Vous êtes sur la page 1sur 11

Republic of the Philippines

Province of Ilocos Norte


MUNICIPALITY OF BURGOS
OFFICE OF THE MUNICIPAL ENGINEER

INDIVIDUAL PROGRAM OF WORK


CONSTRUCTION OF STREET LIGHT FOUNDATION

NAME/LOCATION OF PROJECT: Appropriation


CONSTRUCTION OF STREET LIGHT Source of Fund
Issued Obligated Authority
FOUNDATION Released
BURGOS, ILOCOS NORTE Calendar Days to complete
Desirable Starting Date

PROJECT CATEGORY:

PROJECT DESCRIPTION:
Construction of Street Light Foundation

MINIMUM EQUIPMENT REQUIREMENT TECHNICAL PERSONNEL REQUIRED


Description No. Description No. Description No.

skilled 1
laborer
Laborer 2

ESTIMATED COST OF PROPOSED WORK

ITEM % OF UNIT
NO. DESCRIPTION TOTAL UNIT QTY TOTAL COST Adjusted Unit Cost

1 REINF.CONCRETE WORKS sq.m. 0.17 6,666.08


2 Excavation sq.mtrs 0.36 -
3 -
4 -
5 -
TOTAL 6,666.08
DETAILED ESTIMATES
CONSTRUCTION OF STREET LIGHT FOUNDATION

BREAKDOWN OF ESTIMATED EXPENDITURES % TOTAL AMOUNT

I. ESTIMATED COST:
A. DIRECT COST:

1. Materials 62.8% 4,185.00


1.1 Supply/Delivery
1.2 Testing of Materials
2. Labor including fringe benefits 13.5% 900.00
3. Equipment rentals 3.8% 250.00
B. Indirect Cost
1. Overhead, Contengency, miscellaneous 7.2% 480.15
(7% to 12% of a1 to a4)
2. Profit (5% to 12% of a1 to a4) 8.0% 533.50
3. Comprehensive all risk insurance
(1.5% of a1 to a4)
4. VAT ( 10% of a3 to a4) 4.8% 317.43

SUB-TOTAL (CONTRACT COST) 100.0% 6,666.08


II. ESTIMATED GOVERNMENT EXPENDITURES
1. Engineering and administrative
overhead (3.5% of a4)
2. Project superintendence/prel. Eng'g
3. advertisement

III. CONTENGENCIES/RESERVE
1. Physical ( up to 5% of the
estimated contract cost)
2. Price escalation ( up to 12% of the
estimated contract cost)

TOTAL ESTIMATED PROJECT COST 6,666.08


100% 6,666.08

PREPARED BY: CHECKED AND REVIEWED:

WILMER A. GARALDE MINERVA S. PASCUA


Engineer III Municipal Engineer

APPROVED:

RODOLFO L. GARCIA
Municipal Mayor
d/jet/pow2012/welcomearc1012 500thou

DETAILED ESTIMATES
CONSTRUCTION OF STREET LIGHT FOUNDATION
ITEM NO. % DESCRIPTION QUANTITY & UNIT
1 REINF.CONCRETE WORKS 0.17125 cu.m.

DESCRIPTION QUANTITY UNIT UNIT PRICE SUB-TOTAL


-
-
Vol.of col. Ftng=.5x.5x.20=0.05 cu.m.
Vol.of col.=0.25x0.25x1.3=0.08125 cu.m. -
-
0.17125 cu.m. -
portland cement 0.8 BAGS 250 200.00
Sand Aggregates 0.1 CU.M. 600
MATERIAL COST

60.00
3/4'' Gravel 0.05 CU.M. 500 25.00
2 1/2'' dia. S40 Pipe, 4.5m le 1.0 CU.M. 2500 2,500.00
RSB10MM 1.5 PCS 200 300.00
TIEWIRE#16 0.5 KLS 100 50.00
ORD. PLYWOOD 1/4" 1.0 PCS 450 450.00
2-2X2X12 LUMBER 8.0 BD.FT. 65 520.00
CWN 0.5 KLS 100 50.00
welding rod 0.3 kls 120 30.00
TOTAL MATERIAL COST … 4,185.00
EQUIPMENT COST

QUANTITY DAYS RATE SUB-TOTAL


Welding machine 1 0.50 500.00 250.00
-

TOTAL EQUIPMENT COST…. 250.00


DESCRIPTION NUMBER DAYS RATE SUB-TOTAL
skilled laborer 1 1.0 450 450.0
-
LABOR COST

welder 1 1.0 450 450.0

TOTAL LABOR COST 900.0

Direct Cost 5,335.0


OCM 480.15
CP 533.50
1% M/D
VAT 317.43
Total 6,666.08

Unit Cost 38,926.03

DETAILED ESTIMATES
CONSTRUCTION OF STREET LIGHT FOUNDATION
ITEM NO. % DESCRIPTION QUANTITY & UNIT
2 Excavation 0.36 sq.m.

DESCRIPTION QUANTITY UNIT UNIT PRICE SUB-TOTAL


L COST
MATERIAL COST

-
-
-
-
-
-

TOTAL MATERIAL COST … -


EQUIPMENT COST

QUANTITY DAYS RATE SUB-TOTAL

TOTAL EQUIPMENT COST…. -


DESCRIPTION NUMBER DAYS RATE SUB-TOTAL

-
LABOR COST

TOTAL LABOR COST -

Direct Cost -
OCM -
CP -
1% M/D
VAT -
Total -

Unit Cost -
-
9.47 40.7603 0
5.33 44.09006 0
3.7 54.05405 -
-

Vous aimerez peut-être aussi