefully packed so that they are


fully protected during transport and handling operations and in
storage. Internal surfaces of loose accessories shall be sealed by
means of gaskets and blanking off plates. All parts liable to rust
shall receive an anti-rusting coat and shall be suitably protected. It
shall be the responsibility of the Supplier to make good any damage
caused through insufficient packing.

Each packing case shall be indelibly marked, on two adjacent sides


and on the top, with the following:

¨ Individual serial number;


¨ Purchaser's name;
¨ Contract number;
¨ Destination;
¨ A colour coded marking to indicate destination;
¨ Supplier's name;
¨ Name and address of supplier's agent in Odisha;
¨ Description and numbers of contents;
¨ Manufacturer's name;
¨ Country of origin;
¨ Case measurements;
¨ Gross and net weight in kilograms: and
¨ All necessary slinging and stacking instructions.

36.1.2 Each crate or container shall be marked clearly on the


outside of the case to show TOP and BOTTOM positions with
appropriate signs to indicate where the mass is bearing and the
correct positions for slings. All component parts which are
separately transported shall have permanent identification marks
to facilitate correct matching and assembly at site. Welded parts
shall be marked before welding. Six copies of each packing list
shall be sent to the Purchaser prior to dispatching the equipment.

36.2 Transportation

The Supplier shall be responsible for the transport of all plant and
equipment supplied by them and for the transport of all goods to the
various specified destinations including all road clearance,
offloading, warehousing and insurance.

The Supplier shall inform himself fully as to all relevant


transport facilities and requirements and loading gauges and
ensure that the equipment as packed for transport conform to these
limitations. The Supplier shall also be responsible for verifying the
access facilities specified.

The Supplier shall be responsible for the transportation of all loads


associated with the contract works and shall take all reasonable
steps to prevent any highways or bridges from being damaged by
his traffic and shall select routes, choose and use vehicles and
restrict and distribute loads so that the risk of damage shall be
avoided. The Supplier shall immediately report to the Purchaser
any claims made against the Supplier arising out of alleged damage
to a highway or bridge.

All transport accessories, such as riding lugs, jacking pads or


blanking off plates shall become the property of the Purchaser.All
items of equipment shall be securely clamped against movement
to ensure safe transit from the manufacturer's facilities to the
specified destinations.

The Supplier shall advice the storage requirements for any plant and
equipment that may be delivered to the Purchaser's stores. The
Supplier shall be required to accept responsibility for the advice
given in so far as these arrangements may have a bearing on the
behavior of the equipment in subsequent service.

37.0 Hazardous substances

The Supplier shall submit safety data sheets for all hazardous
substances used with the equipment. The Supplier shall give an
assurance that there are no other substances classified as
hazardous in the equipment supplied. No oil shall be supplied or
used at any stage of manufacture or test without a certificate
acceptable to the Purchaser that it has a PCB content of less than 2
mg/ kg. The Supplier shall accept responsibility for the disposal
of such hazardous substances, should any be found.
The Supplier shall also be responsible for any injuries resulting
from hazardous substances due to non-compliance with these
requirements.

38.0 SUBMITTALS

38.1 Submittals required with the bid

The following shall be required with each copy of the bid :

o Completed technical data schedule;

o Descriptive literature giving full technical details of equipment


offered;

o Outline dimensions drawing for each major component, general


arrangement drawing showing component layout and general
schematic diagram;

o Type test certificates (short circuit withstand test and impulse test) of
the offered transformers conducted at CPRI/ or any NABL
Accredited laboratory without which tender will be out rightly
rejected.

o Sample routine test reports;

Detailed reference list of customers already using equipment offered


along with performance certificates of such equipment, during the
last 3 (three) years with particular emphasis on units of similar
design and rating;

o Details of manufacturer's quality assurance standards and


programme and ISO 9000 series or equivalent national certification;

o Deviations from this specification. Only deviations approved in


writing before award of contract shall be accepted;
o List of recommended spare parts and consumable items for five
year of operation with prices and spare parts catalogue with price list
for future requirements.
38.2 Submittals required after contract award

38.2.1 Programme

Five copies of the programme for production and testing

38.2.2 Technical Particulars

Within 30 days of contract award five bound folders with


records of the technical particulars relating to the equipment.
Each folder shall contain the following information:

¨ General description of the equipment and all components,


including brochures;

¨ Technical data schedule, with approved revision;

¨ Calculations to substantiate choice of electrical,


structural, mechanical component size/ ratings;

¨ Detailed dimension drawing for all components, general


arrangement drawing showing detailed component layout and
detailed schematic and wiring drawings for all components; along
with core-coil assembly drawings, showing details of core such as
grade, thickness, window height, leg centre, diameter, step width,
step thickness and details of windings such as I.D., O.D , thickness
, Conductor size, No. of turns, major and minor insulations, winding
height etc.

¨ Detailed loading drawing to enable the Purchaser to design


and construct foundations for the transformer;
¨ Statement drawing attention to all exposed points in the equipment
at which copper / aluminum or aluminum alloy parts are in
contact with or in close proximity to other metals and stating
clearly what protection is employed to prevent corrosion at each
point;
¨ Detailed installation and commissioning instructions;
¨ At the final hold point for Purchaser approval prior to delivery
of the equipment the following shall be submitted ;
¨ Inspection and test reports carried out in the manufacturer's works
¨ Operation and maintenance instructions as well as trouble shooting
charts.

38.2.3 Operation and Maintenance Instructions

A copy of installation and commissioning instructions and of


the operation and maintenance instructions and troubleshooting
charts shall be supplied with each transformer.

3 8 . 3 D r a wi n g s

38.3.1 Within 15 days of award of contract, the Supplier shall


submit 4 complete sets of drawings as detailed below describing
equipment in details. These drawings would be dul y a ppro ved by
the Pu rcha ser a ft er due securit iz at ion and approval w il l be
communicated within 15 days of receipt of these drawings. After
the drawings are approved and communicated to the supplier, he
would supply ten complete sets of final drawings.

38.3.2 All detail drawings submitted for approval shall be to


scale not less than 1:20. All important dimensions shall be given
and the material of which each part is to be constructed shall be
indicated on the drawings. All documents and drawings shall be
submitted in accordance with the provisions of this specification
and shall become the property of the Purchaser.

38.3.3 All drawings and calculations, submitted to the


Purchaser, shall be on international standard size paper, either
AO, A1, A2, A3 or A4. All such drawings and calculations shall be
provided with a contract title block, which shall include the
name of the Purchaser and shall be assigned an unique project
drawing number; the contract title block and project numbering
system shall be agreed with the Purchaser.

38.3.4 Script sizes and thickness of scripts and lines be selected so


that if reduced by two stages the alphanumeric characters and
lines are still perfectly legible so as to facilitate microfilming.

38.3.5 For presentation of design drawings and circuit


documents IEC Publication 617 or equivalent standards for
graphical symbols are to be followed. The drawing approval will be
communicated within 15 days from the receipt of drawings from
the Bidder and for any delay in furnishing the drawings, if delivery
period will be delayed, no extension of delivery time will be granted
due to this.

38.3.6 The following drawings for each item are to be submitted as


part of this Contract.

a. Outline dimensional drawings of transformers and accessories


b. Assembly drawings and weights of main component parts.
c. Transportation drawings showing dimensions and weights of
each package.
d. Drawings giving the weights for foundations each.
e. Drawing showing details such as clamping arrangements of
core, core assembly showing oil duct section of HT and LT coils
with conductor size showing insulation arrangements of windings
and their reinforcement to withstand short circuit stresses, in side
tank dimensions showing core assembly. Details of core and
windings, as enumerated at Cl. No. 33.2.2 of this part of
Specification shall be indicated in the above drawings.

f. Schematic diagram showing the flow of oil in the cooling system as


well as each limb and winding. Longitudinal and cross-
sectional views showing the duct sizes, cooling pipe etc. for
transformer/ heat exchanger, drawn to scale shall be furnished.

g. Large Scale drawings of high and low tension winding of the


transformers showing the nature and arrangements of insulation
and terminal connection.
h. Na me pla t e dra w in g sh ow i n g det a i l s a s per Cl . 23 o f Pa rt - 2
o f Techn ica l Specification.

Test reports

39.0 FASTENERS

39.1 All bolts, studs, screw threads, pipe threads, bolt heads and
nuts

shall comply with the appropriate Indian Standards for metric


threads, or the technical equivalent.

39.2 Bolts or studs shall not be less than 6 mm in diameter except


when used for small wiring terminals. All nuts and pins shall be
adequately locked.

39.3 Wherever possible, bolts shall be fitted in such a manner that


in the event of failure of locking resulting in the nuts working
loose and falling off, the bolt will remain in position.

39.4 All ferrous bolts, nuts and washers placed in outdoor positions

shall be of anti-corrosive materials except high tensile steel bolts


and spring washers which shall be electro galvanized to service
condition stated elsewhere in the Specification. Appropriate
precautions shall be taken to prevent electrolytic action between
dissimilar metals where bolts are used on external horizontal
surfaces and where water can collect, methods of preventing the
ingress of moisture to the threads shall be provided. Each bolt or
stud shall project at least one thread but not more than three
threads through the nut, except when otherwise approved for
terminal board studs or relay stems. If bolts nuts are placed so
that they are inaccessible by means of ordinary spanners, special
spanners shall be provided. The length of the screwed portion of the
bolts shall be such that no screw thread may form part of a shear
place between members. Taper washers shall be provided where
necessary. Protective washers of suitable material shall be
provided front and back on the securing screws.

40.0 LABELS
40.1 All apparatus shall be clearly labelled indicating, where
necessary, its purpose and service positions. The material of all
labels and plates, their dimensions, legend and the method of
printing shall be subject to approval of the Purchaser. The
surfaces of all labels and plates shall have a mat or satin finish to
avoid dazzle from reflected light. Colours shall be permanent and
free from fading. Labels mounted on black surfaces shall have
white lettering. Danger plates shall have white lettering on a red
background. All labels and plates for outdoor use shall be of in-
corrodible material. Where the use of enameled iron plates is
approved, the whole surface including the back and edges, shall be
properly covered and resistant to corrosion. They shall be engraved in
English. Name plates shall be white with black engraved lettering
and shall carry all the applicable information specified in the
applicable items of the Standards. No scratching, corrections or
changes will be allowed on name plates.

40.2 Name plates shall be provided of white background with


black engraved lettering carrying all the applicable information

specified in the standards and other details as required by the


Purchaser. The name plate inscription and the size and lettering shall
be submitted to the Purchaser for approval.

40.3 Mandatory Spare Parts

The suppliers shall provide the following mandatory spares for each of
transformer supplied.

1. H.V. & L.V. Bushing & Studs –Each 2 Nos

2. Bimetallic terminal connector for H.V & L.V. Bushings – Each 2


sets

41.0 PROFORMA FOR STAGE INSPECTION OF DISTRIBUTION

TRANSFORMERS

(A) GENERAL INFORMATION:

2. Order No and Date :


3. Rating —wise quantity offered :

4. Details of offer

(a) Rating
(b) Quantity
(c) Serial Numbers

5. Details of last stage inspected lot :

(a) Total quantity inspected


(b) Serial Numbers
(c) Date of stage inspection
(d) Quantity offered for final inspection of
6.

(A) Inspection of BIS ENERGY LEVEL-I/ Embossing / Punching


requirement: whether satisfies the Specification: deviation if any to be
mentioned:

(A) AVAILABILITY OF MATERIAL FOR OFFERED


QUANTITY: Details to be filled in

(B) POSITION OF MANUFACTURING STAGE OF THE


:
OFFERED QUANTITY

(a) Complete tanked assembly


(b) Core and coil assembly ready
(c) Core assembled
(d) Coils ready for assembly
(i) HV Coils
( i i ) LV Coils NOTE:

(i) A quantity if more than 100 no's shall not be entertained for stage
inspection

(ii) The stage inspection shall be carried out in case:-

(a) At Least 25% quantity offered has been tanked and


(b) Core coil assembly of further at least 30% of the quantity offered
has been completed.
(iii) Quantity offered for stage inspection should be offered for final
inspection within 15 days from the date of issuance of clearance for stage
inspection, otherwise stage inspection already cleared shall be liable for
cancellation.
3 Material used for top and
bottom yoke and
insulation
I Type and thickness of
I
material used: (mm)

Sl Particulars As Offered As observed Deviation and


. Remarks
N
(iv) INSPECTION
Painting OF
CORE
Channels
(i) Core material
(a)
Tie Rods
(1c) Bolts
(b)

Manufacturer's
7 Characteristic
Whether top yoke is
Certificate in
cut for LV
respect of grade of
connection
lamination used.
8 (Please
If yes, furnish test
at 7 above,
certificate)
whether
2 Remarks regardingis
Reinforcement
9 Size
Rusting of support
and
Channels provided
smoothness of core
for Core base and
Whether
bottom yoke (Single
laminations used for
Piece of channels
top and bottom
are only acceptable)
yoke are in one
(ii
10 Core
piece. Construction: of
Thickness
1
) No of steps provided
insulation
2 Dimension of Steps
between core base
Step No. 1 2 3 4 5 6 7 8 9 1 1 1
and support
0 1 2
11 Core
channellength (leg
As Offered
center to leg centre)
12 WWindow
mm height
13 Core height
14 T mm
Core weight only
As found
(without channel
Wetc.)
mm
(E) TINSPECTION
mm OF
3 WINDING
Core Dia (mm)
(I)
4 Winding
Total Crossmaterial
Section
1 area of core
Material used for
5
Effective cross
(a) HV Winding
Sectional area of
(b) LV Winding
core
2 Grade of material
6 Clamping
for
arrangement
Channel Size
(a) HV Winding
(i)
Bolt size and No
(b) LV Winding
Tie Rods
(ii)

3 Test certificate of
(iii)

manufacturer
(enclosed copy) for
winding material
of :
(a) HV
(b) LV
Diameter of wire
used for delta
3 formation (mm)
4 Diameter of coils in:
a LV Winding
Internal dia (mm)
(i)
Outer dia (mm)
b
(ii)
HV Winding
Internal dia (mm)
Outer dia (mm)
5 Current Density of
winding material
(a) HV
(b) LV
6 Whether neutral
formation on top

7 HV Coils/ Phase
a) Number
b) Turns/ coil
c) Total turns
8 LV Coils/ Phase
a)
Number
b)
Turns/coil
c)
Total turns
9 Method of HV Coil
Joints
10 Total weight of coils
of

(a) HV Winding (Kg)

(b) LV Winding (Kg)

F INSULATION
MATERIALS:
(I) MATERIAL
1 Craft paper
a) Make
b) Thickness (mm)
Test certificate of
c)

manufacturer
(enclosed copy)
2 Press Board
a) Make
Thickness (mm)
Test certificate of
manufacturer
(enclosed copy)

Between core and


LV
a)

b)
Spacers
c)
Interlayer
Between HV & LV
d)

winding

e)
Between phases
End insulation
G CLEARANCES
(I) Related to core and
winding

1 LV to Core (Radial)
2 Between HV and LV
(Radial)
3 (i) Phase to phase
between HV
(ii) Whether two
Nos Press Board
each of minimum 1
1 Constructional
mm ;thick provided
details:
to cover the tie rods
1) Rectangular
4 shape
Thickness of
2) Thickness of side
locking
wall (mm) spacers
between
3) ThicknessLV of coils
top
and
(mm) bottom place
5 Provision wedges
Axial
4) of
slopping
between HV topand cover
LV
towards
coils / phase HV
bushing
5) Tank internal
(Nos)
dimensions(mm)
6 No.Length
(a) of radial spacers
perBreadth
(b) phase between
HV coils
( c) Height
7 Size
(i) OnofLVduct between
side
LV and HV winding
(ii) On LV side
(mm)
(II) General
Between Detailscore-coil
assembly
1) and tank:
Inside painted by
(mm)
varnish/ oil
corrosion resistant
paint (please specify
which type of
coating done)
2) Gasket between
top cover and tank
(i) Material
(ii) Thickness(mm)

(iii) Joint over


1 Between
laps (mm) winding
and body
3) Reinforcement of
a) Tank lengthwise
welded angle
Tank size
(Specify
b) breadth
and
wise
No. of between
angle
2 Clearance
povided)
top cover on
and side
top
yoke upto 100 KVA
and between top
cover and top most
live part of tap
changing switch for
200 KVA and above.
H TANK

6) Provision of air
release plug
7) Provision of
galvanized GI Nuts
Bolts with 1 No Plain
and 1 No spring
washer

8) Deformation of
length wise side wall
of tank when subject
to:
a) Vaccume of (-) 0.7
Kg/sq cm for 30
minutes

b) Pressure of 0.8
Kg/sq cm for 30
minutes
(I) RADIATORS
1. Fin radiators of
1.25 mm thick sheet
a) Dimension of each
fin (L x B x T)

b) Fins per radiators

c) Total No. of
radiators
2. Verification of
manufacturer's test
certificate regarding
Heat dissipation
(excluding Top and
Bottom) in w/sq m
3. Verification of
position of radiator
with respect to
bushing
(J) CONSERVATOR
1. Dimensions ( L x
D) (in mm)
2. Volume (m3)
3.Inside dia of
Conservator tank
4. Whether
conservator outlet
pipe is projected
approx.20 mm inside
the conservator tank
5. Whether
arrangement made so
that oil does not fall
on the active parts

6. Whether die cast


metal oil level gauge
indicator having three
positions at ( -5° C,
30° C and 98 ° C is
provided.

7. Whether drain
plug and filling hole
with cover is provided

8. Inner side of the


conservator tank
painted with.

(K) BREATHER
1.Whether Die cast
Aluminum body
breather for silica
gel provided

2. Make

3. Capacity

(L) TERMINALS

1 Material whether of
Brass Rods/ Tinned
Copper

a) HV

b) LV

2 Size (dia in mm)

a) HV

b) LV

3 Method of Star

connection formed
on LV side of 6mm
thick (Should use
Al./ Cu. Flat
bolted/ brazed with
crimped lugs on
winding
alternatively for 63
and 100 KVA
rating brazed is
done covered with
tubular sleeve duly
crimped) Please
state dimensions of
Al/Cu flat or
tubular sleeve used
(mm)
4 Method of
Connection of LV of
winding to LV
bushing (end od
winding should be
crimped with
lugs(Al/Cu) and
bolted with bushing
stud)
5 Method of
Connection of HV
winding to HV
bushing (Copper
joint should be
done by using silver
brazing alloy and
for Aluminum,
brazing rod or with
tubular connector
crimped at three
spots).
6 Whether SRB P
tube/ insulated
paper used for
formation of Delta
on HV

7 Whether Empire
sleeves used on the
portion of HV
winding joining to
HV bushing

8 Whether neutral
formation is covered
with cotton

tape

(M) BUSHING

1 Whether HV
bushing mounted
on side walls.
2 Whether sheet
metal pocket used
for mounting
bushing (pipe are
not acceptable)

a) HV
b) LV
3 Whether
arrangement for
studs for fitting of
HV bushing are in
diamond shape ( so
that Arcing Horns
are placed

4. Position of
mounting of LV
5. Bushing
Clearance: (mm)
a) LV to Earth
b) HV to Earth
c) Between LV
Bushings
d) Between HV
Bushings
(N) TANK BASE
CHANNEL/ROLLER
S:

1 Size of
2 Whether channels
welded across the
length of the tank
3 Size and type of
roller (mm)
(O) OIL
1 Name of Supplier
2 Break down voltage
of oil:(KV)
i) Filled in tanked
Transformers
In storage tank (to
be tested by
Inspecting Officer).
3. Supplier's test
certificate (Enclosed)
(P) ENGRAVING /
PUNCHINGS

1. Engaraving of Sl.
No and name of
firm
i) On bottom of
clamping channel of
core-coil assembly

ii) On side wall


and top cover of
tank along with
date of dispatch. /
Guarantee Period

i) 3 Star Level:
Whether contains 3
Star Level with style
prescribed by the
B.E.E.

(Q) i) MS plate of size 125 x


125 mm welded on width
side of stiffener

ii) Following details


engraved (as per approved
GTP)

(a) Serial Number


(b) Name of Firm
( c) Order No. and Date

(d) Rating
(e) Name of Inspecting
Officer

(f) Designation
(g) Date of dispatch
( R) NAME PLATE DETAILS

Whether Name Plate is as


per approved drawing
(S) Colour of Transformer

1. Tank body with light


blue colour
2. Conservator with white
colour
(T) CHECKING OF TESTING
FACILITIES
(Calibration certificate
also to be checked for its
validity)

TESTS
1. No Load Current
2. No Load Loss
3. % Impedance
4. Load Losses
5. Insulation Resistance
Test
6. Vector Group Test (phase
relationship)
7. Ratio and Polarity test
relationship
8. Transformer oil Test
(Break down Voltage)
9. Magnetic Balance
1. Measurement of
winding resistance (HV
and LV both)
2. Induced over voltage
withstand test ( Double
voltage and Double
frequency)

12. Separate source power


frequency withstand test
at 28 KV for HV and 3 KV
for LV (one minute)

13. Air Pressure/ Oil


leakage Test
14. Vacuum Test

15. Unbalanced current


test
16. Temperature rise(Heat
Run) test

(U) We have specifically


checked the following and
found the same as per
G.T.P./ deviations
observed as mentioned
against each.
i) Rustlessness of CRGO
laminations used
ii) Core Steps
iii) Core Area
iv) Core Weight
v) Winding cross section
area

a) LV
b) HV
vi) Weight of windings

vii) Clearance between


winding and wall of tank
(mm)

a) Length-wise
b) Breadth- wise
viii) Clearance between top
of yoke top most live part
of tap changer to tank
cover

ix) Details of Neutral


formation
x) Connections to
bushings
a) LV
b) HV
xi) Slope of tank top
xii) Position of mounting of
bushings
COMPANY INSPECTING OFFICER FIRMS

REPRESENTATIVE
DATE OF INSPECTION
APPENDIX-II

QUANTITY & DELIVERY SCHEDULE.

Description of the Quantity Delivery Schedule Destination.


Equipment

9 Months from the Any stores/ sites


date of the placement within Odisha
of the Purchase order. State, same will be
25 KVA DTR 2250 indicated in the
purchase order/
release order,

6 Months from the Any stores/ sites


date of the placement within Odisha
of the Purchase order. State, same will be
63 KVA DTR 197 indicated in the
purchase order/
release order,

9 Months from the Any stores/ sites


date of the placement within Odisha
of the Purchase order. State, same will be
100 KVA DTR 2055 indicated in the
purchase order/
release order,

6 Months from the Any stores/ sites


date of the placement within Odisha
of the Purchase order. State, same will be
250 KVA DTR 1160 indicated in the
purchase order/
release order,

6 Months from the Any stores/ sites


date of the placement within Odisha
of the Purchase order. State, same will be
500 KVA DTR 653 indicated in the
purchase order/
release order,

12 Months from the Any stores/ sites


date of the placement within Odisha
of the Purchase order. State, same will be
5 MVA PTR 156 indicated in the
purchase order/
release order,
12 Months from the Any stores/ sites
date of the placement within Odisha
of the Purchase order. State, same will be
8 MVA PTR 136 indicated in the
purchase order/
release order

Signature of the Tenderer

with seal and date


TECHINICAL SPECIFICATIONS

FOR 5.00 / 8.00 MVA, 33/11KV ONAN

POWER TRANSFORMERS
TABLE OF CONTENTS

OF

POWER TRANSFORMERS

NO DESCRIPTION
PAGE NO.

1.0 Scope 3
2.0 Technical requirements of power transformer 4

3.0 System conditions 8

4.0 Codes & standards 9

5.0 General constructional features 11

6.0 Detailed description 15

7.0 Inspection and testing 37

8.0 Inspection 38

9.0 Performance 44

10.0 Losses 45

11.0 Spare parts 45

12.0 Instruction Manuals 45

13.0 Completeness of Equipment 46

14.0 Technical Data Requirement 46


TECHINICAL SPECIFICATION FOR 33/11KV ONAN POWER TRANSFORMERS

1. SCOPE

1.1This Specification provides for design, manufacture, assembly, stage inspection,


final inspection and testing before despatch, packing and delivery at destination
Sub-station by road transport, transit insurance, unloading at site of 5.00 /
8.00 MVA, 33/11kV Power Transformers, complete with all fittings,
accessories, associated equipment, Spares, 10% extra Transformer Oil, required
for its satisfactory operation.

The material offered shall have been successfully Type Tested during last five
years on the date of bid opening. The Type Test reports shall be submitted
along with the bid.

The Transformer shall be of outdoor type with tap changers as detailed below.

5.00 MVA - OFF Load Tap Changer

8.00 MVA - ON Load In Tank/Flange Mounted typeTap Changer


(with RTCC Panel)

1.2 The core shall be constructed from high grade, non-aging Cold Rolled
Grain Oriented (CRGO) Silicon Steel laminations conforming to HIB grade
with lamination thickness not more than 0.23mm to 0.27mm or better
quoted grade Core. The maximum flux density in any part of the core and yoke
at normal voltage and frequency shall not be more than 1.5 Tesla. The Bidder
shall provide saturation curve of the core material, proposed to be used.
Laminations of different grade(s) and different thickness (s) are not
allowed to be used in any manner or under any circumstances.

1.3 The Power Transformer shall conform in all respects to highest standards of
engineering, design, workmanship based on this specification and the latest
revisions of relevant standards at the time of offer. OPTCL shall have the power
to reject any work or material, which, in his judgment, is not in full accordance
therewith. The Transformer(s) offered, shall be complete with all components,
necessary for their effective and trouble free operation. Such components shall
be deemed to be within the scope of supply, irrespective of whether those are
specifically brought out in this specification and / or in the commercial order or
not.

OPTCL reserves the right to reject the transformer(s)-

i) if on testing the No-load and load- losses exceed the stipulated values
as per this Technical Specification

ii) if the temperature rise in oil and / or winding exceeds the value as per
this Technical Specification
iii) if impedance value differs from the guaranteed value including
tolerance as per this specification
iv) On Inspection and testing, if any of the technical data does not
comply to this specification, bid offer and approved drawings etc.

1.4 The offered rating transformer should have been tested for ‘Short Circuit
withstand capability test’ and ‘Impulse test’ in an NABL accredited Government
Laboratory as per relevant IS/IEC and the Type Test certificates in complete shape
shall be accompanied with the bid offer.

2. TECHNICAL REQUIREMENTS OF POWER TRANSFORMER

1 Rated MVA of Transformer (ONAN | 5.00MVA | 8.00MVA


rating)

2 No. of Phases 3

3 Type of Installation Outdoor

4 Frequency 50 Hz (- 5% to +3%)

5 Cooling medium Insulating Oil (ONAN)

6 Type of mounting On Wheels, Mounted on rails.

7 Rated voltage

a) High Voltage Winding 33 kV

b) Low Voltage Winding 11 kV


8 Highest continuous system Voltage

a) Maximum system Voltage ratio (HV / 36 kV/ 12 kV


LV )

b) Rated Voltage ratio (HV / LV ) 33 kV/ 11 kV

9 No. of windings Two winding Transformers

10 Type of cooling ONAN (Oil natural & Air


natural)

11 MVA Rating corresponding to ONAN 100%


cooling system

12 Method of connection:

HV: Delta

LV: Star

13 Connection symbol Dyn 11

14 System earthing Neutral of LV side to be


solidly earthed.

15 Percentage impedance voltage on % Impedance for


Normal tap and MVA base at 750C
corresponding to HV/ LV rating and 5 MVA - 7.15%
applicable tolerances : 8 MVA - 8.35%

(Tolerance +10%)

(No negative tolerance will be

allowed)

16 Intended regular cyclic overloading of As per IEC –76-1, Clause 4.2


windings

17 a) Anticipated unbalanced loading Around 10%

b) Anticipated continuous loading of


110 % of rated current
windings (HV / LV)

18 Type of tap changer On-Load In-tank or flange


mounted Type tap changer for
8 MVA and OFF load in 5 MVA
transformer
Range of taping + 5% to – 15% in 8 equal
steps of 2.5% each on HV
winding, 9 tap positions. Tap
No 3 wil be the Principal tap
position.

19 Neutral terminal to be brought out On LV side only

20 Over Voltage operating 112.5 % of rated voltage


capability and duration (continuous)

21 Maximum Flux Density in any part of 1.5 Tesla


the core and yoke at rated MVA, rated
voltage i.e 33kV / 11kV and system
frequency of 50 Hz

22 Insulation levels for windings :- 33 kV 11 kV

a) 1.2 / 50 microsecond wave shape 170 95


Impulse

withstand (KVP)

b) Power frequency voltage withstand 70 28

(KVrms)

23 Type of winding insulation

a) HV winding Uniform

b) LV winding Uniform

24 Withstand time for three phase short


As per IS
circuit

25 Noise level at rated voltage and As per NEMA Publication


frequency No. TR-1.

26 Permissible Maximum
Temperature Rise over ambient
temperature of 500 C

a) Of top oil measured by thermometer. 350 C

b) Of winding measured by resistance. 400 C

c)Hot Spot Temperature rise 540 C

27 Minimum clearances in air (mm) :- Phase to Phase Phase to


ground

a) HV 400 320

b) LV 280 140

28 Terminals :-

a) HV winding line end 36kV oil filled communicating


type porcelain bushings
( Antifog type)

b) LV winding 12kV porcelain type of


bushings ( Antifog type)

29 Insulation level of Bushing :- HV LV

a) Lightning Impulse withstand (KVP) 170 95

b) 1 Minute Power Frequency withstand 70 28

voltage (KV-rms)

c) Creepage distance (mm) (minimum) 900 300

30 Material of HV & LV Conductor Electrolytic Copper

31 Maximum current density for HV 2.4 A/ mm2


and LV winding for rated current at
normal tap

32 Polarisation Index i.e ratio of Megger Shall be greater than or equal


values at 600 sec. to 60 sec for HV to to 1.5, but less than or equal
earth, L.V to earth and HV to LV to ‘5’.

33 Core Assembly Boltless type

34 Temperature Indicator

a) Oil One number

b) Winding One number

35 Maximum permissible no load loss at 5.0MVA- 3.6. KW (Maximum)


rated voltage and rated frequency.
8.0MVA- 4.5KW (Maximum)

36 Maximum permissible load loss at rated 5.0MVA- 21.0. KW (Maximum)


current,at normal tap and at 750 C
8.0MVA- 38.0 KW (Maximum)

37 Paper Covering thickness of HV Winding 0.6 mm( minimum )


Conductor

38 Paper Covering thickness of LV Winding 0.5 mm( minimum )


Conductor

39 Clearances:-

a) Gap between HV Coil to the inside of 65 mm( minimum )


the tank on the longer side

b) Gap between HV Coil to the inside of 65 mm( minimum )


the tank on the width side (LV Side)

c) Gap between HV Coil to the inside of 115 mm( minimum )


the tank on the width side (HV Side to

accommodate delta and tapping leads )

d) Gap between Core yoke to tank 55 mm( minimum )


bottom

e) Yoke insulation at top and bottom 130 mm( minimum )

f) Phase to Phase clearance between HV 20 mm( minimum )

Limbs

g) Radial Clearance between LV and HV 20 mm( minimum )

Coil

h) Radial Clearance between Core to LV 12.5 mm( minimum )


Coil

40 The difference of Ampere Turns at each location shall not be more than 5
% at all percentages of tappings

41 Winding to winding clearance should have minimum 20% of sum of


pressboard Cylinder/Barrier.

42 Tap changing gear:-

(i) Type- In Tank,High Speed Resistor


Type

(ii) Provided on HV Side

(iii) Tap range -15% to +5%


(iv) Tap Step 2.5% of 33kV ( 8 equal steps)

(v) Minimum Rated current For 5 MVA-150A & 8 MVA-200A

(vi) Minimum Rated short circuit current 3KA

(vii) Automatic control required YES

(viii) Remote Control Panel required YES

(ix) Marshalling kiosk required YES

43. Minimum Air core reactance of HV winding 20%

44. Type of oil preservation Air-cell type

2.1 MARSHALLING BOX

A metal enclosed, weather, vermin and dust proof marshalling box fitted with
required glands, locks, glass door, terminal Board, heater with switch,
illumination lamp with switch etc. shall be provided with each transformer to
accommodate temperature indicators, terminal blocks etc. It shall have
degree of protection of IP 55 or better as per IS: 2147.

2.2 PERFORMANCE

i) Transformer shall be capable of withstanding for two seconds without


damage to any external short circuit.

ii) The maximum flux density in any part of the core and yoke at rated MVA,
Voltage and frequency, shall be 1.5 Tesla (maximum).

i) Transformer shall under exceptional circumstances due to sudden


disconnection of the load, be capable of operating at the voltage
approximately 25% above normal rated voltage for a period of not
exceeding one minute and 40% above normal for a period of 5
seconds.

iv) The transformer may be operated continuously without danger on


any particular tapping at the rated MVA ± 12.5% of the voltage
corresponding to the tapping.
v) The thermal ability to withstand short circuit shall be demonstrated
by calculation.
iv) Transformer shall be capable of withstanding thermal and
mechanical stress caused by any symmetrical and asymmetrical
faults on any winding. The Bidder shall submit the necessary Short
Circuit Force Calculation with the offer.

2.3 DRAWINGS/ DOCUMENTS INCORPORATING THE FOLLOWING


PARTICULARS SHALL BE SUBMITTED WITH THE BID

a) General outline drawing showing shipping dimensions and overall


dimensions, net weights and shipping weights, quality of insulating oil,
spacing of wheels in either direction of motion, location of coolers,
marshalling box and tap changers etc.
b) Assembly drawings of core, windings etc. and weights of main components
/ parts.
c) Height of center line on HV and LV connectors of transformers from the
rail top level.
d) Dimensions of the largest part to be transported.
e) GA drawings / details of various types of bushing
f) Tap changing and Name Plate diagram
g) Type test certificates of the quoted rating transformer.
h) Illustrative & descriptive literature of the Transformer.
i) The drawings and Type Test certificates of Tap Changer
j) Maintenance and Operating Instructions.
k) The Type Test certificates in complete shape for ‘Lightning Impulse’ and
‘Short Circuit’ Test and Temperature Rise Test

2.4 MISCELLANEOUS

i) Padlocks along with duplicate keys as asked for various valves,


marshalling box etc. shall be supplied by the contractor, wherever
locking arrangement is provided.

ii) Foundation bolts for wheel locking devices of Transformer shall be


supplied by the Contractor.

2.5 DELIVERY
The full quantity of the equipment shall be delivered as per the delivery
schedule appended to this specification.

2.6 SCHEDULES

Any Schedule, if any, annexed to the specification shall be duly filled


by the bidder separately.

2.7 NAME PLATE

Transformer rating plate shall contain the information as given in clause 15


of IS-2026 (part-I). The details on rating plate shall be finalized during the
detailed engineering. Further, each transformer shall have inscription of
DISTCOM’s name which will be intimated by OPTCL to the firm before hand.

The name plate shall also include :

(i) The short circuit rating


(ii) Measured no load current and no load losses at rated voltage and
rated frequency
(iii) Measured load losses at 750 C ( Normal Tap only )
(iv) D.C resistance of each winding at 750 C.

3.0 SYSTEM CONDITIONS

The equipment shall be suitable for installation in supply systems of the following

characteristics.

33 kV 11 kV

1 Frequency 50 Hz (- 5% to 50 Hz (- 5% to
+3%) +3%)

2 Nominal system voltages 33 kV 11 kV

3 Maximum system voltages 36.3 kV 12 kV

4 Nominal short circuit level AS per IS:2026

Insulation levels
5 170 kV (peak) 95kV (peak)
(1.2/50 µ sec impulse
withstand voltage)

6 Power frequency with one 70 kV(rms) 28 kV(rms)


minute withstand (wet &
dry) voltage

7 Neutral earthing - Solidly earthed


arrangements

4.0 CODES & STANDARDS

4.1 The design, material, fabrication, manufacture, inspection, testing before


dispatch and performance of power transformers at site shall comply with all
currently applicable statutory regulations and safety codes in the locality where
the equipment will be installed. The equipment shall also conform to the latest
applicable standards and codes of practice. Nothing in this specification shall be
construed to relieve the Contractor of this responsibility.

4.2 The equipment and materials covered by this specification shall conform to the
latest applicable provision of the following standards.

1 IS: 5 Colour for ready mixed paints &


Enamels

2 IS: 325 Three Phase Induction Motors

3 IS: 335 New insulating oil for transformers,


switch gears

4 IS: 1271 Classification of insulating materials


for electrical machinery and
apparatus in relation to their stability
in services

5 IS: 2026(Part I to IV Power Transformer

6 IS: 2071 Method of high voltage testing


7 IS: 2099 High voltage porcelain bushings

8 IS: 2147 Degree of protection

9 IS: 2705 Current Transformers

10 IS: 3202 Code of practice for climate proofing of


electrical equipment

11 IS: 3347 Dimensions for porcelain Transformer


Bushings

12 IS: 3637 Gas operated relays

13 IS: 3639 Fittings and accessories for power


Transformers

14 IS: 5561 Electric Power Connectors

15 IS: 6600/BS:CP’ 10:0 Guide for loading of oil immersed


Transformers

16 IS: 10028 Code of practice for selection,


installation and maintenance of
transformers, Part I. II and III

17 IS 1002/1981 (Part – III) Maintance of Transformer

18 C.B.I.P. Publication Manual on Transformers

If the standard is not quoted for any item, it shall be presumed that the
latest version of Indian Standard shall be applicable to that item.

The equipment complying other internationally accepted standards, may


also be considered if they ensure performance superior to the Indian
Standards.

4.3 DRAWINGS

a) The contractor shall furnish, within fifteen days after issuing of Letter of
Award. Six copies each of the following drawings/documents
incorporating the transformer rating for approval.

i) Detailed overall general arrangement drawing showing front and side


elevations and plan of the transformer and all accessories including
radiators and external features with details of dimensions, spacing of
wheels in either direction of motion, net weights and shipping weights,
crane lift for un-tanking, size of lugs and eyes, bushing lifting
dimensions, clearances between HV and L.V terminals and ground,
quantity of insulating oil etc.

i) Assembly drawings of core and winging and weights of main


components / parts. In the Core-Coil assembly drawing , the following
dimensions should be clearly mentioned:-

Core:- Window Height, Leg Centre, Core diameter, Grade & thickness of
Core material, gross & net Core Cross-Sectional area, Watt loss per kg at
the quoted flux density, VA per kg at the quoted flux density.

HV & LV Windings: - Conductor Size (both bare and insulated), Inside


and Outside diameters, axial heights, type of windings, No. of spacers
with sizes, No. of discs, No. of turns/disc, gap between discs ,clearance
from top and bottom yoke, gap between windings, Size of the conductor
for delta connection etc.

ii) Foundation plan showing loading on each wheel land jacking points
with respect to Centre line of transformer.
iii) GA drawings details of bushing and terminal connectors.

v) Name plate drawing with terminal marking and connection diagrams.


v) Wheel locking arrangement drawing.
vi) Transportation dimensions drawings.
v) Magnetization characteristic curves of PS class neutral and phase
side current transformers, if applicable.

vi) Interconnection diagrams.


vii) Over fluxing withstand time characteristic of transformer.
vii) GA drawing of marshalling box.
viii) Control scheme/wiring diagram of marshalling box.
v) Technical leaflets of major components and fittings.
xiiv) As built drawings of schematics, wiring diagram etc.

xv) Setting of oil temperature indicator, winding temperature indicator.


xv) Completed technical data sheets.
xvi) Detail Drawings,Type Test Certificates including write-up of On-Load
tap changing gear and its required accessories/equipment ,wiring diagrams
etc. as per this specification.
xvii) HV conductor bushing.
xviii) Bushing Assembly.
xix) Bi-metallic connector suitable for connection to 100 sq. mm up
to 232 Sq.mm AAAC Conductor.

xx) GA of LV cable Box.


xxi) Radiator type assembly
xxii) Specific loss(watt/Kg. vs.Flux density),VA/Kg.vs.Flux density
&B-H Graph for the offered HIB or better core material,to be used for the
offered transformer
b) All drawings, documents, technical data sheets and test certificates,
results and calculations shall be furnished.

c) Ampere –Turns Calculation at various locations and tapping


positions of both LV and HV windings.

4.4 Any approval given to the detailed drawings by the OPTCL shall not relieve the
contractor of the responsibility for correctness of the drawing and in the
manufacture of the equipment. The approval given by the OPTCL shall be
general with overall responsibility with contractor.

5.0 GENERAL CONSTRUCTIONAL FEATURES

5.1 All material used shall be of best quality and of the class most suitable for
working under the conditions specified and shall withstand the variations of
temperature and atmospheric conditions without distortion or deterioration or
the setting up of undue stresses which may impair suitability of the various
parts for the work which they have to perform.

5.2 Similar parts particularly removable ones shall be interchangeable.

5.3 Pipes and pipe fittings, screws, studs, nuts and bolts used for external
Connections shall be as per the relevant standards. Steel bolts and nuts
exposed to atmosphere shall be galvanized.

5.4 Nuts, bolts and pins used inside the transformers and tap changer
compartments shall be provided with lock washer or locknuts.

5.5 Exposed parts shall not have pockets where water can collect.

5.6 Internal design of transformer shall ensure that air is not trapped in any
location.
5.7 Material in contact with oil shall be such as not to contribute to the formation
of acid in oil. Surface in contact with oil shall not be galvanized or cadmium
plated.

5.8 Labels, indelibly marked, shall be provided for all identifiable accessories like
Relays, switches current transformers etc. All label plates shall be of in
corrodible material.

5.9 All internal connections and fastenings shall be capable of operating under
overloads and over-excitation, allowed as per specified stands without injury.

5.10 Transformer and accessories shall be designed to facilitate proper operation,


inspection, maintenance and repairs.

5.11 No patching, plugging, shimming or other such means of overcoming defects,


discrepancies or errors will be accepted.

5.12 Schematic Drawing of the wiring, including external cables shall be put under
the prospane sheet on the inside door of the transformer marshalling box.

5.13 Painting

Particular attention shall be paid to the following:

a) Proper storage to avoid exposure as well as extremes of temperature.


b) Surface preparation prior to painting.
c) Mixing and thinning
d) Application of paints and the recommended limit on time intervals between
coats.
e) Shelf life for storage.

5.13.1.1 All paints, when applied in normal full coat, shall be free from runs, sags,
wrinkles, patchiness, brush marks or other defects.

5.13.1.2 All primers shall be well marked into the surface, particularly in areas
where painting is evident, and the first priming coat shall be applied as
soon as possible after cleaning. The paint shall be applied by airless spray
according to the manufacturer’s recommendations. However, wherever
airless spray is not possible, conventional spray be used with prior
approval of OPTCL.

5.13.1.3 The supplier shall, prior to painting protect nameplates, lettering gauges,
sight glasses, light fittings and similar such items.

5.13.2 Cleaning and Surface Preparation


5.13.2.1 After all machining, forming and welding has been completed, all steel
work surfaces shall be thoroughly cleaned of rust, scale, welding slag or
spatter and other contamination prior to any painting.

5.13.2.2 Steel surfaces shall be prepared by Sand/Shot blast cleaning and


Chemical cleaning by Seven tank process including Phosphating to the
appropriate quality.The surface shall be treated by phosphating and dried
in accordance with IS 6005(Code of practices for phosphating of Iron and
Steel). Immediately after Phosphating, surface shall be given two coats of
high quality Zinc Chromate Primer.

5.13.2.3 The pressure and Volume of the compressed air supply for the blast
cleaning shall meet the work requirements and shall be sufficiently free
from all water contamination prior to any painting.

5.13.2.4 Chipping, scraping and steel wire brushing using manual or power driven
tools cannot remove firmly adherent mill-scale and shall only be used where
blast cleaning is impractical.

5.13.3 Protective Coating

As soon as all items have been cleaned and within four hours of the
subsequent drying, they shall be given suitable anticorrosion protection.

5.13.4 Paint Material

Followings are the type of paints that may be suitably used for the items to
be painted at shop and supply of matching paint to site:

i) Heat resistant paint (Hot oil proof) for inside surface.

i) For external surfaces one coat of Thermo Setting Paint or 2 coats of


Zinc chromate followed by 2 coats of POLYURETHANE . The color of the
finishing coats shall be dark admiral grey conforming to No.632 or IS
5:1961.

5.13.5 Painting Procedure

5.13.5.1 Al painting shall be carried out in conformity with both specifications and
with the paint manufacture’s recommendations. All paints in any one
particular system. Whether shop or site applied, shall originate from one
paint manufacturer.

5.13.5.2 Particular attention shall be paid to the manufacture’s instructions on


storage, mixing, thinning and pot life. The paint shall only be applied in the
manner detailed by the manufacturer e.g. brush, roller, conventional or
airless spray and shall be applied under the manufacturer’s recommended
conditions. Minimum and maximum time intervals between coats shall be
closely followed.

5.13.5.3 All prepared steel surfaces should be primed before visible re-rusting
occurs or within 4 hours whichever is sooner. Chemical treated steel
surfaces shall be primed as soon as the surface is dry and while the
surface is warm.

5.13.5.4 Where the quality of film is impaired by excess film thickness,(wrinkling,


mud cracking or general softness) the supplier shall remove the
unsatisfactory paint coatings and apply another. As a general rule, dry film
thickness should not exceed the specified minimum dry film thickness by
more than 25% . In all instances, where two or more coats of the same
paints are specifies, such coatings may or may not be of contrasting colors.

5.13.5.5 Paint applied to items that are not be painted, shall be removed at
supplier’s expense, leaving the surface clean, un-stained and undamaged.

5.13.6 Damages to Paints Work

5.13.6.1 Any damage occurring to any part of the painting scheme shall be made
good to the same standard of corrosion protection and appearance as that
originally employed.

5.13.6.2 Any damaged paint work shall be made as follows:

a) The damaged area, together with an area extending 25mm around its
boundary, shall be cleaned down to bare metal.

b) A priming coat shall immediately applied, followed by a full paint finish


equal to that originally applied and extending 50mm around the
perimeter of the originally damaged.

5.13.6.3 The repainted surface shall present a smooth surface. This shall be
obtained by carefully chamfering the paint edges before & after priming.

5.13.7 Dry Film Thickness

5.13.7.1 To the maximum extent practicable, the coats shall be applied as a


continuous film of uniform thickness and free of pores. Over-spray, skips,
runs, sags and drips should be avoided. The different coats may or may not
be same color.

5.13.7.2 Each coat of paint shall allowed to hardened before the next is applied as
per manufacture’s recommendations.

5.13.7.3 Particular attention must be paid to full film thickness at edges.


5.13.7.4 The requirement for the dry film thickness (DFT) of paint and the material
to be used shall be as given below:

Sl. Paint Type Area to be No of Total Dry film


No painted Coats thickness(Min)

1. Liquid Paint

a) Zinc Out side 02 45 micron


Chromate(Primer)

b) POLYURETHANE

(Finish Coat) Out side 02 35 micron


c) Hot Oil paint inside 01 35 micron

6.0 DETAILED DESCRIPTION

6.1 Tank

6.1.1 The Transformer tank and cover shall be fabricated from high grade low carbon
plate steel of tested quality. The tank shall be of welded construction. The
transformer Tank shall be of rectangular Shape design(No elliptical shape
design is allowed).

6.1.2 Tank shall be designed to permit lifting by crane or jacks of the complete
transformer assembly filed with oil. Suitable lugs and bossed shall be provided
for this purpose.

6.1.3 All beams, flanges, lifting lugs, braces and permanent parts attached to the
tank shall be welded and where practicable, they shall be double welded.

6.1.4 The main tank body of the transformer, excluding tap changing compartments
and radiators ,shall be capable of withstanding pressure of 760mm of Hg. The
side Tank wall shall be of 8mm(minimum) for 5MVA & 8MVA . The bottom
and Top Plate of the Tank shall be of of 8mm thickness (minimum) for
3.15MVA,10mm(minimum) for 5MVA &12mm.(minimum) for 8MVA.

6.1.5 Inspection hole(s) with welded flange(s) and bolted cover(s) shall be provided on
the tank cover. The inspection hole(s) shall be of sufficient size to afford easy
access to the lower ends of the bushings, terminals etc.

6.1.6 Gaskets of nitrile rubber or equivalent shall be used to ensure perfect oil
tightness. All gaskets shall be closed design (without open ends) and shall be of
one piece only. Rubber gaskets used for flange type connections of the various oil
compartments, shall be laid in grooves or in groove-equivalent sections on bolt
sides of the gasket, throughout their total length. Care shall be taken to secure
uniformly distributed mechanical strength over the gaskets and retains
throughout the total length. Gaskets of neoprene and / or any kind of
impregnated / bonded core or cork only which can easily be damaged by over-
pressing are not acceptable. Use of hemp as gasket material is also not
acceptable.

6.1.7 Suitable guides shall be provided for positioning the various parts during
assemble or dismantling. Adequate space shall be provided between the cores
and windings and the bottom of the tank for collection of any sediment.

6.2 Tank Cover

The transformer top shall be provided with a detachable tank cover with bolted
flanged gasket joint. Lifting lugs shall be provided for removing the cover. The
surface of the cover shall be suitable sloped so that it does not retain rain water.

6.3 UNDER CARRIAGE

6.3.1 The transformer tank shall be supported on steel structure with detachable plain
rollers completely filled with oil. Suitable channels for movement of roller with
transformer shall be space accordingly, rollers wheels shall be provided with
suitable rollers bearings, which will resist rust and corrosion and shall be
equipped with fittings for lubrication. It shall be possible to swivel the wheels in
two directions, at right angle to or parallel to the main axis of the transformers.

6.4 CORE

6.4.1 Stage inspection for core construction shall be carried out by the Purchaser
through OPTCL / DISCOM.

6.4.2 Each lamination shall be insulated such that it will not deteriorate due to
mechanical pressure and the action of hot transformer oil.

6.4.3 The core shall be constructed from high grade, non-aging Cold Rolled Grain

Oriented (CRGO) silicon steel laminations conforming to HIB grade or better


grade with lamination thickness not more than 0.23mm to 0.27mm. The
maximum flux density in any part of the cores and yoke at normal voltage and
frequency shall not be more than 1.5 Tesla. The Bidder shall provide saturation
curve of the core material, proposed to be used. Laminations of different grade(s)
and different thickness (s) are not allowed to be used in any manner or under
any circumstances.
6.4.4 The bidder should offer the core for inspection starting from the destination port
to enable OPTCL for deputing inspecting officers for detail verification as given
below and approval by the OPTCL during the manufacturing stage. Bidder’s call
notice for the purpose should be accompanied with the following documents as
applicable as a proof towards use of prime core material:

The core coils, if found suitable, are to be sealed with proper seals which shall
be opened in presence of the inspecting officers during core- cutting at the
manufacturer’s or it’s sub-vendor’s premises as per approved design drawing.

a) Contract Order No. & Date.

b) Invoice of the supplier


a) Mills test certificate

c) Packing list
d) Bill of lading

e) Bill of entry certificate to customs

Core material shall be directly procured either from the manufacturer or


through their accredited marketing organization of repute, but not through any
agent.

6.4.4 (B) For Transformer Manufacturer (TM), who has in-house core-cutting
facility, the packed core coils shall be verified at their works as per
followings along with witnessing of core- cutting.

a) Purchase Order No. & Date ;


b) No. of packed coils with Package Nos.
c) Gross Weight.
d) Net Weight :
e) Port of loading.
f) Port of Discharge ;
g) Name of the Ocean Vessel :
h) Grade & Thickness of Core Material :
i) Any other information as mentioned on the body of packed coils.

6.4.4 ( C ) For those bidders, who have no in-house core-cutting facility, they should
mention the names of at least three sub-vendors to whom they intend to
assign their core-cutting. Such sub-vendors should have been approved by
other Electricity Board / Electrical Utilities and accredited by some
internationally recognized certification body like ISO- 9000 etc. to ensure
that a minimum quality parameters & tolerance are maintained. The
experience, the details of core-cutting facilities finishing & testing facilities
etc. as available which such sub-vendors should be clearly out-lined in the
bid

6.4.4 (D) On award of Contract the TM is to assign the core-cutting to such sub-
vendors for which approval is to be given by the OPTCL.

6.4.5 The laminations shall be free of all burrs and sharp projections. Each sheet
shall have an insulting coating resistant to the action of hot oil.

6.4.6 The insulation structure for the core to bolts and core to clamp plates, shall be
such as to withstand 2000 V DC voltage for one minute.

6.4.7 The completed core and coil shall be so assembled that the axis and the plane of
the outer surface of the core assemble shall not deviate from the vertical plane by
more than 25mm.

6.4.8 All steel sections used for supporting the core shall be thoroughly shot or sand
blasted, after cutting, drilling and welding.

6.4.9 The finally assembled core with all the clamping structures shall be free from
deformation and shall not vibrate during operation.

6.4.10 The core clamping structure shall be designed to minimize eddy current loss.

6.4.11 The framework and clamping arrangements shall be securely earthed.

6.4.12 The core shall be carefully assembled and rigidly clamped to ensure adequate
mechanical strength.

6.4.13 Oil ducts shall be provided, where necessary, to ensure adequate cooling inside
the core. The welding structure and major insulation shall not obstruct the free
flow of oil through such ducts.

6.4.14The design of magnetic circuit shall be such as to avoid static discharges,

development of short circuit paths within itself or to the earth clamping


structure and production of flux component at right angle to the plane of the
lamination, which may cause local heating. The supporting framework of the
cores shall be so designed as to avoid the presence of pockets, which would
prevent complete emptying of the tank through the drain valve or cause
trapping of air during filling.

6.4.15 The construction is to be of boltless core type. The core shall be provided with
lugs suitable for lifting the complete core and coil assembly. The core and coil
assemble shall be so fixed in the tank that shifting will not occur during
transport or short circuits.

6.4.16 The temperature gradient between core & surrounding oil shall be maintained

less than 20 deg. Centigrade. The manufacturer shall demonstrate this either
through test ( procedure to be mutually agreed) or by calculation.

6.5 INTERNAL EARTHING

6.5.1 All internal metal parts of the transformer, with the exception of individual
laminations and their individual clamping plates shall be earthed.

6.5.2 The top clamping structure shall be connected to the tank by a copper strap.
The bottom clamping structure shall be earthed by one or more the following
methods:

a) By connection through vertical tie-rods to the top structure.


b) By direct metal to metal contact with the tank base.

c) By a connection to the structure on the same side of the core as


the main earth connection to the tank.

6.5.3The magnetic circuit shall be connected to the clamping structure at one point
only and this shall be brought out of the top cover of the transformer tank
through a suitably rated insulator. A disconnecting link shall be provided on
transformer tank to facilitate disconnections from ground for IR measurement
purpose.

6.5.4Coil clamping rings of metal at earth potential shall be connected to the adjacent
core clamping structure on the same side as the main earth connections.

6.6 WINDING:-

6.6.1 Winding shall be subjected to a shrinking and seasoning process, so that no


further shrinkage occurs during service. Adjustable devices shall be provided for
taking up possible shrinkage in service.

6.6.2 All low voltage windings for use in the circular coil concentric winding shall be
wound on a performed insulating cylinder for mechanical protection of the
winding in handling and placing around the core.

6.6.3 Winding shall not contain sharp bends which might damage the insulation or
produce high dielectric stresses. No strip conductor wound on edge shall have
width exceeding six times the thickness.
6.6.4Materials used in the insulation and assembly of the windings shall be insoluble,

non catalytic and chemically inactive in the hot transformer oil and shall not
soften or the otherwise affected under the operating conditions.

6.6.5Varnish application on coil windings may be given only for mechanical protection

and not for improvement in dielectric properties. In no case varnish or other


adhesive be used which will seal the coil and prevent evacuation of air and
moisture and impregnation by oil.

6.6.6Winding and connections shall be braced to withstand shocks during transport


or short circuit.

6.6.7 Permanent current carrying joints in the windings and leads shall be welded

or brazed. Clamping bolts for current carrying parts inside oil shall be made of oil
resistant material which shall not be affected by acidity in the oil steel bolts, if
used, shall be suitably treated.

6.6.8Terminals of all windings shall be brought out of the tank through bushings for

external connections.

6.6.8.1 The completed core and coil assemble shall be dried in vacuum at not
more than 0.5mm of mercury absolute pressure and shall be immediately impregnated
with oil after the drying process to ensure the elimination of air and moisture within
the insulation. Vacuum may be applied in either vacuum over or in the transformer
tank.

6.6.8.2 The winding shall be so designed that all coil assembles of identical
voltage ratings shall be interchangeable and field repairs to the winding can be made
readily without special equipment. The coils shall have high dielectric strength.

6.6.8.3 Coils shall be made of continuous smooth high grade electrolytic copper
conductor, shaped and braced to provide for expansion and contraction due to
temperature changes.

6.6.8.4 Adequate barriers shall be provided between coils and core and between
high and low voltage coil. End turn shall have additional protection against abnormal
line disturbances.

6.6.8.5 The insulation of winding shall be designed to withstand voltage stress


arising from surge in transmission lines due to atmospheric or transient conditions
caused by switching etc.
6.6.8.6 Tapping shall not be brought out from inside the coil or from
intermediate turns and shall be so arranged as to preserve as far as possible magnetic
balance of transformer at all voltage ratios.

6.6.8.7 Magnitude of impulse surges transferred from HV to LV windings by


electro magnetic induction and capacitance coupling shall be limited to BIL of LV
winding.

6.6.8.8 The current density adopted in all winding shall not exceed 2.4
A/mm2. The total net conductor area should be arrived after deducting the area ,lost
due to rounding off the sharp edges of the conductor , which is given below:-

0.21 mm2 up to a depth of 1.6 mm

0.36 mm2 mm up to a depth of 2.24 mm

0.55 mm2 up to a depth of 3.25 mm

0.86 mm2 above 3.25 mm

6.6.8.9 The finally compressed shrunk height of both HV and LV windings should be
equal.

6.7 INSULATING OIL

6.7.1 The insulating oil for the transformer shall be of EHV grade, generally
conforming

to IS: 335. No inhibitors shall be used in the oil.

6.7.2 The quantity of oil required for the first filling of the transformer and its full
specification shall be stated in the bid. The bidder shall quote the price of
transformer complete with all fittings, accessories and new transformer oil
required for first filling plus 10% extra oil. The extra quantity of oil shall be
supplied in non-returnable drums along with the oil required for the radiator
banks.

6.7.3 The design and materials used in the construction of the transformer shall be

such as to reduce the risk of the development of acidity in the oil.


6.7.4Transformer Oil-The contractor shall ensure that the Transformer oil furnished
conforms to IS:335 including amendment,if any.

6.8 VALVES:-

i) Valves shall be of forged carbon steel upto 50mm size and of gun mental
or of cast iron bodies with gun metal fittings for sizes above 50mm. They
shall be of full way type with screwed ends and shall be opened by turning
counter clockwise when facing the hand wheel. There shall be no oil leakage
when the valves are in closed position.
ii) Each valve shall be provided with an indicator to show the open and
closed positions and shall be provided with facility for padlocking in either
open or closed position. All screwed valves shall be furnished with pipe
plugs for protection. Padlocks with duplicate keys shall be supplied along
with the valves.

i) All valves except screwed valves shall be provided with flanges having
machined faced drilled to suit the applicable requirements, Oil tight
blanking plates shall be provided for each connection for use when any
radiator is detached and for all valves opening to atmosphere. If any special
radiator valve tools are required the contractor shall supply the same.

ii) Each transformer shall be provided with following valves on the tank:

a) Drain valve so located as to completely drain the tank & to be


provided with locking arrangement.
b) Two filter valves on diagonally opposite corners of 50mm size & to be
provided with locking arrangement.
c) Oil sampling valves not less than 8mm at top and bottom of main
tank & to be provided with locking arrangement.
d) One 15mm air release plug.
e) Valves between radiators and tank.
Drain and filter valves shall be suitable for applying vacuum as specified in
this specification.

6.9 ACCESSORIES:-

6.9.1 Bushing

i) All porcelain used in bushings shall be homogeneous, non-porous,


uniformly glazed to brown colour and free from blisters, burns and other
defects.
i) Stress due to expansion and contraction in any part of the bushing shall
not lead to deterioration.

ii) Bushing shall be designed and tested to comply with the applicable
standards.

iii) Bushing rated for 400A and above shall have non-ferrous flanges and
hardware.
ii) Fittings made of steel or malleable iron shall be galvanized

iv) Bushing shall be so located on the transformers that full flashover


strength will be utilized. Minimum clearances as required for the BIL shall
be realized between live parts and live parts to earthed structures.

v) All applicable routine and type tests certificates of the bushings shall be
furnished for approval.
i) Bushing shall be supplied with bi-metallic terminal connector/ clamp/
washers suitable for fixing to bush terminal and the OPTCL’s specified
conductors. The connector/clamp shall be rated to carry the bushing rated
current without exceeding a temperature rise of 500 C over an ambient of
500C. The connector/clamp shall be designed to be corona free at the
maximum rated line to ground voltage.

ix) Bushing of identical voltage rating shall be interchangeable.

x) The insulation class of high voltage neutral bushing shall be properly


coordinated with the insulation class of the neutral of the low voltage
winding.

xi) Each bushing shall be so coordinated with the transformer insulation


that all flashover will occur outside the tank.

6.9.2Protection & Measuring Devices:-

i) Oil Conservator Tank

a) A conservator,complete with drain valve shall be provided in such a


position,so as not to obstruct the electrical connections to the Transformer.
The capacity of the conservator between highest and lowest visible levels
shall be minimum of 7.5% of the total cold oil volume in the Transformer.

b) The conservator tank shall be bolted on its support of mounting to allow


for its removal for cleaning/ repairing purposes.

c) The conservator shall be fitted with magnetic oil level gauge with low
level electrically insulated alarm contact.
d) The silica gel breather shall have minimum quantity of silica gel as1kg for
every 3500Ltrs. of oil in the Tank. The container for the dehydring agent shall
be of transparent plastic of best quality,to be approved by OPTCL.

ii) Pressure Relief Device.

The pressure relief device provided shall be of sufficient size for rapid release
of any pressure that may be generated in the tank and which may result in
damage of the equipment. The device shall operate at a static pressure of
less than the hydraulic test pressure of transformer tank. It shall be
mounted direct on the tank. A pair of electrically insulated contract shall be
provided for alarm and tripping.

iii) Buchholz Relay

A double float type Buchholz relay shall be provided., Any gas evolved in the
transformer shall collect in this relay. The relay shall be provided with a test
cock suitable for a flexible pipe connection for checking its operation. A
copper tube shall be connected from the gas collector to a valve located
about 1200 mm above ground level to facilitate sampling with the
transformer in service. The device shall be provided with two electrically
independent potential free contracts, one for alarm on gas accumulation and
the other for tripping on sudden rise of pressure.

iv) Temperature Indicator

a) Oil Temperature Indicator (OTI)

The transformers shall be provided with a mercury contact type


thermometer with 150 mm dial for top oil temperature indication. The
thermometer shall have adjustable, electrically independent potential free
alarm and trip contacts. Maximum reading pointer and resetting device shall
be mounted in the local control panel. A temperature sensing element
suitably located in a pocket on top oil shall be furnished. This shall be
connected to the OTI by means of capillary tubing. Accuracy class of OTI
shall be ± 1% or better. One No electrical contact capable of operating at 5 A
ac at 230 volt supply.

b) Winding Temperature indicator(WTI)

A device for measuring the hot spot temperature of the winding shall be
provided. It shall comprise the following.

i) Temperature sensing element.

i) Image Coil.
ii) Mercury contacts.

iii) Auxiliary CTS, If required to match the image coil, shall be furnished and
mounted in the local control panel.

iv) 150mm dial local indicating instrument with maximum reading pointer
mounted in local panel and with adjustable electrically independent
ungrounded contacts, besides that required for control of cooling equipment,
one for high winding temperature alarm and on for trip.

v) Calibration device.

vi) Two number electrical contact each capable of operating at 5 A ac at


230 Volt supply.

6.9.3 Oil Preservation Equipment

6.9.3.1 :-

The oil preservation shall be diaphragm type oil sealing in conservator to


prevent oxidation and contamination of oil due to contact with atmospheric
moisture.

The conservator shall be fitted with a dehydrating filter breather. It shall be so


designed that.

i) Passage of air is through a dust filter & Silica gel.

ii) Silica gel is isolated from atmosphere by an oil seal.

i) Moisture absorption indicated by a change in colour of the crystals of


the silica gel can be easily observed from a distance.

i) Breather is mounted not more than 1400 mm above rail top level.

6.10 MARSHALLING BOX:-

i) Sheet steel, weather, vermin and dust proof marshalling box fitted with
required glands, locks, glass door, terminal Board, heater with switch,
illumination lamp with switch, watertight hinged and padlocked door of a
suitable construction shall be provided with each transformer to
accommodate temperature indicators, terminal blocks etc. The box shall
have slopping roof and the interior and exterior painting shall be in
accordance with the specification. Padlock along with duplicate keys shall be
supplied for marshalling box. The degree of protection shall be IP-55 or
better.

ii) The schematic diagram of the circuitry inside the marshalling box be
prepared and fixed inside the door under a suitable sheet.

iii) The marshalling box shall accommodate the following equipment:

a) Temperature indicators.

b) Space for accommodating Control & Protection equipment in future for the
cooling fan (for ONAF type cooling, may be provided in future).

c) Terminal blocks and gland plates for incoming and outgoing cables.

All the above equipment except c) shall be mounted on panels and back of
panel wiring shall be used for inter-connection. The temperature indicators
shall be so mounted that the dials are not more than 1600 mm from the
ground level and the door (s) of the compartment(s) shall be provided with
glazed window of adequate size. The transformer shall be erected on a plinth
which shall be 2.5 feet above ground level.

iii) To prevent internal condensation, a metal clad heater with thermostat


shall be provided. The heater shall be controlled by a MCB of suitable rating
mounted in the box. The ventilation louvers, suitably padded with felt, shall
also be provided. The louvers shall be provided with suitable felt pads to
prevent ingress of dust.

iv) All incoming cables shall enter the kiosk from the bottom and the gland
plate shall not be less than 450 mm from the base of the box. The gland
plate and associated compartment shall be sealed in suitable manner to
prevent the ingress of moisture from the cable trench.

iii)The control connection, wiring etc. shall be as per Clause 3.15 of this

6.11 TAPCHANGER

6.11. ON-LOAD TAP-CHANGERS WITH REMOTE TAP CHANGE CONTROL


1

Transformer of capacity 8MVA shall be provided with an “In-Tank” or


“Flange Mounted” Type on-load tap-changer connected to the high voltage
winding. The on-load tap-changer shall be capable of withstanding the
voltages described earlier and shall comply with the requirements of IEC-
60214, latest revision. Its tapping range, number of steps and tap positions
shall be as specified.
On Load Tap Changer shall be sourced from reputed manufacturer(s) and it
should be type tested as per relevant IEC60214 as given below and test
methods shall be in full conformance to the procedures indicated in IEC60214
Sl.No. IEC Reference Test Description
1. Cl.5.2.1 Temperature rise of contacts.
2. Cl.5.2.2 Switching Tests
3. Cl.5.2.3 Short-circuit current Test.
4. Cl.5.2.4 Short-circuit current Test. .
5. Cl.5.2.5 Mechanical tests.
6. Cl.5.2.6 Dielectric Tests
OLTC manufacturer shall conduct the following routine tests fully in
compliance with IEC 60214 on every unit, as given below, before dispatch to
assure the quality of the OLTC.OPTCL at its sole discretion may test-witness
and inspect the Tap-Changers at the works of the OLTC manufacturer.
The following are the routine tests,to be carried out on each OLTC:-
Sl.No. IEC Reference Test Description
1. Cl.5.3.1 Mechanicaql Test.
2. Cl.5.3.2 Sequence test
3. Cl.5.3.3 Auxiliary circuits Insulation tests

4. Cl.5.3.4 Pressure test

5. Cl.5.3.4 Vacuum test

All the test reports shall be submitted to OPTCL for approval.

Adequate access for personnel shall be provided for inspection and


maintenance. The guaranteed interval between maintenance periods for the
diverter switch shall be 10 years or 50,000 operations. It shall not be
possible for oil in the diverter switch compartment to come in contact with the
oil in the main transformer tank.

The tap-changer shall be driven by a motor operated mechanism


incorporating a stored energy device which shall ensure that once a change of
tap begins it is completed and so shall ensure that the mechanism does not
fail in an intermediate position on loss of the supply voltage to the motor. The
motor shall be rated for 400/230V, 50 Hz and shall operate satisfactorily at
any voltage between 85% and 110% of rated voltage.

A tap-changer mechanism box with hinged door and mounted on the


transformer tank at a convenient height shall contain all electrical and
mechanical parts associated locally with control of the tap-changer. Remote
tap-changer controls shall also be provided at a transformer control panel
(one per transformer, to be supplied under this contract) in the control room.

Facilities for electrical raise and lower operation (Control switch or push
button) as well as mechanical operation shall be provided as the tap-change
mechanism box. An interlock shall be provided which shall interrupt the
electric supply to the drive motor when the manual mechanical operating
device is engaged. The motor drive control shall be such that on initiation of a
tap-change operation by means of a control switch or push-button the tap-
changer shall complete its movement form one service position to an adjacent
one irrespective of whether or not the control switch or push button has been
operated continuously during the running time or motor drive. Another
operation shall only be possible when the previous operation has been
completed, the control switch or push button has been released and the
control system is again in the rest position.

The tap-changer arrangement shall be such that a command to raise tap-


numbers shall result in an increase in the secondary voltage with constant
voltage applied to the high voltage winding.

An under and over voltage monitoring relay fed with line voltage from the
owner’s voltage transformers on the low voltage side of the transformer and
capable of being set in a continuously variable range from 90% to 115%
normal voltage (110V) shall be used to give visual and audible signals at the
remote tap change control panel if the LV voltage lies above or below preset
values.

Limit switches shall be provided to prevent over-running of the tap-change


mechanism. These shall be directly connected in the motor circuit. In addition
mechanical end stops shall be fitted to prevent over-running of the
mechanism under any conditions. A counter shall be provided to indicate the
number of tap-change operations that have been taken place.

A mechanical tap-position indicator shall be provided and it shall be visible


from ground level through a window in the door of the mechanism box.
Position transmitter e.g. dial switches shall be provided to:

a. Signal tap position to the control cabinet in the control room.


b. Signal “out of step” under parallel operating conditions.

A Remote/Local switch shall be provided at the mechanism box to select


either remote or local operation. When this switch is turned to the Remote
position control shall be passed to the control cabinet in the control room. It
should be possible to use only one control, i.e. Local or Remote.

It shall be possible to operate a transformer tap-changer independently or in


parallel with the tap-changers of other similar transformers in the same
substation in either a “master” or “follower” mode. In addition, when operating
independently or in parallel in the master mode, it shall be possible to have
manual operation by means of control switch, push button or, (in future)
automatic operation by means of an automatic voltage regulating relay.
Contacts shall be provided for future SCADA control of the tap-changer and
for reporting of the tap position and mode of control to the SCADA system.
The paralleling scheme shall use the in- step principle and shall have
provision for operating singly or in parallel in any combination. It shall be
possible for any transformer in a group to be selected as either the master or
follower for that group when operating in parallel. Each transformer control
panel shall therefore have a manual/automatic control switch or push
buttons, independent/master/follower control switch or push buttons as well
as “raise” and lower” control switches or push buttons. Interlock shall be
provided to avoid independent operation when the transformers are running
in parallel. There should not be any out-of-step during such operation.

The control scheme shall be capable of extension to cater for the total number
of transformers to be installed in any future development of the substation.
The control mode selected shall be indicated on the front of the control
cabinet.

Each transformer shall have a miniature circuit breaker (MCB) on the AC


distribution cabinet through which the 400/230V, 50 Hz supply to its tap-
changer and temperature controls is passed. Separate MCB’s shall be
provided at the mechanism box for protection of the motor and control
circuits. The control circuits shall operate at 110V single phase, to be
supplied from a transformer having a ratio of 230/55-0-55 V, with the center
point earthed through a removable link mounted in the marshalling box or
tap-changer mechanism box.

Each tap-changer mechanism box shall be fitted with an anti-condensation


space heater (230V AC) controlled by a humidistat with variable range. A lamp
for illumination purposes controlled by a door switch shall be provided. Solar
gain can give rise to high temperature within a mechanism box. Adequate
ventilation shall be provided to ensure that all equipment contained therein
shall operate satisfactorily under these conditions.

A terminal block with terminals rated for 10 A continuous current, 650V


grade of moulded insulating materials shall be provided for panel wiring and
external connection.

Ten percent spare terminals shall be provided in each mechanism box.

The tap changer mechanism box shall be outdoor, weatherproof type, dust,
vermin and damp proof with a degree of protection of IP54 of IEC 529 or IS
13947 equivalent.

6.11.2 Transformer Tap Change Control Panel:-

The indoor panel suitable for installation in the owner’s control room
mentioned above shall contain.

 Raise and Lower push buttons or switch.


 Independent / master / follower selector switch.
 Remote tap position indicator.
 Necessary audible & visual alarms.
 Out of step relay with two spare contacts ( 2 NO + 2 NC )
In addition to the above the Transformer tap change control panel shall have
an audible and visual annunciation system for the following trips and alarms.

Oil temperature alarm

Oil temperature trip

Winding temperature alarm

Winding temperature trip

Buchholz alarm

Buchholz trip

Surge relay trip(OLTC gear)

Low oil level alarm

Tap changer out-of-step alarm

Failure of D.C supply alarm

Two spare windows shall be supplied on each panel

Indicating lamps shall be panel mounted type with rear terminal connections.
Lamps shall be provided with series connected resistors preferably built
within the lamp assembly. Lamps shall have screwed translucent lamp covers
to diffuse light and shall be continuously rated for 120 percent of the 24 volt
DC supply from a power pack having desired capacity. The ‘DC supply failure’
lamp shall operate from the AC supply and be rated for 230 Volt AC. The
wattage of the lamps shall be not more than five watts. Bulbs and lenses shall
be interchangeable and easily replaceable from the font of the panel.

The Annunciation scheme with facia windows and alarm bells shall work as
follows.

Annunciation scheme functions

Incident Alarm Bell Facia Window

Fault occurrence Ringing Light flashing

Sound cancel Off Light flashing

Acknowledge Off Steady light

Fault cleared and reset Off Clear

Lamp test Off Steady

Any new annunciation operating after the operation of the ‘sound cancel’ shall
cause audible and visual alarm even if the process of acknowledging the
previous alarm is going on or has yet to be carried out. Resetting facilities for
the flasher and audible alarm circuits of the annunciator shall be provided,
and provision shall be made for switching off the entire annunciation system.
Two spare windows shall be provided.

The control and relay panel shall be metal clad, dust, moisture, rodent and
vermin proof with degree of protection not less than IP 41 specified in IEC :
529/ IS : 13947. Panels shall have folded construction and be of unit type.
Each panel shall be a free standing structure, independent floor mounting
type and shall be manufactured from cold rolled sheet steel of thickness not
less than 2.5 mm. There shall be sufficient reinforcement to provide level
surfaces, resistance to vibration and rigidity during transportation,
installation and service. The panel shall be painted as specified in the clause
on “painting” in the specification.
Design, material selection and workmanship shall be such as to result in neat
appearance inside and outside with no welds, rivets or bolt ends apparent
from outside, with all exterior surfaces even and smooth. The equipment on
the front of the panel shall be matched to give neat uniform appearance.
All doors and removable covers shall be gasketted all round with neoprene
bonded gaskets, Ventilating louvers shall be provided with screens and filters.
The screen shall be made of non corroding metal like brass or galvanized iron
wire mesh.
The transformer tap change control panel shall be supplied with all necessary
internal wiring, terminal blocks, relays and alarms to provide the above listed
alarm and trip functions.
Panel wiring shall be suitably bunched and clamped for neat appearance. The
conductors used for wiring purpose shall be PVC insulated 650 Volt grade
semi-flexible heat resistant, flame retardant and vermin proof electrolytic
copper cable conforming to IEC : 227 or IS : 1554. The wiring shall be
securely supported and taken through PVC troughs. All panel wiring shall be
capable of withstanding a voltage of 2 KV AC 50 Hz for one minute.
Terminal blocks of brass studs rated for 10 amps continuous current, 650
volt DC grade covered by moulded insulating materials with adequate
electrical clearance shall be provided for terminating the panel wiring and
outgoing connections. The termination shall be made by crimping lugs or bare
conductor with insulating sleeves at the ends. The arrangement can be
horizontal or vertical as per standard practice adopted by the manufacturer.
All terminals must be numbered and wire terminations provided with
numbered ferrules for identification. All numbering and marking including
those in wiring diagrams shall follow the guidelines provided in IS : 11353.
Ten percent spare terminals shall be provided.

A separate removable gland plate shall be provided at the bottom of each


panel for entry of PVC insulated control and auxiliary power cables in the
cabinet. At least five electroplated brass cable glands of approved sizes with
shrouds shall be provided in the gland plate for these cables. Provision shall
be made for earthing of the cable armours in the glands.
6.11.3 OFF LOAD TAP CHANGER (For 5 MVA transformers)

i The transformers shall be provided with Off-load Taps

ii The Transformer with off-load tap changing gear shall have taps
ranging from +5% to -15% in 8 equal steps of 2.5% each on HV
winding for voltage variation

iii The tap changing switch shall be located in a convenient position


so that it can be operated from ground level. The switch handle
shall be provided with locking arrangement along with tap position
indication, thus enabling the switch to be locked in position

6.12 FITTINGS AND ACCESSORIES:-

The following fittings and accessories shall be provided on the transformers:

i) Conservator with isolating valves, oil filling hole with cap and drain valve. The
conservator vessel shall be filled with constant oil pressure diaphragm oil
sealing system.

ii) Magnetic type oil level gauge (150 mm dia) with low oil level alarm contacts.

iii) Prismatic/ toughened glass oil level gauge.

iv) Silica gel breather with oil seal and connecting pipe complete with first fill of
activated silica gel or Alumina mounted at a level of 1300 mm above ground
level.

v) A double float type Buchholz relay with isolating valve. Bleeding pipe and a
testing cock, the test cock shall be suitable for a flexible (pipe connection for
checking its operation). A 5mm dia. Copper pipe shall be connected from the
relay test cock to a valve located at a suitable height above ground level to
facilitate sampling of gas with the transformer in service. Interconnection
between gas collection box and relay shall also be provided. The device shall
be provided with two electrically independent ungrounded contacts, one for
alarm on gas accumulation and the other for tripping on sudden oil surge.
These contacts shall be wired upto transformer marshalling box. The relay
shall be provided with shut off valve on the conservator side as well as on the
tank side.

v
i)
Pressure relief devices (including pressure relief valve) and necessary air
equalizer connection between this and the conservator with necessary alarm
and trip contacts.

vi
i)
Air release plugs in the top cover.

vii
i)
Inspection cover, access holes with bolted covers for access to inner ends of
bushing etc.

i
x)
Winding temperature (hot spot) indicating device for local mounting complete
in all respects. Winding temperature indicator shall have three set of contacts
to operate at different settings :

a) To provide winding temperature high alarm

b) To provide temperature too high trip

x)
Dial thermometer with pocket for oil temperature indicator with one set of
alarm and one set of trip contacts and maximum reading pointer.
x
i)
Lifting eyes or lugs for the top cover, core and coils and for the complete
transformer.

xi
i)
Jacking pads

xii
i)
Haulage lugs.

xiv
)
Protected type mercury / alcohol in glass thermometer and a pocket to house
the same.

xv
)
Top and bottom filter valves on diagonally opposite ends with pad locking
arrangement on both valves.

xvi
)
Top and bottom sampling valves.

xvii
)
Drain valve with pad locking arrangement

xviii
)
Rating and connection diagram plate.
xix Two numbers tank earthing terminals with associated nuts and bolts for
) connections to Owner’s grounding strip.

x
x)
Bi-directional flagged rollers with locking and bolting device.

xx
i)
Marshalling Box (MB)

xxii
)
Shut off valve on both sides of flexible pipe connections between radiator bank
and transformer tank.

xxiii
)
Cooling Accessories :

a) Requisite number of radiators provided with :-


- One shut off valve on top
- One shut off valve at bottom
- Air release device on top
- Drain and sampling device at bottom
- Lifting lugs.
b) Air release device and oil drain plug on oil pipe connectors :

xxiv
)
Terminal marking plates for Current Transformer and Main Transformer

xxv) On- Load Tap Changer


xxvi
)
Oil Preservation Equipment

xxvii
)
Oil Temperature indicator

Note (i) The fittings listed above are indicative and any other fittings which are
: generally required for satisfactory operation of the transformer are
deemed to be included in the quoted price of the transformer.

(ii) The contacts of various devices required for alarm and trip shall be
potential free and shall be adequately rated for continuous, making and
breaking current duties as specified.

iv)The following fittings and accessories shall be provided on the transformers:

i) Conservator with isolating valves, oil filling hole with cap and drain valve.
The conservator vessel shall be filled with constant oil pressure diaphragm
oil sealing system.

ii) Magnetic type oil level gauge (150 mm dia) with low oil level alarm
contacts.

iii) Prismatic/ toughened glass oil level gauge.

iv) Silica gel breather with oil seal and connecting pipe complete with first fill
of activated silica
gel or Alumina mounted at a level of 1300 mm above ground level.

v) A double float type Buchholz relay with isolating valve. Bleeding pipe and a
testing cock, the test cock shall be suitable for a flexible (pipe connection
for checking its operation). A 5mm dia. Copper pipe shall be connected from
the relay test cock to a valve located at a suitable height above ground level
to facilitate sampling of gas with the transformer in service. Interconnection
between gas collection box and relay shall also be provided. The device shall
be provided with two electrically independent ungrounded contacts, one for
alarm on gas accumulation and the other for tripping on sudden oil surge.
These contacts shall be wired upto transformer marshalling box. The relay
shall be provided with shut off valve on the conservator side as well as on
the tank side.
vi) Pressure relief devices (including pressure relief valve) and necessary air
equalizer connection between this and the conservator with necessary alarm
and trip contacts.

vii) Air release plugs in the top cover.

viii) Inspection cover, access holes with bolted covers for access to inner ends of
bushing etc.

ix) Winding temperature (hot spot) indicating device for local mounting
complete in all respects. Winding temperature indicator shall have two set of
contacts to operate at different settings :

a) To provide winding temperature high alarm

b) To provide temperature too high trip

x) Dial thermometer with pocket for oil temperature indicator with one set of
alarm and one set of trip contacts and maximum reading pointer.

xi) Lifting eyes or lugs for the top cover, core and coils and for the complete
transformer.

xii) Jacking pads

xiii) Haulage lugs.

xiv) Protected type mercury / alcohol in glass thermometer and a pocket to house
the same.

xv) Top and bottom filter valves on diagonally opposite ends with pad locking
arrangement on both valves.

xvi) Top and bottom sampling valves.

xvii) Drain valve with pad locking arrangement

xviii) Rating and connection diagram plate.

xix ) Two numbers tank earthing terminals with associated nuts and bolts for
connections to grounding strip of the S/s.

xx) Bi-directional flagged rollers with locking and bolting device.

xxi) Marshalling Box (MB)

xxii) Shut off valve on both sides of flexible pipe connections between radiator
bank and transformer tank.
xxiii) Cooling Accessories:

a) Requisite number of radiators provided with :-

- One shut off valve on top

- One shut off valve at bottom

- Air release device on top

- Drain and sampling device at bottom

- Lifting lugs.

b) Air release device and oil drain plug on oil pipe connectors :

xxiv) Terminal marking plates for Current Transformer and Main Transformer

xxv) On-Load Tap Changing Gear with all necessary equipment and control
mechanism for both local and remote operation

xxvi) Oil Preservation Equipment


xxvii) Oil Temperature indicator

Note : (i) The fittings listed above are indicative and any other fittings which are
generally required

for satisfactory operation of the transformer including tap-changing by


On-Load Tap changing Gear are deemed to be included in the quoted
price of the transformer.

(ii) The contacts of various devices required for alarm and trip shall be
potential free and shall be adequately rated for continuous, making and
breaking current duties as specified.

6.13 CONTROL CONNECTIONS AND INSTRUMENT AND WIRING TERMINAL


BOARD AND FUSES:-

i) Normally no fuses shall be used anywhere instead of fuses MCB’s (both in AC


& DC circuits) shall be used. Only in cases where a MCB cannot replace a
fuse due to system requirements, a HRC fuse can be accepted.

ii) All wiring connections, terminal boards, fuses MCB’s and links shall be
suitable for tropical atmosphere. Any wiring liable to be in contact with oil
shall have oil resisting insulation and the bare ends of stranded wire shall
be sweated together to prevent seepage of oil along the wire.

iii) Panel connections shall be neatly and squarely fixed to the panel. All
instruments and panel wiring shall be run in PVC or non-rusting metal
cleats of the compression type. All wiring to a panel shall be taken from
suitable terminal boards.

iv) Where conduits are used, the runs shall be laid with suitable falls, and the
lowest parts of the run shall be external to the boxes. All conduit runs shall
be adequately drained and ventilated. Conduits shall not be run at or below
ground level.

v) When 400 volt connections are taken through junction boxes or marshalling
boxes, they shall be adequately screened and 400 volts Danger Notice must
be affixed to the outside of the junction boxes or marshalling box. Proper
colour code for Red, Yellow, Blue wires shall be followed.

vi) All box wiring shall be in accordance with relevant ISS. All wiring shall be of
stranded copper (48 strands ) of 1100 Volt grade and size not less than 2.5
sq.mm

vii) All wires on panels and all multi-core cables shall have ferrules, for easy
identifications, which bear the same number at both ends, as indicated in
the relevant drawing.

viii) At those points of interconnection between the wiring carried out by separate
contractors, where a change of number cannot be avoided double ferrules
shall be provided on each wire. The change of numbering shall be shown on
the appropriate diagram of the equipment.

ix) The same ferrule number shall not be used on wires in different circuits on the
same panels.

x) Ferrules shall be of white insulating material and shall be provided with


glossy finish to prevent the adhesion of dirt. They shall be clearly and
durably marked in black and shall not be affected by dampness or oil.

xi) Stranded wires shall be terminated with tinned Ross Courtney terminals,
claw washers or crimped tubular lugs. Separate washers shall be suited to
the size of the wire terminated. Wiring shall, in general, be accommodated
on the sides of the box and the wires for each circuit shall be separately
grouped. Back of panel wiring shall be arranged so that access to the
connecting items of relays and other apparatus is not impeded.

xii) All circuits, in which the voltage exceeds 125 volts, shall be kept physically
separated from the remaining wiring. The function of each circuit shall be
marked on the associated terminal
boards.

xiii) Where apparatus is mounted on panels, all metal cases shall be separately
earthed by means of stranded (48 No.) copper wire of strip having a cross
section of not less than 2 sq. mm where strip is used, the joints shall be
sweated. The copper wire shall have green colour insulation for earth
connections.

xiv) All wiring diagram for control and relay panel shall preferably be drawn as
viewed from the back and shall show the terminal boards arranged as in
services.

xv) Terminal block rows should be spaced adequately not less than 100 mm
apart to permit convenient access to external cables and terminations.

xvi) Terminal blocks shall be placed with respect to the cable gland ( at a
minimum distance of 200 mm) as to permit satisfactory arrangement of
multicore cable tails .

xvii) Terminal blocks shall have pairs of terminals for incoming and outgoing
wires. Insulating barriers shall be provided between adjacent connections.
The height of the barriers and the spacing between terminals shall be such
as to give adequate protection while allowing easy access to terminals. The
terminals shall be adequately protected with insulating dust proof covers.
No live metal shall be exposed at the back of the terminal boards. CT
terminals shall have shorting facilities. The terminals for CTs should have
provision to insert banana plugs and with isolating links.

xviii) All interconnecting wiring, as per the final approved scheme between
accessories of transformer and marshalling box is included in the scope of
this specification and shall be done by the Transformer supplier.

xix) The schematic diagram shall be drawn and fixed under a transparent
prospane sheet on the inner side of the marshalling box cover.

xx) To avoid condensation in the Marshalling Box, a space heater shall be


provided with an MCB and thermostat.

xxi) Suitable MV, CFL light shall be provided in the Marshalling Box for
lightning purpose.

6.14 RADIO INTERFERENCE AND NOISE LEVEL:-

Transformers shall be designed with particular care to suppress at least the


third and fifth harmonic voltages so as to minimise interference with
communication circuits. Transformer noise level when energised at normal
voltage and frequency shall be as per NEMA stipulations.

7.0 INSPECTION AND TESTING


(i) The Contractor shall carry out a comprehensive inspection and testing
programme during manufacture of the transformer. An indicative in
Standard for inspection is given under Clause No. 4.1. This is, however, not
intended to form a comprehensive programme as it is contractor’s
responsibility to draw up and carry out such a programme duly approved by
the OPTCL.

(ii) The contractor shall carry out type tests and routine tests on the
transformers. Only one no of transformer of each rating will be subjected to
type tests as per relevant IEC/IS in CPRI presence of authorized Engineer(s)
of OPTCL. The charges for conducting each of type tests shall be
included in the bid price and no separate type test charges shall be paid.
Type test report of same voltage class, same ratio (33/11kV) & rating (5MVA
or higher) duly signed by the bidder is required to be scanned & upload along
with the bid. However, designed transformer as per tender specification
parameters to be made by the contractor at his cost. Type test to be done
design wise.

(iii) The pre-shipment checks shall also be carried out by the contractor.

(iv) The requirements on site tests are as listed in the specifications.

(v) Certified test report and oscillograms shall be furnished to the OPTCL for
evaluation as per the schedule of distribution of documents. The Contractor
shall also evaluate the test results and rectify the defects in the equipment
based on his and the OPTCL’s evaluations of the tests without any extra
charges to OPTCL. Manufacturer’s Test Certificates in respect of all
associated auxiliary and ancillary equipment shall be furnished.

(vi) The bidder shall state in his proposal the testing facilities available at his
works. In case full testing facilities are not available, the bidder shall state
the method proposed to be adopted so as to ascertain the transformer
characteristics corresponding to full capacity.

(vii) OPTCL at its discretion may use its power analyser or the power analyser of
authorized testing agency for determination of no load loss, no load current,
load loss and % Impedance at the works of the manufacturer and the
concerned stores/Testing Laboratory of OPTCL/Any other Government
approved laboratory.

8.0 INSPECTION

i) Tank and Conservator

a) Inspection of major weld.


b) Crack detection of major strength weld seams by dye penetration test.
c) Check correct dimensions between wheels, demonstrate turning of
wheels, through 900 and further dimensional check.
d) Leakage test of the conservator.

ii) Core

a) Sample testing of core materials for checking specific loss, properties,


magnetization characteristics and thickness.
b) Check on the quality of varnish if used on the stampings.
c) Check on the amount of burrs.
d) Visual and dimensional check during assembly stage.
e) Check on completed core for measurement of iron loss, determination of
maximum flux density. (Determination of gross and net cross sectional
area of the core & no. of turns/Phase.)
f) Visual and dimensional checks for straightness and roundness of core,
thickness of limbs and suitability of clamps.
g) High voltage DC test (2 KV for one minute) between core and clamps.

iii) Insulating Material

a) Sample check for physical properties of materials.


b) Check for dielectric strength
c) Check for the reaction of hot oil on insulating materials.

iv) Winding

a) Sample check on winding conductor for mechanical and electrical


conductivity.
b) Visual and dimensional checks on conductor for scratches, dent mark
etc.
c) Sample check on insulating paper for PH value, electric strength.
d) Check for the bonding of the insulating paper with conductor.
e) Check and ensure that physical condition of all materials taken for
windings is satisfactory and free of dust.
f) Check for absence of short circuit between parallel strands.

v)Checks Before Drying Process

a) Check condition of insulation on the conductor and between the


windings.
b) Check insulation distance between high voltage connections, between
high voltage connection cables and earth and other live parts.
c) Check insulating distances between low voltage connections and earth
and other parts.
d) Insulating test for core earthing.

vi)Check During Drying Process

a) Measurement and recording of temperature and drying time during


vacuum treatment.
b) Check for completeness of drying
vii)Assembled Transformer

a) Check completed transformer against approved outline drawing,


provision for all fittings, finish level etc.
b) Jacking test on the assembled Transformer.

viii) Oil

All standard tests in accordance with IS: 335 shall be carried out on
Transformer oil sample before filling in the transformer.

ix)Test Report for bought out items

The contractor shall submit the test reports for all bought out / sub
contracted items for approval.

a) Buchholz relay
a) Sudden pressure rise relay on Main Tank
b) Winding temperature indicators (for TX capacity 5 MVA )
c) Oil temperature indicators
d) Bushings
e) Bushing current transformers in neutral (If Provided)
f) Marshalling box
g) Tap changer
h) Any other item required to complete the works.
i) Porcelain, bushings, bushing current transformers, wherever provided,
winding coolers, control devices, insulating oil and other associated
equipment shall be tested by the contractor in accordance with relevant
IS . If such requirement is purchased by the contractor on a sub-
contract, he shall have them tested to comply with these requirements.

8.1 FACTORY TESTS

i) All standards routine tests in accordance IS: 2026 with dielectric tests
corresponding as per latest amendments to IS: 2026 shall be carried out.
ii) All auxiliary equipment shall be tested as per the relevant IS. Test
certificates shall be submitted for bought out items.

iii) High voltage withstand test shall be performed on auxiliary equipment and
wiring after complete assembly.

iv) Following additional routine tests shall also be carried out on each
transformer:

a) Magnetic Circuit Test


Each core shall be tested for 1 minute at 2000 Volt DC

b) Oil leakage test on transformer

8.2 Type Tests:-

The transformer shall be subjected to the following type tests particularly


Short circuit and Impulse withstand tests at CPRI. Before conducting the
short circuit test and Impulse test, the firm will offer for both stage
inspection and final inspection of the transformer by OPTCL / DISCOM at
the manufacturer’s works. If the transformer complies to the specification
and offered technical parameters, the transformer will be sealed by
authorized engineer(s) of OPTCL and thereafter the transformer can be
transported to CPRI for required type tests in presence of OPTCL’s
authorized representative(s) who will verify the seal & allow for conducting
the type tests.

The Type Tests shall include:-

(1) Tan delta measurement and capacitance of each winding to earth (with all
other windings earthed) & between all windings connected together to earth.

(2) Measurement of Zero sequence impedance.


(3) Temperature Rise Test

(4) Short Circuit Test


(5) Tank Vacuum test

(6) Tank Pressure Test

(7) Lightning impulse withstand test for line and neutral terminal.
(8) Measurement of acoustic noise level.
8.3 STAGE INSPECTION:-

The supplier shall offer the core, windings and tank of each transformer for
inspection by OPTCL representative(s). During stage Inspection, all the
measurements like diameter, window height, leg Centre, stack width, stack
thickness, thickness of laminations etc. for core assembly, conductor size,
Insulation thickness, I.D., O.D, winding height, major and minor insulations
for both H.V and L.V windings, length, breadth, height and thickness of
plates of Transformer tank, the quality of fittings and accessories will be
taken / determined. The supplier can offer for final inspection of the
transformers subject to clearance of the stage Inspection report by the
OPTCL. No. of turns is to be determined by wrapping known No. of turns
across LV winding and determining the turns ratio by ratio meter.

8.4 Routine Tests:-

Transformer routine tests shall include tests stated in latest issue of IS:
2026 (Part –1). These tests shall also include but shall not be limited to the
following :

(i) Measurement of winding DC resistance.

(ii) Voltage ratio on each tapping and check of voltage vector relationship.

(iii) Impedance voltage at all tappings.

(iv) Magnetic circuit test as per relevant ISS or CBIP manual or latest standard being
followed.

(v) Measurement of Load losses at normal tap and extreme taps.

(vi) No load losses and no load current at rated voltage and rated frequency, also at
25% to 121 % of rated voltage in steps.

(vii) Absorption index i.e insulation resistance for 15 seconds and 60 seconds ( R
60/ R 15 ) and polarization index i.e Insulation Resistance for 10 minutes and
one minute (R 10 mt / R 1 mt).

(viii) Induced over voltage withstand test.

(ix) Separate source voltage withstand test.

(x) Tan delta measurement and capacitance of each winding to earth (with all other
windings earthed) & between all windings connected together to earth.

(xi) Measurement of zero sequence impedance

(xi) Tests on On- Load tap changer ( fully assembled on transformer ) as per IEC :
214/ 1976 and BS: 4571/ 1970.
(xii) Auxiliary circuit tests

( x i v ) Oil BDV tests

( x i v ) Measurement of neutral unbalance current which shall not exceed 2% of the


full rated current of the transformer.

(xv) Magnetic balance test

( x v i ) Leakage test.

Six (6) set of certified test reports and oscillographs shall be submitted for
evaluation prior to dispatch of the equipment. The contractor shall also
evaluate the test results and shall correct any defect indicated by his and
OPTCL’s evaluation of the tests without charge to the OPTCL.

8.5 TANK TESTS

a) Oil leakage Test :

The tank and oil filled compartments shall be tested for oil tightness
completely filled with air or oil of viscosity not greater than that of insulating
oil conforming to IS : 335 at the ambient temperature and applying a
pressure equal to the normal pressure plus 35 KN/ m2 measured at the
base of the tank. The pressure shall be maintained for a period of not less
than 12 hours of oil and one hour for air and during that time no leak shall
occur.

b) Pressure Test

Where required by the OPTCL, one transformer tank of each size together
with its radiator, conservator vessel and other fittings shall be subjected to a
pressure corresponding to twice the normal head of oil or to the normal
pressure plus 35 KN / m2 whichever is lower, measured at the base of the
tank and maintained for one hour.

c) Vacuum Test

One transformer tank of each size shall be subjected to the vacuum


pressure of 60 mm of mercury. The tanks designed for full vacuum shall be
tested at an internal pressure of 3.33 KN/m2 (25 mm of mercury) for one
hour. The permanent deflection of flat plates after the vacuum has been
released shall not exceed the value specified in C.B.I.P. Manual on
Transformers (Revised 1999) without affecting the performance of the
transformer.

8.6 PRE-SHIPMENT CHECK AT MANUFACTURERS WORKS


i) Check for proper packing and preservation of accessories like radiators,
bushings, explosions vent, dehydrating breather, rollers, buchholz relay,
control cubicle connecting pipes and conservator etc.

ii) Check for proper provision of bracing to arrest the movement of core and
winding assembly inside the tank.

iii) Gas tightness test to conform tightness.

8.7 INSPECTION AND TESTING AT SITE

The Engineer authorized from OPTCL along with the contractor’s site
engineer shall carry out detailed inspection covering areas right from the
receipt of material up to commissioning stage. An indicative program of
inspection as envisaged by the Engineer is given below.

8.7.1Receipt and Storage Checks

i) Check and record conditions of each package visible parts of the


transformers etc for any damage.
ii) Visual check of core and coils before filling up with oil and also check
condition of core and winding in general.

8.2.8Installation Checks

i) Inspection and performance testing of accessories like tap changers etc.

ii) Check choking of the tubes of radiators

iii) Test on oil samples taken from main tank top and bottom and cooling
system. Samples should be taken only after the oil has been allowed to
settle for 24 hours.

iv) Check the whole assembly for tightness, general appearance etc.

v) Oil leakage tests.

8.7.2 Pre-Commissioning Tests

After the transformer is installed, the following pre-commissioning tests and


checks shall be done before putting the transformer in service.

i) Dry out test

ii) Megger Test


iii) DC Resistance measurement of windings
iv) Ratio test on all taps
v) Phase relationship test ( Vector grouping test )

vi) Buchholz relay alarm & surge operation test

vii) Low oil level ( in conservator ) alarm


v i i i ) Temperature Indicators

ix) Marshalling kiosk


x) Protective relays

xi) Magnetising current

xii) Tests on OLTC


8.7.3 The following additional checks shall be made :

i) All oil valves are incorrect position closed or opened as required

ii) All air pocket are cleared.

iii) Thermometer pockets are filled with oil.


iv) Oil is at correct level in the bushing, conservator, diverter switch & tank etc.

v) Earthing connections are made.


vi) Colour of Silica gel is blue.
vii) Bushing arcing horn is set correctly and gap distance is recorded.
Viii) C T polarity and ratio is correct.

9.0 PERFORMANCE

The performance of the transformer shall be measured on the following


aspects.

i) The transformer shall be capable of being operated without danger on any


tapping at the rated KVA with voltage variations and ± 10% corresponding
to the voltage of the tapping

ii) Radio interference and Noise Level

iii) The transformer shall be designed with particular attention to the


suppression of third and fifth harmonics so as to minimize interference with
communication circuits.

9.1 FAULT CONDITIONS

a) The transformer shall be capable of withstanding for two(2) seconds without


damages any external short circuit to earth

b) Transformer shall be capable of withstanding thermal and mechanical


stresses conveyed by symmetrical or asymmetrical faults on any winding.
This shall be demonstrated through calculation as per IS : 2026.

c) Transformer shall accept, without injurious heating, combined voltage and


frequency fluctuation which produce the 125% over fluxing condition for one
minute and 140% for 5 seconds.

Certified test report and oscillograms shall be furnished to the OPTCL for
evaluation as per the schedule of distribution of documents. The Contractor
shall also evaluate the test results and rectify the defects in the equipment
based on his and the OPTCL’s evaluations of the tests without any extra
charges to the OPTCL. Manufacturer’s Test Certificates in respect of all
associated auxiliary and ancillary equipment shall be furnished.

The bidder shall state in his proposal the testing facilities available at his
works. In case full testing facilities are not available, the bidder shall sate the
method proposed to be adopted so as to ascertain the transformer
characteristics corresponding to full capacity testing.

10.0 LOSSES:-

Sl.No Maximum No- Maximum


Load Loss in Load Loss in
Transformer
KW at rated KW at 750C at normal
Rating
voltage & tap position & rated
frequency frequency

1 33/11 KV, 5 MVA 3.6 21

2 33/11 KV, 8 MVA 4.5 38


N.B : There shall be no positive tolerance to above losses. Capitalization of
losses shall not be factored in the comparative statement for selection of
vendors.

11.0 SPARE PARTS:-

In case the manufacturer goes out of production of spare parts, then he shall
make available the drawings of spare parts and specification of materials at
no extra cost to the OPTCL to fabricate or procure spare parts from other
sources.

Mandatory Spare Parts

The suppliers shall provide the following mandatory spare s for each of
Transformer supplied

3. H.V. & L.V. Bushing & Studs –Each 2 Nos

4. Bimetallic connector for H.V & L.V. Bushings – Each 2 sets

12.0 INSTRUCTION MANUAL:-

Eight sets of the instruction manuals shall be supplied at least four (4) weeks
before the actual dispatch of equipment. The manuals shall be in bound
volumes and shall contain all the drawings and information required for
erection, operation and maintenance of the transformer. The manuals shall
include amongst other, the following particular:

a) Marked erection prints identifying the components, parts of the


transformer as dispatched with assembly drawings.
b) Detailed dimensions, assembly and description of all auxiliaries.
c) Detailed views of the core and winding assembly, winding connections
and tapings tap changer construction etc. These drawings are required for
carrying out overhauling operation at site.

d) Salient technical particulars of the transformer.

a) Copies of all final approved drawings.

a) Detailed O&M instructions with periodical check lists and Performa etc.

13.0 COMPLETENESS OF EQUIPMENT:-


All fittings and accessories, which may not be specifically mentioned in the
specification but which are necessary for the satisfactory operation of the
transformer, shall be deemed to be included in the specification and shall be
furnished by the supplier without any extra charge. The equipment shall be
complete in all details whether such details are mentioned in the
specification or not, without any financial liability to the OPTCL under any
circumstances.

13.1 TOOLS AND TACKLES:-

All the necessary tools and tackles required for normal operation &
maintenance of the transformers shall be supplied by the supplier.

13.2 COMMISSIONING:-

The equipment shall be commissioned as per CBIP manual, IS: 10028 and
manufacturer’s recommendations. All the related drawings and manuals shall
be pre-requisite for release of final payment.

14.0 Technical Data Requirement - The Technical Data Schedule for 5MVA & 8
MVA, 33/11kV Power Transformers shall be furnished as per the format
attached..
(GTP, 5MVA & 8 MVA,33/11kV Power Transformers)

Sl.
Description Bidder's offer
No.
1. Name and address of the Manufacturer
a) Transformer
b) HV & LV Bushings
c) Bimetallic connectors
d) Transformer Oil
e) On load tap changer
f) Instruments
g) Neutral Bushing CTs
2. Service ( Indoor / Outdoor )
3. Normal continuous rating in KVA under site conditions at all taps :
a) HV winding (KVA)
b) LV winding (KVA)
4. Rated Voltage
a) HV winding (KV )
b) LV winding (KV)
5. Rated frequency (Hz)
6. No. of phases
7. Type of transformer
8. Connections
a) HV winding
b) LV winding
9. Connections symbols
HV – LV
10. Tappings
a) Range
b) Number of steps
c) Position of tapping on HT winding for high voltage variation
11. Reference ambient temperatures
a) Maximum ambient air temperature (0C)
b) Maximum daily average ambient temperature (0C)
c) Minimum ambient air temperature (0C)
d) Maximum yearly weighted average ambient temperature ( 0C)
12. Maximum temperature rise over ambient temperature
a) Top oil by thermometer (0C)
b) HV & LV windings by resistance measurement (0C)
Sl.
Description Bidder's offer
No.
c) Hot Spot Temperature rise of windings(º C)
d) Limit for hot spot temperature for which the transformer is designed (º C)

e) Temperature gradient between windings and oil ( 0C)


f) Type of maximum winding temperature indicator (0C)
13. Voltage to earth for which the star point will be insulated
14. Cooling type
15. Losses
a) No-Load loss at rated voltage & rated frequency (KW)

b) Load loss at rated current at Normal Tap at 750 C (KW )


16. Max. Current density in winding at rated current for normal tap position

a) HV winding (Amps/ sq.mm.)


b) LV winding (Amps / sq.mm.)
17. Impedance voltage at rated current ,rated frequency and at 75 0 C expressed
as percentage of rated voltage at :-
a) Principal (normal) tap (%)
b) Highest tap (%)
c) Lowest tap (%)
18. Reactance at rated current & frequency as percentage of rated voltage at:
a) Principal (normal) tap
b) Highest Tap
c) Lowest Tap
19. Resistance at 75º C
a) H.V. winding at normal tap position
b) L.V. winding
c) Resistance voltage drop at 75º C winding temperature expressed as percent
of rated voltage (%)
i) Principal/ normal tap
ii) Highest tap
iii) Lowest tap
20. Insulation level
a) Separate source power frequency voltage withstand
i) HV winding (KV rms)
ii) LV winding (KV rms)
b) Induced over voltage withstand
i) HV winding (KV rms)
ii) LV winding (KV rms)
c) Full wave lightning impulse withstand voltage
Sl.
Description Bidder's offer
No.
i) HV winding (KV peak)
d) Power frequency high voltage tests
i) Test voltage for one minute withstand test on high voltage windings
(induced)
ii) Test voltage for one minute withstand test on low voltage windings
iii) Test voltage for one minute withstand test on neutral end of low voltage
windings
e) Lightning impulse withstand tests
i) Impulse test on high voltage winding 1.2/50 µ sec full wave withstand
(KV peak)
ii) Impulse test on low voltage winding 1.2/50 µ sec full wave withstand
(KV peak)
iii) Wave form for impulse test
21. No load current, no load loss, no load power factor at normal ratio and
frequency (Amp/ KW/ P.F.)
a) 10 percent of rated voltage
b) 25 percent of rated voltage
c) 50 percent of rated voltage
d) 85 percent of rated voltage
e) 100 percent of rated voltage
f) 105 percent of rated voltage
g) 110 percent of rated voltage
h) 112.5 percent of rated voltage
i) 115 percent of rated voltage
j) 120 percent of rated voltage
k) 121 percent of rated voltage
22. Efficiency at 75º C at unity power factor
a) Full load
b) 75% load
c) 50% load
d) 25% load
23(a) The minimum percentage of load at which the transformer will run at
maximum efficiency (%)
b) Maximum efficiency of the transformer
24. Regulation at full load at 75º C
a) At unity power factor (%)
b) At 0.8 power factor (lagging) (%)
25. Core data
a) Grade of core material used
b) Thickness of core plate lamination (mm)
c) Whether core laminations are of HIB cold rolled grain oriented
Sl.
Description Bidder's offer
No.
d) Details of oil ducts in core, if any
i) Whether in the plane & at right angle to the plane of winding
ii) Across the plane of lamination
e) i) Insulation of core lamination
ii) Insulation of core plates
iii) Type of core joints(Mitred or Mitred Step-lap)
26. Flux density
a) Designed maximum flux density at rated voltage and rated frequency (Tesla)
b) Designed maximum operating flux density which the transformer can
withstand for one minute at normal tap (Tesla)
c) Designed maximum operating flux density which the transformer can
withstand for five seconds at normal tap (Tesla)
27. Inter-Tap insulation
a) Extent of extreme end turns reinforcement
b) Extent of end turns reinforcement
c) Extent of turn adjacent to tapping reinforced
d) Test voltage for 10 seconds 50Hz inter-turn insulation test on (a)
e) Test voltage for 10 seconds 50Hz inter-turn insulation test on (b)
f) Test voltage for 10 seconds 50Hz inter-turn insulation test on (c)
28. Windings:
a) Material
b) Type of windings:
i) HV windings
ii) LV windings
c) Insulation of HV windings
d) Insulation of LV windings
e) Insulation between HV & LV windings
29. Continuous rating under following conditions:
a) At 40ºC ambient air temp. at site
b) At 30ºC ambient air temp. at site
c) At 20ºC ambient air temp. at site
30. Transformer Tank
a) Material
b) Thickness
- Top
- Sides
- Bottom
c) Details of painting
- Inner surface
- Outer surface
31. Dimensions of 3 phase transformers:
Sl.
Description Bidder's offer
No.
a) Max. Height to top of bushings (mm)
b) Over-all length (mm)
c) Over-all breadth (mm)
32. Weight data of transformer components : (Tolerance + 5% ) (approximate
values not allowed )
a) Core excluding clamping (Kg)
b) Core with clamping (Kg)
c) HV winding insulated conductor (Kg)
d) LV winding Insulated conductor (Kg)
e) Coils with insulation (Kg.)
f) Core and windings (Kg)
g) Weight of steel (Kg)
h) Fittings and accessories (Kg)
i) Oil required for first filling including 10% extra (ltrs / Kg )
1. Oil in main tank ( Ltrs)
2. Oil in the conservator (Ltrs)
3. Oil in the radiators ( Ltrs )
4. Oil in the OLTC (Ltrs.)
5. Overall total quantity of oil with 10% extra oil for first filling (ltrs / Kg)
j) 1. Transportation weight excluding accessories (Kg)
2. Shipping details
i) Weight of heaviest package (Kg.)
ii) Dimension of largest package (Kg)
k) Untanking weight (Kg)
l) Total weight of transformer with oil and fittings (Kg)
33. Bushing data :
a) Type of bushing insulator
i) HV
ii) LV
iii) Neutral
b) Material of bushing (inner part / outer part)
c) Weight of bushing insulator (Kg.)
d) Quantity of oil in one bushing (lt.)
e) Minimum dry withstand & flash over power frequency voltage of bushing
(KV)
f) Minimum wet withstand & flash over power frequency voltage of bushing
(KV)
g) Minimum withstand & flashover impulse level (KV)
h) Voltage rating (KV)
i) Current rating (Amps.)
j) Thermal Short Time current & Duration
Sl.
Description Bidder's offer
No.
k) Rated Dynamic current & its duration
l) Cantilever with stand loading
m) Clearance in oil
- phase to phase (mm)
- phase to earth (mm)
n) Creepage distance in oil & air (mm)
o) Minimum level of immersing / medium (oil ) (mm)
p) Maximum pressure of immersing medium (oil) Kg/ cm 2
q) Free space required at top for removal of bushings (mm)
r) Angle of mounting
34. Details of CT to be provided in the neutral for REF protection.
a) Outdoor bushing type
b) No. of cores and their function
c) Location (Line / Neutral)
d) Current rating for various cores (Primary / Secondary)
e) VA burden / Knee Point voltage (Core wise)
f) Magnetising current at half knee point voltage. (mA)
g) Classification (PS class) core wise
h) Test voltage
i) Construction details
35. Conservator (Main Transformer and OLTC)
a) Total volume of the Conservator (Cub mtr / Ltr.)
b) Volume of the conservator between the highest and lowest level (Cubic mtr. /
Ltrs )
36. Calculated time constants for natural cooling
37. Type of axial coil supports :
a) HV winding
b) LV winding
38. Details of On Load tap changer
a) Make
b) Type
c) Rating
i) Rated Voltage
ii) Rated current
iii) Step voltage
iv) Number of steps
v)Rated Short Circuit Current

Sl.
Description Bidder's offer
No.
d) Whether Diverter switch provided with gas vent and buchholz relay (Yes /
No )
e) Whether a separate oil surge relay with trip contacts provided (Yes / No)

f) Pressure relief valve


g) Details of motor device unit housed in kiosk / mounted on tap changer
h) Whether Remote control panel provided with Control scheme for
simultaneous operation of Tap changer when transformers are running in
parallel and independent control when in independent operation.
i) Details of equipment in the OLTC kiosk
j) Details of OLTC panels
i) automatic tap changer relay
ii) literature of all the relays
iii) dimensions of OLTC, Panel L x B x H
iv) thickness of sheet
v) degree of protection
vi) details of equipment supplied
39. Dispatch details :
a) Approx. mass of heaviest Package (Kg)
b) Approx. dimensions of largest Package
i) Length (mm)
ii) Breadth (mm)
iii) Height (mm)
40. Un-tanking height (mm)
41. Bimetallic connectors HV / LV
a) Normal current rating (A)
b) Short time current rating (A)
c) Tensile strength (Kg)
d) Maximum temperature limit
e) Dimensional sketch enclosed indicating tolerances (Yes/No)
f) Minimum clearance (mm)
- Phase to phase
- Phase to Earth
42. CORE ASSEMBLY :-
a) Core diameter (mm )
b) Core window height (mm )
c) Core leg centre (mm )
d) Gross core cross – sectional area (m2)
e) Total height of core (mm )
f) Details of top end frame
g) Details of Bottom end frame
Sl.
Description Bidder's offer
No.
h)Details of clamp plate (material, thickness, insulation)
i)Total core weight (Kg )
j)Core loss, basing on core loss graph at operating flux density (rated voltage
and rated frequency ) ( KW )
k) Core stacking factor
l) Net core area (Sq.m)
m) Margin towards corner joints, cross-fluxing, dielectric loss (KW)
n) Total core loss at rated voltage and rated frequency (KW )
o) Describe location / method of core grounding
p) Details of core- belting
i) Material , grade and type
ii) Width
iii) Thickness
iv) Fixing method
43. DETAILS OF WINDING
a) Type of winding
b) Material of the winding conductor
c) Maximum current density of windings at rated current and conductor area
d) Whether windings are pre-shrunk ?
e) Whether adjustable coil clamps are provided for HV and LV windings ?
f) Whether steel rings are used for the windings ? If so, whether these are
split ?
g) Whether electrostatic shields are provided to obtain uniform voltage
distribution in the windings ?
h) Winding Insulation ( Type & Class )
i) Insulating material , used for
i) H.V winding
ii) LV winding
iii) Tapping connection
j) Insulating material used between
i) L.V and H.V winding
ii) Core & L.V winding
k) H.V to H.V winding between phases
l) Type of axial supports
i) H.V winding
ii) L.V winding
m) Type of radial supports
i) H.V winding
ii) L.V winding
n) Maximum allowable torque on coil clamping bolts
Sl.
Description Bidder's offer
No.
o) Clamping ring details
i) Thickness of ring mm
ii) Diameter of ring mm
iii) No. & size of pressure screw
p) Bare conductor size (mm)
i) HV
ii) LV
q) Insulated conductor size (mm)
i) HV
ii) LV
r) No. of conductor in parallel ( Nos.)
i) HV
ii) LV
s) No. of turns / phase
i) HV
ii) LV
t) No. of discs / phase
i) HV
ii) LV
u) No. of turns / Disc
i) HV
ii) LV
v) Gap between discs (mm )
i) HV
ii) LV
w) Inside diameter (mm )
i) HV
ii) LV
x) Outside diameter (mm )
i) HV
ii) LV
y) Axial height after shrinkage (mm )
i) HV
ii) LV
z) D.C Resistance
i) L.V winding at 750 C (Ohms )
ii) H.V winding at normal tap at 750 C (Ohms )
iii) H.V winding at highest tap at 750 C (Ohms )
iv) H.V winding at lowest tap at 750 C (Ohms )
Sl.
Description Bidder's offer
No.
v) Total I2R losses at 750 C for normal tap (KW )
vi) Total I2R losses at 750 C for highest tap (KW )
vii) Total I2R losses at 750 C for lowest tap (KW )
viii) Stray losses including eddy current losses in winding at 750 C (KW)
a) Normal tap position
b) Highest tap position
c) Lowest tap position
d) Any special measures, taken to reduce eddy current losses and stray
losses. Mention in details
ix) Load losses at 750 C (I2 R + Stray )
a) Normal tap position (KW )
b) Highest tap position (KW)
c) Lowest tap position (KW )
x) Details of special arrangement, provided to improve surge voltage
distribution in the windings.
44. DETAILS OF TANK :
a) Material of Transformer tank
b) Type of tank
c) Thickness of sheet (No approximate value to be mentioned)
i) Sides (mm)
ii) Bottom (mm )
iii) Cover (mm )
iv ) Radiators (mm)
d) Inside dimensions of main tank (No approximation in dimensions to be
used )
i) Length (mm)
ii) Breadth (mm)
iii) Height (mm )
e) Outside dimensions of main tank (No approximation in dimensions to be
used )
i) Length (mm)
ii) Breadth (mm)
iii) Height (mm)
f) Vacuum recommended for hot oil circulation (torr / mm of Hg)
g) Vacuum to be maintained during oil filling in transformer tank (torr / mm of
Hg)
h) Vacuum to which the tank can be subjected without distortion (torr / mm of
Hg)
i) No. of bi-directional wheels provided
j) Track gauge required for the wheels
i) Transverse axis
Sl.
Description Bidder's offer
No.
ii) Longitudinal axis
k) Type and make of pressure relief device and minimum pressure at which it
operates (Kpa )
45. CONSERVATOR :-
a) Thickness of sheet (mm)
b) Size (Dia x length ) (mm)
c) Total volume (Litres)
d) Volume between the highest and lowest visible oil levels (Litres)
PART – II
PRICE BID
1. PRICE:
(i) Bidders are required to quote their price(s) for goods offered indicating they are
‘FIRM’
(ii) The prices quoted shall be FOR Destination only at the consignee’s site/store
inclusive of packing, forwarding, Freight & Insurance. In addition, the break-up of
FOR Destination price shall be given as per schedule of Prices in Annexure-V of
Section – III. The Tenderer has to certify in the price bid that MODVAT benefit if
any, has been fully passed on to the Purchaser, while quoting the tender prices.
2. INSURANCE :
Insurance of materials/equipment , covered by the Specification should normally
be done by the Suppliers with their own Insurance Company unless otherwise
stated. The responsibility of delivery of the materials/equipment at destination
stores/site in good condition rests with the Supplier. Any claim with the Insurance
Company or Transport agency arising due to loss or damage in transit has to be
settled by the Supplier. The Supplier shall undertake free replacement of
equipment /materials damaged or lost which will be reported by the Consignee
within 30 days of receipt of the equipment /materials at Destination without
awaiting for the settlement of their claims with the carriers and underwriters.
3. CERTIFICATE FOR EXEMPTION FROM EXCISE DUTY/SALES TAX:
Offers with exemption from excise Duty/ Sales tax shall be accompanied with
authenticated proof of such exemption. Authenticated proof for this clause shall
mean Photostat copy of exemption certificates, attested by Gazetted Officers of
State or Central Government.
4. PROPER FILLING UP OF THE PRICE SCHEDULE:
(i) In case where Freight & Insurance charges are not furnished, 5% of the Ex-works
price shall be considered as the freight & Insurance charges.
(ii) The tenderer should fill up the price schedule (Annexure-V of Section-III) properly
and in full. The tender may be rejected if the schedule of price is submitted in
incomplete form as per clause-34 (ix) of Section-II of the Specification.
5. NATURE OF PRICE INDICATED IN SPECIFICATION SHALL BE FINAL.
The nature of price indicated in the Clause-13, Section – I of PART –I of the
Specification shall be final and binding.

Vous aimerez peut-être aussi