Vous êtes sur la page 1sur 11

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/320552246

Comparative Study of ANFO Versus Emulsion Use in Anisotropic Jointed


Rock Mass

Conference Paper · April 2017

CITATIONS READS

0 116

2 authors, including:

Tawanda Zvarivadza
University of the Witwatersrand
50 PUBLICATIONS   13 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Productivity in platinum mining View project

Digital Mining View project

All content following this page was uploaded by Tawanda Zvarivadza on 21 October 2017.

The user has requested enhancement of the downloaded file.


T. Chikande, T. Zvarivadza

Comparative Study of ANFO Versus Emulsion Use in Anisotropic


Jointed Rock Mass

T. Chikande, T. Zvarivadza
University of the Witwatersrand, Johannesburg, SA

ABSTRACT Appropriate choice of an explosive is critical in blasting to come out with stable
excavations at the same time meeting production requirements. Since inception, the studied
mine has been using ANFO as the main blasting agent in primary blasting. As mining
progresses, there is a general deterioration of ground conditions, hence there is need to find an
explosive with energy to just break the rock into the required fragments and at the same time
avoiding surrounding rockmass disturbances. This study compared and contrasted Emulsion
and ANFO use in bad ground conditions. The following comparisons were made for both
types of explosives: mining profiles after blasting, the effects of explosives on the rock mass,
advance per blast, fragmentation, re-entry periods and charging time per end. The research
approach entailed the following: extensive literature review, data collection, measurements
and observations, trials for the selected alternative explosive were conducted and results
collected were compared with its target, the mine’s target and the mine’s actual results using
ANFO. Trials for bulk emulsion were carried out in two sections operating in bad ground
conditions. The results gathered and analyzed showed that, technically, emulsion explosives
are beneficial but the increase of operational cost down-weighs them. However, in solution to
the problem which prompted this research, the authors suggest the mine to take up emulsion
as it promotes safety at higher productivity in terms of tonnage output.
1 INTRODUCTION the mining industry, there was need to reflect
Sound mining practices based on the on the suitability of the current generation of
appropriate choice of explosive energy lead explosive to the ground conditions that the
to significantly safer mining operations. The mine is now experiencing. The accident
selection of the exact charge mass, explosive statistics gathered as from 2012 shows that
type and blasting pattern is imperative in the greatest share of accidents is coming
mining the desired slice, thereby reducing from fall of ground incidents (FOG) as
stoping overbreak and subsequently shown in Figure 1, thereby making it an area
minimizing Platinum Group Elements (PGE) of concern.
dilution. ANFO explosive is used in
numerous mines due to its simplicity of use.
The area of research is sited on the Great
Dyke of Zimbabwe and is infested by faults
and sympathetic joints. PGEs are the primary
metals exploited and base metals are also
recovered as secondary commodities. The
Zimbabwean Great Dyke is the second
prominent reserve of PGEs following the
South African Bushveld complex (Oberthür
et al, 2012). The widespread section of the Figure 1. Summary of accidents by cause at
Great Dyke is nearly bowl shaped and the mine
encompasses strata that are dipping towards
the axis. The Dyke extends for about 550km 1.1 Mining Operations Overview
having a maximum width of 11km
(Prendergast, 1989). Zero harm and The study was carried out at a shallow
innovation being some of the core values in underground mine with its operations carried
out less than 200m from the surface. The
43
IMCET 2017 / ANTALYA / TURKEY / April 11-14

mining method and the cycle of drilling,


blasting, lashing and supporting are all
described in this section.
1.1.1 Mining method
The mining method utilized at the studied
mine is room and pillar. Mining operations
are carried out from the main decline
advancing towards the strike direction. The
main decline divides the mine into two Figure 3. Drilling pattern
regions, the northern part and the southern
region. The size of the rooms mined varies 1.1.3 Charging and blasting
with ground quality. Figure 2 shows the
standard mining layout used in poor ground After drilling the holes, water is pumped out
conditions. The stoping height is maintained of the holes and the holes are cleaned up.
at 2m to avoid PGMs dilution. In case of Shock tubes with detonators at both ends
poor ground conditions, twin gullies which called dual dets are used, inserted in
are 6m wide are mined leaving in situ pillars megamite cartridges to form a primer. ANFO
of 3m by 3m. Drives were developed from is then used to charge the drilled holes.
the main decline to the working areas. ANFO is a high energy explosive and its
effects will be described in the next sections.
The authors looked at the explosives
currently used at the mine. High gas
explosives widen the joints leading to the
unravelling of rocks which results in a
decrease in safety and productivity. Figure 4
presents FOG trend at the mine for years
2005 to 2016.

Figure 2. Mining layout for a 6m stope


1.1.2 Drilling
Drilling rigs are used to drill 51 holes with a
diameter of 45mm. Three of these holes are
enlarged to 102mm to give a second free
face. A gulley is first marked after being
cleaned up by LHDs and after all support
installation has taken place. The length of
holes drilled is 3.2m to give an advance of Figure 4. FOG trend at the mine (2005-2016)
2.8m to 3m. The average spacing is 0.5m
while the burden is 0.67m. Figure 3 shows Due to the rising FOG incidents (Figure 4),
the drilling pattern followed at the mine. the rock mechanics department came up with
Drilling accuracy is critical to have a good number of interventions such as changing
advance and also for maintaining the regional pillar dimensions, span reduction
designed stoping height. Timing is then done and installation of 4m spiling bolts after
by connecting the shock tubes according to every blast in poor ground conditions to
the pattern shown. work in conjunction with resin bolts. In as
much as an explosive is very essential in a
mining set up to break the ground, it can also
pose greater risk of worsening/damaging the
44
T. Chikande, T. Zvarivadza

rockmass thereby creating a hazardous mechanical impacts during mechanical


working environment for employees. Due to loading to drill holes (Mather, 1997). ANFO
augmented generation of bad hangings and has also some disadvantages which include
the unpredictable unravelling of loose rocks, lack of water resistance and low detonation
there was need to find an explosive with parameters which reduce their range of use
energy to just break the rock into the to dry blasting holes in truncated
required fragments and at the same time compactness rock masses (Maranda, 2011).
avoiding surrounding rockmass disturbances. In a bid to improve the mining practices, the
authors reviewed the other bulk explosives
1.2 Study Aim and Objectives which include bulk emulsion (UG100). The
merits of bulk emulsion explosive over
The study was undertaken with the main aim ANFO and packaged products include easy
to improve the company Key Performance transportation, handling, string charging, low
Indicators (KPIs) of safety and production. gas emissions, water resistant, full coupling,
This was achieved through a comparative increased velocity of detonation, detonator
study of ANFO versus Emulsion use in sensitivity and improved work environment
anisotropic jointed rock mass at the mine. To (Maranda, 2011).
achieve the main aim, the following A study was carried out to find out the
objectives were set: effect of ANFO on the supporting systems
• To compare mining profiles after blasting used in anisotropic jointed rock mass. ANFO
(Emulsion vs ANFO) is well-known for generating a lot of gases
• To Analyse the effects of explosives on the therefore widening the cracks thereby
rock mass affecting the half cast factor. The preliminary
• To measure and compare advance per blast review of ANFO shows that it will result in a
for ANFO (currently in use) against frequent number of keyblocks which will
emulsion. lead to an unstable hangingwall (Bohanek, et
• To compare fragmentation for ANFO al., 2013). In addition, the cut slice will
relative to Emulsion increase due to overbreak and more bad
• To compare re-entry periods hangings will be formed which require
• To compare charging time per end. intense barring down.
2 RELEVANT LITERATURE SURVEY Bulk emulsion comprises of oxidizer
solution droplets suspended in incessant fuel
Safety, production and costs are the most phase (Budin, 2009). Droplet sizes are orders
significant parameters when evaluating the of size smaller than ammonium nitrate prills
overall mining operation. ANFO is a and are soothed with emulsifiers. Budin
supreme explosive used in the mining (2009) pointed out that emulsion can be
industry than most common bulk explosive sensitized by Microballoons, blending with
because it is cheap, easy and safe to handle ANFO or gassing for underground
(Sellers, 2011). ANFO is unfortunately application such as the studied mine.
hygroscopic and despite a lot of efforts being
made to add ingredients in order to increase 2.2 Reflections on Explosive
the water resistance, this has only succeeded Characteristics in Jointed Areas
to a marginal degree.
ANFO is often regarded as a substantially
2.1 Explosives properties copious gas explosive than bulk emulsions
and is thought to cause extensively longer
Various explosives have different cracks, thereby damaging the hangingwall
magnitudes of shock energy as well as gas further (Sellers, 2011). ANFO has a lower
energy (Bohanek, et al., 2013). The merits of detonation pressure and a slower delivery of
using ANFO include simple production, energy than other bulk explosives. The
cheaper and its lack of sensitivity to consequence of this will result in less
45
IMCET 2017 / ANTALYA / TURKEY / April 11-14

expansion of the blast hole by the shock ∑


n
Li
wave and leaving energy for driving crack HCF = i =1
n
(1)
growth and heaving of the fragments that ∑ L
r =1 r

have been created (Szendrei, et al., 2006). Where; HCF = Half cast factor
The extensive driving force that acts on the Li = Post-blast drill mark length
borehole widens the fractures. It is visible (m)
imperative to note that the densities of Lr = Pre-blast drilled length (m)
ANFO and bulk emulsion are different,
hence they deliver different amounts of 3 STUDY APPROACH
energy at different stages during their It is the aim of the study to optimize blasting
reaction process. The stability of an at the studied mine for safety’s sake while
excavation is not only determined by the not neglecting other parameter changes
blast induced fractures, but also by the accompanied. Described herein is the
anisotropic jointed rock mass. The formation research criterion and techniques used in
of argumentative hangingwall conditions in collecting necessary and sufficient data in
any given mining scenario can be changed to order to fulfil this study’s aim.
some degree by the correct choice of
explosive type, drill holes diameter and 3.1 Research Criterion
round design. Minimum overbreak with good
perimeter blasting can be achieved through • The research started off with an extensive
smoothwall blasting (Lee, et al., 1993). literature review related to the study.
Smoothwall blasting works more efficiently • Data collection, measurements and
with bulk emulsion hence the need to observations
compare the blasting results. The damage • Trials for the selected alternative were
conducted and results were collected and
extent depends on the rock characterisation a comprehensive comparison was carried
and the in situ geological settings. In smooth out against the mine’s actual results using
wall blasting, the final row of holes contains ANFO.
a lighter than normal charge and should be • Trials for bulk emulsion were carried out
fired after the main charge is completed in in North 1(N1) and North 7 (N7) for the
order to limit the confinement of the holes following reasons:
and minimise damage back into the -these are adjacent sections hence easier for
the two to share the 1.5t main charging unit
sidewalls. Hustrulid and Iverson (2010) (MCU).
pointed out that the accomplishment of - All of them are operating in bad ground
smoothwall blasting pivots on sound design conditions.
of blasting parameters.
3.2 Collection of Current Blast Output
2.3 Half Cast Factor
Data collection techniques for the study
Half cast factor is defined as the ratio of the included observations and data capturing
total visible drill barrel length in the pertaining to the blast output which lies in
sidewalls and hangingwall after blast and the the hands of safety and production. Collected
total drilling length (Dey and Murthy, 2010). data gave the following:
Half cast factor is vital in the determination i. Advance per blast
of stoping overbreak. Singh (1992) pointed ii.Powder factor
out that blasting can be described as a iii.Fragmentation
destructive process and the effects of blast iv.Half cast factor
damage are deleterious to both safety and
productivity. The authors measured the
length and number of barrels and determined
the half cast factor using equation 1, as given 3.3 Measurements and Calculations
by Mcknown (1984).

46
T. Chikande, T. Zvarivadza

3.3.1 Pre-blasting • Total primers mass (kg) per day – physical


counting of primers used per end.
• Hole diameter (mm) – was measured using • Charged column length (m) – subtract
a vienier calliper. stemming length from drilled length.
• Gulley length (m) – was measured using a • Column charge (kg/m3) – to be calculated
distometer which measures to the nearest from data captured on the blast
mm measurement form.
• Mining width (m) – was measured using a • Volume of column charge (m3) per hole.
distometer • Mass of explosives – column charge/hole
• Holes depth (m) – was measured using a (kg) recorded on the MCU.
5m tape. • Total mass of explosive/section – was
• Burden (m) and spacing – were measured calculated from the data captured on the
using a 5m tape. blast measurement form.
• Advance (m) per blast – subtract distance • Total cost of explosives/gulley – was
from peg to face before blast from calculated from cost of explosives by the
distance from peg to face after blast. planning department.
• Blasts per day- were captured on daily • Explosives cost/t - (USD) was calculated
blast measurement form. from cost of explosives and the blasted
• Average No of holes/panel – physical tonnage.
counting on the face.
• Average meters drilled/day (m) – was 4 RESULTS AND ANALYSIS
captured on daily blast measurement
form. The results and analysis of the trial findings
• Tonnes per blast – calculated from data are given in this section. Table 1 shows a
captured on the blast measurement form. snapshot of the data collected from north 1
• Tonnes per day – calculated from data section during the month of May. Figure 5
captured on the blast measurement form. shows the advance per blast trend during the
• Half cast factor – calculated from data month of April 2016. The average advance
captured on the blast measurement form. per blast during the first month of trial (thus
April 2016) was 2.85m. This was lower than
3.3.2 Blasting the targeted 3.0m mainly due to calibration
fault on the MCU causing holes to be
• Stemming length (m) – was measured undercharged and also poor charging hose
using a one meter clino rule. handling as employees were still
• Polypipes/ round – physical counting of acclimatizing with the new charging system.
perimeter holes.

Table 1. Sample of the collected data from one section

47
IMCET 2017 / ANTALYA / TURKEY / April 11-14

4.1 April 2016 Results and Analysis


4.1.1Advance per blast

Figure 6. April trend in half cast factor


Figure 5. April trend in advance 4.1.3 April powder factor
4.1.2. April half cast factor Powder factor refers to the amount of
explosives used to break one tonne of rock.
Half cast factor is a measure of the blast Figure 7 shows the trend in powder factor for
induced over break. The half cast factors the 2 sections in April 2016. The powder
were determined using Equation 1. Figure 6 factor averaged 1.704kg/t against a target of
shows the half cast factor trend for the month 1.6kg/t. The powder factor was above the
of April. From the graph, it can be noted that desired as a result of the aforementioned
the average half cast factor for the month minimum advance.
was at 23.5%, which was below the target of
50%. Overbreak is predominantly affected
by the properties of the host rock, blast
design and explosive parameters (Dey and
Murthy, 2010). Rock mass characterisation
played a crucial part in lowering the half cast
factors since operations were carried in
geotechnically poor grounds.

Figure 7. April trend in powder factor


4.2 May 2016 Results and Analysis
48
T. Chikande, T. Zvarivadza

4.2.1 Advance per blast


The linear advance increased during the
second month of the trial to 2.95m against a
budget (minimum linear advance planned
for) of 2.8m. Figure 8 shows the advance per
blast trend during the month of May.

Figure 10. May Trend in powder factor


4.3 June 2016 Results and Analysis
4.3.1 Advance per blast
The linear advance increased during the
month of June to 3.01m against a budget of
2.8m. Figure 11 shows the advance per blast
trend during the month of June 2016.
Figure 8. May trend in linear advance
4.2.2 May 2016 half cast factor
Figure 9 shows the trend in half cast factors
during the month of May. The half cast
factor figures were again below the targeted
50% as a result of the prevailing geological
discontinuities.

Figure 11. June trend in linear advance


4.3.2 June 2016 half cast factor
Figure 12 shows the trend in half cast factors
during the month of June 2016. The half cast
factor figures were again below the targeted
50% because smoothwall blasting was not
Figure 9. May trend in half cast factor yet implemented.
4.2.3 May 2016 powder factor
Figure 10 shows the trend in powder factor
during the month of May against a target of
1.6kg/t. The results increased as a result of
the improved advances.

Figure 12. June trend in half cast factor


49
IMCET 2017 / ANTALYA / TURKEY / April 11-14

4.4 Summary of Results 2. The average time taken to charge an end


also decreased from an average of 23
The trial continued to the month of August minutes using ANFO to an average of 13
and significant changes were noted. Average minutes, saving an average of 30 minutes
linear advance for the whole trial was 3.07m within the mining cycle per team, since 3
which was above the targeted advance of (6m gulleys) ends are charged per shift.
3.0m. The achieved advance was found to be
95.9% of the drilled length of 3.2m. The
average powder factor for the whole trial was 3. The increase in explosive quantity utilized
1.83kg/t, which is above the target of per end increased the powder factor to
1.66kg/t. The difference is attributed to the 1.83kg/t despite the increase in advances
subsequent decrease in the span as a result of from 1.66kg/t.
geotechnically poor ground conditions. The
targeted half cast factor was not achieved 4. The scaling time of bad hangings dropped
due to bad grounds and the lag in purchasing remarkably. The time decreased from an
polypipes for smoothwall blasting. The average of 40 minutes to 11 minutes. This
average half cast factor for the whole trial was accounted due to a reduction in the
was 20%. generation of bad hangings brought about
by the use of emulsion.
4.4.1 Blasting profile 5. The half cast factor had an average of 20%
which was below target. Observations
Minimum overbreak into the hanging wall, made show that the board profiles were
footwall, and sidewall were observed during fairly smooth as compared to those
emulsion charging compared to ANFO produced with ANFO. Table 2 compares
loading. Visible barrels were evidence of emulsion explosives with ANFO. Table 3
reduced blast over break. Profiles that were presents cost per blasted tonnage for a 6m
not smooth were observed in extremely poor gulley.
grounds, thus regions with a tunnelling index
less than 0.4. There was reduced throw from 4.6 Comparison of explosives
emulsion explosives compared to ANFO
which actually lessened LHD lashing and Table 2. Emulsion vs ANFO
scraping time.

4.4.2 Fragmentation

Bulk emulsion proved that 97% of the


blasted ore can pass through the
400mm×400mm grizzly apertures without
difficulties compared to 94% from ANFO
charging.

4.5 Study findings

The study done was to a greater extent


conclusive to the following findings:
1. Advance improved from an average of
2.80m using ANFO to an average of 3.0m
using emulsion explosive. This increased
the blasted tonnage from 105t to 113t per
6m end.

50
T. Chikande, T. Zvarivadza

Table 3. Cost per blasted tonnage for a 6m output. A cost benefit analysis clearly
gulley pinpoint to the implementation of emulsion
as a result of optimized KPIs. By making the
effort to implement cautious blasting
practices in tunnel development, the amount
of overbreak is limited, which improves rock
mass conditions and support integrity with
the spin-off of reduced support and
remediation costs, thereby better project
feasibility. The following recommendations
arise from the study:
• At a later stage of the trial, a change of the
drilling pattern to one with a reduced
burden between the lightly charged
The expected tonnage from a 6m gulley after perimeter holes and the next line of
charging with ANFO is 105.84 tonnes; production holes should be implemented
therefore the explosive cost per blasted to further improve the state of remaining
tonnage is $2.23 per tonne. The expected wall.
tonnage from a 6m gulley after charging with • Overtime, there is also need that the trials
emulsion is 113.4 tonnes, which corresponds be carried out in areas of good ground, so
to an explosive cost per blasted tonnage of that specific results for these areas can be
$2.48 per tonne. The study was aimed at obtained for analysis to strengthen the
improving safety through reduction of FOG argument to implement change in
influenced accidents. The implementation of explosive to the whole mine.
bulk emulsion offers additional • The mine should consider using the
improvements in some areas that the mine emulsion explosive in conjunction with a
has been facing such as minimum advance, more powerful and small diameter primer
poor fragmentation and high powder factor. like pentolite booster instead of megamite
Emulsion explosives pose high operating 38 cartridges so as to improve on wall
costs and capital cost as compared to ANFO, smoothness and get even better results out
however, the performance results attained of emulsion explosives.
through this trial show that the use of • Mechanical scalers are also critical for
emulsion as the main column charge is a safety of employees during barring down
worthy sacrifice which will yield benefits process.
over a certain period of time. The high
OPEX and CAPEX cannot be compared to REFERENCES
the savings that the mine would have
realized in achieving the goal of zero harm Bohanek, V., Dobrilovic, M. and Skrlec, V., 2013.
Influence of the Initiation Energy on the Velocity
through avoiding or minimizing FOG related of Detonation on ANFO explosives. Central
accidents. European Journal of Energetic Materials, vol.10,
no.4, pp. 555-567.
5 CONCLUSIONS Budin, M., 2009. The Benefits of Bulk Emulsion
Explosives in UndergroundApplications through
The results gathered and analyzed showed String Loading. [Online]
that, technically, emulsion explosives are Available at:
http://www.infomine.com/library/publications/do
beneficial but high operational and capital cs/budin-sme2009.pdf
costs down-weigh them. The authors [Accessed 9 March 2016].
recommend the mine to take up emulsion in Dey, K. and Murthy, V. M., 2010. Investigations on
solution to the problem which prompted this impact of Blasting in tunnels. International
research since this explosive promotes safety Journal of Geotechnical Earthquake Engineering,
at higher productivity in terms of tonnage vol. 1, no. 2, pp. 59-62.

51
IMCET 2017 / ANTALYA / TURKEY / April 11-14

Hustrulid, W. A. and Iverson, S. R., 2010.


Evaluation of Kiruna mine drifting data using the
NIOSH design approach. In: Sanchidrián, ed.
Rock Fragmentation by Blasting. London: Taylor
and Francis Group, pp. 498-504.
Lee, J., Holmberg, R. and Persson, P., 1993. Rock
Blasting and Explosives. Boca Raton, CRC.
Maranda, A., 2011. ANFO Detonation Parameters.
Central European Journal of Energetic
Materials, vol 8, no. 4, pp. 280-291.
Mather, W., 1997. Bulk Explosives. [Online]
Available at:
https://miningandblasting.files.wordpress.com
[Accessed 13 March 2016].
McKown, A., 1984. Design and evaluation of
perimeter controlled blasting in fractured and
weathered rock. In: Explosives and blasting
techniques, pp. 261-267.
Oberthür, T., Melcher, F., Buchholz, P. & Locmelis,
M., 2012. The oxidized ores of the main sulphide
zone, great dyke, zimbabwe: turning resources
into minable reserves. [Online]
Available at:
http://www.saimm.co.za/Conferences/Pt2012/647
-672_Oberthur.pdf
[Accessed 18 May 2016].
Prendergast, M. D., 1989. The Wedza-Mimosa
platinum deposit, Great Dyke, Zimbabwe. In:
Magmatic Sulphides-the Zimbabwe volume. 1 ed.
London: Institution of Mining and Metallurgy,
pp. 43-69.
Sellers, E. J., 2011. Controlled blasting for enhanced
safety. The Journal of The Southern African
Institute of Mining and Metallurgy, vol. 111,
no.1, pp. 11-16.
Singh, S. P., 1992. Mining industry and blast
damage. Journal of Mines, Metals and Fuels, vol.
1, no. 12, pp. 465-468.
Szendrei, T., Sellers, E. J. and Cunningham, C.,
2006. European Federation of Explosive
Engineers Conference. Vienna, EFEE.

52
View publication stats

Vous aimerez peut-être aussi