Académique Documents
Professionnel Documents
Culture Documents
I. INTRODUCTION .,
".O 5piJ 50 100
Commercial power system sometimes becomes abnormal due to (Cycle:SO&)
lij$tning to transmission lines and something like that. In such a
breaker. But the time to wait for fault clearing is about 0.2 seconds Fig. 1 A case of instantaneous voltage drop on load equipment
A. Measurement results
Test circuit is shown in Fig. 2. Commercial power system and in-
house generation system are connected via circuit breaker and new
equipment developed. Important load of in-house generation system
In case-1 of Fig. 3, generator’s voltage drop is too large. So tlus is
is set to be 75% of generator’s rated power and is simulated with a waveform that under voltage relay of in-house generator operates
before circuit breaker’s opening. Steady state condition remains for
water resistance. Instantaneous voltage drop is generated by short
10 cycles and then fault continues for 305 milliseconds.
circuit in the commercial power system side. Tests are executed
under two conditions to compare the performance of circuit breaker Case-2 of Fig. 3 is a waveform when this new equipment oper-
with that of new equipment. ated 15 milliseconds after the fault’s occurring and isolated com-
mercial power system from in-house generation system. When the
Case-1 : New equipment is short-circuited by switch-B. Perform-
instantaneous voltage drop occurs , generator’s voltage becomes low
ance of CGS and commercial power system is measured when they
30% for half a cycle with the voltage of commercial power system.
are isolated by circuit breaker. On the condition of switch4 off,
By this equipment’s fast isolating the power systems they become
generator is started and supplies 80kW load. Interconnecting switch
steady state in the next half cycle. Comparing with case-1, it was
is on. Then switch-A is closed for about 0.5 seconds long and the
confirmed that this equipment prevents instantaneous voltage drop
instantaneous voltage drop is generated. After 0.3 seconds from the
closing of switch-A, circuit breaker is opened. In these sequence of in-house generation system and made it possible for important
voltages and currents are measured. loads to be in stable operation.
Case-2: Switch-B is opened. Performance of CGS and commer-
cial power system when ths equipment works. Similarly as case-1, B. Simulation results
interconnection with commercial power system and CGS is devel-
oped and instantaneous voltage drop is generated. It will be con- In simulations using EMTP, circuit breaker and new equipment is
simulated with ordinary switch model and generator is simulated
92
Case Measured results S i m u l a t e d results
JCQV
0
-3CQv
-3ooO.4
360V
0
-360V
0 0.2 0.4 06 0 8 0 0.2 0.4 0.6 0 8 I
Time (5) Time ( 5 )
Generator‘s vollagc ( V c ) Generator‘s voltage (Vc)
3CQY JCQY
0
-3CQY
-3wv
2 Short-crrcuilcurrcn( ( I C )
-zmAt’
0 0 2 0.4 0 6
-0 8 I
T i c Is)
4. aMW
3. 6MVar
age drops and that under 50% occupies about 80%. High speed
A . Simulation conditions
93
interruption by this equipment, loads equipment is not affected from
B. Simulation results instantaneous voltage drop and the voltage rise after interruption
is lower.
For the conditions of instantaneous voltage drop 20 % and 50 %,
simulations were performed with circuit breaker connecting buses
and this equipment respectively. In Fig. 6 are shown generator‘s V. CONCLUSION
voltage simulated and influence of instantaneous voltage drop for
various loads mentioned above. And for each condition, maximum In the factory, performance test of high speed switch gear was
voltage drop in faulted period and voltage rise are shown in done. From these results, it was confirmed that this equipment can
Table 2. In simulated waveform of Fig. 6, voltage amplitude is restrain voltage drop of the important loads within one cycle by
oscillating as an dluence of transient b e c t current component the means of tnpping the short circuit current within one cycle, when
subtransient period (Td”=35 milliseconds). the voltage drops under the settmg value. Then, comparison be-
On the condition of voltage drop of 20 %, if these systems are tween measured results and simulated results by EMTP is repre-
interrupted by circuit breaker, high voltage discharge lamp is af- sented, From thls comparison, it was confiied that performance
fected by voltage drop. But intempted by ths equipment, it is not verification of this equipment using EMTP is effective.
affected. Then,dluence of voltage drop (20% and 50%)on loads is inves-
On the condition of voltage drop of 50 YO,most load equipment tigated by simulating transient voltage change of the generator. As a
is affected from voltage drop. As voltage rise after intemption is
greater than 20 YO,there is a possibility that over voltage protective
relay operates according to time delay setting. But in the case of
I I I 1 I I
i
PM
Voltagedrop 23.5% 14.1% 20.0% 7.8% 1 0 >
20% Regulating rate lO[’i]
I I I I I
Voltage drop 50.9% 26.8% 50.0% 9.7%
50%
Fig. 5 Generator control circuit
1.4
1.2
1
0.8
0. 6
Electromedical apparatus
0.4
Voltage drop
0.2 occurrence
I
0 ‘ Ji I I
0.01 0.1 1 10
Time (s)
94
1.4
1.2
0.2
Voltage drop
occurrence I - :Circuit breaker
0
0.01 0.1 1 ~ 10
Time (s)
Fig. 6 Simulated results
(b) Voltage drop : 50%
95