Description of the project The solution


Track renewal for Sleeper pads as vibration protection increase in the level of sound trans-
London Underground mission through the tunnel walls. The

T he track of the London Under-


ground District Line was com-
P roviding elastic bearings for this
stretch of the District Line was
the irst major sleeper pad project
elastic Sylodyn® bearings were for the
irst time placed not only on the bot-
tom of the sleepers, but also on the
pletely renewed between Paddington for London Underground: the vibra- ends, thus reducing the transmission
and High Street Kensington stations tion protection requirements called of noise and vibrations through the
in the city centre. Around 173 mil- for the use of full-surface Sylodyn® tunnel wall.
lion passengers use this line every sleeper pads, which are ideal for ef-
year. Starting in July 2011, this very fectively minimising vibrations. Deliv- Comprehensive project support
busy section of track, which is also eries were made both to the CEMEX
part of the Circle Line, was upgrad- sleeper works and directly to London Around 7,000 pads for concrete
ed with new ballast, rails and brand Underground. sleepers and roughly 1,000 pads
new sleepers with pads supplied by for timber sleepers were used on a
Getzner Werkstoffe. This renovated section of the Dis- stretch of track extending over ap-
trict Line runs through very narrow proximately 2.5 kilometres. CEMEX
The sleeper pads protect the track su- tunnels, meaning that there is lit- itted the elastic bearings to the con-
perstructure and reduce the level of tle to no gap between the sleepers crete sleepers directly in its sleeper
vibrations caused by the underground and the drainage channels adjacent works. London Underground itself it-
trains. They also have a beneicial to the tunnel wall. A particular chal- ted the pads to the timber sleepers.
effect on the numerous dwellings lenge in this case was preventing an Getzner was involved in all phases of
alongside the track, as the decrease
in vibrations noticeably improves the
residents' quality of life.

1 2

1 Pre-assembly of the sleeper


pads in the works
2 Sylodyn® bearings on the
ends of the sleepers
3 Installation in the tunnel
the project – from inding the solution Getzner supported us with excellent Some long-term residents living next
and performing calculations to pro- customer service and was also pres- to the track have even written and
viding support to the sleeper works ent on-site during installation, when thanked us for providing them with
and London Underground. required," explains Andrew Carey, greater peace and quiet. Addition-
Sales Manager of the sleeper manu- ally the sleeper pads supplied by
Successful and long-term facturer CEMEX Rail Products. Getzner required no changes to the
collaboration installation programme, methodolo-
Testing confirms effectiveness gy or equipment for the track renew-
The CEMEX sleeper works is already al. Overall, the use of Getzner sleeper
an experienced partner of Getzner in Structure-borne noise measurements pads on this project has been a great
the pre-assembly of sleeper pads. taken following the installation verify success”, stated Mike Barlow, Prin-
the effectiveness of the vibration pro- cipal Project Engineer from London
"We have worked together with tection solution from Getzner. Underground.
Getzner on a number of projects –
both for Network Rail and for London “A signiicant reduction in ground-
Underground. During the implementa- borne vibration has been achieved in
tion of these projects, we were able to a number of neighbouring properties.
gain valuable experience in the instal-
lation of sleeper pads.

Illustration of the installed sleeper with pad

Concrete sleeper

Lateral Sylodyn® bearing with


geotextile protection layer

Sylodyn® sleeper pad with


geotextile protection layer
Facts and igures at a glance
District Line/Circle Line track renovation between High Street Kensington and Paddington

Track length: approx. 2.5 km

Order details

Scope of the order: Padding of 8,000 sleepers


7,000 full-surface sleeper pads for concrete sleepers,
1,000 for timber sleepers
Innovation: Additional elastic bearings on the ends of the sleepers
Client: London Underground/CEMEX Rail Products
Operator: London Underground/Transport for London
Project manager: Lukas Mayer
Completion: August 2011
Sleeper manufacturer: CEMEX Rail Products
Construction company: Balfour Beatty

Getzner Werkstoffe GmbH Railway references (extract)

Foundation: 1969 (as a subsidiary of Getzner, — Channel Tunnel Rail Link (UK)
Mutter & Cie) Thameslink, Blackfriars Bridge (UK)
CS LU en © Copyright by Getzner Werkstoffe GmbH | 10-2017


Chief Executive Oficer: Ing. Jürgen Rainalter — Crossrail, London (UK)
Employees: 380 — Extension of the East London Line (UK)
2016 turnover: EUR 80.4 million — Marmaray Tunnel, Istanbul (TR)
Business areas: Railway, construction, industry — Gautrain, Johannesburg (SA)
Headquarter: Bürs (AT) — Attiko Metro, Athens (GR)
Locations: Berlin (DE), Munich (DE), Stuttgart — Metro, Madrid (ES)
(DE), Lyon (FR), Amman (JO), — New York City Subway (USA)
Tokyo (JP), Pune (IN), Beijing (CN),
Kunshan (CN), Charlotte (US)
Ratio of exports: 90 %

AUSTRIA — Bürs GERMANY — Berlin — Munich — Stuttgart FRANCE — Lyon JORDAN — Amman
JAPAN — Tokyo INDIA — Pune CHINA — Beijing USA — Charlotte www.getzner.com

Vous aimerez peut-être aussi