 Data terukur yang dibutuhkan adalah t, RH, n/N, u, LL

 Rumus : ETo = C . ETo*

ETo* = w (0,75Rs – Rn1) + (1-w)f(u)(ea - ed)

Rs = (0,25 + 0.54n/N)Ra

Rn1 = f(t). f(ed). f(n/N)

f(t) = s. Ta4

f(ed) = 0.34 – 0.044 ed1/2

ed = ea . RH

f(n/N) = 0.1 + 0.9 n/N

f(u) = 0.27(1+U/100)

Dengan

ETo = evaporasi potensial (mm/hari)

c = Faktor koreksi

ETo* = evaporasi (mm/hari)

Suhu (t) ea w f(t) Suhu (t) ea w f(t)


mbar mbar
24.0 29.85 0.735 15.40 26.6 34.83 0.761 16.02
24.2 30.21 0.737 15.45 26.8 35.25 0.763 16.06
24.4 30.57 0.739 15.50 27.0 35.66 0.765 16.10
24.6 30.94 0.741 15.55 27.2 36.09 0.767 16.14
24.8 31.31 0.743 15.60 27.4 36.50 0.769 16.18
25.0 31.69 0.745 15.65 27.6 36.94 0.771 16.22
25.2 32.06 0.747 15.70 27.8 37.37 0.773 16.26
25.4 32.45 0.749 15.75 28.0 37.81 0.775 16.30
25.6 32.83 0.751 15.80 28.2 38.25 0.777 16.34
25.8 33.22 0.753 15.85 28.4 38.70 0.779 16.38
26.0 33.62 0.753 15.90 28.6 39.14 0.781 16.42
26.2 34.02 0.757 15.94 28.8 39.61 0.783 16.46
26.4 34.42 0.759 15.98 29.0 40.06 0.785 16.50

Tabel 5 : Hubungan t dengan ea, w, f(t)


Tabel PN.3 : Angka Koreksi ( c ) untuk Rumus Penman

Tabel 10 Nilai Ra ekivalen dengan evaporasi dalam mm/hari

Contoh Perhitungan Evapotranspirasi Potensial

Data diambil pada bulan januari

Diketahui : - Temperatur Udara (°C) = 27.8°


- Kelembapan Relatif (RH) % = 68%
- Penyinaran Matahari (n/N) = 76
- Kecepatan Angin "U" (m/detik) = 2.448 m/s
- Kecepatan Angin "U" (km/hari) = 211.515 km/hari
- ea (table 5) 27.8° = 37.37 mbar
- W (table 4) 27.8° = 0.773
- Ra (table 2 atau 10) = 16.10
- F(t) Tk (Tabel 13) = 16.26

Ditanyakan : Evapotranspirasi Potensial (et0)

Jawab : Rumus ETo = C . ETo*

 ETo* = w (0,75Rs – Rn1) + (1-w)f(u)(ea - ed)


 Rs =(0.25 + 0.54 n/N) x Ra
Rs = (0.25 + (0.54 x 76%)) x 16.10
= 10.63
 Rns = (1-a) x Rs mm/hari (a=0,25)
= (1 – 0.25) x 10.63
= 7.97
 f(u) = 0.27(1+U/100)
= 0.27 (1+ 2.448/100)
= 0.277
 ed = ea . (RH/100)
= 37.37 x (68/100)
= 25.41
 F(ed) =0.34 - 0.44 √ed
= 0.34 – ( 0.44 x √25.41 )
= 0.118
 f(n/N) = 0.1 + 0.9 n/N
= 0.1 + ( 0.9 x 76%)
= 0.78
 Rn1 = f(t). f(ed). f(n/N)
= 16.26 x 0.118 x 0.78
= 1.51
 Ud day atau U night dilihat dari tabel 16 = 2
 C (tabel PN.3) = 1.1
 ETo* = w (0,75Rs – Rn1) + (1-w)f(u)(ea - ed)
= 0.773 ((0.75 x 10.63) – 1.51) + (1- 0.773) x 0.277 x 11.96
= 5.750
 ETo = C. ETo*
= 1.1 x 5.750
=6.325 mm/hari
 ETo = 6.325 x 31 hari
= 196.074 mm/bulan