Académique Documents
Professionnel Documents
Culture Documents
CHAPTER - WRD: 7
SCHEDULE OF RATES
CONTENTS PAGES
REFERENCE DATA 1 -- 3
COST OF MATERIALS :
1 Acytelene gas per cum `: 404.00
2 Alloy steel ( Corbon steel : IS : 1570 ) Shafts per kg `: 270.00
3 Alloy steel ( Stainless steel : IS : 1570 ) Pins per kg `: 330.00
4 Bolt / Nut / Washer ( hot dipped galvanized ) per kg `: 127.00
5 Bolt / Nut / Washer ( mild steel ) per kg `: 96.00
6 Bolt / Nut / Washer ( stainless steel ) per kg `: 224.00
7 Bronze / Alluminium alloy ( IS : 305 ) Bearings / Bushes per kg `: 970.00
8 Cast iron blocks per kg `: 55.00
9 Cast steel Drums / Gears per kg `: 205.00
10 Cast steel Pinions per kg `: 210.00
11 Cast steel Wheels / Pulleys / Hubs / Rollers / Retainers per kg `: 170.00
12 Chequered plate per kg `: 44.15
13 Coaltar epoxy paint per ltr `: 256.50
14 Degreasing / derusting / phasphate coating chemical per ltr `: 326.00
15 Forged steel Hooks / Shackles per kg `: 230.00
16 Gas cutting set ( 2 Nos 15 m hose and nozzle unit ) `: 2250.00
17 Grease per kg `: 298.00
18 MS pipe 300 mm dia per kg `: 74.00
19 MS pipe 32 mm dia per Rm `: 208.00
20 Oxygen gas per cum `: 78.00
21 Rails 45 kg / m per tonne `: 52952.00
22 Rubber bottom seal ( flat type ) IS : 11855 per Rm `: 233.00
23 Rubber corner seal ( music note teflon claded ) IS : 11855 per Rm `: 1139.00
24 Rubber corner seal ( music note uncladed ) IS : 11855 per Rm `: 460.00
25 Rubber side seal ( music note teflon claded ) IS : 11855 per Rm `: 1032.00
26 Rubber side seal ( music note uncladed ) IS : 11855 per Rm `: 362.00
27 Rubber side seal ( Z - type ) IS : 11855 per Rm `: 442.00
28 Stainless steel plate / flats per kg `: 189.50
29 Steel wire rope 6x37 construction per kg `: 160.00
30 Structural steel angle / channel / beam / bars per kg `: 41.55
31 Structural steel plate / flats per kg `: 42.05
32 Synthetic enamel paint ( 1st quality ) per ltr `: 259.00
33 Welding electrodes 4 mm x 450 mm ( general purpose ) per No. `: 11.00
34 Welding electrodes 4 mm x 450 mm ( low hydrogen ) / No. `: 21.00
35 Welding electrodes 4 mm x 450 mm ( stainless steel ) per No. `: 66.00
36 Welding holder set ( cable / holder / gloves / mask etc ) per set `: 6750.00
37 Wire brush per Each `: 54.00
38 Zinc per kg `: 229.00
39 Zinc rich ( zinc content : 85 % ) epoxy primer paint per ltr `: 756.00
40 Zinc chromate red oxide primer per ltr `: 209.00
1
GATE / HOIST AND ALLIED WORKS
2
GATE / HOIST AND ALLIED WORKS
OTHER DATA :
1 Contractor's Overheads on Materials / Machinery / Labour % 5.00
2 Contractor's Profit on Materials / Fuel & Energy charges / Labour % 10.00
3 Demand charges per kVA / month `: 196.00
4 Electric power kWhr 8.00
5 Excise duty on cost of supplies % 8.24
6 Insurance charges on gate / hoist parts % on cost 1.00
7 Interest on average capital cost % / annum 11.00
8 Hidden cost on Labour % 15.00
Hidden cost on Labour ( additional for Gate / Hoist works ) % 15.00
9 Small Tools & Plant on Materials / Machinery / Labour % 1.00
10 Sundries ( Lump sum rate for unquantified inputs ) `: 45.00
11 Cost of Power supply arrangements ( Annexure-1.a ) % 2.00
12 Cost of Other enabling works ( Annexure-1.b ) % 1.50
3
GATE / HOIST AND ALLIED WORKS
1. All notes under ' General Notes on Schedule of Rates ' are applicable to ' Gate / Hoist and
Allied Works ' also to the extent they are relevant.
2. All materials / bought out components for embedded parts, gates, hoists and allied works
shall conform to relevant Indian standards / technical specifications and approved drawings.
3. The basic rates are inclusive of preparation of designs / drawings / material schedules etc.,
as per specifications and other technical data including revisions.
4. The basic rates are inclusive of cost of all materials, machinery, labour, fabrication, erection,
commissioning and testing of gates, hoists and other related components as per technical
specifications.
5. The basic rates are inclusive of taxes, duties, levies and all other incidental charges except
sales tax on works contract. Separate provision shall be made in the estimate towards sales
tax on works contract at the rate prevailing at the time of preparation of estimate.
6. The basic rates are inclusive of rehandling at fabrication and erection sites.
7.a. The basic rates are inclusive of 1 km lead and all lifts for structural steel and all leads and lifts
for other materials. For working out additional lead charges for structural steel 1 km lead
included in basic rate shall be deducted from total lead. The quantity of structural steel
for working out additional lead, loading and un-loading charges shall be as per Note: 2 under
each item.
7.b. The basic rates are inclusive of 3 percent provision towards cost of packing, forwarding and
transportation of all materials other than structural steel from their source of supply upto work
site. No lead charges shall be added for materials other than structural steel.
8. Unless otherwise specified the basic rates are inclusive of standard finish required for all the
fabricated and bought out gate and hoist components.
9. The basic rates are inclusive of preparatory works such as rectification of damages, repairing
shop painting, cleaning, positioning and anchoring first stage embedments, cleaning surface
for field painting etc.
10. The basic rates are exclusive of cost of river diversion arrangements, dewatering, desilting etc.
11. Unless otherwise specified the basic rates for items are on per tonne basis. The rate per set
or per number shall be worked out on the basis of rate per tonne and the tonnage computed
as per detailed designs / empirical formulae furnished in the ' Note ' under each item.
12. Minimum dry film thickness for zinc rich epoxy primer paint and coal tar epoxy paint shall be
40 microns per coat and 100 microns per coat respectively.
4
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.1
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts consisting of sill
beam, wall plates, seal seats, anchors, anchor girders, yoke girders, tie flats, trunnion supports,
rope and pulley supports etc., with all accessories for spillway radial gates including cost
of all materials, machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning,
applying one coat of zinc rich epoxy primer and four coats of cold applied coal tar epoxy paint
etc., complete as per specifications and approved drawings with lead upto 1 km and all lifts
for structural steel components and all leads and lifts including packing / forwarding
charges for other materials.
DATA:Embedded parts for radial gate consist of sill beam / wall plates / anchor girders / yoke girders /
tie flats / trunnion supports etc., with all accessories. The weight of embedded parts for radial
gate will be generally at about 25 to 30 percent of weight of radial gate leaf.
Consider embedded parts for radial gate for spillway opening of size 15 m x 9 m at crest.
Size of gate for 15 x 9 m opening at crest with gate sill on d /s 0.6 m below crest level.
Length of gate : 15 m Head of water at sill level : 9.60 m Height of gate : 9.75 m
Weight of radial gate leaf in tonne with end shield and hood based on empirical formula :
2 0.673
Weight of radial gate in tonnes = 0.0710 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
Consider weight of embedded parts in tonnes @ 25% of weight of radial gate.
2 0.673
= 0.25 x 0.710 x ( L x H x h )
0.673
= 0.0177 x ( 15 x 15 x 9.75 x 9.6 ) : 14.377
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per embedded parts fabrication drawings for gate of same size provided for one
of the dam work.
Actual weight of embedded parts as per data in Item :1 of Annexure-2 : 14.334 tonnes
Consider actual weight of embedded parts for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of embedded
parts for radial gate provided for one of the dam having 15 m x 9 m spillway opening at crest for
rate analysis ( for details refer Item :1 of Annexure-2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles / beams / channels / bars with 2.5 % wastage ( 679x1.025) : 696 kg
Plates / flats with 2.5 % wastage ( 13356 x 1.025 ) : 13690 kg
b. Alloy steel conforming to IS : 1570 :
Stainless steel plates / flats with 2.5 % wastage ( 190 x 1.025 ) : 195.00 kg
c. Bolt / Nut / Washer conforming to IS : 1363 :
MS bolts / nuts with 2.5 % wastage ( 109 x 1.025 ) : 112 kg
d. Welding electrodes ( General purpose / Low hydrogen / Stainless steel ) :
GP / LH electrodes as per data sheet ( Item:1 Annexure-2 ) : 7539 Nos
Add for variations / wastage / misc welding @ 10 % ( 7539 x 0.1 ) : 754 Nos
Total requirement of GP / LH electrodes : 8293 Nos
for stitch welding GP electrodes @t 10 % of total ( 8293 x 0.10 ) : 829 Nos
for run welding LH electrodes @ 90 % of total ( 8293 x 0.90 ) : 7464 Nos
Stainless steel electrodes as per data sheet ( Item:1 Annexure-2 ) : 876 Nos
5
GATE / HOIST AND ALLIED WORKS
For cutting structural steel sections to required size gas cutting is assumed for cutting angles /
beams / channels / round bars. For plates / flats less than 12 mm in thickness plate shearing
machine and for the remaining sections pug cutting machine is considered.
6
GATE / HOIST AND ALLIED WORKS
7
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
5 Acetyline gas cum 93.00 404.00 37572.00
6 Welding electrodes ( general purpose ) Nos 829.00 11.00 9119.00
7 Welding electrodes ( low hydrogen ) Nos 7464.00 21.00 156744.00
8 Welding electrodes ( stainless steel ) Nos 920.00 66.00 60720.00
9 Zinc rich epoxy primer ltr 16.00 756.00 12096.00
10 Coal tar epoxy paint ltr 96.00 256.50 24624.00
11 Rust cleaner / inhibitor ltr 18.00 326.00 5868.00
12 Wire brush Nos 2.00 54.00 108.00
13 Use rate welding holder set Hour 983.00 6.75 6635.25
14 Use rate gas cutting torch set Hour 36.00 3.75 135.00
15 Sundries LS 250.00 45.00 11250.00
Total `: 998921.05
Add for small Tools and Plants @ 1% `: 9989.21
Add for Contractor's Profit @ 10% `: 99892.11
Add for Contractor's Overheads @ 5% `: 49946.05
Total cost of Materials : `: 1158748.42
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 983.00 13.00 12779.00
Fuel / Energy charges Hour 614.00 86.00 52804.00
2 Tower crane Hour 4.00 1099.00 4396.00
Fuel / Energy charges Hour 4.00 186.00 744.00
3 Plate shearing machine Hour 5.00 68.00 340.00
Fuel / Energy charges Hour 5.00 143.00 715.00
4 Pug cutting machine Hour 149.00 5.00 745.00
Fuel / Energy charges Hour 149.00 4.00 596.00
5 Mobile crane 8 t Hour 32.00 412.00 13184.00
Fuel / Energy charges Hour 32.00 718.00 22976.00
6 Stationery derric crane Hour 64.00 73.00 4672.00
Fuel / Energy charges Hour 64.00 15.00 960.00
7 Grinding machine Hour 24.00 20.00 480.00
Fuel / Energy charges Hour 24.00 36.00 864.00
8 Drilling machines Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
9 Planing machine Hour 150.00 97.00 14550.00
Fuel / Energy charges Hour 150.00 107.00 16050.00
10 Sundries LS 200.00 45.00 9000.00
Total `: 156303.00
Add for small Tools and Plants @ 1% `: 1563.03
Add for Contractor's Profit on DPOL / Energy @ 10% `: 10499.70
Add for Contractor's Overheads @ 5% `: 7815.15
Total hire charges of Machinery : `: 176180.88
8
GATE / HOIST AND ALLIED WORKS
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Tower crane Hour 4.00 117.00 468.00
2 Crew for Mobile crane Hour 32.00 144.00 4608.00
3 Crew for Shearing machine Hour 5.00 87.00 435.00
4 Crew for Planing machine Hour 150.00 139.00 20850.00
5 Crew for Drilling machine Hour 8.00 111.00 888.00
6 Crew for Grinding machine Hour 24.00 111.00 2664.00
7 Foreman Day 66.00 311.67 20569.89
8 Marker / Fabricator / Erector Day 115.00 289.67 33311.48
9 Gas cutter Day 24.00 289.67 6951.96
10 Welder ( General ) Day 83.00 289.67 24042.20
11 Welder ( X - ray ) Day 9.00 318.63 2867.68
12 Khalasi Day 65.00 276.17 17950.73
13 Helper fabrication / erection Day 304.00 274.67 83498.16
14 Helper for cleaning / painting Day 18.00 274.67 4943.97
15 Painter Cl - II Day 48.00 274.67 13183.92
16 Electrician Day 5.00 276.17 1380.83
Total `: 238613.80
Add for small Tools and Plants @ 1% `: 2386.14
Add for Contractor's Profit @ 10% `: 23861.38
Add for hidden cost on Labour @ 15% `: 35792.07
Add for additional hidden cost on labour @ 15% `: 35792.07
Add for Contractor's Overheads @ 5% `: 11930.69
Total cost of Labour : `: 348376.15
ABSTRACT:
A. Cost of Materials `: 1158748.42
B. Hire charges of Machinery `: 176180.88
C. Cost of Labour `: 348376.15
TOTAL `: 1683305.45
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 32417.62
Add for insurance charges @ 1.00% `: 16833.05
Add for designs and drawings @ 2.50% `: 42082.64
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 42082.64
Add for stress relieving of anchor girders @ 1.50% `: 25249.58
Add for power supply arrangements @ 2.00% `: 33666.11
Add for enabling works @ 1.50% `: 25249.58
Total `: 1900886.68
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2x14.334 tonnes @ `: 247.10 / tonne `: 7083.86
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 12 ) @ 3.00% `: 11289.53
Total cost for 14.334 tonne `: 1907970.54
Rate per tonne `: 133108.03
Rate approved per tonne `: 133100.00
9
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.2
ITEM: Design, fabrication, supply, erection, testing and commissioning of radial gate consisting
of skin plate, stiffeners, horizontal girders, sector arms, trunnion assemblies, tie beam, pulley
supports, bracings, rubber seals, clamps etc., with all accessories for spillway including cost
of all materials, machinery, labour, cutting, bending, aligning, anchoring, welding, finishing,
cleaning, applying one coat of zinc rich epoxy primer and three coats of cold applied coal tar
epoxy paint, seal fixing etc., complete as per specifications and approved drawings with lead
upto 1 km and all lifts for structural steel components and all leads and lifts including
packing / forwarding charges for other materials.
DATA:Spillway radial gate consists of trunnions / sector arms / horizontal girders / Tee- supports /
skin plate / tie beam / bracings for horizontal girders and sector arms / pulley blocks / seals /
end shields etc., with all accessories.
Sector arms are connected to trunions by bolts and nuts with zinc padding in between.
Horizontal girders generally spaced at about 3 m apart are joined to sector arms by welding and
are stiffened by vertical and diagonal stiffeners to form the main frame. Tee- sections are welded
to horizontal girders to make the frame regid and to support the skin plate. Skin plate is welded
to Tee-supports generally spaced vertically at about 40 cm apart.
Consider radial gate for spillway opening of size 15 m x 9 m at crest.
Size of gate for 15 x 9 m opening at crest with gate sill on d /s 0.6 m below crest level :
Length of gate : 15 m Head of water at sill level : 9.60 m Height of gate : 9.75 m
Weight of gate leaf in tonne with end shield and hood based on empirical formula :
2 0.673
= 0.0710 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
2 0.673
= 0.0710 x ( 15 x 9.75 x 9.6 ) : 57.669
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings for gate of same size provided for one of the dam work.
Actual weight as per data in Item : 2 of Annexure-2 : 57.457 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of radial gate
provided for one of the dam having spillway opening of 15 m x 9 m at crest for rate analysis ( for
details refer Item : 2 of Annexure-2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5% wastage ( 15421x1.025 ) : 15806 kg
Plates / flats with 2.5 % wastage ( 37729 x 1.025 ) : 38672 kg
b. Alloy steel components conforming to IS : 1570 :
Stainless steel plates : 6 kg
Lifting pins : 1098 kg
c. Cast steel components conforming to IS : 1030 :
Trunnion hub / Guide roller : 1895 kg
d. Alluminium / Bronze alloy components conforming to IS : 305 :
Trunnion bush / Guide roller bush : 1155 kg
e. Bolts / Nuts / Washers conforming to IS : 1363 :
GI bolts / nuts / washers with 2.5 % wastage ( 76 x 1.025 ) : 78 kg
MS bolts / nuts / washers with 2.5 % wastage ( 77 x 1.025 ) : 79 kg
f. Zinc at 70 kg / trunnion ( 2 x 70 ) : 140 kg
g. Rubber seal conforming to IS : 11855 :
Bottom seal ( flat type ) with wastage ( 15 x 1.025 ) : 15.5 Rm
10
GATE / HOIST AND ALLIED WORKS
11
GATE / HOIST AND ALLIED WORKS
12
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 4552.00 13.00 59176.00
Fuel / Energy charges Hour 2845.00 86.00 244670.00
2 Plate shearing machine Hour 12.00 68.00 816.00
Fuel / Energy charges Hour 12.00 143.00 1716.00
3 Pug cutting machine Hour 228.00 18.00 4104.00
Fuel / Energy charges Hour 228.00 4.00 912.00
4 Bending machine Hour 238.00 43.00 10234.00
Fuel / Energy charges Hour 238.00 107.00 25466.00
Contd
13
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ) :
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
5 Tower crane 5 t cpacity Hour 10.00 1099.00 10990.00
Fuel / Energy charges Hour 10.00 186.00 1860.00
6 Mobile crane ( pick & carry ) 8 t Hour 100.00 412.00 41200.00
Fuel / Energy charges Hour 100.00 718.00 71800.00
7 Mobile crane ( revolving ) 25 t Hour 75.00 4217.00 316275.00
Fuel / Energy charges Hour 75.00 1994.00 149550.00
8 Stationery derric crane Hour 200.00 73.00 14600.00
Fuel / Energy charges Hour 200.00 15.00 3000.00
9 Grinding machine Hour 200.00 20.00 4000.00
Fuel / Energy charges Hour 200.00 36.00 7200.00
10 Drilling machines Hour 50.00 20.00 1000.00
Fuel / Energy charges Hour 50.00 36.00 1800.00
11 Sundries LS 400.00 45.00 18000.00
Total `: 988369.00
Add for small Tools and Plants @ 1% `: 9883.69
Add for Contractor's Profit on DPOL / Energy @ 10% `: 52597.40
Add for Contractor's Overheads @ 5% `: 49418.45
Total hire charges of Machinery : `: 1100268.54
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane 8 t Hour 100.00 144.00 14400.00
2 Crew for Mobile crane 25 t Hour 75.00 139.00 10425.00
3 Crew for Tower crane Hour 10.00 117.00 1170.00
4 Crew for Bending machine Hour 238.00 87.00 20706.00
5 Crew for Drilling machine Hour 50.00 111.00 5550.00
6 Crew for Grinding machine Hour 200.00 111.00 22200.00
7 Foreman Day 180.00 311.67 56099.70
8 Marker / Fabricator / Erector Day 320.00 289.67 92692.80
9 Gas cutter Day 60.00 289.67 17379.90
10 Welder ( General ) Day 384.00 289.67 111231.36
11 Welder ( X - ray ) Day 43.00 318.63 13701.15
12 Khalasi Day 200.00 276.17 55233.00
13 Helper fabrication / erection Day 1374.00 274.67 377389.71
14 Helper for cleaning / painting Day 154.00 274.67 42298.41
15 Painter Cl - II Day 306.00 274.67 84047.49
16 Electrician Day 30.00 276.17 8284.95
Total `: 932809.47
Add for small Tools and Plants @ 1% `: 9328.09
Add for Contractor's Profit @ 10% `: 93280.95
Add for hidden cost on Labour @ 15% `: 139921.42
Add for additional hidden cost on labour @ 15% `: 139921.42
Add for Contractor's Overheads @ 5% `: 46640.47
Total cost of Labour : `: 1361901.83
14
GATE / HOIST AND ALLIED WORKS
ABSTRACT:
A. Cost of Materials `: 6173496.10
B. Hire charges of Machinery `: 1100268.54
C. Cost of Labour `: 1361901.83
TOTAL `: 8635666.48
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 152162.13
Add for insurance charges @ 1.00% `: 86356.66
Add for designs and drawings @ 2.50% `: 215891.66
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 215891.66
Add for power supply arrangements @ 2.00% `: 172713.33
Add for enabling works @ 1.50% `: 129535.00
Total `: 9608216.92
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2x57.457 tonnes @ `: 247.10 / tonne `: 28395.25
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 15 ) @ 3.00% `: 89818.92
Total cost for 57.457 tonne `: 9636612.17
Rate per tonne `: 167718.68
Rate approved per tonne `: 167700.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.3
ITEM: Design, fabrication, supply, erection, testing and commissioning of electrically operated rope
drum hoist of adequate capacity consisting of base frames, rope drums,connecting shaft, gear
system, brake system, electric motor, wire ropes, gate position indicator, manual operation
arrangement etc., with all accessories for spillway radial gate including cost of all materials,
machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning, greasing, providing
hand railing and approach staircase with gate to hoist platform, applying two coats of zinc
chromate red oxide primer and three coats of approved synthetic enamel paint etc., complete
as per specifications and approved drawings with lead upto 1 km and all lifts for structural
steel components and all leads and lifts including packing / forwarding charges for
and lifts including
DATA:Rope drum hoist for radial gate consists of embedded parts for anchorages, hoist supporting
structure, pulley supporting structures, pulleys, drive stool, rope drums, couplings, shafts,
gears and pinions, plummer blocks, worm reducer, floating shaft, electric motor, hand operation
assembly, brake, wire rope, gate position indicator, switch box etc. with related accessories.
Consider rope drum hoist for radial gate for spillway opening of size 15 m x 9 m at crest.
Generally the rope drum hoist capacity in tonnes with 25 % reserve will be about 1.50 times the
weight of radial gate in tonnes.
Size of gate for 15 x 9 m opening at crest with gate sill on d /s 0.6 m below crest level :
Length of gate : 15 m Head of water at sill level : 9.60 m Height of gate : 9.75 m
Weight of radial gate leaf in tonne for 9.6 m water head based on empirical formula :
2 0.673
= 0.0710 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.673
= 0.0710 x ( 15 2 x 9.75 x 9.6 ) : 57.669
Consider capacity of hoist including 25 % reserve capacity @ 1.5 times the weight of gate :
( 1.50 x 57.669 ) : 86.504 tonnes
15
GATE / HOIST AND ALLIED WORKS
Round off the rope drum hoist capacity to next 10 tonne : 90.00 tonnes
Consider weight of hoist with all accessories @ 0.175 tonne per tonne capacity of hoist :
( 0.175 x 90 ) : 15.750 tonnes
The hoist capacity and hoist weight computed as above based on empirical formulae are further
checked by varifying / computing the actual capacity and weight as per fabrication drawings for
radial gate rope drum hoist of same capacity provided for one of the dam work.
Actual capacity of hoist provided : 90.00 tonnes
Actual weight of rope drum hoist as per data in Item : 3 of Annexure-2 : : 15.440 tonnes
Consider actual capacity and weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of 90 tonne
capacity rope drum hoist provided for spillway radial gate for one of the dam for rate analysis
( for details refer Item : 3 of Annexure- 2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 2508x1.025 ) : 2571.00 kg
Plates / flats with 2.5 % wastage ( 3543 x 1.025 ) : 3632.00 kg
b. Cast steel components conforming to IS : 1030 :
Rope drums 2 Nos / Gears 4 Nos : 3680.00 kg
Pinions : 218.00 kg
Pulleys 720 PCD 6 Nos : 1080.00 kg
Plummer blocks / Hubs : 322.00 kg
c. Alloy steel components conforming to IS : 1570 :
Shafts ( carbon steel ) : 557.00 kg
Pins ( stainless steel ) : 546.00 kg
d. Alluminium / Bronze alloy components conforming to IS : 305 :
Bearings / Bush : 144.00 kg
e. Bolt / Nut / Washers conforming to IS : 1363 :
MS Bolts / Nuts / Washers with 2.5 % wastage ( 83 x 1.025 ) : 85.00 kg
f. Steel wire rope conforming to IS : 2266 :
36 mm dia 6 / 37 construction 2 Nos 50 m each @ 4.48 kg / Rm : 448 kg
g. Other components :
Manual operation assembly : 1 No.
Worm reducer : 1 Nos
Electric motor 20 hp : 1 No.
Gate position indicator : 1 No.
Ele-magnetic brake : 1 No.
Wire rope sockets : 2 Nos
MS pipe 300 mm dia 13.32 Rm @ 75 kg / Rm : 1000 kg
Electric cable / switch / control panel etc : 1 set
h. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:3 Annexure-2 ) : 5304 Nos
Add for variations / wastage / misc welding @ 10 % ( 5304 x 0.1 ) : 530 Nos
Total requirement of GP / LH electrodes : 5834 Nos
for stitch welding GP electrodes @t 10 % of total ( 5834 x 0.10 ) : 584 Nos
for run welding LH electrodes @ 90 % of total ( 5834 x 0.90 ) : 5250 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 255 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 25 Rm
Total : 280 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
16
GATE / HOIST AND ALLIED WORKS
17
GATE / HOIST AND ALLIED WORKS
18
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
9 Floating shaft 300 mm dia kg 1000.00 74.00 74000.00
10 Manual operating system No. 1.00 33750.00 33750.00
11 Gate position indicator No. 1.00 13500.00 13500.00
12 Ele-magnetic brake No. 1.00 22500.00 22500.00
13 Electric cable /switch /control panel etc LS 1.00 27000.00 27000.00
14 Oxygen gas cum 216.00 78.00 16848.00
15 Acetyline gas cum 72.00 404.00 29088.00
16 Welding electrodes ( general purpose ) Nos 584.00 11.00 6424.00
17 Welding electrodes ( low hydrogen ) Nos 5250.00 21.00 110250.00
18 Zinc chromate red oxide primer ltr 21.00 209.00 4389.00
19 Synthetic enamel ( 1st quality ) paint ltr 31.00 259.00 8029.00
20 Rust cleaner / inhibitor ltr 16.00 326.00 5216.00
21 Grease kg 50.00 298.00 14900.00
22 Wire brush Nos 3.00 54.00 162.00
23 Use rate welding holder set Hour 623.00 6.75 4205.25
24 Use rate gas cutting torch set Hour 90.00 3.75 337.50
25 Sundries ( hand rail /staircase / gate etc ) LS 1000.00 45.00 45000.00
Total `: 2533759.40
Add for small Tools and Plants @ 1% `: 25337.59
Add for Contractor's Profit @ 10% `: 253375.94
Add for Contractor's Overheads @ 5% `: 126687.97
Total cost of Materials : `: 2939160.90
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 623.00 13.00 8099.00
Fuel / Energy charges Hour 390.00 86.00 33540.00
2 Tower crane 5 t capacity Hour 4.00 1099.00 4396.00
Fuel / Energy charges Hour 4.00 186.00 744.00
3 Pug cutting machine Hour 53.00 18.00 954.00
Fuel / Energy charges Hour 53.00 4.00 212.00
4 Mobile crane 25 t Hour 40.00 4217.00 168680.00
Fuel / Energy charges Hour 20.00 1994.00 39880.00
5 Mobile crane 8 t Hour 40.00 412.00 16480.00
Fuel / Energy charges Hour 20.00 718.00 14360.00
6 Grinding machine Hour 32.00 20.00 640.00
Fuel / Energy charges Hour 32.00 36.00 1152.00
7 Drilling machines Hour 16.00 20.00 320.00
Fuel / Energy charges Hour 16.00 36.00 576.00
8 Sundries LS 600.00 45.00 27000.00
Total `: 317033.00
Add for small Tools and Plants @ 1% `: 3170.33
Add for Contractor's Profit on DPOL / Energy @ 10% `: 10310.40
Add for Contractor's Overheads @ 5% `: 15851.65
Total hire charges of Machinery : `: 346365.38
19
GATE / HOIST AND ALLIED WORKS
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane 25 t Hour 40.00 139.00 5560.00
2 Crew for Mobile crane 8 t Hour 40.00 144.00 5760.00
3 Crew for Tower crane Hour 4.00 117.00 468.00
4 Crew for Drilling machine Hour 16.00 111.00 1776.00
5 Crew for Grinding machine Hour 32.00 111.00 3552.00
6 Foreman Day 37.00 311.67 11531.61
7 Marker / Fabricator / Erector / Mechanic Day 67.00 289.67 19407.56
8 Gas cutter Day 18.00 289.67 5213.97
9 Welder ( General ) Day 58.00 289.67 16800.57
10 Khalasi Day 100.00 276.17 27616.50
11 Helper fabrication / erection Day 196.00 274.67 53834.34
12 Helper for cleaning / painting Day 14.00 274.67 3845.31
13 Painter Cl - II Day 30.00 274.67 8239.95
14 Electrician Day 3.00 276.17 828.50
Total `: 164434.30
Add for small Tools and Plants @ 1% `: 1644.34
Add for Contractor's Profit @ 10% `: 16443.43
Add for hidden cost on Labour @ 15% `: 24665.14
Add for additional hidden cost on labour @ 15% `: 24665.14
Add for Contractor's Overheads @ 5% `: 8221.71
Total cost of Labour : `: 240074.07
ABSTRACT:
A. Cost of Materials `: 2939160.90
B. Hire charges of Machinery `: 346365.38
C. Cost of Labour `: 240074.07
TOTAL `: 3525600.35
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 36241.96
Add for insurance charges @ 1.00% `: 35256.00
Add for designs and drawings @ 2.50% `: 88140.01
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 88140.01
Add for power supply arrangements @ 2.00% `: 70512.01
Add for enabling works @ 1.50% `: 52884.01
Total `: 3896774.35
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 15.44 tonnes @ `: 247.10 / tonne `: 7630.45
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 22 ) @ 3.00% `: 66739.98
Total cost for 15.440 tonne weight `: 3971144.77
90.000 tonne capacity
Rate per tonne wiegt `: 257200.00
Rate per tonne capacity `: 44123.83
Rate approved per tonne capacity `: 44100.00
20
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.4
ITEM: Design, fabrication, supply, erection and commissioning of 1 metre wide catwalk connecting
spillway piers / abutments at trunnion platform level including cost of all materials,
machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning, applying one coat
of zinc rich epoxy primer and two coats of cold applied coal tar epoxy paint etc., complete as
per specifications and approved drawings with lead upto 1 km and all lifts for structural steel
components and all leads and lifts including packing / forwarding charges for other
materials.
DATA:Catwalk at trunnion level generally consists of 1 m wide structural steel bridge spanning across
piers / abutments for inspection and maintenance of gate parts at trunnion level.
Consider 1 m wide catwalk for a clear span of 15 m and 3 m wide piers.
Generally weight of 1 m wide steel catwalk will be about 300 kg / m lenght.
Weight of catwalk for 18 m length ( C / C of piers ) @ 0.3 t / m : 5.400 tonnes
The weight of catwalk ( foot bridge ) computed as above based on empirical formula is further
checked by computing the actual weight as per fabrication drawings of a catwalk of same size
provided for one of the dam work.
Actual weight of catwalk as per data in Item : 4 of Annexure-2 : 5.318 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of catwalk
provided for one of the dam for rate analysis ( for details refer Item : 4 of Annexure-2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 4154x1.025 ) : 4258 kg
Plates / flats with 2.5 % wastage ( 96 x 1.025 ) : 98 kg
Chequered plates with 2.5 % wastage ( 835 x 1.025 ) : 856 kg
b. Bolts / Nuts / Washers conforming to IS : 1363 :
MS bolts / nuts / washers with 2.5 % wastage ( 8 x 1.025 ) : 8 kg
c. Welding electrodes ( General purpose ) :
GP electrodes as per data sheet ( Item:4 Annexure-2 ) : 1387 Nos
Add for variations / wastage / misc welding @ 10 % ( 1387 x 0.1 ) : 139 Nos
Total requirement of GP electrodes : 1526 Nos
for stitch weld GP electrodes @t 10 % of total ( 1526 x 0.10 ) : 153 Nos
for run welding GP electrodes @ 90 % of total ( 1526 x 0.90 ) : 1373 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 57 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 6 Rm
Total : 63 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas manually : 40 m
Length of steel to be cut by gas using pug cutting machine : 23 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 20 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 8 hours
Acetelyne gas @ 0.6 cum / hour ( 20 + 8 ) x 0.60 : 17 cum
Oxygen gas @ 1.8 cum / hour ( 20 + 8 ) x 1.80 : 51 cum
Use of gas cutting torch with 50 min / hr working ( 20 x 60 / 50 ) : 24 hours
Use of pug cutting machine with 50 min / hr working ( 8 x 60 / 50 ) : 10 hours
21
GATE / HOIST AND ALLIED WORKS
3. Welding :
Length of welding as per data sheet : 151 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 153 / 15 ) x 8 / 2 : 41 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 1373 / 15 ) x 8 / 6 : 122 hours
Total : 163 hours
Deploy welding transformer for 163 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 41 x 0.25 + 122 x 0.75 ) : 102 hours
4. Surface cleaning and painting :
Painting area for catwalk at 25 sqm / tonne ( 5.318 x 25 ) : 133 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 133 sqm @ 9 sqm / ltr / coat : 15 ltr
2 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 133 sqm @ 6 sqm / ltr / coat : 44 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 133 sqm at 8 sqm / ltr : 16 ltr
5. Requirement of other machinery :
For erection of fabricated catwalk 1 hour use of tower crane considered.
For handling during fabrication 8 t mobile crane for 2 hours considered.
For drilling holes for bolts 2 hours use of drilling machine considered.
For grinding and finishing weld joints 8 hours use of grinding machine considered
6. Requirement of work force :
Work component Foreman Marker / Gas cutter / Helper /
Fabricator / Welder Painter Cl-II
Erector /
Cutting sections / drilling holes 34 hours 2 4 4 8
Fabricating by stitch welding 41 hours 2 5 --- 10
Run welding 122 hours 1 --- 15 15
Cleaning surface 132 sqm @ 15 sqm/day --- --- --- 9
Painting ( 3 x 133 ) sqm @ 15 sqm / day --- --- --- 33
Erection / anchoring / finishing / checking 1 2 --- 2
Total : 6 11 19 77
Note : a. It is assumed that all stitch welding will be done by fabricator. Hence, no separate provision
is considered for welder for stitch welding.
b. Workforce for painting 1 coat primer and 3 coats finishing paint consists of 26 Painters Cl-II
at 15 sqm / day and 7 helpers to assist painters.
22
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 163.00 13.00 2119.00
Fuel / Energy charges Hour 102.00 86.00 8772.00
2 Tower crane Hour 1.00 1099.00 1099.00
Fuel / Energy charges Hour 1.00 186.00 186.00
3 Pug cutting machine Hour 10.00 18.00 180.00
Fuel / Energy charges Hour 10.00 4.00 40.00
4 Mobile crane 8 t Hour 2.00 412.00 824.00
Fuel / Energy charges Hour 2.00 718.00 1436.00
5 Grinding machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
6 Drilling machines Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
7 Sundries LS 10.00 45.00 450.00
Total `: 15666.00
Add for small Tools and Plants @ 1% `: 156.66
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1124.40
Add for Contractor's Overheads @ 5% `: 783.30
Total hire charges of Machinery : `: 17730.36
23
GATE / HOIST AND ALLIED WORKS
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 2.00 144.00 288.00
2 Crew for Tower crane Hour 1.00 117.00 117.00
3 Crew for Drilling machine Hour 2.00 111.00 222.00
4 Crew for Grinding machine Hour 8.00 111.00 888.00
5 Foreman Day 6.00 311.67 1869.99
6 Marker / Fabricator / Erector Day 11.00 289.67 3186.32
7 Gas cutter Day 4.00 289.67 1158.66
8 Welder ( General ) Day 15.00 289.67 4344.98
9 Helper fabrication / erection Day 35.00 274.67 9613.28
10 Helper for cleaning / painting Day 16.00 274.67 4394.64
11 Painter Cl - II Day 26.00 274.67 7141.29
12 Electrician Day 1.00 276.17 276.17
Total `: 33500.31
Add for small Tools and Plants @ 1% `: 335.00
Add for Contractor's Profit @ 10% `: 3350.03
Add for hidden cost on Labour @ 15% `: 5025.05
Add for additional hidden cost on labour @ 15% `: 5025.05
Add for Contractor's Overheads @ 5% `: 1675.02
Total cost of Labour : `: 48910.45
ABSTRACT:
A. Cost of Materials `: 321055.04
B. Hire charges of Machinery `: 17730.36
C. Cost of Labour `: 48910.45
TOTAL `: 387695.86
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 4118.40
Add for insurance charges @ 1.00% `: 3876.96
Add for designs and drawings @ 2.50% `: 9692.40
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 9692.40
Add for power supply arrangements @ 2.00% `: 7753.92
Add for enabling works @ 1.50% `: 5815.44
Total `: 428645.37
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 5.318 tonnes @ `: 247.10 / tonne `: 2628.16
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 9 ) @ 3.00% `: 1688.88
Total cost for 18.000 Rm `: 432962.40
Rate per Rm `: 24053.47
Rate approved per Rm `: 24100.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.5
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts consisting of
sill beam, slide tracks, seal seats, guide rails, dogging sets for storage of stoplog elements
etc., with all accessories for spillway stop log gate elements including cost of all materials,
machinery, labour, cutting, aligning, welding, anchoring, finishing, cleaning, applying one coat
24
GATE / HOIST AND ALLIED WORKS
of zinc rich epoxy primer and four coats of cold applied coal tar epoxy paint etc., complete as
per specifications and approved drawings with lead upto 1 km and all lifts for structural steel
components and all leads and lifts including packing / forwarding charges for other
materials.
DATA:Spillway stoplog gate embedded parts consist of sill beam, slide tracks / seal tracks and gate
guides and dogging sets for storage of elements with accessories such as first stage anchors.
Weight of embedded parts with dogging sets will be about 4 to 5 percent of stop log gate weight.
Consider embedded parts for stoplog gate for spillway opening of size 15 m x 9 m for analysis.
Size of stoplog gate for 15 x 9 m opening at crest with gate sill 0.4 m below crest level :
Length of gate in m : Clear opening + 0.65 m : 15.00 + 0.65 : 15.65 m
Height of gate ( total height of gate elements ) in m : FRL - Sill level + 0.2 : 9.60 m
Head of water in m : FRL - Sill level : 9.40 m
Weight of stoplog gate elements in tonne for 15 m x 9 m opening based on empirical formula :
2 0.716
= 0.0553 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
Consider weight of embedded parts for stoplog gate @ 4.50 % of weight of gate elements.
2 0.716
= 0.045 x 0.0553 x ( L x H x h )
2 0.716
= 0.0025 x ( 15.65 x 9.6 x 9.4 ) : 3.225
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per embedded parts fabrication drawings for stoplog gate of same size provided
for one of the dam.
Actual weight of embedded parts as per data in Item : 5 of Annexure-2 : 3.179 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of spillway
stoplog gate embedded parts provided for one of the dam for rate analysis ( for details refer
Item : 5 of Annexure-2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 421x1.025 ) : 432 kg
Plates / flats with 2.5 % wastage ( 2245 x 1.025 ) : 2301 kg
b. Alloy steel conforming to IS : 1570 :
Stainless steel plates / flats ( 235+166 ) x 1.025 : 411.00 kg
c. Bolt / Nut / Washer conforming to IS : 1363 :
MS bolts and nuts with 2.5 % wastage ( 112 x 1.025 ) : 115 kg
d. Welding electrodes ( General purpose / Low hydrogen / Stainless steel ) :
GP / LH electrodes as per data sheet ( Item:5 Annexure-2 ) : 1973 Nos
Add for variations / wastage / misc welding @ 10 % ( 1973 x 0.1 ) : 197 Nos
Total requirement of GP / LH electrodes : 2170 Nos
for stitch welding GP electrodes @t 10 % of total ( 2170 x 0.10 ) : 217 Nos
for run welding LH electrodes @ 90 % of total ( 2170 x 0.90 ) : 1953 Nos
Stainless steel electrodes as per data sheet ( Item:5 Annexure-2 ) : 1095 Nos
Add for variations / wastage @ 5 % ( 1095 x 0.05 ) : 55 Nos
Total requirement of Stainless steel ( SS ) electrodes : 1150 Nos
for stitch welding SS electrodes @t 10 % of total ( 1150 x 0.10 ) : 115 Nos
for run welding SS electrodes @t 90 % of total ( 1150 x 0.90 ) : 1035 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 163 Rm
25
GATE / HOIST AND ALLIED WORKS
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 16 Rm
Total length of cutting : 179 Rm
For cutting structural steel sections to required size gas cutting is assumed for cutting angles /
beams / channels / round bars. For plates / flats less than 12 mm in thickness plate shearing
machine and for the remaining sections pug cutting machine is considered.
Length of steel to be cut by using gas manually : 29 m
Length of steel to be cut by gas using pug cutting machine : 120 m
Length of steel to be cut by using shearing machine : 30 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 15 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 40 hours
Time for cutting by shearing machine at ( av ) 10 m cutting / hour : 3 hours
Acetelyne gas @ 0.6 cum / hour ( 15 + 40 ) x 0.60 : 33 cum
Oxygen gas @ 1.8 cum / hour ( 15 + 40 ) x 1.80 : 99 cum
Use of gas cutting torch with 50 min / hr working ( 15 x 60 / 50 ) : 18 hours
Use of pug cutting machine with 50 min / hr working ( 40 x 60 / 50 ) : 48 hours
Use of shearing machine with 50 min / hr working ( 3 x60 / 50 ) : 4 hours
3. Welding :
Length of welding as per data sheet : 303 m
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 217 + 115 ) x 8 / 15 / 2 : 89 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 1953 + 1035 ) x 8 / 15 / 6 : 266 hours
Total : 355 hours
Deploy welding transformer for 355 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 89 x 0.25 + 266 x 0.75 ) : 222 hours
4. Planing SS plates for slide block / seal tracks : :
For surface finishing of SS plates for wheel / seal tracks planing machine is considered.
Length of SS plate for surface finishing by planing machine : 50.4 Rm
Length of planing at a time for 4 m stroke planing machine : 3 Rm
Time for planing 3 m length section with 50 min / hour working : 8 hours
Time for planing 50.4 m SS plates ( 50.4 x 8 / 3 ) : 135 hours
26
GATE / HOIST AND ALLIED WORKS
27
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
14 Use rate gas cutting torch set Hour 18.00 3.75 67.50
15 Sundries LS 72.00 45.00 3240.00
Total `: 356566.40
Add for small Tools and Plants @ 1% `: 3565.66
Add for Contractor's Profit @ 10% `: 35656.64
Add for Contractor's Overheads @ 5% `: 17828.32
Total cost of Materials : `: 413617.02
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 355.00 13.00 4615.00
Fuel / Energy charges Hour 222.00 86.00 19092.00
2 Plate shearing machine Hour 4.00 68.00 272.00
Fuel / Energy charges Hour 4.00 143.00 572.00
3 Pug cutting machine Hour 48.00 18.00 864.00
Fuel / Energy charges Hour 48.00 4.00 192.00
4 Planing machine Hour 135.00 97.00 13095.00
Fuel / Energy charges Hour 135.00 107.00 14445.00
5 Mobile crane 25 t Hour 4.00 4217.00 16868.00
Fuel / Energy charges Hour 4.00 1994.00 7976.00
6 Stationery derric crane Hour 50.00 73.00 3650.00
Fuel / Energy charges Hour 50.00 15.00 750.00
7 Grinding machine Hour 16.00 20.00 320.00
Fuel / Energy charges Hour 16.00 36.00 576.00
8 Drilling machines Hour 16.00 20.00 320.00
Fuel / Energy charges Hour 16.00 36.00 576.00
9 Sundries LS 64.00 45.00 2880.00
Total `: 87063.00
Add for small Tools and Plants @ 1% `: 870.63
Add for Contractor's Profit on DPOL / Energy @ 10% `: 4705.90
Add for Contractor's Overheads @ 5% `: 4353.15
Total hire charges of Machinery : `: 96992.68
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 4.00 139.00 556.00
2 Crew for Shearing machine Hour 4.00 87.00 348.00
3 Crew for Planing machine Hour 135.00 139.00 18765.00
4 Crew for Drilling machine Hour 16.00 111.00 1776.00
5 Crew for Grinding machine Hour 16.00 111.00 1776.00
6 Foreman Day 25.00 311.67 7791.63
7 Marker / Fabricator / Erector Day 38.00 289.67 11007.27
8 Gas cutter Day 9.00 289.67 2606.99
Contd
28
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ) :
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
9 Welder ( General ) Day 30.00 289.67 8689.95
10 Welder ( X - ray ) Day 3.00 318.63 955.89
11 Helper fabrication / erection Day 95.00 274.67 26093.18
12 Helper for cleaning / painting Day 3.00 274.67 824.00
13 Painter Cl - II Day 7.00 274.67 1922.66
14 Electrician Day 2.00 276.17 552.33
Total `: 83664.88
Add for small Tools and Plants @ 1% `: 836.65
Add for Contractor's Profit @ 10% `: 8366.49
Add for hidden cost on Labour @ 15% `: 12549.73
Add for additional hidden cost on labour @ 15% `: 12549.73
Add for Contractor's Overheads @ 5% `: 4183.24
Total cost of Labour : `: 122150.72
ABSTRACT:
A. Cost of Materials `: 413617.02
B. Hire charges of Machinery `: 96992.68
C. Cost of Labour `: 122150.72
TOTAL `: 632760.43
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 13543.06
Add for insurance charges @ 1.00% `: 6327.60
Add for designs and drawings @ 2.50% `: 15819.01
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 15819.01
Add for power supply arrangements @ 2.00% `: 12655.21
Add for enabling works @ 1.50% `: 9491.41
Total `: 706415.73
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 3.179 tonnes @ `: 247.10 / tonne `: 1571.06
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 12 ) @ 3.00% `: 7084.68
Total cost for 3.179 tonne `: 715071.47
Rate per tonne `: 224935.98
Rate approved per tonne `: 224900.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.6
ITEM: Design, fabrication, supply, erection, testing and commissioning of vertical lift sliding type all
interchangeable ( except bottom element ) stoplog gate elements consisting of skin plate,
horizontal and vertical girders, stiffeners, lifting pins, bronze padded slide blocks, guide shoes,
rubber seals, clamps etc., with all accessories for spillway including cost of all materials,
machinery, labour, cutting, aligning, welding, finishing, cleaning, applying one coat of zinc
rich epoxy primer and three coats of cold applied coal tar epoxy paint, seal fixing etc.,
complete as per specifications and approved drawings with lead upto 1 km and all lifts for
structural steel components and all leads and lifts including packing / forwarding
charges for other materials.
29
GATE / HOIST AND ALLIED WORKS
DATA:Spillway stoplog gate consists of number of vertical lift slide gate elements. Each gate element
consists of skin plate, horizontal girders, vertical end girders, stiffeners, slide blocks, gate guide
shoes, lifting pins and seals with all accessories.
Consider spillway stoplog elements for 15 m x 9 m spillway opening for analysis.
Size of stoplog gate for 15 x 9 m opening at crest with gate sill 0.4 m below crest level :
Length of gate in m : Clear opening + 0.65 m : 15.00 + 0.65 : 15.65 m
Height of gate ( total height of gate elements ) in m : FRL - Sill level + 0.2 :9.60 m
Head of water in m : FRL - Sill level : 9.40 m
Generally, the height of each stoplog element will be in the range of 1.00 to 1.20 m.
For 9.60 m total height consider 8 stoplog elements of 1.20 m height each.
Weight of stoplog gate elements in tonne for 15 m x 9 m opening based on empirical formula :
2 0.716
= 0.0553 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.716
= 0.0553 x ( 15.65 x 15.65 x 9.6 x 9.4 ) : 71.340
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings for stoplog gate of same size provided for one of dam.
Actual weight of spillway stoplog elements as per data in Item :6 of Annexure-2 : 71.157 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of spillway
stoplog gate elements provided for one of the dam for rate analysis ( for details refer Item : 6
of Annexure-2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 461x1.025 ) : 473 kg
Plates / flats with 2.5 % wastage ( 70208 x 1.025 ) : 71963 kg
b. Alloy steel components conforming to IS : 1570 :
Lifting pins : 104 kg
c. Alluminium / Bronze alloy components conforming to IS : 305 :
Bronze pads for slide blocks : 48 kg
d. Bolts / Nuts / Washers conforming to IS : 1363 :
GI bolts / nuts / washers with 2.5 % wastage ( 288 x 1.025 ) : 295 kg
MS bolts / nuts / washers with 2.5 % wastage ( 48 x 1.025 ) : 49 kg
e. Rubber seal conforming to IS : 11855 :
Bottom seal ( 120 x 1.025 ) : 123 Rm
Side seals ( music note type uncladed ) ( 19.2 x 1.025 ) : 20 Rm
f. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:6 Annexure-2 ) : 33626 Nos
Add for variations / wastage / misc welding @ 10 % ( 33626 x 0.1 ) : 3363 Nos
Total requirement of GP / LH electrodes : 36989 Nos
for stitch weld GP electrodes @t 10 % of total ( 36989 x 0.10 ) : 3699 Nos
for run welding LH electrodes @ 90 % of total ( 36989 x 0.90 ) : 33290 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 980 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 98 Rm
Total : 1078 Rm
For cutting structural steel sections to required sizes gas cutting is assumed since most of the
sections are above 10 mm thick.
Length of steel to be cut by using gas manually : 50 m
30
GATE / HOIST AND ALLIED WORKS
31
GATE / HOIST AND ALLIED WORKS
b. Workforce for painting 1 coat primer and 3 coats finishing paint consists of 341 Painters Cl-II
at 15 sqm / day and 68 helpers to assist painters.
32
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 3945.00 13.00 51285.00
Fuel / Energy charges Hour 2466.00 86.00 212076.00
2 Pug cutting machine Hour 412.00 18.00 7416.00
Fuel / Energy charges Hour 412.00 4.00 1648.00
3 Mobile crane 25 t Hour 100.00 4217.00 421700.00
Fuel / Energy charges Hour 100.00 1994.00 199400.00
4 Stationery derric crane Hour 100.00 73.00 7300.00
Fuel / Energy charges Hour 100.00 15.00 1500.00
5 Grinding machine Hour 200.00 20.00 4000.00
Fuel / Energy charges Hour 200.00 36.00 7200.00
6 Drilling machines Hour 100.00 20.00 2000.00
Fuel / Energy charges Hour 100.00 36.00 3600.00
7 Sundries LS 150.00 45.00 6750.00
Total `: 925875.00
Add for small Tools and Plants @ 1% `: 9258.75
Add for Contractor's Profit on DPOL / Energy @ 10% `: 43217.40
Add for Contractor's Overheads @ 5% `: 46293.75
Total hire charges of Machinery : `: 1024644.90
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 100.00 144.00 14400.00
2 Crew for Drilling machine Hour 100.00 111.00 11100.00
3 Crew for Grinding machine Hour 200.00 111.00 22200.00
4 Foreman Day 144.00 311.67 44879.76
5 Marker / Fabricator / Erector Day 204.00 289.67 59091.66
6 Gas cutter Day 56.00 289.67 16221.24
7 Welder ( General ) Day 333.00 289.67 96458.45
8 Welder ( X - ray ) Day 37.00 318.63 11789.37
9 Khalasi Day 150.00 276.17 41424.75
10 Helper fabrication / erection Day 766.00 274.67 210393.39
11 Helper cleaning / painting Day 153.00 274.67 42023.75
12 Painter Cl - II Day 341.00 274.67 93660.77
13 Electrician Day 5.00 276.17 1380.83
Total `: 665023.95
Add for small Tools and Plants @ 1% `: 6650.24
Add for Contractor's Profit @ 10% `: 66502.39
Add for hidden cost on Labour @ 15% `: 99753.59
Add for additional hidden cost on labour @ 15% `: 99753.59
Add for Contractor's Overheads @ 5% `: 33251.20
Total cost of Labour : `: 970934.96
ABSTRACT:
A. Cost of Materials `: 5154213.56
B. Hire charges of Machinery `: 1024644.90
33
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.7
ITEM: Design, fabrication, supply, erection, testing and commissioning of automatic lifting beam
with all accessories for handling, lowering and lifting of spillway stop log gate elements
including cost of all materials, machinery, labour, cutting, aligning, welding, finishing, cleaning,
applying one coat of zinc rich epoxy primer and two coats of cold applied coal tar epoxy paint
etc., complete as per specifications and drawings with lead upto 1 km and all lifts for
structural steel components and all leads and lifts including packing / forwarding
charges for other materials.
DATA:Automatic lifting beam for lifting spillway stop log elements consists of fabricated beam with
lifting bracket and automatic engaging / dis-engaging type hooks for under water hooking /
de-hooking of gate element. Lifting beam is an independent attachment to moving gantry crane.
Consider lifting beam for stoplog element for spillway opening of size 15 m x 9 m for analysis.
Spillway stoplog gate consists of number of elements of convenient height. Generally the height
of each stoplog element will be in the range of 1.00 to 1.20 m.
For 9.60 m height of stoplog gate the number of elements of 1.2 m each will be 8.
Generally the weight of lifting beam for spillway stoplog element will be about 40 percent of the
weight of one stoplog element.
Size of stoplog gate for 15 x 9 m opening at crest with gate sill 0.4 m below crest level :
Length of gate in m : Clear opening + 0.65 m : 15.00 + 0.65 : 15.65 m
Height of gate ( total height of gate elements ) in m : FRL - Sill level + 0.2 : 9.60 m
Head of water in m : FRL - Sill level : 9.40 m
Weight of stoplog gate elements in tonne for 15 m x 9 m opening based on empirical formula :
2 0.716
= 0.0553 x ( L x H x h )
Consider weight of lifting beam in tonnes @ 40 % of weight of one stoplog element:
2 0.716
= 0.40 x 0.0553 x ( L x H x h ) /n
Where ( L ) is length and ( H ) is total height and ( h ) is head of water in metres and ( n ) is the
number of stoplog gate elements.
0.716
= 0.0221 x ( 15.65 x 15.65 x 9.6 x 9.4 ) /8 : 3.567
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings for lifting beam for stoplog gate of same size provided
34
GATE / HOIST AND ALLIED WORKS
35
GATE / HOIST AND ALLIED WORKS
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 42 sqm @ 9 sqm / ltr / coat : 5 ltr
2 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 42 sqm @ 6 sqm / ltr / coat : 14 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 42 sqm @ 8 sqm / ltr : 5 ltr
5. Requirement of other machinery :
For handling during fabrication 8 t mobile crane for 2 hours and stationery derric crane for
4 hours considered.
For drilling holes for pins / guide shoes 2 hours use of drilling machine considered.
For grinding and finishing weld joints 2 hours use of grinding machine considered.
6. Requirement of work force :
Work component Foreman Marker / Gas cutter / Helper /
Fabricator / Welder Painter Cl-II
Erector /
Cutting sections 84 hours 6 11 11 22
Drilling holes for pins / bolts fixing --- 1 --- 1
Fabricating by stitch welding 62 hours 4 8 --- 16
Run welding 187 hours 2 --- 24 24
Cleaning surface 42 sqm @ 15 sqm/day --- --- --- 3
Painting ( 3 x 42 ) sqm @ 15 sqm / day --- --- --- 10
Finishing / guide shoe fixing / checking --- 1 --- 1
Total : 12 21 35 77
Note : a. It is assumed that all stitch welding will be done by fabricator. Hence, no separate provision
is considered for welder for stitch welding.
b. Workforce for painting 1 coat primer and 2 coats finishing paint consists of 8 Painters Cl-II
at 15 sqm / day and 2 helpers to assist painters.
7. Excise duty on supply :
Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
8. Use rate of materials :
Cost of welding set @ `: 6750.00 / Each `: 6750.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) `: 6.75
Cost of gas cutting set @ `: 2250.00 / Each `: 2250.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) `: 3.75
36
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ):
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
Lifting pins kg 101.00 330.00 33330.00
3 Bronze alloy components :
Bronze bush kg 5.00 970.00 4850.00
4 Forged steel components :
Lifting hooks kg 103.00 230.00 23690.00
5 MS pipe 100 mm dia kg 11.00 74.00 814.00
6 Bolt / Nut / Washer
MS bolts / nuts / washers kg 3.00 96.00 288.00
7 Oxygen gas cum 126.00 78.00 9828.00
8 Acetyline gas cum 42.00 404.00 16968.00
9 Welding electrodes ( general purpose ) Nos 233.00 11.00 2563.00
10 Welding electrodes ( low hydrogen ) Nos 2100.00 21.00 44100.00
11 Zinc rich epoxy primer ltr 5.00 756.00 3780.00
12 Coal tar epoxy paint ltr 14.00 256.50 3591.00
13 Rust cleaner / inhibitor ltr 5.00 326.00 1630.00
14 Wire brush Nos 1.00 54.00 54.00
15 Use rate welding holder set Hour 249.00 6.75 1680.75
16 Use rate gas cutting torch set Hour 24.00 3.75 90.00
17 Sundries LS 20.00 45.00 900.00
Total `: 291204.35
Add for small Tools and Plants @ 1% `: 2912.04
Add for Contractor's Profit @ 10% `: 29120.44
Add for Contractor's Overheads @ 5% `: 14560.22
Total cost of Materials : `: 337797.05
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 249.00 13.00 3237.00
Fuel / Energy charges Hour 156.00 86.00 13416.00
2 Pug cutting machine Hour 60.00 18.00 1080.00
Fuel / Energy charges Hour 60.00 4.00 240.00
3 Mobile crane 8 t Hour 2.00 412.00 824.00
Fuel / Energy charges Hour 2.00 718.00 1436.00
4 Stationery derric crane Hour 4.00 73.00 292.00
Fuel / Energy charges Hour 4.00 15.00 60.00
5 Grinding machine Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
6 Drilling machines Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
7 Sundries LS 15.00 45.00 675.00
Total `: 21484.00
Add for small Tools and Plants @ 1% `: 214.84
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1597.10
Add for Contractor's Overheads @ 5% `: 1074.20
Total hire charges of Machinery : `: 24370.14
37
GATE / HOIST AND ALLIED WORKS
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 2.00 144.00 288.00
2 Crew for Drilling machine Hour 2.00 111.00 222.00
3 Crew for Grinding machine Hour 2.00 111.00 222.00
4 Foreman Day 12.00 311.67 3739.98
5 Marker / Fabricator / Erector Day 21.00 289.67 6082.97
6 Gas cutter Day 11.00 289.67 3186.32
7 Welder ( General ) Day 24.00 289.67 6951.96
8 Helper fabrication / erection Day 64.00 274.67 17578.56
9 Helper for cleaning / painting Day 5.00 274.67 1373.33
10 Painter Cl - II Day 8.00 274.67 2197.32
11 Electrician Day 1.00 276.17 276.17
Total `: 42118.59
Add for small Tools and Plants @ 1% `: 421.19
Add for Contractor's Profit @ 10% `: 4211.86
Add for hidden cost on Labour @ 15% `: 6317.79
Add for additional hidden cost on labour @ 15% `: 6317.79
Add for Contractor's Overheads @ 5% `: 2105.93
Total cost of Labour : `: 61493.14
ABSTRACT:
A. Cost of Materials `: 337797.05
B. Hire charges of Machinery `: 24370.14
C. Cost of Labour `: 61493.14
TOTAL `: 423660.33
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 5306.35
Add for insurance charges @ 1.00% `: 4236.60
Add for designs and drawings @ 2.50% `: 10591.51
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 10591.51
Add for power supply arrangements @ 2.00% `: 8473.21
Add for enabling works @ 1.50% `: 6354.90
Total `: 469214.41
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 3.528 tonnes @ `: 247.10 / tonne `: 1743.54
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 14 ) @ 3.00% `: 4364.58
Total cost for 3.528 tonne `: 475322.53
Rate per tonne `: 134728.61
Rate approved per tonne `: 134700.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.8
ITEM: Design, fabrication, supply, erection, testing and commissioning of adequate capacity Class- II
type moving gantry crane consisting of rail mounted gantry frame, top platform with hand
railing, long / cross travel arrangements, rope drums, gear systems, electric motors, electro-
magnetic brake system, cabin, control panel, wire rope, ladder, motorised cable reeling drum
etc., with all accessories for operating spillway stop log gate elements and river sluice /
38
GATE / HOIST AND ALLIED WORKS
canal sluice emergency gates including cost of all materials, machinery, labour, cutting,
bending, aligning, anchoring, welding, finishing, cleaning, greasing, applying two coats of zinc
chromate red oxide primer and three coats of approved synthetic enamel paint etc., complete
with lead upto 1 km and all lifts for structural steel components and all leads and lifts
including packing / forwarding charges for other materials.
DATA:Moving gantry crane consists of rail mounted gantry frame with long travel arrangement, cross
travel trolley with track arrangement mounted on gantry frame top platform, rope drum hoist
with all accessories mounted on cross travel trolley for operating stoplog gate elements.
Generally, same moving gantry crane is utilised for operating river sluice emergency gate also.
Therefore, the hoisting capacity of the gantry crane depends on the requirement of hoisting
capacity for spillway stoplog element or river sluice emergency gate whichever is higher.
Consider moving gantry crane for operating spillway stoplog gate element for analysis.
The capacity of moving gantry crane may be considered at 2.5 times wt of 1 stoplog element.
Total weight of spillway stoplog gate elements as per item 6 (W) : 71.34 tonnes
Number of stoplog gate elements as per item 6 (n) : 8 Nos
Capacity of moving gantry crane in tonnes with 25% reserve capacity : 2.5 x ( W / n )
Where ( W ) is weight of 1 set of stoplog elements and ( n ) is number of stoplog elements.
Capacity of moving gantry crane required 2.50 x ( 71.34 / 8 ) : 24.97 tonnes
Round off the capacity to next 5 tonne say : 25 tonne
The weight of moving gantry crane may be considered at 1.25 t per tonne capacity of crane.
Wt of moving gantry crane @ 1.25 t / tonne capacity ( 1.25 x 25 ) : 31.25 tonnes
The hoist capacity and hoist weight computed as above based on empirical formulae are further
checked by varifying / computing the actual capacity and weight as per fabrication drawings of
moving gantry crane for operating spillway stoplogs provided for one of the dam.
Actual capacity of moving gantry crane as per data considered : 25 tonne
Actual weight of moving gantry crane as per data in Item : 8 of Annexure-2 : 30.856 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of moving
gantry crane for operating spillway stoplog gate elements and river sluice emergency gate
provided for one of the dam for rate analysis ( for details refer item : 8 of Annexure-2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 1700x1.025 ) : 1743.00 kg
Plates / flats with 2.5 % wastage ( 19219 x 1.025 ) : 19700.00 kg
Chequered plate with 2.5 % wastage ( 800 x 1.025 ) : 820 kg
b. Cast steel components conforming to IS : 1030 :
Rope drums 2 Nos / Gears : 2336.00 kg
Pinions : 149.00 kg
Wheels and Pulleys : 2255.00 kg
Plummer blocks / Couplings : 817.00 kg
c. Forged steel components conforming to IS : 2004 :
Hook / Shackle : 127.00 kg
d. Alloy steel steel components conforming to IS: 1570 :
Shafts : 556.00 kg
Pins : 524.00 kg
e. Alluminium/ Bronze alloy components conforming to IS : 305 :
Bearings / Bush : 181.00 kg
f. Bolt / Nut / Washers conforming to IS : 1363 :
MS Bolts / Nuts / Washers with 2.5 % wastage ( 61 x 1.025 ) : 63.00 kg
39
GATE / HOIST AND ALLIED WORKS
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 761 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 76 Rm
Total : 837 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas cutting torch manually : 250 m
Length of steel to be cut by gas using pug cutting machine : 587 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 125 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 196 hours
Acetelyne gas @ 0.6 cum / hour ( 125 + 196 ) x 0.60 : 193 cum
Oxygen gas @ 1.8 cum / hour ( 125 + 196 ) x 1.80 : 579 cum
Use of gas cutting torch with 50 min / hr working ( 125 x 60 / 50 ) : 150 hours
Use of pug cutting machine with 50 min/hr working ( 196 x 60 / 50 ) : 235 hours
3. Welding :
Length of welding as per data sheet : 1260 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 1832 / 15 ) x 8 / 2 : 489 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 16484 / 15 ) x 8 / 6 : 1465 hours
Total : 1954 hours
Deploy welding transformer for 1954 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 489 x 0.25 + 1465 x 0.75 ) : 1221 hours
40
GATE / HOIST AND ALLIED WORKS
41
GATE / HOIST AND ALLIED WORKS
42
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 1954.00 13.00 25402.00
Fuel / Energy charges Hour 1221.00 86.00 105006.00
2 Pug cutting machine Hour 235.00 18.00 4230.00
Fuel / Energy charges Hour 235.00 4.00 940.00
3 Mobile crane 25 t Hour 16.00 4217.00 67472.00
Fuel / Energy charges Hour 8.00 1994.00 15952.00
4 Mobile crane 8 t Hour 40.00 412.00 16480.00
Fuel / Energy charges Hour 40.00 718.00 28720.00
5 Grinding machine Hour 64.00 20.00 1280.00
Fuel / Energy charges Hour 64.00 36.00 2304.00
6 Drilling machines Hour 16.00 20.00 320.00
Fuel / Energy charges Hour 16.00 36.00 576.00
7 Sundries LS 150.00 45.00 6750.00
Total `: 275432.00
Add for small Tools and Plants @ 1% `: 2754.32
Add for Contractor's Profit on DPOL / Energy @ 10% `: 16024.80
Add for Contractor's Overheads @ 5% `: 13771.60
Total hire charges of Machinery : `: 307982.72
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane 25 t Hour 16.00 139.00 2224.00
2 Crew for Mobile crane 8 t Hour 40.00 144.00 5760.00
3 Crew for Drilling machine Hour 16.00 111.00 1776.00
4 Crew for Grinding machine Hour 64.00 111.00 7104.00
5 Foreman Day 98.00 311.67 30543.17
6 Marker / Fabricator / Erector Day 159.00 289.67 46056.74
7 Gas cutter Day 48.00 289.67 13903.92
8 Welder ( General ) Day 183.00 289.67 53008.70
9 Khalasi Day 20.00 276.17 5523.30
10 Helper fabrication / erection Day 491.00 274.67 134860.52
11 Helper for cleaning / painting Day 63.00 274.67 17303.90
12 Painter Cl - II Day 135.00 274.67 37079.78
13 Electrician Day 5.00 276.17 1380.83
Total `: 356524.83
Add for small Tools and Plants @ 1% `: 3565.25
Add for Contractor's Profit @ 10% `: 35652.48
Add for hidden cost on Labour @ 15% `: 53478.72
Add for additional hidden cost on labour @ 15% `: 53478.72
Add for Contractor's Overheads @ 5% `: 17826.24
Total cost of Labour : `: 520526.25
ABSTRACT:
A. Cost of Materials `: 4307101.69
B. Hire charges of Machinery `: 307982.72
43
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.9
ITEM: Design, fabrication, supply, erection and commissioning of rail track using 45 kg / m standard
rails on spillway bridge for movement of gantry crane for handling and operating spillway
stoplog gate elements / river sluice / canal sluice emergency gate including cost of all materials,
machinery, labour, aligning, anchoring, welding, cleaning, applying one coat of zinc rich epoxy
primer and two coats of cold applied coal tar epoxy paint for buffers and rail supporting plates
etc., complete as per specifications and approved drawings with lead upto 1 km and all lifts
for structural steel components and all leads and lifts including packing / forwarding
charges for other materials.
DATA:Rail track for moving gantry crane consists of 45 kg / m standard rails fixed by welding and
bolting to anchors embedded in concrete at intervals. The width of track shall be as per the
requirement of gantry long travel specifications.
Consider track length of 200 m for rate analysis.
Weight of 45 kg / m rails in tonnes ( 2 x 200 x 45 ) / 1000 : 18.00
Add for anchors and fixtures @ 15 % including wastage : 2.70
Total weight in tonnes : 20.70
The weight computed as above based on percentage provision for fixtures is further checked by
computing the actual weight as per fabrication drawings for gantry track provided for one of dam.
Actual weight of materials as per data in Item : 9 of Annexure-2 : 20.722 t
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of gantry
track provided for one of the dam for rate analysis ( for details refer Item : 9 of Annexure-2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 1531x1.025 ) : 1570 kg
Plates / flats with 2.5 % wastage ( 951 x 1.025 ) : 975 kg
b. Bolt / Nut / Washer conforming to IS : 1363 :
MS bolts and nuts with 2.5 % wastage ( 240 x 1.025 ) : 246 kg
44
GATE / HOIST AND ALLIED WORKS
45
GATE / HOIST AND ALLIED WORKS
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
8. Use rate of materials :
Cost of welding set @ `: 6750.00 / Each `: 6750.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) `: 6.75
Cost of gas cutting set @ `: 2250.00 / Each `: 2250.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) `: 3.75
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 200.00 13.00 2600.00
Fuel / Energy charges Hour 125.00 86.00 10750.00
2 Mobile crane 8 t Hour 2.00 412.00 824.00
Fuel / Energy charges Hour 2.00 718.00 1436.00
3 Grinding machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
4 Drilling machines Hour 24.00 20.00 480.00
Fuel / Energy charges Hour 24.00 36.00 864.00
5 Sundries LS 10.00 45.00 450.00
Total `: 17852.00
Add for small Tools and Plants @ 1% `: 178.52
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1378.80
Add for Contractor's Overheads @ 5% `: 892.60
Total hire charges of Machinery : `: 20301.92
46
GATE / HOIST AND ALLIED WORKS
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 2.00 144.00 288.00
2 Crew for Drilling machine Hour 24.00 111.00 2664.00
3 Crew for Grinding machine Hour 8.00 111.00 888.00
4 Foreman Day 8.00 311.67 2493.32
5 Marker / Fabricator / Erector Day 32.00 289.67 9269.28
6 Gas cutter Day 17.00 289.67 4924.31
7 Welder ( General ) Day 19.00 289.67 5503.64
8 Helper fabrication / erection Day 53.00 274.67 14557.25
9 Painter Cl- II Day 1.00 274.67 274.67
10 Electrician Day 1.00 276.17 276.17
Total `: 41138.62
Add for small Tools and Plants @ 1% `: 411.39
Add for Contractor's Profit @ 10% `: 4113.86
Add for hidden cost on Labour @ 15% `: 6170.79
Add for additional hidden cost on labour @ 15% `: 6170.79
Add for Contractor's Overheads @ 5% `: 2056.93
Total cost of Labour : `: 60062.38
ABSTRACT:
A. Cost of Materials `: 1360892.16
B. Hire charges of Machinery `: 20301.92
C. Cost of Labour `: 60062.38
TOTAL `: 1441256.46
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 4966.51
Add for insurance charges @ 1.00% `: 14412.56
Add for designs and drawings @ 2.50% `: 36031.41
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 36031.41
Add for power supply arrangements @ 2.00% `: 28825.13
Add for enabling works @ 1.50% `: 21618.85
Total `: 1583142.34
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2x20.722 tonnes @ `: 247.10 / tonne `: 10240.81
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 8 ) @ 3.00% `: 31939.56
Total cost for 200.000 Rm `: 1625322.71
Rate per Rm `: 8126.61
Rate approved per Rm `: 8100.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.10
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts ( without groove
liner ) consisting of sill beam, wheel tracks, seal seats, guide rails, breast wall liner ( upto one
vent height plus 1 m above the roof of vent ) etc., with all accessories for river / canal sluice
service gate including cost of all materials, machinery, labour, cutting, aligning, anchoring,
welding, finishing, cleaning, applying one coat of zinc rich epoxy primer and four coats of cold
applied coal tar epoxy paint etc., complete as per specifications and approved drawings with
47
GATE / HOIST AND ALLIED WORKS
lead upto 1 km and all lifts for structural steel components and all leads and lifts
including packing / forwarding charges for other materials.
DATA:Embedded parts for river / canal sluice service gate without groove lining consist of sill beam,
wheel / seal tracks, breast wall lining and gate guide with accessories such as first / second
stage anchors.
The weight of embedded parts depends on the height of gate groove and height upto which
breast wall lining is to be provided. Weight of embedded parts will be about 50% of wt of gate.
Consider embedded parts for river sluice service gate for sluice opening of size 1.5 m x 3 m.
Weight of breast wall lining for 20 mm MS plate and 6 mm SS plate including stiffeners and
anchors will be about 250 kg per sqm area of breast wall.
Size of gate for 1.5 m x 3 m opening : Length : 2.2 m Height : 3.3 m
Head of water above sill level considered : 16 m
Weight of vertical lift roller gate in tonne for 1.5 m x 3 m opening based on empirical formula :
2 0.659
= 0.0888 x ( L x H x h )
Consider weight of embedded parts in tonnes @ 50 % of weight of gate leaf :
2 0.659
= 0.50 x 0.0888 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.659
= 0.0444 x ( 2.2 x 2.2 x 3.3 x 16 ) : 1.714 tonnes
Weight of breast wall lining about 7 sqm @ 250 kg / sqm : 1.750 tonnes
Total : 3.464 tonnes
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of embedded parts for river sluice service gate of same
size provided for one of the dam.
Actual weight of embedded parts as per data in Item :10 of Annexure-2 : 3.172 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on embedded parts drawings for
river sluice service gate provided for one of the dam for rate analysis ( for details refer Item : 10
of Annexure - 2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 588x1.025 ) : 603 kg
Plates / flats with 2.5 % wastage ( 2109 x 1.025 ) : 2162 kg
b. Alloy steel components conforming to IS : 1570 :
Stainless steel plates / flats ( 414 x 1.025 ) : 424.00 kg
c. Bolt / Nut / Washer conforming ti IS : 1363 :
MS bolts and nuts with 2.5 % wastage ( 61 x 1.025 ) : 62.5 kg
d. Welding electrodes ( General purpose / Low hydrogen / Stainless steel ) :
GP / LH electrodes as per data sheet ( Item:10 Annexure-2 ) : 1359 Nos
Add for variations / wastage / misc welding @ 10 % ( 1359 x 0.1 ) : 136 Nos
Total requirement of GP / LH electrodes : 1495 Nos
for stitch welding GP electrodes @t 10 % of total ( 1495 x 0.10 ) : 150 Nos
for run welding LH electrodes @ 90 % of total ( 1495 x 0.90 ) : 1345 Nos
Stainless steel electrodes as per data sheet ( Item:10 Annexure-2 ) : 417 Nos
Add for variations / wastage @ 5 % ( 417 x 0.05 ) : 21 Nos
Total requirement of Stainless steel ( SS ) electrodes : 438 Nos
for stitch weld SS electrodes @t 10 % of total ( 438 x 0.10 ) : 44 Nos
for run weld SS electrodes @t 90 % of total ( 438 x 0.90 ) : 394 Nos
48
GATE / HOIST AND ALLIED WORKS
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 152 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 15 Rm
Total length of cutting Total : 167 Rm
For cutting structural steel sections to required size gas cutting is assumed for cutting angles /
beams / channels / round bars. For plates / flats less than 12 mm in thickness plate shearing
machine and for the remaining sections pug cutting machine is considered.
Length of steel to be cut by using gas manually : 30 m
Length of steel to be cut by gas using pug cutting machine : 107 m
Length of steel to be cut by using shearing machine : 30 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 15 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 36 hours
Time for cutting by shearing machine at ( av ) 10 m cutting / hour : 3 hours
Acetelyne gas @ 0.6 cum / hour ( 15 + 36 ) x 0.60 : 31 cum
Oxygen gas @ 1.8 cum / hour ( 15 + 36 ) x 1.80 : 93 cum
Use of gas cutting torch with 50 min / hr working ( 15 x 60 / 50 ) : 18 hours
Use of pug cutting machine with 50 min / hr working ( 36 x 60 / 50 ) : 43 hours
Use of shearing machine with 50 min / hr working ( 3 x 60 / 50 ) : 4 hours
3. Welding :
Length of welding as per data sheet : 191 m
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 150 + 44 ) x 8 / 15 / 2 : 52 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 1345 + 394 ) x 8 / 15 / 6 : 154 hours
Total : 206 hours
Deploy welding transformer for 206 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 52 x 0.25 + 154 x 0.75 ) : 129 hours
4. Planing SS plates for wheel / seal tracks :
For surface finishing of SS plates for wheel / seal tracks planing machine is considered.
Length of SS plate for surface finishing by planing machine : 30 Rm
Length of planing at a time for 4 m stroke planing machine : 3 Rm
Time for planing 3 m length section with 50 min / hour working : 8 hours
Time for planing 30 m SS plates ( 30 x 8 / 3 ) : 80 hours
5. Surface cleaning and painting :
Painting area for embedded parts at 10 sqm / tonne ( 3.172 x 10 ) : 32 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 32 sqm @ 9 sqm / ltr / coat : 4 ltr
4 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 32 sqm @ 6 sqm / ltr / coat : 22 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor @ 8 sqm / ltr : 4 ltr
6. Requirement of other machinery :
For drilling holes for anchor bolts use of drilling machine for 8 hours considered.
For grinding weld joints and edges requiring finishing use of grinding machine for 8 hours
considered.
For handling parts during fabrication and erection use of 8 t mobile crane for 4 hours and
stationery derric crane for 8 hours considered
49
GATE / HOIST AND ALLIED WORKS
50
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
13 Use rate welding holder set Hour 206.00 6.75 1390.50
14 Use rate gas cutting torch set Hour 18.00 3.75 67.50
15 Sundries LS 20.00 45.00 900.00
Total `: 293278.75
Add for small Tools and Plants @ 1% `: 2932.79
Add for Contractor's Profit @ 10% `: 29327.88
Add for Contractor's Overheads @ 5% `: 14663.94
Total cost of Materials : `: 340203.35
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 206.00 13.00 2678.00
Fuel / Energy charges Hour 129.00 86.00 11094.00
2 Plate shearing machine Hour 4.00 68.00 272.00
Fuel / Energy charges Hour 4.00 143.00 572.00
3 Pug cutting machine Hour 43.00 18.00 774.00
Fuel / Energy charges Hour 43.00 4.00 172.00
4 Planing machine Hour 80.00 97.00 7760.00
Fuel / Energy charges Hour 80.00 107.00 8560.00
5 Mobile crane 8 t Hour 4.00 412.00 1648.00
Fuel / Energy charges Hour 4.00 718.00 2872.00
6 Stationery derric crane Hour 8.00 73.00 584.00
Fuel / Energy charges Hour 8.00 15.00 120.00
7 Grinding machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
8 Drilling machines Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
9 Sundries LS 10.00 45.00 450.00
Total `: 38452.00
Add for small Tools and Plants @ 1% `: 384.52
Add for Contractor's Profit on DPOL / Energy @ 10% `: 2441.60
Add for Contractor's Overheads @ 5% `: 1922.60
Total hire charges of Machinery : `: 43200.72
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 4.00 144.00 576.00
2 Crew for Shearing machine Hour 4.00 87.00 348.00
3 Crew for Planing machine Hour 80.00 139.00 11120.00
4 Crew for Drilling machine Hour 8.00 111.00 888.00
5 Crew for Grinding machine Hour 8.00 111.00 888.00
6 Foreman Day 18.00 311.67 5609.97
7 Marker / Fabricator / Erector Day 30.00 289.67 8689.95
Contd
51
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ) :
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
8 Gas cutter Day 8.00 289.67 2317.32
9 Welder ( General ) Day 17.00 289.67 4924.31
10 Welder ( X - ray ) Day 2.00 318.63 637.26
11 Helper fabrication / erection Day 73.00 274.67 20050.55
12 Helper for cleaning / painting Day 4.00 274.67 1098.66
13 Painter Cl - II Day 11.00 274.67 3021.32
14 Electrician Day 2.00 276.17 552.33
Total `: 60721.66
Add for small Tools and Plants @ 1% `: 607.22
Add for Contractor's Profit @ 10% `: 6072.17
Add for hidden cost on Labour @ 15% `: 9108.25
Add for additional hidden cost on labour @ 15% `: 9108.25
Add for Contractor's Overheads @ 5% `: 3036.08
Total cost of Labour : `: 88653.62
ABSTRACT:
A. Cost of Materials `: 340203.35
B. Hire charges of Machinery `: 43200.72
C. Cost of Labour `: 88653.62
TOTAL `: 472057.69
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 8148.60
Add for insurance charges @ 1.00% `: 4720.58
Add for designs and drawings @ 2.50% `: 11801.44
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 11801.44
Add for power supply arrangements @ 2.00% `: 9441.15
Add for enabling works @ 1.50% `: 7080.87
Total `: 525051.77
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 3.172 tonnes @ `: 247.10 / tonne `: 1567.60
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 12 ) @ 3.00% `: 5248.62
Total cost for 3.172 tonne `: 531867.99
Rate per tonne `: 167675.91
Rate approved per tonne `: 167700.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.11
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts ( with groove
liner upto breast wall level ) consisting of sill beam, wheel tracks, seal seats, guide rails,
breast wall liner ( upto one vent height plus 1 m above the roof of vent ) etc., with all accessories
for river / canal sluice service gate including cost of all materials, machinery, labour,
cutting, aligning, anchoring, welding, finishing, cleaning, applying ne coat of zinc rich epoxy
primer and four coats of cold applied coal tar epoxy paint etc., complete as per specifications
and approved drawings with lead upto 1 km and all lifts for structural steel components
and all leads and lifts including packing / forwarding charges for other materials.
52
GATE / HOIST AND ALLIED WORKS
DATA:Embedded parts for river sluice service gate consist of sill beam, wheel / seal tracks, groove
lining upto breast wall level, breast wall lining upto 1 vent plus 1 m above top of vent, gate guide
etc., with all accessories such as first stage anchors.
The wt of embedded parts depends on the height of gate groove and height upto which breast
wall lining is to be provided. Generally wt of embedded parts will be about 50% of wt of gate.
Weight of breast wall lining for 20 mm MS plate and 6 mm SS plate including stiffeners and
anchors will be about 250 kg per sqm area of breast wall.
Weight of groove liner for 20 mm MS plate including stiffeners and anchors will be about
200 kg / sqm area of groove liner.
Consider embedded parts for river sluice service gate for sluice opening of size 2.5 m x 3 m.
Size of gate for 2.5 m x 3 m opening : Length : 3.2 m Height : 3.3 m
Head of water above sill level considered : 34 m
Weight of vertical lift roller in tonne for 2.5 m x 3 m opening based on empirical formula :
2 0.659
= 0.0888 x ( L x H x h )
Consider weight of embedded parts in tonnes @ 50 % of weight of gate leaf :
2 0.659
= 0.50 x 0.0888 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.659
= 0.0444 x ( 3.2 x 3.2 x 3.3 x 34 ) : 4.615 tonnes
Weight of breast wall lining about 12 sqm @ 250 kg / sqm : 3.000 tonnes
Weight of groove liner about 15 sqm @ 200 kg / sqm : 3.000 tonnes
Total : 10.615 tonnes
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of embedded parts with groove liners for river sluice
service gate of same size provided for one of the dam.
Actual weight of embedded parts as per data in Item : 11 of Annexure-2 : : 10.657 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on embedded parts and gate groove
liner drawings for river sluice service gate provided for one of the dam work for rate analysis ( for
details refer Item : 11 of Annexure - 2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 681x1.025 ) : 698 kg
Plates / flats with 2.5 % wastage ( 8971 x 1.025 ) : 9195 kg
b. Alloy steel components conforming to IS : 1570 :
Stainless steel plates / flats ( 825 x 1.025 ) : 846 kg
c. Bolt / Nut / Washer conforming ti IS : 1363 :
MS bolts and nuts with 2.5 % wastage ( 180 x 1.025 ) : 185 kg
d. Welding electrodes ( General purpose / Low hydrogen / Stainless steel ) :
GP / LH electrodes as per data sheet ( Item:11 Annexure-2 ) : 5569 Nos
Add for variations / wastage / misc welding @ 10 % ( 5569 x 0.1 ) : 557 Nos
Total requirement of GP / LH electrodes : 6126 Nos
for stitch welding GP electrodes @t 10 % of total ( 6126 x 0.10 ) : 613 Nos
for run welding LH electrodes @ 90 % of total ( 6126 x 0.90 ) : 5513 Nos
Stainless steel electrodes as per data sheet ( Item:11 Annexure-2 ) : 457 Nos
Add for variations / wastage @ 5 % ( 457 x 0.05 ) : 23 Nos
Total requirement of Stainless steel ( SS ) electrodes : 480 Nos
for stitch weld SS electrodes @t 10 % of total ( 480 x 0.10 ) : 48 Nos
for run weld SS electrodes @t 90 % of total ( 480 x 0.90 ) : 432 Nos
53
GATE / HOIST AND ALLIED WORKS
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 301 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 30 Rm
Total length of cutting Total : 331 Rm
For cutting structural steel sections to required size gas cutting is assumed for cutting angles /
beams / channels / round bars. For plates / flats less than 12 mm in thickness plate shearing
machine and for the remaining sections pug cutting machine is considered.
Length of steel to be cut by using gas manually : 60 m
Length of steel to be cut by gas using pug cutting machine : 211 m
Length of steel to be cut by using shearing machine : 60 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 30 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 70 hours
Time for cutting by shearing machine at ( av ) 10 m cutting / hour : 6 hours
Acetelyne gas @ 0.6 cum / hour ( 30 + 70 ) x 0.60 : 60 cum
Oxygen gas @ 1.8 cum / hour ( 30 + 70 ) x 1.80 : 180 cum
Use of gas cutting torch with 50 min / hr working ( 30 x 60 / 50 ) : 36 hours
Use of pug cutting machine with 50 min / hr working ( 70 x 60 / 50 ) : 84 hours
Use of shearing machine with 50 min / hr working ( 6 x 60 / 50 ) : 7 hours
3. Welding :
Length of welding as per data sheet : 552 m
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 613 + 48 ) x 8 / 15 / 2 : 176 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 5513 + 432 ) x 8 / 15 / 6 : 528 hours
Total : 704 hours
Deploy welding transformer for 704 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 176 x 0.25 + 528 x 0.75 ) : 440 hours
4. Planing SS plates for wheel / seal tracks :
For surface finishing of SS plates for wheel / seal tracks planing machine is considered.
Length of SS plate for surface finishing by planing machine : 30 Rm
Length of planing at a time for 4 m stroke planing machine : 3 Rm
Time for planing 3 m length section with 50 min / hour working : 8 hours
Time for planing 30 m SS plates ( 30 x 8 / 3 ) : 80 hours
5. Surface cleaning and painting :
Painting area for embedded parts at 10 sqm / tonne ( 10.657 x 10 ) : 107 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 107 sqm @ 9 sqm / ltr / coat : 12 ltr
4 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 107 sqm @ 6 sqm / ltr / coat : 72 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 107 sqm @ 8 sqm / ltr : 14 ltr
6. Requirement of other machinery :
For drilling holes for anchor bolts use of drilling machine for 50 hours considered.
For grinding weld joints and edges requiring finishing use of grinding machine for 25 hours
considered.
For handling of parts during fabrication and erection 8 t mobile crane for 10 hours and stationery
derric crane for 40 hours considered.
54
GATE / HOIST AND ALLIED WORKS
55
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
12 Wire brush Nos 2.00 54.00 108.00
13 Use rate welding holder set Hour 704.00 6.75 4752.00
14 Use rate gas cutting torch set Hour 36.00 3.75 135.00
15 Sundries LS 40.00 45.00 1800.00
Total `: 825103.65
Add for small Tools and Plants @ 1% `: 8251.04
Add for Contractor's Profit @ 10% `: 82510.37
Add for Contractor's Overheads @ 5% `: 41255.18
Total cost of Materials : `: 957120.23
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 704.00 13.00 9152.00
Fuel / Energy charges Hour 440.00 86.00 37840.00
2 Plate shearing machine Hour 7.00 68.00 476.00
Fuel / Energy charges Hour 7.00 143.00 1001.00
3 Pug cutting machine Hour 84.00 18.00 1512.00
Fuel / Energy charges Hour 84.00 4.00 336.00
4 Planing machine Hour 80.00 97.00 7760.00
Fuel / Energy charges Hour 80.00 107.00 8560.00
5 Mobile crane 8 t Hour 10.00 412.00 4120.00
Fuel / Energy charges Hour 10.00 718.00 7180.00
6 Stationery derric crane Hour 40.00 73.00 2920.00
Fuel / Energy charges Hour 40.00 15.00 600.00
7 Grinding machine Hour 25.00 20.00 500.00
Fuel / Energy charges Hour 25.00 36.00 900.00
8 Drilling machines Hour 50.00 20.00 1000.00
Fuel / Energy charges Hour 50.00 36.00 1800.00
9 Sundries LS 40.00 45.00 1800.00
Total `: 87457.00
Add for small Tools and Plants @ 1% `: 874.57
Add for Contractor's Profit on DPOL / Energy @ 10% `: 6001.70
Add for Contractor's Overheads @ 5% `: 4372.85
Total hire charges of Machinery : `: 98706.12
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 10.00 144.00 1440.00
2 Crew for Shearing machine Hour 7.00 87.00 609.00
3 Crew for Planing machine Hour 80.00 139.00 11120.00
4 Crew for Drilling machine Hour 50.00 111.00 5550.00
5 Crew for Grinding machine Hour 25.00 111.00 2775.00
6 Foreman Day 42.00 311.67 13089.93
Contd
56
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ) :
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
7 Marker / Fabricator / Erector Day 70.00 289.67 20276.55
8 Gas cutter Day 16.00 289.67 4634.64
9 Welder ( General ) Day 59.00 289.67 17090.24
10 Welder ( X - ray ) Day 7.00 318.63 2230.42
11 Helper fabrication / erection Day 190.00 274.67 52186.35
12 Helper for cleaning / painting Day 13.00 274.67 3570.65
13 Painter Cl - II Day 36.00 274.67 9887.94
14 Electrician Day 5.00 276.17 1380.83
Total `: 145841.54
Add for small Tools and Plants @ 1% `: 1458.42
Add for Contractor's Profit @ 10% `: 14584.15
Add for hidden cost on Labour @ 15% `: 21876.23
Add for additional hidden cost on labour @ 15% `: 21876.23
Add for Contractor's Overheads @ 5% `: 7292.08
Total cost of Labour : `: 212928.64
ABSTRACT:
A. Cost of Materials `: 957120.23
B. Hire charges of Machinery `: 98706.12
C. Cost of Labour `: 212928.64
TOTAL `: 1268755.00
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 19259.03
Add for insurance charges @ 1.00% `: 12687.55
Add for designs and drawings @ 2.50% `: 31718.87
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 31718.87
Add for power supply arrangements @ 2.00% `: 25375.10
Add for enabling works @ 1.50% `: 19031.32
Total `: 1408545.75
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2x10.657 tonnes @ `: 247.10 / tonne `: 5266.69
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 12 ) @ 3.00% `: 12082.95
Total cost for 10.657 tonne `: 1425895.39
Rate per tonne `: 133798.95
Rate approved per tonne `: 133800.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.12
ITEM: Design, fabrication, supply, erection and commissioning of vent liner using 20 mm thick
plates with stiffeners and anchors for river sluice / canal sluice vents including cost of all
materials, machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning, applying
one coat of zinc rich epoxy primer and four coats of cold applied coal tar epoxy paint etc.,
complete with lead upto 1 km and all lifts for structural steel components and all leads
and lifts including packing / forwarding charges for other materials.
57
GATE / HOIST AND ALLIED WORKS
DATA:Vent lining consists of forming river / canal sluice of specified size using 20 mm thick structural
steel plates for the specified length. The liner plates are stiffened on the back side and anchors
are provided for embedment in concrete.
Consider vent lining for river / canal sluice of size 2.5 m x 3 m for analysis.
Consider vent lining for 3.40 m length of vent.
Finished area of lining : ( 2 x 3 x 3.4 + 2 x 2.5 x 3.4 ) : 37.40 sqm
Weight of 20 mm thick MS plate per sqm : 157.00 kg
Add 25 % for stiffeners / anchors / projections etc : 39.25 kg
Total requirement of steel for vent lining of sluice per sqm area Total : 196.25 kg
say : 196 kg
Quantity of steel required for 37.40 sqm ( 37.40 x 0.196 ) : 7.330 tonnes
The weight computed as above on percentage basis for stiffeners / anchors is further checked
by computing the actual weight as per fabrication drawings of vent liner for river sluice service
gate vent of same size provided for one of the dam.
Actual weight of liner for 37.4 sqm as per data in Item : 12 of Annexure-2 : 7.281 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on vent liner drawings for river sluice
service gate vent provided for one of the dam for rate analysis ( for details refer Item : 12 of
Annexure - 2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Plates / flats with 2.5 % wastage ( 7281 x 1.025 ) : 7463 kg
b. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:12 Annexure-2 ) : 4194 Nos
Add for variations / wastage / misc welding @ 10 % ( 4194 x 0.1 ) : 419 Nos
Total requirement of GP / LH electrodes : 4613 Nos
for stitch weld GP electrodes @ 10 % of total ( 4613 x 0.10 ) : 461 Nos
for run welding LH electrodes @ 90 % of total ( 4613 x 0.90 ) : 4152 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides : 203 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 20 Rm
Total : 223 Rm
For cutting structural steel sections to required sizes gas cutting is assumed since most of the
sections are above 10 mm thick.
Length of steel to be cut by using gas manually : 30 m
Length of steel to be cut by gas using pug cutting machine : 193 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 15 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 64 hours
Acetelyne gas @ 0.6 cum / hour ( 15 + 64 ) x 0.60 : 47 cum
Oxygen gas @ 1.8 cum / hour ( 15 + 64 ) x 1.80 : 141 cum
Use of gas cutting torch with 50 min / hr working ( 15 x 60 / 50 ) : 18 hours
Use of pug cutting machine with 50 min / hr working ( 64 x 60 / 50 : ) : 77 hours
3. Welding :
Length of welding : 420 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 461 / 15 ) x 8 / 2 : 123 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 4152 / 15 ) x 8 / 6 : 369 hours
Total : 492 hours
Deploy welding transformer for 492 hours.
58
GATE / HOIST AND ALLIED WORKS
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 123 x 0.25 + 369 x 0.75 ) : 308 hours
4. Surface cleaning and painting :
Painting area for liner : 37.5 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 37.5 sqm @ 9 sqm / ltr / coat : 4 ltr
4 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 37.5 sqm @ 6 sqm / ltr / coat : 25 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 37.5 sqm @ 8 sqm / ltr : 5 ltr
5. Requirement of other machinery :
For handling during fabrication and erection 8 t mobile crane for 4 hours and stationery derric
crane for 16 hours considered.
For grinding and finishing weld joints in liner plates 12 hours use of grinding machine considered.
6. Requirement of work force :
Work component Foreman Marker / Gas cutter / Helper /
Fabricator / Welder Painter Cl-II
Erector /
Cutting sections 95 hours 6 12 12 24
Fabricating by stitch welding 123 hours 8 15 --- 30
Run welding 369 hours 5 --- 46 46
Cleaning surface 37.4 sqm @15 sqm/day --- --- --- 2
Painting ( 5x37.4 ) sqm @ 15 sqm / day --- --- --- 14
Finishing / Cleaning 1 1 --- 1
Total : 20 28 58 117
Note : a. It is assumed that all stitch welding will be done by fabricator. Hence, no separate provision
is considered for welder for stitch welding.
b. Workforce for painting 1 coat primer and 4 coats finishing paint consists of 12 Painters Cl-II
at 15 sqm / day and 2 helpers to assist painters.
7. Excise duty on supply :
Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
8. Use rate of materials :
Cost of welding set @ `: 6750.00 / Each `: 6750.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) `: 6.75
Cost of gas cutting set @ `: 2250.00 / Each `: 2250.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) `: 3.75
59
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
3 Acetyline gas cum 56.00 404.00 22624.00
4 Welding electrodes ( general purpose ) Nos 461.00 11.00 5071.00
5 Welding electrodes ( low hydrogen ) Nos 4152.00 21.00 87192.00
6 Zinc rich epoxy primer ltr 4.00 756.00 3024.00
7 Coal tar epoxy paint ltr 25.00 256.50 6412.50
8 Rust cleaner / inhibitor ltr 5.00 326.00 1630.00
9 Wire brush Nos 1.00 54.00 54.00
10 Use rate welding holder set Hour 492.00 6.75 3321.00
11 Use rate gas cutting torch set Hour 18.00 3.75 67.50
12 Sundries LS 5.00 45.00 225.00
Total `: 456544.15
Add for small Tools and Plants @ 1% `: 4565.44
Add for Contractor's Profit @ 10% `: 45654.42
Add for Contractor's Overheads @ 5% `: 22827.21
Total cost of Materials : `: 529591.21
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 492.00 13.00 6396.00
Fuel / Energy charges Hour 308.00 86.00 26488.00
2 Pug cutting machine Hour 77.00 18.00 1386.00
Fuel / Energy charges Hour 77.00 4.00 308.00
3 Mobile crane 8 t Hour 4.00 412.00 1648.00
Fuel / Energy charges Hour 4.00 718.00 2872.00
4 Stationery derric crane Hour 16.00 73.00 1168.00
Fuel / Energy charges Hour 16.00 15.00 240.00
5 Grinding machine Hour 12.00 20.00 240.00
Fuel / Energy charges Hour 12.00 36.00 432.00
6 Sundries LS 5.00 45.00 225.00
Total `: 41403.00
Add for small Tools and Plants @ 1% `: 414.03
Add for Contractor's Profit on DPOL / Energy @ 10% `: 3056.50
Add for Contractor's Overheads @ 5% `: 2070.15
Total hire charges of Machinery : `: 46943.68
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 4.00 144.00 576.00
2 Crew for Grinding machine Hour 12.00 111.00 1332.00
3 Foreman Day 20.00 311.67 6233.30
4 Marker / Fabricator / Erector Day 28.00 289.67 8110.62
5 Gas cutter Day 12.00 289.67 3475.98
6 Welder ( General ) Day 46.00 289.67 13324.59
Contd
60
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ) :
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
7 Helper fabrication / erection Day 101.00 274.67 27741.17
8 Helper for cleaning / painting Day 4.00 274.67 1098.66
9 Painter Cl - II Day 12.00 274.67 3295.98
10 Electrician Day 1.00 276.17 276.17
Total `: 65464.46
Add for small Tools and Plants @ 1% `: 654.64
Add for Contractor's Profit @ 10% `: 6546.45
Add for hidden cost on Labour @ 15% `: 9819.67
Add for additional hidden cost on labour @ 15% `: 9819.67
Add for Contractor's Overheads @ 5% `: 3273.22
Total cost of Labour : `: 95578.11
ABSTRACT:
A. Cost of Materials `: 529591.21
B. Hire charges of Machinery `: 46943.68
C. Cost of Labour `: 95578.11
TOTAL `: 672113.01
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 8807.85
Add for insurance charges @ 1.00% `: 6721.13
Add for designs and drawings @ 2.50% `: 16802.83
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 16802.83
Add for power supply arrangements @ 2.00% `: 13442.26
Add for enabling works @ 1.50% `: 10081.70
Total `: 744771.59
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 7.281 tonnes @ `: 247.10 / tonne `: 3598.27
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 9 ) @ 3.00% `: 4173.35
Total cost for 37.400 sqm `: 752543.20
Rate per sqm `: 20121.48
Rate approved per sqm `: 20100.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.13
ITEM: Design, fabrication, supply, erection, testing and commissioning of fixed wheel type vertical
lift service gate consisting of skin plate, vertical and horizontal girders, wheels, stiffeners, lifting
brackets, guide rollers, ballast blocks, teflon claded rubber seals etc., with all accessories for
river sluice / canal sluice vent including cost of all materials, machinery, labour, cutting,
aligning, welding, finishing, cleaning, applying one coat of zinc rich epoxy primer and three
coats of cold applied coal tar epoxy paint, seal fixing etc., complete as per specifications and
approved drawings with lead upto 1 km and all lifts for structural steel components and
all leads and lifts including packing / forwarding charges for other materials.
DATA:Consider upstream seal vertical lift roller gate. The gate leaf consists of skin plate, horizontal
girders, vertical end girders, stiffeners, wheels, gate guide rollers, brackets for pulleys, seals
61
GATE / HOIST AND ALLIED WORKS
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Plates / flats with 2.5 % wastage ( 4370 x 1.025 ) : 4479 kg
b. Cast iron components conforming to IS : 210 :
Cast iron blocks for counter weight ( 4000 x 1.025 ) : 4100 kg
c. Alloy steel components conforming to IS : 1570 :
Wheel axles / Pins : 132 kg
d. Cast steel components conforming to IS : 1030 :
Wheels / guide rollers : 492 kg
e. Alluminium / Bronze alloy components conforming to IS : 305 :
Bearings / Bushes : 76 kg
f. Bolts / Nuts / Washers conforming to IS : 1363 :
SS bolts / nuts / washers with 2.5 % wastage ( 54 x 1.025 ) : 55 kg
GI bolts / nuts / washers with 2.5 % wastage ( 74 x 1.025 ) : 76 kg
MS bolts / nuts / washers with 2.5 % wastage ( 4 x 1.025 ) : 4 kg
g. Rubber seal conforming to IS : 11855 :
Bottom seal ( flat type ) ( 2.76 x 1.025 ) : 2.8 Rm
Side seals ( music note type teflon claded ) ( 5.71 x 1.025 ) : 5.85 Rm
Top seal ( music note type teflon claded ) ( 2.2 x 1.025 ) : 2.25 Rm
Corner seal ( teflon claded ) : 2 Nos
h. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:13 Annexure-2 ) : 3265 Nos
Add for variations / wastage / misc welding @ 10 % ( 3265 x 0.1 ) : 326 Nos
Total requirement of GP / LH electrodes : 3591 Nos
for stitch weld GP electrodes @t 10 % of total ( 3591 x 0.10 ) : 359 Nos
for run welding LH electrodes @ 90 % of total ( 3591 x 0.90 ) : 3232 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 137 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 14 Rm
Total : 151 Rm
For cutting structural steel sections to required sizes gas cutting is assumed since most of the
sections are above 10 mm thick.
Length of steel to be cut by using gas manually : 30 m
62
GATE / HOIST AND ALLIED WORKS
63
GATE / HOIST AND ALLIED WORKS
Note : a. It is assumed that all stitch welding will be done by fabricator. Hence, no separate provision
considered for welder for stitch welding.
b. Workforce for painting 1 coat primer and 3 coats finishing paint consists of 25 Painters Cl-II
at 15 sqm / day and 5 helpers to assist painters.
7. Excise duty on supply :
Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
8. Use rate of materials :
Cost of welding set @ `: 6750.00 / Each `: 6750.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) `: 6.75
Cost of gas cutting set @ `: 2250.00 / Each `: 2250.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) `: 3.75
Contd
64
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ):
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
17 Use rate gas cutting torch set Hour 18.00 3.75 67.50
18 Sundries LS 5.00 45.00 225.00
Total `: 767485.30
Add for small Tools and Plants @ 1% `: 7674.85
Add for Contractor's Profit @ 10% `: 76748.53
Add for Contractor's Overheads @ 5% `: 38374.27
Total cost of Materials : `: 890282.95
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 383.00 13.00 4979.00
Fuel / Energy charges Hour 239.00 86.00 20554.00
2 Pug cutting machine Hour 48.00 18.00 864.00
Fuel / Energy charges Hour 48.00 4.00 192.00
3 Tower crane Hour 1.00 1099.00 1099.00
Fuel / Energy charges Hour 1.00 186.00 186.00
4 Mobile crane 8 t Hour 4.00 412.00 1648.00
Fuel / Energy charges Hour 4.00 718.00 2872.00
5 Stationery derric crane Hour 10.00 73.00 730.00
Fuel / Energy charges Hour 10.00 15.00 150.00
6 Grinding machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
7 Drilling machines Hour 12.00 20.00 240.00
Fuel / Energy charges Hour 12.00 36.00 432.00
8 Sundries LS 5.00 45.00 225.00
Total `: 34619.00
Add for small Tools and Plants @ 1% `: 346.19
Add for Contractor's Profit on DPOL / Energy @ 10% `: 2489.90
Add for Contractor's Overheads @ 5% `: 1730.95
Total hire charges of Machinery : `: 39186.04
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 4.00 144.00 576.00
2 Crew for Tower crane Hour 1.00 117.00 117.00
3 Crew for Drilling machine Hour 12.00 111.00 1332.00
4 Crew for Grinding machine Hour 8.00 111.00 888.00
5 Foreman Day 16.00 311.67 4986.64
6 Marker / Fabricator / Erector Day 27.00 289.67 7820.96
7 Gas cutter Day 8.00 289.67 2317.32
8 Welder ( General ) Day 32.00 289.67 9269.28
9 Welder ( X - ray grade ) Day 4.00 318.63 1274.53
10 Helper fabrication / erection Day 86.00 274.67 23621.19
Contd
65
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
11 Helper for cleaning / painting Day 11.00 274.67 3021.32
12 Painter Cl - II Day 25.00 274.67 6866.63
13 Electrician Day 2.00 276.17 552.33
Total `: 62643.18
Add for small Tools and Plants @ 1% `: 626.43
Add for Contractor's Profit @ 10% `: 6264.32
Add for hidden cost on Labour @ 15% `: 9396.48
Add for additional hidden cost on labour @ 15% `: 9396.48
Add for Contractor's Overheads @ 5% `: 3132.16
Total cost of Labour : `: 91459.04
ABSTRACT:
A. Cost of Materials `: 890282.95
B. Hire charges of Machinery `: 39186.04
C. Cost of Labour `: 91459.04
TOTAL `: 1020928.03
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 8073.87
Add for insurance charges @ 1.00% `: 10209.28
Add for designs and drawings @ 2.50% `: 25523.20
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 25523.20
Add for power supply arrangements @ 2.00% `: 20418.56
Add for enabling works @ 1.50% `: 15313.92
Total `: 1125990.06
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2x9.202 tonnes @ `: 247.10 / tonne `: 4547.63
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 15 ) @ 3.00% `: 17287.97
Total cost for 9.202 tonne `: 1147825.66
Rate per tonne `: 124736.54
Rate approved per tonne `: 124700.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.14
ITEM: Design, fabrication, supply, erection, testing and commissioning of adequate capacity rope
drum hoist consisting of hoist platform, rope drum, gear system, electric motor, electro-
magnetic brake system, hand operation assembly, control panel, wire rope, pulleys, ladder etc.,
with all accessories for operating river sluice / canal sluice service gate including cost of
all materials, machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning,
greasing, applying two coats of zinc chromate red oxide primer and three coats of approved
synthetic enamel paint etc., complete with lead upto 1 km and all lifts for structural
steel components and all leads and lifts including packing / forwarding charges for
other materials.
DATA:Rope drum hoist for river / canal sluice service gate consists of embedded parts for anchorage,
hoist supporting structure, pulley support, pulleys, drive stool, rope drums, shafts, couplings,
66
GATE / HOIST AND ALLIED WORKS
gears and pinions, plummer blocks, gear box, electric motor, hand operation assembly, brake,
wire rope, gate position indicator, switch box etc. with related accessories.
Generally the hoist capacity will be 2.5 times the weight of gate including weight of ballast.
Consider rope drum hoist for river / canal sluice service gate for vent of size 2.5 m x 3 m.
Capacity of hoist in tonnes :
Size of gate for 2.5 x 3 m opening : 3.2 m x 3.3 m
Head of water above sill level considered : 34 m
Weight of gate leaf in tonne including weight of ballast based on empirical formula :
2 0.659
= 0.0888 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.659
= 0.0888 x ( 3.2 x 3.2 x x 3.3 x 34 ) : 9.229
Capacity of hoist in tonnes with 25% reserve capacity at 2.5 times wt of gate with ballast.
( 2.50 x 9.229 ) : 23.073 tonnes
Round off the capacity of hoist to next 5 tonne say : 25.00 tonnes
Weight of hoist with all accessories is considered at 0.25 tonne per tonne capacity of hoist.
Weight of hoist with all accessories ( 0.25 x 25 ) : 6.250 tonnes
The hoist capacity and hoist weight computed as above based on empirical formulae are further
checked by varifying / computing the actual capacity and weight as per fabrication drawings for
sluice gate rope drum hoist of same capacity provided for one of the dam.
Actual capacity of hoist as per data sheet : 25.00 tonnes
Actual weight of rope drum hoist as per data in Item :14 of Annexure-2 : 6.243 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of 25 tonne
capacity rope drum hoist provided for river sluice service gate for one of the dam work for rate
analysis ( for details refer Item : 14 of Annexure- 2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 1451x1.025 ) : 1487.00 kg
Plates / flats with 2.5 % wastage ( 392 x 1.025 ) : 402.00 kg
Chequered plates with 2.5 % wastage ( 283 x 1.025 ) : 290.00 kg
b. Cast steel components conforming to IS : 1030 :
Rope drums 2 Nos / Gears ( 1420 +506 ) : 1926.00 kg
Pinions : 79.00 kg
Pulleys 3 Nos / Couplings 2 Nos : 306.00 kg
Plummer blocks / Hubs : 72.00 kg
c. Alloy steel steel components conforming to IS : 1570 :
Shafts : 346.00 kg
Pins : 73.00 kg
d. Alluminium/ Bronze alloy components conforming to IS : 305 :
Bearings / Bush : 57.00 kg
e. Bolt / Nut / Washers conforming to IS : 1363 :
MS Bolts / Nuts / Washers with 2.5 % wastage ( 31 x 1.025 ) : 32.00 kg
f. Steel wire rope conforming ti IS 2266 :
28 mm dia 6 / 37 construction 1 No 120 Rm @ 2.71 kg / m : 325 kg
g. Other components :
Manual operating system : 1 No.
Worm reducer : 1 No
Electric motor 5 hp : 1 No.
Gate position indicator : 1 No.
Ele-magnetic brake : 1 No.
67
GATE / HOIST AND ALLIED WORKS
68
GATE / HOIST AND ALLIED WORKS
69
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
Plummer blocks / Hubs kg 72.00 170.00 12240.00
3 Alloy steel components
Shafts kg 346.00 270.00 93420.00
Pins kg 73.00 330.00 24090.00
4 Bronze alloy components :
Bronze bearings / bush kg 57.00 970.00 55290.00
5 Wire rope 28 mm dia 6/37 construction kg 325.00 160.00 52000.00
6 MS Bolt / Nut / Washer kg 32.00 96.00 3072.00
7 Worm reducers No. 1.00 78750.00 78750.00
8 Electric motor 5 hp No. 1.00 18000.00 18000.00
9 Manual operating system No. 1.00 16875.00 16875.00
10 Gate position indicator No. 1.00 16875.00 16875.00
11 Ele-magnetic brake No. 1.00 16875.00 16875.00
12 Electric cable / switch / control panel etc LS 1.00 11250.00 11250.00
13 Oxygen gas cum 45.00 78.00 3510.00
14 Acetyline gas cum 15.00 404.00 6060.00
15 Welding electrodes ( general purpose ) Nos 110.00 11.00 1210.00
16 Welding electrodes ( low hydrogen ) Nos 995.00 21.00 20895.00
17 Zinc chromate red oxide primer ltr 7.00 209.00 1463.00
18 Synthetic enamel ( 1st quality ) paint ltr 11.00 259.00 2849.00
19 Rust cleaner / inhibitor ltr 5.00 326.00 1630.00
20 Grease kg 25.00 298.00 7450.00
21 Wire brush Nos 1.00 54.00 54.00
22 Use rate welding holder set Hour 117.00 6.75 789.75
23 Use rate gas cutting torch set Hour 16.00 3.75 60.00
24 Sundries LS 5.00 45.00 225.00
Total `: 999865.93
Add for small Tools and Plants @ 1% `: 9998.66
Add for Contractor's Profit @ 10% `: 99986.59
Add for Contractor's Overheads @ 5% `: 49993.30
Total cost of Materials : `: 1159844.47
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 117.00 13.00 1521.00
Fuel / Energy charges Hour 73.00 86.00 6278.00
2 Pug cutting machine Hour 15.00 18.00 270.00
Fuel / Energy charges Hour 15.00 4.00 60.00
3 Mobile crane 8 t Hour 2.00 412.00 824.00
Fuel / Energy charges Hour 2.00 718.00 1436.00
4 Grinding machine Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
5 Drilling machines Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
Contd
70
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
6 Sundries LS 5.00 45.00 225.00
Total `: 10838.00
Add for small Tools and Plants @ 1% `: 108.38
Add for Contractor's Profit on DPOL / Energy @ 10% `: 814.30
Add for Contractor's Overheads @ 5% `: 541.90
Total hire charges of Machinery : `: 12302.58
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane 8 t Hour 2.00 144.00 288.00
2 Crew for Drilling machine Hour 2.00 111.00 222.00
3 Crew for Grinding machine Hour 2.00 111.00 222.00
4 Foreman Day 14.00 311.67 4363.31
5 Marker / Fabricator / Erector Day 21.00 289.67 6082.97
6 Gas cutter Day 4.00 289.67 1158.66
7 Welder ( General ) Day 11.00 289.67 3186.32
8 Helper fabrication / erection Day 55.00 274.67 15106.58
9 Helper for cleaning / painting Day 5.00 274.67 1373.33
10 Painter Cl - II Day 11.00 274.67 3021.32
11 Electrician Day 2.00 276.17 552.33
Total `: 35576.80
Add for small Tools and Plants @ 1% `: 355.77
Add for Contractor's Profit @ 10% `: 3557.68
Add for hidden cost on Labour @ 15% `: 5336.52
Add for additional hidden cost on labour @ 15% `: 5336.52
Add for Contractor's Overheads @ 5% `: 1778.84
Total cost of Labour : `: 51942.12
ABSTRACT:
A. Cost of Materials `: 1159844.47
B. Hire charges of Machinery `: 12302.58
C. Cost of Labour `: 51942.12
TOTAL `: 1224089.17
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 3970.32
Add for insurance charges @ 1.00% `: 12240.89
Add for designs and drawings @ 2.50% `: 30602.23
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 30602.23
Add for power supply arrangements @ 2.00% `: 24481.78
Add for enabling works @ 1.50% `: 18361.34
Total `: 1344347.97
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 6.243 tonnes @ `: 247.10 / tonne `: 3085.29
71
GATE / HOIST AND ALLIED WORKS
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 21 ) @ 3.00% `: 27218.94
Total cost for 6.243 tonne weight `: 1374652.20
25.000 tonne capacity
Rate per tonne weight `: 220190.00
Rate per tonne capacity `: 54986.09
Rate approved per tonne capacity `: 55000.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.15
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts ( without groove
liners ) consisting of sill beam, wheel tracks, seal seats, guide rails, breast wall liner upto
1m height above the roof of vent etc., with all accessories for river / canal sluice emergency
gate including cost of all materials, machinery, labour, cutting, aligning, anchoring, welding,
finishing, cleaning, applying one coat of zinc rich epoxy primer and four coats of cold applied
coal tar epoxy paint etc., complete as per specifications and approved drawings with lead
upto 1 km and all lifts for structural steel components and all leads and lifts including
packing / forwarding charges for other materials.
DATA:Embedded parts for river sluice emergency gate consist of sill beam, wheel / seal tracks, breast
wall lining upto 1 m height above vent top, gate guide etc., with all accessories such as f irst
stage anchors. The weight of embedded parts depends on the height of gate groove and height
upto which breast wall lining is to be provided.
Generally wt of embedded parts for sluice gate will be 50% of wt of gate including ballast.
Weight of breast wall lining for 20 mm MS plate and 6 mm SS plate including stiffeners and
anchors will be about 250 kg per sqm area of breast wall.
Consider embedded parts for river sluice emergency gate for sluice opening of size 1.5 m x 3 m.
Weight of embedded parts in tonne for 1.5 m x 3 m opening based on empirical formula :
Size of gate for 1.5 m x 3 m opening : Length : 2.2 m Height : 3.3 m
Head of water considered above sill level : 16 m
2 0.659
Weight of gate with ballast in tonnes = 0.0888 x ( L x H x h )
Consider weight of embedded parts at 50 % of weight of gate including ballast:
2 0.659
Weight of embedded parts in tonnes = 0.50 x 0.0888 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.659
= 0.0444 x ( 2.2 x 2.2 x 3.3 x 16 ) : 1.714 tonnes
Weight of breast wall lining about 2 sqm @ 250 kg / sqm : 0.500 tonnes
Total : 2.214 tonnes
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of embedded parts for river sluice emergency gate of
same size provided for one of the dam.
Actual weight of embedded parts as per data in Item : 15 of Annexure-2 : 2.180 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on embedded parts drawings for river
sluice emergency gate provided for one of the dam for rate analysis ( for details refer Item 15 of
Annexure - 2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 593x1.025 ) : 608 kg
Plates / flats with 2.5 % wastage ( 1304 x 1.025 ) : 1337 kg
72
GATE / HOIST AND ALLIED WORKS
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 135 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 14 Rm
Total length of cutting Total : 149 Rm
For cutting structural steel sections to required size gas cutting is assumed for cutting angles /
beams / channels / round bars. For plates / flats less than 12 mm in thickness plate shearing
machine and for the remaining sections pug cutting machine is considered.
Length of steel to be cut by using gas manually : 30 m
Length of steel to be cut by gas using pug cutting machine : 89 m
Length of steel to be cut by using shearing machine : 30 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 15 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 30 hours
Time for cutting by shearing machine at ( av ) 10 m cutting / hour : 3 hours
Acetelyne gas @ 0.6 cum / hour ( 15 + 30 ) x 0.60 : 27 cum
Oxygen gas @ 1.8 cum / hour ( 15 + 30 ) x 1.80 : 81 cum
Use of gas cutting torch with 50 min / hr working ( 15 x 60 / 50 ) : 18 hours
Use of pug cutting machine with 50 min / hr working ( 30 x 60 / 50 ) : 36 hours
Use of shearing machine with 50 min / hr working ( 3 x 60 / 50 ) : 4 hours
3. Welding :
Length of welding as per data sheet : 143 m
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 103 + 45 ) x 8 / 15 / 2 : 40 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 923 + 407 ) x 8 / 15 / 6 : 118 hours
Total : 158 hours
Deploy welding transformer for 158 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 40 x 0.25 + 118 x 0.75 ) : 99 hours
73
GATE / HOIST AND ALLIED WORKS
Time for planing 3 m length section with 50 min / hour working : 8 hours
Time for planing 26 m SS plates ( 26 x 8 / 3 ) : 72 hours
74
GATE / HOIST AND ALLIED WORKS
B. MACHINERY :
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 158.00 13.00 2054.00
Fuel / Energy charges Hour 99.00 86.00 8514.00
2 Plate shearing machine Hour 4.00 68.00 272.00
Fuel / Energy charges Hour 4.00 143.00 572.00
3 Pug cutting machine Hour 36.00 18.00 648.00
Fuel / Energy charges Hour 36.00 4.00 144.00
4 Planing machine Hour 72.00 97.00 6984.00
Fuel / Energy charges Hour 72.00 107.00 7704.00
5 Mobile crane 8 t Hour 2.00 412.00 824.00
Fuel / Energy charges Hour 2.00 718.00 1436.00
6 Stationery derric crane Hour 4.00 73.00 292.00
Fuel / Energy charges Hour 4.00 15.00 60.00
7 Grinding machine Hour 12.00 20.00 240.00
Fuel / Energy charges Hour 12.00 36.00 432.00
Contd
75
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ) :
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
8 Drilling machines Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
9 Sundries LS 10.00 45.00 450.00
Total `: 31074.00
Add for small Tools and Plants @ 1% `: 310.74
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1960.00
Add for Contractor's Overheads @ 5% `: 1553.70
Total hire charges of Machinery : `: 34898.44
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 2.00 144.00 288.00
2 Crew for Shearing machine Hour 4.00 87.00 348.00
3 Crew for Planing machine Hour 72.00 139.00 10008.00
4 Crew for Drilling machine Hour 8.00 111.00 888.00
5 Crew for Grinding machine Hour 12.00 111.00 1332.00
6 Foreman Day 15.00 311.67 4674.98
7 Marker / Fabricator / Erector Day 24.00 289.67 6951.96
8 Gas cutter Day 7.00 289.67 2027.66
9 Welder ( General ) Day 12.00 289.67 3475.98
10 Welder ( X - ray ) Day 2.00 318.63 637.26
11 Helper fabrication / erection Day 61.00 274.67 16754.57
12 Helper for cleaning / painting Day 3.00 274.67 824.00
13 Painter Cl - II Day 9.00 274.67 2471.99
14 Electrician Day 1.00 276.17 276.17
Total `: 50958.54
Add for small Tools and Plants @ 1% `: 509.59
Add for Contractor's Profit @ 10% `: 5095.85
Add for hidden cost on Labour @ 15% `: 7643.78
Add for additional hidden cost on labour @ 15% `: 7643.78
Add for Contractor's Overheads @ 5% `: 2547.93
Total cost of Labour : `: 74399.47
ABSTRACT:
A. Cost of Materials `: 240853.99
B. Hire charges of Machinery `: 34898.44
C. Cost of Labour `: 74399.47
TOTAL `: 350151.90
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 6754.61
Add for insurance charges @ 1.00% `: 3501.52
Add for designs and drawings @ 2.50% `: 8753.80
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 8753.80
Add for power supply arrangements @ 2.00% `: 7003.04
76
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.16
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts ( with groove
liners ) consisting of sill beam, wheel tracks, seal seats, guide rails, breast wall liner ( upto
1 m above the roof of vent ), groove liner upto breast wall level etc., with all accessories for
river / canal sluice emergency gate including cost of all materials, machinery, labour,cutting,
aligning, anchoring, welding, finishing, cleaning, applying one coat of zinc rich epoxy primer
and four coats of cold applied coal tar epoxy paint etc., complete as per specifications and
approved drawings with lead upto 1 km and all lifts for structural steel components and
all leads and lifts including packing / forwarding charges for other materials.
DATA:Embedded parts for river sluice emergency gate consist of sill beam, wheel /seal tracks, groove
lining upto breast wall level, breast wall lining upto 1 m above top of vent, gate guide etc., with
all accessories such as first stage anchors. The weight of embedded parts depends on the
height of gate groove and height upto which breast wall lining is to be provided.
Weight of embedded parts for emergency gate will be about 65 to 70 % of gate wt with ballast.
Weight of breast wall lining for 20 mm MS plate and 6 mm SS plate including stiffeners and
anchors will be about 250 kg per sqm area of breast wall.
Weight of groove liner for 20 mm MS plate including stiffeners and anchors will be about
200 kg / sqm area of groove liner.
Consider embedded parts for river sluice emergency gate for sluice opening of size 2.5 m x 3 m.
Size of gate for 2.5 m x 3 m opening : Length : 3.2 m Height : 3.3 m
Head of water considered above sill level : 34 m
Weight of embedded parts in tonne including weight of ballast based on empirical formula :
2 0.659
= 0.0888 x ( L x H x h )
Consider weight of embedded parts at 67.5 % og weight of gate including ballast:
2 0.659
= 0.675 x 0.0888 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.659
= 0.0600 x ( 3.2 x 3.2 x 3.3 x 34 ) : 6.236 tonnes
Weight of breast wall lining about 3.5 sqm @ 250 kg / sqm : 0.875 tonnes
Weight of groove liner about 10 sqm @ 200 kg / sqm : 2.000 tonnes
Total : 9.111 tonnes
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of embedded parts and groove liner for river sluice
emergency gate of same size provided for one of the dam.
Actual weight of embedded parts as per data in Item :16 of Annexure-2 : 9.088 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on embedded parts and groove liner
drawings for river sluice emergency gate provided for one of the dam work for rate analysis ( for
77
GATE / HOIST AND ALLIED WORKS
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 992x1.025 ) : 1017 kg
Plates / flats with 2.5 % wastage ( 7431 x 1.025 ) : 7617 kg
b. Alloy steel components conforming to IS : 1570 :
Stainless steel plates / flats ( 431 x 1.025 ) : 442 kg
c. Bolt / Nut / Washer conforming ti IS : 1363 :
MS bolts and nuts with 2.5 % wastage ( 234 x 1.025 ) : 240 kg
d. Welding electrodes ( General purpose / Low hydrogen / Stainless steel ) :
GP / LH electrodes as per data sheet ( Item:16 Annexure-2 ) : 5256 Nos
Add for variations / wastage / misc welding @ 10 % ( 5256 x 0.1 ) : 526 Nos
Total requirement of GP / LH electrodes : 5782 Nos
for stitch welding GP electrodes @t 10 % of total ( 5782 x 0.10 ) : 578 Nos
for run welding LH electrodes @ 90 % of total ( 5782 x 0.90 ) : 5204 Nos
Stainless steel electrodes as per data sheet ( Item:16 Annexure-2 ) : 752 Nos
Add for variations / wastage @ 5 % ( 752 x 0.05 ) : 38 Nos
Total requirement of Stainless steel ( SS ) electrodes : 790 Nos
for stitch weld SS electrodes @t 10 % of total ( 790 x 0.10 ) : 79 Nos
for run weld SS electrodes @t 90 % of total ( 790 x 0.90 ) : 711 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 301 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 30 Rm
Total length of cutting Total : 331 Rm
For cutting structural steel sections to required size gas cutting is assumed for cutting angles /
beams / channels / round bars. For plates / flats less than 12 mm in thickness plate shearing
machine and for the remaining sections pug cutting machine is considered.
Length of steel to be cut by using gas manually : 60 m
Length of steel to be cut by gas using pug cutting machine : 211 m
Length of steel to be cut by using shearing machine : 60 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 30 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 70 hours
Time for cutting by shearing machine at ( av ) 10 m cutting / hour : 6 hours
Acetelyne gas @ 0.6 cum / hour ( 30 + 70 ) x 0.60 : 60 cum
Oxygen gas @ 1.8 cum / hour ( 30 + 70 ) x 1.80 : 180 cum
Use of gas cutting torch with 50 min / hr working ( 30 x 60 / 50 ) : 36 hours
Use of pug cutting machine with 50 min / hr working ( 70 x 60 / 50 ) : 84 hours
Use of shearing machine with 50 min / hr working ( 6 x 60 / 50 ) : 7 hours
3. Welding :
Length of welding as per data sheet : 560 m
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 578 + 79 ) x 8 / 15 / 2 : 175 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 5204 + 711 ) x 8 / 15 / 6 : 526 hours
Total : 701 hours
Deploy welding transformer for 701 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 175 x 0.25 + 526 x 0.75 ) : 438 hours
78
GATE / HOIST AND ALLIED WORKS
79
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 701.00 13.00 9113.00
Fuel / Energy charges Hour 438.00 86.00 37668.00
2 Plate shearing machine Hour 7.00 68.00 476.00
Fuel / Energy charges Hour 7.00 143.00 1001.00
3 Pug cutting machine Hour 84.00 18.00 1512.00
Fuel / Energy charges Hour 84.00 4.00 336.00
4 Planing machine Hour 69.00 97.00 6693.00
Fuel / Energy charges Hour 69.00 107.00 7383.00
5 Mobile crane 8 t Hour 4.00 412.00 1648.00
Fuel / Energy charges Hour 4.00 718.00 2872.00
Contd
80
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ) :
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
6 Stationery derric crane Hour 40.00 73.00 2920.00
Fuel / Energy charges Hour 40.00 15.00 600.00
7 Grinding machine Hour 25.00 20.00 500.00
Fuel / Energy charges Hour 25.00 36.00 900.00
8 Drilling machines Hour 50.00 20.00 1000.00
Fuel / Energy charges Hour 50.00 36.00 1800.00
9 Sundries LS 25.00 45.00 1125.00
Total `: 77547.00
Add for small Tools and Plants @ 1% `: 775.47
Add for Contractor's Profit on DPOL / Energy @ 10% `: 5368.50
Add for Contractor's Overheads @ 5% `: 3877.35
Total hire charges of Machinery : `: 87568.32
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 4.00 144.00 576.00
2 Crew for Shearing machine Hour 7.00 87.00 609.00
3 Crew for Planing machine Hour 69.00 139.00 9591.00
4 Crew for Drilling machine Hour 50.00 111.00 5550.00
5 Crew for Grinding machine Hour 25.00 111.00 2775.00
6 Foreman Day 42.00 311.67 13089.93
7 Marker / Fabricator / Erector Day 68.00 289.67 19697.22
8 Gas cutter Day 16.00 289.67 4634.64
9 Welder ( General ) Day 59.00 289.67 17090.24
10 Welder ( X - ray ) Day 7.00 318.63 2230.42
11 Helper fabrication / erection Day 186.00 274.67 51087.69
12 Helper for cleaning / painting Day 12.00 274.67 3295.98
13 Painter Cl - II Day 30.00 274.67 8239.95
14 Electrician Day 2.00 276.17 552.33
Total `: 139019.40
Add for small Tools and Plants @ 1% `: 1390.19
Add for Contractor's Profit @ 10% `: 13901.94
Add for hidden cost on Labour @ 15% `: 20852.91
Add for additional hidden cost on labour @ 15% `: 20852.91
Add for Contractor's Overheads @ 5% `: 6950.97
Total cost of Labour : `: 202968.32
ABSTRACT:
A. Cost of Materials `: 822011.32
B. Hire charges of Machinery `: 87568.32
C. Cost of Labour `: 202968.32
TOTAL `: 1112547.96
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 17955.16
Add for insurance charges @ 1.00% `: 11125.48
81
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.17
ITEM: Design, fabrication, supply, erection, testing and commissioning of fixed wheel type vertical lift
emergency gate consisting of skin plate, horizontal and vertical girders, wheels, stiffeners,
lifting brackets, guide rollers, ballast blocks, teflon claded rubber seals etc., with all accessories
for river sluice / canal sluice vent including cost of all materials, machinery, labour, cutting,
aligning, welding, finishing, cleaning, applying one coat of zinc rich epoxy primer and three
coats of cold applied coal tar epoxy paint, seal fixing etc., complete as per specifications
and approved drawings with lead upto 1 km and all lifts for structural steel components
and all leads and lifts including packing / forwarding charges for other materials.
DATA:Consider upstream seal vertical lift roller gate. The gate leaf consists of skin plate, horizontal
girders, vertical end girders, stiffeners, wheels, gate guide rollers, brackets for hooks, seals
etc., with all accessories.
Consider river / canal sluice emergency gate for 2.5 m x 3 m sluice opening for analysis.
For vent opening of 2.5 x 3.0 m approximate size of gate leaf will be : 3.2 m x 3.3 m
Head of water above sill level considered : 34 m
Weight of vertical lift roller gate in tonnes including ballast based on empirical formula :
2 0.659
= 0.0888 ( L x H x h )
Where ( L ) is length and ( H ) is height of gate and ( h ) is head of water above sill in Rm.
0.659
= 0.0888 ( 3.2 x 3.2 x 3.3 x 34 ) : 9.229
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings for river sluice emergency gate of same size provided
for one of the dam.
Actual wt of river sluice emergency gate as per data in Item :17 of Annexure-2 : 9.215 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of river sluice
gate provided for one of the dam for rate analysis ( for details refer Item:17 of Annexure-2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Plates / flats with 2.5 % wastage ( 4301 x 1.025 ) : 4409 kg
b. Cast iron components conforming to IS : 210 :
Cast iron blocks for counter weight ( 4000 x 1.025 ) : 4100 kg
82
GATE / HOIST AND ALLIED WORKS
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 134 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 13 Rm
Total : 147 Rm
For cutting structural steel sections to required sizes gas cutting is assumed since most of the
sections are above 10 mm thick.
Length of steel to be cut by using gas manually : 29 m
Length of steel to be cut by gas using pug cutting machine : 118 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 15 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 39 hours
Acetelyne gas @ 0.6 cum / hour ( 15 + 39 ) x 0.60 : 32 cum
Oxygen gas @ 1.8 cum / hour ( 15 + 39 ) x 1.80 : 96 cum
Use of gas cutting torch with 50 min / hr working ( 15 x 60 / 50 ) : 18 hours
Use of pug cutting machine with 50 min / hr working ( 39 x 60 / 50 ) : 47 hours
3. Welding :
Length of welding as per data sheet : 271 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 332 / 15 ) x 8 / 2 : 89 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 2987 / 15 ) x 8 / 6 : 265 hours
Total : 354 hours
Deploy welding transformer for 354 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 89 x 0.25 + 265 x 0.75 ) : 221 hours
83
GATE / HOIST AND ALLIED WORKS
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 92 sqm @ 9 sqm / ltr / coat : 10 ltr
3 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 92 sqm @ 6 sqm / ltr / coat : 46 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 92 sqm @ 8 sqm / ltr : 12 ltr
84
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 354.00 13.00 4602.00
Fuel / Energy charges Hour 221.00 86.00 19006.00
2 Pug cutting machine Hour 47.00 18.00 846.00
Fuel / Energy charges Hour 47.00 4.00 188.00
3 Tower crane Hour 1.00 1099.00 1099.00
Fuel / Energy charges Hour 1.00 186.00 186.00
Contd
85
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ) :
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
4 Mobile crane 8 t Hour 4.00 412.00 1648.00
Fuel / Energy charges Hour 4.00 718.00 2872.00
5 Stationery derric crane Hour 10.00 73.00 730.00
Fuel / Energy charges Hour 10.00 15.00 150.00
6 Grinding machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
7 Drilling machines Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
8 Sundries LS 5.00 45.00 225.00
Total `: 32448.00
Add for small Tools and Plants @ 1% `: 324.48
Add for Contractor's Profit on DPOL / Energy @ 10% `: 2320.30
Add for Contractor's Overheads @ 5% `: 1622.40
Total hire charges of Machinery : `: 36715.18
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 4.00 144.00 576.00
2 Crew for Tower crane Hour 1.00 117.00 117.00
3 Crew for Drilling machine Hour 8.00 111.00 888.00
4 Crew for Grinding machine Hour 8.00 111.00 888.00
5 Foreman Day 17.00 311.67 5298.31
6 Marker / Fabricator / Erector Day 25.00 289.67 7241.63
7 Gas cutter Day 8.00 289.67 2317.32
8 Welder ( General ) Day 29.00 289.67 8400.29
9 Welder ( X - ray grade ) Day 4.00 318.63 1274.53
10 Khalasi Day 4.00 276.17 1104.66
11 Helper fabrication / erection Day 79.00 274.67 21698.54
12 Helper for cleaning / painting Day 11.00 274.67 3021.32
13 Painter Cl - II Day 25.00 274.67 6866.63
14 Electrician Day 2.00 276.17 552.33
Total `: 60244.53
Add for small Tools and Plants @ 1% `: 602.45
Add for Contractor's Profit @ 10% `: 6024.45
Add for hidden cost on Labour @ 15% `: 9036.68
Add for additional hidden cost on labour @ 15% `: 9036.68
Add for Contractor's Overheads @ 5% `: 3012.23
Total cost of Labour : `: 87957.01
ABSTRACT:
A. Cost of Materials `: 894789.26
B. Hire charges of Machinery `: 36715.18
C. Cost of Labour `: 87957.01
TOTAL `: 1019461.45
86
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.18
ITEM: Design, fabrication, supply, erection, testing and commissioning of automatic lifting beam
with all accessories for handling, lowering and lifting of river sluice / canal sluice emergency
gate including cost of all materials, machinery, labour, cutting, aligning, welding, finishing,
cleaning, applying one coat of zinc rich epoxy primer and two coats of cold applied coal tar
epoxy paint etc., complete as per specifications and drawings with all lead upto 1 km and all
lifts for structural steel components and all leads and lifts including packing /forwarding
charges for other materials.
DATA:Automatic lifting beam for lifting river sluice emergency gate consists of fabricated beam with
lifting bracket and automatic engaging / dis-engaging type hooks for under water hooking /
de-hooking of gate leaf. Lifting beam is an independent attachment to moving gantry crane.
Generally the weight of lifting beam for river sluice emergency gate will be about 10 percent of
the weight of gate leaf with ballast.
Consider river sluice emergency gate for sluice opening of size 2.5 m x 3 m for analysis.
For vent opening of 2.5 x 3.0 m approximate size of gate leaf will be : 3.2 m x 3.3 m
Head of water above sill level considered : 34 m
Weight of vertical lift roller gate in tonnes including weight of ballast as per empirical formula :
2 0.659
= 0.0888 ( L x H x h )
Where ( L ) is length and ( H ) is height of gate and ( h ) is head of water above sill in Rm.
Consider weight of lifting beam @ 10 % of weight of gate including ballast:
2 0.659
= 0.10 x 0.0888 ( L x H x h )
0.659
= 0.0089 ( 3.2 x 3.2 x 3.3 x 34 ) : 0.925 tonne
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of lifting beam for river sluice emergency gate of same
size provided for one of the dam.
Actual weight of lifting beam as per data in Item : 18 of Annexure-2 : 0.922 tonne
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of lifting
beam for river sluice emergency gate provided for one of the dam for rate analysis ( for details
refer Item : 18 of Annexure-2 ).
87
GATE / HOIST AND ALLIED WORKS
1. Requirement of materials :
a. Structural steel :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 228x1.025 ) : 234 kg
Plates / flats with 2.5 % wastage ( 476 x 1.025 ) : 488 kg
b. Alloy steel components :
Pins : 71 kg
c. Bronze alloy components :
Bush : 4 kg
d. Forged steel components :
Hooks : 130 kg
e. Bolts / Nuts / Washers :
MS bolts / nuts / washers with 2.5 % wastage ( 2 x 1.025 ) : 2 kg
f. MS pipe 100 mm dia : 11 kg
g. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:18 Annexure-2 ) : 508 Nos
Add for variations / wastage / misc welding @ 10 % ( 508 x 0.1 ) : 51 Nos
Total requirement of GP / LH electrodes : 559 Nos
for stitch weld GP electrodes @t 10 % of total ( 559 x 0.10 ) : 56 Nos
for run welding LH electrodes @ 90 % of total ( 559 x 0.90 ) : 503 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 43 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 4 Rm
Total : 47 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas manually : 10 m
Length of steel to be cut by gas using pug cutting machine : 37 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 5 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 12 hours
Acetelyne gas @ 0.6 cum / hour ( 5 + 12 ) x 0.60 : 10 cum
Oxygen gas @ 1.8 cum / hour ( 5 + 12 ) x 1.80 : 30 cum
Use of gas cutting torch with 50 min / hr working ( 5 x 60 / 50 ) : 6 hours
Use of pug cutting machine with 50 min / hr working ( 12 x 60 / 50 ) : 15 hours
3. Welding :
Length of welding as per data sheet : 49 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 56 / 15 ) x 8 / 2 : 15 hours
For run welding @ 6 hrs usage / shift & @ 12 electrodes / hr
( 503 / 15 ) x 8 / 6 : 45 hours
Total : 60 hours
Deploy welding transformer for 60 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 15 x 0.25 + 45 x 0.75 ) : 38 hours
4. Surface cleaning and painting :
Painting area for lifting beam at 12 sqm / tonne ( 0.922 x 12 ) : 11 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 11 sqm @ 9 sqm / ltr / coat : 1.25 ltr
2 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 11 sqm @ 6 sqm / ltr / coat : 4 ltr
88
GATE / HOIST AND ALLIED WORKS
89
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
5 MS pipe 100 mm dia kg 11.00 74.00 814.00
6 Bolt / Nut / Washer
MS bolts / nuts / washers kg 2.00 96.00 192.00
7 Oxygen gas cum 30.00 78.00 2340.00
8 Acetyline gas cum 10.00 404.00 4040.00
9 Welding electrodes ( general purpose ) Nos 56.00 11.00 616.00
10 Welding electrodes ( low hydrogen ) Nos 503.00 21.00 10563.00
11 Zinc rich epoxy primer ltr 1.25 756.00 945.00
12 Coal tar epoxy paint ltr 4.00 256.50 1026.00
13 Rust cleaner / inhibitor ltr 1.50 326.00 489.00
14 Wire brush Nos 1.00 54.00 54.00
15 Use rate welding holder set Hour 60.00 6.75 405.00
16 Use rate gas cutting torch set Hour 6.00 3.75 22.50
17 Sundries LS 5.00 45.00 225.00
Total `: 109184.60
Add for small Tools and Plants @ 1% `: 1091.85
Add for Contractor's Profit @ 10% `: 10918.46
Add for Contractor's Overheads @ 5% `: 5459.23
Total cost of Materials : `: 126654.14
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 60.00 13.00 780.00
Fuel / Energy charges Hour 38.00 86.00 3268.00
2 Pug cutting machine Hour 15.00 18.00 270.00
Fuel / Energy charges Hour 15.00 4.00 60.00
3 Grinding machine Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
4 Drilling machines Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
5 Sundries LS 3.00 45.00 135.00
Total `: 4737.00
Add for small Tools and Plants @ 1% `: 47.37
Add for Contractor's Profit on DPOL / Energy @ 10% `: 360.70
Add for Contractor's Overheads @ 5% `: 236.85
Total hire charges of Machinery : `: 5381.92
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Drilling machine Hour 2.00 111.00 222.00
2 Crew for Grinding machine Hour 2.00 111.00 222.00
3 Foreman Day 3.00 311.67 935.00
4 Marker / Fabricator / Erector Day 7.00 289.67 2027.66
Contd
90
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ) :
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
5 Gas cutter Day 3.00 289.67 869.00
6 Welder ( General ) Day 6.00 289.67 1737.99
7 Helper fabrication / erection Day 18.00 274.67 4943.97
8 Helper for cleaning / painting Day 2.00 274.67 549.33
9 Painter Cl - II Day 2.00 274.67 549.33
10 Electrician Day 1.00 276.17 276.17
Total `: 12332.43
Add for small Tools and Plants @ 1% `: 123.32
Add for Contractor's Profit @ 10% `: 1233.24
Add for hidden cost on Labour @ 15% `: 1849.86
Add for additional hidden cost on labour @ 15% `: 1849.86
Add for Contractor's Overheads @ 5% `: 616.62
Total cost of Labour : `: 18005.35
ABSTRACT:
A. Cost of Materials `: 126654.14
B. Hire charges of Machinery `: 5381.92
C. Cost of Labour `: 18005.35
TOTAL `: 150041.40
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 1445.33
Add for insurance charges @ 1.00% `: 1500.41
Add for designs and drawings @ 2.50% `: 3751.04
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 3751.04
Add for power supply arrangements @ 2.00% `: 3000.83
Add for enabling works @ 1.50% `: 2250.62
Total `: 165740.67
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 0.922 tonnes @ `: 247.10 / tonne `: 455.65
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 14 ) @ 3.00% `: 2348.67
Total cost for 0.922 tonne `: 168544.99
Rate per tonne `: 182803.68
Rate approved per tonne `: 182800.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.19
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts consisting of
sill beam, wheel tracks, seal seats, guide rails etc., with all accessories for vertical lift
barrage gate including cost of all materials, machinery, labour, cutting, aligning, anchoring,
welding, finishing, cleaning, applying one coat of zinc rich epoxy primer and four coats of cold
applied coal tar epoxy paint etc.,complete as per specifications and aproved drawings with lead
upto 1 km and all lifts for structural steel components and all leads and lifts including
packing / forwarding charges for other materials.
DATA:Barrage gate embedded parts consist of sill beam, wheel tracks / seal tracks and gate guides
91
GATE / HOIST AND ALLIED WORKS
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 588x1.025 ) : 603 kg
Plates / flats with 2.5 % wastage ( 3685 x 1.025 ) : 3777 kg
b. Alloy steel components conforming to IS : 1570 :
Stainless steel plates / flats ( 620 + 133 ) x 1.025 : 772.00 kg
c. Bolt / Nut / Washer conforming ti IS : 1363 :
MS bolts and nuts with 2.5 % wastage ( 167 x 1.025 ) : 171 kg
d. Welding electrodes ( General purpose / Low hydrogen / Stainless steel ) :
GP / LH electrodes as per data sheet ( Item:19 Annexure-2 ) : 1734 Nos
Add for variations / wastage / misc welding @ 10 % ( 1734 x 0.1 ) : 173 Nos
Total requirement of GP / LH electrodes : 1907 Nos
for stitch welding GP electrodes @t 10 % of total ( 1907 x 0.10 ) : 191 Nos
for run welding LH electrodes @ 90 % of total ( 1907 x 0.90 ) : 1716 Nos
Stainless steel electrodes as per data sheet ( Item:19 Annexure-2 ) : 1282 Nos
Add for variations / wastage @ 5 % ( 1282 x 0.05 ) : 64 Nos
Total requirement of Stainless steel ( SS ) electrodes : 1346 Nos
for stitch weld SS electrodes @t 10 % of total ( 1346 x 0.10 ) : 135 Nos
for run weld SS electrodes @t 90 % of total ( 1346 x 0.90 ) : 1211 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 210 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 21 Rm
Total length of cutting Total : 231 Rm
For cutting structural steel sections to required size gas cutting and use of plate shearing
machine is considered.
Length of steel to be cut by using gas manually : 50 m
Length of steel to be cut by gas using pug cutting machine : 151 m
Length of steel to be cut by using shearing machine : 30 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 25 hours
92
GATE / HOIST AND ALLIED WORKS
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 50 hours
Time for cutting by shearing machine at ( av ) 10 m cutting / hour : 3 hours
Acetelyne gas @ 0.6 cum / hour ( 25 + 50 ) x 0.60 : 45 cum
Oxygen gas @ 1.8 cum / hour ( 25 + 50 ) x 1.80 : 135 cum
Use of gas cutting torch with 50 min / hr working ( 25 x 60 / 50 ) : 30 hours
Use of pug cutting machine with 50 min / hr working ( 50 x 60 / 50 ) : 60 hours
Use of shearing machine with 50 min / hr working ( 3 x 60 / 50) : 4 hours
3. Welding :
Length of welding as per data sheet : 252 m
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 191 + 135 ) x 8 / 15 / 2 : 87 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 1716 + 1211 ) x 8 / 15 / 6 : 260 hours
Total : 347 hours
Deploy welding transformer for 347 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 87 x 0.25 + 260 x 0.75 ) : 217 hours
4. Planing SS plates for wheel / seal tracks :
For surface finishing of SS plates for wheel / seal tracks planing machine is considered.
Length of SS plate for surface finishing by planing machine : 63.00 Rm
Length of planing at a time for 4 m stroke planing machine : 3 Rm
Time for planing 3 m length section with 50 min / hour working : 8 hours
Time for planing 63 m SS plates ( 63 x 8 / 3 ) : 168 hours
93
GATE / HOIST AND ALLIED WORKS
94
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ):
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
14 Use rate gas cutting torch set Hour 30.00 3.75 112.50
15 Sundries LS 75.00 45.00 3375.00
Total `: 523948.75
Add for small Tools and Plants @ 1% `: 5239.49
Add for Contractor's Profit @ 10% `: 52394.88
Add for Contractor's Overheads @ 5% `: 26197.44
Total cost of Materials : `: 607780.55
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 347.00 13.00 4511.00
Fuel / Energy charges Hour 217.00 86.00 18662.00
2 Plate shearing machine Hour 4.00 68.00 272.00
Fuel / Energy charges Hour 4.00 143.00 572.00
3 Pug cutting machine Hour 60.00 18.00 1080.00
Fuel / Energy charges Hour 60.00 4.00 240.00
4 Planing machine Hour 168.00 97.00 16296.00
Fuel / Energy charges Hour 168.00 107.00 17976.00
5 Mobile crane 25 t Hour 24.00 4217.00 101208.00
Fuel / Energy charges Hour 12.00 1994.00 23928.00
6 Stationery derric crane Hour 75.00 73.00 5475.00
Fuel / Energy charges Hour 75.00 15.00 1125.00
7 Grinding machine Hour 24.00 20.00 480.00
Fuel / Energy charges Hour 24.00 36.00 864.00
8 Drilling machines Hour 24.00 20.00 480.00
Fuel / Energy charges Hour 24.00 36.00 864.00
9 Sundries LS 70.00 45.00 3150.00
Total `: 197183.00
Add for small Tools and Plants @ 1% `: 1971.83
Add for Contractor's Profit on DPOL / Energy @ 10% `: 6738.10
Add for Contractor's Overheads @ 5% `: 9859.15
Total hire charges of Machinery : `: 215752.08
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane 25 t Hour 24.00 144.00 3456.00
2 Crew for Plate shearing machine Hour 4.00 87.00 348.00
3 Crew for Planing machine Hour 168.00 139.00 23352.00
4 Crew for Drilling machine Hour 24.00 111.00 2664.00
5 Crew for Grinding machine Hour 24.00 111.00 2664.00
6 Foreman Day 40.00 311.67 12466.60
7 Marker / Fabricator / Erector Day 63.00 289.67 18248.90
8 Gas cutter Day 12.00 289.67 3475.98
Contd
95
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
9 Welder ( General ) Day 29.00 289.67 8400.29
10 Welder ( X - ray ) Day 3.00 318.63 955.89
11 Helper fabrication / erection Day 154.00 274.67 42298.41
12 Helper for cleaning / painting Day 6.00 274.67 1647.99
13 Painter Cl - II Day 17.00 274.67 4669.31
14 Electrician Day 2.00 276.17 552.33
Total `: 125199.69
Add for small Tools and Plants @ 1% `: 1252.00
Add for Contractor's Profit @ 10% `: 12519.97
Add for hidden cost on Labour @ 15% `: 18779.95
Add for additional hidden cost on labour @ 15% `: 18779.95
Add for Contractor's Overheads @ 5% `: 6259.98
Total cost of Labour : `: 182791.55
ABSTRACT:
A. Cost of Materials `: 607780.55
B. Hire charges of Machinery `: 215752.08
C. Cost of Labour `: 182791.55
TOTAL `: 1006324.18
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 24630.00
Add for insurance charges @ 1.00% `: 10063.24
Add for designs and drawings @ 2.50% `: 25158.10
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 25158.10
Add for power supply arrangements @ 2.00% `: 20126.48
Add for enabling works @ 1.50% `: 15094.86
Total `: 1126554.97
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 5.193 tonnes @ `: 247.10 / tonne `: 2566.38
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 12 ) @ 3.00% `: 10027.25
Total cost for 5.193 tonne `: 1139148.60
Rate per tonne `: 219362.33
Rate approved per tonne `: 219400.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.20
ITEM: Design, fabrication, supply, erection, testing and commissioning of fixed wheel type vertical
lift gate consisting of skin plate, vertical and horizontal girders, wheels, stiffeners, lifting
brackets, guide shoes, rubber seals etc., with all accessories for barrage including cost of all
materials, machinery, labour, cutting, aligning, welding, finishing, cleaning, applying one coat
of zinc rich epoxy primer and three coats of cold applied coal tar epoxy paint, seal fixing etc.,
complete as per specifications and approved drawings with lead upto 1 km and all lifts for
structural steel components and all leads and lifts including packing / forwarding
charges for other materials.
96
GATE / HOIST AND ALLIED WORKS
DATA:Consider upstream seal vertical lift roller gate. The gate leaf consists of skin plate, horizontal
girders, vertical end girders, stiffeners, wheels, gate guide shoes, brackets for pulleys, seals
etc., with all accessories.
Consider vertical lift roller gate for 13.72 m x 8.26 m opening for analysis.
For vent opening of 13.72 x 8.26 m the approximate size of gate leaf will be 14.7 x 8.6 m.
Head of water above sill level considered : 8.26 m
Weight of gate leaf in tonne for vertical lift roller gate based on empirical formula :
2 0.716
= 0.0335 ( L x H x h )
Where ( L ) is length and ( H ) is height of gate and ( h ) is head of water above sill in Rm.
0.716
= 0.0335 x( 14.7 x 14.7 x 8.6 x 8.26 ) : 33.289
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of vertical lift barrage gate of same size provided for
one of the barrage.
Actual weight of vertical lift barrage gate as per data in Item : 20 of Annexure-2 : 33.025 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of vertical lift
gate provided for one of the barrage for rate analysis ( for details refer Item : 20 of Annexure-2 ).
1. Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels with 2.5 % wastage ( 3299x1.025 ) : 3382 kg
Plates / flats with 2.5 % wastage ( 28655 x 1.025 ) : 29372 kg
b. Alloy steel components conforming to IS : 1570 :
Wheel axles / Pins : 176 kg
c. Cast steel components conforming to IS : 1030 :
Wheels : 656 kg
d. Alluminium / Bronze alloy components conforming to IS : 305 :
Bearings / Bushes : 80 kg
e. Bolts / Nuts / Washers conforming to IS : 1363 :
GI bolts / nuts / washers with 2.5 % wastage ( 91 x 1.025 ) : 93 kg
MS bolts / nuts / washers with 2.5 % wastage ( 68 x 1.025 ) : 70 kg
f. Rubber seal conforming to IS : 11855 :
Bottom seal ( flat uncladed ) ( 14 x 1.025 ) : 14.5 Rm
Side seals ( bulb uncladed ) ( 17.2 x 1.025 ) : 18 Rm
g. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:20 Annexure-2 ) : 18400 Nos
Add for variations / wastage / misc welding @ 10 % ( 18400 x 0.1 ) : 1840 Nos
Total requirement of GP / LH electrodes : 20240 Nos
for stitch weld GP electrodes @t 10 % of total ( 20240 x 0.10 ) : 2024 Nos
for run welding LH electrodes @ 90 % of total ( 20240 x 0.90 ) : 18216 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 695 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 70 Rm
Total : 765 Rm
For cutting structural steel sections to required sizes gas cutting and plate shearing machine
for plates less than 12 mm thick are considered.
Length of steel to be cut by using gas manually : 200 m
Length of steel to be cut by gas using pug cutting machine : 465 m
Length of steel to be cut by gas using plate shearing machine : 100 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 100 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 155 hours
97
GATE / HOIST AND ALLIED WORKS
98
GATE / HOIST AND ALLIED WORKS
99
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 2160.00 13.00 28080.00
Fuel / Energy charges Hour 1350.00 86.00 116100.00
2 Pug cutting machine Hour 186.00 18.00 3348.00
Fuel / Energy charges Hour 186.00 4.00 744.00
3 Plate shearing machine Hour 12.00 68.00 816.00
Fuel / Energy charges Hour 12.00 143.00 1716.00
4 Mobile crane 25 t Hour 20.00 4217.00 84340.00
Fuel / Energy charges Hour 10.00 1994.00 19940.00
5 Mobile crane 8 t Hour 40.00 412.00 16480.00
Fuel / Energy charges Hour 40.00 718.00 28720.00
6 Stationery derric crane Hour 150.00 73.00 10950.00
Fuel / Energy charges Hour 150.00 15.00 2250.00
7 Grinding machine Hour 100.00 20.00 2000.00
Fuel / Energy charges Hour 100.00 36.00 3600.00
8 Drilling machines Hour 50.00 20.00 1000.00
Fuel / Energy charges Hour 50.00 36.00 1800.00
9 Sundries LS 75.00 45.00 3375.00
Total `: 325259.00
Add for small Tools and Plants @ 1% `: 3252.59
Add for Contractor's Profit on DPOL / Energy @ 10% `: 17824.50
Add for Contractor's Overheads @ 5% `: 16262.95
Total hire charges of Machinery : `: 362599.04
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane 25 t Hour 20.00 139.00 2780.00
2 Crew for Mobile crane 8 t Hour 40.00 144.00 5760.00
3 Crew for Plate shearing machine Hour 12.00 87.00 1044.00
4 Crew for Drilling machine Hour 50.00 111.00 5550.00
5 Crew for Grinding machine Hour 100.00 111.00 11100.00
6 Foreman Day 85.00 311.67 26491.53
7 Marker / Fabricator / Erector Day 130.00 289.67 37656.45
8 Gas cutter Day 40.00 289.67 11586.60
9 Welder ( General ) Day 183.00 289.67 53008.70
10 Welder ( X - ray grade ) Day 20.00 318.63 6372.63
11 Khalasi Day 100.00 276.17 27616.50
12 Helper fabrication / erection Day 479.00 274.67 131564.54
13 Helper for cleaning / painting Day 70.00 274.67 19226.55
14 Painter Cl - II Day 158.00 274.67 43397.07
15 Electrician Day 10.00 276.17 2761.65
Total `: 385916.21
Add for small Tools and Plants @ 1% `: 3859.16
Add for Contractor's Profit @ 10% `: 38591.62
Add for hidden cost on Labour @ 15% `: 57887.43
Contd
100
GATE / HOIST AND ALLIED WORKS
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
Add for additional hidden cost on labour @ 15% `: 57887.43
Add for Contractor's Overheads @ 5% `: 19295.81
Total cost of Labour : `: 563437.66
ABSTRACT:
A. Cost of Materials `: 2696428.35
B. Hire charges of Machinery `: 362599.04
C. Cost of Labour `: 563437.66
TOTAL `: 3622465.05
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 57229.07
Add for insurance charges @ 1.00% `: 36224.65
Add for designs and drawings @ 2.50% `: 90561.63
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 90561.63
Add for power supply arrangements @ 2.00% `: 72449.30
Add for enabling works @ 1.50% `: 54336.98
Total `: 4023828.30
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2x33.025 tonnes @ `: 247.10 / tonne `: 16320.96
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 14 ) @ 3.00% `: 27880.88
Total cost for 33.025 tonne `: 4068030.13
Rate per tonne `: 123180.32
Rate approved per tonne `: 123200.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.21
ITEM: Design, fabrication, supply, erection and commissioning of structural steel hoist bridge
consisting of columns, beams, bracings, stiffeners, ties, chequered plate covering, hand railing,
ladder etc., with all other accessories for supporting rope drum hoist for operating barrage
gates including cost of all materials, machinery, labour, cutting, aligning, anchoring, welding,
finishing, cleaning, applying two coats of zinc chromate red oxide primer and three coats of
approved synthetic enamel paint etc.,complete with lead upto 1 km and all lifts for structural
steel components and all leads and lifts including packing / forwarding charges for
other materials.
DATA:Structural steel hoist bridge for supporting rope drum hoist for operating barrage gates consists
of steel columns and beams with cross beams, ties, bracings, stiffeners, hand railing, ladder,
chequered plate covering, anchorages etc., with all accessories.
The size of the steel hoist bridge depends on the size of the gate and hoist capacity required to
operate the gate. Generally the hoist capacity will be 1.5 times the weight of the gate and the
weight of hoist bridge will be about 400 kg per metre height of column or per metre span of beam.
Consider vertical lift roller gate for 13.72 m x 8.26 m opening for analysis.
For vent opening of 13.72 x 8.26 m the approximate size of gate leaf will be 14.7 x 8.6 m.
Head of water above sill level considered : 8.26 m
101
GATE / HOIST AND ALLIED WORKS
Weight of gate leaf in tonne for vertical lift roller gate based on empirical formula :
2 0.716
= 0.0335 ( L x H x h )
Where ( L ) is length and ( H ) is height of gate and ( h ) is head of water above sill in Rm.
= 0.0335 x( 14.7 x 14.7 x 8.6 x 8.26 ) 0.716 : 33.289
Consider hoist capacity including 25 % reserve @ 1.5 times the weight of gate :
( 1.5 x 33.289 ) : 49.9335
Round off the hoist capacity to next 10 tonne : 50 tonnes
Consider 15 m span and 10 m over all height ( 9 m columns and 1 m beams ) for bridge.
Assessment of weight of structural steel for bridge:
Columns with bracings, anchors, stiffeners etc @ 400 kg / m for 9 m ht : : 3600.00 kg
Beams with cross beams, stiffeners etc @ 400 kg / m for 15 m span : : 6000.00 kg
Total : 9600.00 kg
Other accessories such as railing, chequered plate, ladder etc @ 10 % : 960.00 kg
Total : 10560.00 kg
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of hoist bridge structure for vertical lift barrage gate of
same size provided for one of the barrage.
Actual weight of hoist supporting bridge as per data in Item : 21 of Annexure-2 : 10239.00 kg
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of hoist
bridge structure for vertical lift barrage gate provided for one of the barrage for rate analysis
( for details refer Item : 21 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles / beams / channels with 2.5 % wastage ( 4453 x 1.025 ) : 4564 kg
Plates / flats with 2.5 % wastage ( 5431 x 1.025 ) : 5567 kg
Chequered plate with 2.5 % wastage ( 133 x 1.025 ) : 136 kg
b. MS pipes 32 mm dia ( 30.86 x 1.025 ) : 32 Rm
MS pipes 25 mm dia ( 61.72 x 1.025 ) : 64 Rm
c. Bolt / Nut / Washer
MS bolt / Nut / Washers with 2.5 % wastage ( 18 x 1.025 ) : 18.5 kg
d. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:21 Annexure-2 ) : 4731 Nos
Add for variations / wastage / misc welding @ 10 % ( 4731 x 0.1 ) : 473 Nos
Total requirement of GP / LH electrodes : 5204 Nos
for stitch weld GP electrodes @t 10 % of total ( 5204 x 0.10 ) : 520 Nos
for run welding LH electrodes @ 90 % of total ( 5204 x 0.90 ) : 4684 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 290 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 29 Rm
Total : 319 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas manually : 100 m
Length of steel to be cut by gas using pug cutting machine : 219 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 50 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 73 hours
Acetelyne gas @ 0.6 cum / hour ( 50 + 73 ) x 0.60 : 74 cum
Oxygen gas @ 1.8 cum / hour ( 50 + 73 ) x 1.80 : 222 cum
102
GATE / HOIST AND ALLIED WORKS
3. Welding :
Length of welding as per data sheet : 473 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 520 / 15 ) x 8 / 2 : 139 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 4684 / 15 ) x 8 / 6 : 416 hours
Total : 553 hours
Deploy welding transformer for 553 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 139 x 0.25 + 416 x 0.75 ) : 347 hours
103
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 553.00 13.00 7189.00
Fuel / Energy charges Hour 347.00 86.00 29842.00
2 Pug cutting machine Hour 88.00 18.00 1584.00
Fuel / Energy charges Hour 88.00 4.00 352.00
3 Mobile crane 8 t Hour 12.00 412.00 4944.00
Fuel / Energy charges Hour 12.00 718.00 8616.00
Contd
104
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
4 Stationery derric crane Hour 40.00 73.00 2920.00
Fuel / Energy charges Hour 40.00 15.00 600.00
5 Drilling machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
6 Grinding machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
7 Sundries LS 20.00 45.00 900.00
Total `: 57843.00
Add for small Tools and Plants @ 1% `: 578.43
Add for Contractor's Profit on DPOL / Energy @ 10% `: 4088.60
Add for Contractor's Overheads @ 5% `: 2892.15
Total hire charges of Machinery : `: 65402.18
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 12.00 144.00 1728.00
2 Crew for Drilling machine Hour 8.00 111.00 888.00
3 Crew for Grinding machine Hour 8.00 111.00 888.00
4 Foreman Day 31.00 311.67 9661.62
5 Marker / Fabricator / Erector Day 50.00 289.67 14483.25
6 Gas cutter Day 18.00 289.67 5213.97
7 Welder ( General ) Day 52.00 289.67 15062.58
8 Helper fabrication / erection Day 159.00 274.67 43671.74
9 Helper for cleaning / painting Day 24.00 274.67 6591.96
10 Painter Cl - II Day 51.00 274.67 14007.92
11 Electrician Day 5.00 276.17 1380.83
Total `: 113577.85
Add for small Tools and Plants @ 1% `: 1135.78
Add for Contractor's Profit @ 10% `: 11357.79
Add for hidden cost on Labour @ 15% `: 17036.68
Add for additional hidden cost on labour @ 15% `: 17036.68
Add for Contractor's Overheads @ 5% `: 5678.89
Total cost of Labour : `: 165823.66
ABSTRACT:
A. Cost of Materials `: 734942.41
B. Hire charges of Machinery `: 65402.18
C. Cost of Labour `: 165823.66
TOTAL `: 966168.25
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 14289.76
Add for insurance charges @ 1.00% `: 9661.68
Add for designs and drawings @ 2.50% `: 24154.21
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 24154.21
105
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.22
ITEM: Design, fabrication, supply, erection, testing and commissioning of adequate capacity rope
drum hoist consisting of hoist platform, rope drum, pulleys, gear system, electri c motor,
electro-magnetic brake system, manual operation assembly, position indicator, control panel,
wire rope etc., with all accessories for operating vertical lift roller gates for barrage
including cost of all materials, machinery, labour, cutting, bending, aligning, anchoring, welding,
finishing, cleaning, greasing, applying two coats of zinc chromate red oxide primer and three
coats of approved synthetic enamel paint etc., complete with lead upto 1 km and all lifts for
structural steel components and all leads and lifts including packing / forwarding
charges for other materials.
DATA:Rope drum hoist for vertical lift barrage gate consists of hoist supporting frames, pulley
supports, pulleys, drive stool, rope drums, shafts, couplings, gears and pinions, plummer
blocks, gear box, electric motor, hand operation assembly, brake, wire rope, gate position
indicator, switch box etc. with related accessories.
Consider rope drum hoist for operating barrage gate for clear opening of 13.72 m x 8.26 m.
For vent opening of 13.72 x 8.26 m the approximate size of gate leaf will be 14.7 x 8.6 m.
Head of water above sill level considered : 8.26 m
Generally the capacity of hoist required for barrage gate will be 1.5 times the weight of gate.
Weight of hoist with all accessories is assumed at 0.1 tonne per tonne capacity of hoist as the
hoist is supported on steel bridge and no anchorages and base frames are required.
Weight of gate leaf in tonnes based on empirical formula :
2 0.716
= 0.0335 ( L x H x h )
Where ( L ) is length and ( H ) is height of gate and ( h ) is head of water above sill in Rm.
= 0.0335 ( 14.7 x 14.7 x 8.6 x 8.26 ) 0.716 : 33.289
Consider capacity of hoist including 25 % reserve capacity at 1.5 times the weight of gate :
( 1.50 x 33.289 ) : 49.933 tonnes
Round off the capacity of hoist to next 10 tonne : 50.00 tonne
Consider Weight of hoist with all accessories @ 0.1 t / tonne capacity of hoist :
( 50 x 0.10 ) : 5.00 tonnes
The hoist capacity and hoist weight computed as above based on empirical formulae are further
checked by varifying / computing the actual capacity and weight as per fabrication drawings for
vertical lift barrage gate rope drum hoist of same capacity provided for one of the barrage.
Actual capacity of rope drum hoist as per data sheet : 50.000 tonnes
Actual wt of barrage gate rope drum hoist as per data in Item :22 of Annexure-2 : 5.069 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of rope drum
hoist for vertical lift barrage gate provided for one of the barrage for rate analysis ( for details
106
GATE / HOIST AND ALLIED WORKS
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles / beams / channels / bars with 2.5 % wastage ( 410x1.025 ) : 420.00 kg
Plates / flats with 2.5 % wastage ( 219 x 1.025 ) : 225.00 kg
b. Cast steel components conforming to IS : 1030 :
Rope drums 2 Nos / Gears : 1290.00 kg
Pinions : 98.00 kg
Pulleys 8 Nos / Couplings 2 Nos : 650.00 kg
Plummer blocks / Hubs : 250.00 kg
c. Alloy steel steel components conforming to IS : 1570 :
Shafts / Keys : 350.00 kg
Pins : 96.00 kg
d. Alluminium/ Bronze alloy components conforming to IS : 305 :
Bearings / Bush : 100.00 kg
e. Bolt / Nut / Washers conforming to IS : 1363 :
MS Bolts / Nuts / Washers with 2.5 % wastage ( 25 x 1.025 ) : 26.00 kg
f. Steel wire rope conforming ti IS 2266 :
28 mm dia 6 / 37 construction 1 No 120 Rm @ 2.71 kg / m : 435.00 kg
g. Other components :
Manual operation assembly : 1 No.
Worm reducer ( size 800 ) : 1 No
Electric motor 12.5 hp : 1 No.
Gate position indicator : 1 No.
Ele-magnetic brake : 1 No.
Electric cable / switch / control panel etc : 1 set
h. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:22 Annexure-2 ) : 553 Nos
Add for variations / wastage / misc welding @ 10 % ( 553 x 0.1 ) : 55 Nos
Total requirement of GP / LH electrodes : 608 Nos
for stitch weld GP electrodes @ 10 % of total ( 608 x 0.10 ) : 61 Nos
for run welding LH electrodes @ 90 % of total ( 608 x 0.90 ) : 547 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 37 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 4 Rm
Total : 41 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas manually : 20 m
Length of steel to be cut by gas using pug cutting machine : 21 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 10 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 7 hours
Acetelyne gas @ 0.6 cum / hour ( 10 + 7 ) x 0.60 : 10 cum
Oxygen gas @ 1.8 cum / hour ( 10 + 7 ) x 1.80 : 30 cum
Use of gas cutting torch with 50 min / hr working ( 10 x 60 / 50 ) : 12 hours
Use of pug cutting machine with 50 min / hr working ( 7 x 60 / 50 ) : 9 hours
3. Welding :
Length of welding as per data sheet : 53 Rm
107
GATE / HOIST AND ALLIED WORKS
108
GATE / HOIST AND ALLIED WORKS
b. Workforce for painting 2 coat primer and 3 coats finishing paint consists of 3 Painters Cl-II
at 15 sqm / day and 1 helper to assist painters.
7. Excise duty on supply :
Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
8. Use rate of materials :
Cost of welding set @ `: 6750.00 / Each `: 6750.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) `: 6.75
Cost of gas cutting set @ `: 2250.00 / Each `: 2250.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) `: 3.75
109
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ):
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
23 Use rate gas cutting torch set Hour 12.00 3.75 45.00
24 Sundries LS 1000.00 45.00 45000.00
Total `: 1207811.50
Add for small Tools and Plants @ 1% `: 12078.12
Add for Contractor's Profit @ 10% `: 120781.15
Add for Contractor's Overheads @ 5% `: 60390.58
Total cost of Materials : `: 1401061.34
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 65.00 13.00 845.00
Fuel / Energy charges Hour 41.00 86.00 3526.00
2 Mobile crane 25 t Hour 56.00 4217.00 236152.00
Fuel / Energy charges Hour 28.00 1994.00 55832.00
3 Pug cutting machine Hour 9.00 18.00 162.00
Fuel / Energy charges Hour 9.00 4.00 36.00
4 Mobile crane 8 t Hour 40.00 412.00 16480.00
Fuel / Energy charges Hour 20.00 718.00 14360.00
5 Grinding machine Hour 16.00 20.00 320.00
Fuel / Energy charges Hour 16.00 36.00 576.00
6 Drilling machines Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
7 Sundries LS 600.00 45.00 27000.00
Total `: 355737.00
Add for small Tools and Plants @ 1% `: 3557.37
Add for Contractor's Profit on DPOL / Energy @ 10% `: 10161.80
Add for Contractor's Overheads @ 5% `: 17786.85
Total hire charges of Machinery : `: 387243.02
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane 8 t Hour 40.00 144.00 5760.00
2 Crew for Mobile crane 25 t Hour 56.00 139.00 7784.00
3 Crew for Drilling machine Hour 8.00 111.00 888.00
4 Crew for Grinding machine Hour 16.00 111.00 1776.00
5 Foreman Day 20.00 311.67 6233.30
6 Marker / Fabricator / Erector Day 35.00 289.67 10138.28
7 Gas cutter Day 3.00 289.67 869.00
8 Welder ( General ) Day 6.00 289.67 1737.99
9 Khalasi Day 90.00 276.17 24854.85
10 Helper fabrication / erection Day 78.00 274.67 21423.87
11 Helper for cleaning / painting Day 2.00 274.67 549.33
Contd
110
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
12 Painter Cl - II Day 3.00 274.67 824.00
13 Electrician Day 3.00 276.17 828.50
Total `: 83667.10
Add for small Tools and Plants @ 1% `: 836.67
Add for Contractor's Profit @ 10% `: 8366.71
Add for hidden cost on Labour @ 15% `: 12550.07
Add for additional hidden cost on labour @ 15% `: 12550.07
Add for Contractor's Overheads @ 5% `: 4183.36
Total cost of Labour : `: 122153.97
ABSTRACT:
A. Cost of Materials `: 1401061.34
B. Hire charges of Machinery `: 387243.02
C. Cost of Labour `: 122153.97
TOTAL `: 1910458.33
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 31480.73
Add for insurance charges @ 1.00% `: 19104.58
Add for designs and drawings @ 2.50% `: 47761.46
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 47761.46
Add for power supply arrangements @ 2.00% `: 38209.17
Add for enabling works @ 1.50% `: 28656.87
Total `: 2123432.60
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 5.069 tonnes @ `: 247.10 / tonne `: 2505.10
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 21 ) @ 3.00% `: 34062.47
Total cost for 5.069 tonne weight `: 2160000.17
50.000 tonne capacity
Rate per tonne weight `: 426120.00
Rate per tonne capacity `: 43200.00
Rate approved per tonne capacity `: 43200.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.23
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts consisting of sill
beam, wall plates, seal seats, first stage anchors, anchor girders, anchor bars,trunnion supports
etc., with all accessories for outflow regulating automatic gates for barrage / escape
including cost of all materials, machinery, labour, cutting, aligning, anchoring, welding, finishing,
cleaning,applying one coat of zinc rich epoxy primer and four coats of cold applied coal tar
epoxy paint etc., complete as per specifications and approved drawings with lead upto 1 km
and all lifts for structural steel components and all leads and lifts including packing /
forwarding charges for other materials.
DATA:Embedded parts for automatic outflow regulating gate consist of sill beam / wall plates / anchor /
girders / anchor bars trunnion supports etc., with all accessories. The weight of embedded parts
111
GATE / HOIST AND ALLIED WORKS
for automatic gate will be about 35 to 40 percent of weight of gate leaf with fulcrum assembly.
Consider embedded parts for automatic outflow regulating gate for barrage opening of size
8.0 m x 3.5 m.
Size of gate : 8.00 m x 3.50 m Head of water : 3.50 m
Weight of automatic outflow regulating gate with fulcrum assembly in tonne for the opening
2 0.673
based on empirical formula = 0.1325 x ( L x H x h )
Consider Weight of embedded parts in tonne @ av. 55 % of weight of gate :
= 0.375 x 0.1325 x ( L 2 x H x h ) 0.673
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.673
= 0.049 x ( 8 x 8 x 3.5 x 3.3 ) : 4.177
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of embedded parts for barrage outflow regulating radial
gate of same size furnished by the designer.
Actual weight of embedded parts : 3.910 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of embedded
parts for automatic outflow regulating gate as provided by the designer. ( for details refer
Item : 23 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming ti IS : 2062 :
Total weight of structural steel excluding wastage : 3800 kg
Weight of Angles / Channels / Beams @ 20 % : 760 kg
Weight of Plates / Flats @ 80 % : 3040 kg
Angles / beams / channels / bars with 2.5 % wastage ( 760x1.025 ) : 779 kg
Plates / flats with 2.5 % wastage ( 3040 x 1.025 ) : 3116 kg
b. Alloy steel conforming to IS : 1570 :
Stainless steel plates / flats AISI 410 ( 49 x 1.025 ) say: 50.00 kg
Stainless steel plates / flats AISI 304L ( 62 x 1.025 ) say: 64.00 kg
c. Bolt / Nut / Washer conforming to IS : 1363 :
MS bolts and nuts with 2.5 % wastage ( 129 x 1.025 ) : 132 kg
d. Welding electrodes ( General purpose / Low hydrogen / Stainless steel ) :
GP / LH electrodes as per data sheet ( Item:23 Annexure-2 ) : 133 Nos
Add for variations / wastage / misc welding @ 10 % ( 133 x 0.1 ) : 14 Nos
Total requirement of GP / LH electrodes : 147 Nos
for stitch welding GP electrodes @t 10 % of total ( 147 x 0.10 ) : 15 Nos
for run welding LH electrodes @ 90 % of total ( 147 x 0.90 ) : 132 Nos
Stainless steel electrodes as per data sheet ( Item:23 Annexure-2 ) : 987 Nos
Add for variations / wastage @ 5 % ( 987 x 0.05 ) : 49 Nos
Total requirement of Stainless steel ( SS ) electrodes : 1036 Nos
for stitch weld SS electrodes @t 10 % of total ( 1036 x 0.10 ) : 104 Nos
for run weld SS electrodes @t 90 % of total ( 1036 x 0.90 ) : 932 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 168.00 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 17.00 Rm
Total : 185.00 Rm
For cutting structural steel sections to required sizes plate shearing machine and gas cutting is
assumed.
Length of steel to be cut by using plate shearing machine : 30 m
112
GATE / HOIST AND ALLIED WORKS
3. Welding :
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 15 + 104 ) x 8 / 15 / 2 : 32 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 932 + 132 ) x 8 / 15 / 6 : 95 hours
Total : 127 hours
Deploy welding transformer for 127 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 32 x 0.25 + 95 x 0.75 ) : 80 hours
4. Planing SS plates for seal seats :
For surface finishing of SS plates for seal tracks planing machine is considered.
Length of SS plate for surface finishing by planing machine : 47 Rm
Length of planing at a time for 4 m stroke planing machine : 3 Rm
Time for planing 3 m length section with 50 min / hour working : 8 hours
Time for planing 47 m SS plates ( 47 x 8 / 3 ) : 126 hours
5. Surface cleaning and painting :
Painting area for embedded parts at 10 sqm / tonne ( 3.9 x 10 ) : 40 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 40 sqm @ 9 sqm / ltr / coat : 5 ltr
4 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 40 sqm @ 6 sqm / ltr / coat : 27 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 40 sqm @ 8 sqm / ltr : 5 ltr
6. Requirement of other machinery :
For drilling holes for anchor bolts 16 hours use of drilling machine considered.
For finishing weld joints / edges 12 hours use of grinding machine considered.
For handling of parts during fabrication and erection use of 8 t mobile crane for 18 hours and
stationery derric crane for 56 hours considered.
7. Requirement of work force :
Work component Foreman Marker / Gas cutter / Helper /
Fabricator / Welder Painter Cl-II
Erector /
Cutting sections 68 hours 4 8 8 24
Drilling holes for anchors / supports --- 2 --- 4
Fabricating by stitch welding 32 hours 4 8 --- 24
Run welding 95 hours 6 --- 12 12
Erection of Anchor girders / anchor bars 2 4 --- 12
Contd
113
GATE / HOIST AND ALLIED WORKS
114
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ):
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
13 Use rate welding holder set Hour 127.00 6.75 857.25
14 Use rate gas cutting torch set Hour 23.00 3.75 86.25
15 Sundries LS 70.00 45.00 3150.00
Total `: 320032.25
Add for small Tools and Plants @ 1% `: 3200.32
Add for Contractor's Profit @ 10% `: 32003.23
Add for Contractor's Overheads @ 5% `: 16001.61
Total cost of Materials : `: 371237.41
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 127.00 13.00 1651.00
Fuel / Energy charges Hour 80.00 86.00 6880.00
2 Plate shearing machine Hour 3.00 68.00 204.00
Fuel / Energy charges Hour 3.00 143.00 429.00
3 Pug cutting machine Hour 45.00 18.00 810.00
Fuel / Energy charges Hour 45.00 4.00 180.00
4 Planing machine Hour 126.00 97.00 12222.00
Fuel / Energy charges Hour 126.00 107.00 13482.00
5 Mobile crane 8 t Hour 18.00 412.00 7416.00
Fuel / Energy charges Hour 18.00 718.00 12924.00
6 Stationery derric crane Hour 56.00 73.00 4088.00
Fuel / Energy charges Hour 56.00 15.00 840.00
7 Grinding machine Hour 16.00 20.00 320.00
Fuel / Energy charges Hour 16.00 36.00 576.00
8 Drilling machines Hour 12.00 20.00 240.00
Fuel / Energy charges Hour 12.00 36.00 432.00
9 Sundries LS 70.00 45.00 3150.00
Total `: 65844.00
Add for small Tools and Plants @ 1% `: 658.44
Add for Contractor's Profit on DPOL / Energy @ 10% `: 3889.30
Add for Contractor's Overheads @ 5% `: 3292.20
Total hire charges of Machinery : `: 73683.94
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 18.00 144.00 2592.00
2 Crew for plate shearing machine Hour 3.00 87.00 261.00
3 Crew for Planing machine Hour 127.00 139.00 17653.00
4 Crew for Drilling machine Hour 12.00 111.00 1332.00
5 Crew for Grinding machine Hour 16.00 111.00 1776.00
6 Foreman Day 22.00 311.67 6856.63
7 Marker / Fabricator / Erector Day 30.00 289.67 8689.95
Contd
115
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
8 Gas cutter Day 8.00 289.67 2317.32
9 Welder ( General ) Day 10.00 289.67 2896.65
10 Welder ( X - ray ) Day 2.00 318.63 637.26
11 Helper fabrication / erection Day 94.00 274.67 25818.51
12 Helper for cleaning / painting Day 5.00 274.67 1373.33
13 Painter Cl - II Day 13.00 274.67 3570.65
14 Electrician Day 2.00 276.17 552.33
Total `: 76326.62
Add for small Tools and Plants @ 1% `: 763.27
Add for Contractor's Profit @ 10% `: 7632.66
Add for hidden cost on Labour @ 15% `: 11448.99
Add for additional hidden cost on labour @ 15% `: 11448.99
Add for Contractor's Overheads @ 5% `: 3816.33
Total cost of Labour : `: 111436.87
ABSTRACT:
A. Cost of Materials `: 371237.41
B. Hire charges of Machinery `: 73683.94
C. Cost of Labour `: 111436.87
TOTAL `: 556358.22
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 11440.47
Add for insurance charges @ 1.00% `: 5563.58
Add for patent royalty charges @ 4.40% `: 24479.76
Add for designs and drawings @ 2.50% `: 13908.96
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 13908.96
Add for power supply arrangements @ 2.00% `: 11127.16
Add for enabling works @ 1.50% `: 8345.37
Total `: 645132.48
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 3.910 tonnes @ `: 247.10 / tonne `: 1932.32
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 12 ) @ 3.00% `: 4576.31
Total cost for 3.910 tonne `: 651641.11
Rate per tonne `: 166660.13
Rate approved per tonne `: 166700.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.24
ITEM: Design, fabrication, supply, erection, testing and commissioning of automatic outflow
regulating gate and fulcrum assembly consisting of skin plate, stiffeners, horizontal girders,
trunnion assemblies, gate bracket, base plate, rolling surface assembly, link brackets, link
assembly, rubber seals, seal clamps etc., with all accessories for barrage including cost of all
materials, machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning, applying
one coat of zinc rich epoxy primer and three coats of cold applied coal tar epoxy paint, seal
fixing etc., complete as per specifications and approved drawings with lead upto 1 km and
116
GATE / HOIST AND ALLIED WORKS
all lifts for structural steel components and all leads and lifts including packing /
forwarding charges for other materials.
DATA:Automatic outflow regulating gate and fulcrum assembly consisting of skin plate, stiffeners,
horizontal girders, trunnion assemblies, gate bracket, base plate, rolling surface assembly, link ,
brackets, link assembly rubber seals, seal clamps etc., with all accessories.
Consider automatic outflow regulating gate for barrage opening of size 8 m x 3.5 m for analysis.
Size of gate : 8.00 m x 3.50 m Head of water : 3.30 m
Weight of automatic gate leaf in tonnes based on empirical formula :
2 0.673
= 0.1325 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.673
= 0.1325 x ( 8 x 8 x 3.5 x 3.3 ) : 11.295
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of automatic outflow regulating gate of same size
furnished by the designer for one of the gate.
Actual weight of radial gate leaf as per data in Item :24 of Annexure-2 : : 11.270 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of canal
regulator radial gate provided for one of the canal regulator for rate analysis ( for details refer
Item : 24 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel :
Angles / beams / channels / bars with 2.5 % wastage ( 3122x1.025 ) : 3200 kg
Plates / flats with 2.5 % wastage ( 7561x1.025 ) : 7750 kg
b. Alloy steel components :
Pins / Axles : 74 kg
Stainless plate / flats AISI 410 ( 49x1.025 ) : 50 kg
c. Cast steel components :
Trunnion hub / Guide roller : 443 kg
d. Alluminium / Bronze alloy components :
Trunnion / Guide roller bush : 33 kg
e. Bolts / Nuts / Washers :
Stainless steel bolts /nuts /washers with 2.5 % wastage ( 31 x 1.025 ) : 32 kg
MS bolts / nuts / washers with 2.5 % wastage ( 23.5x1.025 ) : 24 kg
f. Rubber seal :
Bottom seal ( flat type ) ( 8 x 1.025 ) : 8.5 Rm
Side seals ( Z - type ) (2 x 4 x 1.025 ) : 8.5 Rm
g. Welding electrodes ( Ordinary / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:24 Annexure-2 ) : 6125 Nos
Add for variations / wastage / misc welding @ 10 % ( 6125 x 0.1 ) : 613 Nos
Total requirement of GP / LH electrodes : 6738 Nos
for stitch weld GP electrodes @t 10 % of total (6738 x 0.10 ) : 674 Nos
for run welding LH electrodes @ 90 % of total (6738 x 0.90 ) : 6064 Nos
h. Welding electrodes ( Stainless steel ) :
SS electrodes as per data sheet ( Item:24 Annexure-2 ) : 150 Nos
Add for variations / wastage / misc welding @ 10 % ( 6900 x 0.1 ) : 15 Nos
Total requirement of SS electrodes : 165 Nos
for stitch weld SS electrodes @t 10 % of total (165 x 0.10 ) : 15 Nos
for run welding SS electrodes @ 90 % of total (165 x 0.90 ) : 160 Nos
117
GATE / HOIST AND ALLIED WORKS
2. Cutting :
Total length of cutting assuming cutting for 2 sides : 195 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 20 Rm
Total : 215 Rm
For cutting structural steel sections to required sizes use of plate shearing machine and gas
cutting is assumed.
Length of steel to be cut by using plate shearing machine 40 m
Length of steel to be cut by using gas manually : 62 m
Length of steel to be cut by gas using pug cutting machine : 113 m
Time for cutting by plate shearing machine at ( av ) 10 m cutting / hour : 4 hours
Time for gas cutting manually at ( av ) 2 m cutting / hour : 31 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 38 hours
Acetelyne gas @ 0.6 cum / hour ( 31 + 38 ) x 0.60 : 42 cum
Oxygen gas @ 1.8 cum / hour ( 31 + 38 ) x 1.80 : 126 cum
Use of gas cutting torch with 50 min / hr working ( 31 x 60 / 50 ) : 37 hours
Use of pug cutting machine with 50 min / hr working ( 38 x 60 / 50 ) : 46 hours
4. Welding :
Length of welding : 196 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 674 + 15 ) x 8 / ( 15 x 2 ) : 184 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 6064 + 160 ) x 8 / ( 15 x 6 ) : 553 hours
Total : 737 hours
Deploy welding transformer for 737 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 184 x 0.25 + 553 x 0.75 ) : 461 hours
5. Planing SS plates for seal seats :
For surface finishing of SS plates planing machine is considered.
Length of SS plate for surface finishing by planing machine : 3 Rm
Length of planing at a time for 4 m stroke planing machine : 3 Rm
Time for planing 3 m length section with 50 min / hour working : 8 hours
Time for planing 3 m SS plates (3x8/3) : 8 hours
6. Surface cleaning and painting :
Painting area for gate at 20 sqm / tonne ( 11.27 x 20 ) : 225 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 225 sqm @ 9 sqm / ltr / coat : 25 ltr
3 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 225 sqm @ 6 sqm / ltr / coat : 112 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 225 sqm @ 8 sqm / ltr : 28 ltr
118
GATE / HOIST AND ALLIED WORKS
Contd
119
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
5 Bolt / Nut / Washer :
Stainless steel bolts / nuts / washers kg 32.00 224.00 7168.00
MS bolts / nuts / washers kg 24.00 96.00 2304.00
6 Rubber seals :
Bottom seal Rm 8.50 233.00 1980.50
Side seals ( Z - type ) Rm 8.50 442.00 3757.00
8 Oxygen gas cum 126.00 78.00 9828.00
9 Acetyline gas cum 42.00 404.00 16968.00
10 Welding electrodes ( general purpose ) Nos 674.00 11.00 7414.00
11 Welding electrodes ( low hydrogen ) Nos 6064.00 21.00 127344.00
12 Welding electrodes ( stainless steel ) Nos 165.00 66.00 10890.00
13 Zinc rich epoxy primer ltr 25.00 756.00 18900.00
14 Coal tar epoxy paint ltr 112.00 256.50 28728.00
15 Rust cleaner / inhibitor ltr 28.00 326.00 9128.00
16 Wire brush Nos 5.00 54.00 270.00
17 Use rate welding holder set Hour 737.00 6.75 4974.75
18 Use rate gas cutting torch set Hour 37.00 3.75 138.75
19 Sundries LS 100.00 45.00 4500.00
Total `: 854355.50
Add for small Tools and Plants @ 1% `: 8543.56
Add for Contractor's Profit @ 10% `: 85435.55
Add for Contractor's Overheads @ 5% `: 42717.78
Total cost of Materials : `: 991052.38
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 737.00 13.00 9581.00
Fuel / Energy charges Hour 461.00 86.00 39646.00
2 Plate shearing machine Hour 4.00 68.00 272.00
Fuel / Energy charges Hour 4.00 143.00 572.00
3 Pug cutting machine Hour 46.00 18.00 828.00
Fuel / Energy charges Hour 46.00 4.00 184.00
5 Planing machine Hour 8.00 97.00 776.00
Fuel / Energy charges Hour 8.00 107.00 856.00
7 Mobile crane ( revolving ) 8 t Hour 16.00 412.00 6592.00
Fuel / Energy charges Hour 16.00 718.00 11488.00
8 Stationery derric crane Hour 50.00 73.00 3650.00
Fuel / Energy charges Hour 50.00 15.00 750.00
9 Grinding machine Hour 32.00 20.00 640.00
Fuel / Energy charges Hour 32.00 36.00 1152.00
10 Drilling machines Hour 16.00 20.00 320.00
Fuel / Energy charges Hour 16.00 36.00 576.00
11 Sundries LS 100.00 45.00 4500.00
Total `: 82383.00
Contd
120
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
Add for small Tools and Plants @ 1% `: 823.83
Add for Contractor's Profit on DPOL / Energy @ 10% `: 5972.40
Add for Contractor's Overheads @ 5% `: 4119.15
Total hire charges of Machinery : `: 93298.38
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane 8 t Hour 16.00 144.00 2304.00
2 Crew for plate shearing machine Hour 4.00 87.00 348.00
3 Crew for planing machine Hour 8.00 139.00 1112.00
4 Crew for Drilling machine Hour 16.00 111.00 1776.00
5 Crew for Grinding machine Hour 32.00 111.00 3552.00
6 Foreman Day 29.00 311.67 9038.29
7 Marker / Fabricator / Erector Day 44.00 289.67 12745.26
8 Gas cutter Day 9.00 289.67 2606.99
9 Welder ( General ) Day 62.00 289.67 17959.23
10 Welder ( X - ray ) Day 7.00 318.63 2230.42
11 Khalasi Day 34.00 276.17 9389.61
12 Helper fabrication / erection Day 162.00 274.67 44495.73
13 Helper for cleaning / painting Day 21.00 274.67 5767.97
14 Painter Cl - II Day 60.00 274.67 16479.90
15 Electrician Day 3.00 276.17 828.50
Total `: 130633.88
Add for small Tools and Plants @ 1% `: 1306.34
Add for Contractor's Profit @ 10% `: 13063.39
Add for hidden cost on Labour @ 15% `: 19595.08
Add for additional hidden cost on labour @ 15% `: 19595.08
Add for Contractor's Overheads @ 5% `: 6531.69
Total cost of Labour : `: 190725.47
ABSTRACT:
A. Cost of Materials `: 991052.38
B. Hire charges of Machinery `: 93298.38
C. Cost of Labour `: 190725.47
TOTAL `: 1275076.23
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 17552.67
Add for insurance charges @ 1.00% `: 12750.76
Add for Patent royalty charges @ 4.40% `: 56103.35
Add for designs and drawings @ 2.50% `: 31876.91
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 31876.91
Add for power supply arrangements @ 2.00% `: 25501.52
Add for enabling works @ 1.50% `: 19126.14
Total `: 1469864.49
121
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.25
ITEM: Design, fabrication, supply, erection, testing and commissioning of hoisting cum damping
system consisting of low level horizontal lever link, low level long actuating lever, high level
vertical lever link, high level short actuating lever, high level hoisting bracket, axle for lever
system, friction shoes, supporting box for shoes, track assembly, ratchet pawl, supporting
structure, bracket plate etc., with all accessories for outflow regulating automatic gate
including cost of all materials, machinery, labour, cutting, aligning, anchoring, welding, finishing,
cleaning, applying one coat of zinc rich epoxy primer and three coats of cold applied coal tar
epoxy paint, etc., complete as per specifications and approved drawings with lead upto 1 km
and all lifts for structural steel components and all leads and lifts including packing /
forwarding charges for other materials.
DATA:Hoisting cum damping system for automatic outflow regulating gate consists of low level
horizontal lever link, low level long actuating lever, high level vertical lever link, high level short
actuating lever, high level hoisting bracket, axles for lever system, friction shoes, track assembly,
support box for shoes, ratchet pawl, support structure, bracket plate etc.
Consider hoisting cum damping system for automatic outflow regulating gate of size 8 x 3.50 m
for analysis.
Weight of the hoisting cum damping system will be about 50 to 55 percent of the weight of the
automatic outflow regulating gate.
Consider automatic outflow regulating gate for barrage opening of size 8 m x 3.5 m for analysis.
Size of gate : 8.00 m x 3.50 m Head of water : 3.30 m
Weight of automatic gate leaf in tonnes based on empirical formula :
= 0.1325 x ( L 2 x H x h ) 0.673
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.673
= 0.1325 x ( 8 x 8 x 3.5 x 3.3 ) : 11.295
Weight of hoisting cum damping system = 0.525 x 11.295 : 5.93 tonnes
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings.
Actual weight of radial gate leaf as per data in Item :25 of Annexure-2 : : 5.81 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of hoistingl
cum damping system as furnished by the designer for one of the automatic outflow regulating
gate of size 8.0 x 3.5 m for rate analysis ( for details referItem : 25 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel :
Angles / beams / channels / bars with 2.5 % wastage ( 1483x1.025 ) : 1520 kg
Plates / flats with 2.5 % wastage ( 3622x1.025 ) : 3712 kg
b. Alloy steel components :
Stainless steel plates / flats : 435 kg
Axles / Pins : 59 kg
122
GATE / HOIST AND ALLIED WORKS
123
GATE / HOIST AND ALLIED WORKS
Quantity of primer paint for 105 sqm @ 9 sqm / ltr / coat : 12 ltr
3 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 105 sqm @ 6 sqm / ltr / coat : 52 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 105 sqm @ 8 sqm / ltr : 13 ltr
124
GATE / HOIST AND ALLIED WORKS
B. MACHINERY :
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 380.00 13.00 4940.00
Fuel / Energy charges Hour 238.00 86.00 20468.00
2 Plate shearing machine Hour 2.00 68.00 136.00
Fuel / Energy charges Hour 2.00 143.00 286.00
3 Pug cutting machine Hour 33.00 18.00 594.00
Fuel / Energy charges Hour 33.00 4.00 132.00
4 Planing machine Hour 4.00 97.00 388.00
Fuel / Energy charges Hour 4.00 107.00 428.00
Contd
125
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
5 Mobile crane ( pick & carry ) 8 t Hour 16.00 412.00 6592.00
Fuel / Energy charges Hour 16.00 718.00 11488.00
6 Stationery derric crane Hour 50.00 73.00 3650.00
Fuel / Energy charges Hour 50.00 15.00 750.00
7 Grinding machine Hour 16.00 20.00 320.00
Fuel / Energy charges Hour 16.00 36.00 576.00
8 Drilling machines Hour 16.00 20.00 320.00
Fuel / Energy charges Hour 16.00 36.00 576.00
9 Sundries LS 75.00 45.00 3375.00
Total `: 55019.00
Add for small Tools and Plants @ 1% `: 550.19
Add for Contractor's Profit on DPOL / Energy @ 10% `: 3807.90
Add for Contractor's Overheads @ 5% `: 2750.95
Total hire charges of Machinery : `: 62128.04
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane 8 t Hour 16.00 144.00 2304.00
2 Crew for plate shearing machine Hour 2.00 87.00 174.00
3 Crew for planing machine Hour 4.00 139.00 556.00
4 Crew for Drilling machine Hour 16.00 111.00 1776.00
5 Crew for Grinding machine Hour 16.00 111.00 1776.00
6 Foreman Day 15.00 311.67 4674.98
7 Marker / Fabricator / Erector Day 27.00 289.67 7820.96
8 Gas cutter Day 7.00 289.67 2027.66
9 Welder ( General ) Day 33.00 289.67 9558.95
10 Welder ( X - ray ) Day 3.00 318.63 955.89
11 Khalasi Day 18.00 276.17 4970.97
12 Helper fabrication / erection Day 84.00 274.67 23071.86
13 Helper for cleaning / painting Day 12.00 274.67 3295.98
14 Painter Cl - II Day 28.00 274.67 7690.62
15 Electrician Day 2.00 276.17 552.33
Total `: 71206.18
Add for small Tools and Plants @ 1% `: 712.06
Add for Contractor's Profit @ 10% `: 7120.62
Add for hidden cost on Labour @ 15% `: 10680.93
Add for additional hidden cost on labour @ 15% `: 10680.93
Add for Contractor's Overheads @ 5% `: 3560.31
Total cost of Labour : `: 103961.03
ABSTRACT:
A. Cost of Materials `: 761906.39
B. Hire charges of Machinery `: 62128.04
C. Cost of Labour `: 103961.03
TOTAL `: 927995.46
126
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.26
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts consisting of sill
beam, wall plates, first stage anchors, anchor girders, anchor bars, trunnion supports,wire rope/
pulley supports etc., with all accessories for canal regulator radial gates including cost
of all materials, machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning,
applying one coat of zinc rich epoxy primer and four coats of cold applied coal tar epoxy
paint etc., complete as per specifications and approved drawings with lead upto 1 km
and all lifts for structural steel components and all leads and lifts including packing /
forwarding charges for othermaterials.
DATA:Embedded parts for radial gate consist of sill beam / wall plates / anchor girders / anchor bars /
trunnion supports etc., with all accessories. The weight of embedded parts for small radial gate
will be generally at about 50 to 60 percent of weight of radial gate leaf.
Consider embedded parts for radial gate for canal cross regulator opening of size 3 m x 3.7 m.
Size of radial gate : 3.00 m x 3.90 m Head of water : 3.70 m
Weight of radial gate in tonne for canal regulator opening based on empirical formula :
2 0.673
= 0.1690 x ( L x H x h )
Consider Weight of embedded parts in tonne @ av. 55 % of weight of gate :
= 0.55 x 0.1690 x ( L 2 x H x h ) 0.673
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.673
= 0.0929 x ( 3 x 3 x 3.9 x 3.7 ) : 2.457
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of embedded parts for canal regulator radial gate of
same size provided for one of the canal regulator.
Actual weight of embedded parts as per data in Item :26 of Annexure-2 : : 2.404 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of embedded
parts for canal regulator radial gate provided for one of the canal regulator for rate analysis ( for
details refer Item : 26 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming ti IS : 2062 :
Angles / beams / channels / bars with 2.5 % wastage ( 812x1.025 ) : 832 kg
127
GATE / HOIST AND ALLIED WORKS
128
GATE / HOIST AND ALLIED WORKS
Quantity of coal tar epoxy paint for 12 sqm @ 6 sqm / ltr / coat : 8 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 12 sqm @ 8 sqm / ltr : 1.5 ltr
6. Requirement of other machinery :
For drilling holes for anchor bolts 8 hours use of drilling machine considered.
For finishing weld joints / edges 8 hours use of grinding machine considered.
For handling of parts during fabrication and erection use of mobile crane for 2 hours and
stationery derric crane for 8 hours considered.
7. Requirement of work force :
Work component Foreman Marker / Gas cutter / Helper /
Fabricator / Welder Painter Cl-II
Erector /
Cutting sections 50 hours 3 6 6 12
Drilling holes for anchors / supports --- 1 --- 1
Fabricating by stitch welding 43 hours 2 5 --- 10
Run welding 127 hours 1 --- 16 16
Erection of Anchor girders / anchor bars 2 4 --- 8
Erection of first stage anchors --- 2 --- 2
Erection of Sill beam / Wall plates 1 2 --- 2
Cleaning surface 12 sqm @ 15 sqm/day --- --- --- 1
Painting ( 5 x 12 ) sqm @ 15 sqm / day --- --- --- 5
Finishing / Checking 1 1 --- 1
Total : 10 21 22 58
Note : a. It is assumed that all stitch welding will be done by fabricator. Hence, no separate provision
considered for welder for stitch welding.
b. Workforce for painting 1 coat primer and 4 coats finishing paint consists of 4 Painters Cl-II
at 15 sqm / day and 1 helper to assist painters.
For surface finishing of stainless steel plates for seal seats planing machine is considered.
8. Excise duty on supply :
Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
9. Use rate of materials :
Cost of welding set @ `: 6750.00 / Each `: 6750.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) `: 6.75
Cost of gas cutting set @ `: 2250.00 / Each `: 2250.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) `: 3.75
129
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
2 Stainless steel plates / flats kg 53.00 189.50 10043.50
3 MS bolts and nuts kg 67.00 96.00 6432.00
4 Oxygen gas cum 75.00 78.00 5850.00
5 Acetyline gas cum 25.00 404.00 10100.00
6 Welding electrodes ( general purpose ) Nos 140.00 11.00 1540.00
7 Welding electrodes ( low hydrogen ) Nos 1259.00 21.00 26439.00
8 Welding electrodes ( stainless steel ) Nos 195.00 66.00 12870.00
9 Zinc rich epoxy primer ltr 1.50 756.00 1134.00
10 Coal tar epoxy paint ltr 8.00 256.50 2052.00
11 Rust cleaner / inhibitor ltr 1.50 326.00 489.00
12 Wire brush Nos 2.00 54.00 108.00
13 Use rate welding holder set Hour 170.00 6.75 1147.50
14 Use rate gas cutting torch set Hour 24.00 3.75 90.00
15 Sundries LS 15.00 45.00 675.00
Total `: 177119.20
Add for small Tools and Plants @ 1% `: 1771.19
Add for Contractor's Profit @ 10% `: 17711.92
Add for Contractor's Overheads @ 5% `: 8855.96
Total cost of Materials : `: 205458.27
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 170.00 13.00 2210.00
Fuel / Energy charges Hour 106.00 86.00 9116.00
2 Pug cutting machine Hour 26.00 18.00 468.00
Fuel / Energy charges Hour 26.00 4.00 104.00
3 Planing machine Hour 36.00 97.00 3492.00
Fuel / Energy charges Hour 36.00 107.00 3852.00
4 Mobile crane 8 t Hour 2.00 412.00 824.00
Fuel / Energy charges Hour 2.00 718.00 1436.00
5 Stationery derric crane Hour 8.00 73.00 584.00
Fuel / Energy charges Hour 8.00 15.00 120.00
6 Grinding machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
7 Drilling machines Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
8 Sundries LS 12.00 45.00 540.00
Total `: 23642.00
Add for small Tools and Plants @ 1% `: 236.42
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1574.40
Add for Contractor's Overheads @ 5% `: 1182.10
Total hire charges of Machinery : `: 26634.92
130
GATE / HOIST AND ALLIED WORKS
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 2.00 144.00 288.00
2 Crew for Planing machine Hour 36.00 139.00 5004.00
3 Crew for Drilling machine Hour 8.00 111.00 888.00
4 Crew for Grinding machine Hour 8.00 111.00 888.00
5 Foreman Day 10.00 311.67 3116.65
6 Marker / Fabricator / Erector Day 21.00 289.67 6082.97
7 Gas cutter Day 6.00 289.67 1737.99
8 Welder ( General ) Day 14.00 289.67 4055.31
9 Welder ( X - ray ) Day 2.00 318.63 637.26
10 Helper fabrication / erection Day 52.00 274.67 14282.58
11 Helper for cleaning / painting Day 2.00 274.67 549.33
12 Painter Cl - II Day 4.00 274.67 1098.66
13 Electrician Day 1.00 276.17 276.17
Total `: 38904.91
Add for small Tools and Plants @ 1% `: 389.05
Add for Contractor's Profit @ 10% `: 3890.49
Add for hidden cost on Labour @ 15% `: 5835.74
Add for additional hidden cost on labour @ 15% `: 5835.74
Add for Contractor's Overheads @ 5% `: 1945.25
Total cost of Labour : `: 56801.17
ABSTRACT:
A. Cost of Materials `: 205458.27
B. Hire charges of Machinery `: 26634.92
C. Cost of Labour `: 56801.17
TOTAL `: 288894.36
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 5156.35
Add for insurance charges @ 1.00% `: 2888.94
Add for designs and drawings @ 2.50% `: 7222.36
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 7222.36
Add for power supply arrangements @ 2.00% `: 5777.89
Add for enabling works @ 1.50% `: 4333.42
Total `: 321495.68
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 2.404 tonnes @ `: 247.10 / tonne `: 1188.06
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 12 ) @ 3.00% `: 2311.73
Total cost for 2.404 tonne `: 324995.46
Rate per tonne `: 135189.46
Rate approved per tonne `: 135200.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.27
ITEM: Design, fabrication, supply, erection, testing and commissioning of radial gate consisting
of skin plate, stiffeners, horizontal girders, sector arms, trunnion assemblies, tie beam, pulley
supports, bracings, rubber seals, seal clamps etc., with all accessories for canal regulator
131
GATE / HOIST AND ALLIED WORKS
including cost of all materials, machinery, labour, cutting, bending, aligning, anchoring, welding,
finishing, cleaning, applying one coat of zinc rich epoxy primer and three coats of cold applied
coal tar epoxy paint, seal fixing etc., complete as per specifications and approved drawings
with lead upto 1 km and all lifts for structural steel components and all leads and lifts
including packing / forwarding charges for other materials.
DATA:Regulator radial gate consists of trunnions / sector arms / horizontal girders / Tee- supports /
skin plate / tie beam / bracings for horizontal girders and sector arms / pulley blocks / seals
with all accessories.
Sector arms are connected to trunions by bolts and nuts.
Horizontal girders generally spaced at about 3 m apart are joined to sector arms by welding and
are stiffened by vertical and diagonal stiffeners to form the main frame. Tee- sections are welded
to horizontal girders to make the frame regid and to support the skin plate. Skin plate is welded
to Tee-supports generally spaced vertically at about 40 cm apart.
Consider radial gate for canal cross regulator opening of size 3 m x 3.7 m for analysis.
Size of radial gate : 3.00 m x 3.90 m Head of water : 3.70 m
Weight of regulator radial gate leaf in tonnes based on empirical formula :
= 0.1690 x ( L 2 x H x h ) 0.673
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.673
= 0.1690 x ( 3 x 3 x 3.9 x 3.7 ) : 4.470
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of canal regulator radial gate of same size provided
for one of the canal regulator.
Actual weight of radial gate leaf as per data in Item :27 of Annexure-2 : : 4.455 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of canal
regulator radial gate provided for one of the canal regulator for rate analysis ( for details refer
Item : 27 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel :
Angles / beams / channels / bars with 2.5 % wastage ( 2116x1.025 ) : 2215 kg
Plates / flats with 2.5 % wastage ( 2042 x 1.025 ) : 2093 kg
b. Alloy steel components :
Pins : 41 kg
c. Cast steel components :
Trunnion hub / Guide roller : 122 kg
d. Alluminium / Bronze alloy components :
Trunnion / Guide roller bush : 19 kg
e. Bolts / Nuts / Washers :
GI bolts / nuts / washers with 2.5 % wastage ( 16 x 1.025 ) : 16.5 kg
MS bolts / nuts / washers with 2.5 % wastage ( 54 x 1.025 ) : 55 kg
f. Zinc at 20 kg / trunnion ( 2 x 20 ) : 40 kg
g. Rubber seal :
Bottom seal ( flat type ) ( 3 x 1.025 ) : 3.1 Rm
Side seals ( Z - type ) ( 10 x 1.025 ) : 10.2 Rm
h. Welding electrodes ( Ordinary / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:24 Annexure-2 ) : 1955 Nos
Add for variations / wastage / misc welding @ 10 % ( 1369 x 0.1 ) : 195 Nos
Total requirement of GP / LH electrodes : 2150 Nos
for stitch weld GP electrodes @t 10 % of total ( 2150 x 0.10 ) : 215 Nos
132
GATE / HOIST AND ALLIED WORKS
4. Welding :
Length of welding : 196 Rm
For stich welding @ 2 hrs usage / shift & @ 12 electrodes / hr
( 215 / 12 ) x 8 / 2 : 72 hours
For run welding @ 6 hrs usage / shift & @ 12 electrodes / hr
( 1935 / 12 ) x 8 / 6 : 215 hours
Total : 287 hours
Deploy welding transformer for 287 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 72 x 0.25 + 215 x 0.75 ) : 179 hours
133
GATE / HOIST AND ALLIED WORKS
Contd
134
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ) :
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
5 Bolt / Nut / Washer
GI bolts / nuts / washers kg 16.50 127.00 2095.50
MS bolts / nuts / washers kg 55.00 96.00 5280.00
6 Zinc for trunnion seating kg 40.00 229.00 9160.00
7 Rubber seals
Bottom seal Rm 3.10 233.00 722.30
Side seals ( Z type ) Rm 10.20 442.00 4508.40
8 Oxygen gas cum 90.00 78.00 7020.00
9 Acetyline gas cum 30.00 404.00 12120.00
10 Welding electrodes ( general purpose ) Nos 215.00 11.00 2365.00
11 Welding electrodes ( low hydrogen ) Nos 1935.00 21.00 40635.00
12 Zinc rich epoxy primer ltr 10.00 756.00 7560.00
13 Coal tar epoxy paint ltr 45.00 256.50 11542.50
14 Rust cleaner / inhibitor ltr 11.00 326.00 3586.00
15 Wire brush Nos 2.00 54.00 108.00
16 Use rate welding holder set Hour 287.00 6.75 1937.25
17 Use rate gas cutting torch set Hour 36.00 3.75 135.00
18 Sundries LS 10.00 45.00 450.00
Total `: 341968.85
Add for small Tools and Plants @ 1% `: 3419.69
Add for Contractor's Profit @ 10% `: 34196.89
Add for Contractor's Overheads @ 5% `: 17098.44
Total cost of Materials : `: 396683.87
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 287.00 13.00 3731.00
Fuel / Energy charges Hour 179.00 86.00 15394.00
2 Pug cutting machine Hour 24.00 18.00 432.00
Fuel / Energy charges Hour 24.00 4.00 96.00
3 Bending machine Hour 20.00 43.00 860.00
Fuel / Energy charges Hour 20.00 107.00 2140.00
4 Mobile crane 8 t Hour 10.00 412.00 4120.00
Fuel / Energy charges Hour 10.00 718.00 7180.00
5 Stationery derric crane Hour 20.00 73.00 1460.00
Fuel / Energy charges Hour 20.00 15.00 300.00
6 Grinding machine Hour 12.00 20.00 240.00
Fuel / Energy charges Hour 12.00 36.00 432.00
7 Drilling machines Hour 12.00 20.00 240.00
Fuel / Energy charges Hour 12.00 36.00 432.00
8 Sundries LS 10.00 45.00 450.00
Total `: 37507.00
Add for small Tools and Plants @ 1% `: 375.07
Add for Contractor's Profit on DPOL / Energy @ 10% `: 2642.40
Add for Contractor's Overheads @ 5% `: 1875.35
Total hire charges of Machinery : `: 42399.82
135
GATE / HOIST AND ALLIED WORKS
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 10.00 144.00 1440.00
2 Crew for Bending machine Hour 20.00 87.00 1740.00
3 Crew for Drilling machine Hour 16.00 111.00 1776.00
4 Crew for Grinding machine Hour 8.00 111.00 888.00
5 Foreman Day 20.00 311.67 6233.30
6 Marker / Fabricator / Erector Day 34.00 289.67 9848.61
7 Gas cutter Day 8.00 289.67 2317.32
8 Welder ( General ) Day 24.00 289.67 6951.96
9 Welder ( X - ray ) Day 3.00 318.63 955.89
10 Helper fabrication / erection Day 90.00 274.67 24719.85
11 Helper for cleaning / painting Day 12.00 274.67 3295.98
12 Painter Cl - II Day 24.00 274.67 6591.96
13 Electrician Day 2.00 276.17 552.33
Total `: 67311.20
Add for small Tools and Plants @ 1% `: 673.11
Add for Contractor's Profit @ 10% `: 6731.12
Add for hidden cost on Labour @ 15% `: 10096.68
Add for additional hidden cost on labour @ 15% `: 10096.68
Add for Contractor's Overheads @ 5% `: 3365.56
Total cost of Labour : `: 98274.36
ABSTRACT:
A. Cost of Materials `: 396683.87
B. Hire charges of Machinery `: 42399.82
C. Cost of Labour `: 98274.36
TOTAL `: 537358.04
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 8693.66
Add for insurance charges @ 1.00% `: 5373.58
Add for designs and drawings @ 2.50% `: 13433.95
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 13433.95
Add for power supply arrangements @ 2.00% `: 10747.16
Add for enabling works @ 1.50% `: 8060.37
Total `: 597100.72
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 4.455 tonnes @ `: 247.10 / tonne `: 2201.66
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 15 ) @ 3.00% `: 4782.08
Total cost for 4.455 tonne `: 604084.47
Rate per tonne `: 135596.96
Rate approved per tonne `: 135600.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.28
ITEM: Design, fabrication, supply, erection, testing and commissioning of adequate capacity
electrically operated rope drum hoist consisting of hoist platform, rope drums, connecting
shaft, gear system, electric motor, electro- magnetic brake system, control panel, pulleys, wire
136
GATE / HOIST AND ALLIED WORKS
rope, manual operating system, railing, ladder etc., with all accessories for operating canal
regulator radial gate including cost of all materials, machinery, labour, cutting, aligning,
anchoring, welding, finishing, cleaning, greasing, applying two coats of zinc chromate red
oxide primer and three coats of approved synthetic ename paint etc., complete with lead upto
1 km and all lifts for structural steel components and all leads and lifts including
packing / forwarding charges for other materials.
DATA:Rope drum hoist for radial gate consists of embedded parts for anchorage, hoist supporting
structure, pulley supporting structures, pulleys, drive stool, rope drums, couplings, shafts,
gears and pinions, plummer blocks, worm reducer, floating shaft, electric motor, hand operation
assembly, brake, wire rope, gate position indicator, switch box etc. with related accessories.
Generally the capacity of rope drum hoist for small radial gate will be about 2 times the weight
of radial gate and the weight of hoist with all accessories is assumed at 0.30 tonne per tonne
capacity of the rope drum hoist.
Consider rope drum hoist for radial gate for canal regulator opening of size 3 m x 3.7 m.
Size of radial gate : 3.00 m x 3.90 m Head of water : 3.70 m
Weight of regulator radial gate leaf in tonne based on empirical formula :
= 0.1690 x ( L 2 x H x h ) 0.673
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.673
= 0.1690 x ( 3 x 3 x 3.9 x 3.7 ) : 4.470
Consider Capacity of hoist with 25% reserve capacity at 2 times the weight of gate :
( 2 x 4.470 ) : 8.940 tonnes
Round off the capacity of hoist to next 5 tonne : 10 tonnes
Consider weight of hoist @ 0.3 tonne per tonne capacity of hoist :
( 0.30 x 10 ) : 3.000 tonnes
The hoist capacity and hoist weight computed as above based on empirical formulae are further
checked by varifying / computing the actual capacity and weight as per fabrication drawings for
canal regulator radial gate rope drum hoist of same capacity provided for one of the canal work.
Actual capacity of hoist as per data in Item : 28 of Annexure-2 : 10 tonnes
Actual weight of gate rope drum hoist as per data in Item :28 of Annexure-2 : 3.002 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of rope
drum hoist for canal regulator radial gate provided for one of the canal work for rate analysis
( for details refer Item : 28 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 1238x1.025 ) : 1269 kg
Plates / flats with 2.5 % wastage ( 531 x 1.025 ) : 544 kg
Chequered plate ( 190 x 1.025 ) : 195 kg
b. Cast steel components conforming to IS : 1030 :
Rope drums 2 Nos / Gears : 384 kg
Pinions : 14 kg
Pulleys 6 Nos : 108 kg
Plummer blocks / Hubs : 47 kg
c. Alloy steel components conforming to IS : 1570 :
Shafts : 75 kg
Pins : 24 kg
d. Alluminium/ Bronze alloy components conforming to IS : 305 :
Bearings / Bush : 11 kg
137
GATE / HOIST AND ALLIED WORKS
138
GATE / HOIST AND ALLIED WORKS
139
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 97.00 13.00 1261.00
Fuel / Energy charges Hour 61.00 86.00 5246.00
2 Pug cutting machine Hour 7.00 18.00 126.00
Fuel / Energy charges Hour 7.00 4.00 28.00
Contd
140
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ) :
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
3 Mobile crane 8 t Hour 16.00 412.00 6592.00
Fuel / Energy charges Hour 8.00 718.00 5744.00
4 Stationery derric crane Hour 16.00 73.00 1168.00
Fuel / Energy charges Hour 16.00 15.00 240.00
5 Grinding machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
6 Drilling machines Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
7 Sundries LS 60.00 45.00 2700.00
Total `: 24001.00
Add for small Tools and Plants @ 1% `: 240.01
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1453.40
Add for Contractor's Overheads @ 5% `: 1200.05
Total hire charges of Machinery : `: 26894.46
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 16.00 144.00 2304.00
2 Crew for Drilling machine Hour 8.00 111.00 888.00
3 Crew for Grinding machine Hour 8.00 111.00 888.00
4 Foreman Day 12.00 311.67 3739.98
5 Marker / Fabricator / Erector Day 20.00 289.67 5793.30
6 Gas cutter Day 7.00 289.67 2027.66
7 Welder ( General ) Day 9.00 289.67 2606.99
8 Helper fabrication / erection Day 45.00 274.67 12359.93
9 Helper for cleaning / painting Day 5.00 274.67 1373.33
10 Painter Cl - II Day 10.00 274.67 2746.65
11 Electrician Day 2.00 276.17 552.33
Total `: 35280.15
Add for small Tools and Plants @ 1% `: 352.80
Add for Contractor's Profit @ 10% `: 3528.02
Add for hidden cost on Labour @ 15% `: 5292.02
Add for additional hidden cost on labour @ 15% `: 5292.02
Add for Contractor's Overheads @ 5% `: 1764.01
Total cost of Labour : `: 51509.02
ABSTRACT:
A. Cost of Materials `: 479892.45
B. Hire charges of Machinery `: 26894.46
C. Cost of Labour `: 51509.02
TOTAL `: 558295.93
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 4845.34
Add for insurance charges @ 1.00% `: 5582.96
Add for designs and drawings @ 2.50% `: 13957.40
141
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.29
ITEM: Design, fabrication, supply, erection, testing and commissioning of adequate capacity
manually operated rope drum hoist consisting of hoist platforms, rope drums, connecting
shaft, gear system, brake system, pulleys, wire rope, manual operation system, railing, ladder
etc., with all accessories for operating canal regulator radial gate including cost of all
materials, machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning, greasing,
applying two coats of zinc chromate red oxide primer and three coats of approved synthetic
enamel paint etc., complete as per specifications and approved drawings with lead upto
1 km and all liftsfor structural steel components and all leads and lifts including
packing / forwarding charges for other materials.
DATA:Rope drum hoist for radial gate consists of embedded parts for anchorage, hoist supporting
structure, pulley supporting structures, pulleys, drive stool, rope drums, couplings, shafts,
gears and pinions, plummer blocks, worm reducer, floating shaft, hand operation assembly,
brake, wire rope, gate position indicator etc. with related accessories.
Generally the capacity of rope drum hoist for small radial gate will be about 2 times the weight
of radial gate and the weight of the hoist with all accessories is assumed at 0.30 tonne per
tonne capacity of the rope drum hoist.
Consider rope drum hoist for radial gate for canal regulator opening of size 3 m x 3.7 m.
Size of radial gate : 3.00 m x 3.90 m Head of water : 3.70 m
Weight of regulator radial gate leaf in tonne based on empirical formula :
= 0.1690 x ( L 2 x H x h ) 0.673
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
= 0.1690 x ( 3 x 3 x 3.9 x 3.7 ) 0.673 : 4.470
Consider Capacity of hoist with 25% reserve capacity at 2 times the weight of gate :
( 2 x 4.470 ) : 8.940 tonnes
Round off the capacity of hoist to next 5 tonne : 10 tonnes
Consider weight of hoist @ 0.3 tonne per tonne capacity of hoist :
( 0.30 x 10 ) : 3.000 tonnes
Less weight of drive unit ( electric motor / cover etc ) : 0.200 tonne
Weight of manually operated hoist : 2.800 tonnes
The hoist capacity and hoist weight computed as above based on empirical formulae are further
checked by varifying / computing the actual capacity and weight as per fabrication drawings for
canal regulator radial gate rope drum hoist of same capacity provided for one of the canal work.
Actual capacity of hoist as per data In Item :29 of Annexure-2 : 10 tonnes
142
GATE / HOIST AND ALLIED WORKS
Actual weight of rope drum hoist as per data in Item : 29 of Annexure-2 : 2.804 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of rope drum
hoist for canal regulator radial gate provided for one of the canal work for rate analysis ( for
details refer Item : 29 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 1193x1.025 ) : 1223 kg
Plates / flats with 2.5 % wastage ( 442 x 1.025 ) : 453 kg
Chequered plate ( 190 x 1.025 ) : 195 kg
b. Cast steel components conforming to IS : 1030 :
Rope drums 2 Nos / Gears : 384 kg
Pinions : 14 kg
Pulleys 6 Nos : 108 kg
Plummer blocks / Hubs : 47 kg
c. Alloy steel components conforming to IS : 1570 :
Shafts : 75 kg
Pins : 24 kg
d. Alluminium/ Bronze alloy components conforming to IS : 305 :
Bearings / Bush : 11 kg
e. Bolt / Nut / Washers conforming to IS : 1363 :
MS Bolts / Nuts / Washers with 2.5 % wastage ( 63 x 1.025 ) : 65 kg
f. Steel wire rope conforming to IS : 2266 :
12 mm dia 6 / 36 construction 2 Nos 35 m each @ 0.6 kg / Rm : 42 kg
g. Other components :
Manual operating system : 1 No.
Worm reducers : 1 No.
Wire rope sockets : 2 Nos
MS pipe 32 mm dia : 10.5 Rm
h. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:29 Annexure-2 ) : 755 Nos
Add for variations / wastage / misc welding @ 10 % ( 755 x 0.1 ) : 75 Nos
Total requirement of GP / LH electrodes : 830 Nos
for stitch weld GP electrodes @t 10 % of total ( 830 x 0.10 ) : 83 Nos
for run welding LH electrodes @ 90 % of total ( 830 x 0.90 ) : 747 Nos
2. Cutting :
Length of cutting assuming cutting for 2 sides as per data sheet : 73 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 7 Rm
Total : 80 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas manually : 60 Rm
Length of steel to be cut by gas using pug cutting machine : 20 Rm
Time for gas cutting manually at ( av ) 2 m cutting / hour : 30 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 7 hours
Acetelyne gas @ 0.6 cum / hour ( 30 + 7 ) x 0.60 : 22 cum
Oxygen gas @ 1.8 cum / hour ( 30 + 7 ) x 1.80 : 66 cum
Use of gas cutting torch with 50 min / hr working ( 30 x 60 / 50 ) : 36 hours
Use of pug cutting machine with 50 min / hr working ( 7 x 60 / 50 ) : 8 hours
143
GATE / HOIST AND ALLIED WORKS
3. Welding :
Length of welding as per data sheet : 113 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 83 / 15 ) x 8 / 2 : 22 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 747 / 15 ) x 8 / 6 : 66 hours
Total : 88 hours
Deploy welding transformer for 88 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 22 x 0.25 + 66 x 0.75 ) : 55 hours
144
GATE / HOIST AND ALLIED WORKS
145
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ):
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
23 Use rate gas cutting torch set Hour 36.00 3.75 135.00
24 Sundries LS 100.00 45.00 4500.00
Total `: 376669.04
Add for small Tools and Plants @ 1% `: 3766.69
Add for Contractor's Profit @ 10% `: 37666.90
Add for Contractor's Overheads @ 5% `: 18833.45
Total cost of Materials : `: 436936.08
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 88.00 13.00 1144.00
Fuel / Energy charges Hour 55.00 86.00 4730.00
2 Pug cutting machine Hour 8.00 18.00 144.00
Fuel / Energy charges Hour 8.00 4.00 32.00
3 Mobile crane 8 t Hour 8.00 412.00 3296.00
Fuel / Energy charges Hour 8.00 718.00 5744.00
4 Stationery derric crane Hour 16.00 73.00 1168.00
Fuel / Energy charges Hour 16.00 15.00 240.00
5 Grinding machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
6 Drilling machines Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
7 Sundries LS 50.00 45.00 2250.00
Total `: 19644.00
Add for small Tools and Plants @ 1% `: 196.44
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1357.20
Add for Contractor's Overheads @ 5% `: 982.20
Total hire charges of Machinery : `: 22179.84
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 8.00 144.00 1152.00
2 Crew for Drilling machine Hour 8.00 111.00 888.00
3 Crew for Grinding machine Hour 8.00 111.00 888.00
4 Foreman Day 12.00 311.67 3739.98
5 Marker / Fabricator / Erector Day 20.00 289.67 5793.30
6 Gas cutter Day 6.00 289.67 1737.99
7 Welder ( General ) Day 8.00 289.67 2317.32
8 Helper fabrication / erection Day 45.00 274.67 12359.93
9 Helper for cleaning / painting Day 4.00 274.67 1098.66
10 Painter Cl - II Day 9.00 274.67 2471.99
11 Electrician Day 2.00 276.17 552.33
Total `: 32999.49
Contd
146
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
Add for small Tools and Plants @ 1% `: 329.99
Add for Contractor's Profit @ 10% `: 3299.95
Add for hidden cost on Labour @ 15% `: 4949.92
Add for additional hidden cost on labour @ 15% `: 4949.92
Add for Contractor's Overheads @ 5% `: 1649.97
Total cost of Labour : `: 48179.26
ABSTRACT:
A. Cost of Materials `: 436936.08
B. Hire charges of Machinery `: 22179.84
C. Cost of Labour `: 48179.26
TOTAL `: 507295.18
Machinery / Labour components @ 8.24% `: 4348.19
Add for insurance charges @ 1.00% `: 5072.95
Add for designs and drawings @ 2.50% `: 12682.38
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 12682.38
Add for power supply arrangements @ 2.00% `: 10145.90
Add for enabling works @ 1.50% `: 7609.43
Total `: 559836.41
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 2.804 tonnes @ `: 247.10 / tonne `: 1385.74
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 21 ) @ 3.00% `: 8723.46
Total cost for 2.804 tonne weight `: 569945.61
10.000 tonne capacity
Rate per tonne weight `: 203260.00
Rate per tonne capacity `: 56994.56
Rate approved per tonne capacity `: 57000.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.30
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts ( with top seal
seat ) consisting of sill beam, wheel tracks, seal seats, guide rails, groove lining upto top etc.,
with all accessories for vertical lift roller gate for canal escape / regulator including cost
of all materials, machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning,
applying one coat of zinc rich epoxy primer and four coats of cold applied coal tar epoxy paint
etc., complets as per specifications and approved drawings with lead upto 1 km and all lifts
for structural steel components and all leads and lifts including packing / forwarding
charges for other materials.
DATA:Embedded parts for canal escape / regulator gate consist of sill beam, wheel / seal tracks,
groove lining upto top, gate guide with all accessories such as first stage anchors.
Weight of embedded parts with groove lining for such small gates will be about 150 percent of
gate weight.
Consider embedded parts for canal escape / regulator gate for opening of size 2 m x 2 m.
For 2 m x 2 m opening approximate size of gate : 2.5 m x 2.2 m
147
GATE / HOIST AND ALLIED WORKS
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5% wastage ( 1189.5x1.025 ) : 1219 kg
Plates / flats with 2.5 % wastage ( 514.5 x 1.025 ) : 527 kg
b. Alloy steel components conforming to IS : 1570 :
Stainless steel plates / flats ( 79.5 x 1.025 ) : 82.00 kg
c. Bolt / Nut / Washer conforming to IS : 1363 :
MS bolts and nuts with 2.5 % wastage : 1 kg
d. Welding electrodes ( General purpose / Low hydrogen / Stainless steel ) :
GP / LH electrodes as per data sheet ( Item:30 Annexure-2 ) : 1182 Nos
Add for variations / wastage / misc welding @ 10 % ( 1182 x 0.1 ) : 118 Nos
Total requirement of GP / LH electrodes : 1300 Nos
for stitch welding GP electrodes @t 10 % of total ( 1300 x 0.10 ) : 130 Nos
for run welding LH electrodes @ 90 % of total ( 1300 x 0.90 ) : 1170 Nos
Stainless steel electrodes as per data sheet ( Item:30 Annexure-2 ) : 217 Nos
Add for variations / wastage @ 5 % ( 217 x 0.05 ) : 11 Nos
Total requirement of Stainless steel ( SS ) electrodes : 228 Nos
for stitch weld SS electrodes @t 10 % of total ( 228 x 0.10 ) : 23 Nos
for run weld SS electrodes @t 90 % of total ( 228 x 0.90 ) : 205 Nos
2. Cutting :
Total length of cutting assuming cutting for 2 sides as per data sheet : 40 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 4 Rm
Total : 44 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas manually : 24 m
Length of steel to be cut by gas using pug cutting machine : 20 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 12 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 7 hours
Acetelyne gas @ 0.6 cum / hour ( 12 + 7 ) x 0.60 : 11 cum
Oxygen gas @ 1.8 cum / hour ( 12 + 7 ) x 1.80 : 33 cum
Use of gas cutting torch with 50 min / hr working ( 12 x 60 / 50 ) : 15 hours
Use of pug cutting machine with 50 min / hr working ( 7 x 60 / 50 ) : 9 hours
3. Welding :
Length of welding as per data sheet : 207 m
148
GATE / HOIST AND ALLIED WORKS
149
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 163.00 13.00 2119.00
Fuel / Energy charges Hour 102.00 86.00 8772.00
2 Mobile crane 8 t Hour 2.00 412.00 824.00
Fuel / Energy charges Hour 2.00 718.00 1436.00
3 Pug cutting machine Hour 9.00 18.00 162.00
Fuel / Energy charges Hour 9.00 4.00 36.00
4 Planing machine Hour 48.00 97.00 4656.00
Fuel / Energy charges Hour 48.00 107.00 5136.00
5 Grinding machine Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
Contd
150
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
6 Drilling machines Hour 1.00 20.00 20.00
Fuel / Energy charges Hour 1.00 36.00 36.00
7 Sundries LS 5.00 45.00 225.00
Total `: 23534.00
Add for small Tools and Plants @ 1% `: 235.34
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1571.30
Add for Contractor's Overheads @ 5% `: 1176.70
Total hire charges of Machinery : `: 26517.34
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Planing machine Hour 48.00 139.00 6672.00
2 Crew for Drilling machine Hour 1.00 111.00 111.00
3 Crew for Grinding machine Hour 2.00 111.00 222.00
4 Crew for Mobile crane Hour 2.00 144.00 288.00
5 Foreman Day 6.00 311.67 1869.99
6 Marker / Fabricator / Erector Day 12.00 289.67 3475.98
7 Gas cutter Day 3.00 289.67 869.00
8 Welder ( General ) Day 13.00 289.67 3765.65
9 Welder ( X - ray ) Day 2.00 318.63 637.26
10 Helper fabrication / erection Day 38.00 274.67 10437.27
11 Helper for cleaning / painting Day 2.00 274.67 549.33
12 Painter Cl - II Day 3.00 274.67 824.00
13 Electrician Day 1.00 276.17 276.17
Total `: 29997.63
Add for small Tools and Plants @ 1% `: 299.98
Add for Contractor's Profit @ 10% `: 2999.76
Add for hidden cost on Labour @ 15% `: 4499.64
Add for additional hidden cost on labour @ 15% `: 4499.64
Add for Contractor's Overheads @ 5% `: 1499.88
Total cost of Labour : `: 43796.54
ABSTRACT:
A. Cost of Materials `: 162953.67
B. Hire charges of Machinery `: 26517.34
C. Cost of Labour `: 43796.54
TOTAL `: 233267.55
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 4345.40
Add for insurance charges @ 1.00% `: 2332.68
Add for designs and drawings @ 2.50% `: 5831.69
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 5831.69
Add for power supply arrangements @ 2.00% `: 4665.35
Add for enabling works @ 1.50% `: 3499.01
Total `: 259773.37
151
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.31
ITEM: Design, fabrication, supply, erection, testing and commissioning of fixed wheel type vertical
lift gate ( with top seal ) consisting of skin plate, stiffeners, horizontal and vertical girders,
wheels, guide rollers, rubber seals etc., with all accessories for canal escape / regulator vent
including cost of all materials, machinery, labour, cutting, aligning, welding, finishing, cleaning,
applying one coat of zinc rich epoxy primer and three coats of cold applied coal tar epoxy paint,
seal fixing etc., complete as per specifications and approved drawings with lead upto 1 km
and all lifts for structural steel components and all leads and lifts including packing /
forwarding charges for other materials.
DATA:Consider down stream sealing vertical lift roller gate. The gate leaf consists of skin plate,
horizontal girders, vertical end girders, stiffeners, wheels, gate guide rollers, brackets, pins,
seals etc., with all accessories.
Consider canal escape / regulator gate for 2 m x 2 m vent opening for analysis.
For 2 m x 2 m opening approximate size of gate : 2.5 m x 2.2 m
Head of water above sill level : 3.7 m
Weight of vertical lift roller gate in tonne for regulator / escape based on empirical formula :
2 0.659
= 0.0888 ( L x H x h )
Where ( L ) is length and ( H ) is height of gate and ( h ) is head of water in metre.
= 0.0888 ( 2.5 x 2.5 x 2.2 x 3.7 ) 0.659 : 1.183
The weight computed as above based on empirical formula is further checked by computing
the actual weight as per fabrication drawings of fixed wheel vertical lift roller gate of same size
provided for one of the canal escape structurer.
Actual weight of canal escape gate as per data in Item : 31 of Annexure-2 : 1.217 tonnes
Consider actual weight for data rate analysis.
Consider details of Material /Gas cutting / Welding based on fabrication drawings of fixed wheel
vertical lift roller gate provided for one of the canal escape structure for rate analysis ( for details
refer Item : 31 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles / beams / channels / bars with 2.5 % wastage ( 244x1.025 ) : 250 kg
Plates / flats with 2.5 % wastage ( 877 x 1.025 ) : 899 kg
b. Alloy steel components conforming to IS : 1570 :
Wheel axles / Pins : 30 kg
c. Cast steel components conforming to IS : 1030 :
Wheels / guide rollers : 50 kg
d. Alluminium / Bronze alloy components conforming to IS : 305 :
Bearings / Bushes : 5 kg
e. Bolts / Nuts / Washers conforming to IS : 1363 :
GI bolts / nuts / washers with 2.5 % wastage ( 7.5 x 1.025 ) : 8 kg
MS bolts / nuts / washers with 2.5 % wastage ( 3.5 x 1.025 ) : 4 kg
152
GATE / HOIST AND ALLIED WORKS
153
GATE / HOIST AND ALLIED WORKS
154
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ):
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
7 Oxygen gas cum 36.00 78.00 2808.00
8 Acetyline gas cum 12.00 404.00 4848.00
9 Welding electrodes ( general purpose ) Nos 72.00 11.00 792.00
10 Welding electrodes ( low hydrogen ) Nos 652.00 21.00 13692.00
11 Zinc rich epoxy primer ltr 2.50 756.00 1890.00
12 Coal tar epoxy paint ltr 11.00 256.50 2821.50
13 Rust cleaner / inhibitor ltr 3.00 326.00 978.00
14 Wire brush Nos 1.00 54.00 54.00
15 Use rate welding holder set Hour 77.00 6.75 519.75
16 Use rate gas cutting torch set Hour 12.00 3.75 45.00
17 Sundries LS 2.00 45.00 90.00
Total `: 104680.80
Add for small Tools and Plants @ 1% `: 1046.81
Add for Contractor's Profit @ 10% `: 10468.08
Add for Contractor's Overheads @ 5% `: 5234.04
Total cost of Materials : `: 121429.73
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 77.00 13.00 1001.00
Fuel / Energy charges Hour 48.00 86.00 4128.00
2 Pug cutting machine Hour 12.00 18.00 216.00
Fuel / Energy charges Hour 12.00 4.00 48.00
3 Mobile crane 8 t Hour 2.00 412.00 824.00
Fuel / Energy charges Hour 2.00 718.00 1436.00
4 Stationery derric crane Hour 2.00 73.00 146.00
Fuel / Energy charges Hour 2.00 15.00 30.00
5 Grinding machine Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
6 Drilling machines Hour 1.00 20.00 20.00
Fuel / Energy charges Hour 1.00 36.00 36.00
7 Sundries LS 2.00 45.00 90.00
Total `: 8087.00
Add for small Tools and Plants @ 1% `: 80.87
Add for Contractor's Profit on DPOL / Energy @ 10% `: 584.00
Add for Contractor's Overheads @ 5% `: 404.35
Total hire charges of Machinery : `: 9156.22
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 2.00 144.00 288.00
2 Crew for Drilling machine Hour 1.00 111.00 111.00
3 Crew for Grinding machine Hour 2.00 111.00 222.00
Contd
155
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
4 Foreman Day 5.00 311.67 1558.33
5 Marker / Fabricator / Erector Day 7.00 289.67 2027.66
6 Gas cutter Day 3.00 289.67 869.00
7 Welder ( General ) Day 6.00 289.67 1737.99
8 Welder ( X - ray grade ) Day 1.00 318.63 318.63
9 Helper fabrication / erection Day 21.00 274.67 5767.97
10 Helper for cleaning / painting Day 3.00 274.67 824.00
11 Painter Cl - II Day 6.00 274.67 1647.99
12 Electrician Day 1.00 276.17 276.17
Total `: 15648.71
Add for small Tools and Plants @ 1% `: 156.49
Add for Contractor's Profit @ 10% `: 1564.87
Add for hidden cost on Labour @ 15% `: 2347.31
Add for additional hidden cost on labour @ 15% `: 2347.31
Add for Contractor's Overheads @ 5% `: 782.44
Total cost of Labour : `: 22847.12
ABSTRACT:
A. Cost of Materials `: 121429.73
B. Hire charges of Machinery `: 9156.22
C. Cost of Labour `: 22847.12
TOTAL `: 153433.07
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 1977.81
Add for insurance charges @ 1.00% `: 1534.33
Add for designs and drawings @ 2.50% `: 3835.83
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 3835.83
Add for power supply arrangements @ 2.00% `: 3068.66
Add for enabling works @ 1.50% `: 2301.50
Total `: 169987.01
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 1.217 tonnes @ `: 247.10 / tonne `: 601.44
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 14 ) @ 3.00% `: 1675.07
Total cost for 1.217 tonne `: 172263.52
Rate per tonne `: 141547.68
Rate approved per tonne `: 141500.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.32
ITEM: Design, fabrication, supply, erection, testing and commissioning of adequate capacity screw
type hoist consisting of supporting structure, platform, railing, ladder etc., with all accessories
for operating canal escape / regulator gate including cost of all materials, machinery,labour,
cutting, aligning, anchoring, welding, finishing, cleaning, greasing, applying two coats of zinc
chromate red oxide primer and three coats of approved synthetic enamel paint etc., complete
with lead upto 1 km and all lifts for structural steel components and all leads and lifts
156
GATE / HOIST AND ALLIED WORKS
DATA:Screw type hoist for operating gate consists of supporting structure, hoist body, hoist stem,
thrust bearings, operating wheel / handle with related accessories.
The capacity of screw hoist for canal gate may be considered at 2.5 times the weight of gate.
Consider screw type hoist for canal escape / regulator gate for vent opening of size 2 m x 2 m.
For 2 m x 2 m opening approximate size of gate : 2.5 m x 2.2 m
Head of water above sill level : 3.7 m
Weight of vertical lift gate in tonnes for regulator / escape based on empirical formula :
2 0.659
= 0.0888 x ( L x H x h )
Where ( L ) is length and ( H ) is height and ( h ) is head of water in metres.
0.659
= 0.0888 x ( 2.5 x 2.5 x 2.2 x 3.7 ) : 1.183
Consider capacity of screw hoist with 25 % reserve capacity @ 2.5 times the weight of gate :
( 2.5 x 1.183) : 2.957 tonnes
Round off the capacity of hoist to next 1 tonne : 3.00 tonnes
Consider weight of hoist with all accessories at 0.3 tonne per tonne capacity of hoist :
( 0.3 x 3 ) : 0.900 tonne
The hoist capacity and hoist weight computed as above based on empirical formulae are further
checked by varifying / computing the actual capacity and weight as per fabrication drawings of
screw type hoist of same capacity for vertical lift roller gate provided for one of the canal escape.
Actual capacity of hoist as per data : 3.00 tonnes
Actual weight of screw hoist as per data in Item : 32 of Annexure-2 : 0.871 tonne
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of screw type
hoist for canal escape vertical lift roller gate provided for one of the canal escape structure ( for
details refer Item : 32 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5% wastage ( 392.5x1.025 ) : 402.00 kg
Plates / flats with 2.5 % wastage ( 141.5 x 1.025 ) : 145.00 kg
Chequered plates with 2.5 % wastage ( 172 x 1.025 ) : 176.00 kg
b. Cast iron components conforming to IS : 210 :
Hoist body / Lock nut / Main nut : 55.00 kg
c. Alloy steel components conforming to IS : 1570 :
Hoist stem : 75.00 kg
d. Alluminium/ Bronze alloy components conforming to IS : 305 :
Bearings / Bush : 4.00 kg
e. Bolt / Nut / Washers conforming to IS : 1363 :
MS Bolts / Nuts / Washers with 2.5 % wastage ( 8 x 1.025 ) : 8.00 kg
MS pipe 32 mm dia : 8.8 Rm
f. Welding electrodes ( General purpose ) :
GP / LH electrodes as per data sheet ( Item:32 Annexure-2 ) : 71 Nos
Add for variations / wastage / misc welding @ 10 % ( 71 x 0.1 ) : 7 Nos
Total requirement of GP / LH electrodes : 78 Nos
for stitch weld GP electrodes @t 10 % of total ( 78 x 0.10 ) : 8 Nos
for run welding GP electrodes @ 90 % of total ( 78 x 0.90 ) : 70 Nos
2. Cutting :
Total length of cutting assuming cutting for 2 sides as per data sheet : 18 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 2 Rm
157
GATE / HOIST AND ALLIED WORKS
For cutting structural steel sections to required sizes gas cutting is assumed.
Time for gas cutting manually at average cutting progress of 2 m / hour : 10 hours
Acetelyne gas @ 0.6 cum / hour ( 10 x 0.60 ) : 6 cum
Oxygen gas @ 1.8 cum / hour ( 10 x 1.80 ) : 18 cum
Use of gas cutting torch with 50 min / hr working ( 10 x 60 / 50 ) : 12 hours
3. Welding :
Length of welding as per data sheet : 10 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 8 / 15 ) x 8 / 2 : 2 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 70 / 15 ) x 8 / 6 : 6 hours
Total : 8 hours
Deploy welding transformer for 8 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 2 x 0.25 + 6 x 0.75 ) : 5 hours
4. Surface cleaning and painting :
Painting area for hoist at 20 sqm / tonne of str steel ( 0.723 x 20 ) : 15 sqm
2 coats of zinc chromate red oxide primer.
Quantity of primer paint for 15 sqm @ 12 sqm / ltr / coat : 3 ltr
3 coats of synthetic enamel paint.
Quantity of coal tar epoxy paint for 15 sqm @ 12 sqm / ltr / coat : 4 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 15 sqm @ 8 sqm / ltr : 2 ltr
5. Requirement of other machinery :
For handling of parts during fabrication / erection use of 8 t mobile crane for 1 hour considered.
For drilling holes for bolts 1 hours use of drilling machine considered.
For grinding and finishing weld joints 2 hours use of grinding machine considered
158
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 8.00 13.00 104.00
Fuel / Energy charges Hour 5.00 86.00 430.00
2 Mobile crane 8 t Hour 1.00 412.00 412.00
Fuel / Energy charges Hour 1.00 718.00 718.00
Contd
159
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
3 Grinding machine Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
4 Drilling machines Hour 1.00 20.00 20.00
Fuel / Energy charges Hour 1.00 36.00 36.00
5 Sundries LS 1.00 45.00 45.00
Total `: 1877.00
Add for small Tools and Plants @ 1% `: 18.77
Add for Contractor's Profit on DPOL / Energy @ 10% `: 58.30
Add for Contractor's Overheads @ 5% `: 93.85
Total hire charges of Machinery : `: 2047.92
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Drilling machine Hour 1.00 111.00 111.00
2 Crew for Grinding machine Hour 2.00 111.00 222.00
3 Crew for Mobile crane Hour 1.00 144.00 144.00
4 Foreman Day 3.00 311.67 935.00
5 Marker / Fabricator / Erector Day 5.00 289.67 1448.33
6 Gas cutter Day 2.00 289.67 579.33
7 Welder ( General ) Day 1.00 289.67 289.67
8 Helper fabrication / erection Day 9.00 274.67 2471.99
9 Helper for cleaning / painting Day 2.00 274.67 549.33
10 Painter Cl - II Day 4.00 274.67 1098.66
11 Electrician Day 0.50 276.17 138.08
Total `: 7987.37
Add for small Tools and Plants @ 1% `: 79.87
Add for Contractor's Profit @ 10% `: 798.74
Add for hidden cost on Labour @ 15% `: 1198.11
Add for additional hidden cost on labour @ 15% `: 1198.11
Add for Contractor's Overheads @ 5% `: 399.37
Total cost of Labour : `: 11661.56
ABSTRACT:
A. Cost of Materials `: 87286.62
B. Hire charges of Machinery `: 2047.92
C. Cost of Labour `: 11661.56
TOTAL `: 100996.11
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 847.25
Add for insurance charges @ 1.00% `: 1009.96
Add for designs and drawings @ 2.50% `: 2524.90
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 2524.90
Add for power supply arrangements @ 2.00% `: 2019.92
Add for enabling works @ 1.50% `: 1514.94
Total `: 111437.98
160
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.33
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts consisting of sill
beam, wheel tracks, seal seats, guide rails, gate groove liners etc., with all accessories for
canal escape / regulator stoplog gate including cost of all materials, machinery, labour,
cutting, aligning, anchoring, welding, finishing, cleaning, applying one coat of zinc rich epoxy
primer and four coats of cold applied coal tar epoxy paint etc., complete as per specifications
and approved drawings with lead upto 1 km and all lifts for structural steel components
and all leads and lifts including packing / forwarding charges for other materials.
DATA:Embedded parts for canal escape / regulator stop log gate consist of sill beam, wheel / seal
tracks, groove lining upto top, gate guide with all accessories such as first stage anchors.
Weight of embedded parts for such small gates will be in the range of 65 to 70 % of gate weight.
Consider embedded parts for canal escape / regulator stoplog gate for 2 m wide vent opening.
Length of stoplog element for 2 m wide opening : 2.50 m
Head of water above sill level : 3.70 m
Total height of stoplog gate considering 4 elements of 1 m height each : 4.00 m
Weight of embedded parts for stoplog gate in tonnes based on empirical formula :
2 0.716
= 0.0995 x ( L x H x h )
Where ( L ) is length and ( H ) is total height and ( h ) is head of water in metres.
Consider weight of embedded parts @ 67.5 % of weight of stoplog gate :
2 0.716
= 0.675 x 0.0995 x ( L x H x h )
0.716
= 0.0671 x ( 2.5 x 2.5 x 4 x 3.7 ) : 1.716
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of embedded parts for canal escape/ regulator stoplog
gate of same size provided for one of the canal escape / regulator structure.
Actual weight of embedded parts as per data in Item :33 of Annexure-2 : 1.685 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of embedded
parts for canal escape / regulator stoplog gate provided for one of the canal escape / regulator
structure ( for details refer Item : 33 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5% wastage ( 1106.5x1.025 ) : 1134 kg
Plates / flats with 2.5 % wastage ( 510 x 1.025 ) : 523 kg
b. Alloy steel components conforming to IS : 1570 :
Stainless steel plates / flats ( 68 x 1.025 ) : 70.00 kg
c. Bolt / Nut / Washer conforming to IS : 1363 :
MS bolts and nuts with 2.5 % wastage : 1 kg
161
GATE / HOIST AND ALLIED WORKS
162
GATE / HOIST AND ALLIED WORKS
163
GATE / HOIST AND ALLIED WORKS
A. MATERIALS ( Contd ):
Sl No Perticulars Unit Quantity Rate Amount
in `: in `:
Contd
11 Rust cleaner / inhibitor ltr 1.00 326.00 326.00
12 Wire brush Nos 1.00 54.00 54.00
13 Use rate welding holder set Hour 155.00 6.75 1046.25
14 Use rate gas cutting torch set Hour 12.00 3.75 45.00
15 Sundries LS 2.00 45.00 90.00
Total `: 131256.85
Add for small Tools and Plants @ 1% `: 1312.57
Add for Contractor's Profit @ 10% `: 13125.69
Add for Contractor's Overheads @ 5% `: 6562.84
Total cost of Materials : `: 152257.95
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 155.00 13.00 2015.00
Fuel / Energy charges Hour 97.00 86.00 8342.00
2 Pug cutting machine Hour 8.00 18.00 144.00
Fuel / Energy charges Hour 8.00 4.00 32.00
3 Planing machine Hour 44.00 97.00 4268.00
Fuel / Energy charges Hour 44.00 107.00 4708.00
4 Grinding machine Hour 2.00 20.00 40.00
Fuel / Energy charges Hour 2.00 36.00 72.00
5 Sundries LS 2.00 45.00 90.00
Total `: 19711.00
Add for small Tools and Plants @ 1% `: 197.11
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1324.40
Add for Contractor's Overheads @ 5% `: 985.55
Total hire charges of Machinery : `: 22218.06
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Planing machine Hour 44.00 139.00 6116.00
2 Crew for Grinding machine Hour 2.00 111.00 222.00
3 Foreman Day 6.00 311.67 1869.99
4 Marker / Fabricator / Erector Day 10.00 289.67 2896.65
5 Gas cutter Day 2.00 289.67 579.33
6 Welder ( General ) Day 13.00 289.67 3765.65
7 Welder ( X - ray ) Day 2.00 318.63 637.26
8 Helper fabrication / erection Day 35.00 274.67 9613.28
9 Helper for cleaning / painting Day 1.00 274.67 274.67
10 Painter Cl - II Day 3.00 274.67 824.00
11 Electrician Day 1.00 276.17 276.17
Total `: 27074.98
Add for small Tools and Plants @ 1% `: 270.75
Contd
164
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
Add for Contractor's Profit @ 10% `: 2707.50
Add for hidden cost on Labour @ 15% `: 4061.25
Add for additional hidden cost on labour @ 15% `: 4061.25
Add for Contractor's Overheads @ 5% `: 1353.75
Total cost of Labour : `: 39529.47
ABSTRACT:
A. Cost of Materials `: 152257.95
B. Hire charges of Machinery `: 22218.06
C. Cost of Labour `: 39529.47
TOTAL `: 214005.47
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 3816.00
Add for insurance charges @ 1.00% `: 2140.05
Add for designs and drawings @ 2.50% `: 5350.14
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 5350.14
Add for power supply arrangements @ 2.00% `: 4280.11
Add for enabling works @ 1.50% `: 3210.08
Total `: 238151.99
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 1.685 tonnes @ `: 247.10 / tonne `: 832.73
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 12 ) @ 3.00% `: 1828.97
Total cost for 1.685 tonne `: 240813.69
Rate per tonne `: 142916.14
Rate approved per tonne `: 142900.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.34
ITEM: Design, fabrication, supply, erection, testing and commissioning of sliding type interchangeable
stoplog gate elements consisting of skin plate, stiffeners, horizontal and vertical girders,
lifting hooks, bronze padded slide blocks, guide shoes, rubber seals etc., with all accessories
for canal regulator vent including cost of all materials, machinery, labour, cutting, aligning,
welding, finishing, cleaning, applying one coats of zinc rich epoxy primer and three coats of
cold applied coal tar epoxy paint, seal fixing etc., complete as per specifications and approved
drawings with lead upto 1 km and all lifts for structural steel components and all leads
and lifts including packing / forwarding charges for other materials.
DATA:Consider down stream sealing vertical lift slide gate. The stoplog gate consists of number
of inter-changeable elements having height of each element in the range of 0.9 to 1.2 m. Each
element consists of skin plate, horizontal girders, vertical end girders, stiffeners, slide blocks,
gate guide shoes, brackets, lifting pins,seals etc., with all accessories.
Consider canal escape / regulator gate for 2 m vent opening and 3.7 m depth of water.
Consider 4 elements of size 2.50 m length x 1.00 m height each.
Weight of 1 set of stoplog gate elements in tonne based on empirical formula :
2 0.716
= 0.0995 ( L x H x h )
165
GATE / HOIST AND ALLIED WORKS
Where ( L ) is length and ( H ) is total height of gate and ( h ) is head of water in metres.
0.716
= 0.0995 ( 2.5 x 2.5 x 4.0 x 3.7 ) : 2.544
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of canal escape / regulator stoplog gate elements of
size provided for one of the canal escape / regulator structure.
Actual wt of 1set of stoplog elements as per data in Item : 34 of Annexure-2 : 2.534 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of canal
escape / regulator stoplog gate elements provided for one of the canal escape / regulator ( for
details refer Item : 34 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 1166x1.025 ) : 1195 kg
Plates / flats with 2.5 % wastage ( 1342 x 1.025 ) : 1376 kg
b. Alluminium/ Bronze alloy components conforming to IS : 305 :
Bronze pads : 16.00 kg
c. Bolts / Nuts / Washers conforming to IS : 1363 :
GI bolts / nuts / washers with 2.5 % wastage ( 20 x 1.025 ) : 20.5 kg
MS bolts / nuts / washers with 2.5 % wastage ( 6 x 1.025 ) : 6 kg
d. Rubber seal conforming to IS : 11855 :
Bottom seal ( uncladed ) ( 8 x 1.025 ) : 8.2 Rm
Side seals ( uncladed ) ( 8.05 x 1.025 ) : 8.25 Rm
e. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:34 Annexure-2 ) : 1588 Nos
Add for variations / wastage / misc welding @ 10 % ( 1588 x 0.1 ) : 159 Nos
Total requirement of GP / LH electrodes : 1747 Nos
for stitch weld GP electrodes @t 10 % of total ( 1747 x 0.10 ) : 175 Nos
for run welding LH electrodes @ 90 % of total ( 1747 x 0.90 ) : 1572 Nos
2. Cutting :
Total length of cutting assuming cutting for 2 sides as per data sheet : 70 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 7 Rm
Total : 77 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas manually : 40 m
Length of steel to be cut by gas using pug cutting machine : 37 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 20 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 12 hours
Acetelyne gas @ 0.6 cum / hour ( 20 + 12 ) x 0.60 : 19 cum
Oxygen gas @ 1.8 cum / hour ( 20 + 12 ) x 1.80 : 57 cum
Use of gas cutting torch with 50 min / hr working ( 20 x 60 / 50 ) : 24 hours
Use of pug cutting machine with 50 min / hr working ( 12 x 60 / 50 ) : 14 hours
3. Welding :
Length of welding as per data sheet : 216 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 175 / 15 ) x 8 / 2 : 47 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 1572 / 15 ) x 8 / 6 : 140 hours
Total : 187 hours
Deploy welding transformer for 187 hours.
166
GATE / HOIST AND ALLIED WORKS
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 47 x 0.25 + 140 x 0.75 ) : 117 hours
4. Surface cleaning and painting :
Painting area for stoplog gate at 18 sqm / tonne ( 2.534 x 18 ) : 45 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 45 sqm @ 9 sqm / ltr / coat : 5 ltr
3 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 45 sqm @ 6 sqm / ltr / coat : 23 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 45 sqm @ 8 sqm / ltr : 6 ltr
5. Requirement of other machinery :
For handling of parts during fabrication and erection use of mobile derric crane for 2 hours and
stationery derric crane for 4 hours considered.
For drilling holes in skin plate, end girders and seal clamps use of drilling machine for 8 hours
considered.
For grinding and finishing weld joints in skin plate and other locations 8 hours use of grinding
machine considered.
167
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 187.00 13.00 2431.00
Fuel / Energy charges Hour 117.00 86.00 10062.00
2 Pug cutting machine Hour 14.00 18.00 252.00
Fuel / Energy charges Hour 14.00 4.00 56.00
3 Mobile crane 8 t Hour 2.00 412.00 824.00
Fuel / Energy charges Hour 2.00 718.00 1436.00
4 Stationery derric crane Hour 4.00 73.00 292.00
Fuel / Energy charges Hour 4.00 15.00 60.00
5 Grinding machine Hour 12.00 20.00 240.00
Fuel / Energy charges Hour 12.00 36.00 432.00
6 Drilling machines Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
7 Sundries LS 5.00 45.00 225.00
Total `: 16758.00
Contd
168
GATE / HOIST AND ALLIED WORKS
B. MACHINERY ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
Add for small Tools and Plants @ 1% `: 167.58
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1255.90
Add for Contractor's Overheads @ 5% `: 837.90
Total hire charges of Machinery : `: 19019.38
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 2.00 144.00 288.00
2 Crew for Drilling machine Hour 8.00 111.00 888.00
3 Crew for Grinding machine Hour 12.00 111.00 1332.00
4 Foreman Day 10.00 311.67 3116.65
5 Marker / Fabricator / Erector Day 15.00 289.67 4344.98
6 Gas cutter Day 5.00 289.67 1448.33
7 Welder ( General ) Day 16.00 289.67 4634.64
8 Welder ( X - ray grade ) Day 2.00 318.63 637.26
9 Helper fabrication / erection Day 45.00 274.67 12359.93
10 Helper for cleaning / painting Day 6.00 274.67 1647.99
11 Painter Cl - II Day 12.00 274.67 3295.98
12 Electrician Day 1.00 276.17 276.17
Total `: 34269.91
Add for small Tools and Plants @ 1% `: 342.70
Add for Contractor's Profit @ 10% `: 3426.99
Add for hidden cost on Labour @ 15% `: 5140.49
Add for additional hidden cost on labour @ 15% `: 5140.49
Add for Contractor's Overheads @ 5% `: 1713.50
Total cost of Labour : `: 50034.07
ABSTRACT:
A. Cost of Materials `: 222065.06
B. Hire charges of Machinery `: 19019.38
C. Cost of Labour `: 50034.07
TOTAL `: 291118.52
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 4267.50
Add for insurance charges @ 1.00% `: 2911.19
Add for designs and drawings @ 2.50% `: 7277.96
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 7277.96
Add for power supply arrangements @ 2.00% `: 5822.37
Add for enabling works @ 1.50% `: 4366.78
Total `: 323042.28
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 2.534 tonnes @ `: 247.10 / tonne `: 1252.30
169
GATE / HOIST AND ALLIED WORKS
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 12 ) @ 3.00% `: 2470.35
Total cost for 2.534 tonne `: 326764.94
Rate per tonne `: 128952.22
Rate approved per tonne `: 129000.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.35
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts consisting of
liners for trash rack grooves ( for coarse and fine screens ) with all accessories for pump house
intake structure including cost of all materials, machinery, cutting, labour, aligning, anchoring,
welding, finishing, cleaning, applying one coat of zinc rich epoxy primer and four coats of cold
applied coal tar epoxy paint etc., complete as per specifications and approved drawings with
lead upto 1 km for structural steel components and all leads and lifts including packing/
forwarding charges for other materials.
DATA:Embedded parts for trash rack groove of pump house intake structure consist of groove liners
with anchors.
Weight of one set embedded parts for trash rack groove will be in the range of 100 to 125 kg / m
height of the trash rack groove for one vent.
Consider embedded parts for trash rack groove of pump house intake for 3.55 m wide and 12 m
height vent.
Weight of embedded parts for 12 m height in tonnes based on empirical rule :
( 12 x 112.50 ) : 1350.00 kg
The weight computed as above based on empirical rule is further checked by computing the
actual weight as per fabrication drawings of embedded parts for trash rack groove for one vent
of one of the pump house intake structure.
Actual weight of embedded parts as per data in Item :35 of Annexure-2 : 1.322 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of embedded
parts for one vent of trash rack groove of one of the pump house intake structure ( for details
refer Item : 35 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Plates / flats with 2.5 % wastage ( 1322 x 1.025 ) : 1355 kg
b. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:35 Annexure-2 ) : 983 Nos
Add for variations / wastage / misc welding @ 10 % ( 983 x 0.1 ) : 98 Nos
Total requirement of GP / LH electrodes : 1081 Nos
for stitch welding GP electrodes @t 10 % of total ( 1081 x 0.10 ) : 108 Nos
for run welding LH electrodes @ 90 % of total ( 1081 x 0.90 ) : 973 Nos
2. Cutting :
Total length of cutting assuming cutting for 2 sides as per data sheet : 78 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 8 Rm
Total : 86 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas manually : 10 m
Length of steel to be cut by gas using pug cutting machine : 76 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 5 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 10 hours
170
GATE / HOIST AND ALLIED WORKS
3. Welding :
Length of welding as per data sheet : 98.3 m
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 108 x 8 / 15 / 2 ) : 29 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 973 x 8 / 15 / 6 ) : 86 hours
Total : 115 hours
Deploy welding transformer for 115 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 29 x 0.25 + 86 x 0.75 ) : 72 hours
171
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 115.00 13.00 1495.00
Fuel / Energy charges Hour 72.00 86.00 6192.00
2 Pug cutting machine Hour 30.00 18.00 540.00
Fuel / Energy charges Hour 30.00 4.00 120.00
3 Mobile crane 8 t Hour 4.00 412.00 1648.00
Fuel / Energy charges Hour 4.00 718.00 2872.00
4 Stationery derric crane Hour 6.00 73.00 438.00
Fuel / Energy charges Hour 6.00 15.00 90.00
5 Grinding machine Hour 4.00 20.00 80.00
Fuel / Energy charges Hour 4.00 36.00 144.00
6 Sundries LS 5.00 45.00 225.00
Total `: 13844.00
Add for small Tools and Plants @ 1% `: 138.44
Add for Contractor's Profit on DPOL / Energy @ 10% `: 964.30
Add for Contractor's Overheads @ 5% `: 692.20
Total hire charges of Machinery : `: 15638.94
172
GATE / HOIST AND ALLIED WORKS
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 4.00 144.00 576.00
2 Crew for Grinding machine Hour 4.00 111.00 444.00
3 Foreman Day 6.00 311.67 1869.99
4 Marker / Fabricator / Erector Day 11.00 289.67 3186.32
5 Gas cutter Day 4.00 289.67 1158.66
6 Welder ( General ) Day 11.00 289.67 3186.32
7 Helper fabrication / erection Day 32.00 274.67 8789.28
8 Helper for cleaning / painting Day 4.00 274.67 1098.66
9 Painter Cl - II Day 6.00 274.67 1647.99
10 Electrician Day 1.00 276.17 276.17
Total `: 22233.38
Add for small Tools and Plants @ 1% `: 222.33
Add for Contractor's Profit @ 10% `: 2223.34
Add for hidden cost on Labour @ 15% `: 3335.01
Add for additional hidden cost on labour @ 15% `: 3335.01
Add for Contractor's Overheads @ 5% `: 1111.67
Total cost of Labour : `: 32460.73
ABSTRACT:
A. Cost of Materials `: 111056.95
B. Hire charges of Machinery `: 15638.94
C. Cost of Labour `: 32460.73
TOTAL `: 159156.62
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 2972.56
Add for insurance charges @ 1.00% `: 1591.57
Add for designs and drawings @ 2.50% `: 3978.92
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 3978.92
Add for power supply arrangements @ 2.00% `: 3183.13
Add for enabling works @ 1.50% `: 2387.35
Total `: 177249.06
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 1.322 tonnes @ `: 247.10 / tonne `: 653.33
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 9 ) @ 3.00% `: 1134.82
Total cost for 1.322 tonne `: 179037.21
Rate per tonne `: 135429.05
Rate approved per tonne `: 135400.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.36
ITEM: Design, fabrication, supply, erection and commissioning of trash racks consisting of a number
of panels of suitable height with vertical trash bars welded to structural steel frame at wider
interval and provided with weld mesh frame for pump house intake structure including cost
of all materials, machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning,
applying one coat of zinc rich epoxy primer and four coats of cold applied coal tar epoxy paint
etc., complete as per specifications and approved drawings with lead upto 1 km and all lifts
173
GATE / HOIST AND ALLIED WORKS
for structural steel components and all leads and lifts including packing / forwarding
charges for other materials.
DATA:Tracsh rack consists of a number of panels of suitable size. Each panel consists of structural
steel frame with horizontal stiffeners at interval and vertical trash bars at closer or wider interval.
Where the trash bars are spaced at wider interval a weld mesh frame is attached to main frame.
Consider trash rack panels for pump house intake structure for 3.55 m wide vent opening.
Length of each panel : 3.75 m
Height of each panel : 2.70 m
Number of panels for one vent : 3.00 Nos
Total height of trash rack ( 3 x 2.70 ) : 8.10 m
Head of water : 7.50 m
Weight of trash rack in tonnes based on empirical formula :
2 0.716
= 0.0375 x ( L x H x h )
Where ( L ) is length and ( H ) is total height and ( h ) is head of water in metres.
= 0.0375 x ( 3.75 x 3.75 x 8.1 x 7.5 ) 0.716 : 4.710 tonnes
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of trash rack panels for 1 vent for pump house intake
structure having same vent size provided for one of the pump house.
Actual weight of embedded parts as per data in Item :36 of Annexure-2 : 4.686 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of trash rack
provided for one vent of one of the pump house intake structure.
structure ( for details refer Item : 36 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5% wastage ( 3246.1x1.025 ) : 3327 kg
Plates / flats with 2.5 % wastage ( 1359.3 x 1.025 ) : 1393 kg
b. Weld mesh (2 mm dia 25x25 mm opening ) ( 3.44x2.7x3x1.025 ) : 28.50 sqm
c. Bolt / Nut / Washer conforming to IS : 1363 :
GI bolts / Nuts / Washers with 2.5 % wastage ( 6.7 x 3 x 1.025 ) : 20.6 kg
d. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:36 Annexure-2 ) : 1488 Nos
Add for variations / wastage / misc welding @ 10 % ( 1488 x 0.1 ) : 149 Nos
Total requirement of GP / LH electrodes : 1637 Nos
for stitch welding GP electrodes @t 10 % of total ( 1637 x 0.10 ) : 164 Nos
for run welding LH electrodes @ 90 % of total ( 1637 x 0.90 ) : 1473 Nos
2. Cutting :
Total length of cutting assuming cutting for 2 sides as per data sheet : 76 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 8 Rm
Total : 84 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
As the work involves use angles / channels / beams cutting using cutting torch is considered.
Length of steel to be cut by using gas manually : 84 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 42 hours
Acetelyne gas @ 0.6 cum / hour ( 42 ) x 0.60 : 25 cum
Oxygen gas @ 1.8 cum / hour ( 42 ) x 1.80 : 75 cum
Use of gas cutting torch with 50 min / hr working ( 42 x 60 / 50 ) : 50 hours
174
GATE / HOIST AND ALLIED WORKS
3. Welding :
Length of welding as per data sheet : 149 m
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 164 x 8 / 15 / 2 ) : 44 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 1473 x 8 / 15 / 6 ) : 131 hours
Total : 175 hours
Deploy welding transformer for 175 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 44 x 0.25 + 131 x 0.75 ) : 109 hours
4. Surface cleaning and painting :
Painting area for trash rack panels at 30 sqm / tonne ( 4.686 x 30 ) : 140 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 140 sqm @ 9 sqm / ltr / coat : 16.0 ltr
4 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 140 sqm @ 6 sqm / ltr / coat : 94 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 140 sqm @ 8 sqm / ltr : 18 ltr
For handling parts during fabrication and erection use 8 t mobile crane for 8 hours.
For drilling holes for fixing bolts use drilling machine for 8 hours.
For finishing weld joints / edges 4 hours use of grinding machine considered.
6. Requirement of work force :
Work component Foreman Marker / Gas cutter / Helper /
Fabricator / Welder Painter Cl-II
Erector /
Cutting sections 50 hours 1 6 6 12
Fabricating by stitch welding 39 hours 2 5 --- 10
Run welding 131 hours 2 --- 16 16
Erection of panels 1 2 --- 4
Cleaning surface 140 sqm @ 15 sqm/day --- --- --- 10
Painting ( 5 x 140 ) sqm @ 15 sqm / day --- --- --- 59
Finishing / cleaning --- 1 --- 1
Total : 6 14 22 112
Note : a. It is assumed that all stitch welding will be done by fabricator. Hence, no separate provision
is considered for welder for stitch welding.
b. Workforce for painting 1 coat primer and 4 coats finishing paint consists of 47 Painters Cl-II
at 15 sqm / day and 12 helpers to assist painters.
7. Excise duty on supply :
Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
8. Use rate of materials :
Cost of welding set @ `: 6750.00 / Each `: 6750.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) `: 6.75
Cost of gas cutting set @ `: 2250.00 / Each `: 2250.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) `: 3.75
175
GATE / HOIST AND ALLIED WORKS
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Welding transformer Hour 175.00 13.00 2275.00
Fuel / Energy charges Hour 109.00 86.00 9374.00
2 Mobile crane 8 t Hour 8.00 412.00 3296.00
Fuel / Energy charges Hour 8.00 718.00 5744.00
3 Drilling machine Hour 4.00 20.00 80.00
Fuel / Energy charges Hour 4.00 36.00 144.00
4 Grinding machine Hour 8.00 20.00 160.00
Fuel / Energy charges Hour 8.00 36.00 288.00
5 Sundries LS 15.00 45.00 675.00
Total `: 22036.00
Add for small Tools and Plants @ 1% `: 220.36
Add for Contractor's Profit on DPOL / Energy @ 10% `: 1622.50
Add for Contractor's Overheads @ 5% `: 1101.80
Total hire charges of Machinery : `: 24980.66
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in `: in `:
1 Crew for Mobile crane Hour 8.00 144.00 1152.00
2 Crew for Drilling machine Hour 4.00 111.00 444.00
Contd
176
GATE / HOIST AND ALLIED WORKS
C. LABOUR ( Contd ):
Sl No Description Unit Quantity Rate Amount
in `: in `:
Contd
3 Crew for Grinding machine Hour 8.00 111.00 888.00
4 Foreman Day 6.00 311.67 1869.99
5 Marker / Fabricator / Erector Day 14.00 289.67 4055.31
6 Gas cutter Day 6.00 289.67 1737.99
7 Welder ( General ) Day 16.00 289.67 4634.64
8 Helper fabrication / erection Day 43.00 274.67 11810.60
9 Helper for cleaning / painting Day 22.00 274.67 6042.63
10 Painter Cl - II Day 47.00 274.67 12909.26
11 Electrician Day 1.00 276.17 276.17
Total `: 45820.58
Add for small Tools and Plants @ 1% `: 458.21
Add for Contractor's Profit @ 10% `: 4582.06
Add for hidden cost on Labour @ 15% `: 6873.09
Add for additional hidden cost on labour @ 15% `: 6873.09
Add for Contractor's Overheads @ 5% `: 2291.03
Total cost of Labour : `: 66898.04
ABSTRACT:
A. Cost of Materials `: 344076.24
B. Hire charges of Machinery `: 24980.66
C. Cost of Labour `: 66898.04
TOTAL `: 435954.94
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% `: 5678.10
Add for insurance charges @ 1.00% `: 4359.55
Add for designs and drawings @ 2.50% `: 10898.87
Add for zigs / supports / winches / chain-pulley @ 2.50% `: 10898.87
Add for power supply arrangements @ 2.00% `: 8719.10
Add for enabling works @ 1.50% `: 6539.32
Total `: 483048.76
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 4.686 tonnes @ `: 247.10 / tonne `: 2315.82
Add for packing, forwarding and transportation upto work site on cost of materials
other than structural steel ( on cost of Sl No. 2 to 11 ) @ 3.00% `: 2932.84
Total cost for 4.686 tonne `: 488297.42
Rate per tonne `: 104203.46
Rate approved per tonne `: 104200.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.37
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts consisting of
sill beam, wheel tracks, seal seats, guide rails, gate groove liners etc., with all accessories
for pump house intake stoplog gate including cost of all materials, machinery, labour,
cutting, aligning, anchoring, welding, finishing, cleaning, applying one coat zinc rich epoxy
primer and four coats of cold applied coal tar epoxy paint etc., complete as per specifications
177
GATE / HOIST AND ALLIED WORKS
and approved drawings with lead upto 1 km and all lifts for structural steel components
and all leads and lifts including packing / forwarding charges for other materials.
DATA:The nature of work involved is similar to the embedded parts for stoplog gate proposed for canal
regulator stop-log gate under ' Gate / Hoist and allied works '. Therefore same unit rate as
proposed under ' Gate / Hoist and allied works ' is proposed for this item.
Item : 33 Gate / Hoist and allied works Rate per tonne `: 142900.00
2 0.716
Note: Wt of 1 set of embedded parts in tonnes = 0.0665 x ( L x H x h )
Where ( L ) is length = Clear distance between piers in m + 0.50 m.
( H ) is total height of stoplog gate in m = FSL - Sill level + 0.30 m
( h ) is head of water above sill of gate in m = FSL - Sill level
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.38
ITEM: Design, fabrication, supply, erection, testing and commissioning of sliding type stoplog gate
consisting of skin plate, horizontal and vertical girders, lifting hooks, bronze padded slide blocks,
stiffeners, guide shoes, rubber seals etc., with all accessories for pump house intake vent
including cost of all materials, machinery, labour, cutting, aligning, welding, finishing, cleaning,
applying one coat of zinc rich epoxy primer and three coats of cold applied coal tar epoxy
paint, seal fixing etc., complete as per specifications and approved drawings with lead upto
1 km and all lifts for structural steel components and all leads and lifts including
packing / forwarding charges for other materials.
DATA:The nature of work involved is similar to the stoplog gate proposed for canal regulator under
under ' Gate / Hoist and allied works '. Therefore same unit rate as proposed under ' Gate /
Hoist and allied works ' is proposed for this item.
Item : 34 Gate / Hoist and allied works Rate per tonne `: 129000.00
2 0.716
Note: Wt of 1 stoplog gate in tonnes = 0.0995 ( L x H x h )
Where ( L ) is length = Clear distance between piers in m + 0.50 m.
( H ) is total height of stoplog gate in m = FSL - Sill level + 0.30 m
( h ) is head of water above sill of gate in m = FSL - Sill level
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.39
ITEM: Design, fabrication, supply, erection and commissioning of electrically operated mono-rail
hoist assembly consisting of electric motor, rope drum, gear system, wire rope with lifting
attachment, festoon cabling etc., with all accessories for operating pump house stop-log
gate including cost of all materials ( excluding providing mono-rail hoist supporting structure
and mono-rail with fixtures ), machinery, labour, cleaning, greasing etc., complete as per
specifications and approved drawings with all leads and lifts.
178
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.40
ITEM: Design, fabrication, supply, erection and commissioning of structural steel hoist supporting
structure consisting of columns, cross beams, bracings, stiffeners, mono-rail with fixtures etc.,
with all accessories for electrically operated mono-rail rope drum hoist for operating
pump house intake vertical lift gate including cost of all materials, machinery, labour,
cutting, aligning, anchoring, welding, finishing, cleaning, applying two coats of zinc chromate
red primer and three coats of synthetic enamel paint etc., complete as per specifications and
approved drawings with lead upto I km and all lifts for structural steel components and
all leads and lifts including packing / forwarding charges for other materials.
DATA:The nature of work involved is similar to the hoist supporting structure proposed for barrage gate
rope drum hoists under ' Gate / Hoist and allied works '. Therefore same unit rate as proposed
under ' Gate / Hoist and allied works ' is proposed for this item.
Item : 21 Gate / Hoist and allied works Rate per tonne `: 105800.00
Note: i. Columns with bracings/anchors/stiffeners:
150 kg per metre height.
ii. Weight proposed above is for each intake vent
iii. Mono rail beam with cross beams 100: kg per metre length
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2016-17 ITEM No: WRD: 7.41
ITEM: Design, fabrication, supply, erection, testing and commissioning EOT crane consisting of
double girder box type construction, rail mounted end carraiges with long and cross travel
arrangement, main and auxiliary hoists of specified capacity, rails, pendant control, gear
boxes, electric motors, brakes, rope drums, wire ropes, sheaves, end buffer stoppers, pendant
operated DSL bus bars with all accessories for main and auxiliary hoists for handling pumps
and accessories in pump house including cost of all materials, machinery, labour, cutting,
aligning, welding, finishing, cleaning, greasing, applying two coats of zinc chromate red oxide
primer and three coats of synthetic enamel paint etc., complete as perspecifications and
approved drawings with all leads and lifts .
DATA:The basic requirements of EOT crane are similar to out door moving gantry crane except for
gantry portal legs. The reduction in quantity of portal legs is assumed to off-set to some extent
increase in span for EOT crane base frame and cost of additional auxiliary hoist.
Therefore, similar rate per tonne capacity as provided for out-door moving gantry crane with
about 25 percent reduction per tonne capacity is proposed for EOT crane.
Rate per tonne capacity ( vide Item: 8 under ' Gates & Hoists ' )
EOT crane Rate / tonne hoist capacity `: 173200.00
Note: i. EOT crane Main hoist capacity = 1.25 x Maximum lifting load(round off to next 5 t)
ii. EOT crane Auxiliary hoist capacity = Approximately 10 % of main hoist capacity
iii. Rate for EOT crane shall be based on capacity of main hoist.
179
GATE / HOIST AND ALLIED WORKS
GATE / HOIST AND ALLIED WORKS
ANNEXURE-1
ENABLING WORKS
180
GATE / HOIST AND ALLIED WORKS
ITEM: Provision for Electric sub-station / Demand charges / Lighting fabrication & work areas :
DATA:Generally, contracts provide for arranging HT / LT electric power line within about 1 km distance
from work site by the department. From the departmental bulk supply point laying of further
transmission lines, erection of sub-station, erecting distribution lines and other arrangements
for power supply to various installations will be the responsibility of the contractors requiring
electric power for their works.
For gate / hoist works, generally, cutting / bending / welding operations for most of the parts
are carried out at the contractor's central fabrication yard and fabrcated parts along with the
bought out parts are transported to site of work. Fabrication of some matching parts and minor
modifications to shop fabricated parts / erection / field welding / commissioning are carried out
at specified work site. Therefore, electric power supply arrangements are necessary both at
central fabrication place and erection / commissioning place for gate / hoist works.
Estimation of electric power load for sub-station for gate / hoist works:
Fabrication Erection
place ( in hp ) place ( in hp )
Plate shearing machine 20.00 ---
Bending machine 15.00 15.00
Pug cutting machine 4.00 2.00
Planing machine 15.00 ---
Drilling machine 5.00 5.00
Grinding machine 5.00 5.00
Welding transformers 120.00 120.00
Work shop equipments / miscellaneous 20.00 20.00
Total : 204.00 167.00
Requirement of power in Kw 152.184 124.58
Add for lighting fabrication area & trial running etc @ 5 % 7.61 ---
Add for lighting erection areas & trial running etc @ 10 % --- 12.46
Add for lighting & domestic use for camp @ 5 % 0.00 6.23
Add for reserve capacity @ 5 % 7.61 6.23
Total : 167.40 149.50
Capacity of sub-station required hp / 0.85 196.94 175.88
say : 200 kVA 175 kVA
For working out demand charges sanctioned power requirement is assumed to vary from
100 KVA to 200 kVA ( average 150 kVA ) for fabrication place and from 75 kVA to 175 kVA
( average 125 kVA ) for erection site.
Av. demand for electric power is considered for 2 years each for fabrication and erection sites.
Consider 1 Transformer of 250 KVA at each place.
Capital cost of other sub-station equipments & distribution lines:( for each place )
HT / LT Circuit breaker 3 Nos @ `: 41609.00 / Each `: 124827.00
Poles with fixtures 10 Nos @ `: 6047.00 / Each `: 60470.00
HT / LT Line conductor 2 km @ `: 47000.00 / km `: 94000.00
Other accessories / controls / junctions LS `: 45000.00
Total `: 324297.00
Life of sub-station equipments ( average ) : 20 years
Salvage value : 10 percent
Maintenance & Repairs as % of Capital cost : 25 percent
Miscellaneous charges as % of Repair charges : 10 percent
181
GATE / HOIST AND ALLIED WORKS
182
GATE / HOIST AND ALLIED WORKS
Running 50 KVA DG set is assumed for 1 hour daily for fabrication place and 2 hours daily for
erection site to ensure minimum power supply for lighting and works during break down of main
power supply from grid.
183
GATE / HOIST AND ALLIED WORKS
ABSTRACT:
A. Cost of Materials `: 919660.30
B. Hire charges of Machinery `: 3848112.92
C. Cost of Labour `: 1227842.25
D. Cost of enabling works `: 733737.00
TOTAL `: 6729352.46
Less requirement for camp use at site @ 5% ( - ) `: -336467.62
Total cost for work 1.00 No. `: 6392884.84
Approximate quantity of gate / hoist work is assumed at 2000 tonnes.
As radial gates are major components of work, the basic unit rates worked out for radial gate
and hoist are considered for estimating the approximate cost of gate / hoist works.
The quantity distribution for embedded parts / gate / hoist is assumed as under:
Embedded parts with all accessories : 260 tonnes
Gates with all accessories : 1460 tonnes
Hoists with all accessories : 280 tonnes
Total : : 2000 tonnes
Basic cost of embedded parts / tonne `: 1683305 / 14.334 ( Item-1) `: 117434.45
Basic cost of radial gate / tonne `: 8635666 / 57.457 ( Item-2) `: 150297.90
Basic cost of radial gate hoist / tonne `: 3525600 / 15.440 ( Item-3) `: 228341.99
Total cost of embedded parts / gates / hoists:
Total cost of embedded parts 117434.45 x 260 `: 30532958
Total cost of gates 150297.90 x 1460 `: 219434935
Total cost of hoists 228341.99 x 280 `: 63935758
Total `: 313903650
184
GATE / HOIST AND ALLIED WORKS
Cost of power supply arrangements including lighting and demand charges as percentage of
basic cost of embedded parts / gates / hoists works out to:
6392884.84 x 100 / 313903650 : 2.04
say : 2.00
DATA:Stores / work shop / guarage / fuel depot / power supply arrangements / lighting / sheds for
plant and machinery are necessary both at main fabrication place and field erection place for
gate / hoist and allied works. Plant and machinery required for field erection works require
transportation / erection / dismantling / re-transportation to main work shop or else where.
The cost of enabling works at fabrication place is ignored as the aportioned cost is negligible
in view of long duration use of these enabling works.
This data rate is for other enabling works for erection / commissioning of gate / hoists works.
1 Store for boughtout items 100 sqm @ `: 6750.00 / sqm `: 675000.00
2 General store 100 sqm @ `: 7875.00 / sqm `: 787500.00
3 Work shop 100 sqm @ `: 7875.00 / sqm `: 787500.00
4 Guarage 75 sqm @ `: 5625.00 / sqm `: 421875.00
5 Sheds for machinery 150 sqm @ `: 5625.00 / sqm `: 843750.00
6 Fuel depot 25 sqm @ `: 6750.00 / sqm `: 168750.00
7 Site levelling / field offices etc LS `: 225000.00
8 Local haul roads / fensing store yard etc LS `: 225000.00
Total `: 4134375.00
Add interest for 1 years @ 11% `: 454781.25
Add for maintenance for 2 years @ 2.00% `: 82687.50
Less salvage value @ 25 % for ( 1 ) to ( 6 ) ( - ) `: -921093.75
Total ( A ) `: 3750750.00
Transportation / Erection / Dismantling of plant & machinery for erection:
Bending machine / derric cranes / welding transformers / D.G. set / work shop equipments
are the major plant & machinery requiring erection and dismantling services at work site.
Capital cost of equipments for field erection works:
1 Stationery derric cranes 2 Nos `: 1105562
2 Mobile crane 8 t 1 No `: 1179663
Mobile crane 25 t 1 No `: 18562308
3 Welding transformers 10 Nos `: 390640
4 Truck 1 No ( exclusive transportation not considered ) `: 0
5 Bending machine 1 No. `: 540189
6 D.G set 50 kVA 1 No. `: 782107
7 Transformer 250 kVA 1 No. `: 328303
8 Work shop equipments / fuel pump / Misc LS `: 225000
Total `: 23113772
Transportation to site for ( 1 ) to ( 8 ) @ 1.50% `: 346706.58
Erection cost for ( 5 ) to ( 8 ) @ 6.00% `: 112535.94
Total `: 459242.52
Add interest for 1 year @ 11% `: 50516.68
Add dismantling cost for ( 5 ) to ( 8 ) @ 3.00% `: 56267.97
Add transportation from site for ( 1 ) to ( 8 ) 1.50% `: 346706.58
Total ( B ) `:
Total( 912733.75
185
GATE / HOIST AND ALLIED WORKS
186
GATE / HOIST AND ALLIED WORKS
ANNEXURE-2
DETAILS OF
MATERIALS / CUTTING / WELDING
187
GATE / HOIST AND ALLIED WORKS
188
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 679.00 kg
Structural steel Plates / Flats : 13356.00 kg
2. Alloy steel components : IS : 1570
Stainless steel plates / flats : 190.00 kg
3. Bolt / Nut / Washer : IS : 1363
MS Bolts / Nuts / Washers : 109.00 kg
189
GATE / HOIST AND ALLIED WORKS
4. Other details :
Length of cutting : 428.10 Rm
Length of welding : 600.00 Rm
Number of electrodes ( for structural steel ) : 7539 Nos
Number of electrodes ( for stainless steel ) : 876 Nos
190
GATE / HOIST AND ALLIED WORKS
191
GATE / HOIST AND ALLIED WORKS
192
GATE / HOIST AND ALLIED WORKS
193
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 15421.00 kg
Plates / Flats : 37729.00 kg
2. Cast steel components : IS : 1030
Trunnion hub / Guide roller : 1895.00 kg
3. Alloy steel components : IS : 1570
SS plates / Flats : 6.00 kg
Pins : 1098.00 kg
194
GATE / HOIST AND ALLIED WORKS
195
GATE / HOIST AND ALLIED WORKS
196
GATE / HOIST AND ALLIED WORKS
197
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 2508.00 kg
Plates / Flats : 3543.00 kg
2. Cast steel components : IS : 1030
Rope drums 2 Nos / Gears 4 Nos : 3680.00 kg
Pinions : 218.00 kg
Pulleys 720 PCD 6 Nos : 1080.00 kg
Plummer blocks / Hubs : 322.00 kg
3. Alloy steel steel components : IS : 1570
Shafts : 557.00 kg
Pins : 546.00 kg
4. Alluminium/ Bronze alloy components : IS : 305
Bearings / Bush : 144.00 kg
Bolt / Nut / Washers IS : 1363
MS Bolts / Nuts / Washers : 83.00 kg
5. Wire rope : IS : 2266
36 mm dia 6 / 37 construction 2 Nos : 100 Rm
6. Other components :
Manual operating system : 1 No.
Elecon gears : 2 Nos
Electric motor 20 hp : 1 No.
Gate position indicator : 1 No.
Ele-magnetic brake : 1 No.
MS pipe 300 mm dia : 13.32 Rm
7. Other details :
Length of cutting : 254.60 Rm
198
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 4154.00 kg
Structural steel plates / flats : 96.00 kg
2. Chequered plates : 835.00 kg
3. Bolts / Nuts / Washers : IS : 1363
MS Bolts / Nuts / Washers : 8.00 kg
4. Other components :
MS pipes 32 mm dia : 71.60 Rm
5. Other details :
Length of cutting : 57.2 Rm
Length of welding : 150.7 Rm
Number of electrodes ( for structural steel ) : 1387 Nos
199
GATE / HOIST AND ALLIED WORKS
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
200
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 421.00 kg
Plates / Flats : 2245.00 kg
2. Alloy steel components : IS : 1570
SS plates for wheel track : 235.00 kg
SS plates for seal seat : 166.00 kg
3. Bolts / Nuts / Washers : IS : 1363
MS Bolts / Nuts / Washers : 112.00 kg
4. Other details :
Length of cutting : 163.00 Rm
Length of welding : 303.00 Rm
Number of electrodes ( for structural steel ) : 1973 Nos
Number of electrodes ( for stainless steel ) : 1095 Nos
201
GATE / HOIST AND ALLIED WORKS
202
GATE / HOIST AND ALLIED WORKS
203
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bar : 13.00 kg
Plates / Flats : 3306.00 kg
2. Alloy steel components : IS : 1570
Pin : 101.00 kg
3. Forged steel components : IS : 2004
Hook : 103.00 kg
4. Alluminium / Bronze alloy components : IS : 305
Bush : 5.00 kg
5. Bolts / Nuts / Washers IS : 1363
MS Bolts / Nuts / Washers : 3.00 kg
6. Other details :
Length of cutting : 172.40 Rm
Length of welding : 210.90 Rm
Number of electrodes ( for structural steel ) : 2121 Nos
Note : 1. Data based on fabrication drawings of 25 t moving gantry crane for operating the stoplog
gate elements provided for Alamatti dam spillway under Upper Krishna Project in Karnataka.
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard weiding tables.
204
GATE / HOIST AND ALLIED WORKS
205
GATE / HOIST AND ALLIED WORKS
206
GATE / HOIST AND ALLIED WORKS
207
GATE / HOIST AND ALLIED WORKS
208
GATE / HOIST AND ALLIED WORKS
209
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 1700.00 kg
Plates / Flats : 19219.00 kg
Chequered plate for platform covering : 800.00 kg
2. Cast steel components : IS : 1030
Rope drums : 1320.00 kg
Gears : 1016.00 kg
Wheels with retainers : 1980.00 kg
Pinions : 149.00 kg
Pulley / sheave : 275.00 kg
Plummer blocks / Bearing journals : 508.00 kg
Couplings / Sleeves : 309.00 kg
3. Alloy steel components : IS : 1570
Pins : 524.00 kg
Shafts : 556.00 kg
4. Forged steel components : IS : 2004
Hook : 127.00 kg
5. Alluminium / Bronze alloy components : IS : 305
Bearings / Bushes : 181.00 kg
6. Wire rope : IS : 2266
28 mm dia 6/37 construction : 150 Rm
7. Bolts / Nuts / Washers : IS : 1363
MS Bolts / Nuts / Washers : 61.00 kg
8. Other components :
Electric motor 3 hp : 1 No.
Electric motor 5 hp : 2 Nos.
Electric motor 17.5 hp : 1 No.
Worm reducer : 4 Nos
Brakes 4 Nos : 4 Nos
Pipe 32 mm dia for railing / ladder : 50 Rm
9. Other details :
Length of cutting : 760.60 Rm
Length of welding : 1260.00 Rm
Number of electrodes ( for structural steel ) : 16651 Nos
210
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 1531.00 kg
Plates / Flats : 951.00 kg
2. Bolts / Nuts / Washers : IS : 1363
MS Bolts / Nuts / Washers : 240.00 kg
3. Other components :
Rails 45 kg / m : 18000.00 kg
4. Other details :
Length of cutting : 222.30 Rm
Length of welding : 209.90 Rm
Number of electrodes ( for structural steel ) : 1710 Nos
Item: Embedded parts without groove lining for river / canal sluice service gate :
Details of materials / Gas cutting / Welding for rate analysis :
Note : 1. Data based on emedded parts ( with out groove liner ) fabrication drawings for river sluice
service gate provided for Tunga dam under Upper Tunga Project in Karnataka.
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard weiding tables.
211
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 588.00 kg
212
GATE / HOIST AND ALLIED WORKS
Item: Embedded parts with groove lining for river / canal sluice service gate :
Details of materials / Gas cutting / Welding for rate analysis :
Note : 1. Data based on emedded parts ( with groove liner ) fabrication drawings for river sluice service
gate provided for Kodasalli dam under Kali Stage- II Project in Karnataka.
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
213
GATE / HOIST AND ALLIED WORKS
214
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 681.00 kg
Plates / Flats : 8971.00 kg
2. Alloy steel components : IS : 1570
Stainless steel plates : 825.00 kg
3. Bolt / Nut / Washer : IS : 1363
MS Bolt / Nut / Washer : 180.00 kg
4. Other details :
Length of cutting : 301.00 Rm
Length of welding : 552 Rm
Number of electrodes ( for structural steel ) : 5569 Nos
Number of electrodes ( for stainless steel ) : 457 Nos
215
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Plates / Flats : 7281.00 kg
2. Other details :
Length of cutting : 203 Rm
Length of welding : 420 Rm
Number of electrodes ( for structural steel ) : 4194 Nos
216
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Plates / Flats : 4370.00 kg
217
GATE / HOIST AND ALLIED WORKS
Item: Rope drum hoist for river / canal sluice service gate :
Details of materials / Gas cutting / Welding for rate analysis :
Note : 1. Data based on fabrication drawings of 25 t rope drum hoist provided for operating river sluice
service gate of Kodasalli dam under Kali Stage- II Project in Karnataka.
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
218
GATE / HOIST AND ALLIED WORKS
219
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 1451.00 kg
Plates / Flats : 392.00 kg
Chequered plate for platform covering : 283.00 kg
2. Cast steel components : IS : 1030
Rope drums 2 Nos : 1420.00 kg
Gears 3 Nos : 506.00 kg
Pinions : 79.00 kg
Pulleys 3 Nos / Couplings 2 Nos : 306.00 kg
Plummer blocks : 72.00 kg
3. Alloy steel components : IS : 1570
Shafts : 346.00 kg
Pins : 73.00 kg
4. Alluminium / Bronze alloy components : IS : 305
Bearings / Bushes : 57.00 kg
5. Wire rope : IS : 2266
28 mm dia 6/37 construction rope : 120 Rm
6. Bolts / Nuts / Washers : IS : 1363
Bolts / Nuts / Washers ( various size ) : 31.00 kg
7. Other components :
Electric motor 5 hp Standard : 1 No.
Worm reducer Standard : 1 No
220
GATE / HOIST AND ALLIED WORKS
Item: Embedded parts without groove lining for river / canal sluice emergency gate :
Details of materials / Gas cutting / Welding for rate analysis :
Note : 1. Data based on fabrication drawings of emedded parts ( with out groove liner ) for river sluice
emergency gate provoded for Tunga dam under Upper Tunga Project in Karnataka.
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
221
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 593.00 kg
Plates / Flats : 1304.00 kg
2. Alloy steel components : IS : 1570
Stainless steel plates : 219.00 kg
3. Bolt / Nut / Washer : IS : 1363
MS Bolt / Nut / Washer : 64.00 kg
4. Other details :
Length of cutting : 135 Rm
Length of welding : 143 Rm
Number of electrodes ( for structural steel ) : 933 Nos
Number of electrodes ( for stainless steel ) : 430 Nos
Item: Embedded parts with groove lining for river / canal sluice emergency gate :
Details of materials / Gas cutting / Welding for rate analysis :
Note : 1. Data based on emedded parts ( with groove liner ) fabrication drawings for river sluice
emergency gate provided for Kodasalli dam under Kali Stage- II Project in Karnataka.
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
222
GATE / HOIST AND ALLIED WORKS
223
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 992.00 kg
Plates / Flats : 7431.00 kg
2. Alloy steel components : IS : 1570
Stainless steel plates : 431.00 kg
3. Bolt / Nut / Washer : IS : 1363
MS Bolt / Nut / Washer : 234.00 kg
4. Other details :
Length of cutting : 301 Rm
Length of welding : 560 Rm
Number of electrodes ( for structural steel ) : 5256 Nos
Number of electrodes ( for stainless steel ) : 752 Nos
224
GATE / HOIST AND ALLIED WORKS
225
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Plates / Flats : 4301.00 kg
2. Cast steel components : IS : 1030
Wheels / Guide roller : 492.00 kg
3. Alluminium / Bronze alloy components : IS : 305
Bearings / Bushes : 76.00 kg
4. Alloy steel components : IS : 1570
Wheel axle / lifting pin : 144.00 kg
5 Rubber seals : IS : 11855
Bottom rubber seal ( uncladed ) : 2.76 Rm
Side rubber seal ( teflon claded ) : 5.71 Rm
Top rubber seal ( teflon claded ) : 2.20 Rm
Corner seal : 2 Nos
6. Bolt / Nut / Washer IS : 1363
SS Bolt / Nut / Washer : 54.00 kg
GI Bolt / Nut / Washer : 144.00 kg
MS Bolt / Nut / Washer : 4.00 kg
7. Other components :
CI counter weight : 4000.00 kg
8. Other details :
Length of cutting : 134.10 Rm
Length of welding : 271.30 Rm
Number of electrodes ( for structural steel ) : 3017 Nos
226
GATE / HOIST AND ALLIED WORKS
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 228.00 kg
Plates / Flats : 476.00 kg
2. Forged steel components IS : 2004
Lifting hooks : 130.00 kg
227
GATE / HOIST AND ALLIED WORKS
228
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 588.00 kg
Structural steel Plates / Flats : 3685.00 kg
2. Alloy steel components : IS : 1570
Stainless steel plates / flats for track : 620.00 kg
Stainless steel plates / flats for seal seat : 133.00 kg
3. Bolt / Nut / Washer : IS : 1363
MS Bolts / Nuts / Washers : 167.00 kg
4. Other details :
Length of cutting : 210.00 Rm
Length of welding : 251.40 Rm
Number of electrodes ( for structural steel ) : 1734 Nos
Number of electrodes ( for stainless steel ) : 1282 Nos
229
GATE / HOIST AND ALLIED WORKS
230
GATE / HOIST AND ALLIED WORKS
231
GATE / HOIST AND ALLIED WORKS
232
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 3299.00 kg
Plates / Flats : 28655.00 kg
2. Cast steel components : IS : 1030
Wheels / Guide roller : 656.00 kg
3. Alluminium / Bronze alloy components : IS : 305
Bearings / Bushes : 80.00 kg
4. Alloy steel components : IS : 1570
Wheel axle / lifting pin : 176.00 kg
5. Rubber seals : IS : 11855
Bottom rubber seal ( uncladed ) : 14.00 Rm
Side rubber seal ( uncladed ) : 17.20 Rm
6. Bolt / Nut / Washer IS : 1363
GI Bolt / Nut / Washer : 91.00 kg
MS Bolt / Nut / Washer : 68.00 kg
7. Other details :
Length of cutting : 694.50 Rm
Length of welding : 1837.10 Rm
Number of electrodes ( for structural steel ) : 18400 Nos
233
GATE / HOIST AND ALLIED WORKS
234
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 4453.00 kg
Structural steel Plates / Flats : 5431.00 kg
Chequered plate : 133.00 kg
2 Bolt / Nut / Washer : IS : 1363
MS Bolts / Nuts / Washers : 18.00 kg
MS pipes :
32 mm dia pipe : 30.86 Rm
25 mm dia pipe : 61.72 Rm
3 Other details :
Length of cutting : 290.20 Rm
Length of welding : 473.10 Rm
Number of electrodes ( for structural steel ) : 4731 Nos
235
GATE / HOIST AND ALLIED WORKS
236
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 410.00 kg
Plates / Flats : 219.00 kg
2. Cast steel components : IS : 1030
Rope drums 2 Nos / Gears : 1290.00 kg
Pinions : 98.00 kg
Pulleys 8 Nos / Couplings 2 Nos : 650.00 kg
Plummer blocks : 250.00 kg
3. Alloy steel components : IS : 1570
Shafts / Keys : 350.00 kg
Pins : 96.00 kg
4. Alluminium / Bronze alloy components : IS : 305
Bearings / Bushes : 100.00 kg
5. Wire rope : IS : 2266
28 mm dia 6/36 construction rope : 160 Rm
6. Bolts / Nuts / Washers : IS : 1363
Bolts / Nuts / Washers ( various size ) : 25.00 kg
7. Other components :
Electric motor 12.5 hp Standard : 1 No.
Worm reducer 60 :1 ( size 800 ) 1 No. Standard : 1 No
Electro-megnatic brake Standard : 1 No
Manual operation assembly : 1 No.
Position indicator : 1 No.
8. Other details :
Length of cutting : 37.30 Rm
Length of welding : 53.10 Rm
Number of electrodes ( for structural steel ) : 531 Nos
237
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS :2062
Angle / Channel / Beam / Bars 0.94059 : 760.00 kg
Plates / Flats : 3040.00 kg
2. Alloy steel components : IS : 1570
Stainless steel plates AISI-410 : 49.00 kg
Stainless steel plates AISI-304L : 62.00 kg
3. Bolt / Nut / Washer : IS :1363
MS Bolt / Nut / Washer : 129.00 kg
4. Other details :
Length of cutting : 168.00 Rm
Number of electrodes ( for structural steel ) : 133 Nos
Number of electrodes ( for stainless steel ) : 987 Nos
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 3122.00 kg
Plates / Flats : 7561.00 kg
2. Cast steel components : IS : 1030 94.23%
Trunnion hub / Guide roller : 443.00 kg
3. Alloy steel components : IS : 1570
Pins : 74.00 kg
Stainless steel plate : 49.00 kg
4. Alluminium / Bronze alloy components : IS : 305
Trunnion & Guide roller bush : 33.00 kg
5. Bolt / Nut / Washer IS :1363
SS Bolts / Nuts / Washers : 31.00 kg
MS Bolts / Nuts / Washers / Screws : 23.50 kg
6. Rubber seals : IS : 11855
Bottom seal : 8.00 Rm
Side seals : 8.00 Rm
238
GATE / HOIST AND ALLIED WORKS
7. Other details :
Length of cutting : 195.00 Rm
Length of welding : 196.00 Rm
Number of electrodes ( for structural steel ) : 6125 Nos
Number of electrodes ( for stainless steel ) : 150 Nos
Item: Hoisting and damping system for out-flow regulating automatic gate :
Details of materials / Gas cutting / Welding for rate analysis :
Note : 1. Data based on details made available by the designer of gate for 8.00 x 3.50 m size
out-flow regulating automatic gate.
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
3. Unless otherwise specified 5 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 1483.00 kg
Plates / Flats : 3712.00 kg
2. Cast steel components : IS : 1030 81.38%
Wheels / Trunnion hub : 76.00 kg
Trunnion / Guide roller : 443.00 kg
3. Alloy steel components : IS : 1570
Pins / Axles : 59.00 kg
Stainless steel plate : 435.00 kg
4. Alluminium / Bronze alloy components : IS : 305
Trunnion & Guide roller bearings / bush : 118.00 kg
50 NB pipe : 28.00 kg
5. Bolt / Nut / Washer IS :1363
SS Bolts / Nuts / Washers : 15.50 kg
MS Bolts / Nuts / Washers / Screws : 14.50 kg
6 Disc springs : 64 Nos
7. Other details :
Length of cutting : 124.00 Rm
Length of welding :
Number of electrodes ( for structural steel ) : 2911 Nos
Number of electrodes ( for stainless steel ) : 324 Nos
239
GATE / HOIST AND ALLIED WORKS
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
240
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS :2062
Angle / Channel / Beam / Bars : 812.00 kg
Plates / Flats : 1475.00 kg
2. Alloy steel components : IS : 1570
Stainless steel plates : 52.00 kg
3. Bolt / Nut / Washer : IS :1363
MS Bolt / Nut / Washer : 65.00 kg
4. Other details :
Length of cutting : 96.70 Rm
Length of welding : 142.30 Rm
Number of electrodes ( for structural steel ) : 1272 Nos
Number of electrodes ( for stainless steel ) : 185 Nos
241
GATE / HOIST AND ALLIED WORKS
241.00
Sl No. DESCRIPTION OF MATERIALS Weight Gas cutting Weld length Number of
in kg length in m in m electrodes
Contd
20 ISA 75x75x8 x 1400 mm 4 Nos 50.00 0.6 1.8 18
21 ISA 75x75x8 x 1900 mm 4 Nos 68.00 0.6 1.8 18
22 ISA 75x75x8 x 550 mm 4 Nos 20.00 0.6 1.8 18
23 Gusset pl 250x150x10 mm 4 Nos 12.00 1.6 1.6 16
24 Gusset pl 200x150x10 mm 4 Nos 10.00 1.4 1.4 14
25 Gusset pl 250x200x10 mm 4 Nos 16.00 1.8 1.8 18
26 Gusset pl 200x200x10 mm 4 Nos 13.00 1.6 1.6 16
27 Gusset pl 250x200x10 mm 4 Nos 16.00 1.8 1.8 18
28 Plate 280x160x20 mm 4 Nos 28.00 1.8 4.0 40
29 Plate 300x160x20 mm 4 Nos 30.00 1.8 4.0 40
30 Bolt/Nut/Washer 20 dia x 70 mm 24 Nos 12.00 --- --- ---
31 H-Girder ISMB 300 x 2900 mm 2 Nos 256.00 1.8 --- ---
32 Stiffener 70x320x20 mm 16 Nos 56.00 6.3 14.7 147
33 Plate 300x160x20 mm 4 Nos 30.00 1.8 3.7 37
34 Bolt/Nut/Washer 20 dia x 100 mm 24 Nos 15.00 --- --- ---
35 ISA 75x75x8 x 1994 mm 3 Nos 53.00 0.5 1.3 13
36 ISA 75x75x8 x 2150 mm 2 Nos 38.00 0.3 0.9 9
37 Gusset pl 200x200x10 mm 3 Nos 9.00 1.2 1.2 12
38 Gusset pl 240x200x10 mm 2 Nos 8.00 0.9 0.8 8
39 Gusset pl 300x200x10 mm 1 Nos 5.00 0.5 0.5 5
Skin plate assembly :
40 Skin plate 2880x4950x10 mm 1 No. 1119.00 12.8 5.0 50
41 Tee ISMB 250/2 x 4950 mm 6 Nos 554.00 14.9 59.4 594
42 Top plate 150x2880x10 mm 1 Nos 34.00 3.0 6.0 60
43 Stiffener 120x120x10 mm 14 Nos 16.00 3.4 6.7 67
44 Bottom pl 150x2880x10 mm 1 No. 34.00 3.0 3.8 38
45 Seal support 10x10x2880 1 No. 2.00 --- 5.8 58
46 Side clamp ISA 45x45x6x5000 mm 2 Nos 40.00 0.2 --- ---
47 Bottom clamp 70x2880x10 mm 1 No 16.00 3.0 --- ---
48 Z - seal 5000 mm 2 Nos --- --- --- ---
49 Flat seal 3000 mm 1 No. --- --- --- ---
50 Back plate 60x5000x10 mm 1 No. 24.00 --- 10.0 100
51 GI Bolt/Nut/Washer 12 dia x 50 mm 140 14.00 --- --- ---
Guide roller assembly :
52 Plates 48.00 5.2 2.9 29
53 Guide roller 4 Nos 30.00 --- --- ---
54 Bronze bush 4 Nos 6.00 --- --- ---
55 Pins 4 Nos 4.00 --- --- ---
56 GI Bolt/Nut/Washer 12 dia x 50 mm 16 2.00 --- --- ---
Pulley supports in gate :
57 Bracket pl 300x350x20 mm 4 Nos 66.00 2.7 5.2 52
58 Plate 160x400x6 mm 2 Nos 6.00 1.1 3.2 32
59 Plate 300x360x20 mm 2 Nos 34.00 1.3 1.9 19
60 Stiffener 70x150x10 mm 8 Nos 7.00 2.0 3.5 35
61 Stiffener 123x220x10 mm 4 Nos 9.00 1.4 2.8 28
4696.00 107.3 195.5 1955
Total : kg Rm Rm Nos
242
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 2161.00 kg
Plates / Flats : 2042.00 kg
2. Cast steel components : IS : 1030
Trunnion hub / Guide roller : 122.00 kg
3. Alloy steel components : IS : 1570
Pins : 41.00 kg
4. Alluminium / Bronze alloy components : IS : 305
Trunnion & Guide roller bush : 19.00 kg
5. Bolt / Nut / Washer IS :1363
GI Bolts / Nuts / Washers : 16.00 kg
MS Bolts / Nuts / Washers / Screws : 54.00 kg
6. Rubber seals : IS : 11855
Bottom seal : 3.00 Rm
Side seals : 10.00 Rm
7. Other details :
Length of cutting : 107.30 Rm
Length of welding : 195.50 Rm
Number of electrodes ( for structural steel ) : 1955 Nos
243
GATE / HOIST AND ALLIED WORKS
244
GATE / HOIST AND ALLIED WORKS
245
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 1238.00 kg
Plates / Flats : 531.00 kg
Chequered plate : 190.00 kg
2. Cast steel components : IS : 1030
Rope drums 2 Nos Gears 2 Nos : 384.00 kg
Pinions : 14.00 kg
Pulleys 6 Nos : 108.00 kg
Plummer blocks 6 Nos / couplings : 47.00 kg
3. Alloy steel components : IS : 1570
Shafts : 75.00 kg
Pins : 24.00 kg
4. Alluminium/ Bronze alloy components : IS : 305
Bearings / Bush : 10.50 kg
Bolt / Nut / Washers IS : 1363
MS Bolts / Nuts / Washers : 66.00 kg
5. Wire rope : IS : 2266
12 mm dia 6 / 36 construction 2 x 35 Rm : 40.00 kg
6. Other components :
Manual operating system : 1 No.
Worm reducer : 1 Nos
Electric motor 2 hp : 1 No.
Ele-magnetic brake : 1 No.
Rope socket with pin : 2 Nos
MS pipe 32 mm dia : 10.50 Rm
246
GATE / HOIST AND ALLIED WORKS
7. Other details :
Length of cutting : 85.50 Rm
Length of welding : 129.50 Rm
Number of electrodes ( for structural steel ) : 825 Nos
Item: Manually operated Rope drum hoist for regulator radial gate :
Details of materials / Gas cutting / Welding for rate analysis :
Note : 1. Data based on fabrication drawings of rope drum hoist without considering drive unit for cross
regulator radial gate for Alamatti Left Bank Canal under Upper Krishna Project in Karnataka.
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
247
GATE / HOIST AND ALLIED WORKS
Contd
248
GATE / HOIST AND ALLIED WORKS
249
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angles / Beams / Channels / Bars : 1193.00 kg
Plates / Flats : 442.00 kg
Chequered plate : 190.00 kg
2. Cast steel components : IS : 1030
Rope drums 2 Nos Gears 2 Nos : 384.00 kg
Pinions : 14.00 kg
Pulleys 6 Nos : 108.00 kg
Plummer blocks 6 Nos / couplings : 47.00 kg
3. Alloy steel components : IS : 1570
Shafts : 75.00 kg
Pins : 24.00 kg
4. Alluminium/ Bronze alloy components : IS : 305
Bearings / Bush : 10.50 kg
Bolt / Nut / Washers IS : 1363
MS Bolts / Nuts / Washers : 63.00 kg
5. Wire rope : IS : 2266
12 mm dia 6 / 36 construction 2 x 35 Rm : 40.00 kg
6. Other components :
Manual operating system : 1 No.
Worm reducer : 1 Nos
Rope socket with pin : 2 Nos
MS pipe 32 mm dia : 10.50 Rm
7. Other details :
Length of cutting : 73 Rm
Length of welding : 113 Rm
Number of electrodes ( for structural steel ) : 755 Nos
Manual operation assembly :
Note: For this assembly a lumpsum rate is proposed in the data rate analysis. The details furnished
below for this assembly are only for information to assess approximate cost of the assembly.
Therefore, the quantity details of this assembly are not included in the abstract of materials.
250
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 1189.50 kg
Plates / Flats : 514.50 kg
251
GATE / HOIST AND ALLIED WORKS
252
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 244.00 kg
Plates / Flats : 877.00 kg
2. Cast steel components : IS : 1030
Wheels / Guide roller : 49.50 kg
3. Alluminium / Bronze alloy components : IS : 305
Bearings / Bushes : 5.00 kg
4. Alloy steel components : IS : 1570
Wheel axle / lifting pin : 30.00 kg
5. Rubber seals : IS : 11855
Bottom rubber seal ( uncladed ) : 2.25 Rm
Side rubber seal ( uncladed ) : 3.95 Rm
Top rubber seal ( uncladed ) : 1.85 Rm
6. Bolt / Nut / Washer IS : 1363
GI Bolt / Nut / Washer : 7.50 kg
MS Bolt / Nut / Washer : 3.50 kg
7. Other details :
Length of cutting : 45.10 Rm
Length of welding : 93.70 Rm
Number of electrodes ( for structural steel ) : 658 Nos
253
GATE / HOIST AND ALLIED WORKS
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 392.50 kg
Plates / Flats : 141.50 kg
Chequered plate : 172.00 kg
2. Cast iron components : IS : 1030
Hoist body / Lock nut / Main nut : 55.00 kg
3. Alluminium / Bronze alloy components : IS : 305
Bearings / Bushes : 4.00 kg
4. Alloy steel components : IS : 1570
Hoist stem : 75.50 kg
5. Bolt / Nut / Washer : IS : 1363
MS Bolt / Nut / Washer : 8.00 kg
6. Other components :
Pipe 32 mm dia : 8.80 Rm
7. Other details :
Length of cutting : 18.00 Rm
Length of weld : 10.00 Rm
Number of electrodes ( for structural steel ) : 71 Nos
254
GATE / HOIST AND ALLIED WORKS
ABSTRACT :
1. Structural steel : IS : 2062
Angle / Channel / Beam / Bars : 1106.50 kg
Plates / Flats : 510.00 kg
2. Alloy steel components : IS : 1570
Stainless steel plates : 68.00 kg
3. Other details :
Length of cutting : 36.40 Rm
Length of welding : 195.00 Rm
Number of electrodes ( for structural steel ) : 1131 Nos
Number of electrodes ( for stainless steel ) : 199 Nos
255
GATE / HOIST AND ALLIED WORKS
256
GATE / HOIST AND ALLIED WORKS
Item: Embedded parts for trash rack structure of pump hpuse / penstock intake.
( Data for one vent / bay )
Details of materials / Gas cutting / Welding for rate analysis :
Note : 1. Data based on fabrication drawings of embedded parts for coarse screen for pump house
intake of Maralihalla pump house for Bellary Thermal station in Karnataka.
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
ABSTRACT :
1. Structural steel : IS :2062
Plates / Flats : 1322.00 kg
2. Other details :
Length of cutting : 78.00 Rm
Length of welding : 98.30 Rm
Number of electrodes ( for structural steel ) : 983 Nos
Item: Coarse and Fine screens for pump house intake ( Data for one vent ).
Details of materials / Gas cutting / Welding for rate analysis :
Note : 1. Data based on fabrication drawings of coarse and fine screens for pump house intake of
Maralihalla pump house for Bellary Thermal station in Karnataka.
2. Plate cutting considered for 2 sides assuming other 2 sides free face.
257
GATE / HOIST AND ALLIED WORKS
3. Unless otherwise specified 6 mm thick fillet weld considered for computing requirement of
welding electrodes and 450 mm long electrodes are considered for computing the quantity.
4. Number of welding electrodes computed is based on length, type and thickness of weld and
the requirement of electrodes per metre length of weld is based on standard welding tables.
ABSTRACT :
1. Structural steel : IS :2062
Angle / Channel / Beam / Bars : 3246.09 kg
Plates / Flats : 1359.27 kg
2. Weld mesh ( 2 mm dia 25x25 mm opening ) : 27.86 sqm
3. GI Bolt / Nut / Washer : 20.10 kg
4. Other details :
Length of cutting : 76.00 Rm
Length of welding : 149.00 Rm
Number of electrodes ( for structural steel ) : 1488 Nos
258