CALENDARIO DE AVANCE DE OBRA VALORIZADO A LA FECHA CONTRACTUAL

Obra MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVO DE LA I.E.P. POLITECNICO REGIONAL DEL CENTRO EL TAMBO HUANCAYO
Propietario GOBIERNO REGIONAL JUNIN
Contratista VASMER CADS S.A.
Lugar JUNIN - HUANCAYO- EL TAMBO

Mes 1 Mes 2 Mes 3 Mes 4 Mes 5 Mes 6 Mes 7 Mes 8 Mes 9


28-Jan-11 01-Feb-11 01-Mar-11 01-Apr-11 01-May-11 01-Jun-11 01-Jul-11 01-Aug-11 01-Sep-11
31-Jan-11 28-Feb-11 31-Mar-11 30-Apr-11 31-May-11 30-Jun-11 31-Jul-11 31-Aug-11 24-Sep-11
Item Descripción Precio Parcial ( 04 ) ( 28 ) ( 31 ) ( 30 ) ( 31 ) ( 30 ) ( 31 ) ( 31 ) ( 24 )
PABELLON ADMINISTRACION
01 ESTRUCTURAS "ADM "
01.01 OBRAS PRELIMINARES 6,890.45 918.72 5,971.73
01.02 MOVIMIENTO DE TIERRAS 999.43 999.43
01.03 CONCRETO ARMADO 5,002.82 667.06 4,335.76
01.04 ESTRUCTURAS DE MADERA Y COBERTURA 2,479.50 2,479.50
02 ARQUITECTURA "ADM "
02.01 MUROS Y TABIQUES 9,313.14 9,313.14
02.02 REVOQUES ENLUCIDOS Y MOLDURAS 20,852.66 20,852.66
02.03 PISOS Y PAVIMENTOS 19,304.95 19,304.95
02.04 ZOCALO Y CONTRAZOCALOS 14,308.09 572.41 13,735.68
02.05 CARPINTERIA DE MADERA 2,534.40 2,534.40
02.06 CARPINTERIA METALICA 5,029.88 5,029.88
02.07 VIDRIOS, CRISTALES Y SIMILARES 12,807.20 10,977.60 1,829.60
02.08 PINTURA 21,581.91 3,596.91 17,985.00
02.09 APARATOS Y ACCESORIOS SANITARIOS 1,410.12 1,410.12
02.10 OTROS 504.00 504.00
03 INSTALACIONES SANITARIAS "ADM "
03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 2,950.45 2,950.45
03.02 SISTEMA DE DESAGUE 4,727.27 675.35 4,051.92
03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS 1,066.80 1,066.80
04 INSTALACIONES ELECTRICAS "ADM "
04.01 TUBERIA Y CANALIZACION 5,358.79 5,358.79
04.02 CAJAS DE PASE 473.65 473.65
04.03 CONDUCTORES 4,692.15 4,692.15
04.04 INSTALACION DE PLACAS 2,256.61 2,256.61
04.05 INSTALACION DE ARTEFACTOS 4,890.65 611.34 4,279.31
04.06 TABLEROS 1,048.76 1,048.76
04.07 LLAVES TERMOMAGNETICA 1,009.58 1,009.58
04.08 SISTEMA DE PUESTA A TIERRA 3,634.34 3,634.34
04.09 EQUIPOS ELECTRICOS Y MECANICOS 1,491.39 1,491.39
PABELLON A,B,C
01 ESTRUCTURAS "ABC"
01.01 OBRAS PRELIMINARES 6,078.72 6,078.72
01.02 MOVIMIENTO DE TIERRAS 28.12 28.12
01.03 CONCRETO SIMPLE 3,326.77 2,217.84 1,108.93
01.04 CONCRETO ARMADO
01.04.01 ZAPATAS 194.47 194.47
01.04.02 COLUMNAS DE CONFINAMIENTO 3,036.39 1,518.20 1,518.19
01.04.03 COLUMNAS 753.79 753.79
01.04.04 VIGUETAS DE CONFINAMIENTO 2,059.08 2,059.08
02 ARQUITECTURA "ABC"
02.01 MUROS Y TABIQUES 2,925.63 975.19 1,950.44
02.02 REVOQUES ENLUCIDOS Y MOLDURAS 23,135.74 23,135.74
02.03 PISOS Y PAVIMENTOS 34,625.17 12,984.47 21,640.70
02.04 CONTRAZOCALOS 5,006.10 5,006.10
02.05 ZOCALOS 5,486.63 5,486.63
02.06 CARPINTERIA DE MADERA 12,096.00 10,368.00 1,728.00
02.07 CARPINTERIA METALICA 18,574.26 9,287.10 9,287.16
02.08 CERRAJERIA
02.08.01 CERRADURAS 2,419.31 2,419.31
02.09 VIDRIOS, CRISTALES Y SIMILARES 15,261.66 15,261.66
02.10 PINTURA 53,076.42 53,076.42
02.11 APARATOS Y ACCESORIOS SANITARIOS 9,325.63 9,325.63
02.12 OTROS 1,506.97 1,506.97
03 INSTALACIONES SANITARIAS "ABC"
03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 4,065.61 903.50 3,162.11
03.02 SISTEMA DE DESAGUE 4,578.43 4,578.43
03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS 914.40 914.40
03.04 SISTEMA DE DESAGUE FLUVIAL 1,168.77 1,168.77
04 INSTALACIONES ELECTRICAS "ABC"
04.01 TUBERIA Y CANALIZACION 4,997.85 4,997.85
04.02 CAJAS DE PASE 248.85 248.85
04.03 CONDUCTORES 7,419.58 3,709.78 3,709.80
04.04 INSTALACION DE PLACAS 3,663.37 3,663.37
04.05 INSTALACION DE ARTEFACTOS 10,779.75 3,593.27 7,186.48
04.06 TABLEROS 1,127.16 1,127.16
04.07 LLAVES TERMOMAGNETICA 2,234.11 2,234.11
PABELLON D
01.01 ESTRUCTURAS " D "
01.01.01 OBRAS PRELIMINARES 6,706.07 1,788.28 4,917.79
01.01.02 MOVIMIENTO DE TIERRAS 3,025.05 3,025.05
01.01.03 CONCRETO SIMPLE 6,857.27 6,857.27
01.01.04 CONCRETO ARMADO
01.01.04.01 ZAPATAS 1,171.48 1,171.48
01.01.04.02 COLUMNAS 4,928.16 4,928.16
01.01.04.03 VIGAS 334.65 334.65
01.01.04.04 ESCALERAS DE CONCRETO ARMADO 5,439.08 5,439.08
01.01.01.05 ESTRUCTURAS DE MADERA Y COBERTURA 22,575.17 14,512.59 8,062.58
01.02 ARQUITECTURA " D "
01.02.01 MUROS Y TABIQUES 1,309.15 1,309.15
01.02.02 REVOQUES ENLUCIDOS Y MOLDURAS 23,769.28 8,556.96 15,212.32
01.02.03 CIELORRASOS 17,415.95 13,061.95 4,354.00
01.02.04 PISOS Y PAVIMENTOS 22,879.31 22,879.31
01.02.05 CONTRAZOCALOS 1,948.55 1,948.55
01.02.06 ZOCALOS 3,525.72 3,525.72
01.02.07 CARPINTERIA DE MADERA 3,744.00 3,744.00
01.02.08 CARPINTERIA METALICA 19,334.44 19,334.44
01.02.09 CERRAJERIA
01.02.09.01 CERRADURAS 1,042.08 1,042.08
01.02.10 VIDRIOS, CRISTALES Y SIMILARES 4,105.90 4,105.90
01.02.11 PINTURA 8,351.54 8,351.54
01.02.12 APARATOS Y ACCESORIOS SANITARIOS 1,344.62 1,344.62
01.02.13 OTROS 104.60 104.60
01.03 INSTALACIONES SANITARIAS " D "
01.03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 1,307.35 1,307.35
01.03.02 SISTEMA DE DESAGUE 4,833.29 4,833.29
01.03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS 457.20 457.20
01.04 INSTALACIONES ELECTRICAS " D "
01.04.01 TUBERIA Y CANALIZACION 1,971.45 1,971.45
01.04.02 CAJAS DE PASE 55.30 55.30
01.04.03 CONDUCTORES 1,312.14 1,312.14
01.04.04 INSTALACION DE PLACAS 1,088.92 1,088.92
01.04.05 INSTALACION DE ARTEFACTOS 1,914.42 1,914.42
01.04.06 TABLEROS 281.74 281.74
01.04.07 LLAVES TERMOMAGNETICA 563.78 563.78
PABELLON E
02.01 ESTRUCTURAS " E "
02.01.01 OBRAS PRELIMINARES 6,278.92 6,278.92
02.01.02 MOVIMIENTO DE TIERRAS 3,805.09 3,805.09
02.01.03 CONCRETO SIMPLE 8,236.73 8,236.73
02.01.04 CONCRETO ARMADO
02.01.04.01 ZAPATAS 2,342.99 2,342.99
02.01.04.02 COLUMNAS 7,480.53 6,233.77 1,246.76
02.01.04.03 VIGAS 856.65 856.65
02.01.04.04 ESCALERAS DE CONCRETO ARMADO 10,694.33 10,694.33
02.01.05 ESTRUCTURAS DE MADERA Y COBERTURA 26,124.09 26,124.09
02.02 ARQUITECTURA " E "
02.02.01 MUROS Y TABIQUES 1,923.21 1,923.21
02.02.02 REVOQUES ENLUCIDOS Y MOLDURAS 34,893.04 30,531.48 4,361.56
02.02.03 CIELORRASOS 22,198.52 7,769.43 14,429.09
02.02.04 PISOS Y PAVIMENTOS 21,864.91 21,864.91
02.02.05 CONTRAZOCALOS 2,573.69 2,573.69
02.02.06 ZOCALOS 930.33 930.33
02.02.07 CARPINTERIA DE MADERA 4,985.60 4,985.60
02.02.08 CARPINTERIA METALICA 14,528.59 14,528.59
02.02.09 CERRADURAS 836.55 836.55
02.02.10 VIDRIOS, CRISTALES Y SIMILARES 5,240.98 5,240.98
02.02.11 PINTURA 11,705.52 6,503.04 5,202.48
02.02.12 APARATOS Y ACCESORIOS SANITARIOS 70.00 70.00
02.02.13 OTROS 109.09 109.09
02.03 INSTALACIONES SANITARIAS " E "
02.03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 463.88 463.88
02.03.02 SISTEMA DE DESAGUE 2,835.36 2,835.36
02.03.03 COLOCACION DE APARATOS ANITARIOS 50.80 50.80
02.04 INSTALACIONES ELECTRICAS " E "
02.04.01 TUBERIA Y CANALIZACION 2,214.33 1,230.20 984.13
02.04.02 CAJAS DE PASE 55.30 55.30
02.04.03 CONDUCTORES 1,573.29 1,573.29
02.04.04 INSTALACION DE PLACAS 1,065.94 1,065.94
02.04.05 INSTALACION DE ARTEFACTOS 1,957.79 1,957.79
02.04.06 TABLEROS 281.74 281.74
02.04.07 LLAVES TERMOMAGNETICA 563.78 563.78
PABELLON F
01.01 ESTRUCTURAS " F "
01.01.01 OBRAS PRELIMINARES 693.43 396.24 297.19
01.01.02 MOVIMIENTO DE TIERRAS 495.45 495.45
01.01.03 CONCRETO SIMPLE 8,555.30 8,555.30
01.01.04 CONCRETO ARMADO
01.01.04.01 ZAPATAS 465.12 465.12
01.01.04.02 COLUMNAS DE CONFINAMIENTO 216.71 216.71
01.01.04.03 COLUMNAS 1,857.13 1,857.13
01.01.04.04 VIGAS 112.07 112.07
01.01.04.05 ESCALERAS DE CONCRETO ARMADO 3,551.18 3,551.18
01.02 ARQUITECTURA " F "
01.02.01 MUROS Y TABIQUES 1,495.43 1,495.43
01.02.02 REVOQUES ENLUCIDOS Y MOLDURAS 2,395.55 2,395.55
01.02.03 PISOS Y PAVIMENTOS 2,695.88 2,695.88
01.02.04 CONTRAZOCALOS 1,272.30 1,090.54 181.76
01.02.05 CARPINTERIA DE MADERA 2,049.60 2,049.60
01.02.06 CARPINTERIA METALICA 576.48 576.48
01.02.07 CERRAJERIA 704.94 704.94
01.02.08 VIDRIOS, CRISTALES Y SIMILARES 99.37 99.37
01.02.09 PINTURA 3,977.24 3,977.24
01.02.10 OTROS 71.82 71.82
01.03 INSTALACIONES SANITARIAS " F "
01.03.01 DESAGUE PLUVIAL 1,347.87 1,347.87
01.04 INSTALACIONES ELECTRICAS " F "
01.04.01 TUBERIA Y CANALIZACION 3,509.88 3,509.88
01.04.02 CAJAS DE PASE 1,231.49 1,231.49
01.04.03 CONDUCTORES 1,658.80 1,658.80
01.04.04 INSTALACION DE PLACAS 458.65 305.76 152.89
01.04.05 INSTALACION DE ARTEFACTOS 1,354.77 1,354.77
01.04.06 TABLEROS 479.02 479.02
01.04.07 LLAVES TERMOMAGNETICA 2,208.82 2,208.82
PABELLON G
01 ESTRUCTURAS " G "
01.01 OBRAS PROVISIONALES 7,560.45 7,560.45
01.02 OBRAS PRELIMINARES 16,064.87 4,760.00 11,304.87
01.03 MOVIMIENTO DE TIERRAS 25,113.08 15,695.70 9,417.38
01.04 CONCRETO SIMPLE 32,934.17 32,934.17
01.05 CONCRETO ARMADO
01.05.01 ZAPATAS 25,661.63 25,661.63
01.05.02 COLUMNAS 103,965.88 72,776.11 31,189.77
01.05.03 COLUMNAS DE CONFINAMIENTO 19,507.40 10,267.01 9,240.39
01.05.04 PLACAS 32,817.37 15,443.50 17,373.87
01.05.05 VIGAS 157,100.09 62,840.03 94,260.06
01.05.06 ESCALERAS DE CONCRETO ARMADO 15,722.39 7,337.11 8,385.28
01.05.07 LOSAS ALIGERADAS E=25CM 183,303.36 4,582.74 87,069.02 45,825.80 45,825.80
01.05.08 MESAS DE CONCRETO ARMADO EN LABORATORIO 3,156.90 3,156.90
01.05.09 CISTERNA 4,596.49 4,596.49
01.05.10 TANQUE ELEVADO 4,059.61 4,059.61
01.05.11 COBERTURAS 959.22 959.22
02 ARQUITECTURA " G "
02.01 MUROS Y TABIQUES 67,423.92 42,701.74 24,722.18
02.02 REVOQUES ENLUCIDOS Y MOLDURAS 91,366.39 22,841.60 34,262.40 34,262.39
02.03 CIELORRASOS 65,871.87 19,961.11 45,910.76
02.04 PISOS Y PAVIMENTOS 68,562.78 27,425.13 41,137.65
02.05 CONTRAZOCALOS 6,484.04 6,484.04
02.06 ZOCALOS 10,802.90 10,802.90
02.07 CARPINTERIA DE MADERA 22,155.20 6,330.00 15,825.20
02.08 CARPINTERIA METALICA 21,665.44 5,416.24 16,249.20
02.09 CERRAJERIA
02.09.01 CERRADURAS 2,947.77 2,947.77
02.10 VIDRIOS, CRISTALES Y SIMILARES 17,009.35 17,009.35
02.11 PINTURA 31,177.89 31,177.89
02.12 APARATOS Y ACCESORIOS SANITARIOS 9,602.98 3,201.00 6,401.98
02.13 OTROS 576.08 576.08
03 INSTALACIONES SANITARIAS " G "
03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 5,407.82 5,407.82
03.02 SISTEMA DE DESAGUE 7,240.49 7,240.49
03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS 1,549.40 1,549.40
04 INSTALACIONES ELECTRICAS " G "
04.01 TUBERIA Y CANALIZACION 9,140.30 9,140.30
04.02 INSTALACION DE PLACAS 11,682.71 11,682.71
04.03 SALIDA PARA COMUNICACIONES Y SEÑALES 4,697.69 4,697.69
04.04 SISTEMA DE DATA Y VOZ 7,616.44 3,808.24 3,808.20
04.05 CONDUCTORES Y/O CABLES 9,511.29 9,511.29
04.06 TABLEROS 2,232.36 2,232.36
04.07 LLAVES Y CUCHILLAS 3,611.96 3,611.96
04.08 ARTEFACTOS 7,949.43 7,949.43
04.09 EQUIPOS SISTEMA CONTRA INCENDIO 1,411.88 1,411.88
04.10 SISTEMA DE PUESTA A TIERRA 3,634.34 1,514.30 2,120.04
04.11 EQUIPOS ELECTRICOS Y MECANICOS 1,113.24 927.70 185.54
02 PABELLON H
02.01 ESTRUCTURAS " H "
02.01.01 OBRAS PRELIMINARES 16,646.83 16,646.83
02.01.02 CONCRETO SIMPLE 12,865.39 12,865.39
02.01.03 CONCRETO ARMADO
02.01.03.01 PLATAFORMAS PARA MAQUINARIAS 4,163.01 4,163.01
02.02 ARQUITECTURA " H "
02.02.01 MUROS Y TABIQUES 12,616.10 12,616.10
02.02.02 REVOQUES ENLUCIDOS Y MOLDURAS 22,378.94 22,378.94
02.02.03 CIELORRASOS 5,210.26 5,210.26
02.02.04 PISOS Y PAVIMENTOS 46,543.83 9,308.79 37,235.04
02.02.05 CONTRAZOCALOS 5,177.64 5,177.64
02.02.06 ZOCALOS 1,932.18 1,932.18
02.02.07 CARPINTERIA DE MADERA 11,726.40 11,726.40
02.02.08 CARPINTERIA METALICA 14,740.14 7,861.38 6,878.76
02.02.09 VIDRIOS, CRISTALES Y SIMILARES 15,234.79 15,234.79
02.02.10 PINTURA 24,412.26 1,627.54 22,784.72
02.02.11 APARATOS Y ACCESORIOS SANITARIOS 4,054.39 4,054.39
02.02.12 OTROS 199.43 199.43
02.03 INSTALACIONES ELECTRICAS " H "
02.03.01 TUBERIA Y CANALIZACION 6,790.09 6,790.09
02.03.02 CAJAS DE PASE 19.41 19.41
02.03.03 CONDUCTORES 8,342.77 8,342.77
02.03.04 INSTALACION DE PLACAS 1,503.36 1,503.36
02.03.05 INSTALACION DE ARTEFACTOS 7,696.35 7,696.35
02.03.06 TABLEROS 1,593.66 1,593.66
02.03.07 LLAVES TERMOMAGNETICA 5,115.02 5,115.02
PABELLON I
01.01 ESTRUCTURAS " I "
01.01.01 OBRAS PRELIMINARES 7,257.34 7,257.34
01.01.02 MOVIMIENTO DE TIERRAS 6,814.73 6,814.73
01.01.03 CONCRETO SIMPLE 21,725.99 21,725.99
01.01.04 CONCRETO ARMADO
01.01.04.01 ZAPATAS 354.98 354.98
01.01.04.02 COLUMNAS 1,311.58 1,311.58
01.01.04.03 VIGAS 484.10 484.10
01.01.04.04 ESCALERAS DE CONCRETO ARMADO 2,405.16 801.72 1,603.44
01.01.04.05 LOSA MACIZA E=20 CM 959.80 319.94 639.86
01.01.04.06 ESTRUCTURAS METALICAS Y COBERTURA 11,098.95 11,098.95
01.02 ARQUITECTURA "I"
01.02.01 MUROS Y TABIQUES 1,718.53 1,718.53
01.02.02 REVOQUES ENLUCIDOS Y MOLDURAS 20,379.26 20,379.26
01.02.03 CIELORRASOS 1,515.03 1,515.03
01.02.04 PISOS Y PAVIMENTOS 4,998.42 4,998.42
01.02.05 CONTRAZOCALOS 567.30 567.30
01.02.06 ZOCALOS 4,201.94 4,201.94
01.02.07 CARPINTERIA DE MADERA 1,092.80 1,092.80
01.02.08 CARPINTERIA METALICA 34,263.12 34,263.12
01.02.09 CERRAJERIA 1,387.68 1,387.68
01.02.10 VIDRIOS, CRISTALES Y SIMILARES 2,338.35 2,338.35
01.02.11 PINTURA 9,447.20 9,447.20
01.02.12 APARATOS Y ACCESORIOS SANITARIOS 176.20 176.20
01.02.13 OTROS 202.59 202.59
01.03 INSTALACIONES SANITARIAS " I "
01.03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 655.15 655.15
01.03.02 SISTEMA DE DESAGUE 6,487.40 6,487.40
01.03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS 127.00 127.00
01.04 INSTALACIONES ELECTRICAS " I "
01.04.01 TUBERIA Y CANALIZACION 2,356.65 2,062.06 294.59
01.04.02 CAJAS DE PASE 194.10 194.10
01.04.03 CONDUCTORES 1,795.23 1,795.23
01.04.04 INSTALACION DE PLACAS 608.68 608.68
01.04.05 INSTALACION DE ARTEFACTOS 1,833.92 1,833.92
01.04.06 TABLEROS 967.76 967.76
01.04.07 LLAVES TERMOMAGNETICA 1,476.76 1,476.76
PABELLON J
02.01 ESTRUCTURAS " J "
02.01.01 OBRAS PRELIMINARES 10,451.62 10,451.62
02.01.02 MOVIMIENTO DE TIERRAS 6,625.77 6,625.77
02.01.03 CONCRETO SIMPLE 21,854.35 21,854.35
02.01.04 CONCRETO ARMADO
02.01.04.01 ZAPATAS 3,973.35 3,973.35
02.01.04.02 COLUMNAS 10,666.86 10,666.86
02.01.04.03 VIGAS 4,048.52 4,048.52
02.01.04.04 ESCALERAS DE CONCRETO ARMADO 2,053.49 2,053.49
02.01.04.05 ESTRUCTURAS METALICAS Y COBERTURA 28,373.68 14,186.82 14,186.86
02.02 ARQUITECTURA " J "
02.02.01 MUROS Y TABIQUES 4,022.90 3,017.18 1,005.72
02.02.02 REVOQUES ENLUCIDOS Y MOLDURAS 15,283.46 1,273.64 14,009.82
02.02.03 CIELORRASOS 2,828.66 2,828.66
02.02.04 PISOS Y PAVIMENTOS 7,328.69 7,328.69
02.02.05 CONTRAZOCALOS 2,505.45 2,505.45
02.02.06 ZOCALOS 312.95 312.95
02.02.07 CARPINTERIA DE MADERA 4,596.48 4,596.48
02.02.08 CARPINTERIA METALICA 9,502.54 9,502.54
02.02.09 CERRAJERIA 920.64 920.64
02.02.10 VIDRIOS, CRISTALES Y SIMILARES 2,823.11 2,823.11
02.02.11 PINTURA 7,874.21 7,874.21
02.02.12 APARATOS Y ACCESORIOS SANITARIOS 176.20 176.20
02.02.13 OTROS 257.51 257.51
02.03 INSTALACIONES SANITARIAS " J "
02.03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 398.80 398.80
02.03.02 SISTEMA DE DESAGUE 4,202.82 4,202.82
02.03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS 127.00 127.00
02.04 INSTALACIONES ELECTRICAS " J "
02.04.01 TUBERIA Y CANALIZACION 4,373.39 4,373.39
02.04.02 CAJAS DE PASE 155.28 155.28
02.04.03 CONDUCTORES 5,249.10 5,249.10
02.04.04 INSTALACION DE PLACAS 550.57 550.57
02.04.05 INSTALACION DE ARTEFACTOS 2,199.49 2,199.49
02.04.06 TABLEROS 1,093.62 1,093.62
02.04.07 LLAVES TERMOMAGNETICA 4,233.99 4,233.99
PABELLON K
0101 ESTRUCTURAS " K "
010101 OBRAS PRELIMINARES 5,358.05 5,358.05
010102 MOVIMIENTO DE TIERRAS 6,495.29 6,495.29
010103 CONCRETO SIMPLE 13,632.33 13,632.33
010104 CONCRETO ARMADO
01010401 ZAPATAS 2,354.12 2,354.12
01010402 COLUMNAS 3,813.25 3,813.25
01010403 VIGAS 1,590.88 1,590.88
01010404 ESTRUCTURAS METALICAS Y COBERTURA 8,367.05 2,789.01 5,578.04
0102 ARQUITECTURA " K "
010201 MUROS Y TABIQUES 6,071.52 3,035.76 3,035.76
010202 REVOQUES ENLUCIDOS Y MOLDURAS 15,390.89 15,390.89
010203 CIELORRASOS 1,852.00 1,852.00
010204 PISOS Y PAVIMENTOS 142.26 142.26
010205 ZOCALOS 1,809.05 1,809.05
010206 CARPINTERIA DE MADERA 315.39 315.39
010207 CARPINTERIA METALICA 14,620.04 13,645.37 974.67
010208 CERRAJERIA 1,155.84 1,155.84
010209 VIDRIOS, CRISTALES Y SIMILARES 2,199.02 2,199.02
010210 PINTURA 6,718.63 4,703.02 2,015.61
010211 APARATOS Y ACCESORIOS SANITARIOS 176.20 176.20
010212 OTROS 162.70 162.70
0103 INSTALACIONES SANITARIAS " K "
010301 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 263.89 263.89
010302 SISTEMA DE DESAGUE 2,037.73 2,037.73
010303 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS 127.00 127.00
0104 INSTALACIONES ELECTRICAS " K "
010401 TUBERIA Y CANALIZACION 6,252.25 6,252.25
010402 CAJAS DE PASE 97.05 97.05
040403 CONDUCTORES 4,169.38 2,779.58 1,389.80
010404 INSTALACION DE PLACAS 388.97 388.97
010405 INSTALACION DE ARTEFACTOS 1,350.52 1,350.52
010406 TABLEROS 1,446.98 1,446.98
010407 LLAVES TERMOMAGNETICA 1,635.17 1,635.17
PABELLON L
0201 ESTRUCTURAS " L "
020101 OBRAS PRELIMINARES 5,655.71 5,655.71
020102 MOVIMIENTO DE TIERRAS 4,870.00 4,870.00
020103 CONCRETO SIMPLE 12,194.38 12,194.38
020104 CONCRETO ARMADO
02010401 ZAPATAS 3,270.82 3,270.82
02010402 COLUMNAS 5,413.20 5,413.20
02010403 VIGAS 1,801.55 1,801.55
02010404 ESCALERAS DE CONCRETO ARMADO 2,114.50 2,114.50
02010405 ESTRUCTURAS METALICAS Y COBERTURA 19,433.41 13,881.01 5,552.40
0202 ARQUITECTURA " L "
020201 MUROS Y TABIQUES 6,796.53 6,796.53
020202 REVOQUES ENLUCIDOS Y MOLDURAS 13,950.39 5,812.68 8,137.71
020203 CIELORRASOS 5,277.40 5,277.40
020204 PISOS Y PAVIMENTOS 6,693.65 6,693.65
020205 CONTRAZOCALOS 1,697.25 1,697.25
020206 ZOCALOS 370.82 370.82
020207 CARPINTERIA DE MADERA 5,257.73 5,257.73
020208 CARPINTERIA METALICA 5,662.08 5,662.08
020209 CERRAJERIA 1,058.40 1,058.40
020210 VIDRIOS, CRISTALES Y SIMILARES 1,466.33 1,466.33
020211 PINTURA 6,472.03 6,472.03
020212 APARATOS Y ACCESORIOS SANITARIOS 176.20 176.20
020213 OTROS 340.20 243.00 97.20
0203 INSTALACIONES SANITARIAS " L "
020301 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 398.80 398.80
020302 SISTEMA DE DESAGUE 2,842.82 2,842.82
020303 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS 127.00 127.00
0204 INSTALACIONES ELECTRICAS " L "
020401 TUBERIA Y CANALIZACION 8,723.26 8,723.26
020402 CAJAS DE PASE 97.05 97.05
020403 CONDUCTORES 3,311.19 3,311.19
020404 INSTALACION DE PLACAS 610.48 610.48
020405 INSTALACION DE ARTEFACTOS 2,965.10 2,965.10
020406 TABLEROS 770.48 770.48
020407 LLAVES TERMOMAGNETICA 1,548.92 1,548.92
TRATAMIENTO PAISAJISTICO DEL PATIO DE HONOR
0101 ESTRUCTURAS " TP "
010101 OBRAS PRELIMINARES 29,783.76 29,783.76
010102 MOVIMIENTO DE TIERRAS 47,035.93 47,035.93
010103 CONCRETO SIMPLE 73,725.16 8,191.72 40,958.40 24,575.04
010104 CONCRETO ARMADO 2,993.36 2,993.36
010105 ESTRUCTURAS DE METALICA Y COBERTURA 1,768.08 1,768.08
0102 ARQUITECTURA " TP "
010201 REVOQUES ENLUCIDOS Y MOLDURAS 12,067.05 12,067.05
010202 PISOS Y PAVIMENTOS 198,141.06 66,047.06 79,256.40 52,837.60
010203 JARDINERIA 16,194.63 6,072.98 10,121.65
010204 CARPINTERIA METALICA 33,794.42 33,794.42
010205 PINTURA 7,358.71 7,358.71
0103 INSTALACIONES SANITARIAS " TP "
010301 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 26,175.17 13,087.56 13,087.61
010302 SISTEMA DE DESAGUE PLUVIAL
01030209 SUMIDEROS 29,960.33 29,960.33
01030210 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS 431.80 431.80
010303 SISTEMA DE DESAGUE 20,438.36 20,438.36
0104 INSTALACIONES ELECTRICAS " TP "
010401 OBRAS PRELIMINARES 2,508.45 2,508.45
010402 MOVIMIENTO DE TIERRAS 15,292.25 15,292.25
010403 TUBERIA Y CANALIZACION 23,916.39 2,391.63 9,566.56 11,958.20
010404 CAJAS DE PASE 1,941.12 1,941.12
010405 CONDUCTORES Y/O CABLES 88,994.59 88,994.59
010406 TABLEROS
01040601 TABLERO GENERAL 300.51 300.51
01040602 TABLEROS DE DISTRIBUCION 77.82 77.82
010407 LLAVES Y CUCHILLAS 3,524.65 3,524.65
010408 POSTES DE ILUMINACION 4,223.88 4,223.88
010409 ARTEFACTOS DE ILUMINACION 6,974.52 6,974.52
010410 POZOS A TIERRA 8,439.34 8,439.34
CERCO PERIMETRICO
0201 ESTRUCTURAS " CP "
020101 OBRAS PRELIMINARES 686.32 686.32
020102 MOVIMIENTO DE TIERRAS 313.64 313.64
020103 CONCRETO SIMPLE 1,118.68 1,118.68
020104 CONCRETO ARMADO
02010401 ZAPATAS 391.86 391.86
02010402 COLUMNAS 1,495.55 1,495.55
02010403 COLUMNAS DE CONFINAMIENTO 4,295.43 4,295.43
02010404 VIGAS 1,386.46 1,386.46
0202 ARQUITECTURA "CP"
020201 REVOQUES ENLUCIDOS Y MOLDURAS 3,065.08 3,065.08
020202 VIDRIOS, CRISTALES Y SIMILARES 31.00 31.00
020203 PINTURA 2,964.83 2,964.83

COSTOS DIRECTOS:
ADMINISTRACION 156,618.99 918.72 16,951.36 51,742.29 63,626.97 18,596.34 4,783.31 0.00 0.00 0.00
PABELLON A,B,C 240,114.74 0.00 12,669.83 81,404.90 137,346.56 8,693.45 0.00 0.00 0.00 0.00
PABELLON D 173,697.66 1,788.28 62,466.15 41,811.12 23,969.14 43,662.97 0.00 0.00 0.00 0.00
PABELLON E 198,741.57 0.00 33,350.15 81,746.92 76,375.14 7,269.36 0.00 0.00 0.00 0.00
PABELLON F 43,534.30 396.24 33,969.19 9,168.87 0.00 0.00 0.00 0.00 0.00 0.00
PABELLON G 1,124,968.87 0.00 0.00 28,016.15 79,318.05 172,156.20 290,978.34 252,231.36 201,812.78 100,455.99
PABELLON H 228,962.25 0.00 0.00 29,512.22 75,538.05 74,759.89 49,152.09 0.00 0.00 0.00
PABELLON I 151,203.70 0.00 0.00 0.00 49,993.52 101,007.59 202.59 0.00 0.00 0.00
PABELLON J 169,064.50 0.00 94,118.35 20,804.17 27,991.29 25,893.18 257.51 0.00 0.00 0.00
PABELLON K 109,993.45 0.00 51,946.17 51,344.76 6,702.52 0.00 0.00 0.00 0.00 0.00
PABELLON L 131,367.68 0.00 0.00 0.00 80,113.38 51,157.10 97.20 0.00 0.00 0.00
TRATAMIENTO PAISAJISTICO DEL PATIO DE HONOR 656,061.34 0.00 0.00 0.00 0.00 0.00 139,107.99 164,889.07 158,957.31 193,106.97
CERCO PERIMETRICO 15,748.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,748.85 0.00

TOTAL DE COSTOS DIRECTOS 3,400,077.90 3,103.24 305,471.20 395,551.40 620,974.62 503,196.08 484,579.03 417,120.43 376,518.94 293,562.96
AVANCE PORCENTUAL MENSUALISADO ( % ) 0.09% 8.98% 11.63% 18.26% 14.80% 14.25% 12.27% 11.07% 8.65%
AVANCE PORCENTUAL MENSUALISADO ACUMULADO ( % ) 0.09% 9.07% 20.70% 38.96% 53.76% 68.01% 80.28% 91.35% 100.00%

SUBTOTALES:
ADMINISTRACION 176,979.46 1,038.15 19,155.04 58,468.79 71,898.48 21,013.86 5,405.14 0.00 0.00 0.00
PABELLON A,B,C 271,329.66 0.00 14,316.91 91,987.54 155,201.61 9,823.60 0.00 0.00 0.00 0.00
PABELLON D 196,278.36 2,020.76 70,586.75 47,246.57 27,085.13 49,339.15 0.00 0.00 0.00 0.00
PABELLON E 224,577.97 0.00 37,685.67 92,374.02 86,303.91 8,214.37 0.00 0.00 0.00 0.00
PABELLON F 49,193.76 447.75 38,385.18 10,360.83 0.00 0.00 0.00 0.00 0.00 0.00
PABELLON G 1,271,214.82 0.00 0.00 31,658.25 89,629.40 194,536.51 328,805.52 285,021.44 228,048.44 113,515.26
PABELLON H 258,727.34 0.00 0.00 33,348.81 85,358.00 84,478.68 55,541.85 0.00 0.00 0.00
PABELLON I 170,860.18 0.00 0.00 0.00 56,492.68 114,138.58 228.92 0.00 0.00 0.00
PABELLON J 191,042.89 0.00 106,353.74 23,508.71 31,630.16 29,259.29 290.99 0.00 0.00 0.00
PABELLON K 124,292.60 0.00 58,699.17 58,019.58 7,573.85 0.00 0.00 0.00 0.00 0.00
PABELLON L 148,445.48 0.00 0.00 0.00 90,528.12 57,807.52 109.84 0.00 0.00 0.00
TRATAMIENTO PAISAJISTICO DEL PATIO DE HONOR 741,349.31 0.00 0.00 0.00 0.00 0.00 157,192.03 186,324.65 179,621.76 218,210.87
CERCO PERIMETRICO 17,796.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,796.20 0.00

TOTAL DE SUBTOTALES 3,842,088.03 3,506.66 345,182.46 446,973.10 701,701.34 568,611.56 547,574.29 471,346.09 425,466.40 331,726.13
AVANCE PORCENTUAL MENSUALISADO ( % ) 0.09% 8.98% 11.63% 18.26% 14.80% 14.25% 12.27% 11.07% 8.65%
AVANCE PORCENTUAL MENSUALISADO ACUMULADO ( % ) 0.09% 9.07% 20.70% 38.96% 53.76% 68.01% 80.28% 91.35% 100.00%
176,979.46 0.00
271,329.66 0.00
196,278.36 0.00
224,577.97 0.00
49,193.76 0.00
1,271,214.82 0.00
258,727.34 0.00
170,860.18 0.00
191,042.89 0.00
124,292.60 0.00
148,445.48 0.00
741,349.31 0.00
17,796.20 0.00

3,842,088.03 0.00
FICHA DE IDENTIFICACION DE LA OBRA

1 Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVO DE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
2 Ubicación : JUNIN - HUANCAYO - TAMBO
Region : JUNIN
Departamento : JUNIN
Provincia : HUANCAYO
Distrito : TAMBO
Localidad : TAMBO
Area Geografica : 3
3 Cliente : GOBIERNO REGIONAL DE JUNIN
4 Contratista : VASMER CADS S.A
5 Financiamiento : RECURSOS ORDINARIOS
6 Sistema de Contratacion : A SUMA ALZADA
7 Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
8 Presupuesto Base : S/. 4,572,084.75 con I.G.V. 3,842,088.03 sin I.G.V.
9 Contrato Nº : 982-2010-GRJ/UEIM
10 Factor de Relacion (Fr) : 1.00000
11 Monto del Contrato : S/. 4,572,084.75 con I.G.V. 3,842,088.03 sin I.G.V.
12 Plazo Contractual : 240 dias calendarios
13 Costo Directo de la Obra : S/. 3,400,077.90
14 Gastos Generales : S/. 272,006.23 8%
15 Utilidad : S/. 170,003.89 5%
16 Monto del Adelanto Directo : S/. 914,416.95 con I.G.V. 768,417.61 sin I.G.V.
17 Monto del Adelanto para Materiales : S/. 1,828,833.90 con I.G.V. 1,536,835.21 sin I.G.V.
Eventos:
1 Fecha del Valor Referencial : February-2010 Bases Administrativas
2 Fecha de Otorgamiento de Buena Pro : 02-November-2010
3 Fecha de Firma de Contrato : 18-November-2010 Contrato N° 982- 2010
4 Fecha Solicitud de Adelanto Directo : 24-November-2010 Carta Nº 211 -2010-VCSA
5 Fecha Factura de Adelanto Directo : 01-December-2010 Factura N° 001-002047 por S/. 914,416.95
6 Fecha de cambio de Residente de Obra : 06-December-2010 Carta Nº 219 -2010-VCSA ING. PABLO SARMIENTO REYES
7 Fecha de Entrega de Terreno : 16-December-2010 Acta
8 Designacion del Supervisor : 24-November-2010 Carta Nº 1358 -2010-GRJ7UEIM ING. ANTONIO VALENZUELA SALAS
9 Fecha de Pago de Adelanto Directo : 24-November-2010 Carta Nº 1357 -2010-GRJ7UEIM
10 Fecha de Entrega de Expedeinte Tecnico : 04-October-2010 Carta N° 1138-2010-GRJUNIN/UEIM (04/10/2010)
11 Fecha de Inicio Contractual : 28-January-2011
12 Fecha Solicitud de Adelanto de Materiales : 02-February-2011 Carta Nº 026 -2010-VCSA por S/. 1,828,833.90
13 Fecha Factura de Adelanto de Materiales : 01-February-2011 Factura N° 001-002074 por S/. 1,828,833.90
14 Fecha de Pago de Adelanto Materiales : 01-April-2011 Factura N° 001-002078 por S/. 1,709,705.80
15 Fecha de Fin Contractual : 24-September-2011
VALORIZACION DE OBRA Nº 04
(Periodo : Del 01 Mayo al 31 Mayo 2011)

Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVODE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A Valor Referencial (S/.) : 4,572,084.75 con IGV
Plazo de Ejecucion : 240 Dias Calendarios Costos al : February-2010
Supervisor : ING. ANTONIO VALENZUELA SALAS Monto del Contrato (S/.) : 4,572,084.75 con IGV
Residente : ING. PABLO SARMIENTO REYES Factor de Relacion : 1.0000

Formula : 001 - PABELLON ADMINISTRATIVO


AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UNIDAD METRADO PRECIO PARCIAL Metrado Monto Metrado Monto Metrado Monto % Metrado
UNITARIO
01 ESTRUCTURAS "ADM"
01.01 OBRAS PRELIMINARES
01.01.01 DEMOLICION DE PISOS DE CEMENTO PULIDO Y LOSETA DE GRANITO m2 590.06 4.33 2,554.96 590.06 2,554.96 0.00 590.06 2,554.96 100.00% 0.00
01.01.02 DEMOLICION DE PISOS DE PARQUET m2 106.72 2.64 281.74 106.72 281.74 0.00 106.72 281.74 100.00% 0.00
01.01.03 DEMOLICION DE MUROS DE LADRILLO m2 16.49 28.84 475.57 16.49 475.57 0.00 16.49 475.57 100.00% 0.00
01.01.04 RETIRO DE PUERTAS Y VENTANAS m2 7.77 3.20 24.86 7.77 24.86 0.00 7.77 24.86 100.00% 0.00
01.01.05 ACARREO MATERIAL PROVENIENTE DE DEMOLICIONES D=50M M3 159.27 12.36 1,968.58 159.27 1,968.58 0.00 159.27 1,968.58 100.00% 0.00
01.01.06 ELIMINACION DE DEMOLICIONES M3 159.27 9.95 1,584.74 159.27 1,584.74 0.00 159.27 1,584.74 100.00% 0.00
01.02 MOVIMIENTOS DE TIERRAS
01.02.01 EXCAVACION PARA CAJA DE CISTERNA M3 40.43 24.72 999.43 40.43 999.43 0.00 40.43 999.43 100.00% 0.00
01.03 CONCRETO ARMADO
01.03.01 CONCRETO f´c=175kg/cm2 PARA CAJA DE CISTERNA M3 15.10 256.63 3,875.11 15.10 3,875.11 0.00 15.10 3,875.11 100.00% 0.00
01.03.02 ACERO FÝ=4200 KG/CM2 CAJA DE CISTERNA kg 295.98 3.41 1,009.29 295.98 1,009.29 0.00 295.98 1,009.29 100.00% 0.00
01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL EN CISTERNA SUBTERRANEA m2 5.88 20.14 118.42 5.88 118.42 0.00 5.88 118.42 100.00% 0.00
01.04 ESTRUCTURA DE MADERA Y COBERTURA
01.04.01 COBERTURA DE FIBRAFORTE TIPO TEJA ANDINA m2 38.00 23.53 894.14 0.00 0.00 0.00 0.00 0.00 0.00% 38.00

01.04.02 ESTRUCTURA METALICA SEGÚN PLANOS Y ESPECIFICACIONES TECNICAS m2 38.00 41.72 1,585.36 0.00 0.00 0.00 0.00 0.00 0.00% 38.00

02 ARQUITECTURA "ADM"
02.01 MUROS Y TABIQUES
02.01.01 TABIQUERIA SISTEMA DRALL WALL E=4" m2 135.76 68.60 9,313.14 0.00 0.00 135.76 9,313.14 135.76 9,313.14 100.00% 0.00
02.02 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.01 TARRAJEO EN EXTERIORES CON CEMENTO ARENA 1:5 m2 181.33 19.63 3,559.51 181.33 3,559.51 0.00 0.00 181.33 3,559.51 100.00% 0.00
02.02.02 TARRAJEO CON IMPERMEABILIZANTE m2 62.14 23.22 1,442.89 62.14 1,442.89 0.00 0.00 62.14 1,442.89 100.00% 0.00
02.02.03 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS m 140.00 20.23 2,832.20 0.00 0.00 0.00 0.00 0.00 0.00% 140.00

02.02.04 RESANE INST. ELECTRICAS TECHO Y PARED ANCHO = 15cm, E = 1.5cm, MEZCLA 1:5 m 837.00 8.27 6,921.99 780.00 6,450.60 0.00 0.00 780.00 6,450.60 93.00% 57.00

02.02.05 RESANE INST. ELECTRICAS PISO - PARED ANCHO = 15cm, E = 1.5cm, MEZCLA 1:5 m 714.00 8.08 5,769.12 680.00 5,494.40 0.00 0.00 680.00 5,494.40 95.00% 34.00

02.02.06 DESCANSO DE ESCALERA, ACABADO CON CEMENTO PULIDO m2 18.79 17.40 326.95 0.00 0.00 0.00 0.00 0.00 0.00% 18.79
02.03 PISOS Y PAVIMENTOS
02.03.01 PISO DE CONCRETO, ACABADO PULIDO Y COLOREADO 1:2X1cm m2 303.28 13.76 4,173.13 303.28 4,173.14 0.00 0.00 303.28 4,173.14 100.00% 0.00
02.03.02 PISO CERAMICO DE 30X30 CM. m2 463.03 32.68 15,131.82 451.79 14,764.50 0.00 0.00 451.79 14,764.50 98.00% 11.24
02.04 ZOCALO Y CONTRAZOCALO
02.04.01 ZOCALO DE CERAMICA BLANCA DE 20 X 30 cm DE 1RA m2 74.88 33.65 2,519.71 0.00 0.00 74.88 2,519.71 74.88 2,519.71 100.00% 0.00
02.04.02 CONTRAZOCALO EN INTERIORES DE CERAMICO H=10CM. m 1,557.25 7.57 11,788.38 1,400.00 10,598.00 126.00 953.82 1,526.00 11,551.82 98.00% 31.25
02.05 CARPINTERIA DE MADERA
02.05.01 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5mm DE TORNILLO m2 15.84 160.00 2,534.40 0.00 0.00 0.00 0.00 0.00 0.00% 15.84
02.06 CARPINTERIA METALICA
02.06.01 VENTANA DE FIERRO PERFIL DE 1" X 1/8" FIJO MARCO "T" DE 1" m2 50.73 99.15 5,029.88 0.00 0.00 0.00 0.00 0.00 0.00% 50.73
02.07 VIDRIOS, CRISTALES Y SIMILARES
02.07.01 PUERTA VAIVEN DE VIDRIO TEMPLADO DE 10MM CON INC/ACCESORIOS u 1.00 1,344.53 1,344.53 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.07.02 VIDRIOS DOBLES NACIONALES p2 3,031.50 3.69 11,186.24 0.00 0.00 0.00 0.00 0.00 0.00% 3,031.50
02.07.03 VIDRIOS TRIPLES POLARIZADOS p2 51.67 5.35 276.43 0.00 0.00 0.00 0.00 0.00 0.00% 51.67
02.08 PINTURA
02.08.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS m2 1,244.22 4.53 5,636.32 0.00 0.00 560.00 2,536.80 560.00 2,536.80 45.00% 684.22
02.08.02 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS m2 1,244.22 5.47 6,805.88 0.00 0.00 560.00 3,063.20 560.00 3,063.20 45.00% 684.22
02.08.03 PINTURA LATEX EN SUPERFICIE DE COLUMNAS, 2 MANOS m2 246.85 5.17 1,276.21 0.00 0.00 111.00 573.87 111.00 573.87 45.00% 135.85
02.08.04 PINTURA LATEX EN CIELORRASO 2 MANOS m2 1,474.00 4.71 6,942.54 0.00 0.00 0.00 0.00 0.00 0.00% 1,474.00
02.08.05 PINTURA EN CARPINTERIA METALICA CON ANTICORROSIVO Y ESMALTE m2 50.73 7.56 383.52 0.00 0.00 0.00 0.00 0.00 0.00% 50.73
02.08.06 PINTURA ESLMALTE EN TANQUE ELEVADO, 2 MANOS m2 88.98 6.04 537.44 0.00 0.00 0.00 0.00 0.00 0.00% 88.98
02.09 APARATOS Y ACCESORIOS SANITARIOS
02.09.01 INODORO C/BLANCO TANQUE BAJO u 6.00 75.63 453.78 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
02.09.02 URINARIOS DE LOZA DE PICO BLANCO pza 6.00 58.82 352.92 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
02.09.03 LAVATORIO DE PARED BLANCO 1 LLAVE pza 6.00 75.36 452.16 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
02.09.04 PAPELERA DE LOZA BLANCA DE 15 X 15 cm pza 6.00 25.21 151.26 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
02.10 OTROS
02.10.01 LIMPIEZA FINAL m2 1,400.00 0.36 504.00 0.00 0.00 0.00 0.00 0.00 0.00% 1,400.00
03 INSTALACIONES SANITARIAS "ADM"
03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
03.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" pto 18.00 55.86 1,005.48 18.00 1,005.48 0.00 0.00 18.00 1,005.48 100.00% 0.00
03.01.02 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m 41.10 7.97 327.57 41.10 327.57 0.00 0.00 41.10 327.57 100.00% 0.00
03.01.03 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP m 12.00 8.28 99.36 12.00 99.36 0.00 0.00 12.00 99.36 100.00% 0.00
03.01.04 RED DE DISTRIBUCION TUBERIA DE 1" PVC-SAP m 12.00 28.48 341.76 12.00 341.76 0.00 0.00 12.00 341.76 100.00% 0.00
03.01.05 RED DE DISTRIBUCION TUNERIA DE 11/2" PVC - SAP m 12.00 31.78 381.36 12.00 381.36 0.00 0.00 12.00 381.36 100.00% 0.00
03.01.06 CODO PVC SAP 1/2" X 90" u 12.00 8.51 102.12 12.00 102.12 0.00 0.00 12.00 102.12 100.00% 0.00
03.01.07 TEE PVC-SAP 1/2" u 12.00 10.34 124.08 12.00 124.08 0.00 0.00 12.00 124.08 100.00% 0.00
03.01.08 VALVULA COMPUERTA DE BRONCE 1/2" u 6.00 42.52 255.12 0.00 0.00 6.00 255.12 6.00 255.12 100.00% 0.00
03.01.09 VALVULA COMPUERTA DE BRONCE 3/4" u 1.00 43.33 43.33 0.00 0.00 1.00 43.33 1.00 43.33 100.00% 0.00
03.01.10 VALVULA COMPUERTA DE BRONCE 1" u 1.00 78.72 78.72 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
03.01.11 VALVULA COMPUERTA DE BRONCE 2" u 1.00 191.55 191.55 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
03.02 SISTEMA DE DESAGUE
03.02.01 SALIDA DE DESAGUE DE 4" pto 6.00 43.36 260.16 6.00 260.16 0.00 0.00 6.00 260.16 100.00% 0.00
03.02.02 SALIDA DE DESAGUE DE 2" pto 18.00 37.67 678.06 18.00 678.06 0.00 0.00 18.00 678.06 100.00% 0.00
03.02.03 SALIDA DE DESAGUE DE VENTILACION DE 2" pto 2.00 35.02 70.04 0.00 0.00 2.00 70.04 2.00 70.04 100.00% 0.00
03.02.04 TUBERIA DE PVC SAL 2" m 137.70 17.39 2,394.60 80.00 1,391.20 37.05 644.30 117.05 2,035.50 85.00% 20.65
03.02.05 TUBERIA DE PVC SAL 4" m 15.30 18.55 283.82 15.30 283.82 0.00 0.00 15.30 283.82 100.00% 0.00
03.02.06 REGISTRO DE BRONCE DE 4" pza 6.00 45.75 274.50 0.00 0.00 6.00 274.50 6.00 274.50 100.00% 0.00
03.02.07 REGISTRO DE BRONCE 2" u 3.00 38.05 114.15 0.00 0.00 3.00 114.15 3.00 114.15 100.00% 0.00
03.02.08 SUMIDERO DE BRONCE DE 2" u 6.00 48.23 289.38 0.00 0.00 6.00 289.38 6.00 289.38 100.00% 0.00
03.02.09 CAJA DE REGISTRO DE DESAGUE 12" X 24" CON TAPA DE FºGº u 1.00 100.45 100.45 0.00 0.00 1.00 100.45 1.00 100.45 100.00% 0.00
03.02.10 YEE PVC SAL 2" u 12.00 11.92 143.04 12.00 143.04 0.00 0.00 12.00 143.04 100.00% 0.00
03.02.11 YEE DE PVC SAL SP RAMAL CON REDUCCION DE 4"-2" u 3.00 12.05 36.15 3.00 36.15 0.00 0.00 3.00 36.15 100.00% 0.00
03.02.12 TEE PVC - SAP 4" u 6.00 13.82 82.92 6.00 82.92 0.00 0.00 6.00 82.92 100.00% 0.00
03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS
03.03.01 COLOCACION DE APARATOS SANITARIOS pza 18.00 50.80 914.40 0.00 0.00 0.00 0.00 0.00 0.00% 18.00
03.03.02 COLOCACION DE ACCESORIOS SANITARIOS pza 6.00 25.40 152.40 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
04 INSTALACIONES ELECTRICAS "ADM"
04.01 TUBERIA Y CANALIZACION
04.01.01 CANALIZACION PARA DUCTO EN PARED Y PISO m 837.15 2.70 2,260.31 738.92 1,995.08 56.37 152.20 795.29 2,147.28 95.00% 41.86
04.01.02 TUBERIA DE PVC SEL 20mm m 714.63 3.08 2,201.06 637.68 1,964.05 41.22 126.96 678.90 2,091.01 95.00% 35.73
04.01.03 TUBERIA DE PVC SEL 25mm m 26.05 34.45 897.42 23.40 806.13 1.35 46.51 24.75 852.64 95.00% 1.30
04.02 CAJAS DE PASE
04.02.01 CAJAS DE PASE 4" x 4" x 2" pza 5.00 94.73 473.65 0.00 0.00 3.00 284.19 3.00 284.19 60.00% 2.00
04.03 CONDUCTORES
04.03.01 CONDUCTOR THW C/CABLE 1 x 6 mm2 m 166.50 2.59 431.24 0.00 0.00 0.00 0.00 0.00 0.00% 166.50
04.03.02 CONDUCTOR THW C/CABLE 1 x 4 mm2 m 1,257.99 1.98 2,490.82 0.00 0.00 377.00 746.46 377.00 746.46 30.00% 880.99
04.03.03 CONDUCTOR THW C/CABLE 1 x 2.5 mm2 m 1,187.98 1.49 1,770.09 0.00 0.00 594.00 885.06 594.00 885.06 50.00% 593.98
04.04 INSTALACION DE PLACAS
04.04.01 TOMACORRIENTES UNIVERSAL DOBLE PARA EMPOTRADO u 84.00 15.66 1,315.44 0.00 0.00 0.00 0.00 0.00 0.00% 84.00
04.04.02 INTERRUPTORES SIMPLE PARA EMPOTRADO u 44.00 17.10 752.40 0.00 0.00 0.00 0.00 0.00 0.00% 44.00
04.04.03 INTERRUPTORES DOBLE PARA EMPOTRADO u 6.00 17.27 103.62 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
04.04.04 INTERRUPTORES DE CONMUTACION SIMPLE u 5.00 17.03 85.15 0.00 0.00 0.00 0.00 0.00 0.00% 5.00
04.05 INSTALACION DE ARTEFACTOS
04.05.01 EQUIPO FLUORESCENTE DOBLE DE 2 x 36 W CON PANTALLA ACRILICO REJILLA u 64.00 54.07 3,460.48 0.00 0.00 0.00 0.00 0.00 0.00% 64.00
04.05.02 LUMINARIA TIPO SPOT LINGH ADOSABLE INC. FOCO AHORRADOR u 15.00 43.37 650.55 0.00 0.00 0.00 0.00 0.00 0.00% 15.00

04.05.03 FLUORESCENTE CIRCULAR DE 32 W INC. BASE ADOSABLE DE ALUMINIO + ACCES. u 9.00 62.53 562.77 0.00 0.00 0.00 0.00 0.00 0.00% 9.00

04.05.04 LUMINARIA TIPO BRAQUETE CON FOCO AHORRADOR DE 18W, PROTECCION A INTERPERIE u 5.00 43.37 216.85 0.00 0.00 0.00 0.00 0.00 0.00% 5.00

04.06 TABLEROS
04.06.01 TABLERO GENERAL 18 POLOS u 1.00 291.26 291.26 0.00 0.00 0.50 145.63 0.50 145.63 50.00% 0.50
04.06.02 TABLERO DE DISTRIBUCION 16 POLOS u 1.00 219.84 219.84 0.00 0.00 0.50 109.92 0.50 109.92 50.00% 0.50
04.06.03 TABLERO DE DISTRIBUCION 14 POLOS u 2.00 219.84 439.68 0.00 0.00 1.00 219.84 1.00 219.84 50.00% 1.00
04.06.04 TABLERO DE DISTRIBUCION 03 POLOS u 1.00 97.98 97.98 0.00 0.00 0.50 48.99 0.50 48.99 50.00% 0.50
04.07 LLAVES TERMOMAGNETICAS
04.07.01 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3 X 50A pza 1.00 78.10 78.10 0.00 0.00 1.00 78.10 1.00 78.10 100.00% 0.00
04.07.02 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3 X 30A pza 1.00 57.09 57.09 0.00 0.00 1.00 57.09 1.00 57.09 100.00% 0.00
04.07.03 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3 X 20A pza 1.00 57.09 57.09 0.00 0.00 1.00 57.09 1.00 57.09 100.00% 0.00
04.07.04 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 30A pza 6.00 37.15 222.90 0.00 0.00 6.00 222.90 6.00 222.90 100.00% 0.00
04.07.05 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 20A pza 7.00 37.15 260.05 0.00 0.00 7.00 260.05 7.00 260.05 100.00% 0.00
04.07.06 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 15A pza 9.00 37.15 334.35 0.00 0.00 9.00 334.35 9.00 334.35 100.00% 0.00
04.08 SISTEMA DE PUESTA A TIERRA
04.08.01 SISTEMA DE TIERRA DE PROTECCION u 1.00 1,205.62 1,205.62 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
04.08.02 PARARRAYOS CON DISPOSOTIVOS DE CEBADO jgo 1.00 2,428.72 2,428.72 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
04.09 EQUIPOS ELECTRICOS Y MECANICOS
04.09.01 ELECTROBOMBA PARA TANQUE CISTERNA TRIFASICO DE 3HP u 1.00 1,491.39 1,491.39 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

COSTO DIRECTO 156,618.99 69,398.08 24,527.15 93,925.23


GASTOS GENERALES % 8.00 12,529.52 5,551.85 1,962.17 7,514.02
UTILIDAD % 5.00 7,830.96 3,469.90 1,226.36 4,696.26
SUBTOTAL 176,979.46 78,419.83 27,715.68 106,135.51
FACTOR DE RELACION 1.0000
SUBTOTAL - con Factor de Relacion 176,979.46 78,419.83 27,715.68 106,135.51

VALORIZACION DE OBRA Nº 04
(Periodo : Del 01 Mayo al 31 Mayo 2011)

Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVODE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A Valor Referencial (S/.) : 4,572,084.75 con IGV
Plazo de Ejecucion : 240 Dias Calendarios Costos al : February-2010
Supervisor : ING. ANTONIO VALENZUELA SALAS Monto del Contrato (S/.) : 4,572,084.75 con IGV
Factor de
Residente : ING. PABLO SARMIENTO REYES Relacion : 1.00

Formula : 002 - PABELLON A,B,C


AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
PRECIO
UNIDAD METRADO UNITARIO PARCIAL Metrado Monto Metrado Monto Metrado Monto % Metrado
01 ESTRUCTURAS "ABC"
01.01 OBRAS PRELIMINARES
01.01.01 DEMOLICION DE PISOS DE CEMENTO PULIDO m2 286.28 4.33 1,239.59 286.28 1,239.59 0.00 286.28 1,239.59 100.00% 0.00
01.01.02 DEMOLICION DE PISOS DE CONCRETO DE 0.10m m2 27.54 6.00 165.24 27.54 165.24 0.00 27.54 165.24 100.00% 0.00
01.01.03 DESENTABLADO DE PISOS DE MADERA MACHIMBRADA m2 595.76 2.64 1,572.81 595.76 1,572.81 0.00 595.76 1,572.81 100.00% 0.00
01.01.04 DEMOLICION DE ZOCALOS DE CERAMICOS m2 115.80 9.87 1,142.95 115.80 1,142.95 0.00 115.80 1,142.95 100.00% 0.00
01.01.05 PICADO EN MUROS PARA ZOCALO CERAMICO m2 31.88 11.54 367.90 31.88 367.90 0.00 0.00 31.88 367.90 100.00%
01.01.06 DEMOLICION DE MUROS DE LADRILLO m3 4.62 5.28 24.39 4.62 24.39 0.00 4.62 24.39 100.00% 0.00
01.01.07 RETIRO DE PUERTAS Y VENTANAS m2 287.49 3.20 919.97 287.49 919.97 0.00 287.49 919.97 100.00% 0.00
01.01.08 ACARREO MATERIAL PROVENIENTE DE DEMOLICIONES D=50M m3 28.95 12.36 357.82 28.95 357.82 0.00 28.95 357.82 100.00% 0.00
01.01.09 ELIMINACION DE DEMOLICIONES m3 28.95 9.95 288.05 28.95 288.05 28.95 288.05 100.00% 0.00
01.02 MOVIMIENTOS DE TIERRAS
01.02.01 EXCAVACION DE ZANJAS PARA ZAPATAS m3 1.30 21.63 28.12 1.30 28.12 0.00 1.30 28.12 100.00% 0.00
01.03 CONCRETO SIMPLE
01.03.01 PISO DE CONCRETO F´C=175 KG/CM2 DE 4" m2 92.32 30.76 2,839.76 92.32 2,839.76 92.32 2,839.76 100.00% 0.00
01.03.02 SOLADOS PARA ZAPATAS E=4" m2 1.00 17.30 17.30 1.00 17.30 0.00 1.00 17.30 100.00% 0.00
01.03.03 PISO CON IMPERMEABILIZANTE SOBRE LOSA DE TECHO DE 1 A 8 CM m2 30.72 15.29 469.71 30.72 469.71 0.00 0.00 30.72 469.71 100.00% 0.00
01.04 CONCRETO ARMADO
01.04.01 ZAPATAS
01.04.01.01 CONCRETO f´c=210kg/cm2 PARA ZAPATAS M3 0.60 253.19 151.91 0.60 151.91 0.00 0.60 151.91 100.00% 0.00
01.04.01.02 ACERO FÝ=4200 KG/CM2 GRADO 60 EN ZAPATAS kg 12.48 3.41 42.56 12.48 42.56 0.00 12.48 42.56 100.00% 0.00
01.04.02 COLUMNAS DE CONFINAMIENTO
01.04.02.01 CONCRETO f´c=175kg/cm2 PARA COLUMNETAS m3 2.43 288.25 700.45 2.43 700.45 0.00 2.43 700.45 100.00% 0.00
01.04.02.02 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS m2 53.58 35.16 1,883.87 53.58 1,883.87 0.00 53.58 1,883.87 100.00% 0.00
01.04.02.03 ACERO FÝ=4200 KG/CM2 PARA COLUMNETAS kg 139.96 3.23 452.07 139.96 452.07 0.00 139.96 452.07 100.00% 0.00
01.04.03 COLUMNAS
01.04.03.01 CONCRETO f´c=210kg/cm2 PARA COLUMNAS m3 0.33 305.86 100.93 0.33 100.93 0.00 0.33 100.93 100.00% 0.00
01.04.03.02 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 4.92 45.92 225.93 4.92 225.93 0.00 4.92 225.93 100.00% 0.00
01.04.03.03 ACERO FÝ=4200 KG/CM2 PARA COLUMNAS kg 125.20 3.41 426.93 125.20 426.93 0.00 125.20 426.93 100.00% 0.00
01.04.04 VIGUETAS DE CONFINAMIENTO
01.04.04.01 CONCRETO f´c=175kg/cm2 PARA VIGUETAS DE CONFINAMIENTO m3 1.64 302.67 496.38 1.64 496.38 0.00 1.64 496.38 100.00% 0.00
01.04.04.02 ENCOFRADO Y DESENCOFRADO PARA VIGUETAS DE CONFINAMIENTO m2 26.04 47.87 1,246.53 26.04 1,246.53 0.00 26.04 1,246.53 100.00% 0.00
01.04.04.03 ACERO FÝ=4200 KG/CM2 PARA VIGUETAS DE CONFINAMIENTO kg 93.82 3.37 316.17 93.82 316.17 0.00 93.82 316.17 100.00% 0.00
02 ARQUITECTURA "ABC"
02.01 MUROS Y TABIQUES

02.01.01 MURO DE LADRILLO CORRIENTE ARTESANAL SOGA 13 x 24 x 8cm CEMENTO - ARENA 1:5 m2 33.85 37.36 1,264.64 33.85 1,264.64 0.00 33.85 1,264.64 100.00% 0.00

02.01.02 MURO DE LADRILLO CORRIENTE ARTESANAL CABEZA 13 x 24 x 8cm CEMENTO - ARENA 1:5 m2 10.78 60.62 653.48 10.78 653.48 0.00 10.78 653.48 100.00% 0.00

02.01.03 MURO DE LADRILLO CORRIENTE ARTESANAL CANTO 13 x 24 x 8cm CEMENTO - ARENA 1:5 m2 25.92 38.87 1,007.51 25.92 1,007.51 0.00 25.92 1,007.51 100.00% 0.00

02.02 REVOQUES ENLUCIDOS Y MOLDURAS


02.02.01 TARRAJEO PRIMARIO RAYADO CON CEMENTO - ARENA 1:5 E=1.5CM m2 130.44 13.24 1,727.03 130.44 1,727.03 0.00 130.44 1,727.03 100.00% 0.00
02.02.02 TARRAJEO EN INTERIORES ACABADO CON CEMENTO - ARENA 1:5 m2 123.69 10.71 1,324.72 123.69 1,324.72 0.00 0.00 123.69 1,324.72 100.00% 0.00
02.02.03 TARRAJEO EN ESTERIORES CON CEMENTO ARENA 1:5 m2 213.95 19.63 4,199.84 213.95 4,199.84 0.00 0.00 213.95 4,199.84 100.00% 0.00
02.02.04 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO - ARENA 1:5 m2 148.30 22.45 3,329.34 148.30 3,329.34 0.00 0.00 148.30 3,329.34 100.00% 0.00
02.02.05 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO - ARENA 1:5 m2 90.23 28.68 2,587.80 90.23 2,587.80 0.00 0.00 90.23 2,587.80 100.00% 0.00
02.02.06 VESTIDURAS DE DERRAMES ANCHO = 15cm, E=1.5cm, MEZCLA 1:5 m 21.57 12.71 274.15 21.57 274.15 21.57 274.15 100.00% 0.00
02.02.07 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS m 229.50 20.23 4,642.79 229.50 4,642.79 0.00 0.00 229.50 4,642.79 100.00% 0.00
02.02.08 DESCANSO DE ESCALERA, ACABADO CON CEMENTO PULIDO m2 25.50 17.40 443.70 25.50 443.70 0.00 0.00 25.50 443.70 100.00% 0.00

02.02.09 RESANE INST. ELECTRICAS TECHO Y PARED ANCHO =15cm E=1.5cm, MEZCLA 1:5 m 336.58 8.27 2,783.52 336.58 2,783.52 0.00 336.58 2,783.52 100.00% 0.00

02.02.10 RESANE INST. ELECTRICAS PISO-PARED ANCHO = 15cm, E= 1.5cm MEZCLA 1:5 m 225.60 8.08 1,822.85 225.60 1,822.85 0.00 225.60 1,822.85 100.00% 0.00

02.03 PISOS Y PAVIMENTOS


02.03.01 CONTRAPISO DE 40mm m2 825.32 25.21 20,806.32 825.32 20,806.32 0.00 0.00 825.32 20,806.32 100.00% 0.00
02.03.02 PISO CERAMICO DE 30 x 30cm. ANTIDESLIZANTE m2 92.34 32.68 3,017.67 92.34 3,017.67 0.00 0.00 92.34 3,017.67 100.00% 0.00
02.03.03 PISO DE CONCRETO ACABADO PULIDO 1:2 x 1cm m2 13.50 12.91 174.29 13.50 174.29 0.00 0.00 13.50 174.29 100.00% 0.00
02.03.04 PISO DE CONCRETO, ACABADO PULIDO Y COLOREADO 1:2 x 1cm m2 692.78 13.76 9,532.65 692.78 9,532.65 0.00 692.78 9,532.65 100.00% 0.00
02.03.05 PISO DE CONCRETO, ACABADO PULIDO BRUÑADO 1:2 x 1cm m2 40.20 27.22 1,094.24 40.20 1,094.24 0.00 0.00 40.20 1,094.24 100.00% 0.00
02.04 CONTRAZOCALOS

02.04.01 CONTRAZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2cm H=30cm m 839.95 5.96 5,006.10 839.95 5,006.10 0.00 0.00 839.95 5,006.10 100.00% 0.00

02.05 ZOCALOS
02.05.01 ZOCALO DE CERAMICA BLANCA DE 20 x 30cm m2 163.05 33.65 5,486.63 163.05 5,486.63 0.00 0.00 163.05 5,486.63 100.00% 0.00
02.06 CARPINTERIA MADERA
02.06.01 PUERTAS DE MADERA TABLERO REBAJADOS DE 4.5mm DE TORNILLO m2 75.60 160.00 12,096.00 63.98 10,236.80 11.62 1,859.20 75.60 12,096.00 100.00% 0.00
02.07 CARPINTERIA METALICA
02.07.01 REHABILITACION DE VENTANA DE FIERRO CON PERFIL DE 1" x 1/8" m2 389.50 16.70 6,504.65 389.50 6,504.65 0.00 389.50 6,504.65 100.00% 0.00
02.07.02 PUERTA METALICA m2 1.85 540.24 999.44 0.00 0.00 1.85 999.44 1.85 999.44 100.00% 0.00
02.07.03 BARANDA METALICA PARA DISCAPACITADOS EN SS.HH. m 2.80 51.14 143.19 0.00 0.00 2.80 143.19 2.80 143.19 100.00% 0.00
02.07.04 MODULO DE TABIQUERIA METALICA u 7.00 517.74 3,624.18 7.00 3,624.18 0.00 0.00 7.00 3,624.18 100.00% 0.00
02.07.05 TAPA JUNTA METALICA 6" x 1/16" CON TORNILLO DE FIJACION m 20.73 69.14 1,433.27 16.00 1,106.24 4.73 327.03 20.73 1,433.27 100.00% 0.00

02.07.06 TAPA JUNTA METALICA EN TECHO 12" x 1/16 CON TORNILLO DE FIJACION m 10.95 66.15 724.34 8.50 562.28 2.45 162.06 10.95 724.34 100.00% 0.00

02.07.07 CANTONERA DE PLANCHA DE FIERRO ESTRIADA EN ANGULO 1/16 m 191.20 26.91 5,145.19 191.20 5,145.19 0.00 191.20 5,145.19 100.00% 0.00
02.08 CERRAJERIA
02.08.01 CERRADURAS
02.08.01.01 CERRADURA FORTE DE 3 GOLPES u 31.00 77.28 2,395.68 10.00 772.80 21.00 1,622.88 31.00 2,395.68 100.00% 0.00
02.08.02 CERROJO DE FIERRO REDONDO DE 1/2" x 0.35m u 1.00 23.63 23.63 1.00 23.63 0.00 0.00 1.00 23.63 100.00% 0.00
02.09 VIDRIOS, CRISTALES Y SIMILARES
02.08.04 VIDRIOS DOBLES NACIONALES p2 4,135.95 3.69 15,261.66 0.00 0.00 4,135.95 15,261.66 4,135.95 15,261.66 100.00% 0.00
02.10 PINTURA
02.10.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS m2 2,977.56 4.53 13,488.35 2,779.47 12,591.00 198.09 897.35 2,977.56 13,488.35 100.00% 0.00
02.10.02 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS m2 915.64 5.47 5,008.55 837.69 4,582.16 77.95 426.39 915.64 5,008.55 100.00% 0.00
02.10.03 PINTURA LATEX EN SUPERFICIES DE VIGAS m2 420.46 5.43 2,283.10 393.48 2,136.60 26.98 146.50 420.46 2,283.10 100.00% 0.00
02.10.04 PINTURA LATEX EN SUPERFICIES DE COLUMNAS 2 MANOS m2 670.17 5.17 3,464.78 609.00 3,148.53 61.17 316.25 670.17 3,464.78 100.00% 0.00
02.10.05 PINTURA LATEX EN DERRAMES, 2 MANOS m2 394.30 3.29 1,297.25 373.35 1,228.32 20.95 68.93 394.30 1,297.25 100.00% 0.00
02.10.06 PINTURA LATEX EN CIELORRASO 2 MANOS m2 2,956.08 4.71 13,923.14 2,741.22 12,911.15 214.86 1,011.99 2,956.08 13,923.14 100.00% 0.00
02.10.07 PINTURA EN VESTIDURAS DE FONDO DE ESCALERA m2 36.38 9.39 341.61 33.00 309.87 3.38 31.74 36.38 341.61 100.00% 0.00
02.10.08 PINTURA DE CONTRAZOCALO CON ESMALTE H=0.40CM EXTERIOR m 839.95 2.66 2,234.27 0.00 0.00 839.95 2,234.27 839.95 2,234.27 100.00% 0.00
02.10.09 PINTURA BARNIZ CON CARPINTERIA DE MADERA m2 151.20 8.92 1,348.70 0.00 0.00 151.20 1,348.70 151.20 1,348.70 100.00% 0.00
02.10.10 PINTURA EN CARPINTERIA METALICA CON ANTICORROSIVO Y ESMALTE m2 1,219.48 7.56 9,219.27 1,121.87 8,481.34 97.61 737.93 1,219.48 9,219.27 100.00% 0.00
02.10.11 PINTURA ESMALTE EN CONTRAZOCALO m 114.00 4.10 467.40 114.00 467.40 0.00 0.00 114.00 467.40 100.00% 0.00
02.11 APARATOS Y ACCESORIOS SANITARIOS
02.11.01 INODORO C/BLANCO TANQUE BAJO u 18.00 75.63 1,361.34 18.00 1,361.34 0.00 0.00 18.00 1,361.34 100.00% 0.00
02.11.02 URINARIO CORRIDO DE CONCRETO HECHO EN OBRA m 15.30 294.43 4,504.78 15.30 4,504.78 0.00 15.30 4,504.78 100.00% 0.00
02.11.03 LAVADERO CORRIDO DE CONCRETO HECHO EN OBRA m 9.00 384.39 3,459.51 9.00 3,459.51 0.00 9.00 3,459.51 100.00% 0.00
02.12 OTROS
02.12.01 LIMPIEZA FINAL m2 4,186.02 0.36 1,506.97 4,186.02 1,506.97 0.00 0.00 4,186.02 1,506.97 100.00% 0.00
03 INSTALACIONES SANITARIAS "ABC"
03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
03.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" pto 36.00 55.86 2,010.96 36.00 2,010.96 0.00 36.00 2,010.96 100.00% 0.00
03.01.02 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m 18.15 7.97 144.66 18.15 144.66 0.00 18.15 144.66 100.00% 0.00
03.01.03 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP m 111.00 8.28 919.08 111.00 919.08 0.00 0.00 111.00 919.08 100.00% 0.00
03.01.04 CODO PVC SAP 1/2" X 90" u 10.00 8.51 85.10 10.00 85.10 0.00 0.00 10.00 85.10 100.00% 0.00
03.01.05 TEE PVC-SAP 1/2" u 32.00 10.34 330.88 32.00 330.88 0.00 32.00 330.88 100.00% 0.00
03.01.06 VALVULA COMPUERTA DE BRONCE 1/2" u 12.00 42.52 510.24 12.00 510.24 0.00 12.00 510.24 100.00% 0.00
03.01.07 VALVULA CHECK DE BRONCE 3/4" u 1.00 64.69 64.69 1.00 64.69 0.00 0.00 1.00 64.69 100.00% 0.00
03.02 SISTEMA DE DESAGUE
03.02.01 SALIDA DE DESAGUE DE 4" pto 18.00 43.36 780.48 18.00 780.48 0.00 18.00 780.48 100.00% 0.00
03.02.02 SALIDA DE DESAGUE DE 2" pto 18.00 37.67 678.06 18.00 678.06 0.00 18.00 678.06 100.00% 0.00
03.02.03 TUBERIA DE PVC SAL 2" m 11.00 17.39 191.29 11.00 191.29 0.00 11.00 191.29 100.00% 0.00
03.02.04 TUBERIA DE PVC SAL 4" m 26.50 18.55 491.58 26.50 491.58 0.00 26.50 491.58 100.00% 0.00
03.02.05 REGISTRO DE BRONCE DE 4" pza 8.00 45.75 366.00 8.00 366.00 0.00 0.00 8.00 366.00 100.00% 0.00
03.02.06 REGISTRO DE BRONCE 2" u 6.00 38.05 228.30 6.00 228.30 0.00 0.00 6.00 228.30 100.00% 0.00
03.02.07 SUMIDERO DE BRONCE DE 2" u 18.00 48.23 868.14 18.00 868.14 0.00 0.00 18.00 868.14 100.00% 0.00
03.02.08 CAJA DE REGISTRO DE DESAGUE 12" X 24" CON TAPA DE FºGº u 6.00 100.45 602.70 6.00 602.70 0.00 0.00 6.00 602.70 100.00% 0.00
03.02.09 YEE PVC SAL 2" u 18.00 11.92 214.56 18.00 214.56 0.00 18.00 214.56 100.00% 0.00
03.02.10 YEE DE PVC SAL SP RAMAL CON REDUCCION DE 4"-2" u 6.00 12.05 72.30 6.00 72.30 0.00 6.00 72.30 100.00% 0.00
03.02.11 CODO PVC SAP 4" X 45" pza 2.00 21.78 43.56 2.00 43.56 0.00 2.00 43.56 100.00% 0.00
03.02.12 TEE PVC - SAP 4" u 3.00 13.82 41.46 3.00 41.46 3.00 41.46 100.00% 0.00
03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS
03.03.01 COLOCACION DE APARATOS SANITARIOS pza 18.00 50.80 914.40 18.00 914.40 0.00 0.00 18.00 914.40 100.00% 0.00
03.04 SISTEMA DE DESAGUE FLUVIAL
03.04.01 TUBERIA DE PVC SAP 3" INC. ABRAZADERA DE 3" m 49.68 16.65 827.17 35.00 582.75 14.68 244.42 49.68 827.17 100.00% 0.00
03.04.02 CODO PVC SAP 3" x 90" u 16.00 21.35 341.60 11.00 234.85 5.00 106.75 16.00 341.60 100.00% 0.00
04 INSTALACIONES ELECTRICAS "ABC"
04.01 TUBERIA Y CANALIZACION
04.01.01 CANALIZACION PARA DUCTO EN PARED Y PISO m 562.18 2.70 1,517.89 562.18 1,517.89 0.00 562.18 1,517.89 100.00% 0.00
04.01.02 TUBERIA DE PVC SEL 20mm m 514.68 3.08 1,585.21 514.68 1,585.21 0.00 514.68 1,585.21 100.00% 0.00
04.01.03 TUBERIA DE PVC SEL 25mm m 55.00 34.45 1,894.75 55.00 1,894.75 0.00 55.00 1,894.75 100.00% 0.00
04.02 CAJAS DE PASE
04.02.01 CAJAS DE PASE de 4" x 4" x 2" u 9.00 27.65 248.85 9.00 248.85 0.00 9.00 248.85 100.00% 0.00
04.03 CONDUCTORES
04.03.01 CONDUCTOR THW C/CABLE 1 x 6 mm2 m 230.00 2.59 595.70 230.00 595.70 0.00 0.00 230.00 595.70 100.00% 0.00
04.03.02 CONDUCTOR THW C/CABLE 1 x 2.5 mm2 m 2,353.20 1.49 3,506.27 2,353.20 3,506.27 0.00 2,353.20 3,506.27 100.00% 0.00
04.03.03 CONDUCTOR THW C/CABLE 1 x 4 mm3 m 1,675.56 1.98 3,317.61 1,675.56 3,317.61 0.00 1,675.56 3,317.61 100.00% 0.00
04.04 INSTALACION DE PLACAS
04.04.01 TOMACORRIENTES UNIVERSAL DOBLE PARA EMPOTRADO u 158.00 15.66 2,474.28 158.00 2,474.28 0.00 0.00 158.00 2,474.28 100.00% 0.00

04.04.02 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRAR A PRUEBA DE AGUA u 3.00 40.98 122.94 3.00 122.94 0.00 0.00 3.00 122.94 100.00% 0.00

04.04.03 INTERRUPTORES SIMPLE PARA EMPOTRADO u 27.00 17.10 461.70 27.00 461.70 0.00 27.00 461.70 100.00% 0.00
04.04.04 INTERRUPTORES DOBLE PARA EMPOTRADO u 35.00 17.27 604.45 35.00 604.45 0.00 0.00 35.00 604.45 100.00% 0.00
04.05 INSTALACION DE ARTEFACTOS

04.05.01 EQUIPO FLUORESCENTE DOBLE DE 2 x 36 W CON PANTALLA ACRILICO REJILLA u 136.00 54.07 7,353.52 122.00 6,596.54 14.00 756.98 136.00 7,353.52 100.00% 0.00

04.05.02 LUMINARIA TIPO SPOT LINGH ADOSABLE INC. FOCO AHORRADOR u 78.00 43.37 3,382.86 29.00 1,257.73 49.00 2,125.13 78.00 3,382.86 100.00% 0.00

04.05.03 LUMINARIA TIPO BRAQUETE CON FOCO AHORRADOR DE 18W, PROTECCION A INTERPERIE u 1.00 43.37 43.37 0.00 0.00 1.00 43.37 1.00 43.37 100.00% 0.00

04.06 TABLEROS
04.06.01 TABLERO GENERAL 12 POLOS u 3.00 93.78 281.34 0.00 0.00 3.00 281.34 3.00 281.34 100.00% 0.00
04.06.02 TABLERO DE DISTRIBUCION 12 POLOS u 9.00 93.98 845.82 0.00 0.00 9.00 845.82 9.00 845.82 100.00% 0.00
04.07 LLAVES TERMOMAGNETICAS
04.07.01 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 15A pza 18.00 37.15 668.70 0.00 0.00 18.00 668.70 18.00 668.70 100.00% 0.00
04.07.02 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 20A pza 13.00 37.15 482.95 0.00 0.00 13.00 482.95 13.00 482.95 100.00% 0.00
04.07.03 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 30A pza 9.00 37.15 334.35 0.00 0.00 9.00 334.35 9.00 334.35 100.00% 0.00
04.07.04 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3 X 30A pza 9.00 57.09 513.81 0.00 0.00 9.00 513.81 9.00 513.81 100.00% 0.00
04.07.05 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3 X 60A pza 3.00 78.10 234.30 0.00 0.00 3.00 234.30 3.00 234.30 100.00% 0.00

COSTO DIRECTO 240,114.74 205,881.33 34,233.43 240,114.74


GASTOS GENERALES % 8.00 19,209.18 16,470.51 2,738.67 19,209.18
UTILIDAD % 5.00 12,005.73 10,294.07 1,711.67 12,005.74
SUBTOTAL 271,329.66 232,645.91 38,683.77 271,329.66
FACTOR DE RELACION 1.0000
SUBTOTAL - con Factor de Relacion 271,329.66 232,645.91 38,683.77 271,329.66

VALORIZACION DE OBRA Nº 04
(Periodo : Del 01 Mayo al 31 Mayo 2011)
Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVODE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A Valor Referencial (S/.) : 4,572,084.75 con IGV
Plazo de Ejecucion : 240 Dias Calendarios Costos al : February-2010
Supervisor : ING. ANTONIO VALENZUELA SALAS Monto del Contrato (S/.) : 4,572,084.75 con IGV
Residente : ING. PABLO SARMIENTO REYES Factor de Relacion : 1.00

Formula : 003 - PABELLON D Y E


AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
PRECIO
UNIDAD METRADO UNITARIO PARCIAL Metrado Monto Metrado Monto Metrado Monto % Metrado

01 PABELLON "D"
01.01 ESTRUCTURAS "D"
01.01.01 OBRAS PRELIMINARES
01.01.01.01 DEMOLICION DE PISOS DE CONCRETO DE 0.10m m2 284.05 6.00 1,704.30 284.05 1,704.30 0.00 284.05 1,704.30 100.00% 0.00
01.01.01.02 DEMOLICION DE MUROS DE LADRILLO m3 43.65 5.28 230.47 43.65 230.47 0.00 43.65 230.47 100.00% 0.00
01.01.01.03 DEMOLICION DE COLUMNETAS DE CONCRETO m3 0.43 53.87 23.16 0.43 23.16 0.00 0.43 23.16 100.00% 0.00
01.01.01.04 DEMOLICION DE LOSA ALIGERADA m3 7.64 54.80 418.67 7.64 418.67 0.00 7.64 418.67 100.00% 0.00
01.01.01.05 DEMOLICION DE ESCALERA DE CONCRETO m3 2.28 24.14 55.04 2.28 55.04 0.00 2.28 55.04 100.00% 0.00
01.01.01.06 DESMONTAJE DE COBERTURA DE CALAMINA m2 300.20 3.65 1,095.73 300.20 1,095.73 0.00 300.20 1,095.73 100.00% 0.00
01.01.01.07 RETIRO DE TIJERALES DE MADERA u 9.00 55.23 497.07 9.00 497.07 0.00 9.00 497.07 100.00% 0.00
01.01.01.08 RETIRO DE PUERTAS Y VENTANAS m2 121.23 3.20 387.94 121.23 387.94 0.00 121.23 387.94 100.00% 0.00
01.01.01.09 ACARREO MATERIAL PROVENIENTE DE DEMOLICION D=50M m3 102.81 12.36 1,270.73 102.81 1,270.73 0.00 102.81 1,270.73 100.00% 0.00
01.01.01.10 ELIMINACION DE DEMOLICIONES m3 102.81 9.95 1,022.96 102.81 1,022.96 0.00 102.81 1,022.96 100.00% 0.00
01.01.02 MOVIMIENTOS DE TIERRAS
01.01.02.01 EXCAVACION PARA ZANJAS EN TERRENO NORMAL m3 9.70 24.24 235.13 9.70 235.13 0.00 9.70 235.13 100.00% 0.00
01.01.02.02 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 2.71 21.63 58.62 2.71 58.62 0.00 2.71 58.62 100.00% 0.00
01.01.02.03 RELLENO CON MATERIAL PROPIO m3 5.20 42.66 221.83 5.20 221.83 5.20 221.83 100.00% 0.00
01.01.02.04 ACRREO MATERIAL EXCEDENTE D=50M m3 9.01 12.36 111.36 9.01 111.36 0.00 9.01 111.36 100.00% 0.00
01.01.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO m3 9.01 9.58 86.32 9.01 86.32 0.00 9.01 86.32 100.00% 0.00
01.01.02.06 AFIRMADO E=4" PARA VEREDAS m2 73.35 5.92 434.23 0.00 0.00 73.35 434.23 73.35 434.23 100.00% 0.00

01.01.02.07 NIVELACION, RELLENO Y COMPACTACION CON MATERIAL DE PRESTAMO m2 252.70 7.43 1,877.56 252.70 1,877.56 0.00 252.70 1,877.56 100.00% 0.00

01.01.03 CONCRETO SIMPLE


01.01.03.01 CONCRETO 1:10 + 30% P.G. PARA CIMIENTOS CORRIDOS m3 1.89 150.25 283.97 1.89 283.97 0.00 1.89 283.97 100.00% 0.00
01.01.03.02 CONCRETO 1:8 + 25% PM PARA SOBRECIMIENTOS m3 0.63 228.31 143.84 0.63 143.84 0.00 0.63 143.84 100.00% 0.00
01.01.03.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 2.52 21.46 54.08 2.52 54.08 0.00 2.52 54.08 100.00% 0.00
01.01.03.04 SOLADOS PARA ZAPATAS E=4" m2 5.88 17.30 101.72 5.88 101.72 0.00 5.88 101.72 100.00% 0.00
01.01.03.05 FALSO PISO DE 4" DE CONCRETO 1:10 m2 252.70 15.60 3,942.12 252.70 3,942.12 0.00 252.70 3,942.12 100.00% 0.00
01.01.03.06 VEREDA F´C =175 KG/CM2 DE CONCRETO DE 4" m2 62.90 30.76 1,934.80 0.00 0.00 25.16 773.92 25.16 773.92 40.00% 37.74
01.01.03.07 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 9.61 29.44 282.92 0.00 0.00 3.84 113.05 3.84 113.05 40.00% 5.77
01.01.03.08 JUNTAS ASFALTICAS EN VEREDAS m 22.10 5.15 113.82 0.00 0.00 0.00 0.00 0.00 0.00% 22.10
01.01.04 CONCRETO ARMADO
01.01.04.01 ZAPATAS
01.01.04.01.01 CONCRETO f´c=210kg/cm2 PARA ZAPATAS M3 3.82 253.19 967.19 3.82 967.19 0.00 3.82 967.19 100.00% 0.00
01.01.04.01.02 ACERO FÝ=4200 KG/CM2 GRADO 60 EN ZAPATAS kg 59.91 3.41 204.29 59.91 204.29 0.00 59.91 204.29 100.00% 0.00
01.01.04.02 COLUMNAS
01.01.04.02.01 CONCRETO f´c=210kg/cm2 PARA COLUMAS m3 3.41 305.86 1,042.98 3.41 1,042.98 3.41 1,042.98 100.00% 0.00
01.01.04.02.02 ENCOFRADO Y DESENCOFRADO NOMAL EN COLUMNAS m2 49.11 45.92 2,255.13 49.11 2,255.13 49.11 2,255.13 100.00% 0.00
01.01.04.02.03 ACERO FÝ=4200 KG/CM2 PARA COLUMNAS kg 478.02 3.41 1,630.05 478.02 1,630.05 0.00 478.02 1,630.05 100.00% 0.00
01.01.04.03 VIGAS
01.01.04.03.01 CONCRETO f´c=210kg/cm2 PARA VIGAS m3 0.23 267.17 61.45 0.23 61.45 0.00 0.23 61.45 100.00% 0.00
01.01.04.03.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS m2 2.78 47.87 133.08 2.78 133.08 0.00 2.78 133.08 100.00% 0.00
01.01.04.03.03 ACERO FÝ=4200 KG/CM2 PARA VIGAS kg 41.58 3.37 140.12 41.58 140.12 0.00 41.58 140.12 100.00% 0.00
01.01.04.04 ESCALERA DE CONCRETO ARMADO
01.01.04.04.01 CONCRETO f´c=210kg/cm2 PARA ESCALERAS m3 5.92 305.13 1,806.37 5.92 1,806.37 0.00 5.92 1,806.37 100.00% 0.00
01.01.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESCALERAS m2 29.98 86.74 2,600.47 29.98 2,600.47 0.00 29.98 2,600.47 100.00% 0.00
01.01.04.04.03 ACERO FÝ=4200 KG/CM2 PARA ESCALERAS kg 303.60 3.40 1,032.24 303.60 1,032.24 0.00 303.60 1,032.24 100.00% 0.00
01.01.01.05 ESTRUCTURAS DE MADERA Y COBERTURA
01.01.01.05.01 TIJERALES DE MADERA TIPO 1, L=9.60m u 9.00 944.88 8,503.92 8.50 8,031.48 0.50 472.44 9.00 8,503.92 100.00% 0.00
01.01.01.05.02 CORREAS DE MADERA DE 2 x 3" m 468.00 6.83 3,196.44 100.00 683.00 368.00 2,513.44 468.00 3,196.44 100.00% 0.00
01.01.01.05.03 FRISOS DE MADERA DE 1 x 10" m 87.90 9.29 816.59 22.00 204.38 0.00 0.00 22.00 204.38 25.00% 65.90
01.01.01.05.04 COBERTURA DE FIBRAFORTE TIPO TEJA ANDINA m2 393.90 23.53 9,268.47 0.00 0.00 354.51 8,341.62 354.51 8,341.62 90.00% 39.39
01.01.01.05.05 CUMBRERA PARA TEJA ANDINA m 39.00 20.25 789.75 0.00 0.00 35.10 710.78 35.10 710.78 90.00% 3.90
01.02 ARQUITECTURA "D"
01.02.01 MUROS Y TABIQUES
01.02.01.01 MURO DE CABEZA LADRILLO CORRIENTE CON CEMENTO - ARENA m2 20.36 64.30 1,309.15 20.36 1,309.15 0.00 20.36 1,309.15 100.00% 0.00
01.02.02 REVOQUES ENLUCIDOS Y MOLDURAS
01.02.02.01 TARRAJEO PRIMARIO RAYADO CON CEMENTO - ARENA 1:5 E=1.5CM m2 81.00 13.24 1,072.44 81.00 1,072.44 0.00 81.00 1,072.44 100.00% 0.00
01.02.02.02 TARRAJEO EN INTERIORES ACABADO CON CEMENTO - ARENA 1:5 m2 705.56 10.71 7,556.55 634.59 6,796.46 35.69 382.24 670.28 7,178.70 95.00% 35.28
01.02.02.03 TARRAJEO EN EXTERIORES CON CEMENTO ARENA 1:5 m2 290.70 19.63 5,706.44 261.00 5,123.43 15.16 297.59 276.16 5,421.02 95.00% 14.54
01.02.02.04 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO - ARENA 1:5 m2 32.82 22.45 736.81 32.00 718.40 0.00 0.00 32.00 718.40 98.00% 0.82
01.02.02.05 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO - ARENA 1:5 m2 155.09 28.68 4,447.98 145.00 4,158.60 2.34 67.11 147.34 4,225.71 95.00% 7.75
01.02.02.06 VESTIDURAS DE DERRAMES ANCHO = 15cm, E=1.5cm, MEZCLA 1:5 m 220.52 12.71 2,802.81 193.92 2,464.72 15.57 197.89 209.49 2,662.61 95.00% 11.03
01.02.02.07 VESTIDURA DE FONDO ESCALERA CON CEMENTO - ARENA m2 20.33 23.58 479.38 18.00 424.44 2.33 54.94 20.33 479.38 100.00% 0.00
01.02.02.08 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS m 43.70 20.23 884.05 0.00 0.00 0.00 0.00 0.00 0.00% 43.70
01.02.02.09 DESCANSO DE ESCALERA, ACABADO CON CEMENTO PULIDO m2 4.76 17.40 82.82 0.00 0.00 0.00 0.00 0.00 0.00% 4.76
01.02.03 CIELORRASOS
01.02.03.01 CIELORRASOS CON MEZCLA DE CEMENTO - ARENA MEZCLA 1:5 m2 252.70 33.63 8,498.30 225.81 7,593.99 14.25 479.23 240.06 8,073.22 95.00% 12.64

01.02.03.02 CIELORRASOS CON TRIPLEY DE 4MM C/ENTRAMADO DE MADERA MAS TAPAJUNTA m2 255.96 34.84 8,917.65 0.00 0.00 0.00 0.00 0.00 0.00% 255.96

01.02.04 PISOS Y PAVIMENTOS


01.02.04.01 CONTRAPISO DE 25 mm m2 470.16 15.22 7,155.84 470.16 7,155.84 0.00 0.00 470.16 7,155.84 100.00% 0.00
01.02.04.02 PISO CERAMICO DE 30 X 30 CM m2 424.66 32.68 13,877.89 0.00 0.00 0.00 0.00 0.00 0.00% 424.66
01.02.04.03 PISO CERAMICO DE 30 X 30 CM ANTIDESLIZANTE m2 45.50 32.68 1,486.94 45.50 1,486.94 0.00 0.00 45.50 1,486.94 100.00% 0.00
01.02.04.04 PISO DE CONCRETO ACBADO PULIDO 1:2 X 1cm m2 27.78 12.91 358.64 0.00 0.00 27.78 358.64 27.78 358.64 100.00% 0.00
01.02.05 CONTRAZOCALOS
01.02.05.01 CONTRAZOCALO EN INTERIORES DE CERAMICO H=10CM m 232.84 7.57 1,762.60 0.00 0.00 0.00 0.00 0.00 0.00% 232.84

01.02.05.02 CONTRAZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2cm H=30cm m 31.20 5.96 185.95 9.00 53.64 22.20 132.31 31.20 185.95 100.00% 0.00

01.02.06 ZOCALOS
01.02.06.01 ZOCALO DE CERAMICA BLANCA DE 20 X 30 cm DE 1RA m2 81.00 33.65 2,725.65 73.00 2,456.45 8.00 269.20 81.00 2,725.65 100.00% 0.00
01.02.06.02 ZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2 cm H=60cm m 45.33 17.65 800.07 0.00 0.00 45.33 800.07 45.33 800.07 100.00% 0.00
01.02.07 CARPINTERIA DE MADERA
01.02.07.01 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5mm DE TORNILLO m2 23.40 160.00 3,744.00 0.00 0.00 0.00 0.00 0.00 0.00% 23.40
01.02.08 CARPINTERIA METALICA
01.02.08.01 PUERTA METALICA LAC 1/16" CON MARCO 2" X 2" X 1/4" Y REFUERZOS m2 7.02 504.08 3,538.64 0.00 0.00 0.00 0.00 0.00 0.00% 7.02
01.02.08.02 VENTANA DE FIERRO PERFIL DE 1" X 1/8" FIJA MARCO "T" DE 1" m2 103.41 99.15 10,253.10 0.00 0.00 51.70 5,126.06 51.70 5,126.06 50.00% 51.71
01.02.08.03 BARANDA METALICA DE TUBO m 13.60 36.11 491.10 0.00 0.00 0.00 0.00 0.00 0.00% 13.60
01.02.08.04 TABIQUERIA METALICA PARA SS.HH. (SEGÚN DISEÑO) m2 12.33 409.70 5,051.60 0.00 0.00 7.40 3,030.96 7.40 3,030.96 60.00% 4.93
01.02.09 CERRAJERIA
01.02.09.01 CERRADURAS
01.02.09.01.01 CERRADURA FORTE DE 3 GOLPES u 10.00 77.28 772.80 0.00 0.00 0.00 0.00 0.00 0.00% 10.00
CERRADURA PUERTA BAÑO SEGURO INTERNO PERILLA MANIJA CERRADURA GOAL 42 NP
01.02.09.01.02 BAÑO pza 2.00 63.75 127.50 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

01.02.09.01.03 CERROJO DE FIERRO REDONDO DE 1/2" X 0.35m u 6.00 23.63 141.78 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
01.02.10 VIDRIOS, CRISTALES Y SIMILARES
01.02.10.01 VIDRIOS DOBLES NACIONALES p2 1,112.71 3.69 4,105.90 0.00 0.00 0.00 0.00 0.00 0.00% 1,112.71
01.02.11 PINTURA
01.02.11.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS m2 705.56 4.53 3,196.19 70.00 317.10 176.00 797.28 246.00 1,114.38 35.00% 459.56
01.02.11.02 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS m2 290.70 5.47 1,590.13 29.00 158.63 73.00 399.31 102.00 557.94 35.00% 188.70
01.02.11.03 PINTURA LATEX EN SUPERFICIES DE COLUMNAS 2 MANOS m2 32.82 5.17 169.68 3.00 15.51 8.00 41.36 11.00 56.87 34.00% 21.82
01.02.11.04 PINTURA LATEX EN SUPERFICIES DE VIGAS m2 155.09 5.43 842.14 15.00 81.45 39.00 211.77 54.00 293.22 35.00% 101.09
01.02.11.05 PINTURA LATEX EN DERRAMES, 2 MANOS m2 33.08 3.29 108.83 0.00 0.00 0.00 0.00 0.00 0.00% 33.08
01.02.11.06 PINTURA LATEX EN CIELORRASO 2 MANOS m2 273.03 4.71 1,285.97 0.00 0.00 0.00 0.00 0.00 0.00% 273.03

01.02.11.07 PINTIURA EN CARPINTERIA DE METALICA CON ANTICORROSIVO Y ESMALTE m2 128.67 7.56 972.75 0.00 0.00 0.00 0.00 0.00 0.00% 128.67

01.02.11.08 PINTURA ESMALTE EN ZOCALOS m 45.33 4.10 185.85 0.00 0.00 0.00 0.00 0.00 0.00% 45.33
01.02.12 APARATOS Y ACCESORIOS SANITARIOS
01.02.12.01 INODORO C/BLANCO TANQUE BAJO u 6.00 75.63 453.78 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
01.02.12.02 LAVATORIO DE PARED BLANCO 1 LLAVE pza 2.00 75.36 150.72 0.00 0.00 2.00 150.72 2.00 150.72 100.00% 0.00
01.02.12.03 URINARIO CORRIDO DE CONCRETO HECHO EN OBRA m 2.00 294.43 588.86 0.00 0.00 2.00 588.86 2.00 588.86 100.00% 0.00
01.02.12.04 PAPELRA DE LOZA BLANCA DE 13 X 15cm pza 6.00 25.21 151.26 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
01.02.13 OTROS
01.02.13.01 LIMPIEZA FINAL m2 290.55 0.36 104.60 217.91 78.45 0.00 0.00 217.91 78.45 75.00% 72.64
01.03 INSTALACIONES SANITARIAS "D"
01.03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.03.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" pto 6.00 55.86 335.16 6.00 335.16 0.00 6.00 335.16 100.00% 0.00
01.03.01.02 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m 30.00 7.97 239.10 30.00 239.10 0.00 30.00 239.10 100.00% 0.00
01.03.01.03 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP m 30.00 8.28 248.40 0.00 0.00 0.00 0.00 0.00 0.00% 30.00
01.03.01.04 CODO PVC SAP 1/2" X 90" u 20.00 8.51 170.20 20.00 170.20 0.00 20.00 170.20 100.00% 0.00
01.03.01.05 TEE PVC-SAP 1/2" u 18.00 10.34 186.12 18.00 186.12 0.00 18.00 186.12 100.00% 0.00
01.03.01.06 VALVULA COMPUERTA DE BRONCE 1/2" u 2.00 42.52 85.04 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.03.01.07 VALVULA COMPUERTA DE BRONCE 3/4" u 1.00 43.33 43.33 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.03.02 SISTEMA DE DESAGUE
01.03.02.01 SALIDA DE DESAGUE DE 2" pto 11.00 37.67 414.37 11.00 414.37 0.00 11.00 414.37 100.00% 0.00
01.03.02.02 SALIDA DE DESAGUE DE 4" pto 6.00 43.36 260.16 6.00 260.16 0.00 6.00 260.16 100.00% 0.00
01.03.02.03 SALIDA DE DESAGUE DE VENTILACION DE 2" pto 2.00 35.02 70.04 2.00 70.04 0.00 2.00 70.04 100.00% 0.00
01.03.02.04 TUBERIA DE PVC SAL 2" m 20.00 17.39 347.80 20.00 347.80 0.00 20.00 347.80 100.00% 0.00
01.03.02.05 EXCAVACION DE ZANJAS PARA TUBERIAS m3 25.00 8.65 216.25 25.00 216.25 0.00 25.00 216.25 100.00% 0.00
01.03.02.06 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 25.00 47.22 1,180.50 25.00 1,180.50 0.00 25.00 1,180.50 100.00% 0.00
01.03.02.07 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 25.00 35.39 884.75 25.00 884.75 0.00 25.00 884.75 100.00% 0.00
01.03.02.08 TUBERIA DE PVC SAL 4" m 25.00 18.55 463.75 25.00 463.75 0.00 25.00 463.75 100.00% 0.00
01.03.02.09 REGISTRO DE BRONCE DE 4" pza 6.00 45.75 274.50 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
01.03.02.10 SUMIDERO DE BRONCE DE 2" u 6.00 48.23 289.38 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
01.03.02.11 YEE PVC SAL 4" u 6.00 16.67 100.02 6.00 100.02 0.00 6.00 100.02 100.00% 0.00
01.03.02.12 YEE DE PVC SAL SP RAMAL CON REDUCCIONDE 4" - 2" u 4.00 12.05 48.20 4.00 48.20 0.00 4.00 48.20 100.00% 0.00
01.03.02.13 CODO PVC SAL 2" X 45" u 2.00 12.13 24.26 2.00 24.26 0.00 2.00 24.26 100.00% 0.00
01.03.02.14 CODO PVC SAL 2 X 90" u 7.00 11.92 83.44 7.00 83.44 0.00 7.00 83.44 100.00% 0.00
01.03.02.15 TEE PVC - SAL 4" 2" u 6.00 12.57 75.42 6.00 75.42 0.00 6.00 75.42 100.00% 0.00
01.03.02.16 CAJA DE REGISTRO DE DESAGUE 12" X 24" CON TAPA DE FºGº u 1.00 100.45 100.45 1.00 100.45 0.00 0.00 1.00 100.45 100.00% 0.00
01.03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS
01.03.03.01 COLOCACION DE APARATOS SANITARIOS pza 6.00 50.80 304.80 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
01.03.03.02 COLOCACION DE ACCESORIOS SANITARIOS pza 6.00 25.40 152.40 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
01.04 INSTALACIONES ELECTRICAS "D"
01.04.01 TUBERIA Y CANALIZACION
01.04.01.01 CANALIZACION PARA DUCTO EN PARED Y PISO m 293.40 2.70 792.18 252.65 682.16 26.08 70.42 278.73 752.58 95.00% 14.67
01.04.01.02 TUBERIA DE PVC SEL 20mm m 293.40 3.08 903.67 252.65 778.17 26.08 80.33 278.73 858.50 95.00% 14.67
01.04.01.03 TUBERIA DE PVC SEL 25mm m 8.00 34.45 275.60 7.00 241.15 0.00 0.00 7.00 241.15 88.00% 1.00
01.04.02 CAJAS DE PASE
01.04.02.01 CAJAS DE PASE de 4" x 4" x 2" u 2.00 27.65 55.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.04.03 CONDUCTORES
01.04.03.01 CONDUCTOR THW C/CABLE 1 x 6 mm2 m 10.00 2.59 25.90 0.00 0.00 0.00 0.00 0.00 0.00% 10.00
01.04.03.02 CONDUCTOR THW C/CABLE 1 x 2.5 mm2 m 372.50 1.49 555.03 0.00 0.00 0.00 0.00 0.00 0.00% 372.50
01.04.03.03 CONDUCTOR THW C/CABLE 1 x 4 mm3 m 369.30 1.98 731.21 0.00 0.00 0.00 0.00 0.00 0.00% 369.30
01.04.04 INSTALACION DE PLACAS
01.04.04.01 TOMACORRIENTES UNIVERSAL DOBLE PARA EMPOTRADO u 16.00 15.66 250.56 0.00 0.00 0.00 0.00 0.00 0.00% 16.00
01.04.04.02 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRAR A PRUEBA DE AGUA u 2.00 40.98 81.96 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

01.04.04.03 TOMACORRIENTE UNIVERSAL SIMPLE PARA EMPOTRADO u 16.00 31.46 503.36 0.00 0.00 0.00 0.00 0.00 0.00% 16.00
01.04.04.04 INTERRUPTORES SIMPLE PARA EMPOTRADO u 7.00 17.10 119.70 0.00 0.00 0.00 0.00 0.00 0.00% 7.00
01.04.04.05 INTERRUPTORES DOBLE PARA EMPOTRADO u 4.00 17.27 69.08 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
01.04.04.06 INTERRUPTORES DE CONMUTACION SIMPLE u 2.00 17.03 34.06 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.04.04.07 INTERRUPTORES TRIPLES PARA EMPOTRADO u 1.00 30.20 30.20 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.04.05 INSTALACION DE ARTEFACTOS

01.04.05.01 EQUIPO FLUORESCENTE DOBLE DE 2 x 36 W CON PANTALLA ACRILICO REJILLA u 33.00 54.07 1,784.31 0.00 0.00 0.00 0.00 0.00% 33.00

01.04.05.02 LUMINARIA TIPO SPOT LINGH ADOSABLE INC. FOCO AHORRADOR u 3.00 43.37 130.11 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
01.04.06 TABLEROS
01.04.06.01 TABLERO GENERAL 12 POLOS u 1.00 93.78 93.78 0.00 0.00 0.50 46.89 0.50 46.89 50.00% 0.50
01.04.06.02 TABLERO DE DISTRIBUCION 12 POLOS u 2.00 93.98 187.96 0.00 0.00 1.00 93.98 1.00 93.98 50.00% 1.00
01.04.07 LLAVES TERMOMAGNETICAS
01.04.07.01 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 15A pza 4.00 37.15 148.60 0.00 0.00 4.00 148.60 4.00 148.60 100.00% 0.00
01.04.07.02 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 20A pza 4.00 37.15 148.60 0.00 0.00 4.00 148.60 4.00 148.60 100.00% 0.00
01.04.07.03 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 30A pza 2.00 37.15 74.30 0.00 0.00 2.00 74.30 2.00 74.30 100.00% 0.00
01.04.07.04 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3 X 30A pza 2.00 57.09 114.18 0.00 0.00 2.00 114.18 2.00 114.18 100.00% 0.00
01.04.07.05 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3 X 60A pza 1.00 78.10 78.10 0.00 0.00 1.00 78.10 1.00 78.10 100.00% 0.00
02 PABELLON "E"
02.01 ESTRUCTURAS "E"
02.01.01 OBRAS PRELIMINARES
02.01.01.01 DEMOLICION DE PISOS DE CONCRETO DE 0.10m m2 323.62 6.00 1,941.72 323.62 1,941.72 0.00 323.62 1,941.72 100.00% 0.00
02.01.01.02 DEMOLICION DE MUROS DE LADRILLO m3 12.54 5.28 66.21 12.54 66.21 12.54 66.21 100.00% 0.00
02.01.01.03 DEMOLICION DE COLUMNETAS DE CONCRETO m3 0.43 53.87 23.16 0.43 23.16 0.00 0.43 23.16 100.00% 0.00
02.01.01.04 DEMOLICION DE LOSA ALIGERADA m3 3.60 54.80 197.28 3.60 197.28 0.00 3.60 197.28 100.00% 0.00
02.01.01.05 DEMOLICION DE ESCALERA DE CONCRETO m3 5.54 24.14 133.74 5.54 133.74 0.00 5.54 133.74 100.00% 0.00
02.01.01.06 DESMONTAJE DE COBERTURA DE CALAMINA m2 394.20 3.65 1,438.83 394.20 1,438.83 0.00 394.20 1,438.83 100.00% 0.00
02.01.01.07 RETIRO DE TIJERALES DE MADERA u 13.00 55.23 717.99 13.00 717.99 0.00 13.00 717.99 100.00% 0.00
02.01.01.08 RETIRO DE PUERTAS Y VENTANAS m2 75.28 3.20 240.90 75.28 240.90 0.00 75.28 240.90 100.00% 0.00
02.01.01.09 ACARREO MATERIAL PROVENIENTE DE DEMOLICION D=50M m3 68.09 12.36 841.59 68.09 841.59 68.09 841.59 100.00% 0.00
02.01.01.10 ELIMINACION DE DEMOLICIONES m3 68.09 9.95 677.50 68.09 677.50 68.09 677.50 100.00% 0.00
02.01.02 MOVIMIENTOS DE TIERRAS
02.01.02.01 EXCAVACION PARA ZAPATAS EN TERRENO NORMAL m3 19.40 24.24 470.26 19.40 470.26 19.40 470.26 100.00% 0.00
02.01.02.02 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 3.75 21.63 81.11 3.75 81.11 3.75 81.11 100.00% 0.00
02.01.02.03 RELLENO CON MATERIAL PROPIO m3 10.42 42.66 444.52 10.42 444.52 10.42 444.52 100.00% 0.00
02.01.02.04 ACRREO MATERIAL EXCEDENTE D=50M m3 13.56 12.36 167.60 13.56 167.60 13.56 167.60 100.00% 0.00
02.01.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO m3 13.56 9.58 129.90 13.56 129.90 13.56 129.90 100.00% 0.00
02.01.02.06 AFIRMADO E=4" PARA VEREDAS m2 79.08 5.92 468.15 0.00 0.00 79.08 468.15 79.08 468.15 100.00% 0.00

02.01.02.07 NIVELACION, RELLENO Y COMPACTACION CON MATERIAL DE PRESTAMO m2 275.04 7.43 2,043.55 207.65 1,542.84 67.39 500.71 275.04 2,043.55 100.00% 0.00

02.01.03 CONCRETO SIMPLE


02.01.03.01 CONCRETO 1:10 + 30% P.G. PARA CIMIENTOS CORRIDOS m3 2.33 150.25 350.08 2.33 350.08 2.33 350.08 100.00% 0.00
02.01.03.02 CONCRETO 1:8 + 25% PM PARA SOBRECIMIENTOS m3 0.47 228.31 107.31 0.47 107.31 0.47 107.31 100.00% 0.00
02.01.03.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 3.11 21.46 66.74 3.11 66.74 3.11 66.74 100.00% 0.00
02.01.03.04 SOLADOS PARA ZAPATAS E=4" m2 11.76 17.30 203.45 11.76 203.45 11.76 203.45 100.00% 0.00
02.01.03.05 FALSO PISO DE 4" DE CONCRETO 1:10 m2 275.04 15.60 4,290.62 275.04 4,290.62 275.04 4,290.62 100.00% 0.00
02.01.03.06 VEREDA F´C =175 KG/CM2 DE CONCRETO DE 4" m2 88.48 30.76 2,721.64 0.00 0.00 0.00 0.00 0.00 0.00% 88.48
02.01.03.07 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 12.12 29.44 356.81 0.00 0.00 0.00 0.00 0.00 0.00% 12.12
02.01.03.08 JUNTAS ASFALTICAS EN VEREDAS m 27.20 5.15 140.08 0.00 0.00 0.00 0.00 0.00 0.00% 27.20
02.01.04 CONCRETO ARMADO
02.01.04.01 ZAPATAS
02.01.04.01.01 CONCRETO f´c=210kg/cm2 PARA ZAPATAS M3 7.64 253.19 1,934.37 7.64 1,934.37 0.00 7.64 1,934.37 100.00% 0.00
02.01.04.01.02 ACERO FÝ=4200 KG/CM2 GRADO 60 EN ZAPATAS kg 119.83 3.41 408.62 119.83 408.62 0.00 119.83 408.62 100.00% 0.00
02.01.04.02 COLUMNAS
02.01.04.02.01 CONCRETO f´c=210kg/cm2 PARA COLUMAS m3 5.41 305.86 1,654.70 5.41 1,654.70 0.00 5.41 1,654.70 100.00% 0.00
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 76.40 45.92 3,508.29 76.40 3,508.29 0.00 76.40 3,508.29 100.00% 0.00
02.01.04.02.03 ACERO FÝ=4200 KG/CM2 PARA COLUMNAS kg 679.63 3.41 2,317.54 679.63 2,317.54 0.00 679.63 2,317.54 100.00% 0.00
02.01.04.03 VIGAS
02.01.04.03.01 CONCRETO f´c=210kg/cm2 PARA VIGAS m3 0.60 267.17 160.30 0.60 160.30 0.00 0.60 160.30 100.00% 0.00
02.01.04.03.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS m2 7.20 47.87 344.66 7.20 344.66 0.00 7.20 344.66 100.00% 0.00
02.01.04.03.03 ACERO FÝ=4200 KG/CM2 PARA VIGAS kg 104.36 3.37 351.69 104.36 351.69 0.00 104.36 351.69 100.00% 0.00
02.01.04.04 ESCALERA DE CONCRETO ARMADO
02.01.04.04.01 CONCRETO f´c=210kg/cm2 PARA ESCALERAS m3 10.88 305.13 3,319.81 10.88 3,319.81 0.00 10.88 3,319.81 100.00% 0.00
02.01.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESCALERAS m2 55.27 86.74 4,794.12 55.27 4,794.12 0.00 55.27 4,794.12 100.00% 0.00
02.01.04.04.03 ACERO FÝ=4200 KG/CM2 PARA ESCALERAS kg 758.94 3.40 2,580.40 758.94 2,580.40 0.00 758.94 2,580.40 100.00% 0.00
02.01.05 ESTRUCTURAS DE MADERA Y COBERTURA
02.01.05.01 TIJERALES DE MADERA TIPO 1, L=8.60m u 13.00 762.65 9,914.45 11.00 8,389.15 2.00 1,525.30 13.00 9,914.45 100.00% 0.00
02.01.05.02 CORREAS DE MADERA DE 2 x 3" m 506.20 6.83 3,457.35 150.00 1,024.50 356.20 2,432.85 506.20 3,457.35 100.00% 0.00
02.01.05.03 FRISOS DE MADERA DE 1 x 10" m 98.60 9.29 915.99 30.00 278.70 0.00 0.00 30.00 278.70 30.00% 68.60
02.01.05.04 COBERTURA DE FIBRAFORTE TIPO TEJA ANDINA m2 460.00 23.53 10,823.80 0.00 0.00 460.00 10,823.80 460.00 10,823.80 100.00% 0.00
02.01.05.05 CUMBRERA PARA TEJA ANDINA m 50.00 20.25 1,012.50 0.00 0.00 50.00 1,012.50 50.00 1,012.50 100.00% 0.00
02.02 ARQUITECTURA "E"
02.02.01 MUROS Y TABIQUES
02.02.01.01 MURO DE CABEZA LADRILLO CORRIENTE CON CEMENTO - ARENA m2 29.91 64.30 1,923.21 29.91 1,923.21 0.00 29.91 1,923.21 100.00% 0.00
02.02.02 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.02.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO - ARENA 1:5 m2 995.25 10.71 10,659.13 889.54 9,526.97 55.95 599.22 945.49 10,126.19 95.00% 49.76
02.02.02.02 TARRAJEO EN EXTERIORES CON CEMENTO ARENA 1:5 m2 439.39 19.63 8,625.23 389.54 7,646.67 27.88 547.28 417.42 8,193.95 95.00% 21.97
02.02.02.03 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO - ARENA 1:5 m2 112.47 22.45 2,524.95 102.10 2,292.15 4.75 106.64 106.85 2,398.79 95.00% 5.62
02.02.02.04 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO - ARENA 1:5 m2 207.80 28.68 5,959.70 181.92 5,217.47 15.49 444.25 197.41 5,661.72 95.00% 10.39
02.02.02.05 VESTIDURAS DE DERRAMES ANCHO = 15cm, E=1.5cm, MEZCLA 1:5 m 356.20 12.71 4,527.30 160.60 2,041.22 177.79 2,259.71 338.39 4,300.93 95.00% 17.81
02.02.02.06 VESTIDURA DE FONDO ESCALERA CON CEMENTO - ARENA m2 35.57 23.58 838.74 0.00 0.00 0.00 0.00 0.00 0.00% 35.57
02.02.02.07 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS m 78.60 20.23 1,590.08 0.00 0.00 0.00 0.00 0.00 0.00% 78.60
02.02.02.08 DESCANSO DE ESCALERA, ACABADO CON CEMENTO PULIDO m2 9.65 17.40 167.91 0.00 0.00 0.00 0.00 0.00 0.00% 9.65
02.02.03 CIELORRASOS
02.02.03.01 CIELORRASOS CON MEZCLA DE CEMENTO - ARENA MEZCLA 1:5 m2 266.45 33.63 8,960.71 72.50 2,438.18 180.63 6,074.59 253.13 8,512.77 95.00% 13.32

02.02.03.02 CIELORRASOS CON TRIPLEY DE 4MM C/ENTRAMADO DE MADERA MAS TAPAJUNTA m2 379.96 34.84 13,237.81 0.00 0.00 0.00 0.00 0.00 0.00% 379.96

02.02.04 PISOS Y PAVIMENTOS


02.02.04.01 CONTRAPISO DE 25 mm m2 422.54 15.22 6,431.06 422.54 6,431.06 0.00 0.00 422.54 6,431.06 100.00% 0.00
02.02.04.02 PISO CERAMICO DE 30 X 30 CM m2 422.54 32.68 13,808.61 0.00 0.00 0.00 0.00 0.00 0.00% 422.54
02.02.04.03 PISO DE CONCRETO ACBADO PULIDO 1:2 X 1cm m2 125.89 12.91 1,625.24 0.00 0.00 125.89 1,625.24 125.89 1,625.24 100.00% 0.00
02.02.05 CONTRAZOCALOS
02.02.05.01 CONTRAZOCALO EN INTERIORES DE CERAMICO H=10CM m 268.26 7.57 2,030.73 0.00 0.00 0.00 0.00 0.00 0.00% 268.26

02.02.05.02 CONTRAZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2cm H=30cm m 91.10 5.96 542.96 0.00 0.00 77.50 461.90 77.50 461.90 85.00% 13.60

02.02.06 ZOCALOS
02.02.06.01 ZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2 cm H=60cm m 52.71 17.65 930.33 15.81 279.10 15.81 279.05 31.62 558.15 60.00% 21.09
02.02.07 CARPINTERIA DE MADERA
02.02.07.01 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5mm DE TORNILLO m2 31.16 160.00 4,985.60 0.00 0.00 0.00 0.00 0.00 0.00% 31.16
02.02.08 CARPINTERIA METALICA
02.02.08.01 VENTANA DE FIERRO PERFIL DE 1" X 1/8" FIJA MARCO "T" DE 1" m2 132.00 99.15 13,087.80 0.00 0.00 0.00 0.00 0.00 0.00% 132.00
02.02.08.02 BARANDA METALICA DE TUBO m 39.90 36.11 1,440.79 0.00 0.00 0.00 0.00 0.00 0.00% 39.90
02.02.09 CERRADURAS
02.02.09.01 CERRADURA FORTE DE 3 GOLPES u 10.00 77.28 772.80 0.00 0.00 0.00 0.00 0.00 0.00% 10.00
CERRADURA PUERTA BAÑO SEGURO INTERNO PERILLA MANIJA CERRADURA GOAL 42 NP
02.02.09.02 BAÑO pza 1.00 63.75 63.75 0.00 0.00 0.00 0.00 0.00% 1.00

02.02.10 VIDRIOS, CRISTALES Y SIMILARES


02.02.10.01 VIDRIOS DOBLES NACIONALES p2 1,420.32 3.69 5,240.98 0.00 0.00 0.00 0.00 0.00 0.00% 1,420.32
02.02.11 PINTURA
02.02.11.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS m2 995.25 4.53 4,508.48 99.00 448.47 299.10 1,354.92 398.10 1,803.39 40.00% 597.15
02.02.11.02 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS m2 439.39 5.47 2,403.46 43.00 235.21 132.75 726.14 175.75 961.35 40.00% 263.64
02.02.11.03 PINTURA LATEX EN SUPERFICIES DE COLUMNAS 2 MANOS m2 112.47 5.17 581.47 11.00 56.87 33.98 175.68 44.98 232.55 40.00% 67.49
02.02.11.04 PINTURA LATEX EN SUPERFICIES DE VIGAS m2 207.80 5.43 1,128.35 20.00 108.60 63.12 342.74 83.12 451.34 40.00% 124.68
02.02.11.05 PINTURA LATEX EN DERRAMES, 2 MANOS m2 53.43 3.29 175.78 0.00 0.00 0.00 0.00 0.00 0.00% 53.43
02.02.11.06 PINTURA LATEX EN CIELORRASO 2 MANOS m2 302.01 4.71 1,422.47 0.00 0.00 0.00 0.00 0.00 0.00% 302.01

02.02.11.07 PINTIURA EN CARPINTERIA DE METALICA CON ANTICORROSIVO Y ESMALTE m2 167.91 7.56 1,269.40 0.00 0.00 0.00 0.00 0.00 0.00% 167.91

02.02.11.08 PINTURA ESMALTE EN ZOCALOS m 52.71 4.10 216.11 0.00 0.00 0.00 0.00 0.00 0.00% 52.71
02.02.12 APARATOS Y ACCESORIOS SANITARIOS
02.02.12.01 LAVADERO DE COCINA DE ACERO INOXIDABLE pza 1.00 70.00 70.00 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.02.13 OTROS
02.02.13.01 LIMPIEZA FINAL m2 303.03 0.36 109.09 0.00 0.00 227.00 81.72 227.00 81.72 75.00% 76.03
02.03 INSTALACIONES SANITARIAS "E"
02.03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
02.03.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" pto 2.00 55.86 111.72 0.00 0.00 1.00 55.86 1.00 55.86 50.00% 1.00
02.03.01.02 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m 6.00 7.97 47.82 0.00 0.00 3.00 23.91 3.00 23.91 50.00% 3.00
02.03.01.03 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP m 20.00 8.28 165.60 0.00 0.00 20.00 165.60 20.00 165.60 100.00% 0.00
02.03.01.04 CODO PVC SAP 1/2" X 90" u 5.00 8.51 42.55 0.00 0.00 2.00 17.02 2.00 17.02 40.00% 3.00
02.03.01.05 TEE PVC-SAP 1/2" u 1.00 10.34 10.34 0.00 0.00 1.00 10.34 1.00 10.34 100.00% 0.00
02.03.01.06 VALVULA COMPUERTA DE BRONCE 1/2" u 1.00 42.52 42.52 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.01.07 VALVULA COMPUERTA DE BRONCE 3/4" u 1.00 43.33 43.33 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.02 SISTEMA DE DESAGUE
02.03.02.01 SALIDA DE DESAGUE DE 2" pto 3.00 37.67 113.01 0.00 0.00 2.00 75.34 2.00 75.34 67.00% 1.00
02.03.02.02 SALIDA DE DESAGUE DE VENTILACION DE 2" pto 1.00 35.02 35.02 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.02.03 EXCAVACION DE ZANJAS PARA TUBERIAS m3 20.00 8.65 173.00 0.00 0.00 10.00 86.50 10.00 86.50 50.00% 10.00
02.03.02.04 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 20.00 47.22 944.40 0.00 0.00 10.00 472.20 10.00 472.20 50.00% 10.00
02.03.02.05 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 20.00 35.39 707.80 0.00 0.00 10.00 353.90 10.00 353.90 50.00% 10.00
02.03.02.06 TUBERIA DE PVC SAL 2" m 20.00 17.39 347.80 0.00 0.00 10.00 173.90 10.00 173.90 50.00% 10.00
02.03.02.07 REGISTRO DE BRONCE DE 2" u 3.00 38.05 114.15 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
02.03.02.08 SUMIDERO DE BRONCE DE 2" u 2.00 48.23 96.46 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02.03.02.09 CODO PVC SAL 2" X 45" u 3.00 12.13 36.39 0.00 0.00 1.00 12.13 1.00 12.13 33.00% 2.00
02.03.02.10 CODO PVC SAL 2 X 90" u 14.00 11.92 166.88 0.00 0.00 5.00 59.60 5.00 59.60 36.00% 9.00
02.03.02.11 CAJA DE REGISTRO DE DESAGUE 12" X 24" CON TAPA DE FºGº u 1.00 100.45 100.45 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.03 COLOCACION DE APARATOS SANITARIOS
02.03.03.01 COLOCACION DE APARATOS SANITARIOS pza 1.00 50.80 50.80 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.04 INSTALACIONES ELECTRICAS "E"
02.04.01 TUBERIA Y CANALIZACION
02.04.01.01 CANALIZACION PARA DUCTO EN PARED Y PISO m 335.41 2.70 905.61 289.91 782.76 28.73 77.57 318.64 860.33 95.00% 16.77
02.04.01.02 TUBERIA DE PVC SEL 20mm m 335.43 3.08 1,033.12 289.91 892.92 28.75 88.55 318.66 981.47 95.00% 16.77
02.04.01.03 TUBERIA DE PVC SEL 25mm m 8.00 34.45 275.60 6.90 237.71 0.00 0.00 6.90 237.71 86.00% 1.10
02.04.02 CAJAS DE PASE
02.04.02.01 CAJAS DE PASE de 4" x 4" x 2" u 2.00 27.65 55.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02.04.03 CONDUCTORES
02.04.03.01 CONDUCTOR THW C/CABLE 1 x 6 mm2 m 16.00 2.59 41.44 0.00 0.00 0.00 0.00 0.00 0.00% 16.00
02.04.03.02 CONDUCTOR THW C/CABLE 1 x 2.5 mm2 m 445.17 1.49 663.30 0.00 0.00 0.00 0.00 0.00 0.00% 445.17
02.04.03.03 CONDUCTOR THW C/CABLE 1 x 4 mm3 m 438.66 1.98 868.55 0.00 0.00 0.00 0.00 0.00 0.00% 438.66
02.04.04 INSTALACION DE PLACAS
02.04.04.01 TOMACORRIENTES UNIVERSAL DOBLE PARA EMPOTRADO u 31.00 15.66 485.46 0.00 0.00 0.00 0.00 0.00 0.00% 31.00

02.04.04.02 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRAR A PRUEBA DE AGUA u 1.00 40.98 40.98 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.04.04.03 TOMACORRIENTE UNIVERSAL SIMPLE PARA EMPOTRADO u 8.00 31.46 251.68 0.00 0.00 0.00 0.00 0.00 0.00% 8.00
02.04.04.04 INTERRUPTORES SIMPLE PARA EMPOTRADO u 7.00 17.10 119.70 0.00 0.00 0.00 0.00 0.00 0.00% 7.00
02.04.04.05 INTERRUPTORES DOBLE PARA EMPOTRADO u 7.00 17.27 120.89 0.00 0.00 0.00 0.00 0.00 0.00% 7.00
02.04.04.06 INTERRUPTORES DE CONMUTACION SIMPLE u 1.00 17.03 17.03 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.04.04.07 INTERRUPTORES TRIPLES PARA EMPOTRADO u 1.00 30.20 30.20 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.04.05 INSTALACION DE ARTEFACTOS

02.04.05.01 EQUIPO FLUORESCENTE DOBLE DE 2 x 36 W CON PANTALLA ACRILICO REJILLA u 33.00 54.07 1,784.31 0.00 0.00 0.00 0.00 0.00 0.00% 33.00

02.04.05.02 LUMINARIA TIPO SPOT LINGH ADOSABLE INC. FOCO AHORRADOR u 4.00 43.37 173.48 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
02.04.06 TABLEROS
02.04.06.01 TABLERO GENERAL 12 POLOS u 1.00 93.78 93.78 0.00 0.00 0.50 46.89 0.50 46.89 50.00% 0.50
02.04.06.02 TABLERO DE DISTRIBUCION 12 POLOS u 2.00 93.98 187.96 0.00 0.00 1.00 93.98 1.00 93.98 50.00% 1.00
02.04.07 LLAVES TERMOMAGNETICAS
02.04.07.01 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 15A pza 4.00 37.15 148.60 0.00 0.00 4.00 148.60 4.00 148.60 100.00% 0.00
02.04.07.02 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 20A pza 4.00 37.15 148.60 0.00 0.00 4.00 148.60 4.00 148.60 100.00% 0.00
02.04.07.03 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 30A pza 2.00 37.15 74.30 0.00 0.00 2.00 74.30 2.00 74.30 100.00% 0.00
02.04.07.04 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3 X 30A pza 2.00 57.09 114.18 0.00 0.00 2.00 114.18 2.00 114.18 100.00% 0.00
02.04.07.05 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3 X 60A pza 1.00 78.10 78.10 0.00 0.00 1.00 78.10 1.00 78.10 100.00% 0.00

COSTO DIRECTO 372,439.23 168,740.73 61,819.88 230,560.61


GASTOS GENERALES % 8.00 29,795.14 13,499.26 4,945.59 18,444.85
UTILIDAD % 5.00 18,621.96 8,437.04 3,090.99 11,528.03
SUBTOTAL 420,856.33 190,677.03 69,856.46 260,533.49
FACTOR DE RELACION 1.0000
SUBTOTAL - con Factor de Relacion 420,856.33 190,677.02 69,856.46 260,533.49

VALORIZACION DE OBRA Nº 04
(Periodo : Del 01 Mayo al 31 Mayo 2011)

Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVODE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A Valor Referencial (S/.) : 4,572,084.75 con IGV
Plazo de Ejecucion : 240 Dias Calendarios Costos al : February-2010
Supervisor : ING. ANTONIO VALENZUELA SALAS Monto del Contrato (S/.) : 4,572,084.75 con IGV
Residente : ING. PABLO SARMIENTO REYES Factor de Relacion : 1.000

Formula : 004 - PABELLON F Y H


AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
PRECIO
UNIDAD METRADO UNITARIO PARCIAL Metrado Monto Metrado Monto Metrado Monto % Metrado

01 PABELLON F
01.01 ESTRUCTURAS F
01.01.01 OBRAS PRELIMINARES
01.01.01.01 DEMOLICION DE VEREDAS DE CONCRETO DE 0.10M M2 17.66 6.00 105.96 17.66 105.96 0.00 17.66 105.96 100.00% 0.00
01.01.01.02 DEMOLICION DE MUROS DE LADRILLO M3 11.75 5.28 62.04 11.75 62.04 0.00 11.75 62.04 100.00% 0.00
01.01.01.03 RETIRO DE PUERTAS Y VENTANAS M2 16.17 3.20 51.74 16.17 51.74 0.00 16.17 51.74 100.00% 0.00
01.01.01.04 ACARREO DE MATERIAL PROVENIENTE DE DEMOLICIONES D=50M M3 16.89 12.36 208.76 16.89 208.76 0.00 16.89 208.76 100.00% 0.00
01.01.01.05 ELIMINACION DE DEMOLICIONES CON EQUIPO M3 16.89 9.95 168.06 16.89 168.06 0.00 16.89 168.06 100.00% 0.00
01.01.01.06 TRAZO Y REPLANTEO INICIAL M2 261.81 0.37 96.87 261.81 96.87 0.00 261.81 96.87 100.00% 0.00
01.01.02 MOVIMIENTO DE TIERRAS
01.01.02.01 EXCAVACION PARA ZAPATAS EN TERRENO NORMAL M3 3.63 24.24 87.99 3.63 87.99 0.00 3.63 87.99 100.00% 0.00
01.01.02.02 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 4.09 21.63 88.47 4.09 88.47 0.00 4.09 88.47 100.00% 0.00
01.01.02.03 RELLENO CON MATERIAL PROPIO M3 2.26 42.66 96.41 2.26 96.41 0.00 2.26 96.41 100.00% 0.00
01.01.02.04 ACARREO MATERIAL EXCEDENTE D=50M M3 6.44 12.36 79.60 6.44 79.60 0.00 6.44 79.60 100.00% 0.00
01.01.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO M3 6.44 9.58 61.70 6.44 61.70 0.00 6.44 61.70 100.00% 0.00
01.01.02.06 AFIRMADO DE 3=4" PARA VEREDAS M2 13.73 5.92 81.28 0.00 0.00 0.00 0.00 0.00 0.00% 13.73
01.01.03 CONCRETO SIMPLE
01.01.03.01 CONCRETO 1:10+30% P.G. PARA CIMIENTOS CORRIDOS M3 3.27 150.25 491.32 3.27 491.32 0.00 3.27 491.32 100.00% 0.00
01.01.03.02 CONCRETO 1:8 + 25% PM PARA SOBRECIMIENTOS M3 0.75 228.31 171.23 0.75 171.23 0.00 0.75 171.23 100.00% 0.00
01.01.03.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS M2 10.05 21.46 215.67 10.05 215.67 0.00 10.05 215.67 100.00% 0.00
01.01.03.04 SOLADOS PARA ZAPATAS E=4" M2 2.40 17.30 41.52 2.40 41.52 0.00 2.40 41.52 100.00% 0.00
01.01.03.05 PISO DE CONCRETO E=4" FC 175KG/CM2 ACABADO PULIDO 1:2 X 1CM M2 235.85 28.81 6,794.84 235.85 6,794.84 0.00 235.85 6,794.84 100.00% 0.00

01.01.03.06 VEREDA FC=175 KG/CM2 DE CONCRETO DE 4" M2 17.39 30.76 534.92 0.00 0.00 0.00 0.00 0.00 0.00% 17.39
01.01.03.07 ENCOFRADO Y DESENCOFRADO EN VEREDAS M2 9.60 29.44 282.62 0.00 0.00 0.00 0.00 0.00 0.00% 9.60
01.01.03.08 JUNTAS ASFALTICAS EN VEREDAS M 4.50 5.15 23.18 0.00 0.00 0.00 0.00 0.00 0.00% 4.50
01.01.04 CONCRETO ARMADO
01.01.04.01 ZAPATAS
01.01.04.01.01 CONCRETO FC=210 KG/CM2 PARA ZAPATAS M3 1.44 253.19 364.59 1.44 364.59 0.00 1.44 364.59 100.00% 0.00
01.01.04.01.02 ACERO FY=4200 KG/CM2 GRADO 60 EN ZAPATAS KG 29.48 3.41 100.53 29.48 100.53 0.00 29.48 100.53 100.00% 0.00
01.01.04.02 COLUMNAS DE CONFINAMIENTO
01.01.04.02.01 CONCRETO FC=210 KG/CM2 PARA COLUMNAS M3 0.24 305.86 73.41 0.24 73.41 0.00 0.24 73.41 100.00% 0.00
01.01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 3.12 45.92 143.27 3.12 143.27 0.00 3.12 143.27 100.00% 0.00
01.01.04.02.03 ACERO FY=4200 KG/CM2 PARA COLUMNAS KG 0.01 3.41 0.03 0.01 0.03 0.00 0.01 0.03 100.00% 0.00
01.01.04.03 COLUMNAS
01.01.04.03.01 CONCRETO FC=210 KG/CM2 PARA COLUMNAS M3 0.97 305.86 296.68 0.97 296.68 0.00 0.97 296.68 100.00% 0.00
01.01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 22.50 45.92 1,033.20 22.50 1,033.20 0.00 22.50 1,033.20 100.00% 0.00
01.01.04.03.03 ACERO FY=4200 KG/CM2 PARA COLUMNAS KG 154.62 3.41 527.25 154.62 527.25 0.00 154.62 527.25 100.00% 0.00
01.01.04.04 VIGAS
01.01.04.04.01 CONCRETO FC=210 KG/CM2 PARA VIGAS M3 0.06 267.17 16.03 0.06 16.03 0.00 0.06 16.03 100.00% 0.00
01.01.04.04.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS M2 0.48 47.87 22.98 0.48 22.98 0.00 0.48 22.98 100.00% 0.00
01.01.04.04.03 ACERO FY=4200 KG/CM2 PARA VIGAS KG 21.68 3.37 73.06 21.68 73.06 0.00 21.68 73.06 100.00% 0.00
01.01.04.05 ESCALERAS DE CONCRETO ARMADO
01.01.04.05.01 CONCRETO FC=210 KG/CM2 PARA ESCALERAS M3 3.02 305.13 921.49 3.02 921.49 0.00 3.02 921.49 100.00% 0.00
01.01.04.05.02 ENCOFRADO Y DESENCOFRADO PARA ESCALERAS M2 18.62 86.74 1,615.10 18.62 1,615.10 0.00 18.62 1,615.10 100.00% 0.00
01.01.04.05.03 ACERO FY=4200 KG/CM2 PARA ESCALERAS KG 298.41 3.40 1,014.59 298.41 1,014.59 0.00 298.41 1,014.59 100.00% 0.00
01.02 ARQUITECTURA F
01.02.01 MUROS Y TABIQUES
01.02.01.01 MURO DE SOGA LADRILLO CORRIENTE CON CEMENTO-ARENA M2 42.80 34.94 1,495.43 42.80 1,495.43 0.00 42.80 1,495.43 100.00% 0.00
01.02.02 REVOQUES ENLUCIDOS Y MOLDURAS
01.02.02.01 TARRAEJO EN INTERIORES ACABADO CON CEMENTO ARENA 1:5 M2 82.61 10.71 884.75 82.61 884.75 0.00 82.61 884.75 100.00% 0.00
01.02.02.02 TARRAJEO EN EXTERIORES CON CEMENTO ARENA 1:5 M2 2.99 19.63 58.69 0.00 0.00 0.00 0.00 0.00 0.00% 2.99
01.02.02.03 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA 1:5 M2 14.81 22.45 332.48 14.81 332.48 0.00 14.81 332.48 100.00% 0.00
01.02.02.04 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO-ARENA 1:5 M2 0.48 28.68 13.77 0.48 13.77 0.00 0.48 13.77 100.00% 0.00
01.02.02.05 VESTIDURA DE DERRAMES M 29.60 9.09 269.06 29.60 269.06 0.00 29.60 269.06 100.00% 0.00
01.02.02.06 VESTIDURA DE FONDO ESCALERA CON CEMENTO-ARENA M2 11.85 23.58 279.42 11.85 279.42 0.00 11.85 279.42 100.00% 0.00
01.02.02.07 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS M 24.00 20.23 485.52 0.00 0.00 0.00 0.00 0.00 0.00% 24.00
01.02.02.08 DESCANSO DE ESCALERA, ACABADO CON CEMENTO PULIDO M2 4.13 17.40 71.86 0.00 0.00 4.13 71.86 4.13 71.86 100.00% 0.00
01.02.03 PISOS Y PAVIMENTOS
01.02.03.01 CONTRAPISO DE 48MM M2 50.10 21.13 1,058.61 0.00 0.00 0.00 0.00 0.00 0.00% 50.10
01.02.03.02 PISO CERAMICO DE 30X30 CM M2 50.10 32.68 1,637.27 0.00 0.00 0.00 0.00 0.00 0.00% 50.10
01.02.04 CONTRAZOCALOS
01.02.04.01 CONTRAZOCALO EN INTERIORES DE CERAMICO H=10CM M 30.37 7.57 229.90 0.00 0.00 0.00 0.00 0.00 0.00% 30.37

01.02.04.02 CONTRAZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2CM H=30CM M 174.90 5.96 1,042.40 0.00 0.00 0.00 0.00 0.00 0.00% 174.90

01.02.05 CARPINTERIA DE MADERA

01.02.05.01 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5MM DE TORNILLO M2 12.81 160.00 2,049.60 0.00 0.00 0.00 0.00 0.00 0.00% 12.81

01.02.06 CARPINTERIA METALICA


01.02.06.01 VENTANA DE FIERRO PERFIL DE 1"X18" FIJA MARCO T DE 1" M2 2.50 99.15 247.88 0.00 0.00 0.00 0.00 0.00 0.00% 2.50
01.02.06.02 BARANDA METALICA DE TUBOS M 9.10 36.11 328.60
01.02.07 CERRAJERIA
01.02.07.01 BISAGRA CAPUCHINA DE 4"X4" U 18.00 14.15 254.70 0.00 0.00 0.00 0.00 0.00 0.00% 18.00
01.02.07.02 CERRADURA FORTE DE 3 GOLPES U 2.00 77.28 154.56 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.02.07.03 CERRADURA TIPO PERILLA U 4.00 73.92 295.68 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
01.02.08 VIDRIOS, CRISTALES Y SIMILARES
01.02.08.01 VIDRIOS DOBLES NACIONALES P2 26.93 3.69 99.37 0.00 0.00 0.00 0.00 0.00 0.00% 26.93
01.02.09 PINTURA
01.02.09.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS M2 188.91 4.53 855.76 0.00 0.00 0.00 0.00 0.00 0.00% 188.91
01.02.09.02 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 93.49 5.47 511.39 0.00 0.00 0.00 0.00 0.00 0.00% 93.49
01.02.09.03 PINTURA LATEX EN SUPERFICIE DE COLUMNAS, 2 MANOS M2 50.48 5.17 260.98 0.00 0.00 0.00 0.00 0.00 0.00% 50.48
01.02.09.04 PINTURA LATEX EN SUPERFICIE DE VIGAS M2 42.33 5.43 229.85 0.00 0.00 0.00 0.00 0.00 0.00% 42.33

01.02.09.05 PINTURA EN CARPINTERIA METALICA CON ANTICORROSIVO Y ESMALTE M2 48.61 7.56 367.49 0.00 0.00 0.00 0.00 0.00 0.00% 48.61

01.02.09.06 PINTURA ESMALTE EN CONTRAZOCALOS M 174.90 4.10 717.09 0.00 0.00 0.00 0.00 0.00 0.00% 174.90
01.02.09.07 PINTURA BARNIZ EN MURO CARAVISTA M2 105.58 9.80 1,034.68 0.00 0.00 0.00 0.00 0.00 0.00% 105.58
01.02.10 OTROS
01.02.10.01 LIMPIEZA DE VIDRIOS M2 33.25 2.16 71.82 0.00 0.00 0.00 0.00 0.00 0.00% 33.25
01.03 INSTALACIONES SANITARIAS F
01.03.01 DESAGUE PLUVIAL
01.03.01.01 CANALETA DE PLANCHA GALVANIZADA M 36.80 24.16 889.09 0.00 0.00 0.00 0.00 0.00 0.00% 36.80
01.03.01.02 MONTNTE CON TUBERIA PVC DE 3" M 16.80 14.48 243.26 0.00 0.00 0.00 0.00 0.00 0.00% 16.80
01.03.01.03 CODO PVC SAL 3"X45 U 8.00 20.90 167.20 0.00 0.00 0.00 0.00 0.00 0.00% 8.00
01.03.01.04 CODO PVC SAL 3"X90 U 4.00 12.08 48.32 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
01.04 INSTALACIONES ELECTRICAS F
01.04.01 TUBERIA Y CANALIZACION
01.04.01.01 CANALIZACION PARA DUCTO EN PARED Y PISO M 218.00 2.70 588.60 188.65 509.36 18.45 49.82 207.10 559.18 95.00% 10.90
01.04.01.02 TUBERIA DE PVC SEL 35MM M 19.00 10.94 207.86 19.00 207.86 0.00 19.00 207.86 100.00% 0.00
01.04.01.03 TUBERIA DE PVC SEL 25MM M 65.55 34.45 2,258.20 65.55 2,258.20 0.00 65.55 2,258.20 100.00% 0.00
01.04.01.04 TUBERIA DE PVC SEL 20MM M 147.80 3.08 455.22 133.10 409.95 7.31 22.51 140.41 432.46 95.00% 7.39
01.04.02 CAJAS DE PASE
01.05.02.01 CAJAS DE PASE DE 4"X4"X2" PZA 13.00 94.73 1,231.49 8.00 757.84 0.00 0.00 8.00 757.84 62.00% 5.00
01.04.03 CONDUCTORES
01.04.03.01 CONDUCTOR THW C/CABLE 1X35MM2 M 12.00 17.07 204.84 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
01.04.03.02 CONDUCTOR THW C/CABLE 1X16MM2 M 4.00 9.18 36.72 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
01.04.03.03 CONDUCTOR THW C/CABLE 1X10MM2 M 213.00 4.95 1,054.35 0.00 0.00 0.00 0.00 0.00 0.00% 213.00
01.04.03.04 CONDUCTOR THW C/CABLE 1X6MM2 M 12.00 2.59 31.08 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
01.04.03.05 CONDUCTOR THW C/CABLE 1X4MM2 M 10.00 1.98 19.80 0.00 0.00 0.00 0.00 0.00 0.00% 10.00
01.04.03.06 CONDUCTOR THW C/CABLE 1X2.5MM3 M 209.40 1.49 312.01 0.00 0.00 0.00 0.00 0.00 0.00% 209.40
01.04.04 INSTALACION DE PLACAS
01.04.04.01 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRADO U 12.00 15.66 187.92 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
01.04.04.02 INTERRUPTOR SIMPLE PARA EMPOTRADO U 4.00 17.10 68.40 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
01.04.04.03 INTERRUPTOR DOBLE PARA EMPOTRADO U 1.00 17.27 17.27 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.04.04.04 INTERRUPTOR TRIPLE PARA EMPOTRADO U 5.00 30.20 151.00 0.00 0.00 0.00 0.00 0.00 0.00% 5.00
01.04.04.05 INTERRUPTOR DE CONMUTADOR SIMPLE U 2.00 17.03 34.06 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.04.05 INSTALACION DE ARTEFACTOS

01.04.05.01 EQUIPO FLUORESCENTE DOBLE DE 2X36W CON PATALLA ACRILICO REJILLA U 9.00 54.07 486.63 0.00 0.00 0.00 0.00 0.00 0.00% 9.00

01.04.05.02 EQUIPO FLUORESCENTE DOBLE DE 2X36W COLGANTE U 13.00 66.78 868.14 0.00 0.00 0.00 0.00 0.00 0.00% 13.00
01.04.06 TABLEROS
01.05.06.01 TABLERO GENERAL 12 POLOS U 1.00 93.78 93.78 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.05.06.02 TABLERO DE DISTRIBUCION 24 POLOS U 1.00 291.26 291.26 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.05.06.03 TABLERO DE DISTRIBUCION 12 POLOS U 1.00 93.98 93.98 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.04.07 LLAVES TERMOMAGNETICA
01.04.07.01 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X15A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.04.07.02 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X20A PZA 1.00 37.15 37.15 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.04.07.03 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X30A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.04.07.04 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X20A PZA 1.00 57.09 57.09 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.04.07.05 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X60A PZA 5.00 78.10 390.50 0.00 0.00 0.00 0.00 0.00 0.00% 5.00
01.04.07.06 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X160A PZA 3.00 525.16 1,575.48 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
02 PABELLON H
02.01 ESTRUCTURAS H
02.01.01 OBRAS PRELIMINARES
02.01.01.01 DEMOLICION DE PISOS DE CONCRETO DE 0.10M M2 689.39 6.00 4,136.34 583.48 3,500.88 71.44 428.64 654.92 3,929.52 95.00% 34.47
02.01.01.02 DEMOLICION DE PISO CERAMICO Y DE CEMENTO M2 913.65 1.50 1,370.48 913.65 1,370.48 0.00 913.65 1,370.48 100.00% 0.00
02.01.01.03 DEMOLICION DE MUROS DE LADRILLO M3 96.86 5.28 511.42 96.86 511.42 0.00 96.86 511.42 100.00% 0.00
02.01.01.04 DEMOLICION DE LOSA ALIGERADA M3 5.49 54.80 300.85 5.49 300.85 0.00 5.49 300.85 100.00% 0.00
02.01.01.05 DEMOLICION DE COLUMNAS DE CONCRETO M3 2.01 53.87 108.28 2.01 108.28 0.00 2.01 108.28 100.00% 0.00
02.01.01.06 DESMONTAJE DE COBERTURAS DE CALAMINA M2 294.05 3.65 1,073.28 294.05 1,073.28 0.00 294.05 1,073.28 100.00% 0.00
02.01.01.07 RETIRO DE TIJERALES DE MADERA U 36.00 55.23 1,988.28 36.00 1,988.28 0.00 36.00 1,988.28 100.00% 0.00
02.01.01.08 RETIRO DE PUERTAS Y VENTANAS M2 147.21 3.20 471.07 147.21 471.07 0.00 147.21 471.07 100.00% 0.00
02.01.01.09 ACARREO MATERIAL PROVENIENTE DE DEMOLICIONES D=50M M3 274.10 12.36 3,387.88 229.61 2,837.98 30.78 380.44 260.39 3,218.42 95.00% 13.71
02.01.01.10 ELIMINACION DE DEMOLICIONES M3 274.10 9.95 2,727.30 229.61 2,284.62 30.78 306.26 260.39 2,590.88 95.00% 13.71
02.01.01.11 TRAZO Y REPLANTEO INICIAL M2 1,545.00 0.37 571.65 1,320.00 488.40 147.75 54.67 1,467.75 543.07 95.00% 77.25
02.01.02 CONCRETO SIMPLE

02.01.02.01 PISO DE CONCRETO E=4" FC 175KG/CM2 ACABADO PULIDO 1:2 X 1CM M2 446.56 28.81 12,865.39 380.00 10,947.80 0.00 0.00 380.00 10,947.80 85.00% 66.56

02.01.03 CONCRETO ARMADO


02.01.03.01 PLATAFORMAS PARA MAQUINARIAS
02.01.03.02 CONCRETO FC=210 KG/CM2 PARA COLUMNAS M3 8.21 293.10 2,406.35 0.00 0.00 0.00 0.00 0.00 0.00% 8.21
02.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 26.88 16.85 452.93 0.00 0.00 0.00 0.00 0.00 0.00% 26.88
02.01.03.04 ACERO FY=4200 KG/CM2 PARA COLUMNAS KG 383.45 3.40 1,303.73 0.00 0.00 0.00 0.00 0.00 0.00% 383.45
02.02 ARQUITECTURA H
02.02.01 MUROS Y TABIQUES

02.02.01.01 MURO DE SOGA LADRILLO ARTESANAL SOGA 13X24X8CM CEMENTO-ARENA 1:5 M2 337.69 37.36 12,616.10 337.69 12,616.10 0.00 337.69 12,616.10 100.00% 0.00

02.02.02 REVOQUES ENLUCIDOS Y MOLDURAS


02.02.02.01 TARRAEJO EN INTERIORES ACABADO CON CEMENTO ARENA 1:5 M2 604.38 10.71 6,472.91 604.38 6,472.91 0.00 0.00 604.38 6,472.91 100.00% 0.00
02.02.02.02 TARRAJEO DE EXTERIORES CON CEMENTO ARENA 1:5 M2 40.92 19.63 803.26 31.00 608.53 9.92 194.73 40.92 803.26 100.00% 0.00
02.02.02.03 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO ARENA 1:5 M2 14.36 22.45 322.38 13.05 292.97 1.31 29.41 14.36 322.38 100.00% 0.00
02.02.02.04 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO-ARENA 1:5 M2 15.52 28.68 445.11 13.86 397.50 1.66 47.61 15.52 445.11 100.00% 0.00
02.02.02.05 VESTIDURA DE FONDO ESCALERA CON CEMENTO-ARENA M2 33.22 23.58 783.33 0.00 0.00 33.22 783.33 33.22 783.33 100.00% 0.00
02.02.02.06 TARRAJEO CON IMPERMEBILIZANTE SOBRE LOSA DE TECHO M2 533.58 22.42 11,962.86 0.00 0.00 533.58 11,962.86 533.58 11,962.86 100.00% 0.00
02.02.02.07 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS M 69.52 20.23 1,406.39 0.00 0.00 0.00 0.00 0.00 0.00% 69.52
02.02.02.08 DESCANSO DE ESCALERA, ACABADO CON CEMENTO PULIDO M2 10.50 17.40 182.70 0.00 0.00 0.00 0.00 0.00 0.00% 10.50
02.02.03 CIELORRASOS
02.02.03.01 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA MEZCLA 1:5 M2 24.35 33.63 818.89 22.04 741.21 2.31 77.69 24.35 818.90 100.00% 0.00

02.02.03.02 RESANE INST ELECTRICAS TECHO Y PARED ANCHO= 15CM, E=1.5CM, MEZCLA 1:5 M 531.00 8.27 4,391.37 496.70 4,107.71 34.30 283.66 531.00 4,391.37 100.00% 0.00

02.02.04 PISOS Y PAVIMENTOS


02.02.04.01 CONTRAPISO DE 48MM M2 619.83 21.13 13,097.01 560.00 11,832.80 28.84 609.39 588.84 12,442.19 95.00% 30.99
02.02.04.02 PISO CERAMICO DE 30X30 CM M2 600.66 32.68 19,629.57 0.00 0.00 570.00 18,627.60 570.00 18,627.60 95.00% 30.66
02.02.04.03 PISO CERAMICO DE 30X30 CM ANTIDESLIZANTE M2 19.17 32.68 626.48 0.00 0.00 0.00 0.00 0.00 0.00% 19.17
02.02.04.04 PISO DE CEMENTO FROTACHADO M2 430.93 30.61 13,190.77 385.50 11,800.16 0.00 0.00 385.50 11,800.16 89.00% 45.43
02.02.05 CONTRAZOCALOS
02.02.05.01 CONTRAZOCALO EN INTERIORES DE CERAMICO H=10CM M 354.05 7.57 2,680.16 0.00 0.00 318.00 2,407.26 318.00 2,407.26 90.00% 36.05

02.02.05.02 CONTRAZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2CM H=30CM M 419.04 5.96 2,497.48 0.00 0.00 356.00 2,121.76 356.00 2,121.76 85.00% 63.04

02.02.06 ZOCALOS
02.02.06.01 ZOCALO DE CERAMICA BLANCA DE 20X30CM DE 1RA M2 57.42 33.65 1,932.18 0.00 0.00 0.00 0.00 0.00 0.00% 57.42
02.02.07 CARPINTERIA DE MADERA

02.02.07.01 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5MM DE TORNILLO M2 73.29 160.00 11,726.40 0.00 0.00 0.00 0.00 0.00 0.00% 73.29

02.02.08 CARPINTERIA METALICA


02.02.08.01 MAMPARA METALICA PERFIL DE 1"X1/8 FIJA MARCO T DE 1" M2 15.04 136.87 2,058.52 0.00 0.00 0.00 0.00 0.00 0.00% 15.04
02.02.08.02 VENTANA DE FIERRO PERFIL DE 1"X1/8 FIJA MARCO T DE 1" M2 383.71 33.05 12,681.62 134.30 4,438.57 134.00 4,428.70 268.30 8,867.27 70.00% 115.41
02.02.09 VIDRIOS, CRISTALES Y SIMILARES 0.00
02.02.09.01 VIDRIOS DOBLES NACIONALES P2 4,128.67 3.69 15,234.79 0.00 0.00 0.00 0.00 0.00 0.00% 4,128.67
02.02.10 PINTURA
02.02.10.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS M2 1,583.72 4.53 7,174.25 0.00 0.00 396.00 1,793.88 396.00 1,793.88 25.00% 1,187.72
02.02.10.02 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 362.05 5.47 1,980.41 0.00 0.00 0.00 0.00 0.00 0.00% 362.05
02.02.10.03 PINTURA LATEX EN SUPERFICIE DE COLUMNAS, 2 MANOS M2 402.81 5.17 2,082.53 0.00 0.00 100.00 517.00 100.00 517.00 25.00% 302.81
02.02.10.04 PINTURA LATEX EN SUPERFICIE DE VIGAS M2 291.66 5.43 1,583.71 0.00 0.00 73.00 396.39 73.00 396.39 25.00% 218.66
02.02.10.05 PINTURA LATEX EN CIELORRASO 2 MANOS M2 1,468.28 4.71 6,915.60 0.00 0.00 0.00 0.00 0.00 0.00% 1,468.28

02.02.10.06 PINTURA EN CARPINTERIA METALICA CON ANTICORROSIVO Y ESMALTE M2 391.23 7.56 2,957.70 0.00 0.00 0.00 0.00 0.00 0.00% 391.23

02.02.10.07 PINTURA ESMALTE EN CONTRAZOCALOS H=30 CM M 419.04 4.10 1,718.06 0.00 0.00 0.00 0.00 0.00 0.00% 419.04
02.02.11 APARATOS Y ACCESORIOS SANITARIOS
02.02.11.01 INODORO DE PORCELANA TANQUE BAJO BLANCO U 6.00 75.63 453.78 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
02.02.11.02 LAVATORIO DE LOSA VITRIFICADA U 2.00 75.36 150.72 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02.02.11.03 URINARIO CORRIDO DE CONCRETO HECHO EN OBRA M 1.40 294.43 412.20 0.00 0.00 0.00 0.00 0.00 0.00% 1.40
02.02.11.04 LAVADERO CORRIDO DE CONCRETO HECHO EN OBRA M 5.88 384.39 2,260.21 0.00 0.00 0.00 0.00 0.00 0.00% 5.88
02.02.11.05 DISPENSOR DE PAPEL TOALLA PZA 1.00 42.02 42.02 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.02.11.06 PAPELERA DE LOZA BLANCA DE 13X15 CM PZA 6.00 25.21 151.26 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
02.02.11.07 COLOCACION DE ACCESORIOS SANITARIOS PZA 8.00 50.80 406.40 0.00 0.00 0.00 0.00 0.00 0.00% 8.00
02.02.11.08 COLOCACION DE APARATOS SANITARIOS PZA 7.00 25.40 177.80 0.00 0.00 0.00 0.00 0.00 0.00% 7.00
02.02.12 OTROS
02.02.12.01 LIMPIEZA FINAL M2 553.98 0.36 199.43 415.49 149.57 0.00 0.00 415.49 149.57 75.00% 138.50
02.03 INSTALACIONES ELECTRICAS H
02.03.01 TUBERIA Y CANALIZACION
02.03.01.01 CANALIZACION PARA DUCTO EN PARED Y PISO M 789.80 2.70 2,132.46 668.66 1,805.38 81.65 220.46 750.31 2,025.84 95.00% 39.49
02.03.01.02 TUBERIA DE PVC SEL 25MM M 74.66 34.45 2,572.04 64.00 2,204.80 6.93 238.74 70.93 2,443.54 95.00% 3.73
02.03.01.03 TUBERIA DE PVC SEL 20MM M 677.14 3.08 2,085.59 573.66 1,766.87 69.62 214.43 643.28 1,981.30 95.00% 33.86
02.03.02 CAJAS DE PASE
02.03.02.01 CAJAS DE PASE DE 4"X4" U 1.00 19.41 19.41 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.03 CONDUCTORES
02.03.03.01 CONDUCTOR THW C/CABLE 1X35MM2 M 110.80 17.07 1,891.36 0.00 0.00 0.00 0.00 0.00 0.00% 110.80
02.03.03.02 CONDUCTOR THW C/CABLE 1X16MM2 M 72.00 9.18 660.96 0.00 0.00 0.00 0.00 0.00 0.00% 72.00
02.03.03.03 CONDUCTOR THW C/CABLE 1X6MM2 M 682.68 2.59 1,768.14 0.00 0.00 0.00 0.00 0.00 0.00% 682.68
02.03.03.04 CONDUCTOR THW C/CABLE 1X4MM2 M 1,013.00 1.98 2,005.74 0.00 0.00 0.00 0.00 0.00 0.00% 1,013.00
02.03.03.05 CONDUCTOR THW C/CABLE 1X2.5MM3 M 1,353.40 1.49 2,016.57 0.00 0.00 0.00 0.00 0.00 0.00% 1,353.40
02.03.04 INSTALACION DE PLACAS
02.03.04.01 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRADO U 96.00 15.66 1,503.36 0.00 0.00 0.00 0.00 0.00 0.00% 96.00
02.03.05 INSTALACION DE ARTEFACTOS

02.03.05.01 EQUIPO FLUORESCENTE DOBLE DE 2X36W CON PATALLA ACRILICO REJILLA U 98.00 54.07 5,298.86 0.00 0.00 0.00 0.00 0.00 0.00% 98.00

02.03.05.02 EQUIPO FLUORESCENTE DOBLE DE 2X36W COLGANTE U 24.00 66.78 1,602.72 0.00 0.00 0.00 0.00 0.00 0.00% 24.00

02.03.05.03 FLUORESCENTE CIRCULAR DE 32W INC BASE ADOSABLE DE ALUMINIO+ACCES U 3.00 62.53 187.59 0.00 0.00 0.00 0.00 0.00 0.00% 3.00

02.03.05.04 LUMINARIA TIPO SPOT LINGH ADOSABLE INC FOCO AHORRADOR U 14.00 43.37 607.18 0.00 0.00 0.00 0.00 0.00 0.00% 14.00
02.03.06 TABLEROS
02.03.06.01 TABLERO GENERAL 12 POLOS U 1.00 93.78 93.78 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.06.02 TABLERO DE DISTRIBUCION 12 POLOS U 1.00 93.98 93.98 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.06.03 TABLERO DE DISTRIBUCION 16 POLOS U 1.00 219.84 219.84 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.06.04 TABLERO DE DISTRIBUCION 20 POLOS U 1.00 291.26 291.26 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.06.05 TABLERO DE DISTRIBUCION 24 POLOS U 1.00 291.26 291.26 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.06.06 TABLERO DE DISTRIBUCION 32 POLOS U 1.00 301.77 301.77 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.06.07 TABLERO DE DISTRIBUCION 36 POLOS U 1.00 301.77 301.77 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.07 LLAVES TERMOMAGNETICA
02.03.07.01 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X15A PZA 12.00 37.15 445.80 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
02.03.07.02 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X20A PZA 10.00 37.15 371.50 0.00 0.00 0.00 0.00 0.00 0.00% 10.00
02.03.07.03 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X30A PZA 1.00 37.15 37.15 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.07.04 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X50A PZA 2.00 51.43 102.86 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02.03.07.05 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X30A PZA 20.00 57.09 1,141.80 0.00 0.00 0.00 0.00 0.00 0.00% 20.00
02.03.07.06 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X50A PZA 9.00 78.10 702.90 0.00 0.00 0.00 0.00 0.00 0.00% 9.00
02.03.07.07 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X60A PZA 3.00 78.10 234.30 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
02.03.07.08 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X80A PZA 2.00 102.39 204.78 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02.03.07.09 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X100A PZA 1.00 92.56 92.56 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02.03.07.10 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X160A PZA 2.00 525.16 1,050.32 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02.03.07.11 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X200A PZA 1.00 731.05 731.05 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

COSTO DIRECTO 272,496.55 107,560.93 46,269.10 153,830.03


GASTOS GENERALES % 8.00 21,799.72 8,604.87 3,701.53 12,306.40
UTILIDAD % 5.00 13,624.84 5,378.05 2,313.46 7,691.50
SUBTOTAL 307,921.10 121,543.85 52,284.09 173,827.93
FACTOR DE RELACION 1.0000
SUBTOTAL - con Factor de Relacion 307,921.10 121,543.85 52,284.09 173,827.93

VALORIZACION DE OBRA Nº 04
(Periodo : Del 01 Mayo al 31 Mayo 2011)

Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVODE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A Valor Referencial (S/.) : 4,572,084.75 con IGV
Plazo de Ejecucion : 240 Dias Calendarios Costos al : February-2010
Supervisor : ING. ANTONIO VALENZUELA SALAS Monto del Contrato (S/.) : 4,572,084.75 con IGV
Residente : ING. PABLO SARMIENTO REYES Factor de Relacion : 1.000

Formula : 005 - PABELLON G


AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
PRECIO
UNIDAD METRADO UNITARIO PARCIAL Metrado Monto Metrado Monto Metrado Monto % Metrado

01 PABELLON G
01.01 OBRAS PROVISIONALES
01.01.01 ALMACENES Y GUARDIANIA EST 1.00 6,300.00 6,300.00 1.00 6,300.00 0.00 1.00 6,300.00 100.00% 0.00

010102 CARTELL DE IDENTIFICACION DE LA OBRA DE 3.60X5.2M INC INSTALACION U 1.00 1,260.45 1,260.45 1.00 1,260.45 0.00 1.00 1,260.45 100.00% 0.00

01.02 OBRAS PRELIMINARES


01.02.01 DEMOLICION DE PISOS DE CONCRETO DE 0.10M M2 659.75 6.00 3,958.50 659.75 3,958.50 0.00 659.75 3,958.50 100.00% 0.00
01.02.02 DEMOLICION DE MUROS DE CONCRETO ARMADO M3 9.20 60.21 553.93 9.20 553.93 0.00 9.20 553.93 100.00% 0.00
01.02.03 DEMOLICION DE MUROS DE ADOBE M3 46.63 15.09 703.65 46.63 703.65 0.00 46.63 703.65 100.00% 0.00
01.02.04 DEMOLICION DE MUROS DE LADRILLO M3 18.79 5.28 99.21 18.79 99.21 0.00 18.79 99.21 100.00% 0.00
01.02.05 DEMOLICION DE COLUMNAS DE CONCRETO M3 7.28 53.87 392.17 7.28 392.17 0.00 7.28 392.17 100.00% 0.00
01.02.06 DESMONTAJE DE COBERTURAS DE CALAMINA M2 626.30 3.65 2,286.00 626.30 2,286.00 0.00 626.30 2,286.00 100.00% 0.00
01.02.07 RETIRO DE TIJERALES DE MADERA U 36.00 55.23 1,988.28 36.00 1,988.28 0.00 36.00 1,988.28 100.00% 0.00
01.02.08 RETIRO DE PUERTAS Y VENTANAS M2 86.64 3.20 277.25 86.64 277.25 0.00 86.64 277.25 100.00% 0.00
01.02.09 ACARREO MATERIAL PROVENIENTE DE DEMOLICIONES D=50M M3 184.84 12.36 2,284.62 184.84 2,284.62 0.00 184.84 2,284.62 100.00% 0.00
01.02.10 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO M3 184.84 9.95 1,839.16 184.84 1,839.16 0.00 184.84 1,839.16 100.00% 0.00
01.02.11 TRAZO Y REPLANTEO INICIAL M2 945.00 1.78 1,682.10 945.00 1,682.10 945.00 1,682.10 100.00% 0.00
01.03 MOVIMIENTO DE TIERRAS
01.03.01 EXCAVACION PARA ZAPATAS EN TERRENO NORMAL M3 290.72 24.24 7,047.05 290.72 7,047.05 0.00 290.72 7,047.05 100.00% 0.00
01.03.02 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 42.12 21.63 911.06 42.12 911.06 0.00 0.00 42.12 911.06 100.00% 0.00
01.03.03 EXCAVACION PARA CAJA DE CISTERNA M3 11.59 24.72 286.50 11.59 286.50 0.00 0.00 11.59 286.50 100.00% 0.00
01.03.04 RELLENO CON MATERIAL PROPIO M3 220.95 42.66 9,425.73 220.95 9,425.73 0.00 0.00 220.95 9,425.73 100.00% 0.00
01.03.05 ACARREO MATERIAL EXCEDENTE D=50M M3 141.93 12.36 1,754.25 141.93 1,754.25 0.00 0.00 141.93 1,754.25 100.00% 0.00
01.03.06 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO M3 141.93 9.58 1,359.69 141.93 1,359.69 0.00 0.00 141.93 1,359.69 100.00% 0.00
01.03.07 AFIRMADO DE 3=4" PARA VEREDAS M2 45.61 5.92 270.01 0.00 0.00 0.00 0.00 0.00 0.00% 45.61

01.03.08 NIVELACION, RELLENO Y COMPACTACION CON MATERIAL DE PRESTAMO M2 546.27 7.43 4,058.79 546.27 4,058.79 0.00 0.00 546.27 4,058.79 100.00% 0.00

01.04 CONCRETO SIMPLE


01.04.01 CONCRETO 1:10+30% P.G. PARA CIMIENTOS CORRIDOS M3 57.62 150.25 8,657.41 57.62 8,657.41 0.00 0.00 57.62 8,657.41 100.00% 0.00
01.04.02 CONCRETO 1:8 + 25% PM PARA SOBRECIMIENTOS M3 9.47 228.31 2,162.10 9.47 2,162.10 0.00 0.00 9.47 2,162.10 100.00% 0.00
01.04.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS M2 124.60 21.46 2,673.92 124.60 2,673.92 0.00 0.00 124.60 2,673.92 100.00% 0.00
01.04.04 SOLADOS PARA ZAPATAS E=4" M2 117.14 17.30 2,026.52 117.14 2,026.53 0.00 0.00 117.14 2,026.53 100.00% 0.00
01.04.05 FALSO PISO DE 4" DE CONCRETO 1:10 M2 136.02 15.60 2,121.91 136.02 2,121.91 0.00 0.00 136.02 2,121.91 100.00% 0.00
01.04.06 PISO DE CONCRETO E=4" FC 175KG/CM2 ACABADO PULIDO 1:2 X 1CM M2 425.38 28.81 12,255.20 0.00 0.00 0.00 0.00 0.00 0.00% 425.38
01.04.07 RAMPA DE CONCRETO 1:10 PARA MINUSVALIDOS M2 1.87 47.35 88.54 0.00 0.00 0.00 0.00 0.00 0.00% 1.87
01.04.08 ENCOFRADO Y DESENCOFRADO RAMPAS M2 1.36 36.53 49.68 0.00 0.00 0.00 0.00 0.00 0.00% 1.36
01.04.09 ESCALERAS DE CONCRETO 1:10 M3 3.51 189.56 665.36 3.51 665.36 0.00 0.00 3.51 665.36 100.00% 0.00
01.04.10 ENCOFRADO Y DESENCOFRADO ESCALERAS M2 4.98 35.03 174.45 4.98 174.45 0.00 0.00 4.98 174.45 100.00% 0.00
01.04.11 VEREDA FC=175 KG/CM2 DE CONCRETO DE 4" M2 45.61 30.76 1,402.96 45.61 1,402.96 0.00 0.00 45.61 1,402.96 100.00% 0.00
01.04.12 ENCOFRADO Y DESENCOFRADO VEREDAS M2 19.40 29.44 571.14 0.00 0.00 0.00 0.00 0.00 0.00% 19.40
01.04.13 JUNTAS ASFALTICAS EN VEREDAS M 16.50 5.15 84.98 0.00 0.00 0.00 0.00 0.00 0.00% 16.50
01.05 CONCRETO ARMADO
01.05.01 ZAPATAS
01.05.01.01 CONCRETO FC=210 KG/CM2 PARA ZAPATAS M3 76.20 253.19 19,293.08 76.20 19,293.08 0.00 0.00 76.20 19,293.08 100.00% 0.00
01.05.01.02 ACERO FY=4200 KG/CM2 GRADO 60 EN ZAPATAS KG 1,867.61 3.41 6,368.55 1,867.61 6,368.55 0.00 1,867.61 6,368.55 100.00% 0.00
01.05.02 COLUMNAS
01.05.02.01 CONCRETO FC=210 KG/CM2 PARA COLUMNAS M3 73.52 305.86 22,486.83 29.69 9,080.99 19.57 5,985.68 49.26 15,066.67 67.00% 24.26
01.05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 652.23 45.92 29,950.40 268.37 12,323.55 168.62 7,743.03 436.99 20,066.58 67.00% 215.24
01.05.02.03 ACERO FY=4200 KG/CM2 PARA COLUMNAS KG 15,111.04 3.41 51,528.65 12,088.84 41,222.94 3,022.20 10,305.70 15,111.04 51,528.64 100.00% 0.00
01.05.03 COLUMNAS CON AFINAMIENTO
01.05.03.01 CONCRETO FC=210 KG/CM2 PARA COLUMNETAS M3 20.32 288.25 5,857.24 0.00 0.00 6.10 1,758.33 6.10 1,758.33 30.00% 14.22
01.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS M2 254.42 35.16 8,945.41 0.00 0.00 76.32 2,683.41 76.32 2,683.41 30.00% 178.10
01.05.03.03 ACERO FY=4200 KG/CM2 PARA COLUMNETAS KG 1,456.58 3.23 4,704.75 0.00 0.00 436.97 1,411.41 436.97 1,411.41 30.00% 1,019.61
01.05.04 PLACAS
01.05.04.01 CONCRETO FC=210 KG/CM2 PARA PLACAS M3 28.27 334.85 9,466.21 9.45 3,164.33 9.49 3,177.73 18.94 6,342.06 67.00% 9.33
01.05.04.02 ENCOFRADO Y DESENCOFRADO PARA PLACAS M2 384.16 45.90 17,632.94 141.12 6,477.41 116.27 5,336.79 257.39 11,814.20 67.00% 126.77
01.05.04.03 ACERO FY=4200 KG/CM2 PARA PLACAS KG 1,681.83 3.40 5,718.22 610.77 2,076.62 516.05 1,754.57 1,126.82 3,831.19 67.00% 555.01
01.05.05 VIGAS
01.05.05.01 CONCRETO FC=210 KG/CM2 PARA VIGAS M3 170.48 267.17 45,547.14 56.20 15,014.95 58.02 15,501.20 114.22 30,516.15 67.00% 56.26
01.05.05.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS M2 1,203.17 47.87 57,595.75 400.73 19,182.95 405.39 19,406.02 806.12 38,588.97 67.00% 397.05
01.05.05.03 ACERO FY=4200 KG/CM2 PARA VIGAS KG 16,011.04 3.37 53,957.20 4,710.52 15,874.46 6,016.88 20,276.89 10,727.40 36,151.35 67.00% 5,283.64
01.05.06 ESCALERAS DE CONCRETO ARMADO
01.05.06.01 CONCRETO FC=210 KG/CM2 PARA ESCALERAS M3 14.05 305.13 4,287.08 4.99 1,522.60 4.42 1,348.67 9.41 2,871.27 67.00% 4.64
01.05.06.02 ENCOFRADO Y DESENCOFRADO PARA ESCALERAS M2 86.89 86.74 7,536.84 24.72 2,144.21 33.50 2,905.79 58.22 5,050.00 67.00% 28.67
01.05.06.03 ACERO FY=4200 KG/CM2 PARA ESCALERAS KG 1,146.61 3.40 3,898.47 356.18 1,211.01 412.05 1,400.97 768.23 2,611.98 67.00% 378.38
01.05.07 LOSAS ALIGERADAS E=E=25CM
01.05.07.01 CONCRETO FC=210 KG/CM2 PARA LOSAS ALIGERADAS M3 207.98 270.24 56,204.52 68.35 18,470.90 71.00 19,187.04 139.35 37,657.94 67.00% 68.63

01.05.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS DOBLE SENTIDO M2 1,273.38 27.83 35,438.17 424.46 11,812.72 428.70 11,930.72 853.16 23,743.44 67.00% 420.22

01.05.07.03 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS M2 306.71 46.74 14,335.63 87.04 4,068.25 118.46 5,536.82 205.50 9,605.07 67.00% 101.21
01.05.07.04 ACERO FY=4200 KG/CM2 PARA LOSAS ALIGERADAS KG 13,784.86 3.40 46,868.52 3,968.65 13,493.41 5,267.20 17,908.48 9,235.85 31,401.89 67.00% 4,549.01
01.05.07.05 LADRILLO HUECO DE ARCILLA H=20 CM PARA LOSA ALIGERADO PZA 10,320.34 2.91 30,032.19 2,644.39 7,695.17 4,270.24 12,426.40 6,914.63 20,121.57 67.00% 3,405.71
01.05.07.06 LADRILLO HUECO DE ARCILLA H=15 CM PARA LOSA ALIGERADO PZA 167.72 2.53 424.33 167.72 424.33 0.00 0.00 167.72 424.33 100.00% 0.00
01.05.08 MESAS DE CONCRETO ARMADO EN LABORATORIO
01.05.08.01 CONCRETO FC=175 KG/CM2 PARA MESA EN LABORATORIO M3 2.61 263.07 686.61 0.00 0.00 0.00 0.00 0.00 0.00% 2.61
01.05.08.02 ENCOFRADO Y DESENCOFRADO EN MESAS DE LABORATORIO M2 51.97 16.85 875.69 0.00 0.00 0.00 0.00 0.00 0.00% 51.97
01.05.08.03 ACERO FY=4200 KG/CM2 PARA MESAS EN LABORATORIO KG 469.00 3.40 1,594.60 0.00 0.00 0.00 0.00 0.00 0.00% 469.00
01.05.09 CISTERNA
01.05.09.01 CONCRETO FC=210 KG/CM2 PARA CISTERNA M3 6.18 321.37 1,986.07 6.18 1,986.07 0.00 0.00 6.18 1,986.07 100.00% 0.00
01.05.09.02 ENCOFRADO Y DESENCOFRADO PARA CAJA DE CISTERNA M2 32.53 49.22 1,601.13 32.53 1,601.13 0.00 0.00 32.53 1,601.13 100.00% 0.00
01.05.09.03 ACERO FY=4200 KG/CM2 PARA CISTERNA KG 295.98 3.41 1,009.29 269.08 917.56 26.90 91.73 295.98 1,009.29 100.00% 0.00
01.05.10 TANQUE ELEVADO
01.05.10.01 CONCRETO FC=210 KG/CM2 PARA TANQUE ELEVADO M3 4.97 315.29 1,566.99 0.00 0.00 0.00 0.00 0.00 0.00% 4.97
01.05.10.02 ENCOFRADO Y DESENCOFRADO PARA TANQUE ELEVADO M2 30.53 54.28 1,657.17 0.00 0.00 0.00 0.00 0.00 0.00% 30.53
01.05.10.03 ACERO FY=4200 KG/CM2 PARA TANQUE ELEVADO KG 245.72 3.40 835.45 0.00 0.00 0.00 0.00 0.00 0.00% 245.72
01.05.11 COBERTURAS

01.05.11.01 COBERTURA, TECHO TIPO FIBRAFORTE TRANSLUCIDO, INCLUYE ESTRUCTURA METALICA M2 15.35 62.49 959.22 0.00 0.00 0.00 0.00 0.00 0.00% 15.35

02 ARQUITECTURA G
02.01 MUROS Y TABIQUES
02.01.01 MURO DE SOGA LADRILLO CORRIENTE CON CEMENTO-ARENA M2 1,830.92 34.94 63,972.34 0.00 0.00 640.82 22,390.25 640.82 22,390.25 35.00% 1,190.10
02.01.02 MURO DE CABEZA LADRILLO CORRIENTE CON CEMENTO-ARENA M2 29.28 64.30 1,882.70 0.00 0.00 0.00 0.00 0.00 0.00% 29.28
02.01.03 TABIQUERIA SISTEMA DRALL WALL E=4" M2 22.87 68.60 1,568.88 0.00 0.00 0.00 0.00 0.00 0.00% 22.87
02.02 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.01 TARRAEJO PRIMARIO RAYADO CON CEMENTO ARENA 1:5 E=1.5CM M2 192.80 13.24 2,552.67 0.00 0.00 0.00 0.00 0.00 0.00% 192.80
02.02.02 TARRAEJO EN INTERIORES ACABADO CON CEMENTO ARENA 1:5 M2 2,478.64 10.71 26,546.23 0.00 0.00 0.00 0.00 0.00 0.00% 2,478.64
02.02.03 TARRAJEO EN EXTERIORES CON CEMENTO ARENA 1:5 M2 786.08 19.63 15,430.75 0.00 0.00 0.00 0.00 0.00 0.00% 786.08
02.02.04 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA 1:5 M2 450.09 22.45 10,104.52 0.00 0.00 90.00 2,020.50 90.00 2,020.50 20.00% 360.09
02.02.05 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO-ARENA 1:5 M2 706.89 28.68 20,273.61 0.00 0.00 141.00 4,043.88 141.00 4,043.88 20.00% 565.89
02.02.06 VESTIDURA DE DERRAMES ANCHO =15CM, E=1.5CM, MEZCLA 1:5 M 940.90 12.71 11,958.84 0.00 0.00 0.00 0.00 0.00 0.00% 940.90
02.02.07 VESTIDURA DE FONDO ESCALERA CON CEMENTO-ARENA M2 50.26 23.58 1,185.13 0.00 0.00 0.00 0.00 0.00 0.00% 50.26
02.02.08 TARRAJEO CON IMPERMEABILIZANTES M2 56.52 23.22 1,312.39 0.00 0.00 56.52 1,312.39 56.52 1,312.39 100.00% 0.00
02.02.09 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS M 89.04 20.23 1,801.28 0.00 0.00 0.00 0.00 0.00 0.00% 89.04
02.02.10 DESCANSO DE ESCALERA, ACABADO CON CEMENTO PULIDO 2M 11.55 17.40 200.97 0.00 0.00 0.00 0.00 0.00 0.00% 11.55
02.03 CIELORRASOS
02.03.01 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA MEZCLA 1:5 M2 1,005.31 33.63 33,808.58 0.00 0.00 201.00 6,759.63 201.00 6,759.63 20.00% 804.31
02.03.02 CIELORRASOS CON BALDOSAS ACUSTICAS M2 523.91 61.20 32,063.29 0.00 0.00 0.00 0.00 0.00 0.00% 523.91
02.04 PISOS Y PAVIMENTOS
02.04.01 CONTRAPISO DE 40MM M2 1,043.37 25.21 26,303.36 420.00 10,588.20 0.00 0.00 420.00 10,588.20 40.00% 623.37
02.04.02 PISO CERAMICO DE 30X30 CM M2 976.61 32.68 31,915.61 0.00 0.00 0.00 0.00 0.00 0.00% 976.61
02.04.03 PISO CERAMICO DE 30X30 CM ANTIDESLIZANTE M2 66.76 32.68 2,181.72 0.00 0.00 0.00 0.00 0.00 0.00% 66.76
02.04.04 PISO DE CONCRETO, ACABADO PULIDO 1:2X1CM M2 632.23 12.91 8,162.09 0.00 0.00 0.00 0.00 0.00 0.00% 632.23
02.05 CONTRAZOCALOS
02.05.01 CONTRAZOCALO EN INTERIORES DE CERAMICO H=10CM M 582.10 7.57 4,406.50 0.00 0.00 0.00 0.00 0.00 0.00% 582.10

02.05.02 CONTRAZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2CM H=30CM M 348.58 5.96 2,077.54 0.00 0.00 0.00 0.00 0.00 0.00% 348.58

02.06 ZOCALOS
02.06.01 ZOCALO DE CERAMICA BLANCA DE 20X30CM DE 1RA M2 203.48 33.65 6,847.10 0.00 0.00 0.00 0.00 0.00 0.00% 203.48
02.06.02 ACABADO CON CERAMICO DE MESAS DE LABORATORIO M2 95.16 41.57 3,955.80 0.00 0.00 0.00 0.00 0.00 0.00% 95.16
02.07 CARPINTERIA DE MADERA
02.07.01 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5MM DE TORNILLO M2 138.47 160.00 22,155.20 0.00 0.00 0.00 0.00 0.00 0.00% 138.47
02.08 CARPINTERIA METALICA
02.08.01 PUERTA METALICA LAC 1/16" CON MARCO 2"X2"X1/4" Y REFUERZOS M2 12.96 504.08 6,532.88 0.00 0.00 0.00 0.00 0.00 0.00% 12.96
02.08.02 VENTANA DE FIERRO PERFIL DE 1"X18" FIJA MARCO T DE 1" M2 424.96 33.05 14,044.93 0.00 0.00 0.00 0.00 0.00 0.00% 424.96
02.08.03 BARANDA METALICA DE TUBO M 30.12 36.11 1,087.63 0.00 0.00 0.00 0.00 0.00 0.00% 30.12
02.09 CERRAJERIA
02.09.01 CERRADURAS
02.09.01.01 CERRADURA FORTE DE 3 GOLPES U 32.00 77.28 2,472.96 0.00 0.00 0.00 0.00 0.00 0.00% 32.00

02.09.01.02 CERRADURA
PUERTA BAÑO SEGURO INTERNO PERILLA MANIJA CERRADURA GOAL 42 NP
BAÑO PZA 3.00 63.75 191.25 0.00 0.00 0.00 0.00 0.00 0.00% 3.00

02.09.01.03 CERROJO DE FIERRO REDONDO DE 1/2"X0.35M U 12.00 23.63 283.56 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
02.10 VIDRIOS, CRISTALES Y SIMILARES
02.10.01 VIDRIOS DOBLES NACIONALES P2 4,609.58 3.69 17,009.35 0.00 0.00 0.00 0.00 0.00 0.00% 4,609.58
02.11 PINTURA
02.11.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS M2 2,515.70 4.53 11,396.12 0.00 0.00 0.00 0.00 0.00 0.00% 2,515.70
02.11.02 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 518.26 5.47 2,834.88 0.00 0.00 0.00 0.00 0.00 0.00% 518.26
02.11.03 PINTURA LATEX EN SUPERFICIE DE COLUMNAS, 2 MANOS M2 450.09 5.17 2,326.97 0.00 0.00 0.00 0.00 0.00 0.00% 450.09
02.11.04 PINTURA LATEX EN SUPERFICIE DE VIGAS M2 706.89 5.43 3,838.41 0.00 0.00 0.00 0.00 0.00 0.00% 706.89
02.11.05 PINTURA LATEX EN DERRAMES, 2 MANOS M2 141.14 3.29 464.35 0.00 0.00 0.00 0.00 0.00 0.00% 141.14
02.11.06 PINTURA LATEX EN CIELORRASO 2 MANOS M2 1,005.31 4.71 4,735.01 0.00 0.00 0.00 0.00 0.00 0.00% 1,005.31
02.11.07 PINTURA BARNIZ CON CARPINTERIA DE MADERA M2 88.80 8.92 792.10 0.00 0.00 0.00 0.00 0.00 0.00% 88.80
02.11.08 PINTURA EN CARPINTERIA METALICA CON ANTICORROSIVO Y ESMALTE M2 444.56 7.56 3,360.87 0.00 0.00 0.00 0.00 0.00 0.00% 444.56
02.11.09 PINTURA ESMALTE EN CONTRAZOCALOS M 348.58 4.10 1,429.18 0.00 0.00 0.00 0.00 0.00 0.00% 348.58
02.12 APARATOS Y ACCESORIOS SANITARIOS
02.12.01 INODORO C/BLANCO TANQUE BAJO U 10.00 75.63 756.30 0.00 0.00 0.00 0.00 0.00 0.00% 10.00
02.12.02 LAVATORIO DE PARED BLANCO 1 LLAVE PZA 6.00 75.36 452.16 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
02.12.03 URINARIOS DE LOZA DE PICO BLANCO PZA 3.00 58.82 176.46 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
02.12.04 URINARIO CORRIDO DE CONCRETO HECHO EN OBRA M 15.90 294.43 4,681.44 0.00 0.00 0.00 0.00 0.00 0.00% 15.90
02.12.05 LAVADERO CORRIDO DE CONCRETO HECHO EN OBRA M 7.08 384.39 2,721.48 0.00 0.00 0.00 0.00 0.00 0.00% 7.08
02.12.06 JABONERA DE LOSA COLOR BLANCO U 12.00 25.21 302.52 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
02.12.07 DISPENSOR DE PAPEL TOALLA PZA 5.00 42.02 210.10 0.00 0.00 0.00 0.00 0.00 0.00% 5.00
02.12.08 PAPELERA DE LOZA BLANCA DE 15X15 CM PZA 12.00 25.21 302.52 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
02.13 OTROS
02.13.01 ESCALERA METALICA TIPO GATO DE FºGº U 2.00 182.04 364.08 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02.13.02 TAPA METALICA DE FºGº DE 60X60CM U 2.00 106.00 212.00 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
03 INSTALACIONES SANITARIAS G
03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
03.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" PTO 49.00 55.86 2,737.14 0.00 0.00 0.00 0.00 0.00 0.00% 49.00
03.01.02 RED DE DISTRIBUCIÓN TUBERIA DE 1/2" PVC-SAP M 71.65 7.97 571.05 52.00 414.44 0.00 0.00 52.00 414.44 73.00% 19.65
03.01.03 RED DE DISTRIBUCIÓN TUBERIA DE 3/4" PVC-SAP M 77.73 8.28 643.60 0.00 0.00 0.00 0.00 0.00 0.00% 77.73
03.01.04 CODO PVC SAP 1/2"X90 U 27.00 8.51 229.77 15.00 127.65 0.00 0.00 15.00 127.65 56.00% 12.00
03.01.05 CODO PVC SAP 3/4"X90 U 16.00 14.92 238.72 0.00 0.00 0.00 0.00 0.00 0.00% 16.00
03.01.06 TEE PVC SAP 3/4X90º U 5.00 11.63 58.15 0.00 0.00 0.00 0.00 0.00 0.00% 5.00
03.01.07 REDUCCIONES PVC-SAP 3/4" A 1/2" U 12.00 13.45 161.40 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
03.01.08 VALVULA COMPUERTA DE BRONCE 1/2" U 14.00 42.52 595.28 0.00 0.00 0.00 0.00 0.00 0.00% 14.00
03.01.09 VALVULA COMPUERTA DE BRONCE 3/4" U 1.00 43.33 43.33 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
03.01.10 VALVULA CHECK DE BRONCE 3/4" U 2.00 64.69 129.38 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
03.02 SISTEMA DE DESAGUE
03.02.01 SALIDA DE DESAGUE DE 4" PTO 12.00 43.36 520.32 8.00 346.88 0.00 0.00 8.00 346.88 67.00% 4.00
03.02.02 SALIDA DE DESAGUE DE 2" PTO 25.00 37.67 941.75 17.00 640.39 0.00 0.00 17.00 640.39 68.00% 8.00
03.02.03 SALIDA DE DESAGUE DE VENTILACION DE 2" PTO 2.00 35.02 70.04 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
03.02.04 EXCAVACION DE ZANJAS PARA TUBERIAS M3 2.40 8.65 20.76 2.40 20.76 0.00 0.00 2.40 20.76 100.00% 0.00
03.02.05 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 1.56 47.22 73.66 1.56 73.66 0.00 0.00 1.56 73.66 100.00% 0.00
03.02.06 RELLENO COMPACTADO MANUAL MATERIAL PROPIO M3 1.56 35.39 55.21 1.56 55.21 0.00 0.00 1.56 55.21 100.00% 0.00
03.02.07 TUBERIA DE PVC SAL 4" M 59.27 18.55 1,099.46 35.12 651.48 0.00 0.00 35.12 651.48 59.00% 24.15
03.02.08 TUBERIA DE PVC SAL 2" M 91.80 17.39 1,596.40 56.50 982.54 0.00 0.00 56.50 982.54 62.00% 35.30
03.02.09 REGISTRO DE BRONCE DE 4" PZA 8.00 45.75 366.00 0.00 0.00 0.00 0.00 0.00 0.00% 8.00
03.02.10 REGISTRO DE BRONCE DE 2" U 7.00 38.05 266.35 0.00 0.00 0.00 0.00 0.00 0.00% 7.00
03.02.11 SUMIDERO DE BRONCE DE 2" U 28.00 48.23 1,350.44 0.00 0.00 0.00 0.00 0.00 0.00% 28.00
03.02.12 CAJA DE REGISTRO DE DESAGUE 12"X24" CON TAPA DE FºFº U 2.00 100.45 200.90 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
03.02.13 YEE PVC SAL 4" U 26.00 11.92 309.92 18.00 214.56 0.00 0.00 18.00 214.56 69.00% 8.00
03.02.14 YEE PVC SAL 2" U 8.00 16.67 133.36 2.00 33.34 4.00 66.68 6.00 100.02 75.00% 2.00
03.02.15 YEE PVC SAL SP RAMAL CON REDUCCION DE 4" A 2" U 11.00 12.05 132.55 8.00 96.40 0.00 0.00 8.00 96.40 73.00% 3.00
03.02.16 CODO PVC SAL 2"X45º U 6.00 12.13 72.78 4.00 48.52 0.00 0.00 4.00 48.52 67.00% 2.00
03.02.17 CODO PVC SAL 4"X90º U 1.00 16.77 16.77 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
03.02.18 TEE PVC-SAP 4" U 1.00 13.82 13.82 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS
03.03.01 COLOCACION DE APARATOS SANITARIOS PZA 16.00 50.80 812.80 0.00 0.00 0.00 0.00 0.00 0.00% 16.00
03.03.02 COLOCACION DE ACCESORIOS SANITARIOS PZA 29.00 25.40 736.60 0.00 0.00 0.00 0.00 0.00 0.00% 29.00
04 INSTALACIONES ELECTRICAS F
04.01 TUBERIA Y CANALIZACION
04.01.01 TUBERIA DE PVC SEL 50MM M 93.18 7.30 680.21 0.00 0.00 0.00 0.00 0.00 0.00% 93.18
04.01.02 TUBERIA DE PVC SEL 40MM M 16.28 15.26 248.43 0.00 0.00 0.00 0.00 0.00 0.00% 16.28
04.01.03 TUBERIA DE PVC SEL 35MM M 55.15 10.94 603.34 19.90 217.71 0.00 0.00 19.90 217.71 36.00% 35.25
04.01.04 TUBERIA DE PVC SEL 25MM M 102.30 34.45 3,524.24 50.00 1,722.50 18.54 638.70 68.54 2,361.20 67.00% 33.76
04.01.05 TUBERIA DE PVC SEL 20MM M 1,326.00 3.08 4,084.08 423.01 1,302.87 465.41 1,433.46 888.42 2,736.33 67.00% 437.58
04.02 INSTALACION DE PLACAS
04.02.01 SALIDA DE TECHO (CENTRO DE LUZ) PTO 146.00 45.07 6,580.22 49.00 2,208.43 49.00 2,208.43 98.00 4,416.86 67.00% 48.00
04.02.02 SALIDA DE PARED (BRAQUETES) PTO 2.00 44.90 89.80 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
04.02.03 INTERRUPTOR SIMPLE PARA EMPOTRADO U 23.00 17.10 393.30 0.00 0.00 0.00 0.00 0.00 0.00% 23.00
04.02.04 INTERRUPTOR DOBLE PARA EMPOTRADO U 17.00 17.27 293.59 0.00 0.00 0.00 0.00 0.00 0.00% 17.00
04.02.05 INTERRUPTOR TRIPLE PARA EMPOTRADO U 2.00 30.20 60.40 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
04.02.06 INTERRUPTOR DE CONMUTACION SIMPLE U 6.00 17.03 102.18 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
04.02.07 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRADO U 258.00 15.66 4,040.28 0.00 0.00 0.00 0.00 0.00 0.00% 258.00

04.02.08 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRADO A PRUEBA DE AGUA U 3.00 40.98 122.94 0.00 0.00 0.00 0.00 0.00 0.00% 3.00

04.03 SALIDA PARA COMUNICACIONES Y SEÑALES


04.03.01 SALIDA PARA TELEFONOS PTO 11.00 163.10 1,794.10 3.00 489.30 4.00 652.40 7.00 1,141.70 64.00% 4.00
04.03.02 SALIDA PARA INTERCOMUNICADOR PTO 18.00 64.16 1,154.88 0.00 0.00 0.00 0.00 0.00 0.00% 18.00
04.03.03 SALIDA DE TECHO DETECTOR DE HUMO PTO 20.00 56.41 1,128.20 8.00 451.28 5.00 282.05 13.00 733.33 65.00% 7.00
04.03.04 SALIDA PARA PULSADOR DE ALARMA CONTRA INCENDIO PTO 3.00 56.41 169.23 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
04.03.05 SALIDA PARA PULSADOR ALARMA AUDIOVISUAL CONTRA INCENDIO PTO 3.00 56.41 169.23 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
04.03.06 SALIDA PARA SIRENA DE ALARMA CONTRA INCENDIO PTO 4.00 56.41 225.64 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
04.03.07 SALIDA PARA CENTRAL DE ALARMA CONTRA INCENDIO PTO 1.00 56.41 56.41 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
04.04 SISTEMA DE DATA Y VOZ
04.04.01 SALIDA DE DATA Y VOZ PTO 97.00 78.52 7,616.44 10.00 785.20 48.00 3,768.96 58.00 4,554.16 60.00% 39.00
04.05 CONDUCTORES Y/O CABLES
04.05.01 CONDUCTOR THW C/CABLE 1X16MM2 M 179.80 9.18 1,650.56 0.00 0.00 0.00 0.00 0.00 0.00% 179.80
04.05.02 CONDUCTOR THW C/CABLE 1X10MM2 M 82.88 4.95 410.26 0.00 0.00 0.00 0.00 0.00 0.00% 82.88
04.05.03 CONDUCTOR THW C/CABLE 1X6MM2 M 149.73 2.59 387.80 0.00 0.00 0.00 0.00 0.00 0.00% 149.73
04.05.04 CONDUCTOR THW C/CABLE 1X4MM2 M 2,498.82 1.98 4,947.66 0.00 0.00 0.00 0.00 0.00 0.00% 2,498.82
04.05.05 CONDUCTOR THW C/CABLE 1X2.5MM3 M 1,419.47 1.49 2,115.01 0.00 0.00 0.00 0.00 0.00 0.00% 1,419.47
04.06 TABLEROS
04.06.01 TABLERO GENERAL 24 POLOS U 1.00 291.26 291.26 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
04.06.02 TABLERO DE DISTRIBUCION 24 POLOS U 3.00 291.26 873.78 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
04.06.03 TABLERO DE DISTRIBUCION 16 POLOS U 4.00 219.84 879.36 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
04.06.04 TABLERO DE DISTRIBUCION 12 POLOS U 2.00 93.98 187.96 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
04.07 LLAVES Y CUCHILLAS
04.07.01 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X15A PZA 15.00 37.15 557.25 0.00 0.00 0.00 0.00 0.00 0.00% 15.00
04.07.02 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X20A PZA 16.00 37.15 594.40 0.00 0.00 0.00 0.00 0.00 0.00% 16.00
04.07.03 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X25A PZA 6.00 37.15 222.90 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
04.07.04 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X30A PZA 5.00 37.15 185.75 0.00 0.00 0.00 0.00 0.00 0.00% 5.00
04.07.05 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X40A PZA 4.00 9.42 37.68 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
04.07.06 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X50A PZA 2.00 51.43 102.86 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
04.07.07 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X80A PZA 1.00 64.04 64.04 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
04.07.08 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X100A PZA 1.00 127.06 127.06 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
04.07.09 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X30A PZA 11.00 57.09 627.99 0.00 0.00 0.00 0.00 0.00 0.00% 11.00
04.07.10 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X60A PZA 2.00 78.10 156.20 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
04.07.11 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X80A PZA 2.00 102.39 204.78 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
04.07.12 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X200A PZA 1.00 731.05 731.05 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
04.08 ARTEFACTOS
04.08.01 LUMINARIA TIPO SPOT LINGH ADOSABLE INC FOCO AHORRADOR U 8.00 43.37 346.96 0.00 0.00 0.00 0.00 0.00 0.00% 8.00

04.08.02 EQUIPO FLUORESCENTE DOBLE DE 2X36W CON PANTALLA ACRILICO REJILLA U 139.00 54.07 7,515.73 0.00 0.00 0.00 0.00 0.00 0.00% 139.00

04.08.03 LUMINARIA TIPO BRAQUETE CON FOCO AHORRADOR DE 18W, PROTECCION A INTERPERIE U 2.00 43.37 86.74 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

04.09 EQUIPOS SISTEMA CONTRA INCENDIO


04.09.01 DIRECTOR DE HUMO IONICO U 20.00 42.84 856.80 0.00 0.00 0.00 0.00 0.00 0.00% 20.00
04.09.02 PULSADOR DE ALARMA CONTRA INCENDIO U 3.00 45.84 137.52 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
04.09.03 ALARMA AUDIO VISUAL CONTRA INCENDIO U 3.00 55.45 166.35 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
04.09.04 SIRENA ALARMA AUDO VISUAL CONTRA INCENDIO U 3.00 51.25 153.75 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
04.09.05 CENTRAL DE ALARMA CONTRA INCENDIO ACI U 1.00 97.46 97.46 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
04.10 SISTEMA DE PUESTA A TIERRA
04.10.01 SISTEMA DE TIERRA A PROTECCION U 1.00 1,205.62 1,205.62 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
04.10.02 PARARRAYOS CON DISPOSITIVOS DE CEBADO JGO 1.00 2,428.72 2,428.72 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
04.11 EQUIPOS ELECTRICOS Y MECANICOS
04.11.01 ELECTROBOMB PARA TANQUE CISTERNA TRIFASICO DE 1HP U 1.00 1,113.24 1,113.24 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

COSTO DIRECTO 1,124,968.87 305,251.54 213,654.71 518,906.25


GASTOS GENERALES % 8.00 89,997.51 24,420.12 17,092.38 41,512.50
UTILIDAD % 5.00 56,248.45 15,262.58 10,682.74 25,945.31
SUBTOTAL 1,271,214.82 344,934.24 241,429.83 586,364.06
FACTOR DE RELACION 868.1400
SUBTOTAL - con Factor de Relacion 1,271,214.82 344,934.24 241,429.83 586,364.06

VALORIZACION DE OBRA Nº 04
(Periodo : Del 01 Mayo al 31 Mayo 2011)

Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVODE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A Valor Referencial (S/.) : 4,572,084.75 con IGV
Plazo de Ejecucion : 240 Dias Calendarios Costos al : February-2010
Supervisor : ING. ANTONIO VALENZUELA SALAS Monto del Contrato (S/.) : 4,572,084.75 con IGV
Residente : ING. PABLO SARMIENTO REYES Factor de Relacion : 1.000

Formula : 006 - PABELLON I Y J


AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
PRECIO
UNIDAD METRADO UNITARIO PARCIAL Metrado Monto Metrado Monto Metrado Monto % Metrado

01 PABELLON I
01.01 ESTRUCTURAS I
01.01.01 OBRAS PRELIMINARES
01.01.01.01 DEMOLICION DE PISOS DE CONCRETO DE 0.10M M2 76.40 6.00 458.40 76.40 458.40 0.00 76.40 458.40 100.00% 0.00
01.01.01.02 DEMOLICION DE CIMIENTO Y SOBRECIMIENTO M3 4.83 72.46 349.98 4.83 349.98 0.00 4.83 349.98 100.00% 0.00
01.01.01.03 DEMOLICION DE MUROS DE LADRILLO M3 37.84 5.28 199.80 37.84 199.80 37.84 199.80 100.00% 0.00
01.01.01.04 DEMOLICION DE ESCALERAS DE CONCRETO M3 1.11 24.14 26.80 1.11 26.80 1.11 26.80 100.00% 0.00
01.01.01.05 RETIRO DE REJAS METALICAS M2 81.52 25.20 2,054.30 0.00 0.00 40.00 1,008.00 40.00 1,008.00 49.00% 41.52
01.01.01.06 RETIRO DE PUERTAS Y VENTANAS M2 150.62 3.20 481.98 150.62 481.98 150.62 481.98 100.00% 0.00
01.01.01.07 ACARREO DE MATERIAL PROVENIENTE DE DEMOLICIONES D=50M M3 150.23 12.36 1,856.84 150.23 1,856.84 150.23 1,856.84 100.00% 0.00
01.01.01.08 ELIMINACION DE DEMOLICIONES CON EQUIPO M3 150.23 9.95 1,494.79 150.23 1,494.79 0.00 150.23 1,494.79 100.00% 0.00
01.01.01.09 TRAZO Y REPLANTEO INICIAL M2 903.91 0.37 334.45 903.91 334.45 0.00 903.91 334.45 100.00% 0.00
01.01.02 MOVIMIENTO DE TIERRAS
01.01.02.01 EXCAVACION PARA ZAPATAS EN TERRENO NORMAL M3 2.59 24.24 62.78 2.59 62.78 0.00 2.59 62.78 100.00% 0.00
01.01.02.02 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 5.63 21.63 121.78 5.63 121.78 0.00 5.63 121.78 100.00% 0.00
01.01.02.03 RELLENO CON MATERIAL PROPIO M3 1.20 42.66 51.19 1.20 51.19 0.00 1.20 51.19 100.00% 0.00
01.01.02.04 RELLENO CON MATERIAL DE PRESTAMO M3 17.64 68.04 1,200.23 17.64 1,200.23 0.00 17.64 1,200.23 100.00% 0.00
01.01.02.05 ACARREO MATERIAL EXCEDENTE D=50M M3 8.37 12.36 103.45 8.37 103.45 0.00 8.37 103.45 100.00% 0.00
01.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO M3 8.37 9.58 80.18 8.37 80.18 0.00 8.37 80.18 100.00% 0.00
01.01.02.07 AFIRMADO DE 3=4" PARA VEREDAS M2 96.25 5.92 569.80 0.00 0.00 48.12 284.87 48.12 284.87 50.00% 48.13

01.01.02.08 NIVELACION, RELLENO Y COMPACTACION CON MATERIAL DE PRESTAMO M2 622.52 7.43 4,625.32 622.52 4,625.33 0.00 0.00 622.52 4,625.33 100.00% 0.00

01.01.03 CONCRETO SIMPLE


01.01.03.01 CONCRETO 1:10+30% P.G. PARA CIMIENTOS CORRIDOS M3 5.11 150.25 767.78 5.11 767.78 0.00 5.11 767.78 100.00% 0.00
01.01.03.02 CONCRETO 1:8 + 25% PM PARA SOBRECIMIENTOS M3 0.72 228.31 164.38 0.72 164.38 0.00 0.72 164.38 100.00% 0.00
01.01.03.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS M2 8.67 21.46 186.06 8.67 186.06 0.00 8.67 186.06 100.00% 0.00
01.01.03.04 SOLADOS PARA ZAPATAS E=4" M2 1.62 17.30 28.03 1.62 28.03 0.00 1.62 28.03 100.00% 0.00
01.01.03.05 FALSO PISO DE 4" DE CONCRETO 1:10 M2 42.64 15.60 665.18 42.64 665.18 0.00 0.00 42.64 665.18 100.00% 0.00
01.01.03.06 PISO DE CONCRETO E=4" FC 175KG/CM2 ACABADO PULIDO 1:2 X 1CM M2 579.87 28.81 16,706.05 579.87 16,706.05 0.00 0.00 579.87 16,706.05 100.00% 0.00
01.01.03.07 VEREDA FC=175 KG/CM2 DE CONCRETO DE 4" M2 96.25 30.76 2,960.65 0.00 0.00 0.00 0.00 0.00 0.00% 96.25
01.01.03.08 ENCOFRADO Y DESENCOFRADO EN VEREDAS M2 6.67 29.44 196.36 0.00 0.00 0.00 0.00 0.00 0.00% 6.67
01.01.03.09 JUNTAS ASFALTICAS EN VEREDAS M 10.00 5.15 51.50 0.00 0.00 0.00 0.00 0.00 0.00% 10.00
01.01.04 CONCRETO ARMADO
01.01.04.01 ZAPATAS
01.01.04.01.01 CONCRETO FC=210 KG/CM2 PARA ZAPATAS M3 1.13 253.19 286.10 1.13 286.10 0.00 1.13 286.10 100.00% 0.00
01.01.04.01.02 ACERO FY=4200 KG/CM2 GRADO 60 EN ZAPATAS KG 20.20 3.41 68.88 20.20 68.88 0.00 20.20 68.88 100.00% 0.00
01.01.04.02 COLUMNAS
01.01.04.02.01 CONCRETO FC=210 KG/CM2 PARA COLUMNAS M3 0.62 305.86 189.63 0.62 189.63 0.00 0.62 189.63 100.00% 0.00
01.01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 9.90 45.92 454.61 9.90 454.61 0.00 9.90 454.61 100.00% 0.00
01.01.04.02.03 ACERO FY=4200 KG/CM2 PARA COLUMNAS KG 195.70 3.41 667.34 195.70 667.34 0.00 195.70 667.34 100.00% 0.00
01.01.04.03 VIGAS
01.01.04.03.01 CONCRETO FC=210 KG/CM2 PARA VIGAS M3 0.31 267.17 82.82 0.31 82.82 0.00 0.31 82.82 100.00% 0.00
01.01.04.03.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS M2 2.81 47.87 134.51 2.81 134.51 0.00 2.81 134.51 100.00% 0.00
01.01.04.03.03 ACERO FY=4200 KG/CM2 PARA VIGAS KG 79.16 3.37 266.77 79.16 266.77 0.00 79.16 266.77 100.00% 0.00
01.01.04.04 ESCALERAS DE CONCRETO ARMADO
01.01.04.04.01 CONCRETO FC=210 KG/CM2 PARA ESCALERAS M3 2.09 305.13 637.72 2.09 637.72 0.00 2.09 637.72 100.00% 0.00
01.01.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESCALERAS M2 12.56 86.74 1,089.45 12.56 1,089.45 0.00 12.56 1,089.45 100.00% 0.00
01.01.04.04.03 ACERO FY=4200 KG/CM2 PARA ESCALERAS KG 199.41 3.40 677.99 199.41 677.99 0.00 199.41 677.99 100.00% 0.00
01.01.04.05 LOSA MACIZA E=20CM
01.01.04.05.01 CONCRETO FC=210 KG/CM2 PARA LOSA MACIZA M3 1.53 280.14 428.61 1.53 428.61 0.00 1.53 428.61 100.00% 0.00
01.01.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZA M2 7.67 27.83 213.46 7.67 213.46 0.00 7.67 213.46 100.00% 0.00
01.01.04.05.03 ACERO FY=4200 KG/CM2 PARA LOSA MACIZAS KG 93.45 3.40 317.73 93.45 317.73 0.00 93.45 317.73 100.00% 0.00
01.01.04.06 ESTRUCTURAS METALICAS Y COBERTURA
01.01.04.06.01 COBERTURA TECHO ETERNIT GRAN ONDA M2 256.52 33.98 8,716.55 0.00 0.00 0.00 0.00 0.00 0.00% 256.52
01.01.04.06.02 CUMBRETA PARA TECHO GRAN ONDA M 25.70 38.27 983.54 0.00 0.00 0.00 0.00 0.00 0.00% 25.70
01.01.04.06.03 CANALETA DE PLANCHA GALVANIZADA M 57.90 24.16 1,398.86 0.00 0.00 0.00 0.00 0.00 0.00% 57.90
01.02 ARQUITECTURA I
01.02.01 MUROS Y TABIQUES
01.02.01.01 MURO DE SOGA LADRILLO CORRIENTE CON CEMENTO-ARENA M2 41.64 34.94 1,454.90 41.64 1,454.90 0.00 41.64 1,454.90 100.00% 0.00
01.02.01.02 MURO DE CABEZA LADRILLO CORRIENTE CON CEMENTO-ARENA M2 4.10 64.30 263.63 4.10 263.63 0.00 4.10 263.63 100.00% 0.00
01.02.02 REVOQUES ENLUCIDOS Y MOLDURAS
01.02.02.01 TARRAJEO PRIMARIO RAYADO CON CEMENTO ARENA 1:5 E=1.5CM M2 8.78 13.24 116.25 8.78 116.25 0.00 8.78 116.25 100.00% 0.00
01.02.02.02 TARRAJEO EN INTERIORES ACABADO CON CEMENTO ARENA 1:5 M2 633.82 10.71 6,788.21 633.82 6,788.21 0.00 0.00 633.82 6,788.21 100.00% 0.00
01.02.02.03 TARRAJEO EN EXTERIORES CON CEMENTO ARENA 1:5 M2 333.31 19.63 6,542.88 333.31 6,542.88 0.00 0.00 333.31 6,542.88 100.00% 0.00
01.02.02.04 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA 1:5 M2 171.32 22.45 3,846.13 171.32 3,846.13 0.00 0.00 171.32 3,846.13 100.00% 0.00
01.02.02.05 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO-ARENA 1:5 M2 32.66 28.68 936.69 32.66 936.69 0.00 0.00 32.66 936.69 100.00% 0.00
01.02.02.06 VESTIDURA DE DERRAMES M 169.86 9.09 1,544.03 169.86 1,544.03 0.00 0.00 169.86 1,544.03 100.00% 0.00
01.02.02.07 VESTIDURA DE FONDO ESCALERA CON CEMENTO-ARENA M2 6.70 23.58 157.99 6.70 157.99 0.00 0.00 6.70 157.99 100.00% 0.00
01.02.02.08 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS M 22.10 20.23 447.08 0.00 0.00 0.00 0.00 0.00 0.00% 22.10
01.02.03 CIELORRASOS
01.02.03.01 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA MEZCLA 1:5 M2 45.05 33.63 1,515.03 0.00 0.00 0.00 0.00 0.00 0.00% 45.05
01.02.04 PISOS Y PAVIMENTOS
01.02.04.01 CONTRAPISO DE 48MM M2 92.89 21.13 1,962.77 92.89 1,962.77 0.00 0.00 92.89 1,962.77 100.00% 0.00
01.02.04.02 PISO CERAMICO DE 30X30 CM M2 90.47 32.68 2,956.56 0.00 0.00 0.00 0.00 0.00 0.00% 90.47
01.02.04.03 PISO CERAMICO DE 30X30 CM ANTIDESLIZANTE M2 2.42 32.68 79.09 0.00 0.00 0.00 0.00 0.00 0.00% 2.42
01.02.05 CONTRAZOCALOS
01.02.05.01 CONTRAZOCALO EN INTERIORES DE CERAMICO H=10CM M 74.94 7.57 567.30 67.45 510.57 0.00 0.00 67.45 510.57 90.00% 7.49
01.02.06 ZOCALOS
01.02.06.01 ZOCALO DE CERAMICA BLANCA DE 20X30CM DE 1RA M2 8.78 33.65 295.45 0.00 0.00 0.00 0.00 0.00 0.00% 8.78
01.02.06.02 ZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2CM H=60CM M 38.01 17.65 670.88 32.31 570.25 0.00 0.00 32.31 570.25 85.00% 5.70

01.02.06.03 ZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2CM H=1.00CM M 137.51 23.53 3,235.61 0.00 0.00 0.00 0.00 0.00 0.00% 137.51

01.02.07 CARPINTERIA DE MADERA


01.02.07.01 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5MM DE TORNILLO M2 6.83 160.00 1,092.80 0.00 0.00 0.00 0.00 0.00 0.00% 6.83
01.02.08 CARPINTERIA METALICA
01.02.08.01 PUERTA METALICA LAC 1/16" CON MARCO 2"X2"X1/4" Y REFUERZOS M2 49.25 504.08 24,825.94 0.00 0.00 0.00 0.00 0.00 0.00% 49.25
01.02.08.02 PUERTA METALICA ENRROLLABLE (INCLUYE COLOCACION) M2 19.95 160.00 3,192.00 0.00 0.00 0.00 0.00 0.00 0.00% 19.95
01.02.08.03 VENTANA DE FIERRO PERFIL DE 1"X18" FIJA MARCO T DE 1" M2 58.89 99.15 5,838.94 0.00 0.00 0.00 0.00 0.00 0.00% 58.89
01.02.08.04 BARANDA METALICA DE TUBOS M 11.25 36.11 406.24 0.00 0.00 0.00 0.00 0.00 0.00% 11.25
01.02.09 CERRAJERIA
01.02.09.01 CERRADURA FORTE DE 3 GOLPES U 17.00 77.28 1,313.76 0.00 0.00 0.00 0.00 0.00 0.00% 17.00
01.02.09.02 CERRADURA TIPO PERILLA U 1.00 73.92 73.92 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.02.10 VIDRIOS, CRISTALES Y SIMILARES
01.02.10.01 VIDRIOS DOBLES NACIONALES P2 633.70 3.69 2,338.35 0.00 0.00 0.00 0.00 0.00 0.00% 633.70
01.02.11 PINTURA
01.02.11.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS M2 633.82 4.53 2,871.20 0.00 0.00 0.00 0.00 0.00 0.00% 633.82
01.02.11.02 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 333.31 5.47 1,823.21 0.00 0.00 0.00 0.00 0.00 0.00% 333.31
01.02.11.03 PINTURA LATEX EN SUPERFICIE DE COLUMNAS, 2 MANOS M2 171.32 5.17 885.72 0.00 0.00 0.00 0.00 0.00 0.00% 171.32
01.02.11.04 PINTURA LATEX EN SUPERFICIE DE VIGAS M2 32.66 5.43 177.34 0.00 0.00 0.00 0.00 0.00 0.00% 32.66
01.02.11.05 PINTURA LATEX EN DERRAMES DE VIGAS M2 169.86 3.29 558.84 0.00 0.00 0.00 0.00 0.00 0.00% 169.86
01.02.11.06 PINTURA LATEX EN CIELORASO DE VIGAS M2 45.05 4.71 212.19 0.00 0.00 0.00 0.00 0.00 0.00% 45.05
01.02.11.07 PINTURA BARNIZ CON CARPINTERIA DE MADERA M2 13.65 8.92 121.76 0.00 0.00 0.00 0.00 0.00 0.00% 13.65
01.02.11.08 PINTURA EN CARPINTERIA METALICA CON ANTICORROSIVO Y ESMALTE M2 242.97 7.56 1,836.85 0.00 0.00 0.00 0.00 0.00 0.00% 242.97
01.02.11.09 PINTURA ESMALTE EN ZOCALOS M2 175.52 5.47 960.09 0.00 0.00 0.00 0.00 0.00 0.00% 175.52
01.02.12 APARATOS Y ACCESORIOS SANITARIOS
01.02.12.01 INODORO C/BLANCO TANQUE BAJO U 1.00 75.63 75.63 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.02.12.02 LAVATORIO DE PARED BLANCO 1 LLAVE PZA 1.00 75.36 75.36 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.02.12.03 PAPELERA DE LOZA BLANCA DE 13X15 CM PZA 1.00 25.21 25.21 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.02.13 OTROS
01.02.13.01 LIMPIEZA FINAL M2 562.75 0.36 202.59 422.06 151.94 0.00 0.00 422.06 151.94 75.00% 140.69
01.03 INSTALACIONES SANITARIAS I
01.03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.03.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" PTO 4.00 55.86 223.44 4.00 223.44 0.00 4.00 223.44 100.00% 0.00
01.03.01.02 RED DE DISTRIBUCIÓN TUBERIA DE 1/2" PVC-SAP M 24.80 7.97 197.66 24.80 197.66 0.00 24.80 197.66 100.00% 0.00
01.03.01.03 CODO PVC SAP 1/2" U 11.00 8.51 93.61 11.00 93.61 0.00 11.00 93.61 100.00% 0.00
01.03.01.04 CODO PVC SAP 1/2"X91 U 3.00 10.34 31.02 3.00 31.02 0.00 3.00 31.02 100.00% 0.00
01.03.01.05 CODO PVC SAP 3/4"X90 U 1.00 10.93 10.93 0.00 0.00 1.00 10.93 1.00 10.93 100.00% 0.00
01.03.01.06 REDUCCIONES PVC-SAP 3/4" A 1/2" U 1.00 13.45 13.45 0.00 0.00 1.00 13.45 1.00 13.45 100.00% 0.00
01.03.01.07 VALVULA COMPUERTA DE BRONCE 1/2" U 2.00 42.52 85.04 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.03.02 SISTEMA DE DESAGUE
01.03.02.01 SALIDA DE DESAGUE DE 3" PTO 7.00 41.95 293.65 0.00 0.00 0.00 0.00 0.00 0.00% 7.00
01.03.02.02 SALIDA DE DESAGUE DE 4" PTO 3.00 43.36 130.08 3.00 130.08 0.00 3.00 130.08 100.00% 0.00
01.03.02.03 SALIDA DE DESAGUE DE 2" PTO 5.00 37.67 188.35 5.00 188.35 0.00 5.00 188.35 100.00% 0.00
01.03.02.04 SALIDA DE DESAGUE DE VENTILACION DE 2" PTO 1.00 35.02 35.02 1.00 35.02 0.00 1.00 35.02 100.00% 0.00
01.03.02.05 EXCAVACION DE ZANJAS PARA TUBERIAS M3 37.00 8.65 320.05 37.00 320.05 0.00 37.00 320.05 100.00% 0.00
01.03.02.06 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 37.00 47.22 1,747.14 37.00 1,747.14 0.00 37.00 1,747.14 100.00% 0.00
01.03.02.07 RELLENO COMPACTADO MANUAL MATERIAL PROPIO M3 37.00 35.39 1,309.43 37.00 1,309.43 0.00 37.00 1,309.43 100.00% 0.00
01.03.02.08 TUBERIA DE PVC SAL 4" M 28.70 18.55 532.39 28.70 532.39 0.00 0.00 28.70 532.39 100.00% 0.00
01.03.02.09 TUBERIA DE PVC SAL 3" M 54.25 18.04 978.67 0.00 0.00 0.00 0.00 0.00 0.00% 54.25
01.03.02.10 TUBERIA DE PVC SAL 2" M 10.70 17.39 186.07 10.70 186.07 0.00 0.00 10.70 186.07 100.00% 0.00
01.03.02.11 REGISTRO DE BRONCE DE 4" PZA 1.00 45.75 45.75 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.03.02.12 REGISTRO DE BRONCE DE 2" U 1.00 48.23 48.23 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.03.02.13 CAJA DE REGISTRO DE DESAGUE 12"X24" CON TAPA DE FºFº U 1.00 100.45 100.45 1.00 100.45 0.00 0.00 1.00 100.45 100.00% 0.00
01.03.02.14 YEE PVC SAL 4" U 2.00 16.67 33.34 2.00 33.34 0.00 2.00 33.34 100.00% 0.00
01.03.02.15 YEE PVC SAL 2" U 1.00 11.92 11.92 1.00 11.92 0.00 1.00 11.92 100.00% 0.00
01.03.02.16 YEE PVC SAL SP RAMAL CON REDUCCION DE 4" A 2" U 3.00 12.05 36.15 3.00 36.15 0.00 3.00 36.15 100.00% 0.00
01.03.02.17 CODO PVC SAL 2"X45º U 2.00 12.13 24.26 2.00 24.26 0.00 2.00 24.26 100.00% 0.00
01.03.02.18 CODO PVC SAL 2"X90º U 7.00 11.92 83.44 7.00 83.44 0.00 7.00 83.44 100.00% 0.00
01.03.02.19 CODO PVC SAL 3"X90º U 21.00 12.08 253.68 0.00 0.00 0.00 0.00 0.00 0.00% 21.00
01.03.02.20 CODO PVC SAL 4"X45º U 1.00 21.78 21.78 1.00 21.78 0.00 1.00 21.78 100.00% 0.00
01.03.02.21 CODO PVC SAL 4"X90º U 3.00 16.77 50.31 3.00 50.31 0.00 3.00 50.31 100.00% 0.00
01.03.02.22 TEE PVC-SAP 4" U 2.00 13.82 27.64 2.00 27.64 0.00 2.00 27.64 100.00% 0.00
01.03.02.23 TRAMPA P DE PVC SAL PARA DESAGUE DE 2" U 1.00 29.60 29.60 1.00 29.60 0.00 1.00 29.60 100.00% 0.00
01.03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS
01.03.03.01 COLOCACION DE APARATOS SANITARIOS PZA 2.00 50.80 101.60 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.03.03.02 COLOCACION DE ACCESORIOS SANITARIOS PZA 1.00 25.40 25.40 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.04 INSTALACIONES ELECTRICAS I
01.04.01 TUBERIA Y CANALIZACION
01.04.01.01 CANALIZACION PARA DUCTO EN PARED Y PISO M 290.93 2.70 785.51 269.67 728.11 21.26 57.40 290.93 785.51 100.00% 0.00
01.04.01.02 TUBERIA DE PVC SEL 35MM M 20.85 16.92 352.78 18.00 304.56 2.85 48.22 20.85 352.78 100.00% 0.00
01.04.01.03 TUBERIA DE PVC SEL 25MM M 17.24 34.45 593.92 17.24 593.92 0.00 0.00 17.24 593.92 100.00% 0.00
01.04.01.04 TUBERIA DE PVC SEL 20MM M 202.74 3.08 624.44 202.74 624.44 0.00 0.00 202.74 624.44 100.00% 0.00
01.04.02 CAJAS DE PASE
01.04.02.01 CAJAS DE PASE DE 4"X4" U 10.00 19.41 194.10 5.00 97.05 0.00 0.00 5.00 97.05 50.00% 5.00
01.04.03 CONDUCTORES
01.04.03.01 CONDUCTOR THW C/CABLE 1X10MM2 M 83.40 4.95 412.83 0.00 0.00 0.00 0.00 0.00 0.00% 83.40
01.04.03.02 CONDUCTOR THW C/CABLE 1X6MM2 M 24.00 2.59 62.16 0.00 0.00 0.00 0.00 0.00 0.00% 24.00
01.04.03.03 CONDUCTOR THW C/CABLE 1X4MM2 M 425.61 1.98 842.71 0.00 0.00 0.00 0.00 0.00 0.00% 425.61
01.04.03.04 CONDUCTOR THW C/CABLE 1X2.5MM3 M 320.49 1.49 477.53 0.00 0.00 0.00 0.00 0.00 0.00% 320.49
01.04.04 INSTALACION DE PLACAS
01.04.04.01 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRADO U 23.00 15.66 360.18 0.00 0.00 0.00 0.00 0.00 0.00% 23.00
01.04.04.02 INTERRUPTOR SIMPLE PARA EMPOTRADO U 11.00 17.10 188.10 0.00 0.00 0.00 0.00 0.00 0.00% 11.00
01.04.04.03 INTERRUPTOR TRIPLE PARA EMPOTRADO U 2.00 30.20 60.40 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.04.05 INSTALACION DE ARTEFACTOS

01.04.05.01 EQUIPO FLUORESCENTE DOBLE DE 2X36W CON PATALLA ACRILICO REJILLA U 13.00 54.07 702.91 0.00 0.00 0.00 0.00 0.00 0.00% 13.00

01.04.05.02 EQUIPO FLUORESCENTE DOBLE DE 2X36W COLGANTE U 16.00 66.78 1,068.48 0.00 0.00 0.00 0.00 0.00 0.00% 16.00

01.04.05.03 FLUORESCENTE CIRCULAR DE 32W INC BASE ADOSABLE DE ALUMINIO+ACCES U 1.00 62.53 62.53 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

01.04.06 TABLEROS
01.04.06.01 TABLERO GENERAL 24 POLOS U 1.00 291.26 291.26 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.04.06.02 TABLERO DE DISTRIBUCION 24 POLOS U 2.00 291.26 582.52 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.04.06.03 TABLERO DE DISTRIBUCION 12 POLOS U 1.00 93.98 93.98 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01.04.07 LLAVES TERMOMAGNETICA
01.04.07.01 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X20A PZA 3.00 37.15 111.45 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
01.04.07.02 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X25A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.04.07.03 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X30A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01.04.07.04 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X30A PZA 9.00 57.09 513.81 0.00 0.00 0.00 0.00 0.00 0.00% 9.00
01.04.07.05 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X50A PZA 6.00 78.10 468.60 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
01.04.07.06 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X60A PZA 3.00 78.10 234.30 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
02 PABELLON "J"
02.01 ESTRUCTURAS J
02.01.01 OBRAS PRELIMINARES
02.01.01.01 DEMOLICION DE PISOS DE CONCRETO DE 0.10M M2 649.07 6.00 3,894.42 649.07 3,894.42 0.00 0.00 649.07 3,894.42 100.00% 0.00
02.01.01.02 DEMOLICION DE MUROS DE LADRILLO M3 5.27 5.28 27.83 5.27 27.83 0.00 5.27 27.83 100.00% 0.00
02.01.01.03 DEMOLICION DE ESCALERAS DE CONCRETO M3 1.89 24.14 45.62 1.89 45.63 0.00 1.89 45.62 100.00% 0.00
02.01.01.04 DESMONTAJE DE COBERTURAS DE CALAMINA M2 650.27 3.65 2,373.49 563.65 2,057.32 0.00 0.00 563.65 2,057.32 87.00% 86.62
02.01.01.05 RETIRO DE TIJERALES DE MADERA U 3.00 55.23 165.69 3.00 165.69 0.00 3.00 165.69 100.00% 0.00
02.01.01.06 RETIRO DE PUERTAS Y VENTANAS M2 110.41 3.20 353.31 110.41 353.31 0.00 110.41 353.31 100.00% 0.00
02.01.01.07 RETIRO DE ESCALERA METALICA U 1.00 361.00 361.00 1.00 361.00 0.00 1.00 361.00 100.00% 0.00
02.01.01.08 ACARREO MATERIAL PROVENIENTE DE DEMOLICIONES D=50M M3 87.72 12.36 1,084.22 87.72 1,084.22 0.00 0.00 87.72 1,084.22 100.00% 0.00
02.01.01.09 ELIMINACION DE DEMOLICIONES M3 87.72 9.95 872.81 87.72 872.82 0.00 0.00 87.72 872.81 100.00% 0.00
02.01.01.10 TRAZO, NIVELACION Y REPLANTEO M2 715.30 1.78 1,273.23 715.30 1,273.24 0.00 715.30 1,273.23 100.00% 0.00
02.01.02 MOVIMIENTO DE TIERRAS
02.01.02.01 EXCAVACION PARA ZAPATAS EN TERRENO NORMAL M3 31.82 24.24 771.32 31.82 771.32 0.00 31.82 771.32 100.00% 0.00
02.01.02.02 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 7.85 21.63 169.80 7.85 169.79 0.00 7.85 169.80 100.00% 0.00
02.01.02.03 RELLENO CON MATERIAL PROPIO M3 0.89 42.66 37.97 0.89 37.97 0.00 0.89 37.97 100.00% 0.00
02.01.02.04 ACARREO MATERIAL EXCEDENTE D=50M M3 46.50 12.36 574.74 46.50 574.74 0.00 46.50 574.74 100.00% 0.00
02.01.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO M3 46.50 9.58 445.47 46.50 445.47 0.00 46.50 445.47 100.00% 0.00
02.01.02.06 AFIRMADO DE 3=4" PARA VEREDAS M2 129.88 5.92 768.89 0.00 0.00 129.88 768.89 129.88 768.89 100.00% 0.00

02.01.02.07 NIVELACION, RELLENO Y COMPACTACION CON MATERIAL DE PRESTAMO M2 519.19 7.43 3,857.58 147.53 1,096.15 371.66 2,761.43 519.19 3,857.58 100.00% 0.00

02.01.03 CONCRETO SIMPLE


02.01.03.01 CONCRETO 1:10+30% P.G. PARA CIMIENTOS CORRIDOS M3 5.32 150.25 799.33 5.32 799.33 0.00 5.32 799.33 100.00% 0.00
02.01.03.02 CONCRETO 1:8 + 25% PM PARA SOBRECIMIENTOS M3 1.88 228.31 429.22 1.88 429.22 0.00 1.88 429.22 100.00% 0.00
02.01.03.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS M2 36.52 21.46 783.72 36.52 783.72 0.00 36.52 783.72 100.00% 0.00
02.01.03.04 SOLADOS PARA ZAPATAS E=4" M2 18.72 17.30 323.86 18.72 323.85 0.00 18.72 323.86 100.00% 0.00
02.01.03.05 FALSO PISO DE 4" DE CONCRETO 1:10 M2 277.41 15.60 4,327.60 277.41 4,327.60 0.00 0.00 277.41 4,327.60 100.00% 0.00
02.01.03.06 PISO DE CONCRETO E=4" FC 175KG/CM2 ACABADO PULIDO 1:2 X 1CM M2 371.66 28.81 10,707.52 371.66 10,707.52 0.00 0.00 371.66 10,707.52 100.00% 0.00
02.01.03.07 VEREDA FC=175 KG/CM2 DE CONCRETO DE 4" M2 129.88 30.76 3,995.11 0.00 0.00 110.00 3,383.60 110.00 3,383.60 85.00% 19.88
02.01.03.08 ENCOFRADO Y DESENCOFRADO EN VEREDAS M2 12.01 29.44 353.57 0.00 0.00 10.21 300.58 10.21 300.58 85.00% 1.80
02.01.03.09 JUNTAS ASFALTICAS EN VEREDAS M 26.10 5.15 134.42 0.00 0.00 0.00 0.00 0.00 0.00% 26.10
02.01.04 CONCRETO ARMADO
02.01.04.01 ZAPATAS
02.01.04.01.01 CONCRETO FC=210 KG/CM2 PARA ZAPATAS M3 13.10 253.19 3,316.79 13.10 3,316.79 0.00 13.10 3,316.79 100.00% 0.00
02.01.04.01.02 ACERO FY=4200 KG/CM2 GRADO 60 EN ZAPATAS KG 192.54 3.41 656.56 192.54 656.56 0.00 192.54 656.56 100.00% 0.00
02.01.04.02 COLUMNAS
02.01.04.02.01 CONCRETO FC=210 KG/CM2 PARA COLUMNAS M3 3.98 305.86 1,217.32 3.98 1,217.32 0.00 3.98 1,217.32 100.00% 0.00
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 87.75 45.92 4,029.48 87.75 4,029.48 0.00 87.75 4,029.48 100.00% 0.00
02.01.04.02.03 ACERO FY=4200 KG/CM2 PARA COLUMNAS KG 1,589.46 3.41 5,420.06 1,589.46 5,420.06 0.00 1,589.46 5,420.06 100.00% 0.00
02.01.04.03 VIGAS
02.01.04.03.01 CONCRETO FC=210 KG/CM2 PARA VIGAS M3 2.13 267.17 569.07 2.13 569.07 0.00 2.13 569.07 100.00% 0.00
02.01.04.03.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS M2 20.40 47.87 976.55 20.40 976.55 0.00 20.40 976.55 100.00% 0.00
02.01.04.03.03 ACERO FY=4200 KG/CM2 PARA VIGAS KG 742.70 3.37 2,502.90 742.70 2,502.90 0.00 742.70 2,502.90 100.00% 0.00
02.01.04.04 ESCALERAS DE CONCRETO ARMADO
02.02.04.04.01 CONCRETO FC=210 KG/CM2 PARA ESCALERAS M3 1.65 305.13 503.46 1.65 503.46 0.00 1.65 503.46 100.00% 0.00
02.02.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESCALERAS M2 12.04 86.74 1,044.35 12.04 1,044.35 0.00 12.04 1,044.35 100.00% 0.00
02.02.04.04.03 ACERO FY=4200 KG/CM2 PARA ESCALERAS KG 148.73 3.40 505.68 148.73 505.68 0.00 148.73 505.68 100.00% 0.00
02.01.04.05 ESTRUCTURAS METALICAS Y COBERTURA
02.01.04.05.01 TIJERALES DE MADERA TIPO 1, L=14.42M U 2.00 2,121.32 4,242.64 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02.01.04.05.02 TIJERALES DE MADERA TIPO II, L=15.40M U 2.00 2,259.34 4,518.68 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.01.04.05.03 TIJERALES DE MADERA TIPO III, L=6.05M U 3.00 1,016.34 3,049.02 0.00 0.00 0.00 0.00 0.00 0.00% 3.00

02.01.04.05.04 CORREAS DE MADERA DE 2X3" M 432.90 6.83 2,956.71 0.00 0.00 0.00 0.00 0.00 0.00% 432.90

02.01.04.05.05 FRISOS DE MADERA DE 1 X 2" M 31.14 11.98 373.06 0.00 0.00 0.00 0.00 0.00 0.00% 31.14

02.01.04.05.06 COBERTURA FIBRAFORTE TIPO TEJA ANDINA M2 203.60 23.53 4,790.71 0.00 0.00 0.00 0.00 0.00 0.00% 203.60

02.01.04.05.07 COBERTURA, TECHO ETERNIT GRAN-ONDA M2 130.50 33.98 4,434.39 0.00 0.00 0.00 0.00 0.00 0.00% 130.50

02.01.04.05.08 CUMBRERA PARA TEJA ANDINA M 31.14 20.25 630.59 0.00 0.00 0.00 0.00 0.00 0.00% 31.14

02.01.04.05.09 CUMBRERA PARA TECHO GRAN ONDA M 30.50 38.27 1,167.24 0.00 0.00 0.00 0.00 0.00 0.00% 30.50

02.01.04.05.10 CANALETA DE PLANCHA GALVANIZADA M 91.50 24.16 2,210.64 0.00 0.00 0.00 0.00 0.00 0.00% 91.50

02.02 ARQUITECTURA I

02.02.01 MUROS Y TABIQUES

02.02.01.01 MURO DE SOGA LADRILLO CORRIENTE ARTESANL SOGA 13 X24X8CM CEMENTO ARENA M2 81.15 37.36 3,031.76 81.15 3,031.76 0.00 81.15 3,031.76 100.00% 0.00

02.02.01.02 MURO DE LADRILLO CORRIENTE ARETSANAK CABEZA 13X24X8CM CEMENTO ARENA 1:5 M2 16.35 60.62 991.14 16.35 991.14 0.00 16.35 991.14 100.00% 0.00

02.02.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.02.01 TARRAJEO PRIMARIO RAYADO CON CEMENTO ARENA 1:5 E=1.5CM M2 9.30 13.24 123.13 9.30 123.13 0.00 9.30 123.13 100.00% 0.00

02.02.02.02 TARRAJEO EN INTERIORES ACABADO CON CEMENTO ARENA 1:5 M2 647.93 10.71 6,939.33 647.93 6,939.33 0.00 0.00 647.93 6,939.33 100.00% 0.00

02.02.02.03 TARRAJEO EN EXTERIORES CON CEMENTO ARENA 1:5 M2 238.05 19.63 4,672.92 238.05 4,672.92 0.00 0.00 238.05 4,672.92 100.00% 0.00

02.02.02.04 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA 1:5 M2 61.50 22.45 1,380.68 61.50 1,380.68 0.00 0.00 61.50 1,380.68 100.00% 0.00
02.02.02.05 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO-ARENA 1:5 M2 20.40 28.68 585.07 20.40 585.07 0.00 20.40 585.07 100.00% 0.00

02.02.02.06 VESTIDURA DE DERRAMES M 110.38 9.09 1,003.35 102.11 928.18 8.27 75.17 110.38 1,003.35 100.00% 0.00

02.02.02.07 VESTIDURA DE FONDO ESCALERA CON CEMENTO-ARENA M2 5.25 23.58 123.80 2.90 68.38 2.35 55.41 5.25 123.80 100.00% 0.00

02.02.02.08 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS M 22.50 20.23 455.18 0.00 0.00 0.00 0.00 0.00 0.00% 22.50

02.02.03 CIELORRASOS

02.02.03.01 CIELORRASO CON TRIPLAY DE 4MM C/ENTRAMADO DE MADERA MAS TAPAJUNTA M2 81.19 34.84 2,828.66 0.00 0.00 0.00 0.00 0.00 0.00% 81.19

02.02.04 PISOS Y PAVIMENTOS

02.02.04.01 CONTRAPISO DE 48MM M2 131.87 21.13 2,786.41 131.87 2,786.41 0.00 131.87 2,786.41 100.00% 0.00

02.02.04.02 PISO CERAMICO DE 30X30 CM M2 129.50 32.68 4,232.06 0.00 0.00 0.00 0.00 0.00 0.00% 129.50

02.02.04.03 PISO CERAMICO DE 30X30 CM ANTIDESLIZANTE M2 2.37 32.68 77.45 0.00 0.00 0.00 0.00 0.00 0.00% 2.37

02.02.04.04 PISO DE CONCRETO , ACABADO PULIDO 1:2 X 1CM M2 18.03 12.91 232.77 18.03 232.77 0.00 18.03 232.77 100.00% 0.00

02.02.05 CONTRAZOCALOS

02.02.05.01 CONTRAZOCALO EN INTERIORES DE CERAMICO H=10CM M 90.69 7.57 686.52 0.00 0.00 0.00 0.00 0.00 0.00% 90.69

02.02.05.02 CONTRAZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2 CM H=30CM M 305.19 5.96 1,818.93 305.19 1,818.93 0.00 0.00 305.19 1,818.93 100.00% 0.00

02.02.06 ZOCALOS

02.02.06.01 ZOCALO DE CERAMICA BLANCA DE 20X30CM DE 1RA M2 9.30 33.65 312.95 0.00 0.00 0.00 0.00 0.00 0.00% 9.30

02.02.07 CARPINTERIA DE MADERA

02.02.07.01 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5MM DE CEDRO M2 25.65 179.20 4,596.48 0.00 0.00 0.00 0.00 0.00 0.00% 25.65

02.02.08 CARPINTERIA METALICA

02.02.08.01 PUERTA METALICA ENRROLLABLE M2 13.90 160.00 2,224.00 0.00 0.00 0.00 0.00 0.00 0.00% 13.90

02.02.08.02 VENTANA DE FIERRO PERFIL DE 1"X18" FIJA MARCO T DE 1" M2 70.86 99.15 7,025.77 0.00 0.00 0.00 0.00 0.00 0.00% 70.86

02.02.08.03 BARANDA METALICA DE 4" M 7.00 36.11 252.77 0.00 0.00 0.00 0.00 0.00 0.00% 7.00

02.02.09 CERRAJERIA

02.02.09.01 CERRADURA FORTE DE 3 GOLPES U 10.00 77.28 772.80 0.00 0.00 0.00 0.00 0.00 0.00% 10.00

02.02.09.02 CERRADURA TIPO PERILLA U 2.00 73.92 147.84 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.02.10 VIDRIOS, CRISTALES Y SIMILARES

02.02.10.01 VIDRIOS DOBLES NACIONALES P2 765.07 3.69 2,823.11 0.00 0.00 0.00 0.00 0.00 0.00% 765.07

02.02.11 PINTURA

02.02.11.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS M2 647.93 4.53 2,935.12 0.00 0.00 0.00 0.00 0.00 0.00% 647.93

02.02.11.02 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 238.05 5.47 1,302.13 0.00 0.00 0.00 0.00 0.00 0.00% 238.05

02.02.11.03 PINTURA LATEX EN SUPERFICIE DE COLUMNAS, 2 MANOS M2 61.50 5.17 317.96 0.00 0.00 0.00 0.00 0.00 0.00% 61.50

02.02.11.04 PINTURA LATEX EN SUPERFICIE DE VIGAS M2 20.40 5.43 110.77 0.00 0.00 0.00 0.00 0.00 0.00% 20.40

02.02.11.05 PINTURA LATEX EN DERRAMES 2 MANOS M2 110.38 3.29 363.15 0.00 0.00 0.00 0.00 0.00 0.00% 110.38

02.02.11.06 PINTURA BARNIZ CON CARPINTERIA DE MADERA M2 106.84 8.92 953.01 0.00 0.00 0.00 0.00 0.00 0.00% 106.84

02.02.11.07 PINTURA EN CARPINTERIA METALICA CON ANTICORROSIVO Y ESMALTE M2 84.76 7.56 640.79 0.00 0.00 0.00 0.00 0.00 0.00% 84.76

02.02.11.08 PINTURA ESMALTE EN ZOCALOS M 305.19 4.10 1,251.28 0.00 0.00 0.00 0.00 0.00 0.00% 305.19

02.02.12 APARATOS Y ACCESORIOS SANITARIOS

02.02.12.01 INODORO C/BLANCO TANQUE BAJO U 1.00 75.63 75.63 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.02.12.02 LAVATORIO DE LOSA VITRIFICADA U 1.00 75.36 75.36 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.02.12.03 PAPELERA DE LOZA BLANCA DE 13X15 CM PZA 1.00 25.21 25.21 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.02.13 OTROS

02.02.13.01 LIMPIEZA FINAL M2 715.30 0.36 257.51 536.48 193.13 0.00 0.00 536.48 193.13 75.00% 178.83

02.03 INSTALACIONES SANITARIAS "J"


02.03.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO

02.03.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" PTO 3.00 55.86 167.58 3.00 167.58 0.00 3.00 167.58 100.00% 0.00

02.03.01.02 RED DE DISTRIBUCIÓN TUBERIA DE 1/2" PVC-SAP M 8.56 7.97 68.22 8.56 68.22 0.00 8.56 68.22 100.00% 0.00

02.03.01.03 RED DE DISTRIBUCIÓN TUBERIA DE 3/4" PVC-SAP M 8.56 8.28 70.88 0.00 0.00 0.00 0.00 0.00 0.00% 8.56

02.03.01.04 CODO PVC SAP 1/2"X90 U 3.00 8.51 25.53 3.00 25.53 0.00 3.00 25.53 100.00% 0.00

02.03.01.05 TEE PVC - SAP 3/4" U 2.00 11.63 23.26 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.03.01.06 VALVULA COMPUERTA DE BRONCE 3/4" U 1.00 43.33 43.33 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.03.02 SISTEMA DE DESAGUE

02.03.02.01 SALIDA DE DESAGUE DE 4" PTO 2.00 43.36 86.72 2.00 86.72 0.00 2.00 86.72 100.00% 0.00

02.03.02.02 SALIDA DE DESAGUE DE 2" PTO 3.00 37.67 113.01 3.00 113.01 0.00 3.00 113.01 100.00% 0.00

02.03.02.03 SALIDA DE DESAGUE DE 3" PTO 9.00 41.95 377.55 0.00 0.00 0.00 0.00 0.00 0.00% 9.00

02.03.02.04 SALIDA DE DESAGUE DE VENTILACION DE 2" PTO 1.00 35.02 35.02 1.00 35.02 0.00 1.00 35.02 100.00% 0.00

02.03.02.05 EXCAVACION DE ZANJAS PARA TUBERIAS M3 20.00 8.65 173.00 20.00 173.00 0.00 20.00 173.00 100.00% 0.00

02.03.02.06 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 20.00 47.22 944.40 20.00 944.40 0.00 20.00 944.40 100.00% 0.00

02.03.02.07 RELLENO COMPACTADO MANUAL MATERIAL PROPIO M3 20.00 35.39 707.80 20.00 707.80 0.00 20.00 707.80 100.00% 0.00

02.03.02.08 TUBERIA DE PVC SAL 4" M 20.00 18.55 371.00 20.00 371.00 0.00 20.00 371.00 100.00% 0.00

02.03.02.09 TUBERIA DE PVC SAL 2" M 15.00 17.39 260.85 15.00 260.85 0.00 15.00 260.85 100.00% 0.00

02.03.02.10 TUBERIA DE PVC SAL 3" M 40.00 18.04 721.60 0.00 0.00 0.00 0.00 0.00 0.00% 40.00

02.03.02.11 REGISTRO DE BRONCE DE 4" PZA 1.00 45.75 45.75 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.03.02.12 REGISTRO DE BRONCE DE 2" U 2.00 48.23 96.46 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.03.02.13 CAJA DE REGISTRO DE DESAGUE 12"X24" CON TAPA DE FºFº U 1.00 100.45 100.45 1.00 100.46 0.00 0.00 1.00 100.46 100.00% 0.00

02.03.02.14 YEE PVC SAL 2" U 3.00 11.92 35.76 3.00 35.76 0.00 3.00 35.76 100.00% 0.00

02.03.02.15 YEE PVC SAL 4" U 4.00 16.67 66.68 4.00 66.68 0.00 4.00 66.68 100.00% 0.00

02.03.02.16 CODO PVC SAL 2"X45º U 2.00 12.13 24.26 2.00 24.26 0.00 2.00 24.26 100.00% 0.00

02.03.02.17 CODO PVC SAL 2"X90º u 1.00 11.92 11.92 1.00 11.92 0.00 1.00 11.92 100.00% 0.00

02.03.02.20 CODO PVC SAL 4"X90º U 1.00 16.77 16.77 1.00 16.77 0.00 1.00 16.77 100.00% 0.00

02.03.02.21 TEE PVC-SAP 4" U 1.00 13.82 13.82 1.00 13.82 0.00 1.00 13.82 100.00% 0.00

02.03.03 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS

02.03.03.01 COLOCACION DE APARATOS SANITARIOS PZA 2.00 50.80 101.60 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.03.03.02 COLOCACION DE ACCESORIOS SANITARIOS PZA 1.00 25.40 25.40 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.04 INSTALACIONES ELECTRICAS I

02.04.01 TUBERIA Y CANALIZACION

02.04.01.01 CANALIZACION PARA DUCTO EN PARED Y PISO M 241.21 2.70 651.27 241.21 651.27 0.00 0.00 241.21 651.27 100.00% 0.00

02.04.01.02 TUBERIA DE PVC SEL 35MM M 54.73 16.92 926.03 54.73 926.04 0.00 0.00 54.73 926.04 100.00% 0.00

02.04.01.03 TUBERIA DE PVC SEL 25MM M 76.84 34.45 2,647.14 67.26 2,317.10 5.74 197.74 73.00 2,514.84 95.00% 3.84

02.04.01.04 TUBERIA DE PVC SEL 20MM M 48.36 3.08 148.95 46.00 141.68 0.00 0.00 46.00 141.68 95.00% 2.36

02.04.02 CAJAS DE PASE

02.04.02.01 CAJAS DE PASE DE 4"X4" U 8.00 19.41 155.28 4.00 77.64 0.00 0.00 4.00 77.64 50.00% 4.00

02.04.03 CONDUCTORES

02.04.03.01 CONDUCTOR THW C/CABLE 1X35MM2 M 124.56 17.07 2,126.24 0.00 0.00 0.00 0.00 0.00 0.00% 124.56

02.04.03.02 CONDUCTOR THW C/CABLE 1X16MM3 M 94.36 9.18 866.22 0.00 0.00 0.00 0.00 0.00 0.00% 94.36

02.04.03.03 CONDUCTOR THW C/CABLE 1X10MM4 M 214.20 4.95 1,060.29 0.00 0.00 0.00 0.00 0.00 0.00% 214.20

02.04.03.04 CONDUCTOR THW C/CABLE 1X6MM2 M 93.16 2.59 241.28 0.00 0.00 0.00 0.00 0.00 0.00% 93.16
02.04.03.05 CONDUCTOR THW C/CABLE 1X4MM2 M 328.92 1.98 651.26 0.00 0.00 0.00 0.00 0.00 0.00% 328.92

02.04.03.06 CONDUCTOR THW C/CABLE 1X2.5MM3 M 203.90 1.49 303.81 0.00 0.00 0.00 0.00 0.00 0.00% 203.90

02.04.04 INSTALACION DE PLACAS

02.04.04.01 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRADO U 22.00 15.66 344.52 0.00 0.00 0.00 0.00 0.00 0.00% 22.00

02.04.04.02 INTERRUPTOR SIMPLE PARA EMPOTRADO U 7.00 17.10 119.70 0.00 0.00 0.00 0.00 0.00 0.00% 7.00

02.04.04.03 INTERRUPTOR DOBLE PARA EMPOTRADO U 5.00 17.27 86.35 0.00 0.00 0.00 0.00 0.00 0.00% 5.00

02.04.05 INSTALACION DE ARTEFACTOS

02.04.05.01 EQUIPO FLUORESCENTE DOBLE DE 2X36W COLGANTE U 32.00 66.78 2,136.96 0.00 0.00 0.00 0.00 0.00 0.00% 32.00

02.04.05.02 FLUORESCENTE CIRCULAR DE 32W INC BASE ADOSABLE DE ALUMINIO+ACCES U 1.00 62.53 62.53 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.04.06 TABLEROS

02.04.06.01 TABLERO GENERAL 24 POLOS U 1.00 291.26 291.26 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.04.06.02 TABLERO DE DISTRIBUCION 24 POLOS U 2.00 291.26 582.52 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.04.06.03 TABLERO DE DISTRIBUCION 16 POLOS U 1.00 219.84 219.84 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.04.07 LLAVES TERMOMAGNETICA

02.04.07.01 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X15A PZA 3.00 37.15 111.45 0.00 0.00 0.00 0.00 0.00 0.00% 3.00

02.04.07.02 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X20A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.04.07.03 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X30A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.04.07.04 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3X30A PZA 1.00 57.09 57.09 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

02.04.07.05 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3X50A PZA 2.00 78.10 156.20 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.04.07.06 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3X60A PZA 4.00 78.10 312.40 0.00 0.00 0.00 0.00 0.00 0.00% 4.00

02.04.07.07 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3X80A PZA 2.00 102.39 204.78 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.04.07.08 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3X160A PZA 2.00 525.16 1,050.32 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

02.04.07.09 INTERRUPTOR THERMOMAGNETICO TRIFASICA 3X200A PZA 3.00 731.05 2,193.15 0.00 0.00 0.00 0.00 0.00 0.00% 3.00

COSTO DIRECTO 320,268.20 150,521.29 8,965.69 159,486.98


GASTOS GENERALES % 8.00 25,621.46 12,041.70 717.26 12,758.96
UTILIDAD % 5.00 16,013.42 7,526.06 448.28 7,974.35
SUBTOTAL 361,903.07 170,089.05 10,131.23 180,220.29
FACTOR DE RELACION 0.0000
SUBTOTAL - con Factor de Relacion 361,903.07 170,089.05 10,131.23 180,220.29

VALORIZACION DE OBRA Nº 04
(Periodo : Del 01 Mayo al 31 Mayo 2011)

Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVODE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A Valor Referencial (S/.) : 4,572,084.75 con IGV
Plazo de Ejecucion : 240 Dias Calendarios Costos al : February-2010
Supervisor : ING. ANTONIO VALENZUELA SALAS Monto del Contrato (S/.) : 4,572,084.75 con IGV
Residente : ING. PABLO SARMIENTO REYES Factor de Relacion : 1.000

Formula : 007 - PABELLON K Y L


AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
PRECIO
UNIDAD METRADO UNITARIO PARCIAL Metrado Monto Metrado Monto Metrado Monto % Metrado

01 PABELLON K
0101 ESTRUCTURAS
010101 OBRAS PRELIMINARES
01010101 DEMOLICION DE PISOS DE CONCRETO DE 0.10M M2 385.06 6.00 2,310.36 385.06 2,310.36 0.00 385.06 2,310.36 100.00% 0.00
01010102 DEMOLICION DE CIMIENTO Y SOBRECIMIENTO M3 2.18 72.46 157.96 2.18 157.96 0.00 2.18 157.96 100.00% 0.00
01010103 DEMOLICION DE MUROS DE LADRILLO M3 14.67 5.28 77.46 14.67 77.46 0.00 14.67 77.46 100.00% 0.00
01010104 RETIRO DE PUERTAS Y VENTANAS M2 80.58 3.20 257.86 80.58 257.86 0.00 80.58 257.86 100.00% 0.00
01010105 ACARREO DE MATERIAL PROVENIENTE DE DEMOLICIONES D=50M M3 69.21 12.36 855.44 69.21 855.44 69.21 855.44 100.00% 0.00
01010106 ELIMINACION DE DEMOLICIONES M3 69.21 9.95 688.64 69.21 688.64 69.21 688.64 100.00% 0.00
01010107 TRAZO, NIVELACION Y REPLANTEO M2 567.60 1.78 1,010.33 567.60 1,010.33 567.60 1,010.33 100.00% 0.00
010102 MOVIMIENTO DE TIERRAS
01010201 EXCAVACION PARA ZAPATAS EN TERRENO NORMAL M3 13.75 24.24 333.30 13.75 333.30 0.00 13.75 333.30 100.00% 0.00
01010202 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 6.46 21.63 139.73 6.46 139.73 0.00 6.46 139.73 100.00% 0.00
01010203 CORTE DE TERRENO NORMAL M3 39.96 23.48 938.26 39.96 938.26 0.00 39.96 938.26 100.00% 0.00
01010204 RELLENO CON MATERIAL PROPIO M3 5.10 42.66 217.57 5.10 217.57 0.00 5.10 217.57 100.00% 0.00
01010205 ACARREO MATERIAL EXCEDENTE D=50M M3 65.83 12.36 813.66 65.83 813.66 0.00 65.83 813.66 100.00% 0.00
01010206 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO M3 65.83 9.58 630.65 65.83 630.65 0.00 65.83 630.65 100.00% 0.00
01010207 AFIRMADO DE 3=4" PARA VEREDAS M2 16.38 5.92 96.97 0.00 0.00 16.38 96.97 16.38 96.97 100.00% 0.00

01010208 NIVELACION, RELLENO Y COMPACTACION CON MATERIAL DE PRESTAMO M2 447.53 7.43 3,325.15 447.53 3,325.14 0.00 0.00 447.53 3,325.15 100.00% 0.00

010103 CONCRETO SIMPLE


01010301 CONCRETO 1:10+30% P.G. PARA CIMIENTOS CORRIDOS M3 8.11 150.25 1,218.53 8.11 1,218.53 0.00 8.11 1,218.53 100.00% 0.00
01010302 CONCRETO 1:8 + 25% PM PARA SOBRECIMIENTOS M3 2.62 228.31 598.17 2.62 598.17 0.00 2.62 598.17 100.00% 0.00
01010303 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS M2 5.23 21.46 112.24 5.23 112.24 0.00 5.23 112.24 100.00% 0.00
01010304 SOLADOS PARA ZAPATAS E=4" M2 10.98 17.30 189.95 10.98 189.95 0.00 10.98 189.95 100.00% 0.00
01010305 PISO DE CONCRETO E=4" FC 175KG/CM2 ACABADO PULIDO 1:2 X 1CM M2 368.78 28.81 10,624.55 368.78 10,624.55 0.00 0.00 368.78 10,624.55 100.00% 0.00
01010306 VEREDA FC=175 KG/CM2 DE CONCRETO DE 4" M2 16.38 30.76 503.85 0.00 0.00 0.00 0.00 0.00 0.00% 16.38
01010307 ENCOFRADO Y DESENCOFRADO EN VEREDAS M2 9.93 29.44 292.34 0.00 0.00 0.00 0.00 0.00 0.00% 9.93
01010308 JUNTAS ASFALTICAS EN VEREDAS M 18.00 5.15 92.70 0.00 0.00 0.00 0.00 0.00 0.00% 18.00
010104 CONCRETO ARMADO
01010401 ZAPATAS
0101040101 CONCRETO FC=210 KG/CM2 PARA ZAPATAS M3 7.69 253.19 1,947.03 7.69 1,947.03 0.00 7.69 1,947.03 100.00% 0.00
0101040102 ACERO FY=4200 KG/CM2 GRADO 60 EN ZAPATAS KG 119.38 3.41 407.09 119.38 407.09 0.00 119.38 407.09 100.00% 0.00
01010402 COLUMNAS
0101040201 CONCRETO FC=210 KG/CM2 PARA COLUMNAS M3 2.34 305.86 715.71 2.34 715.71 0.00 2.34 715.71 100.00% 0.00
0101040202 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 37.40 45.92 1,717.41 37.40 1,717.41 0.00 37.40 1,717.41 100.00% 0.00
0101040203 ACERO FY=4200 KG/CM2 PARA COLUMNAS KG 404.73 3.41 1,380.13 404.73 1,380.13 0.00 404.73 1,380.13 100.00% 0.00
01010403 VIGAS
0101040301 CONCRETO FC=210 KG/CM2 PARA VIGAS M3 1.04 267.17 277.86 1.04 277.86 0.00 1.04 277.86 100.00% 0.00
0101040302 ENCOFRADO Y DESENCOFRADO PARA VIGAS M2 11.18 47.87 535.19 11.18 535.19 0.00 11.18 535.19 100.00% 0.00
0101040303 ACERO FY=4200 KG/CM2 PARA VIGAS KG 230.81 3.37 777.83 230.81 777.83 0.00 230.81 777.83 100.00% 0.00
01010404 ESTRUCTURAS METALICAS Y COBERTURA
0101040401 TIJERALES DE MADERA TIPO 2, L=8.60M U 3.00 762.65 2,287.95 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
0101040402 CORREAS DE MADERA DE 2X3" M 52.00 6.83 355.16 0.00 0.00 0.00 0.00 0.00 0.00% 52.00
0101040403 FRISOS DE MADERA DE 1 X 10" M 11.40 9.29 105.91 0.00 0.00 0.00 0.00 0.00 0.00% 11.40
0101040404 COBERTURA, TECHO ETERNIT GRAN-ONDA M2 93.12 33.98 3,164.22 0.00 0.00 0.00 0.00 0.00 0.00% 93.12
0101040405 CUMBRERA PARA TECHO GRAN ONDA M 46.00 38.27 1,760.42 0.00 0.00 0.00 0.00 0.00 0.00% 46.00
0101040406 CANALETA DE PLANCHA GALVANIZADA M 28.70 24.16 693.39 0.00 0.00 0.00 0.00 0.00 0.00% 28.70
0102 ARQUITECTURA K
010201 MUROS Y TABIQUES
01020101 MURO DE SOGA LADRILLO CORRIENTE CON CEMENTO-ARENA M2 173.77 34.94 6,071.52 173.77 6,071.52 0.00 173.77 6,071.52 100.00% 0.00
010202 REVOQUES ENLUCIDOS Y MOLDURAS
01020201 TARRAJEO PRIMARIO RAYADO CON CEMENTO ARENA 1:5 E=1.5CM M2 2.40 13.24 31.78 0.00 0.00 0.00 0.00 0.00 0.00% 2.40
01020202 TARRAEJO EN INTERIORES ACABADO CON CEMENTOARENA 1:5 M2 537.37 10.71 5,755.23 537.37 5,755.23 0.00 0.00 537.37 5,755.23 100.00% 0.00
01020203 TARRAJEO EN EXTERIORES CON CEMENTO ARENA 1:5 M2 278.16 19.63 5,460.28 278.16 5,460.28 0.00 0.00 278.16 5,460.28 100.00% 0.00
01020204 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA 1:5 M2 98.60 22.45 2,213.57 98.60 2,213.57 0.00 0.00 98.60 2,213.57 100.00% 0.00
01020205 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO-ARENA 1:5 M2 11.76 28.68 337.28 11.76 337.28 0.00 0.00 11.76 337.28 100.00% 0.00
01020206 VESTIDURA DE DERRAMES M 175.22 9.09 1,592.75 175.22 1,592.75 0.00 0.00 175.22 1,592.75 100.00% 0.00
010203 CIELORRASOS
01020301 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA MEZCLA 1:5 M2 55.07 33.63 1,852.00 0.00 0.00 0.00 0.00 0.00 0.00% 55.07
010204 PISOS Y PAVIMENTOS
0102041 CONTRAPISO DE 25MM M2 2.97 15.22 45.20 2.97 45.20 0.00 0.00 2.97 45.20 100.00% 0.00
01020402 PISO CERAMICO DE 30X30 CM ANTIDESLIZANTE M2 2.97 32.68 97.06 0.00 0.00 0.00 0.00 0.00 0.00% 2.97
010205 ZOCALOS
01020501 ZOCALO DE CERAMICA BLANCA DE 20X30CM DE 1RA M2 2.40 33.65 80.76 0.00 0.00 0.00 0.00 0.00 0.00% 2.40
01020502 ZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2CM H=60CM M 97.92 17.65 1,728.29 39.17 691.32 58.75 1,036.94 97.92 1,728.26 100.00% 0.00
010206 CARPINTERIA DE MADERA
01020601 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5MM DE CEDRO U 1.76 179.20 315.39 0.00 0.00 0.00 0.00 0.00 0.00% 1.76
010207 CARPINTERIA METALICA
01020701 PUERTA METALICA ENROLLABLE M2 14.80 160.00 2,368.00 0.00 0.00 0.00 0.00 0.00 0.00% 14.80
01020702 PUERTA METALICA LAC 1/16" CON MARCO 2"X2"X14" Y REFUERXOS M2 23.10 504.08 11,644.25 0.00 0.00 0.00 0.00 0.00 0.00% 23.10
01020703 VENTANA DE FIERRO PERFIL DE 1"X18" FIJA MARCO T DE 1" M2 18.39 33.05 607.79 0.00 0.00 0.00 0.00 0.00 0.00% 18.39
010208 CERRAJERIA
0120801 CERRADURA FORTE DE 3 GOLPES U 14.00 77.28 1,081.92 0.00 0.00 0.00 0.00 0.00 0.00% 14.00
0120802 CERRADURA TIPO PERILLA U 1.00 73.92 73.92 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
010209 VIDRIOS, CRISTALES Y SIMILARES
01020901 VIDRIOS DOBLES NACIONALES P2 595.94 3.69 2,199.02 0.00 0.00 0.00 0.00 0.00 0.00% 595.94
010210 PINTURA
01021001 PINTURA LATEX EN MUROS INTERIORES 2 MANOS M2 537.37 4.53 2,434.29 0.00 0.00 0.00 0.00 0.00 0.00% 537.37
01021002 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 278.16 5.47 1,521.54 0.00 0.00 0.00 0.00 0.00 0.00% 278.16
01021003 PINTURA LATEX EN SUPERFICIE DE COLUMNAS, 2 MANOS M2 98.60 5.17 509.76 0.00 0.00 0.00 0.00 0.00 0.00% 98.60
01021004 PINTURA LATEX EN SUPERFICIE DE VIGAS M2 11.76 5.43 63.86 0.00 0.00 0.00 0.00 0.00 0.00% 11.76
01021005 PINTURA LATEX EN DERRAMES, 2 MANOS M2 26.28 3.29 86.46 0.00 0.00 0.00 0.00 0.00 0.00% 26.28
01021006 PINTURA LATEX EN CIELORRASO 2 MANOS M2 55.07 4.71 259.38 0.00 0.00 0.00 0.00 0.00 0.00% 55.07
01021007 PINTURA BARNIZ CON CARPINTERIA DE MADERA M2 3.52 8.92 31.40 0.00 0.00 0.00 0.00 0.00 0.00% 3.52
01021008 PINTURA EN CARPINTERIA METALICA CON ANTICORROSIVO Y ESMALTE M2 186.57 7.56 1,410.47 0.00 0.00 0.00 0.00 0.00 0.00% 186.57
01021009 PINTURA ESMALTE EN CONTRAZOCALOS M 97.92 4.10 401.47 0.00 0.00 0.00 0.00 0.00 0.00% 97.92
010211 APARATOS Y ACCESORIOS SANITARIOS
01021101 INODORO DE PORCELANA TANQUE BAJO BLANCO U 1.00 75.63 75.63 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01021102 LAVATORIO DE LOSA VITRIICADA U 1.00 75.36 75.36 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01021103 PAPELERA DE LOZA BLANCA DE 13X15 CM PZA 1.00 25.21 25.21 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
010212 OTROS
01021201 LIMPIEZA FINAL M2 451.95 0.36 162.70 345.00 124.20 0.00 0.00 345.00 124.20 76.00% 106.95
0103 INSTALACIONES SANITARIAS K
010301 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01030101 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" PTO 2.00 55.86 111.72 2.00 111.72 0.00 0.00 2.00 111.72 100.00% 0.00
01030102 RED DE DISTRIBUCIÓN TUBERIA DE 1/2" PVC-SAP M 6.40 7.97 51.01 6.40 51.01 0.00 0.00 6.40 51.01 100.00% 0.00
01030103 CODO PVC SAP 1/2"X90 U 4.00 8.51 34.04 0.00 0.00 4.00 34.04 4.00 34.04 100.00% 0.00
01030104 TEE PVC-SAP 1/2" U 1.00 10.34 10.34 0.00 0.00 1.00 10.34 1.00 10.34 100.00% 0.00
01030105 REDUCCIONES PVC-SAP 3/4" A 1/2" U 1.00 13.45 13.45 0.00 0.00 1.00 13.45 1.00 13.45 100.00% 0.00
01030106 VALVULA COMPUERTA DE BRONCE 3/4" U 1.00 43.33 43.33 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
010302 SISTEMA DE DESAGUE
01030201 SALIDA DE DESAGUE DE 4" PTO 2.00 43.36 86.72 0.00 0.00 2.00 86.72 2.00 86.72 100.00% 0.00
01030202 SALIDA DE DESAGUE DE 3" PTO 5.00 41.95 209.75 0.00 0.00 0.00 0.00 0.00 0.00% 5.00
01030203 SALIDA DE DESAGUE DE 2" PTO 3.00 37.67 113.01 0.00 0.00 3.00 113.01 3.00 113.01 100.00% 0.00
01030204 SALIDA DE DESAGUE DE VENTILACION DE 2" PTO 1.00 35.02 35.02 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01030205 EXCAVACION DE ZANJAS PARA TUBERIAS M3 4.70 8.65 40.66 0.00 0.00 4.70 40.66 4.70 40.66 100.00% 0.00
01030206 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 4.70 47.22 221.93 0.00 0.00 4.70 221.93 4.70 221.93 100.00% 0.00
01030207 RELLENO COMPACTADO MANUAL MATERIAL PROPIO M3 4.70 35.39 166.33 0.00 0.00 4.70 166.33 4.70 166.33 100.00% 0.00
01030208 TUBERIA DE PVC SAL 4" M 3.10 18.55 57.51 0.00 0.00 3.10 57.51 3.10 57.51 100.00% 0.00
01030209 TUBERIA DE PVC SAL 3" M 31.25 18.04 563.75 0.00 0.00 0.00 0.00 0.00 0.00% 31.25
01030210 TUBERIA DE PVC SAL 2" M 3.10 17.39 53.91 0.00 0.00 3.10 53.91 3.10 53.91 100.00% 0.00
01030211 REGISTRO DE BRONCE DE 4" PZA 1.00 45.75 45.75 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01030212 SUMIDERO DE BRONCE DE 2" U 1.00 48.23 48.23 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01030213 CAJA DE REGISTRO DE DESAGUE 12"X24" CON TAPA DE FºFº U 1.00 100.45 100.45 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01030214 YEE PVC SAL 4" PZA 2.00 16.67 33.34 0.00 0.00 2.00 33.34 2.00 33.34 100.00% 0.00
01030215 CODO PVC SAL 2"X45º U 3.00 11.92 35.76 0.00 0.00 3.00 35.76 3.00 35.76 100.00% 0.00
01030216 CODO PVC SAL 2"X90º U 15.00 12.08 181.20 0.00 0.00 10.00 120.80 10.00 120.80 67.00% 5.00
01030217 CODO PVC SAL 4"X90º U 1.00 16.77 16.77 0.00 0.00 1.00 16.77 1.00 16.77 100.00% 0.00
01030218 TEE PVC-SAL 4" U 2.00 13.82 27.64 0.00 0.00 2.00 27.64 2.00 27.64 100.00% 0.00
010303 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS
01030301 COLOCACION DE APARATOS SANITARIOS PZA 2.00 50.80 101.60 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01030302 COLOCACION DE ACCESORIOS SANITARIOS PZA 1.00 25.40 25.40 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
0104 INSTALACIONES ELECTRICAS K
010401 TUBERIA Y CANALIZACION
01040101 CANALIZACION PARA DUCTO EN PARED Y PISO M 308.85 2.70 833.90 308.85 833.90 0.00 0.00 308.85 833.90 100.00% 0.00
01040102 TUBERIA DE PVC SEL 25MM M 142.40 34.45 4,905.68 125.00 4,306.25 0.00 0.00 125.00 4,306.25 88.00% 17.40
01040103 TUBERIA DE PVC SEL 20MM M 166.45 3.08 512.67 166.45 512.66 0.00 0.00 166.45 512.66 100.00% 0.00
010402 CAJAS DE PASE
01040201 CAJAS DE PASE DE 4"X4" U 5.00 19.41 97.05 3.00 58.23 0.00 0.00 3.00 58.23 60.00% 2.00
040403 CONDUCTORES
01040301 CONDUCTOR THW C/CABLE 1X16MM2 M 292.80 9.18 2,687.90 0.00 0.00 0.00 0.00 0.00 0.00% 292.80
01040302 CONDUCTOR THW C/CABLE 1X6MM2 M 276.80 2.59 716.91 0.00 0.00 0.00 0.00 0.00 0.00% 276.80
01040303 CONDUCTOR THW C/CABLE 1X4MM2 M 194.25 1.98 384.62 0.00 0.00 0.00 0.00 0.00 0.00% 194.25
01040304 CONDUCTOR THW C/CABLE 1X2.5MM2 M 255.00 1.49 379.95 0.00 0.00 0.00 0.00 0.00 0.00% 255.00
010404 INSTALACION DE PLACAS
01040401 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRADO U 15.00 15.66 234.90 0.00 0.00 0.00 0.00 0.00 0.00% 15.00
01040402 INTERRUPTOR SIMPLE PARA EMPOTRADO U 8.00 17.10 136.80 0.00 0.00 0.00 0.00 0.00 0.00% 8.00
01040403 INTERRUPTOR DOBLE PARA EMPOTRADO U 1.00 17.27 17.27 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
010405 INSTALACION DE ARTEFACTOS

01040501 EQUIPO FLUORESCENTE DOBLE DE 2X36W CON PATALLA ACRILICO REJILLA U 9.00 54.07 486.63 0.00 0.00 0.00 0.00 0.00 0.00% 9.00

01040502 EQUIPO FLUORESCENTE DOBLE DE 2X36W COLGANTE U 12.00 66.78 801.36 0.00 0.00 0.00 0.00 0.00 0.00% 12.00

01040503 FLUORESCENTE CIRCULAR DE 32W INC BASE ADOSABLE DE ALUMINIO+ACCES U 1.00 62.53 62.53 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

010406 TABLEROS
01040601 TABLERO GENERAL 24 POLOS U 1.00 291.26 291.26 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01040602 TABLERO DE DISTRIBUCION 24 POLOS U 3.00 291.26 873.78 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
01040603 TABLERO DE DISTRIBUCION 12 POLOS U 3.00 93.98 281.94 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
010407 LLAVES TERMOMAGNETICA
01040701 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X15A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01040702 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X20A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01040703 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X30A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01040704 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X30A PZA 12.00 57.09 685.08 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
01040705 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X50A PZA 8.00 78.10 624.80 0.00 0.00 0.00 0.00 0.00 0.00% 8.00
01040706 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X60A PZA 1.00 102.39 102.39 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02 PABELLON L
0201 ESTRUCTURAS L
020101 OBRAS PRELIMINARES
02010101 DEMOLICION DE PISOS DE CONCRETO DE 0.10M M2 251.48 6.00 1,508.88 251.48 1,508.88 0.00 0.00 251.48 1,508.88 100.00% 0.00
02010102 DEMOLICION DE MUROS DE LADRILLO M3 4.87 5.28 25.71 4.87 25.71 0.00 4.87 25.71 100.00% 0.00
02010103 DEMOLICION DE ESCALERAS DE CONCRETO M3 0.66 24.14 15.93 0.66 15.93 0.00 0.66 15.93 100.00% 0.00
02010104 DESMONTAJE DE COBERTURAS DE CALAMINA M2 65.55 3.65 239.26 0.00 0.00 65.55 239.26 65.55 239.26 100.00% 0.00
02010105 RETIRO DE TIJERALES DE MADERA U 6.00 55.23 331.38 0.00 0.00 6.00 331.38 6.00 331.38 100.00% 0.00
02010106 RETIRO DE PUERTAS Y VENTANAS M2 68.70 3.20 219.84 68.70 219.84 0.00 68.70 219.84 100.00% 0.00
02010107 RETIRO DE ESCALERA METALICA U 1.00 361.00 361.00 1.00 361.00 0.00 1.00 361.00 100.00% 0.00
02010108 ACARREO MATERIAL PROVENIENTE DE DEMOLICIONES D=50M M3 38.36 12.36 474.13 38.36 474.13 0.00 0.00 38.36 474.13 100.00% 0.00
02010109 ELIMINACION DE DEMOLICIONES M3 38.36 9.95 381.68 38.36 381.68 0.00 0.00 38.36 381.68 100.00% 0.00
02010110 LIMPIEZA DE TERRENO MANUAL M2 945.00 0.44 415.80 0.00 0.00 708.75 311.85 708.75 311.85 75.00% 236.25
02010111 TRAZO, NIVELACION Y REPLANTEO M2 945.00 1.78 1,682.10 945.00 1,682.10 0.00 0.00 945.00 1,682.10 100.00% 0.00
020102 MOVIMIENTO DE TIERRAS
02010201 EXCAVACION PARA ZAPATAS EN TERRENO NORMAL M3 25.34 24.24 614.24 25.34 614.24 0.00 0.00 25.34 614.24 100.00% 0.00
02010202 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 9.96 21.63 215.43 9.96 215.43 0.00 0.00 9.96 215.43 100.00% 0.00
02010204 RELLENO CON MATERIAL PROPIO M3 8.97 42.66 382.66 8.97 382.66 0.00 0.00 8.97 382.66 100.00% 0.00
02010205 ACARREO MATERIAL EXCEDENTE D=50M M3 32.92 12.36 406.89 32.92 406.89 0.00 0.00 32.92 406.89 100.00% 0.00
02010206 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO M3 32.92 9.58 315.37 32.92 315.37 0.00 0.00 32.92 315.37 100.00% 0.00
02010207 AFIRMADO DE 3=4" PARA VEREDAS M2 79.64 5.92 471.47 0.00 0.00 0.00 0.00 0.00 0.00% 79.64

02010208 NIVELACION, RELLENO Y COMPACTACION CON MATERIAL DE PRESTAMO M2 331.62 7.43 2,463.94 298.00 2,214.14 33.62 249.80 331.62 2,463.94 100.00% 0.00

020103 CONCRETO SIMPLE


02010301 CONCRETO 1:10+30% P.G. PARA CIMIENTOS CORRIDOS M3 11.93 150.25 1,792.48 10.00 1,502.50 1.93 289.98 11.93 1,792.48 100.00% 0.00
02010302 CONCRETO 1:8 + 25% PM PARA SOBRECIMIENTOS M3 2.98 228.31 680.36 2.50 570.78 0.48 109.59 2.98 680.37 100.00% 0.00
02010303 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS M2 36.92 21.46 792.30 32.00 686.72 4.92 105.58 36.92 792.30 100.00% 0.00
02010304 SOLADOS PARA ZAPATAS E=4" M2 15.84 17.30 274.03 15.84 274.03 0.00 0.00 15.84 274.03 100.00% 0.00
02010305 FALSO PISO DE 4" DE CONCRETO 1:10 M2 87.81 15.60 1,369.84 0.00 0.00 74.64 1,164.38 74.64 1,164.38 85.00% 13.17
02010306 PISO DE CONCRETO E=4" FC 175KG/CM2 ACABADO PULIDO 1:2 X 1CM M2 244.07 28.81 7,031.66 0.00 0.00 146.44 4,218.94 146.44 4,218.94 60.00% 97.63
02010307 VEREDA FC=175 KG/CM2 DE CONCRETO DE 4" M2 5.87 30.76 180.56 0.00 0.00 0.00 0.00 0.00 0.00% 5.87
02010308 ENCOFRADO Y DESENCOFRADO EN VEREDAS M2 1.89 29.44 55.64 0.00 0.00 0.00 0.00 0.00 0.00% 1.89
02010309 JUNTAS ASFALTIVAS EN VEREDAS M 3.40 5.15 17.51 0.00 0.00 0.00 0.00 0.00 0.00% 3.40
020104 CONCRETO ARMADO
02010401 ZAPATAS
0201040101 CONCRETO FC=210 KG/CM2 PARA ZAPATAS M3 11.09 253.19 2,807.88 11.09 2,807.88 0.00 0.00 11.09 2,807.88 100.00% 0.00
0201040102 ACERO FY=4200 KG/CM2 GRADO 60 EN ZAPATAS KG 135.76 3.41 462.94 135.76 462.94 0.00 0.00 135.76 462.94 100.00% 0.00
02010402 COLUMNAS
0201040201 CONCRETO FC=210 KG/CM2 PARA COLUMNAS M3 3.01 305.86 920.64 3.01 920.64 0.00 0.00 3.01 920.64 100.00% 0.00
0201040202 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 46.55 45.92 2,137.58 46.55 2,137.58 0.00 0.00 46.55 2,137.58 100.00% 0.00
0201040203 ACERO FY=4200 KG/CM2 PARA COLUMNAS KG 690.61 3.41 2,354.98 690.61 2,354.98 0.00 0.00 690.61 2,354.98 100.00% 0.00
02010403 VIGAS
0102040301 CONCRETO FC=210 KG/CM2 PARA VIGAS M3 1.45 267.17 387.40 0.00 0.00 1.45 387.40 1.45 387.40 100.00% 0.00
0102040302 ENCOFRADO Y DESENCOFRADO PARA VIGAS M2 21.00 47.87 1,005.27 0.00 0.00 21.00 1,005.27 21.00 1,005.27 100.00% 0.00
0102040303 ACERO FY=4200 KG/CM2 PARA VIGAS KG 121.33 3.37 408.88 0.00 0.00 121.33 408.88 121.33 408.88 100.00% 0.00
02010404 ESCALERAS DE CONCRETO ARMADO
0201040401 CONCRETO FC=210 KG/CM2 PARA ESCALERAS M3 2.24 305.13 683.49 0.00 0.00 2.24 683.49 2.24 683.49 100.00% 0.00
0201040402 ENCOFRADO Y DESENCOFRADO PARA ESCALERAS M2 11.91 86.74 1,033.07 0.00 0.00 11.91 1,033.07 11.91 1,033.07 100.00% 0.00
0201040403 ACERO FY=4200 KG/CM2 PARA ESCALERAS KG 117.04 3.40 397.94 0.00 0.00 117.04 397.94 117.04 397.94 100.00% 0.00
02010405 ESTRUCTURAS METALICAS Y COBERTURA
0201040501 TIJERALES DE MADERA TIPO 2, L=8.60M U 14.00 762.65 10,677.10 0.00 0.00 0.00 0.00 0.00 0.00% 14.00
0201040502 CORREAS DE MADERA DE 2X3" M 112.60 6.83 769.06 0.00 0.00 0.00 0.00 0.00 0.00% 112.60
0201040503 FRISOS DE MADERA DE 1 X 10" M 17.20 9.29 159.79 0.00 0.00 0.00 0.00 0.00 0.00% 17.20
0201040504 COBERTURA DE FIBRAFORTE TIPO TEJA ANDINA M2 97.43 23.53 2,292.53 0.00 0.00 0.00 0.00 0.00 0.00% 97.43
0201040505 COBERTURA, TECHO ETERNIT GRAN-ONDA M2 145.64 33.98 4,948.85 0.00 0.00 0.00 0.00 0.00 0.00% 145.64
0201040506 CUMBRERA PARA TEJA ANDINA M 12.50 20.25 253.13 0.00 0.00 0.00 0.00 0.00 0.00% 12.50
0201040507 CUMBRERA PARA TECHO GRAN ONDA M 8.70 38.27 332.95 0.00 0.00 0.00 0.00 0.00 0.00% 8.70
0202 ARQUITECTURA L
020201 MUROS Y TABIQUES
02020101 MURO DE SOGA LADRILLO CORRIENTE CON CEMENTO-ARENA M2 194.52 34.94 6,796.53 168.00 5,869.92 26.52 926.61 194.52 6,796.53 100.00% 0.00
020202 REVOQUES ENLUCIDOS Y MOLDURAS
02020201 TARRAJEO PRIMARIO RAYADO CON CEMENTO ARENA 1:5 E=1.5CM M2 11.50 13.24 152.26 0.00 0.00 0.00 0.00 0.00 0.00% 11.50
02020202 TARRAEJO EN INTERIORES ACABADO CON CEMENTOARENA 1:5 M2 414.04 10.71 4,434.37 0.00 0.00 414.04 4,434.37 414.04 4,434.37 100.00% 0.00
02020203 TARRAJEO EN EXTERIORES CON CEMENTO ARENA 1:5 M2 154.00 19.63 3,023.02 0.00 0.00 154.00 3,023.02 154.00 3,023.02 100.00% 0.00
02020204 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA 1:5 M2 72.69 22.45 1,631.89 0.00 0.00 72.69 1,631.89 72.69 1,631.89 100.00% 0.00
02020205 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO-ARENA 1:5 M2 85.77 28.68 2,459.88 0.00 0.00 85.77 2,459.88 85.77 2,459.88 100.00% 0.00
02020206 VESTIDURA DE DERRAMES M 167.92 9.09 1,526.39 0.00 0.00 167.92 1,526.39 167.92 1,526.39 100.00% 0.00
02020207 VESTIDURA DE FONDO ESCALERA CON CEMENTO-ARENA M2 11.34 23.58 267.40 0.00 0.00 0.00 0.00 0.00 0.00% 11.34
02020208 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS M 22.50 20.23 455.18 0.00 0.00 0.00 0.00 0.00 0.00% 22.50
020203 CIELORRASOS
02020301 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA MEZCLA 1:5 M2 46.50 33.63 1,563.80 0.00 0.00 0.00 0.00 0.00 0.00% 46.50

02020302 CIELORRASOS CON TRIPLAY DE 4MM CENTRAMADO DE MADERA MAS TAPAJUNTAS M2 106.59 34.84 3,713.60 0.00 0.00 0.00 0.00 0.00 0.00% 106.59

020204 PISOS Y PAVIMENTOS


02020401 CONTRAPISO DE 25MM M2 139.79 15.22 2,127.60 0.00 0.00 41.94 638.33 41.94 638.33 30.00% 97.85
02020402 PISO CERAMICO DE 30X30 CM M2 136.04 32.68 4,445.79 0.00 0.00 0.00 0.00 0.00 0.00% 136.04
02020403 PISO CERAMICO DE 30X30 CM ANTIDESLIZANTE M2 3.68 32.68 120.26 0.00 0.00 0.00 0.00 0.00 0.00% 3.68
020205 CONTRAZOCALOS 0.00
02020501 CONTRAZOCALO EN INTERIORES DE CERAMICO H=10CM M 94.04 7.57 711.88 0.00 0.00 0.00 0.00 0.00 0.00% 94.04

02020502 CONTRAZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2CM H=30CM M 165.33 5.96 985.37 0.00 0.00 165.33 985.37 165.33 985.37 100.00% 0.00

020206 ZOCALOS 0.00


02020601 ZOCALO DE CERAMICA BLANCA DE 20X30CM DE 1RA M2 11.02 33.65 370.82 0.00 0.00 0.00 0.00 0.00 0.00% 11.02
020207 CARPINTERIA DE MADERA
02020701 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5MM DE CEDRO U 29.34 179.20 5,257.73 0.00 0.00 0.00 0.00 0.00 0.00% 29.34
020208 CARPINTERIA METALICA
02020801 PUERTA METALICA ENROLLABLE (INCLUYE COLOCACION) M2 7.20 160.00 1,152.00 0.00 0.00 0.00 0.00 0.00 0.00% 7.20
02020802 VENTANA DE FIERRO PERFIL DE 1"X18" FIJA MARCO T DE 1" M2 42.41 99.15 4,204.95 0.00 0.00 0.00 0.00 0.00 0.00% 42.41
02020803 BARANDA METALICA DE 4" M 8.45 36.11 305.13 0.00 0.00 0.00 0.00 0.00 0.00% 8.45
020209 CERRAJERIA
02020901 CERRADURA FORTE DE 3 GOLPES U 7.00 77.28 540.96 0.00 0.00 0.00 0.00 0.00 0.00% 7.00
02020902 CERRADURA TIPO PERILLA U 7.00 73.92 517.44 0.00 0.00 0.00 0.00 0.00 0.00% 7.00
020210 VIDRIOS, CRISTALES Y SIMILARES
02021001 VIDRIOS DOBLES NACIONALES P2 397.38 3.69 1,466.33 0.00 0.00 0.00 0.00 0.00 0.00% 397.38
020211 PINTURA
02021101 PINTURA LATEX EN MUROS INTERIORES 2 MANOS M2 414.04 4.53 1,875.60 0.00 0.00 0.00 0.00 0.00 0.00% 414.04
02021102 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 154.00 5.47 842.38 0.00 0.00 0.00 0.00 0.00 0.00% 154.00
02021103 PINTURA LATEX EN SUPERFICIE DE COLUMNAS, 2 MANOS M2 72.69 5.17 375.81 0.00 0.00 0.00 0.00 0.00 0.00% 72.69
02021104 PINTURA LATEX EN SUPERFICIE DE VIGAS M2 85.77 5.43 465.73 0.00 0.00 0.00 0.00 0.00 0.00% 85.77
02021105 PINTURA LATEX EN DERRAMES, 2 MANOS M2 25.19 3.29 82.88 0.00 0.00 0.00 0.00 0.00 0.00% 25.19
02021106 PINTURA LATEX EN CIELORRASO 2 MANOS M2 46.50 4.71 219.02 0.00 0.00 0.00 0.00 0.00 0.00% 46.50
02021107 PINTURA BARNIZ CON CARPINTERIA DE MADERA M2 165.27 8.92 1,474.21 0.00 0.00 0.00 0.00 0.00 0.00% 165.27
02021108 PINTURA EN CARPINTERIA METALICA CON ANTICORROSIVO Y ESMALTE M2 114.43 7.56 865.09 0.00 0.00 0.00 0.00 0.00 0.00% 114.43
02021109 PINTURA ESMALTE EN CONTRAZOCALOS M2 49.60 5.47 271.31 0.00 0.00 0.00 0.00 0.00 0.00% 49.60
020212 APARATOS Y ACCESORIOS SANITARIOS
02021201 INODORO DE PORCELANA TANQUE BAJO BLANCO U 1.00 75.63 75.63 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02021202 LAVATORIO DE LOSA VITRIFICADA U 1.00 75.36 75.36 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02021203 PAPELERA DE LOZA BLANCA DE 13X15 CM PZA 1.00 25.21 25.21 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
020213 OTROS
02021301 LIMPIEZA FINAL M2 945.00 0.36 340.20 0.00 0.00 0.00 0.00 0.00 0.00% 945.00
0203 INSTALACIONES SANITARIAS L
020301 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
02030101 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" PTO 3.00 55.86 167.58 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
02030102 RED DE DISTRIBUCIÓN TUBERIA DE 1/2" PVC-SAP M 8.56 7.97 68.22 0.00 0.00 0.00 0.00 0.00 0.00% 8.56
02030103 RED DE DISTRIBUCIÓN TUBERIA DE 3/4" PVC-SAP M 8.56 8.28 70.88 0.00 0.00 0.00 0.00 0.00 0.00% 8.56
02030104 CODO PVC SAP 1/2"X90 U 3.00 8.51 25.53 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
02030105 TEE PVC-SAP 3/4" U 2.00 11.63 23.26 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02030106 VALVULA COMPUERTA DE BRONCE 3/4" U 1.00 43.33 43.33 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
020302 SISTEMA DE DESAGUE
02030201 SALIDA DE DESAGUE DE 4" PTO 2.00 43.36 86.72 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02030202 SALIDA DE DESAGUE DE 2" PTO 3.00 37.67 113.01 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
02030203 SALIDA DE DESAGUE DE VENTILACION DE 2" PTO 1.00 35.02 35.02 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02030204 EXCAVACION DE ZANJAS PARA TUBERIAS M3 20.00 8.65 173.00 0.00 0.00 0.00 0.00 0.00 0.00% 20.00
02030205 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 20.00 47.22 944.40 0.00 0.00 0.00 0.00 0.00 0.00% 20.00
02030206 RELLENO COMPACTADO MANUAL MATERIAL PROPIO M3 20.00 35.39 707.80 0.00 0.00 0.00 0.00 0.00 0.00% 20.00
02030207 TUBERIA DE PVC SAL 4" M 20.00 18.55 371.00 0.00 0.00 0.00 0.00 0.00 0.00% 20.00
02030208 REGISTRO DE BRONCE DE 4" PZA 1.00 45.75 45.75 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02030209 SUMIDERO DE BRONCE DE 2" U 2.00 48.23 96.46 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02030210 CAJA DE REGISTRO DE DESAGUE 12"X24" CON TAPA DE FºFº U 1.00 100.45 100.45 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02030211 YEE PVC SAL 4" PZA 3.00 11.92 35.76 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
02030212 YEE PVC SAL 2" 4.00 16.67 66.68 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
02030213 CODO PVC SAL 2"X90 U 2.00 12.13 24.26 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02030214 CODO PVC SAL 3"X90 U 1.00 11.92 11.92 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02030215 CODO PVC SAL 4"X90 U 1.00 16.77 16.77 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02030216 TEE PVC-SAL 4" U 1.00 13.82 13.82 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
020303 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS
02030301 COLOCACION DE APARATOS SANITARIOS PZA 2.00 50.80 101.60 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02030302 COLOCACION DE ACCESORIOS SANITARIOS PZA 1.00 25.40 25.40 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
0204 INSTALACIONES ELECTRICAS K
020401 TUBERIA Y CANALIZACION
02040101 CANALIZACION PARA DUCTO EN PARED Y PISO M 328.05 2.70 885.74 0.00 0.00 131.22 354.29 131.22 354.29 40.00% 196.83
02040102 TUBERIA DE PVC SEL 25MM M 205.60 34.45 7,082.92 0.00 0.00 41.12 1,416.58 41.12 1,416.58 20.00% 164.48
02040103 TUBERIA DE PVC SEL 20MM M 245.00 3.08 754.60 0.00 0.00 98.00 301.84 98.00 301.84 40.00% 147.00
020402 CAJAS DE PASE
02040201 CAJAS DE PASE DE 4"X4" U 5.00 19.41 97.05 0.00 0.00 0.00 0.00 0.00 0.00% 5.00
020403 CONDUCTORES
02040301 CONDUCTOR THW C/CABLE 1X16MM2 M 126.60 9.18 1,162.19 0.00 0.00 0.00 0.00 0.00 0.00% 126.60
02040302 CONDUCTOR THW C/CABLE 1X6MM2 M 205.60 2.59 532.50 0.00 0.00 0.00 0.00 0.00 0.00% 205.60
02040303 CONDUCTOR THW C/CABLE 1X4MM2 M 573.80 1.98 1,136.12 0.00 0.00 0.00 0.00 0.00 0.00% 573.80
02040304 CONDUCTOR THW C/CABLE 1X2.5MM2 M 322.40 1.49 480.38 0.00 0.00 0.00 0.00 0.00 0.00% 322.40
020404 INSTALACION DE PLACAS
02040401 TOMACORRIENTE UNIVERSAL DOBLE PARA EMPOTRADO U 25.00 15.66 391.50 0.00 0.00 0.00 0.00 0.00 0.00% 25.00
02040402 INTERRUPTOR SIMPLE PARA EMPOTRADO U 7.00 17.10 119.70 0.00 0.00 0.00 0.00 0.00 0.00% 7.00
02040403 INTERRUPTOR DOBLE PARA EMPOTRADO U 4.00 17.27 69.08 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
02040404 INTERRUPTOR TRIPLE PARA EMPOTRADO U 1.00 30.20 30.20 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
020405 INSTALACION DE ARTEFACTOS

02040501 EQUIPO FLUORESCENTE DOBLE DE 2X36W CON PATALLA ACRILICO REJILLA U 33.00 54.07 1,784.31 0.00 0.00 0.00 0.00 0.00 0.00% 33.00

02040502 EQUIPO FLUORESCENTE DOBLE DE 2X36W COLGANTE U 13.00 66.78 868.14 0.00 0.00 0.00 0.00 0.00 0.00% 13.00

02040503 FLUORESCENTE CIRCULAR DE 32W INC BASE ADOSABLE DE ALUMINIO+ACCES U 5.00 62.53 312.65 0.00 0.00 0.00 0.00 0.00 0.00% 5.00

020406 TABLEROS
02040601 TABLERO GENERAL 24 POLOS U 1.00 291.26 291.26 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02040602 TABLERO DE DISTRIBUCION 24 POLOS U 1.00 291.26 291.26 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
02040603 TABLERO DE DISTRIBUCION 12 POLOS U 2.00 93.98 187.96 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
020407 LLAVES TERMOMAGNETICA
02040701 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X15A PZA 3.00 37.15 111.45 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
02040702 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X20A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02040703 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X30A PZA 2.00 37.15 74.30 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
02040704 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X30A PZA 13.00 57.09 742.17 0.00 0.00 0.00 0.00 0.00 0.00% 13.00
02040705 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X50A PZA 6.00 78.10 468.60 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
02040706 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X80A PZA 1.00 78.10 78.10 0.00 0.00 0.00 0.00 0.00 0.00% 1.00

COSTO DIRECTO 241,361.13 86,829.14 30,801.50 117,630.65


GASTOS GENERALES % 8.00 19,308.89 6,946.33 2,464.12 9,410.45
UTILIDAD % 5.00 12,068.07 4,341.46 1,540.08 5,881.53
SUBTOTAL 272,738.08 98,116.93 34,805.70 132,922.63
FACTOR DE RELACION 0.0000
SUBTOTAL - con Factor de Relacion 272,738.08 98,116.93 34,805.70 132,922.63

VALORIZACION DE OBRA Nº 04
(Periodo : Del 01 Mayo al 31 Mayo 2011)
Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVODE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A Valor Referencial (S/.) 0.62 189.63 1
Plazo de Ejecucion : 240 Dias Calendarios Costos al 9.9 March-1901
Supervisor : ING. ANTONIO VALENZUELA SALAS Monto del Contrato (S/.) 195.7 667.34 1
Residente : ING. PABLO SARMIENTO REYES Factor de Relacion 0 0.000

Formula : 008 - TRATAMIENTO PAISAJISTICO DEL PATIO DE HONOR Y CERCO PERIMETRICO


AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
PRECIO
UNIDAD METRADO UNITARIO PARCIAL Metrado Monto Metrado Monto Metrado Monto % Metrado

01 TRATAMIENTO PAISAJISTICO DEL PATIO DE HONOR


0101 ESTRUCTURAS TP
010101 OBRAS PRELIMINARES
01010101 DEMOLICION DE MUROS DE LADRILLO M3 11.25 5.28 59.40 11.25 59.40 0.00 11.25 59.40 100.00% 0.00
01010102 DEMOLICION DE PISOS DE PAVIMENTO RIGIDO M2 504.23 11.01 5,551.57 504.23 5,551.57 0.00 504.23 5,551.57 100.00% 0.00
01010103 DEMOLICION DE SARDINELES M3 53.50 32.66 1,747.31 53.50 1,747.31 0.00 0.00 53.50 1,747.31 100.00% 0.00
01010104 DEMOLICION DE VEREDAS DE CONCRETO DE 0.10M M2 175.37 6.00 1,052.22 175.37 1,052.22 0.00 175.37 1,052.22 100.00% 0.00
01010105 DEMOLICION DE GRADAS DE CONCRETO M3 8.47 24.14 204.47 8.47 204.47 0.00 8.47 204.47 100.00% 0.00
01010106 DEMOLICION DE PERGOLA, BANCA Y MURAL U 3.00 173.04 519.12 3.00 519.12 0.00 3.00 519.12 100.00% 0.00
01010107 ACARREO MATERIAL PROVENIENTE DE DEMOLICIONES D=50M M3 741.73 12.36 9,167.78 741.73 9,167.78 0.00 741.73 9,167.78 100.00% 0.00
01010108 ELIMINACION DE DEMOLICIONES M3 741.73 9.95 7,380.21 741.73 7,380.21 741.73 7,380.21 100.00% 0.00
01010109 DESMONTAJE DE COBERTURAS DE CALAMINA M2 71.38 3.65 260.54 71.38 260.54 0.00 71.38 260.54 100.00% 0.00
01010110 RETIRO DE POSTES DE LUZ U 4.00 50.40 201.60 4.00 201.60 0.00 4.00 201.60 100.00% 0.00
01010111 TRAZO, NIVELACION Y REPLANTEO M2 11,373.57 0.32 3,639.54 9,636.79 3,083.77 0.00 0.00 9,636.79 3,083.77 85.00% 1,736.78
010102 MOVIMIENTO DE TIERRAS
01010201 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 151.54 21.63 3,277.81 0.00 0.00 53.04 1,147.26 53.04 1,147.26 35.00% 98.50
01010202 EXCAVACION EN PLATAFORMA MANUAL M3 783.57 15.86 12,427.42 310.00 4,916.60 356.03 5,646.64 666.03 10,563.24 85.00% 117.54
01010203 NIVELACION Y COMPACTACION M2 4,087.76 3.54 14,470.67 1,720.00 6,088.80 1,754.60 6,211.28 3,474.60 12,300.08 85.00% 613.16
01010204 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 412.50 31.85 13,138.13 0.00 0.00 350.62 11,167.25 350.62 11,167.25 85.00% 61.88
01010205 ACARREO MATERIAL EXCEDENTE D=50M M3 169.64 12.36 2,096.75 70.00 865.20 74.19 916.99 144.19 1,782.19 85.00% 25.45
01010206 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO M3 169.64 9.58 1,625.15 70.00 670.60 74.19 710.74 144.19 1,381.34 85.00% 25.45
010103 CONCRETO SIMPLE
01010301 CONCRETO FC=175 KG/CM2 EN SARDINELES M3 86.48 304.93 26,370.35 0.00 0.00 34.59 10,547.53 34.59 10,547.53 40.00% 51.89
01010302 CONCRETO FC=175 KG/CM2 PARA RAMPAS M3 22.68 265.93 6,031.29 9.80 2,606.11 3.81 1,013.19 13.61 3,619.30 60.00% 9.07
01010303 CONCRETO FC=175 KG/CM2 PARA GRADAS M3 15.44 297.54 4,594.02 5.00 1,487.70 0.00 0.00 5.00 1,487.70 32.00% 10.44
01010304 CONCRETO FC=175 KG/CM2 PARA CUNETAS M3 64.49 250.29 16,141.20 40.00 10,011.60 0.00 0.00 40.00 10,011.60 62.00% 24.49
01010305 ENCOFRADO Y DESENCOFRADO PARA SARDINELES M2 333.39 48.67 16,226.09 0.00 0.00 133.35 6,490.14 133.35 6,490.14 40.00% 200.04
01010306 ENCOFRADO Y DESENCOFRADO PARA RAMPAS M2 16.98 45.16 766.82 7.20 325.15 2.99 135.03 10.19 460.18 60.00% 6.79
01010307 ENCOFRADO Y DESENCOFRADO PARA GRADAS M2 8.70 52.49 456.66 3.00 157.47 0.00 0.00 3.00 157.47 34.00% 5.70
01010308 ENCOFRADO Y DESENCOFRADO PARA CUNETAS M2 64.49 48.67 3,138.73 40.00 1,946.80 0.00 0.00 40.00 1,946.80 62.00% 24.49
010104 CONCRETO ARMADO
01010401 CONCRETO FC=175 KG/CM2 EN OBRAS DE ARTE M3 3.24 281.77 912.93 0.00 0.00 0.97 273.32 0.97 273.32 30.00% 2.27
01010402 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE M2 40.97 24.82 1,016.88 0.00 0.00 8.19 203.28 8.19 203.28 20.00% 32.78
01010403 ACERO FY=4200 KG/CM2 PARA OBRAS DE ARTE KG 303.87 3.50 1,063.55 0.00 0.00 60.77 212.70 60.77 212.70 20.00% 243.10
010105 ESTRUCTURAS METALICAS Y COBERTURA
010105 COBERTURA DE FIBRAFORTE TRANSLUCIDO M2 71.38 24.77 1,768.08 0.00 0.00 0.00 0.00 0.00 0.00% 71.38
0102 ARQUITECTURA TP
010201 REVOQUES ENLUCIDOS Y MOLDURAS
01020101 TARRAEJO EN SARDINELES M2 555.26 15.82 8,784.21 0.00 0.00 222.10 3,513.62 222.10 3,513.62 40.00% 333.16
01020102 TARRAJEO DE GRANITO PULIDO EN BANCAS M2 38.68 30.97 1,197.92 0.00 0.00 0.00 0.00 0.00 0.00% 38.68
01020103 TARRAJEO DE GRANITO LAVADO EN BANCAS M2 64.87 32.14 2,084.92 0.00 0.00 0.00 0.00 0.00 0.00% 64.87
010202 PISOS Y PAVIMENTOS
01020201 PISO DE CONCRETO FC=175 KG/CM2 E=4" ACABADO FROTACHADO M2 2,642.15 30.61 80,876.21 520.00 15,917.20 669.00 20,478.09 1,189.00 36,395.29 45.00% 1,453.15
01020202 PISO DE CONCRETO FC=175 KG/CM2 ACABADO FROTACHADO E=2" M2 162.79 21.92 3,568.36 0.00 0.00 0.00 0.00 0.00 0.00% 162.79
01020203 EMULSION ASFALTICA E=1! M2 4,260.22 25.21 107,400.15 0.00 0.00 0.00 0.00 0.00 0.00% 4,260.22
01020204 JUNTAS ASFALTICAS M 1,222.59 5.15 6,296.34 0.00 0.00 0.00 0.00 0.00 0.00% 1,222.59
010203 JARDINERIA
01020301 RELLENO CON TIERRA AGRICOLA M3 214.83 37.68 8,094.79 0.00 0.00 0.00 0.00 0.00 0.00% 214.83
01020302 SEMBRIO DE GRASS M2 2,148.26 3.54 7,604.84 0.00 0.00 0.00 0.00 0.00 0.00% 2,148.26
01020303 PLANTACION DE ARBUSTOS U 75.00 6.60 495.00 0.00 0.00 0.00 0.00 0.00 0.00% 75.00
010204 CARPINTERIA METALICA

01020401 TACHOS DE BASURA (ORGANICO E INORGANICO) INCLUYE INSTALACION U 6.00 314.77 1,888.62 0.00 0.00 0.00 0.00 0.00 0.00% 6.00

01020402 POSTES DE FºGº DE 3" A 2" X 4.5" U 40.00 288.48 11,539.20 0.00 0.00 0.00 0.00 0.00 0.00% 40.00
01020403 ASTA DE BANDERA U 3.00 449.06 1,347.18 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
01020404 PARANTE METALICO MAS TABLERO DE BASKET SIMPLE U 4.00 1,186.11 4,744.44 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
01020405 PARANTE METALICO MAS TABLERO DE BASKET DOBLE U 4.00 1,317.61 5,270.44 0.00 0.00 0.00 0.00 0.00 0.00% 4.00
01020406 ARCOS DE TUBO NEGRO DE 3" U 6.00 504.21 3,025.26 0.00 0.00 0.00 0.00 0.00 0.00% 6.00
01020407 REJILLA FIERRO PARA CUNETAS (0.25M DE ANCHO) M 248.00 24.11 5,979.28 0.00 0.00 60.00 1,446.60 60.00 1,446.60 24.00% 188.00
010205 PINTURA
01020501 PINTURA EN LOSAS DEPORTIVAS M 1,768.32 4.15 7,338.53 0.00 0.00 0.00 0.00 0.00 0.00% 1,768.32
01020502 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 3.69 5.47 20.18 0.00 0.00 0.00 0.00 0.00 0.00% 3.69
0103 INSTALACIONES SANITARIAS TP
010301 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01030101 EXCAVACION DE ZANJAS PARA TUBERIAS M3 336.18 8.65 2,907.96 120.00 1,038.00 81.71 706.79 201.71 1,744.79 60.00% 134.47
01030102 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 112.06 47.22 5,291.47 44.00 2,077.68 23.24 1,097.39 67.24 3,175.07 60.00% 44.82
01030103 RELLENO COMPACTADO MANUAL MATERIAL PROPIO M3 291.35 35.39 10,310.88 100.00 3,539.00 74.81 2,647.53 174.81 6,186.53 60.00% 116.54
01030104 RED DE DISTRIBUCIÓN TUBERIA DE 3/4" PVC-SAP M 422.04 8.28 3,494.49 160.00 1,324.80 93.22 771.86 253.22 2,096.66 60.00% 168.82
01030105 RED DE DISTRIBUCIÓN TUBERIA DE 1/2 PVC-SAP M 200.51 7.97 1,598.06 80.00 637.60 40.31 321.27 120.31 958.87 60.00% 80.20
01030106 CODO PVC SAP 3/4"X90 U 3.00 14.92 44.76 2.00 29.84 0.00 0.00 2.00 29.84 67.00% 1.00
01030107 CODO PVC SAP 1/2"X90 U 3.00 8.51 25.53 2.00 17.02 0.00 0.00 2.00 17.02 67.00% 1.00
01030108 REDUCCION PVC PARA RED AGUA POTABLE DE 3/4" A 1/2" U 2.00 1.19 2.38 1.00 1.19 0.00 0.00 1.00 1.19 50.00% 1.00
01030109 TEE PVC-SAP 3/4" A 1/2" U 12.00 11.63 139.56 5.00 58.15 3.00 34.89 8.00 93.04 67.00% 4.00
01030110 TEE PVC-SAP 3/4" U 1.00 10.93 10.93 0.00 0.00 1.00 10.93 1.00 10.93 100.00% 0.00
01030111 TEE PVC-SAP 1/2" U 2.00 10.34 20.68 1.00 10.34 0.00 0.00 1.00 10.34 50.00% 1.00
01030112 VALVULA COMPUERTA DE BRONCE 3/4" U 1.00 43.33 43.33 1.00 43.33 0.00 0.00 1.00 43.33 100.00% 0.00
01030113 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" PTO 17.00 55.86 949.62 0.00 0.00 4.00 223.44 4.00 223.44 24.00% 13.00
01030114 GRIFO PARA GASS TIPO ASPESOR EMERGENTE U 17.00 78.56 1,335.52 0.00 0.00 4.00 314.24 4.00 314.24 24.00% 13.00
010302 SISTEMA DE DESAGUE PLUVIAL
01030201 EXCAVACION DE ZANJAS PARA TUBERIAS M3 217.69 8.65 1,883.02 65.00 562.25 65.61 567.53 130.61 1,129.78 60.00% 87.08
01030202 REFINE Y NIVELACION DE FONDO DE ZANJA DE TUBERIA M 380.06 1.84 699.31 120.00 220.80 108.04 198.79 228.04 419.59 60.00% 152.02
01030203 PREPARACION DE CAMA PARA TUBERIA M 380.06 3.19 1,212.39 120.00 382.80 108.04 344.65 228.04 727.45 60.00% 152.02

01030204 RELLENO COMP ZANJA TERR NORMAL CON MAT PROPIO SELECCIONADO M3 162.78 20.14 3,278.39 50.00 1,007.00 47.67 960.07 97.67 1,967.07 60.00% 65.11

01030205 TUBERIA DE A-C CLASE A-10 DE 8"+ELEM UNION M 254.37 23.60 6,003.13 50.87 1,200.63 101.75 2,401.30 152.62 3,601.93 60.00% 101.75
01030206 TUBERIA DE A-C CLASE A-10 DE 6"+ELEM UNION M 601.33 16.76 10,078.29 0.00 0.00 0.00 0.00 0.00 0.00% 601.33
01030207 TUBERIA DE PVC SAL 3" M 89.63 18.04 1,616.93 0.00 0.00 36.00 649.44 36.00 649.44 40.00% 53.63
01030208 CAJA DE REGISTRO DE DESAGUE 12"X20" CON TAPA DE FºFº U 18.00 100.45 1,808.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 18.00
01030209 SUMIDEROS
0103020901 EXCAVACION PARA SUMIDEROS M3 6.25 21.63 135.19 0.00 0.00 0.00 0.00 0.00 0.00% 6.25
0103020902 REJILLA PARA SUMIDERO DE 20X30 U 9.00 62.38 561.42 0.00 0.00 0.00 0.00 0.00 0.00% 9.00
0103020903 CONSTRUCCION DE SUMIDEROS U 9.00 298.24 2,684.16 0.00 0.00 0.00 0.00 0.00 0.00% 9.00
01030210 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS
0103021001 COLOCACION DE ACCESORIOS SANITARIOS PZA 17.00 25.40 431.80 0.00 0.00 0.00 0.00 0.00 0.00% 17.00
010303 SISTEMA DE DESAGUE
01030301 EXCAVACION DE ZANJAS PARA TUBERIAS M3 342.61 8.65 2,963.58 282.00 2,439.30 0.00 0.00 282.00 2,439.30 82.00% 60.61
01030302 REFINE Y NIVELACION DE FONDO DE ZANJA DE TUBERIA M 571.01 1.84 1,050.66 470.00 864.80 0.00 0.00 470.00 864.80 82.00% 101.01
01030303 PREPARACION DE CAMA PARA TUBERIA M 571.01 3.19 1,821.52 470.00 1,499.30 0.00 0.00 470.00 1,499.30 82.00% 101.01
01030304 RELLENO COMP ZANJA TERR NORMAL CON MAT PROPIO SELECCIONADO M3 148.00 20.14 2,980.72 121.84 2,453.86 0.00 0.00 121.84 2,453.86 82.00% 26.16

01030305 TUBERIA DE A-C CLASE A-10 DE 6"+ELEM UNION M 151.73 16.76 2,542.99 124.00 2,078.24 0.00 0.00 124.00 2,078.24 82.00% 27.73
01030306 TUBERIA DE PVC SAL 4" M 266.49 18.55 4,943.39 200.00 3,710.00 0.00 0.00 200.00 3,710.00 75.00% 66.49
01030307 TUBERIA DE PVC SAL 2" M 152.79 17.39 2,657.02 30.56 531.40 30.55 531.26 61.11 1,062.66 40.00% 91.68
01030308 YEE PVC SAL 4" PZA 3.00 16.67 50.01 2.00 33.34 0.00 0.00 2.00 33.34 67.00% 1.00
01030309 YEE PVC SAL 2" U 3.00 11.92 35.76 0.00 0.00 2.00 23.84 2.00 23.84 67.00% 1.00
01030310 CODO PVC SAL 6"X45 U 1.00 16.61 16.61 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01030311 CODO PVC SAL 4"X45 PZA 4.00 21.78 87.12 0.00 0.00 2.00 43.56 2.00 43.56 50.00% 2.00
01030312 CODO PVC SAL 2"X45 U 2.00 12.13 24.26 1.00 12.13 0.00 0.00 1.00 12.13 50.00% 1.00
01030313 CAJA DE REGISTRO DE DESAGUE 12"X24" CON TAPA DE FºFº U 8.00 100.45 803.60 4.00 401.80 0.00 0.00 4.00 401.80 50.00% 4.00
01030314 CAJA DE REGISTRO DE DESAGUE 1.00X1.00M CON TAPA DE FºFº U 4.00 115.28 461.12 2.00 230.56 0.00 0.00 2.00 230.56 50.00% 2.00
0104 INSTALACIONES ELECTRICAS TP
010401 OBRAS PRELIMINARES
01040101 TRAZO Y REPLANTEO OBRAS ELECTRICAS M 908.86 2.76 2,508.45 454.43 1,254.23 181.77 501.69 636.20 1,755.92 70.00% 272.66
010402 MOVIMIENTO DE TIERRAS
01040201 EXCAVACION DE ZANJAS PARA TUBERIAS M3 205.31 8.65 1,775.93 70.00 605.50 12.12 104.84 82.12 710.34 40.00% 123.19
01040202 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 111.21 47.22 5,251.34 38.00 1,794.36 6.48 305.99 44.48 2,100.35 40.00% 66.73
01040203 RELLENO COMPACTADO MANUAL MATERIAL PROPIO M3 233.54 35.39 8,264.98 80.00 2,831.20 13.42 474.93 93.42 3,306.13 40.00% 140.12
010403 TUBERIA Y CANALIZACION
01040301 TUBERIA DE PVC SAP 20MM M 294.93 12.58 3,710.22 0.00 0.00 59.00 742.22 59.00 742.22 20.00% 235.93
01040302 TUBERIA DE PVC SAP 35MM M 1,257.77 10.94 13,760.00 450.00 4,923.00 53.10 580.91 503.10 5,503.91 40.00% 754.67
01040303 TUBERIA DE PVC SAP 40MM M 199.14 15.26 3,038.88 52.00 793.52 27.65 421.94 79.65 1,215.46 40.00% 119.49
01040304 TUBERIA DE PVC SAP 50MM M 199.14 17.11 3,407.29 0.00 0.00 0.00 0.00 0.00 0.00% 199.14
010404 CAJAS DE PASE
01040401 CAJA DE PASE DE REGISTRO E INSPECCION INC TAPA (SEGÚN DETALLE) U 9.00 215.68 1,941.12 1.00 215.68 0.00 0.00 1.00 215.68 11.00% 8.00
010405 CONDUCTORES Y/O CABLES
01040501 CABLE ELECTRICO NYY 1X70MM2 M 204.78 45.04 9,223.29 0.00 0.00 0.00 0.00 0.00 0.00% 204.78
01040502 CABLE ELECTRICO NYY 1X50MM2 M 597.42 22.48 13,430.00 0.00 0.00 0.00 0.00 0.00 0.00% 597.42
01040503 CABLE ELECTRICO NYY 1X25MM2 M 1,041.42 11.89 12,382.48 420.00 4,993.80 0.00 0.00 420.00 4,993.80 40.00% 621.42
01040504 CABLE ELECTRICO NYY 1X16MM2 M 622.11 15.42 9,592.94 250.00 3,855.00 0.00 0.00 250.00 3,855.00 40.00% 372.11
01040505 CABLE ELECTRICO DESNUDO 1X35MM2 M 2,465.73 14.10 34,766.79 0.00 0.00 0.00 0.00 0.00 0.00% 2,465.73
01040506 CABLE ELECTRICO DESNUDO 1X25MM2 M 213.42 11.93 2,546.10 85.00 1,014.05 0.00 0.00 85.00 1,014.05 40.00% 128.42
01040507 CABLE ELECTRICO DESNUDO 1X16MM2 M 236.58 7.04 1,665.52 0.00 0.00 0.00 0.00 0.00 0.00% 236.58
01040508 CABLE ELECTRICO DESNUDO 1X10MM2 M 242.31 5.28 1,279.40 98.00 517.44 0.00 0.00 98.00 517.44 40.00% 144.31
01040509 CONDUCTOR THW C/CABLE 1X4MM2 M 673.83 1.98 1,334.18 270.00 534.60 0.00 0.00 270.00 534.60 40.00% 403.83
01040510 CONDUCTOR THW C/CABLE 1X6MM2 M 1,071.00 2.59 2,773.89 430.00 1,113.70 0.00 0.00 430.00 1,113.70 40.00% 641.00
010406 TABLEROS
01040601 TABLERO GENERAL
0104060101 TABLERO GENERAL DE FUERZA DE 32 POLOS U 1.00 300.51 300.51 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01040602 TABLERO DE DISTRIBUCION
0104060201 TABLERO DE DISTRIBUCION DE FUERZA DE 12 POLOS U 1.00 77.82 77.82 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
010407 LLAVES Y CUCHILLAS
01040701 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X20A PZA 3.00 37.15 111.45 0.00 0.00 0.00 0.00 0.00 0.00% 3.00
01040702 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X30A PZA 1.00 37.15 37.15 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01040703 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2X60A PZA 2.00 78.10 156.20 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01040704 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X80A PZA 1.00 102.39 102.39 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01040705 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X1600A PZA 1.00 525.16 525.16 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
01040706 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X200A PZA 2.00 731.05 1,462.10 0.00 0.00 0.00 0.00 0.00 0.00% 2.00
01040707 INTERRUPTOR THERMOMAGNETICO MONOFASICA 3X400A PZA 1.00 1,130.20 1,130.20 0.00 0.00 0.00 0.00 0.00 0.00% 1.00
010408 POSTES DE ILUMINACION
01040801 APROVICIONAMIENTO E INSTALACION DE POSTE LUZ DE 9MTS U 2.00 599.94 1,199.88 0.00 0.00 0.00 0.00 0.00 0.00% 2.00

01040802 SC FABRICACION, INSTALACION Y PINTADO DE POSTES METALICOS PARA FAROLA (SEGÚN PZA 12.00 252.00 3,024.00 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
DISEÑO Y ESP TECNICAS)
010409 ARTEFACTOS DE ILUMINACION
01040901 REFLECTOR ALUMINIZADO 400 250 WATTS IP65 ALUMINIO U 12.00 300.70 3,608.40 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
FAROLA ESFERICA E35 CON DEFLECTOR DE ALUMINIO, CON EQUIPO DE SODIO DE 70WTS
01040902 U 12.00 280.51 3,366.12 0.00 0.00 0.00 0.00 0.00 0.00% 12.00
LUZ AMARILLA
010410 POZOS A TIERRA
01041001 SISTEMA DE TIERRA DE PROTECCION U 7.00 1,205.62 8,439.34 0.00 0.00 0.00 0.00 0.00 0.00% 7.00
02 CERCO PERIMETRICO
0201 ESTRUCTURAS CP
020101 OBRAS PRELIMINARES
02010101 DEMOLICION DE MUROS DE LADRILLO M3 9.11 5.28 48.10 0.00 0.00 9.11 48.10 9.11 48.10 100.00% 0.00
02010102 DEMOLICION DE CIMIENTO Y SOBRECIMIENTO M3 3.24 72.46 234.77 0.00 0.00 3.24 234.77 3.24 234.77 100.00% 0.00
02010103 ACARREO DE MATERIAL PROVENIENTE DE DEMOLICIONES D=50M M3 17.29 12.36 213.70 0.00 0.00 17.29 213.70 17.29 213.70 100.00% 0.00
02010104 ELIMINACION DE DEMOLICIONES M3 17.29 9.95 172.04 0.00 0.00 17.29 172.04 17.29 172.04 100.00% 0.00
02010105 LIMPIEZA DE TERRENO MANUAL M2 7.98 0.44 3.51 0.00 0.00 7.98 3.51 7.98 3.51 100.00% 0.00
02010106 TRAZO, NIVELACION Y REPLANTEO M2 7.98 1.78 14.20 0.00 0.00 7.98 14.20 7.98 14.20 100.00% 0.00
020102 MOVIMIENTO DE TIERRAS
02010201 EXCAVACION PARA ZAPATAS EN TERRENO NORMAL M3 3.18 24.24 77.08 0.00 0.00 3.18 77.08 3.18 77.08 100.00% 0.00
02010202 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 1.35 21.63 29.20 0.00 0.00 1.35 29.20 1.35 29.20 100.00% 0.00
02010203 RELLENO CON MATERIAL PROPIO M3 1.91 42.66 81.48 0.00 0.00 1.91 81.48 1.91 81.48 100.00% 0.00
02010204 ACARREO MATERIAL EXCEDENTE D=50M M3 7.82 12.36 96.66 0.00 0.00 7.82 96.66 7.82 96.66 100.00% 0.00
02010205 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO M3 3.05 9.58 29.22 0.00 0.00 3.05 29.22 3.05 29.22 100.00% 0.00
020103 CONCRETO SIMPLE
02010301 CONCRETO 1:10+30% P.G. PARA CIMIENTOS CORRIDOS M3 1.73 150.25 259.93 0.00 0.00 1.73 259.93 1.73 259.93 100.00% 0.00
02010302 CONCRETO 1:8 + 25% PM PARA SOBRECIMIENTOS M3 2.03 228.31 463.47 0.00 0.00 2.03 463.47 2.03 463.47 100.00% 0.00
02010303 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS M2 16.71 21.46 358.60 0.00 0.00 16.71 358.60 16.71 358.60 100.00% 0.00
02010304 SOLADOS PARA ZAPATAS E=4" M2 2.12 17.30 36.68 0.00 0.00 2.12 36.68 2.12 36.68 100.00% 0.00
020104 CONCRETO ARMADO
02010401 ZAPATAS
0201040101 CONCRETO FC=210 KG/CM2 PARA ZAPATAS M3 1.27 253.19 321.55 0.00 0.00 1.27 321.55 1.27 321.55 100.00% 0.00
0201040102 ACERO FY=4200 KG/CM2 GRADO 60 EN ZAPATAS KG 20.62 3.41 70.31 0.00 0.00 20.62 70.31 20.62 70.31 100.00% 0.00
02010402 COLUMNAS
0201040201 CONCRETO FC=210 KG/CM2 PARA COLUMNAS M3 1.06 305.86 324.21 0.00 0.00 1.06 324.21 1.06 324.21 100.00% 0.00
0201040202 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 15.32 45.92 703.49 0.00 0.00 15.32 703.49 15.32 703.49 100.00% 0.00
0201040203 ACERO FY=4200 KG/CM2 PARA COLUMNAS KG 137.20 3.41 467.85 0.00 0.00 137.20 467.85 137.20 467.85 100.00% 0.00
02010403 COLUMNAS DE CONFINAMIENTO
0201040301 CONCRETO FC=175 KG/CM2 PARA COLUMNETAS M3 2.18 288.25 628.39 0.84 242.13 1.34 386.26 2.18 628.39 100.00% 0.00
0201040302 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS M2 79.81 35.16 2,806.12 30.00 1,054.80 49.81 1,751.32 79.81 2,806.12 100.00% 0.00
0201040303 ACERO FY=4200 KG/CM2 PARA COLUMNETAS KG 266.54 3.23 860.92 110.00 355.30 156.54 505.62 266.54 860.92 100.00% 0.00
02010404 VIGAS
0201040401 CONCRETO FC=210 KG/CM2 PARA VIGAS M3 2.09 267.17 558.39 0.00 0.00 2.09 558.39 2.09 558.39 100.00% 0.00
0201040402 ENCOFRADO Y DESENCOFRADO PARA VIGAS M2 13.80 47.87 660.61 0.00 0.00 13.80 660.61 13.80 660.61 100.00% 0.00
0201040403 ACERO FY=4200 KG/CM2 PARA VIGAS KG 49.69 3.37 167.46 0.00 0.00 49.69 167.46 49.69 167.46 100.00% 0.00
0202 ARQUITECTURA CP
020201 REVOQUES ENLUCIDOS Y MOLDURAS
02020101 TARRAEJO EN EXTERIORES CON CEMENTOARENA 1:5 M2 12.66 19.63 248.52 0.00 0.00 12.66 248.52 12.66 248.52 100.00% 0.00
02020102 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA 1:5 M2 89.49 22.45 2,009.05 0.00 0.00 89.49 2,009.05 89.49 2,009.05 100.00% 0.00
02020103 TARRAJEO DE SUPERFICIE DE VIGAS CON CEMENTO-ARENA 1:5 M2 13.80 28.68 395.78 0.00 0.00 13.80 395.78 13.80 395.78 100.00% 0.00
02020104 TARRAJEO EN COBERTURA M2 11.14 36.96 411.73 0.00 0.00 11.14 411.73 11.14 411.73 100.00% 0.00
020202 VIDRIOS, CRISTALES Y SIMILARES
02020201 VIDRIOS DOBLES NACIONALES P2 8.40 3.69 31.00 0.00 0.00 0.00 0.00 0.00 0.00% 8.40
020203 PINTURA
02020301 PINTURA LATEX EN MUROS INTERIORES 2 MANOS M2 52.39 4.53 237.33 0.00 0.00 0.00 0.00 0.00 0.00% 52.39
02020302 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 52.98 5.47 289.80 0.00 0.00 0.00 0.00 0.00 0.00% 52.98
02020303 PINTURA LATEX EN SUPERFICIE DE COLUMNAS, 2 MANOS M2 80.14 5.17 414.32 0.00 0.00 0.00 0.00 0.00 0.00% 80.14
02020304 PINTURA LATEX EN SUPERFICIE DE VIGAS M2 193.14 5.43 1,048.75 0.00 0.00 0.00 0.00 0.00 0.00% 193.14
02020305 PINTURA LATEX EN CIELORRASO 2 MANOS M2 31.97 4.71 150.58 0.00 0.00 0.00 0.00 0.00 0.00% 31.97
02020306 PINTURA EN CARPINTERIA METALICA CON ANTICORROSIVO Y ESMALTE M2 12.63 7.56 95.48 0.00 0.00 0.00 0.00 0.00 0.00% 12.63
02020307 PINTURA ESMALTE EN CONTRAZOCALOS M 177.70 4.10 728.57 0.00 0.00 0.00 0.00 0.00 0.00% 177.70
COSTO DIRECTO 671,810.19 126,724.69 96,195.75 222,920.44
GASTOS GENERALES % 8.00 53,744.82 10,137.98 7,695.66 17,833.64
UTILIDAD % 5.00 33,590.52 6,336.23 4,809.79 11,146.02
SUBTOTAL 759,145.51 143,198.90 108,701.20 251,900.10
FACTOR DE RELACION 0.0000
SUBTOTAL - con Factor de Relacion 759,145.51 143,198.90 108,701.20 251,900.10

CUADROS RESUMENES
AVANCES
PRESUPUESTO SALDO
RESUMEN 1 - Subtotales con Factor de Relacion (sin IGV) ANTERIOR ACTUAL ACUMULADO

ITEM DESCRIPCION DE PARTIDA UNIDAD METRADO PRECIO PARCIAL Metrado Monto Metrado Monto Metrado Monto % Metrado
UNITARIO
001 PABELLON ADMINISTRATIVO 176,979.46 78,419.83 27,715.68 106,135.51
002 PABELLON ABC 271,329.66 232,645.91 38,683.77 271,329.68
003 PABELLON D y E 420,856.33 190,677.03 69,856.46 260,533.49
004 PABELLON F y H 307,921.10 121,543.85 52,284.09 173,827.94
005 PABELLON G 1,271,214.82 344,934.24 241,429.83 586,364.07
006 PABELLON I y J 361,903.07 170,089.07 10,131.23 180,220.30
007 PABELLON K y L 272,738.08 98,116.92 34,805.70 132,922.62

008 TRATAMIENTO PAISAJISTICO DEL PATIO DE HONOR Y CERCO PERIMETRICO 759,145.51 143,198.91 108,701.20 251,900.11

TOTALES 3,842,088.03 1,379,625.76 583,607.96 1,963,233.72


35.91% 15.19% 51.10%
SALDO

Monto

0.00 590.06 2,554.96


0.00 106.72 281.74
0.00 16.49 475.57
0.00 7.77 24.86
0.00 159.27 1,968.58
0.00 159.27 1,584.74

0.00 40.43 999.43

0.00 15.10 3,875.11


0.00 295.98 1,009.29
0.00 5.88 118.42

894.14 0.00 0.00


1,585.36 0.00 0.00

0.00 0.00 0.00

0.00 181.33 3,559.51


0.00 62.14 1,442.89
2,832.20 0.00 0.00
471.39 780.00 6,450.60

274.72 680.00 5,494.40


326.95 0.00 0.00

303.28 4,173.14
367.32 451.79 14,764.50

0.00 0.00 0.00


236.56 1,400.00 10,598.00

2,534.40 0.00 0.00

5,029.88 0.00 0.00


1,344.53 0.00 0.00
11,186.24 0.00 0.00
276.43 0.00 0.00

3,099.52 0.00 0.00


3,742.68 0.00 0.00
702.34 0.00 0.00
6,942.54 0.00 0.00
383.52 0.00 0.00
537.44 0.00 0.00

453.78 0.00 0.00


352.92 0.00 0.00
452.16 0.00 0.00
151.26 0.00 0.00

504.00 0.00 0.00

0.00 18.00 1,005.48


0.00 41.10 327.57
0.00 12.00 99.36
0.00 12.00 341.76
0.00 12.00 381.36
0.00 12.00 102.12
0.00 12.00 124.08
0.00 0.00 0.00
0.00 0.00 0.00
78.72 0.00 0.00
191.55 0.00 0.00

0.00 6.00 260.16


0.00 18.00 678.06
0.00 0.00 0.00
359.10 80.00 1,391.20
0.00 15.30 283.82
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 12.00 143.04
0.00 3.00 36.15
0.00 6.00 82.92

914.40 0.00 0.00


152.40 0.00 0.00

113.03 738.92 1,995.08


110.05 637.68 1,964.05
44.78 23.40 806.13

189.46 0.00 0.00

431.24 0.00 0.00


1,744.36 0.00 0.00
885.03 0.00 0.00

1,315.44 0.00 0.00


752.40 0.00 0.00
103.62 0.00 0.00
85.15 0.00 0.00

3,460.48 0.00 0.00


650.55 0.00 0.00
562.77 0.00 0.00

216.85 0.00 0.00

145.63 0.00 0.00


109.92 0.00 0.00
219.84 0.00 0.00
48.99 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

1,205.62 0.00 0.00


2,428.72 0.00 0.00

1,491.39 0.00 0.00

62,693.77
5,015.50
3,134.68
70,843.95

70,843.95

SALDO

Monto
0.00 286.28 1,239.59
0.00 27.54 165.24
0.00 595.76 1,572.81
0.00 115.80 1,142.95
31.88 367.90
0.00 4.62 24.39
0.00 287.49 919.97
0.00 28.95 357.82
0.00 28.95 288.05

0.00 1.30 28.12

0.00 92.32 2,839.76


0.00 1.00 17.30
0.00 30.72 469.71

0.00 0.60 151.91


0.00 12.48 42.56

0.00 2.43 700.45


0.00 53.58 1,883.87
0.00 139.96 452.07

0.00 0.33 100.93


0.00 4.92 225.93
0.00 125.20 426.93

0.00 1.64 496.38


0.00 26.04 1,246.53
0.00 93.82 316.17

0.00 33.85 1,264.64

0.00 10.78 653.48

0.00 25.92 1,007.51

0.00 130.44 1,727.03


0.00 123.69 1,324.72
0.00 213.95 4,199.84
0.00 148.30 3,329.34
0.00 90.23 2,587.80
0.00 21.57 274.15
0.00 229.50 4,642.79
0.00 25.50 443.70
0.00 336.58 2,783.52

0.00 225.60 1,822.85

0.00 825.32 20,806.32


0.00 92.34 3,017.67
0.00 13.50 174.29
0.00 692.78 9,532.65
0.00 40.20 1,094.24

0.00 839.95 5,006.10

0.00 163.05 5,486.64

0.00 63.98 10,236.80

0.00 389.50 6,504.66


0.00 0.00 0.00
0.00 0.00 0.00
0.00 7.00 3,624.18
0.00 16.00 1,106.24
0.00 8.50 562.28
0.00 191.20 5,145.19

0.00 10.00 772.80


0.00 1.00 23.63

0.00 0.00 0.00

0.00 2,779.47 12,591.00


0.00 837.69 4,582.16
0.00 393.48 2,136.60
0.00 609.00 3,148.53
0.00 373.35 1,228.32
0.00 2,741.22 12,911.15
0.00 33.00 309.87
0.00 0.00 0.00
0.00 0.00 0.00
0.00 1,121.87 8,481.34
0.00 114.00 467.40

0.00 18.00 1,361.34


0.00 15.30 4,504.78
0.00 9.00 3,459.51

0.00 4,186.02 1,506.97

0.00 36.00 2,010.96


0.00 18.15 144.66
0.00 111.00 919.08
0.00 10.00 85.10
0.00 32.00 330.88
0.00 12.00 510.24
0.00 1.00 64.69

0.00 18.00 780.48


0.00 18.00 678.06
0.00 11.00 191.29
0.00 26.50 491.58
0.00 8.00 366.00
0.00 6.00 228.30
0.00 18.00 868.14
0.00 6.00 602.70
0.00 18.00 214.56
0.00 6.00 72.30
0.00 2.00 43.56
0.00 3.00 41.46

0.00 18.00 914.40

0.00 35.00 582.75


0.00 11.00 234.85

0.00 562.18 1,517.89


0.00 514.68 1,585.21
0.00 55.00 1,894.75

0.00 9.00 248.85

0.00 230.00 595.70


0.00 2,353.20 3,506.27
0.00 1,675.56 3,317.61

0.00 158.00 2,474.28


0.00 3.00 122.94
0.00 27.00 461.70
0.00 35.00 604.45

0.00 122.00 6,596.54


0.00 29.00 1,257.73
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00
0.00
SALDO

Monto

0.00 284.05 1,704.30


0.00 43.65 230.47
0.00 0.43 23.16
0.00 7.64 418.67
0.00 2.28 55.04
0.00 300.20 1,095.73
0.00 9.00 497.07
0.00 121.23 387.94
0.00 102.81 1,270.73
0.00 102.81 1,022.96

0.00 9.70 235.13


0.00 2.71 58.62
0.00 5.20 221.83
0.00 9.01 111.36
0.00 9.01 86.32
0.00 0.00 0.00
0.00 252.70 1,877.56

0.00 1.89 283.97


0.00 0.63 143.84
0.00 2.52 54.08
0.00 5.88 101.72
0.00 252.70 3,942.12
1,160.88 0.00 0.00
169.87 0.00 0.00
113.82 0.00 0.00

0.00 3.82 967.19


0.00 59.91 204.29

0.00 3.41 1,042.98


0.00 49.11 2,255.13
0.00 478.02 1,630.05

0.00 0.23 61.45


0.00 2.78 133.08
0.00 41.58 140.12
0.00 5.92 1,806.37
0.00 29.98 2,600.47
0.00 303.60 1,032.24

0.00 8.50 8,031.48


0.00 100.00 683.00
612.21 22.00 204.38
926.85 0.00 0.00
78.97 0.00 0.00

0.00 20.36 1,309.15

0.00 81.00 1,072.44


377.85 634.59 6,796.46
285.42 261.00 5,123.43
18.41 32.00 718.40
222.27 145.00 4,158.60
140.20 193.92 2,464.72
0.00 18.00 424.44
884.05 0.00 0.00
82.82 0.00 0.00

425.08 225.81 7,593.99


8,917.65 0.00 0.00

0.00 470.16 7,155.84


13,877.89 0.00 0.00
0.00 45.50 1,486.94
0.00 0.00 0.00

1,762.60 0.00 0.00


0.00 9.00 53.64

0.00 73.00 2,456.45


0.00 0.00 0.00

3,744.00 0.00 0.00

3,538.64 0.00 0.00


5,127.04 0.00 0.00
491.10 0.00 0.00
2,020.64 0.00 0.00

772.80 0.00 0.00


127.50 0.00 0.00
141.78 0.00 0.00

4,105.90 0.00 0.00

2,081.81 70.00 317.10


1,032.19 29.00 158.63
112.81 3.00 15.51
548.92 15.00 81.45
108.83 0.00 0.00
1,285.97 0.00 0.00
972.75 0.00 0.00
185.85 0.00 0.00

453.78 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
151.26 0.00 0.00

26.15 217.91 78.45

0.00 6.00 335.16


0.00 30.00 239.10
248.40 0.00 0.00
0.00 20.00 170.20
0.00 18.00 186.12
85.04 0.00 0.00
43.33 0.00 0.00

0.00 11.00 414.37


0.00 6.00 260.16
0.00 2.00 70.04
0.00 20.00 347.80
0.00 25.00 216.25
0.00 25.00 1,180.50
0.00 25.00 884.75
0.00 25.00 463.75
274.50 0.00 0.00
289.38 0.00 0.00
0.00 6.00 100.02
0.00 4.00 48.20
0.00 2.00 24.26
0.00 7.00 83.44
0.00 6.00 75.42
0.00 1.00 100.45

304.80 0.00 0.00


152.40 0.00 0.00

39.60 252.65 682.16


45.17 252.65 778.17
34.45 7.00 241.15

55.30 0.00 0.00

25.90 0.00 0.00


555.03 0.00 0.00
731.21 0.00 0.00

250.56 0.00 0.00


81.96 0.00 0.00
503.36 0.00 0.00
119.70 0.00 0.00
69.08 0.00 0.00
34.06 0.00 0.00
30.20 0.00 0.00

1,784.31 0.00 0.00


130.11 0.00 0.00

46.89 0.00 0.00


93.98 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 323.62 1,941.72


0.00 12.54 66.21
0.00 0.43 23.16
0.00 3.60 197.28
0.00 5.54 133.74
0.00 394.20 1,438.83
0.00 13.00 717.99
0.00 75.28 240.90
0.00 68.09 841.59
0.00 68.09 677.50

0.00 19.40 470.26


0.00 3.75 81.11
0.00 10.42 444.52
0.00 13.56 167.60
0.00 13.56 129.90
0.00 0.00 0.00
0.00 207.65 1,542.84

0.00 2.33 350.08


0.00 0.47 107.31
0.00 3.11 66.74
0.00 11.76 203.45
0.00 275.04 4,290.62
2,721.64 0.00 0.00
356.81 0.00 0.00
140.08 0.00 0.00

0.00 7.64 1,934.37


0.00 119.83 408.62

0.00 5.41 1,654.70


0.00 76.40 3,508.29
0.00 679.63 2,317.54

0.00 0.60 160.30


0.00 7.20 344.66
0.00 104.36 351.69

0.00 10.88 3,319.81


0.00 55.27 4,794.12
0.00 758.94 2,580.40

0.00 11.00 8,389.15


0.00 150.00 1,024.50
637.29 30.00 278.70
0.00 0.00 0.00
0.00 0.00 0.00

0.00 29.91 1,923.21

532.94 889.54 9,526.97


431.28 389.54 7,646.67
126.16 102.10 2,292.15
297.98 181.92 5,217.47
226.37 160.60 2,041.22
838.74 0.00 0.00
1,590.08 0.00 0.00
167.91 0.00 0.00

447.94 72.50 2,438.18


13,237.81 0.00 0.00

0.00 422.54 6,431.06


13,808.61 0.00 0.00
0.00 0.00 0.00

2,030.73 0.00 0.00


81.06 0.00 0.00

372.18 15.81 279.10

4,985.60 0.00 0.00

13,087.80 0.00 0.00


1,440.79 0.00 0.00

772.80 0.00 0.00


63.75 0.00 0.00

5,240.98 0.00 0.00

2,705.09 99.00 448.47


1,442.11 43.00 235.21
348.92 11.00 56.87
677.01 20.00 108.60
175.78 0.00 0.00
1,422.47 0.00 0.00
1,269.40 0.00 0.00
216.11 0.00 0.00

70.00 0.00 0.00

27.37 0.00 0.00

55.86 0.00 0.00


23.91 0.00 0.00
0.00 0.00 0.00
25.53 0.00 0.00
0.00 0.00 0.00
42.52 0.00 0.00
43.33 0.00 0.00

37.67 0.00 0.00


35.02 0.00 0.00
86.50 0.00 0.00
472.20 0.00 0.00
353.90 0.00 0.00
173.90 0.00 0.00
114.15 0.00 0.00
96.46 0.00 0.00
24.26 0.00 0.00
107.28 0.00 0.00
100.45 0.00 0.00

50.80 0.00 0.00

45.28 289.91 782.76


51.65 289.91 892.92
37.89 6.90 237.71

55.30 0.00 0.00

41.44 0.00 0.00


663.30 0.00 0.00
868.55 0.00 0.00

485.46 0.00 0.00


40.98 0.00 0.00
251.68 0.00 0.00
119.70 0.00 0.00
120.89 0.00 0.00
17.03 0.00 0.00
30.20 0.00 0.00

1,784.31 0.00 0.00


173.48 0.00 0.00
46.89 0.00 0.00
93.98 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

141,878.62
11,350.29
7,093.93
160,322.84

160,322.84

SALDO

Monto

0.00 17.66 105.96


0.00 11.75 62.04
0.00 16.17 51.74
0.00 16.89 208.76
0.00 16.89 168.06
0.00 261.81 96.87

0.00 3.63 87.99


0.00 4.09 88.47
0.00 2.26 96.41
0.00 6.44 79.60
0.00 6.44 61.70
81.28 0.00 0.00

0.00 3.27 491.32


0.00 0.75 171.23
0.00 10.05 215.67
0.00 2.40 41.52
0.00 235.85 6,794.84
534.92 0.00 0.00
282.62 0.00 0.00
23.18 0.00 0.00

0.00 1.44 364.59


0.00 29.48 100.53

0.00 0.24 73.41


0.00 3.12 143.27
0.00 0.01 0.03

0.00 0.97 296.68


0.00 22.50 1,033.20
0.00 154.62 527.25

0.00 0.06 16.03


0.00 0.48 22.98
0.00 21.68 73.06

0.00 3.02 921.49


0.00 18.62 1,615.10
0.00 298.41 1,014.59

0.00 42.80 1,495.43

0.00 82.61 884.75


58.69 0.00 0.00
0.00 14.81 332.48
0.00 0.48 13.77
0.00 29.60 269.06
0.00 11.85 279.42
485.52 0.00 0.00
0.00 0.00 0.00

1,058.61 0.00 0.00


1,637.27 0.00 0.00

229.90 0.00 0.00


1,042.40 0.00 0.00

2,049.60 0.00 0.00

247.88 0.00 0.00

254.70 0.00 0.00


154.56 0.00 0.00
295.68 0.00 0.00

99.37 0.00 0.00


855.76 0.00 0.00
511.39 0.00 0.00
260.98 0.00 0.00
229.85 0.00 0.00
367.49 0.00 0.00
717.09 0.00 0.00
1,034.68 0.00 0.00

71.82 0.00 0.00

889.09 0.00 0.00


243.26 0.00 0.00
167.20 0.00 0.00
48.32 0.00 0.00

29.42 188.65 509.36


0.00 19.00 207.86
0.00 65.55 2,258.20
22.76 133.10 409.95

473.65 8.00 757.84

204.84 0.00 0.00


36.72 0.00 0.00
1,054.35 0.00 0.00
31.08 0.00 0.00
19.80 0.00 0.00
312.01 0.00 0.00

187.92 0.00 0.00


68.40 0.00 0.00
17.27 0.00 0.00
151.00 0.00 0.00
34.06 0.00 0.00

486.63 0.00 0.00


868.14 0.00 0.00

93.78 0.00 0.00


291.26 0.00 0.00
93.98 0.00 0.00

74.30 0.00 0.00


37.15 0.00 0.00
74.30 0.00 0.00
57.09 0.00 0.00
390.50 0.00 0.00
1,575.48 0.00 0.00

206.82 583.48 3,500.88


0.00 913.65 1,370.48
0.00 96.86 511.42
0.00 5.49 300.85
0.00 2.01 108.28
0.00 294.05 1,073.28
0.00 36.00 1,988.28
0.00 147.21 471.07
169.46 229.61 2,837.98
136.42 229.61 2,284.62
28.58 1,320.00 488.40

1,917.59 380.00 10,947.80

2,406.35 0.00 0.00


452.93 0.00 0.00
1,303.73 0.00 0.00

0.00 337.69 12,616.10

0.00 604.38 6,472.91


0.00 31.00 608.53
0.00 13.05 292.97
0.00 13.86 397.50
0.00 0.00 0.00
0.00 0.00 0.00
1,406.39 0.00 0.00
182.70 0.00 0.00

-0.01 22.04 741.21


0.00 496.70 4,107.71

654.82 560.00 11,832.80


1,001.97 0.00 0.00
626.48 0.00 0.00
1,390.61 385.50 11,800.16

272.90 0.00 0.00


375.72 0.00 0.00

1,932.18 0.00 0.00

11,726.40 0.00 0.00

2,058.52 0.00 0.00


3,814.35 134.30 4,438.57

15,234.79 0.00 0.00

5,380.37 0.00 0.00


1,980.41 0.00 0.00
1,565.53 0.00 0.00
1,187.32 0.00 0.00
6,915.60 0.00 0.00
2,957.70 0.00 0.00
1,718.06 0.00 0.00

453.78 0.00 0.00


150.72 0.00 0.00
412.20 0.00 0.00
2,260.21 0.00 0.00
42.02 0.00 0.00
151.26 0.00 0.00
406.40 0.00 0.00
177.80 0.00 0.00

49.86 415.49 149.57

106.62 668.66 1,805.38


128.50 64.00 2,204.80
104.29 573.66 1,766.87

19.41 0.00 0.00

1,891.36 0.00 0.00


660.96 0.00 0.00
1,768.14 0.00 0.00
2,005.74 0.00 0.00
2,016.57 0.00 0.00

1,503.36 0.00 0.00

5,298.86 0.00 0.00


1,602.72 0.00 0.00
187.59 0.00 0.00
607.18 0.00 0.00

93.78 0.00 0.00


93.98 0.00 0.00
219.84 0.00 0.00
291.26 0.00 0.00
291.26 0.00 0.00
301.77 0.00 0.00
301.77 0.00 0.00

445.80 0.00 0.00


371.50 0.00 0.00
37.15 0.00 0.00
102.86 0.00 0.00
1,141.80 0.00 0.00
702.90 0.00 0.00
234.30 0.00 0.00
204.78 0.00 0.00
92.56 0.00 0.00
1,050.32 0.00 0.00
731.05 0.00 0.00

118,337.92
9,467.03
5,916.91
133,721.86

133,721.86

SALDO

Monto

0.00 1.00 6,300.00


0.00 1.00 1,260.45

0.00 659.75 3,958.50


0.00 9.20 553.93
0.00 46.63 703.65
0.00 18.79 99.21
0.00 7.28 392.17
0.00 626.30 2,286.00
0.00 36.00 1,988.28
0.00 86.64 277.25
0.00 184.84 2,284.62
0.00 184.84 1,839.16
0.00 945.00 1,682.10

0.00 290.72 7,047.05


0.00 42.12 911.06
0.00 11.59 286.50
0.00 220.95 9,425.73
0.00 141.93 1,754.25
0.00 141.93 1,359.69
270.01 0.00 0.00
0.00 546.27 4,058.79

0.00 57.62 8,657.41


0.00 9.47 2,162.10
0.00 124.60 2,673.92
-0.01 117.14 2,026.53
0.00 136.02 2,121.91
12,255.20 0.00 0.00
88.54 0.00 0.00
49.68 0.00 0.00
0.00 3.51 665.36
0.00 4.98 174.45
0.00 45.61 1,402.96
571.14 0.00 0.00
84.98 0.00 0.00

0.00 76.20 19,293.08


0.00 1,867.61 6,368.55

7,420.16 29.69 9,080.99


9,883.82 268.37 12,323.55
0.01 12,088.84 41,222.94

4,098.91 0.00 0.00


6,262.00 0.00 0.00
3,293.34 0.00 0.00

3,124.15 9.45 3,164.33


5,818.74 141.12 6,477.41
1,887.03 610.77 2,076.62

15,030.99 56.20 15,014.95


19,006.78 400.73 19,182.95
17,805.85 4,710.52 15,874.46

1,415.81 4.99 1,522.60


2,486.84 24.72 2,144.21
1,286.49 356.18 1,211.01

18,546.58 68.35 18,470.90


11,694.73 424.46 11,812.72
4,730.56 87.04 4,068.25
15,466.63 3,968.65 13,493.41
9,910.62 2,644.39 7,695.17
0.00 167.72 424.33

686.61 0.00 0.00


875.69 0.00 0.00
1,594.60 0.00 0.00

0.00 6.18 1,986.07


0.00 32.53 1,601.13
0.00 269.08 917.56

1,566.99 0.00 0.00


1,657.17 0.00 0.00
835.45 0.00 0.00
959.22 0.00 0.00

41,582.09 0.00 0.00


1,882.70 0.00 0.00
1,568.88 0.00 0.00

2,552.67 0.00 0.00


26,546.23 0.00 0.00
15,430.75 0.00 0.00
8,084.02 0.00 0.00
16,229.73 0.00 0.00
11,958.84 0.00 0.00
1,185.13 0.00 0.00
0.00 0.00 0.00
1,801.28 0.00 0.00
200.97 0.00 0.00

27,048.95 0.00 0.00


32,063.29 0.00 0.00

15,715.16 420.00 10,588.20


31,915.61 0.00 0.00
2,181.72 0.00 0.00
8,162.09 0.00 0.00

4,406.50 0.00 0.00


2,077.54 0.00 0.00

6,847.10 0.00 0.00


3,955.80 0.00 0.00

22,155.20 0.00 0.00

6,532.88 0.00 0.00


14,044.93 0.00 0.00
1,087.63 0.00 0.00

2,472.96 0.00 0.00


191.25 0.00 0.00
283.56 0.00 0.00

17,009.35 0.00 0.00

11,396.12 0.00 0.00


2,834.88 0.00 0.00
2,326.97 0.00 0.00
3,838.41 0.00 0.00
464.35 0.00 0.00
4,735.01 0.00 0.00
792.10 0.00 0.00
3,360.87 0.00 0.00
1,429.18 0.00 0.00

756.30 0.00 0.00


452.16 0.00 0.00
176.46 0.00 0.00
4,681.44 0.00 0.00
2,721.48 0.00 0.00
302.52 0.00 0.00
210.10 0.00 0.00
302.52 0.00 0.00

364.08 0.00 0.00


212.00 0.00 0.00
0.00
0.00
2,737.14 0.00 0.00
156.61 52.00 414.44
643.60 0.00 0.00
102.12 15.00 127.65
238.72 0.00 0.00
58.15 0.00 0.00
161.40 0.00 0.00
595.28 0.00 0.00
43.33 0.00 0.00
129.38 0.00 0.00

173.44 8.00 346.88


301.36 17.00 640.39
70.04 0.00 0.00
0.00 2.40 20.76
0.00 1.56 73.66
0.00 1.56 55.21
447.98 35.12 651.48
613.86 56.50 982.54
366.00 0.00 0.00
266.35 0.00 0.00
1,350.44 0.00 0.00
200.90 0.00 0.00
95.36 18.00 214.56
33.34 2.00 33.34
36.15 8.00 96.40
24.26 4.00 48.52
16.77 0.00 0.00
13.82 0.00 0.00

812.80 0.00 0.00


736.60 0.00 0.00

680.21 0.00 0.00


248.43 0.00 0.00
385.63 19.90 217.71
1,163.04 50.00 1,722.50
1,347.75 423.01 1,302.87

2,163.36 49.00 2,208.43


89.80 0.00 0.00
393.30 0.00 0.00
293.59 0.00 0.00
60.40 0.00 0.00
102.18 0.00 0.00
4,040.28 0.00 0.00
122.94 0.00 0.00

652.40 3.00 489.30


1,154.88 0.00 0.00
394.87 8.00 451.28
169.23 0.00 0.00
169.23 0.00 0.00
225.64 0.00 0.00
56.41 0.00 0.00

3,062.28 10.00 785.20

1,650.56 0.00 0.00


410.26 0.00 0.00
387.80 0.00 0.00
4,947.66 0.00 0.00
2,115.01 0.00 0.00

291.26 0.00 0.00


873.78 0.00 0.00
879.36 0.00 0.00
187.96 0.00 0.00

557.25 0.00 0.00


594.40 0.00 0.00
222.90 0.00 0.00
185.75 0.00 0.00
37.68 0.00 0.00
102.86 0.00 0.00
64.04 0.00 0.00
127.06 0.00 0.00
627.99 0.00 0.00
156.20 0.00 0.00
204.78 0.00 0.00
731.05 0.00 0.00

346.96 0.00 0.00


7,515.73 0.00 0.00

86.74 0.00 0.00

856.80 0.00 0.00


137.52 0.00 0.00
166.35 0.00 0.00
153.75 0.00 0.00
97.46 0.00 0.00

1,205.62 0.00 0.00


2,428.72 0.00 0.00
1,113.24 0.00 0.00

606,062.62
48,485.01
30,303.14
684,850.77

684,850.77

SALDO

Monto

0.00 76.40 458.40


0.00 4.83 349.98
0.00 37.84 199.80
0.00 1.11 26.80
1,046.30 0.00 0.00
0.00 150.62 481.98
0.00 150.23 1,856.84
0.00 150.23 1,494.79
0.00 903.91 334.45

0.00 2.59 62.78


0.00 5.63 121.78
0.00 1.20 51.19
0.00 17.64 1,200.23
0.00 8.37 103.45
0.00 8.37 80.18
284.93 0.00 0.00
-0.01 622.52 4,625.33

0.00 5.11 767.78


0.00 0.72 164.38
0.00 8.67 186.06
0.00 1.62 28.03
0.00 42.64 665.18
0.00 579.87 16,706.05
2,960.65 0.00 0.00
196.36 0.00 0.00
51.50 0.00 0.00

0.00 1.13 286.10


0.00 20.20 68.88

0.00 0.62 189.63


0.00 9.90 454.61
0.00 195.70 667.34

0.00 0.31 82.82


0.00 2.81 134.51
0.00 79.16 266.77

0.00 2.09 637.72


0.00 12.56 1,089.45
0.00 199.41 677.99

0.00 1.53 428.61


0.00 7.67 213.46
0.00 93.45 317.73

8,716.55 0.00 0.00


983.54 0.00 0.00
1,398.86 0.00 0.00

0.00 41.64 1,454.90


0.00 4.10 263.63

0.00 8.78 116.25


0.00 633.82 6,788.21
0.00 333.31 6,542.88
0.00 171.32 3,846.13
0.00 32.66 936.69
0.00 169.86 1,544.03
0.00 6.70 157.99
447.08 0.00 0.00

1,515.03 0.00 0.00

0.00 92.89 1,962.77


2,956.56 0.00 0.00
79.09 0.00 0.00

56.73 67.45 510.57

295.45 0.00 0.00


100.63 32.31 570.25
3,235.61 0.00 0.00

1,092.80 0.00 0.00


24,825.94 0.00 0.00
3,192.00 0.00 0.00
5,838.94 0.00 0.00
406.24 0.00 0.00

1,313.76 0.00 0.00


73.92 0.00 0.00

2,338.35 0.00 0.00

2,871.20 0.00 0.00


1,823.21 0.00 0.00
885.72 0.00 0.00
177.34 0.00 0.00
558.84 0.00 0.00
212.19 0.00 0.00
121.76 0.00 0.00
1,836.85 0.00 0.00
960.09 0.00 0.00

75.63 0.00 0.00


75.36 0.00 0.00
25.21 0.00 0.00

50.65 422.06 151.94

0.00 4.00 223.44


0.00 24.80 197.66
0.00 11.00 93.61
0.00 3.00 31.02
0.00 0.00 0.00
0.00 0.00 0.00
85.04 0.00 0.00

293.65 0.00 0.00


0.00 3.00 130.08
0.00 5.00 188.35
0.00 1.00 35.02
0.00 37.00 320.05
0.00 37.00 1,747.14
0.00 37.00 1,309.43
0.00 28.70 532.39
978.67 0.00 0.00
0.00 10.70 186.07
45.75 0.00 0.00
48.23 0.00 0.00
0.00 1.00 100.45
0.00 2.00 33.34
0.00 1.00 11.92
0.00 3.00 36.15
0.00 2.00 24.26
0.00 7.00 83.44
253.68 0.00 0.00
0.00 1.00 21.78
0.00 3.00 50.31
0.00 2.00 27.64
0.00 1.00 29.60

101.60 0.00 0.00


25.40 0.00 0.00

0.00 269.67 728.11


0.00 18.00 304.56
0.00 17.24 593.92
0.00 202.74 624.44

97.05 5.00 97.05

412.83 0.00 0.00


62.16 0.00 0.00
842.71 0.00 0.00
477.53 0.00 0.00

360.18 0.00 0.00


188.10 0.00 0.00
60.40 0.00 0.00

702.91 0.00 0.00


1,068.48 0.00 0.00
62.53 0.00 0.00

291.26 0.00 0.00


582.52 0.00 0.00
93.98 0.00 0.00

111.45 0.00 0.00


74.30 0.00 0.00
74.30 0.00 0.00
513.81 0.00 0.00
468.60 0.00 0.00
234.30 0.00 0.00

0.00 649.07 3,894.42


0.00 5.27 27.83
0.00 1.89 45.63
316.17 563.65 2,057.32
0.00 3.00 165.69
0.00 110.41 353.31
0.00 1.00 361.00
0.00 87.72 1,084.22
0.00 87.72 872.82
0.00 715.30 1,273.24

0.00 31.82 771.32


0.00 7.85 169.79
0.00 0.89 37.97
0.00 46.50 574.74
0.00 46.50 445.47
0.00 0.00 0.00
0.00 147.53 1,096.15

0.00 5.32 799.33


0.00 1.88 429.22
0.00 36.52 783.72
0.00 18.72 323.85
0.00 277.41 4,327.60
0.00 371.66 10,707.52
611.51 0.00 0.00
52.99 0.00 0.00
134.42 0.00 0.00

0.00 13.10 3,316.79


0.00 192.54 656.56

0.00 3.98 1,217.32


0.00 87.75 4,029.48
0.00 1,589.46 5,420.06

0.00 2.13 569.07


0.00 20.40 976.55
0.00 742.70 2,502.90

0.00 1.65 503.46


0.00 12.04 1,044.35
0.00 148.73 505.68

4,242.64 0.00 0.00


4,518.68 0.00 0.00
3,049.02 0.00 0.00
2,956.71 0.00 0.00
373.06 0.00 0.00
4,790.71 0.00 0.00
4,434.39 0.00 0.00
630.59 0.00 0.00
1,167.24 0.00 0.00
2,210.64 0.00 0.00

0.00 81.15 3,031.76


0.00 16.35 991.14

0.00 9.30 123.13


0.00 647.93 6,939.33
0.00 238.05 4,672.92
0.00 61.50 1,380.68
0.00 20.40 585.07
0.00 102.11 928.18
0.00 2.90 68.38
455.18 0.00 0.00

2,828.66 0.00 0.00

0.00 131.87 2,786.41


4,232.06 0.00 0.00
77.45 0.00 0.00
0.00 18.03 232.77

686.52 0.00 0.00


0.00 305.19 1,818.93

312.95 0.00 0.00

4,596.48 0.00 0.00

2,224.00 0.00 0.00


7,025.77 0.00 0.00
252.77 0.00 0.00

772.80 0.00 0.00


147.84 0.00 0.00

2,823.11 0.00 0.00

2,935.12 0.00 0.00


1,302.13 0.00 0.00
317.96 0.00 0.00
110.77 0.00 0.00
363.15 0.00 0.00
953.01 0.00 0.00
640.79 0.00 0.00
1,251.28 0.00 0.00

75.63 0.00 0.00


75.36 0.00 0.00
25.21 0.00 0.00

64.38 536.48 193.13


0.00 3.00 167.58
0.00 8.56 68.22
70.88 0.00 0.00
0.00 3.00 25.53
23.26 0.00 0.00
43.33 0.00 0.00

0.00 2.00 86.72


0.00 3.00 113.01
377.55 0.00 0.00
0.00 1.00 35.02
0.00 20.00 173.00
0.00 20.00 944.40
0.00 20.00 707.80
0.00 20.00 371.00
0.00 15.00 260.85
721.60 0.00 0.00
45.75 0.00 0.00
96.46 0.00 0.00
-0.01 1.00 100.46
0.00 3.00 35.76
0.00 4.00 66.68
0.00 2.00 24.26
0.00 1.00 11.92
0.00 1.00 16.77
0.00 1.00 13.82

101.60 0.00 0.00


25.40 0.00 0.00

0.00 241.21 651.27


-0.01 54.73 926.04
132.30 67.26 2,317.10
7.27 46.00 141.68

77.64 4.00 77.64

2,126.24 0.00 0.00


866.22 0.00 0.00
1,060.29 0.00 0.00
241.28 0.00 0.00
651.26 0.00 0.00
303.81 0.00 0.00

344.52 0.00 0.00


119.70 0.00 0.00
86.35 0.00 0.00

2,136.96 0.00 0.00


62.53 0.00 0.00

291.26 0.00 0.00


582.52 0.00 0.00
219.84 0.00 0.00

111.45 0.00 0.00


74.30 0.00 0.00
74.30 0.00 0.00
57.09 0.00 0.00
156.20 0.00 0.00
312.40 0.00 0.00
204.78 0.00 0.00
1,050.32 0.00 0.00
2,193.15 0.00 0.00

160,781.22
12,862.50
8,039.07
181,682.79

181,682.79

SALDO

Monto
0.00 385.06 2,310.36
0.00 2.18 157.96
0.00 14.67 77.46
0.00 80.58 257.86
0.00 69.21 855.44
0.00 69.21 688.64
0.00 567.60 1,010.33

0.00 13.75 333.30


0.00 6.46 139.73
0.00 39.96 938.26
0.00 5.10 217.57
0.00 65.83 813.66
0.00 65.83 630.65
0.00 0.00 0.00
0.00 447.53 3,325.14

0.00 8.11 1,218.53


0.00 2.62 598.17
0.00 5.23 112.24
0.00 10.98 189.95
0.00 368.78 10,624.55
503.85 0.00 0.00
292.34 0.00 0.00
92.70 0.00 0.00

0.00 7.69 1,947.03


0.00 119.38 407.09

0.00 2.34 715.71


0.00 37.40 1,717.41
0.00 404.73 1,380.13

0.00 1.04 277.86


0.00 11.18 535.19
0.00 230.81 777.83

2,287.95 0.00 0.00


355.16 0.00 0.00
105.91 0.00 0.00
3,164.22 0.00 0.00
1,760.42 0.00 0.00
693.39 0.00 0.00

0.00 173.77 6,071.52

31.78 0.00 0.00


0.00 537.37 5,755.23
0.00 278.16 5,460.28
0.00 98.60 2,213.57
0.00 11.76 337.28
0.00 175.22 1,592.75

1,852.00 0.00 0.00

0.00 2.97 45.20


97.06 0.00 0.00

80.76 0.00 0.00


0.03 39.17 691.32

315.39 0.00 0.00

2,368.00 0.00 0.00


11,644.25 0.00 0.00
607.79 0.00 0.00

1,081.92 0.00 0.00


73.92 0.00 0.00

2,199.02 0.00 0.00

2,434.29 0.00 0.00


1,521.54 0.00 0.00
509.76 0.00 0.00
63.86 0.00 0.00
86.46 0.00 0.00
259.38 0.00 0.00
31.40 0.00 0.00
1,410.47 0.00 0.00
401.47 0.00 0.00

75.63 0.00 0.00


75.36 0.00 0.00
25.21 0.00 0.00

38.50 345.00 124.20

0.00 2.00 111.72


0.00 6.40 51.01
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
43.33 0.00 0.00

0.00 0.00 0.00


209.75 0.00 0.00
0.00 0.00 0.00
35.02 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
563.75 0.00 0.00
0.00 0.00 0.00
45.75 0.00 0.00
48.23 0.00 0.00
100.45 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
60.40 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

101.60 0.00 0.00


25.40 0.00 0.00

0.00 308.85 833.90


599.43 125.00 4,306.25
0.01 166.45 512.66

38.82 3.00 58.23

2,687.90 0.00 0.00


716.91 0.00 0.00
384.62 0.00 0.00
379.95 0.00 0.00

234.90 0.00 0.00


136.80 0.00 0.00
17.27 0.00 0.00

486.63 0.00 0.00


801.36 0.00 0.00
62.53 0.00 0.00

291.26 0.00 0.00


873.78 0.00 0.00
281.94 0.00 0.00

74.30 0.00 0.00


74.30 0.00 0.00
74.30 0.00 0.00
685.08 0.00 0.00
624.80 0.00 0.00
102.39 0.00 0.00

0.00 251.48 1,508.88


0.00 4.87 25.71
0.00 0.66 15.93
0.00 0.00 0.00
0.00 0.00 0.00
0.00 68.70 219.84
0.00 1.00 361.00
0.00 38.36 474.13
0.00 38.36 381.68
103.95 0.00 0.00
0.00 945.00 1,682.10

0.00 25.34 614.24


0.00 9.96 215.43
0.00 8.97 382.66
0.00 32.92 406.89
0.00 32.92 315.37
471.47 0.00 0.00
0.00 298.00 2,214.14

0.00 10.00 1,502.50


-0.01 2.50 570.78
0.00 32.00 686.72
0.00 15.84 274.03
205.46 0.00 0.00
2,812.72 0.00 0.00
180.56 0.00 0.00
55.64 0.00 0.00
17.51 0.00 0.00

0.00 11.09 2,807.88


0.00 135.76 462.94

0.00 3.01 920.64


0.00 46.55 2,137.58
0.00 690.61 2,354.98

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

10,677.10 0.00 0.00


769.06 0.00 0.00
159.79 0.00 0.00
2,292.53 0.00 0.00
4,948.85 0.00 0.00
253.13 0.00 0.00
332.95 0.00 0.00

0.00 168.00 5,869.92

152.26 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
267.40 0.00 0.00
455.18 0.00 0.00
1,563.80 0.00 0.00
3,713.60 0.00 0.00

1,489.27 0.00 0.00


4,445.79 0.00 0.00
120.26 0.00 0.00

711.88 0.00 0.00


0.00 0.00 0.00

370.82 0.00 0.00

5,257.73 0.00 0.00

1,152.00 0.00 0.00


4,204.95 0.00 0.00
305.13 0.00 0.00

540.96 0.00 0.00


517.44 0.00 0.00

1,466.33 0.00 0.00

1,875.60 0.00 0.00


842.38 0.00 0.00
375.81 0.00 0.00
465.73 0.00 0.00
82.88 0.00 0.00
219.02 0.00 0.00
1,474.21 0.00 0.00
865.09 0.00 0.00
271.31 0.00 0.00

75.63 0.00 0.00


75.36 0.00 0.00
25.21 0.00 0.00

340.20 0.00 0.00

167.58 0.00 0.00


68.22 0.00 0.00
70.88 0.00 0.00
25.53 0.00 0.00
23.26 0.00 0.00
43.33 0.00 0.00

86.72 0.00 0.00


113.01 0.00 0.00
35.02 0.00 0.00
173.00 0.00 0.00
944.40 0.00 0.00
707.80 0.00 0.00
371.00 0.00 0.00
45.75 0.00 0.00
96.46 0.00 0.00
100.45 0.00 0.00
35.76 0.00 0.00
66.68 0.00 0.00
24.26 0.00 0.00
11.92 0.00 0.00
16.77 0.00 0.00
13.82 0.00 0.00

101.60 0.00 0.00


25.40 0.00 0.00

531.45 0.00 0.00


5,666.34 0.00 0.00
452.76 0.00 0.00

97.05 0.00 0.00

1,162.19 0.00 0.00


532.50 0.00 0.00
1,136.12 0.00 0.00
480.38 0.00 0.00

391.50 0.00 0.00


119.70 0.00 0.00
69.08 0.00 0.00
30.20 0.00 0.00

1,784.31 0.00 0.00


868.14 0.00 0.00
312.65 0.00 0.00

291.26 0.00 0.00


291.26 0.00 0.00
187.96 0.00 0.00

111.45 0.00 0.00


74.30 0.00 0.00
74.30 0.00 0.00
742.17 0.00 0.00
468.60 0.00 0.00
78.10 0.00 0.00

123,730.48
9,898.44
6,186.53
139,815.45

139,815.45
SALDO

Monto

0.00 11.25 59.40


0.00 504.23 5,551.57
0.00 53.50 1,747.31
0.00 175.37 1,052.22
0.00 8.47 204.47
0.00 3.00 519.12
0.00 741.73 9,167.78
0.00 741.73 7,380.21
0.00 71.38 260.54
0.00 4.00 201.60
555.77 9,636.79 3,083.77

2,130.55 0.00 0.00


1,864.18 310.00 4,916.60
2,170.59 1,720.00 6,088.80
1,970.88 0.00 0.00
314.56 70.00 865.20
243.81 70.00 670.60

15,822.82 0.00 0.00


2,411.99 9.80 2,606.11
3,106.32 5.00 1,487.70
6,129.60 40.00 10,011.60
9,735.95 0.00 0.00
306.64 7.20 325.15
299.19 3.00 157.47
1,191.93 40.00 1,946.80

639.61 0.00 0.00


813.60 0.00 0.00
850.85 0.00 0.00

1,768.08 0.00 0.00

5,270.59 0.00 0.00


1,197.92 0.00 0.00
2,084.92 0.00 0.00
44,480.92 520.00 15,917.20
3,568.36 0.00 0.00
107,400.15 0.00 0.00
6,296.34 0.00 0.00

8,094.79 0.00 0.00


7,604.84 0.00 0.00
495.00 0.00 0.00

1,888.62 0.00 0.00


11,539.20 0.00 0.00
1,347.18 0.00 0.00
4,744.44 0.00 0.00
5,270.44 0.00 0.00
3,025.26 0.00 0.00
4,532.68 0.00 0.00

7,338.53 0.00 0.00


20.18 0.00 0.00

1,163.17 120.00 1,038.00


2,116.40 44.00 2,077.68
4,124.35 100.00 3,539.00
1,397.83 160.00 1,324.80
639.19 80.00 637.60
14.92 2.00 29.84
8.51 2.00 17.02
1.19 1.00 1.19
46.52 5.00 58.15
0.00 0.00 0.00
10.34 1.00 10.34
0.00 1.00 43.33
726.18 0.00 0.00
1,021.28 0.00 0.00

753.24 65.00 562.25


279.72 120.00 220.80
484.94 120.00 382.80
1,311.32 50.00 1,007.00
2,401.20 50.87 1,200.63
10,078.29 0.00 0.00
967.49 0.00 0.00
1,808.10 0.00 0.00

135.19 0.00 0.00


561.42 0.00 0.00
2,684.16 0.00 0.00

431.80 0.00 0.00

524.28 282.00 2,439.30


185.86 470.00 864.80
322.22 470.00 1,499.30
526.86 121.84 2,453.86
464.75 124.00 2,078.24
1,233.39 200.00 3,710.00
1,594.36 30.56 531.40
16.67 2.00 33.34
11.92 0.00 0.00
16.61 0.00 0.00
43.56 0.00 0.00
12.13 1.00 12.13
401.80 4.00 401.80
230.56 2.00 230.56

752.53 454.43 1,254.23

1,065.59 70.00 605.50


3,150.99 38.00 1,794.36
4,958.85 80.00 2,831.20

2,968.00 0.00 0.00


8,256.09 450.00 4,923.00
1,823.42 52.00 793.52
3,407.29 0.00 0.00

1,725.44 1.00 215.68

9,223.29 0.00 0.00


13,430.00 0.00 0.00
7,388.68 420.00 4,993.80
5,737.94 250.00 3,855.00
34,766.79 0.00 0.00
1,532.05 85.00 1,014.05
1,665.52 0.00 0.00
761.96 98.00 517.44
799.58 270.00 534.60
1,660.19 430.00 1,113.70

300.51 0.00 0.00

77.82 0.00 0.00

111.45 0.00 0.00


37.15 0.00 0.00
156.20 0.00 0.00
102.39 0.00 0.00
525.16 0.00 0.00
1,462.10 0.00 0.00
1,130.20 0.00 0.00

1,199.88 0.00 0.00


3,024.00 0.00 0.00

3,608.40 0.00 0.00


3,366.12 0.00 0.00

8,439.34 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.84 242.13


0.00 30.00 1,054.80
0.00 110.00 355.30

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

31.00 0.00 0.00

237.33 0.00 0.00


289.80 0.00 0.00
414.32 0.00 0.00
1,048.75 0.00 0.00
150.58 0.00 0.00
95.48 0.00 0.00
728.57 0.00 0.00
448,889.75
35,911.18
22,444.50
507,245.43

507,245.43

SALDO

Monto

70,843.95
-0.02
160,322.84
134,093.16
684,850.75
181,682.77
139,815.46

507,245.40

1,878,854.31
48.90%
RESUMEN DE VALORIZACIONES DE OBRA EJECUTADAS
Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVO DE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A
Valor Referencial (S/.) : 4,572,084.75 con IGV
Costos al : February-2010
Monto del Contrato (S/.) : 4,572,084.75 con IGV
Factor de Relacion : 1.00000
Plazo de Ejecucion : 240 dias calendarios
Supervisor : ING. ANTONIO VALENZUELA SALAS
Residente : ING. PABLO SARMIENTO REYES

Mes 1 Mes 2 Mes 3 Mes 4 Mes 5 Mes 6 Mes 7 Mes 8 Mes 9


28-Jan-11 01-Feb-11 01-Mar-11 01-Apr-11 01-May-11 01-Jun-11 01-Jul-11 01-Aug-11 01-Sep-11 Monto
Items Subprepuestos Monto Total (S/.) Acumulado Saldo
31-Jan-11 28-Feb-11 31-Mar-11 30-Apr-11 31-May-11 30-Jun-11 31-Jul-11 31-Aug-11 24-Sep-11
( 04 ) ( 28 ) ( 31 ) ( 30 ) ( 31 ) ( 30 ) ( 31 ) ( 31 ) ( 24 )

001 PABELLON ADMINISTRATIVO 176,979.46 6,873.74 27,695.32 43,850.78 27,715.68 106,135.52 70,843.94

002 PABELLON ABC 271,329.66 34,906.57 102,537.28 95,202.06 38,683.77 271,329.68 -0.02

003 PABELLON D y E 420,856.33 21,265.76 85,940.94 83,470.32 69,856.46 260,533.48 160,322.85

004 PABELLON F y H 307,921.10 9,010.02 56,487.91 56,045.92 52,284.09 173,827.94 134,093.16

005 PABELLON G 1,271,214.82 78,560.53 110,280.01 156,093.70 241,429.83 586,364.07 684,850.75

006 PABELLON I y J 361,903.07 21,078.12 89,575.54 59,435.41 10,131.23 180,220.30 181,682.77

007 PABELLON K y L 272,738.08 5,433.78 38,389.74 54,293.40 34,805.70 132,922.62 139,815.46

TRATAMIENTO PAISAJISTICO DEL PATIO DE HONOR Y CERCO


008 PERIMETRICO 759,145.51 21,217.57 14,578.98 107,402.36 108,701.20 251,900.11 507,245.40

SUB TOTAL (sin IGV) 3,842,088.03 0.00 198,346.09 525,485.72 655,793.95 583,607.96 0.00 0.00 0.00 0.00 1,963,233.72 1,878,854.31

TOTAL (con IGV) 4,572,084.76 0.00 236,031.85 625,328.01 780,394.80 694,493.47 0.00 0.00 0.00 0.00 2,336,248.13 2,235,836.63

AVANCE PORCENTUAL MENSUAL 0.00% 5.16% 13.68% 17.07% 15.19% 0.00% 0.00% 0.00% 0.00%

AVANCE PORCENTUAL ACUMULADO 0.00% 5.16% 18.84% 35.91% 51.10%


INDICES UNIFICADOS - ZONA 03

Año
Indices 2010 2011
Feb-10 Jan-11 Feb-11 Mar-11 Apr-11
03 Acero de Construcción corrugado (Indice Base Jul.1992=100,0) 439.27 528.61 573.48 580.80 586.47
05-3 Agregado grueso (Indice Base Jul.1992=100,0) 332.39 352.46 358.90 364.19 360.53
19 Cable NYY - N2XY (Indice Base Jul.1992=100,0) 647.64 762.06 781.47 778.19 786.31
21-3 Cemento Portland Tipo I (Indice Base Jul.1992=100,0) 357.75 357.75 357.75 354.74 354.74
39 Índice General de precios al Consumidor (Indice Base Jul.1992=100,0) 349.61 356.05 357.41 359.92 362.38
43-3 Madera nac para enc/car (Indice Base Jul.1992=100,0) 684.75 738.70 738.57 735.31 730.68
47 Mano de obra (Indice Base Jul.1992=100,0) 415.58 427.68 427.68 427.68 427.68
49 Maquinaria y Equipo Imp. (Indice Base Jul.1992=100,0) 245.24 238.94 238.57 240.07 243.55
54 Pintura Látex (Indice Base Jul.1992=100,0) 329.49 327.68 327.55 330.00 330.58
Fuente : Instituto Nacional de Estadística e Informática
FORMULAS POLINOMICAS
Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVO DE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Contratista : VASMER CADS S.A
Fecha de Valor Referencial : February-2010
Ubicación : JUNIN - HUANCAYO - TAMBO
Area Geográfica : 3
Mes Valorizado : (Periodo : Del 01 Mayo al 31 Mayo 2011)
Simbolo Código Coef. Ind. Base Feb-2011 Mar-2011 Apr-2011 May-2011 Jun-2011 Jul-2011 Aug-2011
Elemento Representativo %
Monomio No. Inc. Feb-2010 Indice K Indice K Indice K Indice K Indice K Indice K Indice K
SUBPRESUPUESTO : 001 GENERAL
J MANO DE OBRA 47 0.307 100.000% 415.58 427.68 427.68 427.68 427.68
415.58 427.68 0.316 427.68 0.316 427.68 0.316 427.68 0.316
A AGREGADO GRUESO 05 0.097 100.000% 332.39 352.46 358.90 364.19 360.53
332.39 352.46 0.103 358.90 0.105 364.19 0.106 360.53 0.105
C CEMENTO PORTLAND TIPO I 21 0.076 100.000% 357.75 357.75 357.75 354.74 354.74
357.75 357.75 0.076 357.75 0.076 354.74 0.075 354.74 0.075
A ACERO DE CONSTRUCCION CORRUGADO 03 0.059 100.000% 439.27 528.61 573.48 580.80 586.47
439.27 528.61 0.071 573.48 0.077 580.80 0.078 586.47 0.079
C CABLE NYY Y NKY 19 0.050 100.000% 647.64 762.06 781.47 778.19 786.31
647.64 762.06 0.059 781.47 0.060 778.19 0.060 786.31 0.061
M MAQUINARIA Y EQUIPO IMPORTADO 49 0.046 100.000% 245.24 238.94 238.57 240.07 243.55
245.24 238.94 0.045 238.57 0.045 240.07 0.045 243.55 0.046
PINTURA LATEX 54 0.068 48.529% 329.49 327.68 327.55 330.00 330.58
MP MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 43 51.471% 684.75 738.70 738.57 735.31 730.68
512.35 539.24 0.072 539.11 0.072 538.62 0.071 536.52 0.071
IGP INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 0.297 100.000% 349.61 356.05 357.41 359.92 362.38
349.61 356.05 0.302 357.41 0.304 359.92 0.306 362.38 0.308

COEFICIENTE DE REAJUSTE (K) 1.000 1.044 1.055 1.057 1.061 0.000 0.000 0.000
CALCULO DEL REAJUSTE AUTORIZADO

Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVO DE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A
Costos al : February-2010
Monto del Contrato (S/.) : 4,572,084.75 con IGV
Plazo de Ejecucion : 240 dias calendarios
Supervisor : ING. ANTONIO VALENZUELA SALAS
Residente : ING. PABLO SARMIENTO REYES
Mes Valorizado : (Periodo : Del 01 Mayo al 31 Mayo 2011)

VALORIZACION PROGRAMADO EJECUTADO REINTEGRO


VAL INDICE REAJUSTE VAL INDICE REAJUSTE BRUTO
Nº MES
V K R=(Vx(K-1)) V K R=(Vx(K-1)) AUTORIZADO

001 - GENERAL
1 January-2011 3,506.66 0.00
2 February-2011 345,182.46 1.044 15,188.03 198,346.09 1.044 8,727.23 8,727.23
3 March-2011 446,973.10 1.055 24,583.52 525,485.72 1.055 28,901.71 28,901.71
4 April-2011 701,701.34 1.057 39,996.98 655,793.95 1.057 37,380.26 37,380.26
5 May-2011 568,611.56 1.061 34,685.31 583,607.96 1.061 35,600.09 35,600.09
6 June-2011 547,574.29 0.000 0.00 0.000 0.00 0.00
7 July-2011 471,346.09 0.000 0.00 0.000 0.00 0.00
8 August-2011 425,466.40 0.000 0.00 0.000 0.00 0.00
9 September-2011 331,726.13 0.000 0.00 0.000 0.00 0.00
SUB-TOTAL 3,842,088.03 114,453.84 1,963,233.72 110,609.29 110,609.29

TOTAL 3,842,088.03 1,963,233.72 110,609.29 110,609.29


RESUMEN DE VALORIZACION MENSUAL Nº 04
Obra : MEJORAMIENTO INTEGRAL DEL SERVICIO EDUCATIVO DE LA I.E.P POLITECNICO REGIONAL DEL CENTRO EL TAMBO - HUANCAYO
Ubicación : JUNIN - HUANCAYO - TAMBO
Tipo de Proceso : ADJUDICACION MENOR CUANTIA Nº 198-2010-GRJ-CE-O
Contratista : VASMER CADS S.A
Valor Referencial (S/.) : 4,572,084.75 con IGV
Costos al : February-2010
Monto del Contrato (S/.) : 4,572,084.75 con IGV
Factor de Relacion : 1.00000
Plazo de Ejecucion : 240 dias calendarios
Supervisor : ING. ANTONIO VALENZUELA SALAS
Residente : ING. PABLO SARMIENTO REYES
Mes Valorizado : DEL 01 DE MAYO AL 31 DE MAYO DEL 2011

MONTO CONTRATO VALORIZACION % AVANCE SALDO POR


DESCRIPCION (S/IGV) ACUMULADO VALORIZAR
ANTERIOR ACTUAL ACUMULADO
A: VALORIZACION CONTRACTUAL
001 - PABELLON ADMINISTRATIVO 176,979.46 78,419.84 27,715.68 106,135.52 59.97% 70,843.94
002 - PABELLON A,B,C 271,329.66 232,645.91 38,683.77 271,329.68 100.00% -0.02
003 - PABELLON D Y E 420,856.33 190,677.02 69,856.46 260,533.48 61.91% 160,322.85
004 - PABELLON F Y H 307,921.10 121,543.85 52,284.09 173,827.94 56.45% 134,093.16
005 - PABELLON G 1,271,214.82 344,934.24 241,429.83 586,364.07 46.13% 684,850.75
006 - PABELLON I Y J 361,903.07 170,089.07 10,131.23 180,220.30 49.80% 181,682.77
007 - PABELLON K Y L 272,738.08 98,116.92 34,805.70 132,922.62 48.74% 139,815.46
008 - TRATAMIENTO PAISAJISTICO DEL PATIO DE HONOR Y CERCO PERIMETRICO 759,145.51 143,198.91 108,701.20 251,900.11 33.18% 507,245.40
TOTAL (A) 3,842,088.03 1,379,625.76 583,607.96 1,963,233.72 51.10% 1,878,854.31
AVANCE FISICO DE OBRA 35.91% 15.19% 51.10% 48.90%
B: REAJUSTES
001 - GENERAL 75,009.20 35,600.09 110,609.29
75,009.20 35,600.09 110,609.29
VALORIZACION BRUTA (VB=A+B) 1,454,634.96 619,208.05 2,073,843.01
C: DEDUCCIONES
DEDUCCION DEL ADELANTO EN EFECTIVO
DEDUCCIONDEL ADELANTO PARA MATERIALES
TOTAL (C)
D: AMORTIZACIONES
AMORTIZACION DEL ADELANTO EN EFECTIVO 768,417.61 275,925.15 116,721.59 392,646.74 51.10% 375,770.87
AMORTIZACION DEL ADELANTO PARA MATERIALES 1,436,727.56 245,230.48 218,236.93 463,467.40 32.26% 973,260.16
TOTAL (D) 2,205,145.17 521,155.63 334,958.52 856,114.14 38.82% 1,349,031.03
VALORIZACION NETA (VN=VB-D-C) 933,479.33 284,249.53 1,217,728.87
E: RETENCIONES
FONDO DE GARANTIA (5%*VB)
GASTOS DE LICITACION
MULTA POR ATRASO DE OBRA
TOTAL (E) 0.00 0.00 0.00
F: MONTO A PAGAR AL CONTRATISTA
EN EFECTIVO 933,479.33 284,249.53 1,217,728.87
EN I.G.V. 168,026.28 51,164.92 219,191.20
TOTAL (F) 1,101,505.62 335,414.45 1,436,920.07
TOTAL COMPROMISO A SOLICITAR 1,101,505.62 335,414.45 1,436,920.07