STEP-BY-STEP PROCEDURE
The following step by step procedure will guide you to repair a damage potion of RC beams &
columns.
Note:
Here we are dealing with only carbon induced corrosion of steel. Because chloride induced
corrosion is difficult to identify and this demands for replacement of whole concrete near steel.
STEP-4 (CLEANING)
Using water or any rust removal solutions, clean the concrete and steel surface thoroughly.
Note:
If the area to be repaired is small, then instead of using concrete, use polymer modified cement
mortar.
In case of large area repair work, shotcrete/gunite method of concrete placing is suggested.
STEP-10 (CURING)
Cure the repaired work for at least 7 days.