Académique Documents
Professionnel Documents
Culture Documents
Date: 3-May-18
Subject: Cost Comparison using
I. CIVIL WORKS
1 Concrete Works
MATERIAL COST: Concrete Mix, 3000 Psi G-1 (7 days-High Early Strength Concrete)
1 m3 - Concrete Ready Mix G-1 3000 Psi @ 7 days (RMC Supp X 4,274.87
EQUIPMENT COST:
TOTAL VOLUME =
MATERIAL COST: Concrete Mix, 3000 Psi G-3/4 (7 days-High Early Strength Concrete)
1 m3 - Concrete Ready Mix G-3/4 3000 Psi @ 7 days (RMC SuX 4,450.00
EQUIPMENT COST:
F-1 8
F-2 58.8
F-3 110.2
C-2 60 30
C-3 65 26
Deformed Bar 10mm x 6.00m G-40 194 1.00 194 = 194 pcs
Deformed Bar 16mm x 6.00m G-40 257 1.00 257 = 257 pcs
TOTAL WEIGHT
MATERIAL COST:
Consumables X 2%
LABOR COST:
TOTAL RATE
EQUIPMENT COST:
HAULING OF MATERIALS
TOTAL AREA =
Consumables X 0.05
LABOR COST:
TOTAL RATE
EQUIPMENT COST:
HAULING OF MATERIALS:
TOTAL AREA =
Consumables X 0.05
LABOR COST:
TOTAL RATE
EQUIPMENT COST:
HAULING OF MATERIALS:
3 Concrete Ready Mix G-3/4 3000 Psi @ 7 days (RMC Supplier) 12.06
Volume Unit
1.10 m3
8.32 m3
19.80 m3
29.22 m3
P/m3 = 4,274.87 P/m3 Concrete Ready Mix G-1 3000 Psi @ 7 days (RMC Supplier)
= 4,274.87 P/m3
= 4,274.87 P/m3
= 102.74 P/mh
= 334.98 P/mh
= 555.00 P/mh
= 85.11 P/mh
= 468.12 P/m3
= 468.12 P/m3
= 36.00 P/m3
= 36.00 P/m3
= 4,778.99 P/m3
1.58 m3
3.96 m3
4.58 m3
1.94 m3
12.06 m3
P/m3 = 4,450.00 P/m3 Concrete Ready Mix G-3/4 3000 Psi @ 7 days (RMC Supplier)
= 4,450.00 P/m3
= 4,450.00 P/m3
= 102.74 P/mh
= 334.98 P/mh
= 555.00 P/mh
= 85.11 P/mh
= 468.12 P/m3
= 468.12 P/m3
= 36.00 P/m3
= 36.00 P/m3
= 4,954.12 P/m3
20mmØ 25mmØ
C 3rd Gen.
= 0.72 P/kg
= 36.16 P/kg
= 36.16 P/kg
= 91.67 P/mh
= 98.27 P/mh
= 10.48 P/kg
= 10.48 P/kg
= 2.06 P/kg
= 2.06 P/kg
= 46.64 P/kg
Area Unit
22.40 m2
48.00 m2
46.80 m2
16.80 m2
134.00 m2
= 82.13
= 1,724.70 P/m2
= 1,724.70 P/m2
3= 574.90 P/m2
= 167.49 P/mh
= 167.49 P/mh
= 358.37 P/m2
= 358.37 P/m2
= 34.25 P/m2
= 34.25 P/m2
= 967.52 P/m2
Area Unit
4.20 m2
26.25 m2
36.90 m2
67.35 m2
= 33.28 P/m2
= 715.61 P/m2
= 715.61 P/m2
3= 238.54 P/m2
= 167.49 P/mh
= 167.49 P/mh
= 278.47 P/m2
= 278.47 P/m2
= 34.25 P/m2
= 34.25 P/m2
= 551.26 P/m2
m3 4,274.87 124,894.60
m3 4,450.00 53,649.20
TOTAL = 390,796.34
BOQ = 504,143.26
BALANCE = 113,346.92
MTO UNIT UNIT COST
I. CIVIL WORKS
1 Concrete Works
COMPUTATION: Length
FOOTING: PRECAST
F-1 1.00
F-2 1.20
F-3 2.00
MATERIAL COST: Concrete Mix, 3000 Psi G-1 (7 days-High Early Strength Concrete)
1 m3 - Concrete Ready Mix G-1 3000 Psi @ 7 days (SMIP BATCHING PLANT)
RATE: 1 Foreman @
4 Carpenter Mason @
8 Helper @
13 Manpower
1 Crew - Pouring @
EQUIPMENT COST:
PEDESTAL: PRECAST
C-1 0.30
C-2 0.30
C-3 0.30
C-5 0.30
TOTAL VOLUME
MATERIAL COST: Concrete Mix, 3000 Psi G-3/4 (7 days-High Early Strength Concrete)
1 m3 - Concrete Ready Mix G-3/4 3000 Psi @ 7 days (SMIP BATCHING PLANT)
RATE: 1 Foreman @
4 Carpenter Mason @
8 Helper @
13 Manpower
1 Crew - Pouring @
EQUIPMENT COST:
C-1 1.70
C-2 1.70
C-3 1.70
C-5 1.70
TOTAL VOLUME
MATERIAL COST: Concrete Mix, 3000 Psi G-3/4 (7 days-High Early Strength Concrete)
RATE: 1 Foreman @
4 Carpenter Mason @
8 Helper @
13 Manpower
1 Crew - Pouring @
EQUIPMENT COST:
10mmØ
REBARS_MARCOS HIGHWAY DRIVETHRU
6.00m 7.50m
FOOTING: PRECAST
F-1
F-2
F-3
PEDESTAL: PRECAST
C-1 26.66
C-2 60
C-3 65
C-5 42.67
LIFTING EYE
F1/C1
F2/C1
F2/C2
F2/C3
F3/C3
F3/C5
TOTAL WEIGHT
MATERIAL COST:
Consumables
LABOR COST:
RATE: 1 Steelman @
1 Manwork - Fabrication @
1 Manwork - Installation @
EQUIPMENT COST:
HAULING OF MATERIALS
COMPUTATION: Length
PEDESTAL: PRECAST
C-1 0.300
C-2 0.300
C-3 0.300
C-5 0.300
TOTAL AREA
Consumables
LABOR COST:
RATE: 2 Carpenter @
1 Crew - Fabrication @
1 Crew - Installation @
1 Crew - Stripping @
EQUIPMENT COST:
HAULING OF MATERIALS:
1 m2 - Hauling of Formworks
COMPUTATION Length
FOOTING: PRECAST
F-1 1.00
F-2 1.20
F-3 2.00
TOTAL AREA
Consumables
LABOR COST:
RATE: 2 Carpenter @
1 Crew - Fabrication @
1 Crew - Installation @
1 Crew - Stripping @
EQUIPMENT COST:
HAULING OF MATERIALS:
1 m2 - Hauling of Formworks
PEDESTAL:
C-1 1.700
C-2 1.700
C-3 1.700
C-5 1.700
TOTAL AREA
Consumables
LABOR COST:
RATE: 2 Carpenter @
Services @
1 Crew - Fabrication @
1 Crew - Installation @
1 Crew - Stripping @
EQUIPMENT COST:
HAULING OF MATERIALS:
1 m2 - Hauling of Formworks
SUMMARY OF MATERIALS TAKE-OFF:
2 Concrete Ready Mix G-3/4 3000 Psi @ 7 days (SMIP BATCHING PLANT)
11 CWN Assorted
12 Form Oil
1)
Equipment time include loading & unloading of construction materials from SMIPC Warehouse in Sta. Maria, Bulac
2) Additional time of 1-hours for loading & unloading time and 1 hours travel time from SMIPC to Project site area
1.0 First batch of delivery & hauling of Pre-Cast Footing/Pedestal items from SMIP Sta. Maria, Bulacan to KFC Cavite
4 pcs - Pre-Cast Footing/Pedestal: F3/C3, Footing size: 2.00m W x 2.00m L x 0.30m thk.; Pede
3 pcs - Pre-Cast Footing/Pedestal: F2/C2, Footing size: 1.20m W x 1.20m L x 0.25m thk.; Pede
LABOR COST: Assume: 2.00 manhours for loading and unloading of pre-cast materials
RATE: 1 Leadman @
2 Skilled Worker @
2 Helper @
EQUIPMENT COST:
Travel time = 13.00 hrs vise versa including loading & unloading
2.0 Second batch of delivery & hauling of Pre-Cast Footing/Pedestal items from SMIP Sta. Maria, Bulacan to KFC Cav
4 pcs - Pre-Cast Footing/Pedestal: F3/C3, Footing size: 2.00m W x 2.00m L x 0.30m thk.; Pede
3 pcs - Pre-Cast Footing/Pedestal: F2/C2, Footing size: 1.20m W x 1.20m L x 0.25m thk.; Pede
LABOR COST: Assume: 2.00 manhours for loading and unloading of pre-cast materials
RATE: 1 Leadman @
2 Skilled Worker @
2 Helper @
EQUIPMENT COST:
Travel time = 13.00 hrs vise versa including loading & unloading
1 pcs - Pre-Cast Footing/Pedestal: F3/C5, Footing size: 2.00m W x 2.00m L x 0.30m thk.; Pede
3 pcs - Pre-Cast Footing/Pedestal: F3/C3, Footing size: 2.00m W x 2.00m L x 0.30m thk.; Pede
3 pcs - Pre-Cast Footing/Pedestal: F2/C2, Footing size: 1.20m W x 1.20m L x 0.25m thk.; Pede
LABOR COST: Assume: 2.00 manhours for loading and unloading of pre-cast materials
RATE: 1 Leadman @
2 Skilled Worker @
2 Helper @
EQUIPMENT COST:
Travel time = 13.00 hrs vise versa including loading & unloading
4.0 Fourth batch of delivery & hauling of Pre-Cast Footing/Pedestal items from SMIP Sta. Maria, Bulacan to KFC Cav
3 pcs - Pre-Cast Footing/Pedestal: F3/C5, Footing size: 2.00m W x 2.00m L x 0.30m thk.; Pede
2 pcs - Pre-Cast Footing/Pedestal: F2/C3, Footing size: 1.20m W x 1.20m L x 0.30m thk.; Pede
2 pcs - Pre-Cast Footing/Pedestal: F1/C1, Footing size: 1.00m W x 1.00m L x 0.25m thk.; Pede
LABOR COST: Assume: 2.00 manhours for loading and unloading of pre-cast materials
RATE: 1 Leadman @
2 Skilled Worker @
2 Helper @
EQUIPMENT COST:
Travel time = 13.00 hrs vise versa including loading & unloading
5.0 Fifth batch of delivery & hauling of Pre-Cast Footing/Pedestal items from SMIP Sta. Maria, Bulacan to KFC Cavite
6 pcs - Pre-Cast Footing/Pedestal: F2/C2, Footing size: 1.20m W x 1.20m L x 0.250m thk.; Ped
LABOR COST: Assume: 2.00 manhours for loading and unloading of pre-cast materials
RATE: 1 Leadman @
2 Skilled Worker @
2 Helper @
EQUIPMENT COST:
Travel time = 13.00 hrs vise versa including loading & unloading
4 pcs - Pre-Cast Footing/Pedestal: F2/C1, Footing size: 1.20m W x 1.20m L x 0.250m thk.; Ped
2 pcs - Pre-Cast Footing/Pedestal: F1/C1, Footing size: 1.00m W x 1.00m L x 0.250m thk.; Ped
LABOR COST: Assume: 2.00 manhours for loading and unloading of pre-cast materials
RATE: 1 Leadman @
2 Skilled Worker @
2 Helper @
EQUIPMENT COST:
Travel time = 13.00 hrs vise versa including loading & unloading
LABOR COST:
EQUIPMENT COST:
LABOR COST:
EQUIPMENT COST:
LABOR COST:
288.00 kg/pc - Pre-cast Column 2, size: 0.20m W x 0.20m D x 3.00m L
EQUIPMENT COST:
LABOR COST:
90.00 kg/pc - Pre-cast wall panel, size: 1.50m L x 0.50m W x 0.05m thk.
EQUIPMENT COST:
90.00 kg/pc - Pre-cast wall panel, size: 1.50m L x 0.50m W x 0.05m thk.
LABOR COST:
EQUIPMENT COST:
40.00
= 29.22 m3
rength Concrete)
5.50 mh/cu.m.
AVERAGE RATE =
40.00
= 1.81 m3
Strength Concrete)
5.50 mh/cu.m.
AVERAGE RATE =
40.00
= 10.25 m3
Strength Concrete)
AVERAGE RATE =
58.8
110.2
10.66
30
26
13.33
2.67
2.67
10.00
1.33
8.80
3.20
29 - 257 - - -
REBARS_MARCOS HIGHWAY DRIVETHRU
= 5,494.67
X 35.21 P/kg =
X 45.00 P/kg =
X 2% =
TOTAL RATE =
X 2.06 P/kg =
40.00
= 20.10 m2
X 730.00 P/pc =
X 200.00 P/pc =
X 36.35 P/kg =
X 55.00 P/kg =
X 280.00 P/gal =
X 45.00 P/kg =
X 0.05 =
TOTAL RATE =
X 34.25 P/m2 =
40.00
1.00 0.25 4.00 4.20 4.20 m2
= 67.35 m2
X 730.00 P/pc =
X 200.00 P/pc =
X 36.35 P/kg =
X 55.00 P/kg =
X 280.00 P/gal =
X 45.00 P/kg =
X 0.05 =
TOTAL RATE =
X 34.25 P/m2 =
40.00
= 113.90 m2
X 730.00 P/pc =
X 200.00 P/pc =
X 36.35 P/kg =
X 55.00 P/kg =
X 280.00 P/gal =
X 45.00 P/kg =
X 0.05 =
TOTAL RATE =
X 34.25 P/m2 =
29.22 m3 3,802.81
1.81 m3 3,872.15
10.25 m3 4,450.00
TOTAL =
BOQ =
BALANCE =
=
rom SMIPC Warehouse in Sta. Maria, Bulacan to KFC Sto. Tomas, Batangas Project Site area.
ize: 2.00m W x 2.00m L x 0.30m thk.; Pedestal size: 0.40m W x 0.40m L x 0.30m thk. 594261% 3,053.21
ize: 1.20m W x 1.20m L x 0.25m thk.; Pedestal size: 0.30m W x 0.40m L x 0.30m thk. 141423% 968.81
TOTAL RATE =
ize: 2.00m W x 2.00m L x 0.30m thk.; Pedestal size: 0.40m W x 0.40m L x 0.30m thk. 594261% 3,053.21
ize: 1.20m W x 1.20m L x 0.25m thk.; Pedestal size: 0.30m W x 0.40m L x 0.30m thk. 141423% 968.81
TOTAL RATE =
ize: 2.00m W x 2.00m L x 0.30m thk.; Pedestal size: 0.40m W x 0.550m L x 0.30m thk. 150708% 3,097.25
ize: 2.00m W x 2.00m L x 0.30m thk.; Pedestal size: 0.40m W x 0.40m L x 0.30m thk. 445696% 3,053.21
ize: 1.20m W x 1.20m L x 0.25m thk.; Pedestal size: 0.30m W x 0.40m L x 0.30m thk. 141423% 968.81
TOTAL RATE =
ize: 2.00m W x 2.00m L x 0.30m thk.; Pedestal size: 0.40m W x 0.550m L x 0.30m thk. 452124% 3,097.25
ize: 1.20m W x 1.20m L x 0.30m thk.; Pedestal size: 0.40m W x 0.40m L x 0.30m thk. 97139% 998.17
ize: 1.00m W x 1.00m L x 0.25m thk.; Pedestal size: 0.30m W x 0.30m L x 0.30m thk. 65950% 677.68
TOTAL RATE =
ize: 1.20m W x 1.20m L x 0.250m thk.; Pedestal size: 0.30m W x 0.40m L x 0.30m thk. 282846% 968.81
TOTAL RATE =
ize: 1.20m W x 1.20m L x 0.250m thk.; Pedestal size: 0.30m W x 0.30m L x 0.30m thk. 184278% 946.79
ize: 1.00m W x 1.00m L x 0.250m thk.; Pedestal size: 0.30m W x 0.30m L x 0.30m thk. 65950% 677.68
TOTAL RATE =
X - P/kg =
X - P/kg =
Unit wt. =
X - P/kg =
X - P/kg =
Unit wt. =
X - P/kg =
X - P/kg =
Unit wt. =
X - P/kg =
X - P/kg =
Unit wt. =
X - P/kg =
X - P/kg =
3,802.81 P/m3 Concrete Ready Mix G-1 3000 Psi @ 7 days (SMIP BATCHING P
3,802.81 P/m3
3,802.81 P/m3
102.74 P/mh
334.98 P/mh
555.00 P/mh
76.36 P/mh
419.99 P/m3
419.99 P/m3
419.99 P/m3
36.00 P/m3
36.00 P/m3
36.00 P/m3
4,258.80 P/m3
3,872.15 P/m3 Concrete Ready Mix G-3/4 3000 Psi @ 7 days (SMIP BATCHING
3,872.15 P/m3
3,872.15 P/m3
102.74 P/mh
334.98 P/mh
555.00 P/mh
76.36 P/mh
419.99 P/m3
419.99 P/m3
419.99 P/m3
36.00 P/m3
36.00 P/m3
36.00 P/m3
4,328.14 P/m3
4,450.00 P/m3 Concrete Ready Mix G-3/4 3000 Psi @ 7 days (RMC Supplier)
4,450.00 P/m3
4,450.00 P/m3
102.74 P/mh
334.98 P/mh
555.00 P/mh
76.36 P/mh
419.99 P/m3
419.99 P/m3
419.99 P/m3
36.00 P/m3
36.00 P/m3
36.00 P/m3
4,905.99 P/m3
25mmØ
6.00m 7.50m
23.12 28.905
- -
Unit Cost
kgs/m3
35.21 P/kg
0.95 P/kg
0.72 P/kg
36.16 P/kg
36.16 P/kg
91.67 P/mh
91.67 P/mh
3.67 P/kg
6.11 P/kg
9.78 P/kg
9.78 P/kg
2.06 P/kg
2.06 P/kg
2.06 P/kg
45.93 P/kg
253.47 Marine Plywood 1/2" x 4' x 8' 2.33 say
82.13
1,724.70 P/m2
1,724.70 P/m2
574.90 P/m2
167.49 P/mh
167.49 P/mh
90.05 P/m2
197.05 P/m2
71.27 P/m2
358.37 P/m2
358.37 P/m2
34.25 P/m2
34.25 P/m2
34.25 P/m2
967.52 P/m2
253.47 P/m2 Marine Plywood 1/2" x 4' x 8' 7.80 say
33.28 P/m2
715.61 P/m2
715.61 P/m2
238.54 P/m2
167.49 P/mh
167.49 P/mh
90.05 P/m2
167.49 P/m2
20.94 P/m2
278.47 P/m2
278.47 P/m2
34.25 P/m2
34.25 P/m2
34.25 P/m2
551.26 P/m2
253.47 Marine Plywood 1/2" x 4' x 8' 13.18 say
82.13
1,724.70 P/m2
1,724.70 P/m2
574.90 P/m2
167.49 P/mh
13.21 P/mh
180.70 P/mh
97.15 P/m2
212.58 P/m2
76.89 P/m2
386.63 P/m2
386.63 P/m2
34.25 P/m2
34.25 P/m2
34.25 P/m2
995.78 P/m2
Amount
111,102.90
7,002.40
45,601.82
25,246.42
5,440.37
85,729.94
6,309.96
17,012.21
66,593.00
365.95
2,029.64
9,111.43
381,546.03
504,143.26
122,597.23
Updated_May 3, 2018
11.00 hours
2.00 hours
13.00 hours
Unit
Weight
12,212.84 kgs
2,906.42 kgs
15,119.27 kgs/trip
102.74 P/mh
167.49 P/mh
138.75 P/mh
408.98 P/mh
817.95 P/trip
817.95 P/trip
0.05 P/kg
19,045.00 P/trip
- P/trip
19,045.00 P/trip
1.26 P/kg
1.31 P/kg
Unit
Weight
12,212.84 kgs
2,906.42 kgs
15,119.27 kgs/trip
102.74 P/mh
167.49 P/mh
138.75 P/mh
408.98 P/mh
817.95 P/trip
817.95 P/trip
0.05 P/kg
19,045.00 P/trip
- P/trip
19,045.00 P/trip
1.26 P/kg
1.31 P/kg
Unit
Weight
3,097.25 kgs
9,159.63 kgs
2,906.42 kgs
15,163.30 kgs/trip
102.74 P/mh
167.49 P/mh
138.75 P/mh
408.98 P/mh
817.95 P/trip
817.95 P/trip
0.05 P/kg
19,045.00 P/trip
- P/trip
19,045.00 P/trip
1.26 P/kg
1.31 P/kg
Unit
Weight
9,291.74 kgs
1,996.33 kgs
1,355.35 kgs
12,643.43 kgs/trip
102.74 P/mh
167.49 P/mh
138.75 P/mh
408.98 P/mh
817.95 P/trip
817.95 P/trip
0.06 P/kg
19,045.00 P/trip
- P/trip
19,045.00 P/trip
1.51 P/kg
1.57 P/kg
Unit
Weight
5,812.84 kgs
5,812.84 kgs/trip
102.74 P/mh
167.49 P/mh
138.75 P/mh
408.98 P/mh
817.95 P/trip
817.95 P/trip
0.14 P/kg
19,045.00 P/trip
- P/trip
19,045.00 P/trip
3.28 P/kg
3.42 P/kg
Unit
Weight
3,787.16 kgs
1,355.35 kgs
5,142.51 kgs/trip
102.74 P/mh
167.49 P/mh
138.75 P/mh
408.98 P/mh
817.95 P/trip
817.95 P/trip
0.16 P/kg
19,045.00 P/trip
- P/trip
19,045.00 P/trip
3.70 P/kg
3.86 P/kg
259.20 kg/pc
- P/pc
- P/pc
- P/pc
- P/pc
- P/pc
162.00 kg/pc
- P/pc
- P/pc
- P/pc
- P/pc
- P/pc
288.00 kg/pc
- P/pc
- P/pc
- P/pc
- P/pc
- P/pc
90.00 kg/pc
- P/pc
- P/pc
- P/pc
- P/pc
- P/pc
54.00 kg/pc
- P/pc
- P/pc
- P/pc
- P/pc
- P/pc
MTO UNIT UNIT COST
29.22 m3 3,802.81
MTO UNIT UNIT COST
1.81 m3 3,872.15
10.25 m3 4,450.00
MTO UNIT UNIT COST
CAST IN PLACE
ITEM List of trips using Boomtruck QTY UNIT UNIT COST
1 First batch 1.00 lot 19,862.95
2 Second batch 1.00 lot 19,862.95
3
4
5
6
7
8
9
10
11
12
TOTAL =
PRECAST
TOTAL COST List of trips using Boomtruck QTY
19,862.95 First batch of delivery & hauling of Pre-Cast Footing/Pedestal items from SMI 15,119.27
19,862.95 Second batch of delivery & hauling of Pre-Cast Footing/Pedestal items from S 15,119.27
Third batch of delivery & hauling of Pre-Cast Footing/Pedestal items from SM 15,163.30
Fourth batch of delivery & hauling of Pre-Cast Footing/Pedestal items from S 12,643.43
Fifth batch of delivery & hauling of Pre-Cast Footing/Pedestal items from SMI 5,812.84
Sixth batch of delivery & hauling of Pre-Cast Footing/Pedestal items from SM 5,142.51
39,725.90
UNIT UNIT COST TOTAL COST
kgs/trip 1.31 19,862.95
kgs/trip 1.31 19,862.95
kgs/trip 1.31 19,862.95
kgs/trip 1.57 19,862.95
kgs/trip 3.42 19,862.95
kgs/trip 3.86 19,862.95
TOTAL = 119,177.70
PROJECT
DATE
SUBJECT
CAST IN PLACE
ITEM MATERIAL DESCRIPTION QTY UNIT
1 Fabrication & installation of rebar 5,340.16 kgs.
2 Fabrication & installation of formworks for footing 67.35 m2
3 Fabrication & installation of formworks for pedestal 134.00 m2
TOTAL
468.12 13,676.59
468.12 5,643.65
= 142,072.13
PRECAST
WORK DESCRIPTION QTY UNIT
Fabrication of rebar 5,494.67 kgs.
Fabrication & installation of formworks for footing 67.35 m2
Fabrication & installation of formworks for pedestal "first lift only 30cm height" 20.10 m2
Fabrication & installation of formworks for pedestal "last lift only 170cm height" 113.90 m2
Concreting of Footing 29.22 m3
Concreting of pedestal "first lift only (30cm in height) " 1.81 m3
Concreting of pedestal "last lift only (170cm in height) " 10.25 m3
TOTAL
88,407.20
UNIT COST TOTAL COST
9.78 53,724.72
278.47 18,755.27
358.37 7,203.19
386.63 44,036.62
419.99 12,270.57
419.99 759.52
419.99 4,303.94
-
-
-
-
= 141,053.83
PROJECT
DATE
SUBJECT
CAST IN PLACE
ITEM MATERIAL DESCRIPTION QTY UNIT UNIT COST
1 Concrete Ready Mix G-1 3000 Psi @ 7 days (RMC Supplier) 29.22 m3 4,274.87
2
3 Concrete Ready Mix G-3/4 3000 Psi @ 7 days (RMC Supplier) 12.06 m3 4,450.00
4 Deformed Bar 10mm x 6.00m G-40 194.00 pcs 130.14
5
6 Deformed Bar 16mm x 6.00m G-40 257.00 pcs 333.58
7 Tie wire, Ga.16 136.98 kgs 45.00
8 Marine Plywood 1/2" x 4' x 8' 23.30 pcs 730.00
9 Good Lumber 2" x 3" x 10' 332.97 pcs 200.00
10 Common Nail 2" 10.07 kgs 36.35
11 CWN Assorted 36.90 kgs 55.00
12 Form Oil 32.54 gal 280.00
TOTAL =
PRECAST
TOTAL COST MATERIAL DESCRIPTION QTY UNIT
124,894.60 Concrete Ready Mix G-1 3000 Psi @ 7 days (SMIP BATCHING PLANT) 29.22 m3
- Concrete Ready Mix G-3/4 3000 Psi @ 7 days (SMIP BATCHING PLANT) 1.81 m3
53,649.20 Concrete Ready Mix G-3/4 3000 Psi @ 7 days (RMC Supplier) 10.25 m3
25,246.42 Deformed Bar 10mm x 6.00m G-40 194.00 pcs
- Deformed Bar 12mm x 6.00m G-40 29.00 pcs
85,729.94 Deformed Bar 16mm x 6.00m G-40 257.00 pcs
6,163.95 Tie wire, Ga.16 140.22 kgs
17,012.21 Marine Plywood 1/2" x 4' x 8' 23.30 pcs
66,593.00 Good Lumber 2" x 3" x 10' 332.97 pcs
365.95 Common Nail 2" 10.07 kgs
2,029.64 CWN Assorted 36.90 kgs
9,111.43 Form Oil 32.54 gal
390,796.34 TOTAL
UNIT COST TOTAL COST
3,802.81 111,102.90
3,872.15 7,002.40
4,450.00 45,601.82
130.14 25,246.42
187.60 5,440.37
333.58 85,729.94
45.00 6,309.96
730.00 17,012.21
200.00 66,593.00
36.35 365.95
55.00 2,029.64
280.00 9,111.43
= 381,546.03
PROJECT: KFC CAVITE 3RD. Gen.
Subject: Cost Comparison CIP vs. Precast
Date: May 5, 2018
ITEM COST BREAKDOWN THEORETICAL ACTUAL NOTE
I. Cast in place
A. Material Cost 390,796.34
B. Labor Cost 142,072.13
Assume 2 batch of
deliver for all
materials needed
for concreting of
40pcs.
Footing/pedestal
C. Equipment Cost 39,725.90 using boomtruck
Total 572,594.37
II. Precast
A. Material Cost 381,546.03 232,173.85 Last lift of pedestal
B. Labor Cost 141,053.83 73,147.86 not included yet
Assume 6 batch of
deliver for 40pcs.
Precast footing
using boomtruck w/
rental rate of
C. Equipment Cost 119,177.70 1465pesos/hr
Total 641,777.56 305,321.71