Vous êtes sur la page 1sur 1

Technical project management in WASH emergencies

YOUR DELIVERY PLAN for Drytera

Month 1 Month 2 Month 3 Month 4 Month 5 Month 6


Materials
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Cement (well
construction X X X X
materials)
Sand (well
construction X X X X
materials)
Gravel (well
construction X X X X
materials)
Borehole dip meter X

Drilling
consumables (in
X X X X X X X X
batches of 15 units,
4” diameter)
Hand pumps X X X X X X X X

Health & Safety


X
Clothing
Engineers tool kit X

Engineers first aid


X
kit
Delagua water
X
testing kit

Vous aimerez peut-être aussi