Vous êtes sur la page 1sur 11

PETROLEUM SOCIETY PAPER 2008-025

Optimum Procedures for


Calibrating Acoustic
Sand Detector,
Gas Field Case
M. IBRAHIM
Suez Canal University

T. HAUGSDAL
ClampOn

This paper is accepted for the Proceedings of the Canadian International Petroleum Conference/SPE Gas Technology Symposium
2008 Joint Conference (the Petroleum Society’s 59th Annual Technical Meeting), Calgary, Alberta, Canada, 17-19 June 2008. This
paper will be considered for publication in Petroleum Society journals. Publication rights are reserved. This is a pre-print and
subject to correction.

Abstract well sand erosion is a serious problem since it can erode holes
in the pipe work in a very short time period1.
Sand production from unconsolidated formations in oil and Produced sand can result in serious damage to the
gas wells has been a world-wide challenge for the petroleum reservoir, where in some cases the reservoir collapses as a
industry for many decades. The challenge is not merely to avoid result of the sand production. Again, this scenario is a costly
or stop sand production, but to be able to maintain commercial experience for the operator who has to overhaul and complete
well productivity after efforts to control sand are implemented. the producing reservoir zone.
At the same time, the control method selected must be justified In this paper, we will present the optimum procedures for
by a reasonable payback time of the investment cost. calibrating ClampOn sand detector which will help us to detect
Produced sand is a major problem in many production sand production. Also, we will present the effect of water
situations since small amount of sand entrained in the produced production and choke change in the sand detector response.
fluid can result in significant erosion and erosion corrosion
problems. Even in “sand free” or clean service situations where
sand production rate is only a few pounds per day, erosion
damage could be very severe at high production velocities. Introduction
Sand erosion can also cause localized erosion damages to Control of sand production is a major concern in Sun Gas
protective corrosion scales on pipe walls and result in Company's offshore Gulf of Mexico operations. Sonic sand
accelerated erosion-corrosion damage. In a high velocity gas detection systems now in service on several Sun operated
production platforms provide effective, relatively low cost

1
platforms provide an effective, relatively low cost method for ( RAW value − Zero)
maintaining optimum production rates while minimizing Sand Rate = , gm/s (1)
equipment erosion and well bore damage. A case history of Step
field application on one Sun platform as well as the theoretical
basis for the Sonic Sand Detector is presented2
The raw value is simply the level of the acoustic signal the
The major advantage of using the ultrasonic sand detector to
sensor is reading. The zero is the background noise made from
detect sand is that sand monitoring has moved forward from a
the flow medium as it passes through the pipe, and the step is
level of production trend to actual quantification in real time.
the sensitivity factor for the specific flow velocity. For the sand
The detector quantifies sand beyond its initial limit of profiling.
output to be accurate, the system needs to use correct zero and
The principle adopted uses an iterative method to locate a
step for the different flow velocities. Each flow velocity will
considerable threshold in the sand signature logged. Raw
give a unique background noise (and zero) and a unique step
signals, in energy/sec, were simulated to reflect true sand
value. The result of the sand injection calibration we will be a
production by marking up the background noise value, with
unique step table for each well.
about 10% to achieve the true sand free level of the signals for
sand rate calculation3.
Some of the lessons learnt from the application of the DSP Sand Type
Sand Monitor are; a single sample from a shakeout (Wellhead Sand type used in the calibration should be the same as
Sample) may not represent the true sand characteristics of a reservoir sand type. If it is difficult to obtain clean reservoir
well. Average sand reading from the monitor should not be sand, we can use similar clean sand with the same diameter. In
expected to match a single value shake out. Successful use of this field “Barskarp 10” sand from Askania was used for the
monitor requires teamwork and coordination among petroleum calibration. The sand has grain sizes from 0.020 too 0.5 mm.
engineers (PEs), Operators4. The most present grain size is 0.09 mm. This type of sand was
Due to economic and safety considerations, a sonic sand chosen because it is most similar to the sand in the reservoir
detection system was installed. The objective was to determine type.
the maximum flow rate at which each well could produce free
of sand. Dry Gas Well Calibration
Calibration of acoustic detectors is required when new
sensor installed in the first time so we can calculate the sand The calibration of dry gas well is done under the well
rate and cumulative sand production. Also, calibration should flowing condition as given in Table 1. This well is one of seven
be performed so that appropriate alarm settings can be wells in dry gas field with condensate-gas ratio less than 1.0
determined. Calibration is undertaken by injecting known bbl/mmscf.
amounts of sand into the system and then noting the sand
detector response which will be used as guide to detect sand Effect of Sensor Location
production in future5-6.
In this paper, the calibration procedures for dry and Acoustic detectors ‘hear’ the impact of sand hitting the pipe
condensate gas field will present. Also, the effect of water wall. They should be located as close to the tree as possible,
production on sand detector will present. while satisfying following criteria:
Mount on the outside of a bend on the downstream
side of an elbow.
Use only vendor supplied mounting hardware. The
Calibration of sand injections detector’s transducer must contact bare pipe.
The ClampOn Sand Injector Unit is a mobile piece of There should be no flow direction changes for at least
equipment that is used to convey small quantities of sand into 5 pipe diameters upstream of the elbow.
oil and gas production streams. The injector unit was installed An injection point upstream of the detector (as far as
on the top of the production wellheads and the sand was possible) is required for calibration.
injected into the fluid stream through the well's swab valve. A location too close to the production choke may
Liquid and gas production from the well is unaffected cause background noise (no sand) to be too high
throughout the operation. (recommend 10+ pipe diameters from choke).
The purpose of sand injection is to test and calibrate The sensor was installed on the flow line of well 1, after the
ClampOn sand production monitoring equipment, installed in second or third bend downstream choke. The placement was
the downstream gas production system. The ClampOn sand decided based on were its physically possible, and then were the
detection system is able to detect the sound when produced sand background noise from the flow is lowest. Fig. 1 showed the
(from the reservoir formation) collides with the walls of the sensor in the flow line of Well-1.
pipe. The magnitude of the sound produced is mainly dependent Another sensor planned to install in another place in the flow
on the quantity of sand in the production fluids and the velocity line for Well-1 to study the effect of sensor location in the Raw
of the sand particles (since the particles are carried in the gas value. This was done to compare two sensor locations during
production stream, their velocity is normally equivalent to that the sand injection.
of the flowing gas stream). Increases in either the quantity of This will demonstrate how sand appears on the detectors vs.
sand or the stream velocity have the effect of increasing the other noise, establish raw value pattern, and a unique step value
magnitude of the sound produced. will be found for each sensor.
By injecting known quantities of sand into gas streams, it is In well-1 there is two ClampOn sensors mounted on the
possible to calibrate the sand monitoring equipment. In same flow line. This makes it possible to compare the two
addition, a positive response of the sand monitoring equipment sensor locations. One sensor is mounted at the second bend
to sand injection provides conclusive proof (and hence downstream choke; the other sensor is mounted at the third
confidence) that the sand monitoring equipment is actually bend downstream choke.
capable of detecting sand carried in the gas production stream. The background noise from the flow is high and a little
The formula for Sand Rate in gm/s is: unstable (seen after the injections). Injected water before the
sand, and there were no response on the raw signal from the

2
water. The injected sand gives high response from the flow velocity during the sand injection was 16.12 m/s. The Zero
background noise baseline. The zero level is set to be 61300 this value is found to be 7000 and step value 42000. The sensor is
is 10% offset from the minimum raw value (55727) seen before now calibrated with high accuracy at this flow velocity.
the sand injection started. All the injections except for the first On December 2007, Well-2 start to produced formation
injection was giving a good response, and by using the same water as confirmed with the water analysis of TDS = 12000
zero and step value on all of them the calculated sand was ppm but there is no sign of sand production. Sand detector does
showing the same amount of sand as injected. not effect of the water production as seen in Fig. 5. This
The flow velocity during the sand injection was 7.94 m/s. concludes that the acoustic sensor does not effect by the flow of
The zero value is found to be 61300 and step value 12000. The water in the flowline or water production.
sensor is now calibrated with high accuracy at this flow
velocity, for other velocities use the zero and step velocities Condensate Gas Well Calibration
suggested in the table below:
There is no sign of sand production from the reservoir during The calibration of condensate gas well is done under the well
the sand injection calibration. The background noise from the flowing condition as given in Table 3&4. There are two well in
flow on the second sensor is much lower (around 24000 this field Well-A and Well-B producing with condensate-gas
compared with 61000) than the sensor mounted in the second ratio greater than 55.0 bbl/mmscf.
bend. The response from the sand is also lower than for the
sensor located at the second bend. This is logic because the Calibration of Well-A
sensor is installed a place were the flow and also the sand The calibration of condensate gas well is done under the well
(which follows the flow) have lower energy. Fig. 2&3 showed flowing condition is given in Table 2. This well is one of two
the calibration of Well-1 at location 1 and 2 in the flow line. well in condensate gas field with condensate-gas ratio close to
The zero level is set to be 24000 this is 10% offset from the 60 bbl/mmscf of gas.
minimum raw value (21818) seen before the sand injection The sand injector was installed on wellhead-A. Pressure
started. All the injections except for the first injection was tested our system, and started the sand injection. We did a few
giving a good response, and by using the same zero and step test injections. One injection with 25 gm of sand at 40 mmscfd
value on all of them the calculated sand was showing the same of gas rate and another injection with 10.0 gm sand at 55
amount of sand as injected. The flow velocity during the sand mmscfd of gas rate. The sand detector detects the 10.0 gm of
injection was 7.94 m/s. Zero value is found to be 24000 and sand as you can see in Fig. 6 which it is easy to differentiate
step value 6000. The sensor is now calibrated with high between back noise and sand production.
accuracy at this flow velocity, for other velocities use the zero All injections went well also the test injections with small
and step velocities suggested in the Table 2. amount of sand. A problem here could be that the sensor
The last injection was 30 gram sand; this injection was done response was low and the signal not possible to separate from
to find the threshold limit for the sand detection. 30 gram sand the background noise. As you can see from the picture above it
was injected over 4 minutes at a production of 45.6 mmscf/d. is no problem to separate the injection from the background
This gives the following average sand concentration: noise. If the background noise don’t change munch the
During the injecting job the production was assumed to be ClampOn system will have no problem to detect 10.0 gm of
higher, because of this an injection with less sand was not done. sand.
The lowest proved average sand concentration threshold limit On late 2007, Well-A starts to produce formation water
for the sensor is: 0.520 [lb/mmscf]. which confirmed from the water analysis result. The sand
The calculation above is the average sand concentration detector shows sand production compared with the calibration
during the injection of 30 gram sand. The system will display a trend of Raw value as shown in Fig. 7.
sand rate also for lower sand production than 0.520 lb/mmscf.
The injector equipment was not able to inject the sand over
longer time period. Calibration of Well-B
After some investigation of the background noise on both We installed the sand injector system on wellhead Well-B on
sensors mounted on the well-1 flow line, it’s clear the location 2005 which is the second gas well in this condensate gas field.
at third bend downstream choke is best. This sensor has lower Pressure tested our system, and started the sand injection. We
background noise; the sand makes less response but the no did three (400g) sand injections on each gas rate of 20, 39 and
problem to detect the sand we inject. 55 MMscf. We had no problems during the injecting. We could
see that we got higher background noise when they increased
Effect of Water Production on Sand the gas rate, this is normal. We compensate for this noise with
Detector for Dry Gas Well the zero values in ClampOn software. Fig. 8 showed the sand
detector during the calibration for Well-B.
Well-2 produced from the same reservoir as Well-1. During On early 2006, Well-B production starts to decline sharply
the calibration of Well-2, there is no sign of water production due to production of formation water. This water production
which confirm from the total dissolved solid of the water (TDS associated with sand production as shown in Fig. 9. This well is
= 1200 ppm). This low TDS value is for water vapor content. currently shut-down due the very low gas production.
The background noise from the flow on this sensor is low
and stable. There is no sign of sand production from the Effect of Choke Change
reservoir during the sand injection calibration. Fig. 4 shows the
sand detector response for the injection of 400 and 20 gm of Sand detector is very sensitive to choke change in case of gas
sand. rate increase or decrease. The well choke back effect in Raw
The zero level is set to be 7000 this is 10% offset from the value which make the Raw value to go up as it happen in case
minimum raw value (6363) seen before the sand injection of gas rate increased. Fig. 10 shows the well has been choked
started. All the injections were giving a good response. By back to deceased the gas rate. This make the Raw value to go as
using the same zero and step value on all of them the calculated it look like the well start to sanding but it does not because the
sand was showing the same amount of sand as injected. The trend of Raw in case of sand production is different from sand

3
noise. Fig. 11 showed the wellhead flowing pressure (WHFP) Learned; SPENC, J. Technical Papers, SPE 88899,
and gas rate which showed the well has been choked back, these (2004) pp. 1-5.
changes in choke make the Raw value increased. 5. M.H. Stein, A.A. Chitale; G. Asher and H.
Vaziri, Y. Sun, J.R. Colbert, and F.A. Gonzalez, :”
Conclusion Integrated Sand and Erosion Alarming on NaKika,
Deepwater Gulf of Mexico,” SPE paper 95515
From this work, the following conclusions have been presented at the SPE Annual Technical Conference
reached. and Exhibition, Dallas, Texas 9-12 October 2005.
1. The calibration of new sand detector is very important
because it will give the base line for back noise under the 6. Anand, Jeevan:” Evaluation and Control of Sand
current flow condition Production in Gas Wells,” SPE paper 6531
2. The location of sand detector affects the Raw value but presented at the SPE California Regional Meeting,
does not effect on the performance of the sand detector. Bakersfield, California ,13-15 April 1977.
3. If the well flow conditions changed, we need to calculate
the new zero value and step rate.
4. The sand detector is not sensitive to the fluid type.
5. Acoustic sand detector can detect any amount of sand
production even with water production.
6. The acoustic sand detector is very sensitive to choke
change which could act like gas meter to track the change
in well rate and choke change.

Acknowledgements
I would like to thank Clampon for supporting this work.

NOMENCLATURE
Raw = the level of the acoustic signal the sensor is
reading
Zero = is the background noise made from the flow
medium as it passes through the pipe.
Step = is the sensitivity factor for the specific flow
velocity
TDS = Total dissolved solid in ppm.
SI Metric Conversion Factors
cp ×1.0 E-03 = Pa • s
ft ×3.048 E-01 = m
ft2 ×9.290 304 E-02 = m2
ft3 ×2.831 685 E-02 = m3
in. ×2.54 E+00 = cm
lbf ×4.448 222 E+00 = N
md ×9.869 233 E-04 = µm2
psi ×6.894 757 E+00 = kPa

REFERENCES
1. ClampOn AS, “Sand Detection in oil and gas wells –
how to optimise production by effective use of
ultrasonic sand monitoring equipment” ClampOn
document (May 9, 2001)
2. Foster, Charles R. and Thomas W., A METHOD OF
MONITORING SAND PRODUCTION IN A
FLOWING WELL STREAM; SPE paper 8214
presented at SPE Annual Technical Conference and
Exhibition, Las Vegas, Nevada, 23-26 September 1979.
3. Lazarus A. Musa, Tuoyo Temisanren, Warri and Dulu
Appah, Establishing Actual Quantity of Sand Using an
Ultrasonic Sand Detector; The Niger Delta Experience;
SPE paper 98820 presented at the 29th Annual SPE
International Technical Conference and Exhibition in
Abuja, Nigeria, August 1 -3, 2005.
4. Fariyibi, F. L, Umurhohwo, J. O., Olson, S. G.,
Scott, K. C., Acoustic Sand Monitor Trials in the
Offshore CVX-NMA: Results and Lessons

4
Well WHFP Temp Gas rate ID Calc. Flow velocity
Tag Bar Deg C mmscf/d Inches m/s
Well 1 70.7 28.4 45.6 7.41 7.94
Well-2 46.03 33.28 47.97 7.41 11.93

Table 1 –Well-1 production data during the calibration.

FIGURE 1 – Shows the sand detector for Well-1.

FIGURE 2 – Shows the calibration for Well-1 in first location.

5
FIGURE 3 – Shows the calibration for Well-1 in second location.

Velocity Step
0 504
2.22 1225
4.44 2973
6.67 7219
8.89 17525
11.11 42548
13.33 103297
15.56 250782
17.78 608846
20 1478147

Table 2 –Step value at different flow velocity for Well-1.

6
FIGURE 4– Shows the calibration for Well-2 without water production.

FIGURE 5– Shows the sand detector reading for Well-2 with water production.

7
Date Time Cum.Gas Sep.Press Sep.Temp THP FLT FLP Calc.Flow
veloc.
mmscf barg C° barg C° barg m/s
11:30
13.05.2005 AM 20.0 96.50 70.70 515.20 89.70 96.00 4.70
12:10
13.05.2005 PM 40.0 98.70 71.30 506.00 90.80 98.20 9.20
13.05.2005 1:45PM 55.0 100.00 72.40 497.00 94.00 106.00 11.92

Table 3 –Production data during the calibration for Well-A.

Date Time Cum.Gas Sep.Press Sep.Temp THP FLT FLP Calc.Flow


veloc.
mmscf barg C° barg C° barg m/s
10:45
11.05.2005 AM 20.0 96.50 66.0 404.30 72.0 96.87 4.45
12:50
11.05.2005 PM 39.0 98.0 68.0 377.00 82.30 98.30 8.82
11.05.2005 2:00 PM 55.0 99.60 70.0 351.00 89.30 100.00 12.46

Table 4 –Production data during the calibration for Well-B.

FIGURE 6 – Shows the calibration for Well-A.

8
FIGURE 7 – Shows the sand detector performance during the sand production for Well-A.

FIGURE 8 – Shows the calibration for Well-B.

9
FIGURE 9 – Shows the sand detector performance during the sand production for Well-B.

FIGURE 10 – Shows the effect of choke change in sand detector performance.

10
70

Gas Rate
WHFP
65

60
Gas Rate, mmscfd & WHFP, barg

55

50

45

40

35

30
2/1/2008 2/6/2008 2/11/2008 2/16/2008 2/21/2008 2/26/2008 3/2/2008
Date

FIGURE 11 – Shows the well has been choked back.

11

Vous aimerez peut-être aussi