METHOD STATEMENT
(SVN-TSCO -MS-E-001)
DATE
No. REVISION DESCRIPTION PREPARED APPROVED
(NGÀY
STT (PHIÊN BẢN) (NGƯỜI LẬP) (NGƯỜI DUYỆT)
TRÌNH)
1 Original Issue / Trình lần đầu
Date: 29.May.2018 TSUCHIYA TSCO HANOI FACTORY PROJECT
MV RECLOSER INSTALLATION WORK SHIMIZU VIETNAM CO., LTD
Rev. 00
SVN-TSCO-MS-E-001
TABLE OF CONTENTS
Article Description Page No.
1. General 3
1.1 Description 3
2. Methodology 4
4
2.1 Preparation works
5
2.2 Sequence of works
5
2.3 Key points of the method statement
6
2.4 Inspection procedure
5. Quality control 8
6. Equipment List 8
7. Environment management 9
8. Safety management 9
APPENDIX:
1 Plan and elevation
2 Typical Installation of MV recloser
3 Job safety analysis
Date: 29.May.2018 TSUCHIYA TSCO HANOI FACTORY PROJECT
MV RECLOSER INSTALLATION WORK SHIMIZU VIETNAM CO., LTD
Rev. 00
SVN-TSCO-MS-E-001
1. GENERAL
1.1. Description
This method of statement describes the procedure installation of MV recloser in the position.
This includes installing it on the MV pole and assuring all the specification is complied.
1.2. Scope of work
- Installation of MV recloser in the position on MV pole.
Shimizu: Permit and hand over plan inside working area
-Inspection work follow ITP that approved by Shimizu.
Subcontractor:
+ Subcontractor will present installation method of statement, preparation work, Job analysis
and risk assessment before executing any works
+Works will be supervised to make sure that all work is carried out in compliance with
approved documentation.
+ Invite Shimizu inspection before and after finished work.
Manufacturer/Country
No. Material Detail of Spec. Category Remarks
of origin
1 MV recloser 3P, 630A Schneider/China Power System
2. METHODOLOGY
2.1. Preparation works
- Delivery the MV recloser on site, inspection by Shimizu
- Submit drawing and document for Shimizu and get approval before installation of MV
recloser.
- Submit permit to Shimizu
- Check all relative documentation and permits if approved and valid.
- Review location of areas by drawing and ensure having enough conditions for installing
- Check again the installation manual of the MV recloser (supplying by supplier)
- Prepare tools, materials and accessories need for installation
- Install the safety sign boards on site according to stipulated regulations of safety and other
instructions of the employer’s engineer
- The temporary works such as: material stock, fabrication yard will be arranged on installation
area; machine and hand tool will be prepared in advance
Date: 29.May.2018 TSUCHIYA TSCO HANOI FACTORY PROJECT
MV RECLOSER INSTALLATION WORK SHIMIZU VIETNAM CO., LTD
Rev. 00
SVN-TSCO-MS-E-001
- Contractor must comply with the requirements for wearing mandatory PPE and any additional
PPE as identified in the job safety analysis sheet
2.2. Sequence of works for Transformer displacement
MV recloser
Material approval document approval
Material procurement
Delivery MV recloser
Inspection by Shimizu
Installation of MV Inspection by
recloser Shimizu
SMZ-M&E Manager
Mr. Toyoshima
Worker: 06
Date: 29.May.2018 TSUCHIYA TSCO HANOI FACTORY PROJECT
MV RECLOSER INSTALLATION WORK SHIMIZU VIETNAM CO., LTD
Rev. 00
SVN-TSCO-MS-E-001
6. EQUIPMENT LIST
2 Accessory 1 lot
7. ENVIRONMENT MANAGEMENT
Shimizu shall have responsibility for the surrounding environment during execution of installation
work, complying with the condition of the Contract and Vietnam’s National Law on Protection of
Environment and other relevant legislation
If any problem is identified on the site during execution, applicable counter measures shall be
implemented as soon as possible and preventative action shall be initiated to prevent re-
occurrence of the identified problem.
At the management level, the Site Manager shall be reponsible for the management and control
of the work while at the direct execution level, the respective Engineer shall be responsible in this
project.
8. SAFETY MANAGEMENT
8.1. Joint meeting
Prior to start any activity, a meeting with member directly join on work will be held for purpose of
explanation whole content of work and point all potential risk may occur during construction work
and inform schedule of area and zone connection to owner factory.
8.2. Instruction
For new staff join the works, a safety course will be held by Shimizu.
The instruction will be explained same content as above meeting item.
8.3. Prevention of Accident.
. Preventive maintenance check shall be done regularly at equipment working at site prior to full
operation. The machine range must be indicated by safety barricade and place warning sign; it is
not allowed for human.
8.4. Prevention of Accident of Electrocution.
Equipment use electric power shall be properly protected and properly installed with earth
connection. Electric wires shall be connected with electrical tapes to prevent electric leakage.
Only skilled operator shall be allowed to operate equipment on site.
Date: 29.May.2018 TSUCHIYA TSCO HANOI FACTORY PROJECT
MV RECLOSER INSTALLATION WORK SHIMIZU VIETNAM CO., LTD
Rev. 00
SVN-TSCO-MS-E-001